Road and bridge construction concrete spreader

By introducing a concrete placing trolley and a leveling and pushing device into the concrete placing machine, the problem of uneven concrete placement was solved, achieving uniform concrete placement and initial leveling, thus improving construction efficiency and preparation for fine leveling.

CN223633758UActive Publication Date: 2025-12-05SHAHE JINGCHEN CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422093517.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-29
Publication Date
2025-12-05
Estimated Expiration
2035-09-29

AI Technical Summary

Technical Problem

Existing concrete placing machines have the problem of uneven concrete distribution in road and bridge construction, which makes subsequent fine leveling construction difficult and adds an extra preliminary leveling process, increasing construction time and labor.

Method used

A concrete placing machine for road and bridge construction was designed, which is combined with a placing trolley and a leveling and pushing device, including an attached vibrator, an electric or hydraulic push rod to control the hopper door, and a motor-driven auger or a leveling trolley scraper, to achieve uniform concrete placement and initial leveling.

Benefits of technology

It achieves uniformity and initial leveling of concrete placement, improves construction efficiency, simplifies the construction process, and reduces construction time and labor.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223633758U_ABST
    Figure CN223633758U_ABST
Patent Text Reader

Abstract

The utility model relates to a road and bridge construction concrete spreader, and belongs to the technical field of concrete road and bridge machinery. A road and bridge construction concrete spreader comprises a main cross beam with walking assemblies arranged at the two ends, a distribution trolley arranged on the main cross beam and moving along the main cross beam, and a leveling and pushing device arranged on the rear side of the advancing direction of the main cross beam. Longitudinal travelling wheels are arranged on two sides of the main cross beam; the distribution trolley comprises a distribution bin and a power assembly driving the distribution bin to move, and a bin door with the controllable opening and closing degree is arranged at the bottom of the distribution bin. The utility model relates to a concrete spreader, which adopts a mode of adding the material spreading trolley and the material flattening and pushing device, can immediately carry out preliminary flattening after material spreading, and is beneficial to subsequent fine flattening construction of a concrete pavement. The material distribution trolley is arranged for movable material distribution, and convenience and rapidness are achieved. Due to the fact that the material distribution trolley is good in moving performance, material distribution is smoother. And in this way, by cooperating with the work of the leveling and pushing device, concrete material distribution and preliminary leveling can be achieved through one-time construction.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a kind of road bridge construction concrete spreaders, belong to concrete road bridge machinery technical field. BACKGROUND

[0002] When the paving construction of road surface of road bridge, first need to spread concrete material, then use corresponding equipment to carry out the fine leveling construction of road surface again.The spreader is needed when spreading, and the mechanized spreading is realized by spreader.

[0003] The currently used spreader only has the function of spreading, and lays concrete material on the road surface to be constructed.However, since spreading belongs to rough construction, there is a problem of uneven spreading after spreading, that is, there is more material in some positions and less material in some positions on the road surface, which is not conducive to subsequent fine leveling construction.If an additional preliminary leveling process is added, the construction time will be increased, which is time-consuming and laborious. UTILITY MODEL CONTENTS

[0004] The utility model aims at providing a kind of road bridge construction concrete spreader, can spread in time preliminary leveling after spreading, facilitate subsequent construction.

[0005] In order to achieve the above-mentioned purpose, the technical scheme adopted by the utility model is as follows:

[0006] A kind of road bridge construction concrete spreader, including the main crossbeam of the two ends setting walking component, the spreading trolley of setting on the main crossbeam and along the main crossbeam movement, the material pushing device of setting in the rear side of the forward direction of main crossbeam;The longitudinal walking wheel is set on the both sides of main crossbeam;Spreading trolley includes spreading bin and the power component of driving spreading bin movement, and the bin door of controllable opening and closing degree is set in the bottom of spreading bin;Main crossbeam is installed on walking component by lifting rod on both sides.

[0007] The further improvement of the technical scheme of the utility model is that the wall of spreading bin is installed with attached vibrator.

[0008] The further improvement of the technical scheme of the utility model is that the bin door is horizontally arranged at the opening of the lower part of spreading bin, and a push rod for pushing opening and closing is arranged on one side of the bin door.

[0009] The further improvement of the technical scheme of the utility model is that the push rod is electric push rod or hydraulic push rod.

[0010] The further improvement of the technical scheme of the utility model is that the material pushing device is spiral auger driven by motor.

[0011] The further improvement of the utility model technical scheme is that the flat material pushing device is a flat material trolley; the flat material trolley is fixedly arranged at the rear of the material trolley, and a rotatable material scraper is arranged at the lower part of the flat material trolley.

[0012] The further improvement of the utility model technical scheme is that the walking assembly of the main cross beam is a motor-driven rolling rubber wheel.

[0013] The further improvement of the utility model technical scheme is that the material trolley is provided with 1-3.

[0014] The further improvement of the utility model technical scheme is that:

[0015] Thanks to the above technical scheme, the utility model has the following technical effects:

[0016] The utility model is a concrete distributing machine, adopts the mode of the material trolley plus the flat material pushing device, can carry out preliminary leveling immediately after distributing, and is favorable for the subsequent fine leveling construction of the concrete pavement.

[0017] The utility model sets the material trolley to move for movable distribution, which is convenient and fast. Thanks to the good moving performance of the material trolley, the distribution is relatively more flat. In this way, the work of the flat material pushing device can realize the distribution and preliminary leveling of the concrete material in one construction.

[0018] The utility model controls the discharge amount through the opening and closing of the hatch door at the lower part of the material bin of the material trolley, further controls the flatness and height of the distribution, has good controllability, and has good distribution effect.

[0019] The utility model sets the flat material pushing device, carries out the scraping, pushing and preliminary leveling of the concrete material distributed by the bin, is flexible and efficient. DRAWINGS

[0020] Figure 1 It is the overall schematic view of the utility model;

[0021] Figure 2 It is the schematic view of the material trolley of the utility model Figure 1 ;

[0022] Figure 3 It is the schematic view of the material trolley of the utility model Figure 2 ;

[0023] Figure 4 It is the schematic view of the utility model when the material trolley is set;

[0024] Figure 5 It is the schematic view of the material trolley of the utility model when the flat material trolley is set;

[0025] Wherein, 1, main beam, 2, push rod, 3, longitudinal walking wheel, 4, cloth storehouse, 5, storehouse door, 6, spiral auger, 7, material scraper, 8, lifting rod, 9, flat material trolley, 10, attached vibrator. DETAILED DESCRIPTION

[0026] In order to make the technical means, creative features, purposes and effects of the utility model easy to understand, the utility model is further described below in combination with specific embodiments.

[0027] In the description of the utility model, it should be pointed out that the directions or position relations indicated by the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end" and "the other end" are based on the directions or position relations shown in the drawings, and are only for the convenience of describing the utility model and simplifying the description, and therefore cannot be understood as limiting the utility model.

[0028] The utility model is a kind of road and bridge construction concrete distributing machine, for the distribution of concrete in road and bridge construction, and preliminary leveling construction is carried out after distribution.

[0029] As Figure 1 Shown, the distributing machine includes main beam 1, distributing trolley and flat material pushing device. Walking assembly is arranged at the both ends of main beam 1, and main beam 1 is driven to move longitudinally by walking assembly. The distributing trolley is arranged on main beam 1, and can move along the transverse length direction of main beam 1. The transverse movement of distributing trolley realizes the distribution of concrete in transverse position. Walking assembly is a conventional setting in the field, mainly including walking seat, longitudinal walking wheel 3 and motor. The both ends of main beam 1 are connected with walking seat, and motor drives longitudinal walking wheel 3 to rotate and move. In specific implementation, the walking assembly of main beam 1 is motor-driven rubber wheel that rolls.

[0030] Further, main beam 1 is installed on walking assembly by lifting rod 8 on both sides. Specifically, lifting rod 8 is fixed on walking seat, and the both ends of main beam 1 are fixedly connected with the lifting end of lifting rod 8. The main beam can be adjusted in whole, and is adjusted according to needs when the thickness of distribution is different.

[0031] Flat material pushing device is arranged at the rear side of the forward direction of main beam 1, that is, located at the rear of the working cross section of distributing trolley, and is used for the preliminary leveling of concrete.

[0032] As Figure 1 , Figure 2As shown, the main cross beam 1 has a certain width, a rectangular frame structure, and the cloth trolley is arranged on the frame structure. Specifically, the cloth trolley includes a cloth bin 4 and a power assembly. The cloth bin 4 has a large opening at the top and a closed bottom. The cloth trolley further includes a moving frame arranged on the main cross beam 1, and a motor-driven roller is arranged on the moving frame as the power assembly. The cloth bin 4 is horizontally moved under the cooperation of the power assembly and the moving frame. The main body of the cloth bin 4 is located below the upper surface of the main cross beam 1.

[0033] A bin door 5 is arranged at the bottom of the cloth bin 4, and the opening and closing degree of the bin door 5 can be controlled as needed. The falling amount of concrete is controlled by controlling the opening and closing degree of the bin door 5, so as to control the thickness of the concrete distribution.

[0034] The cloth bin 4 of the distribution machine is used to buffer and control the distribution speed of the concrete. The lower end of the cloth bin 4 is a discharge port, and a bin door 5 is arranged at a position corresponding to the discharge port. Specifically, the discharge port is horizontal, and the bin door 5 is horizontally arranged and horizontally moved. The bin door 5 is usually arranged as a rectangular plate. A chute is arranged on both sides of the discharge port, and the bin door 5 slides in the chute. A push rod 2 is fixedly arranged on one side. The fixed end of the push rod 2 is in a fixed state, and the outer end of the moving rod is fixedly connected with the bin door 5. The lower part of the cloth bin 4 is fixedly arranged with a frame body for mounting the push rod 2. The moving rod of the push rod 2 is telescopic to realize the position movement of the bin door 5, thereby realizing the control of the opening and closing degree of the bin door 5 on the discharge port. Specifically, as shown in the figure, Figure 2 、 Figure 3 as shown, Figure 3 in the figure, Figure 2 one of the connecting beams above the bin door 5 on the moving frame is hidden, which is convenient for observing the bin door.

[0035] In a specific implementation, the push rod 2 is an electric push rod or a hydraulic push rod.

[0036] An attached vibrator is mounted on the outer wall of the cloth bin 4. During work, the attached vibrator 10 is always in a vibrating state, which can prevent the concrete from blocking the discharge port and prevent the concrete from sticking to the wall. Two attached vibrators 10 are arranged on the two opposite outer sides of the bin door 5.

[0037] The distribution machine is provided with a flat material pushing device to initially level the concrete material. Because the concrete at some positions is in a piled-up state after being distributed by the cloth trolley, it needs to be initially leveled.

[0038] The flat material pushing device can be directly arranged as a spiral auger 6, and the spiral auger 6 is driven to rotate by a motor. The spiral auger 6 transports the concrete at uneven positions.

[0039] Alternatively, the material pushing device can be provided as a material leveling trolley 9. Preferably, the material leveling trolley 9 is directly fixed behind the material distributing trolley. A rotatable material scraper 7 is arranged at the lower part of the material leveling trolley 9. After the material distributing trolley distributes the material, the material leveling trolley 9 directly scrapes and levels the concrete on the construction surface. The material leveling trolley 9 comprises a trolley frame, the material scraper 7 and a motor. The trolley frame is directly fixed to the material distributing trolley. The motor and the material scraper 7 are arranged at the lower part of the trolley frame. The motor drives the material scraper 7 to rotate 360° to scrape and level the material. Details are shown in Figure 4 、 Figure 5 .

[0040] The material distributing machine sets the number of material distributing trolleys according to the width of the construction surface, and usually sets 1-3 material distributing trolleys. When the width of the bridge surface is greater than 19.5 meters, two material distributing trolleys can be arranged to improve the work efficiency.

[0041] The longitudinal movement of the whole machine and the transverse movement of the material distributing trolley are adjusted by the frequency conversion of the driving motor.

[0042] When the material distributing machine is used, a concrete tank truck or other concrete filling equipment is needed to be used in combination. The concrete filling equipment fills the concrete into the material distributing trolley to ensure the continuous supply of the concrete. Details are shown in Figure 4 .

[0043] The material distributing machine adopts the material distributing trolley and the material pushing device to distribute the material, which can immediately level the material after the material is dropped, thereby facilitating the subsequent fine leveling construction of the concrete pavement.

[0044] The above shows and describes the basic principles and main features of the material distributing machine and the advantages of the material distributing machine. It should be understood by those skilled in the art that the material distributing machine is not limited to the above embodiments, and the above embodiments and descriptions in the specification are only to illustrate the principles of the material distributing machine. Without departing from the spirit and scope of the material distributing machine, the material distributing machine can have various changes and improvements, and these changes and improvements all fall within the scope of the claimed material distributing machine. The scope of protection of the material distributing machine is defined by the appended claims and their equivalents.

Claims

1. A concrete spreader for bridge construction, characterized in that: The main beam (1) is provided with walking assemblies at both ends, a material distributing trolley is arranged on the main beam (1) and moves along the main beam (1), and a material leveling and pushing device is arranged at the rear side of the main beam (1) in the advancing direction; longitudinal walking wheels (3) are arranged at both sides of the main beam (1); the material distributing trolley comprises a material distributing bin (4) and a power assembly for driving the material distributing bin (4) to move, and the bottom of the material distributing bin (4) is provided with a bin door (5) with controllable opening and closing degree; the main beam (1) is installed on the walking assemblies through lifting rods (8) at both sides.

2. The concrete distributing machine for road and bridge construction according to claim 1, characterized in that: An attached vibrator (10) is installed on the bin wall of the material distributing bin (4).

3. The concrete distributing machine for road and bridge construction according to claim 1, characterized in that: The bin door (5) is horizontally arranged at the opening of the lower part of the material distributing bin (4), and a push rod (2) for pushing the opening and closing is arranged at one side of the bin door (5).

4. The concrete distributing machine for road and bridge construction according to claim 3, characterized in that: The push rod (2) is an electric push rod or a hydraulic push rod.

5. The concrete distributing machine for road and bridge construction according to any one of claims 1 to 4, characterized in that The material leveling and pushing device is a spiral auger (6) driven to rotate by a motor.

6. The concrete distributing machine for road and bridge construction according to any one of claims 1 to 4, characterized in that: The material leveling and pushing device is a material leveling trolley (9); the material leveling trolley (9) is fixedly arranged at the rear of the material distributing trolley, and a rotatable material scraper (7) is arranged at the lower part of the material leveling trolley (9).

7. The concrete distributing machine for road and bridge construction according to any one of claims 1 to 4, characterized in that: The walking assembly of the main beam (1) is a rubber wheel driven to roll by a motor.

8. The concrete distributing machine for road and bridge construction according to any one of claims 1 to 4, characterized in that: The material distributing trolley is provided with 1-3 units.