Formwork cable-stayed and opposite-jacking integrated device
By using the integrated formwork diagonal bracing device, a stable support system is formed using components such as supporting steel pipes and positive and negative threaded rods, which solves the problems of verticality and flatness caused by formwork swaying, and improves construction quality and progress.
Patent Information
- Application Number
- CN202423196051.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-24
- Publication Date
- 2025-12-05
- Estimated Expiration
- 2034-12-24
AI Technical Summary
In existing technologies, the formwork support system is prone to shaking due to impact during concrete pouring, resulting in substandard verticality, flatness, and internal and external corners, which affects construction quality and progress.
An integrated formwork diagonal bracing and top-mounting device is adopted, which forms a stable support system through components such as supporting steel pipes, positive and negative threaded rods, fixing pads and supporting legs. The overall stability of the formwork is enhanced by the diagonal bracing and top-mounting effect of the supporting steel pipes and the formwork body.
This effectively ensures the verticality, flatness, and pass rate of internal and external corners of the cast-in-place structure, reduces maintenance work, and saves construction costs and time.
Smart Images

Figure CN223634336U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of building construction, especially relates to a formwork cable-stayed counter -top integrated device. BACKGROUND
[0002] Through the search, the existing patent document with the announcement number CN218668556U discloses a cable-stayed formwork anchoring device, including embedded parts, pull rod, sleeve hoop and support, one end of the pull rod has a hook, the other end has a thread, the hook end of the pull rod is hooked on the embedded part, and the hook end of the pull rod is sleeved with the sleeve hoop, the threaded end of the pull rod passes through the formwork and the support outside the formwork and is fixed, the device provides a cable-stayed formwork anchoring device, which generally uses counter-bolts or conventional baskets for traditional concrete inclined wall formwork installation anchoring, the construction effect is general, and the problem of not meeting the requirements of super-high large-area inclined walls is solved, the structure of the pull rod with a hook at one end and a thread at the other end is adopted for anchoring, and in order to reduce the construction difficulty, the pull rod is divided into two sections, which is not only simple in construction operation, but also high in efficiency and excellent in construction quality.
[0003] With the development of cities, people's requirements for housing quality are higher and higher, and in main construction, the perpendicularity, flatness and inside and outside corners of concrete wall columns are difficult to control to high standards, which depends on the support and fixation of formwork and reinforcement, in the support system of formwork, in order to ensure the perpendicularity and flatness, inner support is generally used to support the formwork keel with ordinary steel pipes, so that the formwork does not lean inward, but during concrete pouring, the pouring personnel often stand on the inner side to pour concrete, so that an outward impact force is generated, the formwork system shakes and tilts, and the perpendicularity, flatness and inside and outside corners of the finished product cannot be guaranteed.
[0004] The control of the perpendicularity, flatness and inside and outside corners of cast-in-place building wall columns has always been a problem for builders, and the impact force generated during concrete pouring and the vibration force generated by the distributing machine and the vibration rod will cause the instability of the formwork system, resulting in unqualified quality of the finished product, and then manpower and material resources need to be invested for maintenance and repair, which affects the bearing quality and appearance, and also affects the construction progress, and is labor-intensive and material-intensive. UTILITY MODEL CONTENTS
[0005] The utility model wants to solve the technical problem of overcoming the defects of prior art, provide a template cable-stayed pair of top integrated device, aim at solving the verticality, flatness and the squareness of the cast-in-place structure of the template because of the unstable reinforcement meet the requirement technical problem.
[0006] In order to solve the above technical problem, the utility model provides the following technical scheme:
[0007] The utility model discloses a template cable-stayed pair of top integrated device, including template body, fixed gasket and support steel pipe, the template body is two groups of symmetry and is arranged, and the one side surface of template body is provided with main keel steel pipe, and the two main keel steel pipes of it are one row, and are provided with multiple rows, and are vertically arranged in turn.
[0008] The both ends of the top surface of fixed gasket are provided with support steel pipes, the both ends of support steel pipe are provided with pipe clamp, the top of one side surface of support steel pipe is provided with positive silk, the bottom is provided with reverse silk, the middle part is provided with positive and negative silk, the inside and both side surfaces of the middle part of the two support steel pipes are provided with positive and negative silk screw rods, the end of positive and negative silk screw rod is provided with a hook, the bottom end surface of the inside of the middle part of support steel pipe positive and negative silk screw rod is provided with support leg, the inside of the end of one side surface of support leg is provided with ball head shaft.
[0009] As further description of the above technical scheme:
[0010] The main keel steel pipe and fixed gasket and support steel pipe are all fixed through pipe clamp connecting end, and the thickness of fixed gasket is 5mm steel gasket, and the thickness of pipe clamp is 1cm steel sheet.
[0011] As further description of the above technical scheme:
[0012] The support steel pipe and positive and negative silk screw rod are fixed through hook connection, the diameter of positive and negative silk screw rod is 20mm, and they are all arranged horizontally, the both ends of the both sides of support steel pipe positive and negative silk screw rod are fixed through pipe clamp and main keel steel pipe, and the two support steel pipes are symmetrically arranged as inclined rods.
[0013] As further description of the above technical scheme:
[0014] The positive and negative silk screw rod and support leg are spliced and assembled, the support leg is 3cm thick steel pipe, the support leg and ball head shaft are spliced and assembled, the ball head shaft is provided with multiple groups, and is arranged vertically in turn.
[0015] The utility model has the advantages of:
[0016] The utility model discloses a two -purpose through a rod can produce the tensile force, can also play the effect of the top, and the upper portion, the lower portion of formwork are equipped with the support point respectively, and the bottom is reinforced on the ground and forms the support and the tensile force, plays the role of the strengthening stability to the stability of formwork system. BRIEF DESCRIPTION OF DRAWINGS
[0017] The accompanying drawings are included to provide a further understanding of the present utility model, and constitute a part of the specification, and are used together with the embodiments of the present utility model to explain the present utility model, and do not constitute the limitation to the present utility model.
[0018] Fig. 1 It is the whole structure schematic diagram of the utility model;
[0019] Fig. 2 It is the whole structure front view schematic diagram of the utility model;
[0020] In the drawing: 1, formwork body;2, fixed gasket;3, support steel pipe;4, main keel steel pipe;5, pipe clamp;6, positive and negative silk screw;7, bent hook;8, support leg;9, ball head shaft. PREFERRED EMBODIMENT
[0021] The preferred embodiments of the present utility model are described below in combination with the drawings, and it should be understood that the preferred embodiments described here are only used to illustrate and explain the present utility model, and are not used to limit the present utility model.
[0022] Same reference numerals in the drawings all refer to the same parts.
[0023] Embodiment 1
[0024] Referring to Figs. 1-2 The utility model provides an embodiment: a formwork cable-stayed top integrated device, including formwork body 1, fixed gasket 2 and support steel pipe 3, formwork body 1 is two groups of symmetry and is arranged, and the one side surface of formwork body 1 is provided with main keel steel pipe 4, and the two of its main keel steel pipe 4 are a row, and are provided with multiple rows, and are sequentially arranged in vertical shape.
[0025] Fixed gasket 2 top end surface both ends are provided with support steel pipe 3, and the both ends of support steel pipe 3 are provided with pipe clamp 5, and the one side surface top of support steel pipe 3 is provided with positive silk, and the bottom is provided with negative silk, and the middle part is provided with positive and negative silk, and the inside and both side surfaces of the middle part of the two support steel pipes 3 are provided with positive and negative silk screw 6, and the end of positive and negative silk screw 6 is provided with bent hook 7, and the inside bottom end surface both ends of the middle part of support steel pipe 3 positive and negative silk screw 6 are provided with support leg 8, and the inside end of one side surface of support leg 8 is provided with ball head shaft 9.
[0026] The main keel steel pipe 4 and the fixed gasket 2 are connected and fixed at the end by the pipe clamp 5, the thickness of the fixed gasket 2 is 5mm steel gasket, and the thickness of the pipe clamp 5 is 1cm steel sheet.
[0027] The support steel pipe 3 and the lead screw 6 are connected and fixed by the bent hook 7, the diameter of the lead screw 6 is 20mm, and they are arranged in the horizontal direction, the end of the lead screw 6 on both sides of the support steel pipe 3 is connected and fixed with the main keel steel pipe 4 by the pipe clamp 5, and the two support steel pipes 3 are symmetrically arranged as inclined rods.
[0028] The lead screw 6 and the support leg 8 are spliced and assembled, the support leg 8 is a 3cm thick steel pipe, and the support leg 8 and the ball head shaft 9 are spliced and assembled, the ball head shaft 9 is arranged in multiple groups and arranged in a vertical manner.
[0029] Specifically, the structure is formed by the formwork body 1, the fixed gasket 2, the support steel pipe 3, the main keel steel pipe 4, the pipe clamp 5, the lead screw 6, the bent hook 7, the support leg 8 and the ball head shaft 9, the formwork cable-stayed counter-anchored integrated device improves the overall use efficiency, is convenient to use, adds components on the basis, and further effectively supports one step to the place, and completes the overall stability requirement. The fixed gasket 2 is used to fix on the ground, the support steel pipe 3 is used for inclined cable-stayed support with the formwork body 1, the main keel steel pipe 4 is used to reinforce the formwork system, the pipe clamp 5 is used to hook the end of the support steel pipe 3 and the lower lead screw 6 to fix, when the screw rotates, the nut moves along the screw shaft, thereby realizing the conversion of linear motion, which can be used to realize the telescopic motion of the machine and be used to adjust the length; the bent hook 7 is used to hook the anchor to fix, the support leg 8 is used to support the ground, and the ball head shaft 9 is used to rotate and adjust the angle of the support leg 8, so that the formwork cable-stayed counter-anchored integrated device can play the role of both cable-stayed and counter-anchored in the formwork support system, the inclined rod of the support steel pipe 3 is effectively connected with the upper part of the formwork system, the lead screw 6 near the bottom is arranged as a horizontal pull rod, and the fixed gasket 2 at the bottom is effectively fixed with the ground, so that the overall stability of the formwork body 1 is guaranteed. The formwork cable-stayed counter-anchored integrated device can show the force of each other, reduce the ground reinforcement gravity, through the triangular action of the horizontal steel pipe and the inclined steel pipe, and the triangular action of the bottom support leg 8, when the formwork building concrete shakes, especially the outward force can effectively play a stabilizing role.
[0030] Working principle: the upper pipe clamp 5 of the support steel pipe 3 hooks the second row of main keel steel pipe 4, and the lower part is connected with the fixed pad 2, the fixed pad 2 is fixed with the ground by expanding wire, the length is adjusted by the forward and reverse wire, one end of the horizontal forward and reverse wire screw rod 6 on both sides of the support steel pipe 3 hooks the second row of main keel steel pipe 4 on the lower part, and the other end hooks the anchor of the support steel pipe 3 on the upper part, and the length is also adjusted by the forward and reverse wire. The support leg 8 is supported by adjusting the angle of the ball head shaft 9. The whole can be used on one side, or can be supported on both sides in mirror image relationship.
[0031] The device is mainly used for the overall stability of the template system, and the template is supported and supported by the inclined support steel pipe 3, the lower forward and reverse wire screw rod 6 horizontal rod and the bottom fixed pad 2 and the support leg 8, the support steel pipe 3 is provided with forward and reverse wires at both ends, which are used for adjusting the length and tightness, and the forward and reverse wire screw rod 6 is provided with forward and reverse wires in the middle, which are used for adjusting the length and tightness. The upper pipe clamp 5 of the support steel pipe 3 hooks the horizontal main keel steel pipe 4 of the template, and the lower part is closely connected with the fixed pad 2, one end of the lower forward and reverse wire screw rod 6 hooks the horizontal main keel steel pipe 4 of the lower part of the template body 1, and the other end is effectively and closely connected with the support steel pipe 3, the bottom fixed pad 2 is effectively fixed with the ground by the nail gun, the support steel pipe 3 is supported by the support leg 8 on both sides, forming an inclined triangle, no matter the template is impacted by the internal and external impact, it will not shake, so as to effectively ensure the perpendicularity, flatness and squareness of the template system, the two support legs 8 are connected by the ball head shaft 9, the ball head shaft 9 can rotate freely, and the length is adjusted according to the space and use angle of the scene.
[0032] Finally, it should be pointed out that: the above only for the preferred embodiments of the present application, and is not used to limit the present application, although the present application has been described in detail with reference to the foregoing embodiments, for those skilled in the art, it still can modify the technical scheme recorded in the foregoing embodiments, or make equivalent replacement for part of the technical features. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A template cable-stayed integrated device, comprising a template body (1), a fixed gasket (2) and a supporting steel pipe (3), characterized in that, The template body (1) is symmetrically arranged in two groups, and the one side surface of the template body (1) is provided with a main keel steel pipe (4), and the two main keel steel pipes (4) are arranged in one row and multiple rows, and are arranged in vertical sequence. The top end surface of the fixing gasket (2) is provided with a support steel pipe (3) at both ends, and the support steel pipe (3) is provided with a pipe clamp (5) at both ends, and the top of the one side surface of the support steel pipe (3) is provided with a positive wire, the bottom is provided with a negative wire, and the middle is provided with a positive and negative wire, and the inner side and both side surfaces of the two support steel pipes (3) are provided with positive and negative wire screws (6), and the end of the positive and negative wire screw (6) is provided with a hook (7), and the inner side of the middle of the support steel pipe (3) is provided with a support leg (8) at both ends of the bottom end surface, and the inner side of the end of the one side surface of the support leg (8) is provided with a ball head shaft (9).
2. The template diagonal pull and jacking integrated device according to claim 1, wherein, The main keel steel pipe (4) and the fixing gasket (2) and the support steel pipe (3) are connected and fixed by the pipe clamp (5) at the end, the thickness of the fixing gasket (2) is 5mm steel gasket, and the thickness of the pipe clamp (5) is 1cm steel sheet.
3. The template diagonal pull and jacking integrated device according to claim 1, wherein, The support steel pipe (3) and the positive and negative wire screw (6) are connected and fixed by the hook (7), the diameter of the positive and negative wire screw (6) is 20mm, and they are arranged in horizontal direction, the ends of the positive and negative wire screws (6) on both sides of the support steel pipe (3) are connected and fixed with the main keel steel pipe (4) by the pipe clamp (5), and the two support steel pipes (3) are symmetrically arranged as inclined rods.
4. The template diagonal pull and jacking integrated device of claim 1, wherein, The positive and negative wire screw (6) and the support leg (8) are spliced and assembled, the support leg (8) is a 3cm thick steel pipe, and the support leg (8) and the ball head shaft (9) are spliced and assembled, and the ball head shaft (9) is provided in multiple groups and arranged in vertical sequence.
Citation Information
Patent Citations
Cable-stayed formwork anchoring device
CN218668556U