Convenient scaffold

By combining steel pipe connectors and reinforcing rods, the problem of cumbersome scaffolding connections has been solved, enabling convenient assembly and stable connection, thus improving construction efficiency and stability.

CN223724114UActive Publication Date: 2025-12-26JIANGSU HUASHENG ENG CONSULTING CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520032506.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-07
Publication Date
2025-12-26
Estimated Expiration
2035-01-07

Smart Images

  • Figure CN223724114U_ABST
    Figure CN223724114U_ABST
Patent Text Reader

Abstract

The utility model discloses a convenient scaffold, which relates to the technical field of scaffolds and comprises a steel pipe connector, a framework steel pipe arranged at one end of the steel pipe connector in a penetrating manner, a connecting block arranged on the outer wall of the framework steel pipe in a sleeving manner and a reinforcing rod arranged at one end of the connecting block, the steel pipe connector is composed of a first sleeve, a connecting column arranged on one side of the first sleeve, and a second sleeve arranged on one side of the connecting column and away from one side of the first sleeve. The reinforcing rod is composed of a first plate and a second plate arranged at one end of the first plate. The connecting mode is reasonable, convenience is high, and the assembled scaffold is high in stability.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model mainly relates to the technical field of scaffold, concretely is a convenient scaffold. BACKGROUND

[0002] Scaffold is the working platform that erects to guarantee each construction process to carry on smoothly. According to the materials of erection, it can be divided into steel pipe scaffold, wood scaffold, bamboo scaffold, steel template scaffold, steel pipe fastener type scaffold, door type scaffold, bowl buckle type scaffold, socket type disc buckle type scaffold etc. According to the purposes of erection, it can be divided into operation (job) scaffold, protective scaffold and load-bearing, supporting scaffold. Provide the operation platform of construction personnel, so that construction personnel can work at different heights. Bear the load generated in the construction process, such as the weight of construction personnel, materials, tools, etc. and possible wind load etc. Provide safety protection, such as setting safety net, protective railings etc. to prevent construction personnel from falling from a height or object striking etc. accidents.

[0003] Based on the prior art and according to the application number CN202320647951.2 a convenient building support, including first scaffold, the first scaffold surface wall sliding connection has second scaffold;The first scaffold surface wall is fixedly connected with a pair of first magnetic block;Insert the second scaffold into the first scaffold surface wall, at this time when the second scaffold is inserted into the first scaffold surface wall, the telescopic block is extruded into the groove, when the second scaffold is completely inserted into the first scaffold surface wall, the telescopic block can be popped into the side wall of the clamping groove, in the process, thereby reducing the prior art in the process of connecting the first scaffold with the second scaffold, it is inconvenient for workers to connect, leading to the process of connection is relatively cumbersome, thereby causing certain influence to the progress of construction.

[0004] The above-mentioned scaffold loses certain stability due to its structural characteristics, and the convenience in use is lacking. UTILITY MODEL CONTENTS

[0005] Therefore, the utility model aims at providing a convenient scaffold to solve the technical problems in the background art.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical scheme:

[0007] A convenient scaffold, including steel pipe connector, skeleton steel pipe that is penetrated in one end of the steel pipe connector, connecting block that is sleeved in the outer wall of the skeleton steel pipe, reinforcing rod that is arranged in one end of the connecting block;

[0008] The steel pipe connector is composed of a first sleeve, a connecting column arranged on one side of the first sleeve, a second sleeve arranged on one side of the connecting column and away from the first sleeve.

[0009] The reinforcing rod is composed of a first plate and a second plate arranged on one end of the first plate.

[0010] Preferably, the first sleeve and the second sleeve are of the same structure.

[0011] The inner ring diameter of the first sleeve is the same as the outer ring diameter of the skeleton steel pipe, and the inner walls of the first sleeve and the second sleeve are in sliding connection with the outer wall of the skeleton steel pipe.

[0012] Preferably, a hole position one is arranged on one side of the second sleeve, the inner wall of the hole position one is provided with threads and is in cooperation with a screw.

[0013] Preferably, a contact plane is arranged on the top of the connecting block, a through hole is arranged on one end of the connecting block, the diameter of the through hole is the same as the outer ring diameter of the skeleton steel pipe, and the inner wall of the through hole is in sliding connection with the outer wall of the skeleton steel pipe.

[0014] Preferably, a hole position two is arranged on the top of the contact plane, the hole position two is in communication with the through hole, the inner wall of the hole position two is provided with threads and is in cooperation with a screw.

[0015] Preferably, the reinforcing rod is in the shape of "L" in projection.

[0016] Preferably, a hole position three is arranged on the side wall of the first plate, and a hole position four is arranged on the side wall of the second plate, the inner walls of the hole position three and the hole position four are provided with threads and are in cooperation with a screw.

[0017] Preferably, at least one reserved hole is arranged on the outer wall of the skeleton steel pipe.

[0018] The technical scheme has the following beneficial effects:

[0019] In the utility model, the complete scaffold can be assembled by the universal steel pipe connector and the connecting block, the complete process and the installation method are simple and direct, the convenience of the scaffold is improved, and the reinforcing rod can be used in cooperation with the connecting block, so that the stability of the scaffold is further improved. DRAWINGS

[0020] Figure 1 It is an axonometric view of the important connecting structure of the scaffold of the utility model;

[0021] Figure 2 It is an axonometric view of the overall structure of the connecting block of the utility model;

[0022] Figure 3 is a whole structure of the reinforcing rod of the utility model;

[0023] Figure 4 is a whole structure of the steel pipe connector of the utility model;

[0024] Figure 5 is a whole structure of the scaffold important connection of the utility model.

[0025] BRIEF DESCRIPTION OF DRAWINGS: 10, steel pipe connector; 20, skeleton steel pipe; 30, connecting block; 40, reinforcing rod, 50, pedal; 60, screw; 11, first sleeve; 12, connecting column; 13, second sleeve; 131, hole position one; 31, contact plane; 311, hole position two; 32, through hole; 41, plate one; 411, hole position three; 42, plate two; 421, hole position four. DETAILED DESCRIPTION

[0026] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model.

[0027] Embodiment one:

[0028] As Figures 1 to 4 shown, a convenient scaffold, including steel pipe connector 10, skeleton steel pipe 20 threaded in one end of steel pipe connector 10, connecting block 30 sleeved in the outer wall of skeleton steel pipe 20, reinforcing rod 40 provided at one end of connecting block 30.

[0029] Steel pipe connector 10 is by first sleeve 11, connecting column 12 provided at one side of first sleeve 11, second sleeve 13 provided at one side of connecting column 12 and away from one side of first sleeve 11; first sleeve 11 and second sleeve 13 are the same structure.

[0030] Reinforcing rod 40 is by plate one 41 and plate two 42 provided at one end of plate one 41.

[0031] The inner ring diameter of first sleeve 11 is the same as the outer ring diameter of skeleton steel pipe 20, and the inner walls of first sleeve 11 and second sleeve 13 are slidably connected with the outer wall of skeleton steel pipe 20.

[0032] Second sleeve 13 is threaded with hole position one 131 on one side; the inner wall of hole position one 131 is threaded and cooperatively connected with screw 60.

[0033] Connecting block 30 is provided with contact plane 31 on the top, and is threaded with through hole 32 on one end; the diameter of through hole 32 is the same as the outer ring diameter of skeleton steel pipe 20, and the inner wall of through hole 32 is slidably connected with the outer wall of skeleton steel pipe 20.

[0034] The top of the contact plane 31 is provided with a second hole 311, which is connected to the through hole 32. The inner wall of the second hole 311 is provided with threads and is connected to the screw 60.

[0035] The reinforcement rod 40 has an "L" shape projected.

[0036] The side wall of plate 41 has a hole 411, and the side wall of plate 42 has a hole 421; the inner walls of holes 411 and 421 are threaded and are connected to screws 60.

[0037] The outer wall of the steel pipe 20 has at least one reserved hole.

[0038] It should be noted that in this embodiment, the steel pipe connector 10 consists of a first sleeve 11, a connecting post 12 located on one side of the first sleeve 11, and a second sleeve 13 located on the side of the connecting post 12 away from the first sleeve 11. A hole 131 is provided on one side of the second sleeve 13. The first sleeve 11 of the two steel pipe connectors 10 can be located on either side of the skeleton steel pipe 20, increasing the convenience of connection; and the fixed connection is achieved by screws 60 passing through the hole 131 and connecting to a pre-reserved space on the skeleton steel pipe 20. It should be further noted that the second sleeve 13 with the hole 131 is positioned in the direction of force application of the skeleton steel pipe 20, such as... Figure 1 As shown, the second sleeve 13 should be set in the longitudinal direction of the skeleton steel pipe 20.

[0039] The connecting block 30 has a contact surface 31 at its top, and a through hole 32 at one end. A second hole 311 is provided at the top of the contact surface 31, communicating with the through hole 32. On one hand, it is used to connect the scaffolding steps 50; the connecting blocks 30, which are paired and fitted onto the outer wall of the frame steel pipe 20, are used in conjunction with screws 60 to fix the steps 50. On the other hand, it is used to connect the reinforcing rods 40.

[0040] The reinforcing rod 40 has an "L" shape in its projection and is composed of plate 41 and plate 42. Plate 41 has a hole 411 through its side wall, and plate 42 has a hole 421 through its side wall. Figure 1 As shown, plate 41 is installed on the outer wall of the transverse support frame steel pipe 20 of the scaffold, and plate 42 is installed on the outer wall of the longitudinal frame steel pipe 20 of the scaffold; a significant feature is that the side of the connecting block 30 with the contact plane 31 can be changed according to the setting characteristics of the reinforcing rod 40.

[0041] Example 2:

[0042] like Figures 2 to 5As shown in the accompanying drawings, the utility model discloses a convenient scaffold, including steel pipe connector 10, the skeleton steel pipe 20 of being arranged in one end of steel pipe connector 10, the connecting block 30 of being set up in the outer wall of skeleton steel pipe 20, the reinforcing bar 40 of being set up in one end of connecting block 30.

[0043] Need explanation, in this embodiment, steel pipe connector 10 is by first sleeve 11, the connecting column 12 of being set up in one side of first sleeve 11, the second sleeve 13 of being set up in one side of connecting column 12 and being away from one side of first sleeve 11. The hole position one 131 of being arranged in one side of second sleeve 13. As shown in the accompanying drawings in detail, Figure 5 As shown in the accompanying drawings, the first sleeve 11 in the two steel pipe connectors 10 mentioned in embodiment one can be arranged on either side of the skeleton steel pipe 20, increasing the convenience of connection.

[0044] The connecting block 30 is provided with a contact plane 31 on the top, and a through hole 32 is arranged at one end of the connecting block 30. The contact plane 31 is provided with a hole position two 311 on the top, and the hole position two 311 is communicated with the through hole 32.

[0045] The reinforcing bar 40 is projected as an "L" shape and is composed of a plate one 41 and a plate two 42. The plate one 41 is provided with a hole position three 411 on the side wall, and the plate two 42 is provided with a hole position four 421 on the side wall. The plate one 41 is arranged on the outer wall of the longitudinal support skeleton steel pipe 20 of the scaffold, and the plate two 42 is arranged on the outer wall of the transverse skeleton steel pipe 20 of the scaffold. In addition, it is further explained that the reinforcing bar 40 can be changed according to the actual situation along with the arrangement position of the support skeleton steel pipe 20.

[0046] The working principle of the utility model is as follows:

[0047] In the utility model, the first sleeve 11 in the two steel pipe connectors 10 can be arranged on either side of the skeleton steel pipe 20, increasing the convenience of connection. The fixed connection is achieved by connecting the hole position one 131 and the reserved space on the skeleton steel pipe 20 through the screw 60. It is further explained that the second sleeve 13 with the hole position one 131 is arranged in the stress direction of the skeleton steel pipe 20, as shown in the accompanying drawings, the second sleeve 13 should be arranged in the longitudinal direction of the skeleton steel pipe 20, and the overall structure of the scaffold is more stable in this way. Figure 1

[0048] ​The connecting block 30 is used for connecting the footboard 50 of the scaffold on one hand, and the connecting block 30 is sleeved on the outer wall of the skeleton steel pipe 20 in pairs and is used for fixing the footboard 50 by cooperating with the screw 60; at the same time, when the connecting block 30 is connected with the footboard 50, the footboard 50 naturally plays a role of limiting and fixing the skeleton steel pipes 20 at two ends of the scaffold, which not only limits the rotation of the connecting block 30 itself, but also can limit the skeleton steel pipes 20 on both sides of the footboard 50 from being scattered away from the footboard 50, so that the stability of the whole scaffold is further increased while the connection convenience is ensured.

[0049] The connecting block 30 is used for connecting the footboard 50 of the scaffold on one hand, and the connecting block 30 is sleeved on the outer wall of the skeleton steel pipe 20 in pairs and is used for fixing the footboard 50 by cooperating with the screw 60; at the same time, when the connecting block 30 is connected with the footboard 50, the footboard 50 naturally plays a role of limiting and fixing the skeleton steel pipes 20 at two ends of the scaffold, which not only limits the rotation of the connecting block 30 itself, but also can limit the skeleton steel pipes 20 on both sides of the footboard 50 from being scattered away from the footboard 50, so that the stability of the whole scaffold is further increased while the connection convenience is ensured. Figure 1 As shown in the figure, the plate one 41 is arranged on the outer wall of the transverse support skeleton steel pipe 20 of the scaffold, and the plate two 42 is arranged on the outer wall of the longitudinal skeleton steel pipe 20 of the scaffold; the longitudinal skeleton steel pipe 20, the transverse skeleton steel pipe 20 and the reinforcing rod 40 form a stable triangular structure, and the two skeleton steel pipes 20 connected by the steel pipe connector 10 are more stable.

[0050] The above embodiments only illustrate the technical idea of the utility model, and cannot limit the protection scope of the utility model, and any modification made on the basis of the technical scheme according to the technical idea of the utility model falls within the protection scope of the utility model.

Claims

1. A convenience scaffold characterized by The utility model provides a steel pipe connector (10), skeleton steel pipe (20) is passed in one end of the steel pipe connector (10), the connecting block (30) of sleeve set in the outer wall of skeleton steel pipe (20), reinforcing rod (40) is equipped in one end of the connecting block (30); The steel pipe connector (10) is by first sleeve (11), the connecting column (12) of being equipped in one side of first sleeve (11), the second sleeve (13) of being equipped in one side of connecting column (12) and being away from one side of first sleeve (11); The reinforcing rod (40) is by board one (41) and the board two (42) of being equipped in one end of board one (41) constitute.

2. A portable scaffold according to claim 1, wherein The first sleeve (11) and second sleeve (13) structure are same; The inner ring diameter of first sleeve (11) is same with the outer ring diameter of skeleton steel pipe (20) and is arranged, and the inner wall of first sleeve (11) and second sleeve (13) is slidably connected with the outer wall of skeleton steel pipe (20).

3. The portable scaffold of claim 1, wherein, The second sleeve (13) one side is passed in hole position one (131);The inner wall of hole position one (131) is equipped with thread and is connected with screw (60) cooperation.

4. The portable scaffold of claim 1, wherein, The top of connecting block (30) is equipped with contact plane (31), and one end of connecting block (30) is passed in through -hole (32);The diameter of through -hole (32) is same with the outer ring diameter of skeleton steel pipe (20) and is arranged;And the inner wall of through -hole (32) is slidably connected with the outer wall of skeleton steel pipe (20).

5. A convenience scaffold according to claim 4, wherein, The top of contact plane (31) is passed in hole position two (311), and hole position two (311) is connected with through -hole (32) arrangement, and the inner wall of hole position two (311) is equipped with thread and is connected with screw (60) cooperation.

6. The portable scaffold of claim 1, wherein, The projection of reinforcing rod (40) is '' L '' shape.

7. A convenience scaffold according to claim 6, wherein, The sidewall of board one (41) is passed in hole position three (411), and the sidewall of board two (42) is passed in hole position four (421);The inner wall of hole position three (411) and hole position four (421) is equipped with thread and is connected with screw (60) cooperation.

8. The portable scaffold of claim 1, wherein, The outer wall of skeleton steel pipe (20) is equipped with at least one reserved hole.

Citation Information

Patent Citations

  • Building support convenient to connect

    CN219753880U