Pipe burying and paying-off device for water conservancy building construction

By introducing a movable limiting component and a protective cover component into the pipe laying device for water conservancy construction, the stability problem of the device is solved, enabling flexible movement and stable fixation, thus ensuring construction safety and cable protection.

CN223737365UActive Publication Date: 2025-12-30ZHEJIANG XINFEI CONSTRUCTION CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520319927.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-02-26
Publication Date
2025-12-30
Estimated Expiration
2035-02-26

AI Technical Summary

Technical Problem

Existing hydraulic engineering construction pipe laying and setting equipment suffers from instability due to the bottom rollers affecting stability, leading to construction accidents.

Method used

A device for laying out pipes in water conservancy construction was designed. It adopts a movable limiting component and a protective cover component. The combination structure of casters and pins enables the device to move flexibly and be fixed stably. The protective cover component protects the laying component and avoids the influence of external factors.

Benefits of technology

This improved the stability of the device during the cable laying process, avoided unnecessary construction accidents, protected the cables from damage, and ensured construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223737365U_ABST
    Figure CN223737365U_ABST
Patent Text Reader

Abstract

The utility model discloses a water conservancy building construction buried pipe pay-off device, and relates to the technical field of water conservancy building construction, the water conservancy building construction buried pipe pay-off device comprises a moving table and a moving limiting assembly, the rear side of the moving table is provided with a push handle, the middle of the top of the moving table is provided with a pay-off assembly, and the exterior of the pay-off assembly is provided with a shield assembly; the moving limiting assemblies are symmetrically installed on the left side and the right side of the moving table. According to the pipe burying and paying-off device for water conservancy building construction, the moving limiting assemblies are symmetrically installed on the left side and the right side of the moving table in the front-back direction correspondingly, and it can be ensured that the whole device has good moving flexibility to the maximum extent through universal wheels; the stability of the whole device can be ensured in the take-up and pay-off process of the pay-off assembly, unnecessary structural deviation is avoided, and therefore the laying quality of the cable is guaranteed, and the use of the shield assembly can prevent the pay-off assembly from being affected by external factors in the use process, and consequently the cable is prevented from being damaged.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to water conservancy construction technical field, concretely is a water conservancy construction pipe laying device. BACKGROUND

[0002] Water conservancy construction refers to the construction process of various water conservancy facilities near water, mainly including the construction of reservoirs, dams, canals, hydropower stations and other buildings. These facilities are mainly used for flood control, irrigation, power generation, water supply and other purposes. Water conservancy construction involves various types of engineering, such as water gates, spillways, water tunnels, water intake structures, etc.

[0003] The water conservancy construction pipe laying device is an auxiliary device for laying pipes in water conservancy construction, mainly used for controlling the laying process of the pipes to ensure accurate and efficient laying of the pipes.

[0004] For example, the utility model with application number 202020513767.5 discloses a pipe laying device for water conservancy construction. The device has a pipe inlet on the box, making it easy to put different size pipe fittings into the device. Then, a rotating handle is installed to drive the gear and rack. The rack drives the fixed connection of the push plate to move up and down. The installed bracket and push bracket can fix different size pipes, thus satisfying the need of fixing different size pipes with one device and reducing construction cost. However, similar to the device in the above-mentioned document, the rollers at the bottom of the device can affect the stability of the device during laying, leading to unnecessary construction accidents.

[0005] Therefore, in view of the above, the existing structure and deficiencies are improved, and a water conservancy construction pipe laying device is proposed. UTILITY MODEL CONTENTS

[0006] The utility model aims to provide a water conservancy construction pipe laying device to solve the problems mentioned in the background.

[0007] To achieve the above-mentioned purpose, the utility model provides the following technical scheme: a water conservancy construction pipe laying device, including a mobile platform and a mobile limiting assembly, the rear side of the mobile platform is installed with a push handle, and the top middle of the mobile platform is installed with a laying assembly, and the outside of the laying assembly is provided with a protective cover assembly, the mobile limiting assembly is symmetrically installed on the left and right sides of the mobile platform, the mobile limiting assembly includes a fixed seat, a universal wheel, an adjusting shaft, a connecting seat, a plug and a rotating rod, the bottom of the fixed seat is installed with a universal wheel, and the side away from the mobile platform of the fixed seat is installed with an adjusting shaft, the end away from the fixed seat of the adjusting shaft is connected with the connecting seat, and the end away from the adjusting shaft of the connecting seat is perpendicularly installed with the plug, and the upper end of the plug is horizontally penetrated with the rotating rod.

[0008] Further, the push handle is fixed to the rear end top of the moving table by welding connection, and the pay-off assembly is transversely installed in the middle of the top of the moving table.

[0009] Further, the pay-off assembly comprises a winding roller, a limiting disc, a fixing disc, a connecting shaft and a supporting seat, the left and right ends of the winding roller are installed with the limiting discs, one side of the limiting disc is provided with the fixing disc, the side away from the limiting disc of the fixing disc is horizontally installed with the connecting shaft, and the side away from the fixing disc of the connecting shaft is connected with the supporting seat.

[0010] Further, the connecting shaft and the supporting seat are connected with each other through the bearing seat structure, and the fixing disc and the connecting shaft are fixedly connected.

[0011] Further, the shroud assembly comprises a protective cover, a connecting pile, a supporting pile and a fixing plate, the front and rear sides of the protective cover are installed with the connecting piles, and the ends away from the protective cover of the connecting piles are vertically connected with the supporting piles, and the bottom of the supporting pile is connected with the fixing plate.

[0012] Further, the supporting pile and the fixing plate are weldedly connected, and the connecting pile and the supporting pile are integrally arranged.

[0013] Further, the fixing seat is fixedly connected to the side edge of the moving table, and the fixing seat is symmetrically arranged on the side edge of the moving table.

[0014] Further, the drill rod and the connecting seat are screwedly connected, and the rotating rod and the drill rod are movably connected.

[0015] The water conservancy construction pipe burying pay-off device has the following beneficial effects:

[0016] 1. The water conservancy construction pipe burying pay-off device has the following beneficial effects: The universal wheel at the bottom of the fixing seat can make the whole device have flexible movement adjustment, thereby facilitating equipment carrying, the connecting seat is installed on the side edge of the fixing seat by the adjusting shaft, the connecting seat is rotatable by the structure of the adjusting shaft, axial rotation adjustment in the horizontal direction is realized, the connecting seat can be rotatably adjusted in the unused state, structural interference caused by movement of the whole device is avoided, the flexibility of the device structure is ensured, when the drill rod is needed to be used, the drill rod is rotated to the vertical state by the adjusting shaft, the rotating rod is horizontally inserted into the upper end of the drill rod, the drill rod is screwed into the ground, the whole device is fixed, the above structure can ensure the structural stability of the whole device during cable unwinding, unnecessary influence on cable winding and unwinding is avoided, and unnecessary safety accidents during construction are avoided.

[0017] 2、 The utility model discloses a protective cover is used to the top of the protective cover of setting up the support stake of connecting stake, realizes the structural connection between each other, and the fixed plate of cooperation support stake bottom, cooperates the use of bolt, to fix the whole protective cover assembly on the top surface of mobile station, and the protective cover assembly is covered in it, use the structure of above -mentioned, one aspect can provide good structural protection for the pay -off assembly, avoids the cable damage of the external factor in the mobile transport process, the other aspect is also to ensure that the pay -off assembly does not cause the pay -off problem due to the influence of external factors in the use process, to avoid the occurrence of construction accident. BRIEF DESCRIPTION OF DRAWINGS

[0018] Figure 1 It is the body axis side view structural schematic diagram of the utility model a water conservancy construction pipe laying pay -off device;

[0019] Figure 2 It is the pay -off assembly structure schematic diagram of the utility model a water conservancy construction pipe laying pay -off device;

[0020] Figure 3 It is the protective cover assembly three -dimensional structure schematic diagram of the utility model a water conservancy construction pipe laying pay -off device;

[0021] Figure 4 It is the mobile limiting assembly three -dimensional structure schematic diagram of the utility model a water conservancy construction pipe laying pay -off device.

[0022] In the drawing: 1, mobile station;2, push handle;3, pay -off assembly;301, winding roller;302, limiting disc;303, fixed disc;304, link shaft;305, support seat;4, protective cover assembly;401, protective cover;402, connecting stake;403, support stake;404, fixed plate;5, mobile limiting assembly;501, fixed seat;502, universal wheel;503, adjusting shaft;504, link seat;505, insert stake;506, rotating rod. DETAILED DESCRIPTION

[0023] The embodiment of the utility model is further described in detail below in combination with the drawings and examples. The following examples are used to illustrate the utility model, but cannot be used to limit the scope of the utility model.

[0024] As Figures 1 to 4The utility model discloses a water conservancy construction buried pipe pay-off device, including mobile station 1 and mobile limit component 5, the rear side of mobile station 1 is installed with push handle 2, and the top middle of mobile station 1 is installed with pay-off assembly 3, and the outside of pay-off assembly 3 is provided with shroud assembly 4, and mobile limit component 5 is installed to the left and right sides of mobile station 1 symmetrically, mobile limit component 5 includes fixed seat 501, universal wheel 502, adjusting shaft 503, link seat 504, plug 505 and rotary lever 506, the bottom of fixed seat 501 is installed with universal wheel 502, and the side, away from mobile station 1, of fixed seat 501 is installed with adjusting shaft 503, and the end, away from fixed seat 501, of adjusting shaft 503 is connected with link seat 504, and the end, away from adjusting shaft 503, of link seat 504 is vertically installed with plug 505, the upper end of plug 505 is horizontally penetrated with rotary lever 506 simultaneously, fixed seat 501 is fixedly connected to the side of mobile station 1, and fixed seat 501 is symmetrically arranged on the side of mobile station 1, plug 505 and link seat 504 are screw-connected, and rotary lever 506 and plug 505 are connected with movable insertion structure, the side of fixed seat 501 is installed with link seat 504 by adjusting shaft 503, so that link seat 504 realizes the axial rotation adjustment in horizontal direction by the structure rotation of adjusting shaft 503, when needing to use plug 505, only need to make plug 505 rotate to vertical state by adjusting shaft 503, and rotary lever 506 is horizontally inserted in the upper end of plug 505, plug 505 is inserted into the ground by the vertical screwing of rotary lever 506 plug 505, so that the whole device realizes the fixed effect.

[0025] As Figures 1 to 4As shown, the push handle 2 is fixed to the top rear end of the moving platform 1 by welding, and the wire feeding assembly 3 is horizontally installed in the middle of the top of the moving platform 1. The wire feeding assembly 3 includes a winding roller 301, a limiting plate 302, a fixing plate 303, a connecting shaft 304, and a support base 305. The left and right ends of the winding roller 301 are equipped with limiting plates 302, and a fixing plate 303 is provided on one side of the limiting plate 302. The connecting shaft 304 is horizontally installed on the side of the fixing plate 303 away from the limiting plate 302, and the support base 305 is connected to the side of the connecting shaft 304 away from the fixing plate 303. The connecting shaft 304 and the support base 305 are connected to each other through a bearing seat structure, and the fixing plate 303 and the connecting shaft 304 are fixedly connected. Component 4 includes a protective cover 401, a connecting pile 402, a support pile 403, and a fixing plate 404. The protective cover 401 is equipped with connecting piles 402 on both the front and rear sides. The end of the connecting pile 402 away from the protective cover 401 is vertically connected to the support pile 403. The bottom of the support pile 403 is connected to the fixing plate 404. The support pile 403 and the fixing plate 404 are welded together. The connecting pile 402 and the support pile 403 are integrated into one structure. The protective cover 401 is structurally connected to the support pile 403 with the connecting pile 402 on the top. With the help of the fixing plate 404 at the bottom of the support pile 403 and the use of bolts, the entire protective cover component 4 is fixed to the top surface of the moving platform 1.

[0026] In summary, as Figures 1 to 4 As shown, when using this hydraulic construction pipe laying and setting device, the entire device can first be moved to the designated working position by using the push handle 2 at one end of the moving platform 1 in conjunction with the universal wheels 502 installed at the bottom of the fixed base 501. Then, through the connecting shaft 304 at the upper end of the support base 305, the fixed plate 303 can drive the limiting plate 302 connected to the winding roller 301 to rotate horizontally. This can be used in conjunction with other external equipment and instruments to assist in the setting operation of pipe laying construction.

[0027] After the entire device is moved to the designated working position, the connecting seat 504 with the threaded insert 505 can be rotated and adjusted by adjusting the adjusting shaft 503 on one side of the fixed seat 501, so that the insert 505 is rotated to a suitable vertical state or a certain angle of inclination. Then, the rotating rod 506 is inserted horizontally into the upper end of the insert 505, and the insert 505 is screwed into the ground by using the rotating rod 506, thereby fixing the entire device to the ground to ensure sufficient structural stability.

[0028] During the use of the wire laying assembly 3, the protective cover 401, which is installed on the top of the moving platform 1 using the connecting stake 402, support stake 403 and fixing plate 404 in conjunction with bolts, provides good structural protection for the wire laying assembly 3 and prevents the wire laying from being affected.

[0029] The embodiments of this utility model are given for illustrative and descriptive purposes only, and are not intended to be exhaustive or to limit the utility model to the forms disclosed. Many modifications and variations will be apparent to those skilled in the art. The embodiments were chosen and described in order to better illustrate the principles and practical applications of this utility model, and to enable those skilled in the art to understand this utility model and design various embodiments with various modifications suitable for a particular purpose.

Claims

1. A water conservancy construction pipe laying device, comprising a moving table (1) and a moving limiting assembly (5), characterized in that: The back of the mobile station (1) is provided with a push handle (2), and the middle of the top of the mobile station (1) is provided with a pay-off assembly (3), and the outer part of the pay-off assembly (3) is provided with a shield assembly (4), and the mobile limiting assembly (5) is symmetrically arranged on the left and right sides of the mobile station (1), and the mobile limiting assembly (5) comprises a fixed seat (501), a universal wheel (502), an adjusting shaft (503), a connecting seat (504), a plug (505) and a rotating rod (506), the bottom of the fixed seat (501) is provided with the universal wheel (502), and the side of the fixed seat (501) away from the mobile station (1) is provided with the adjusting shaft (503), and the end of the adjusting shaft (503) away from the fixed seat (501) is connected with the connecting seat (504), and the end of the connecting seat (504) away from the adjusting shaft (503) is vertically provided with the plug (505), and the upper end of the plug (505) is horizontally penetrated by the rotating rod (506).

2. The pipe laying device for hydraulic construction according to claim 1, characterized in that, The push handle (2) is fixed to the rear end of the mobile station (1) by welding, and the pay-off assembly (3) is transversely arranged on the top of the mobile station (1).

3. The pipe laying device for hydraulic construction according to claim 1, characterized in that, The pay-off assembly (3) comprises a winding roller (301), a limiting disc (302), a fixed disc (303), a connecting shaft (304) and a supporting seat (305), the left and right ends of the winding roller (301) are provided with the limiting disc (302), one side of the limiting disc (302) is provided with the fixed disc (303), and the side of the fixed disc (303) away from the limiting disc (302) is horizontally provided with the connecting shaft (304), and the side of the connecting shaft (304) away from the fixed disc (303) is connected with the supporting seat (305).

4. The pipe laying device for hydraulic construction according to claim 3, characterized in that, The connecting shaft (304) and the supporting seat (305) are connected by a bearing seat structure, and the fixed disc (303) and the connecting shaft (304) are fixedly connected.

5. The pipe paying-out device for hydraulic construction according to claim 1, characterized in that The shield assembly (4) comprises a protective cover (401), a connecting pile (402), a supporting pile (403) and a fixed plate (404), the front and back sides of the protective cover (401) are provided with the connecting pile (402), and the end of the connecting pile (402) away from the protective cover (401) is connected with the supporting pile (403) perpendicularly, and the bottom of the supporting pile (403) is connected with the fixed plate (404).

6. A pipe laying device for hydraulic construction according to claim 5, characterized in that The supporting pile (403) and the fixed plate (404) are connected by welding, and the connecting pile (402) and the supporting pile (403) are connected in an integral structure.

7. The pipe laying device for hydraulic construction according to claim 1, wherein The fixed seat (501) is fixedly connected to the side of the mobile station (1), and the fixed seat (501) is symmetrically arranged on the side of the mobile station (1).

8. The pipe laying device for hydraulic construction according to claim 1, characterized in that, The plug (505) and the connecting seat (504) are connected by screwing, and the rotating rod (506) and the plug (505) are connected by an active insertion structure.

Citation Information

Patent Citations

  • Buried pipe pay-off device for water conservancy construction

    CN212075925U