Closure structure for water conservancy construction

By designing the interception structure for water conservancy construction, the connection to the river channel was achieved using enclosures and control machines, solving the problem of screw rusting, improving the stability and safety of water conservancy construction, and realizing flexible control of water flow and convenient river channel cleaning.

CN223738561UActive Publication Date: 2025-12-30李菲
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202520123629.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-19
Publication Date
2025-12-30
Estimated Expiration
2035-01-19

AI Technical Summary

Technical Problem

In existing water conservancy construction, the screws connecting water pipes are prone to rust in humid environments, leading to unstable connections, reducing the strength and safety of structural reinforcement devices, and lacking efficient and quick connection methods.

Method used

A diversion structure for hydraulic construction was designed, including a enclosure structure and a control structure. The enclosure is composed of an installation frame, connecting blocks, connectors, and installation blocks. The control machine and control rod are used to realize the diversion and smooth switching of water flow. The connecting blocks and installation blocks can be disassembled for easy installation and replacement. The cleaning blocks can clean up river debris.

Benefits of technology

It improves the stability and safety of water pipe connections, ensures the stability and efficiency of water conservancy construction, and facilitates installation and cleaning of river debris, enhancing the smoothness and stability of the device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223738561U_ABST
    Figure CN223738561U_ABST
Patent Text Reader

Abstract

The utility model discloses a closure structure for water conservancy construction, which belongs to the technical field of water conservancy construction, and adopts the technical scheme that the closure structure comprises a fence structure, the top of the fence structure is in bolted connection with a control structure, the outer side of a mounting frame is fixedly connected with the inner side of a fixing plate, and the inner side of the mounting frame is in sliding connection with the outer side of a connecting block; the inner side of the mounting frame is in sliding connection with the outer side of the connecting piece, the inner side of the mounting frame is in sliding connection with the outer side of the mounting block, the top of the connecting block is in bolting connection with the bottom of the connecting piece, the top of the connecting piece is in bolting connection with the bottom of the mounting block, and the left side of the connecting block is in bolting connection with the right side of the cleaning net. In the existing water conservancy construction process, a dam or a bridge needs to be built, and generally, the water level needs to be lowered to a certain degree, so that construction of a foundation part is facilitated, it is ensured that the water level is within a controllable range in the construction period, and water conservancy construction is protected against interference.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to water conservancy construction technical field especially relates to a water conservancy construction's cut off structure. BACKGROUND

[0002] Water conservancy construction refers to the engineering activities related to the development, utilization, governance and protection of water resources. These projects usually include reservoir construction, irrigation system construction, flood control facility construction and hydropower station construction. Water conservancy construction projects play an important role in improving agricultural irrigation conditions, flood control and disaster reduction, and providing water and electricity energy. In water conservancy construction, cutoff refers to a measure taken to provide a dry working environment for construction when building a dam or other structures on a river. Specifically, cutoff is to set temporary or permanent barriers in the river to divert the river water or temporarily stop it from flowing into the construction area, thereby ensuring the safety and efficiency of construction.

[0003] In existing water conservancy construction, connecting pipes are used to implement some steps of construction. In the use of connecting pipes, most are set to be used underground. In the setting of a whole section of connecting pipes, a reinforcing structure is usually provided to ensure the stability of the connecting pipe in use and prevent the connecting pipe from breaking in use. At this time, a structure reinforcing device for water conservancy construction is used. In the use of the structure reinforcing device for water conservancy construction, most existing reinforcing devices connect two connecting pieces through screws. However, since the underground environment is mostly humid, the screw is prone to rust in long-term use, which may cause unstable connection. This may reduce the use intensity of the structure reinforcing device for water conservancy construction. However, most existing structure reinforcing devices for water conservancy construction do not have a more efficient, quick and stable connection method, which may reduce the stability and safety of the overall device in use.

[0004] The existing patent (publication number: CN220551621U) discloses a structure reinforcing device for water conservancy construction. One, by aligning the connecting block on the first connecting plate with the connecting slot on the second connecting plate, then moving relatively, finally making the limiting block enter the inside of the clamping slot to realize mutual blocking, finally can be to realize the connection and fixation of the first connecting plate and the second connecting plate on the outside of the connecting pipe, thereby effectively improving the stability of the connecting pipe in use, improving the use effect of the connecting pipe in use in water conservancy engineering construction. Two, since the bottom of the limiting block is provided with an inclined surface, the limiting block can enter the inside of the connecting slot more smoothly during movement with the connecting block. The movement of the limiting block into the inside of the clamping slot under the elastic force of the first spring has a promoting effect, improving the smoothness and stability of the overall device in operation.

[0005] In view of the above problems, the existing patent provides a solution, and in the process of water conservancy construction, the dam or bridge needs to be built, and generally the water level needs to be lowered to a certain extent to facilitate the construction of the foundation part, ensure that the water level is within the controllable range during construction, and protect the water conservancy construction from interference.

[0006] Therefore, a water conservancy construction cutoff structure is provided. Utility model content

[0007] The utility model discloses a water conservancy construction cutoff structure, which can solve the problem that in the process of water conservancy construction, the dam or bridge needs to be built, and generally the water level needs to be lowered to a certain extent to facilitate the construction of the foundation part, ensure that the water level is within the controllable range during construction, and protect the water conservancy construction from interference.

[0008] To achieve the above object, the utility model provides the following technical scheme: a water conservancy construction cutoff structure, comprising a fence structure, the top of the fence structure is connected with a control structure by a bolt;

[0009] The fence structure comprises a mounting frame, a fixed plate, a connecting block, a connecting piece, a mounting block and a cleaning block, the outer side of the mounting frame is fixedly connected with the inner side of the fixed plate, the inner side of the mounting frame is slidably connected with the outer side of the connecting block, the inner side of the mounting frame is slidably connected with the outer side of the connecting piece, the inner side of the mounting frame is slidably connected with the outer side of the mounting block, the top of the connecting block is connected with the bottom of the connecting piece by a bolt, the top of the connecting piece is connected with the bottom of the mounting block by a bolt, and the left side of the connecting block is connected with the right side of the cleaning net by a bolt.

[0010] Preferably, the top of the mounting frame is connected with a mounting piece by a bolt, the top of the mounting piece is connected with a control machine, and a threaded hole is formed in the top of the mounting piece.

[0011] Preferably, the inner wall of the control machine is threadedly connected with a control rod, and the outer wall of the control rod is threadedly connected with the inner wall of the mounting piece.

[0012] Preferably, the bottom of the control rod is connected with the top of the mounting block by a bolt, the bottom of the mounting block is movably connected with the bottom of the control machine, and the top of the control rod is connected with a connecting disc.

[0013] Preferably, the inner side of the cleaning block is fixedly connected with a reinforcing rod, the number of the reinforcing rods is two, and a plurality of communication holes are formed in the top of the cleaning block.

[0014] Preferably, the top of the connecting block and the top of the connecting piece are both fixedly connected with a plug-in block, the bottom of the mounting block and the bottom of the connecting piece are both provided with a rectangular groove, and the outer side of the plug-in block is inserted into the inner side of the rectangular groove.

[0015] Preferably, the outer side of the connecting disc is sleeved with a protective cover, and the bottom of the protective cover is movably connected with the top of the control machine.

[0016] Preferably, the left side of the mounting frame is bolted with a connecting plate, and the left side of the connecting plate is fixedly connected with a measuring rod.

[0017] Compared with the prior art, the utility model has the beneficial effects that:

[0018] 1、The present application is provided with a fence structure, first, the user installs the mounting frame part to the river channel, and fixes the position of the mounting frame by fixing the two side fixed plates of the mounting frame, thereby increasing the stability of the mounting frame, the connecting block, connecting piece and mounting block arranged in the inner side of the mounting frame constitute a fence, which can intercept the river water, and the connecting block, connecting piece and mounting block can be disassembled, which is convenient for the user to install and replace any part, the cleaning block installed on the left side of the connecting block is translated upward in the inner side of the mounting frame, which can lift the garbage blocked on one side of the intercepting structure upward, and the user can clean the garbage on the cleaning block, thereby making the river more unobstructed.

[0019] 2、The present application is provided with a control structure installed on the fence structure, wherein the mounting part is installed on the top of the mounting frame, and the top of the control rod is bolted with the top of the mounting block, when the user needs to stop intercepting the river water flow, the user starts the control machine on the top of the mounting part, the operation of the control machine will make the control rod rise, and the rising of the control rod drives the mounting block part to translate upward in the inner side of the mounting frame, thereby making the river water flow unobstructed, when water conservancy construction treatment is needed, the control machine is used to control the control rod part, so that the mounting block part translates downward to intercept the river. BRIEF DESCRIPTION OF DRAWINGS

[0020] Figure 1 It is the overall structure diagram of the intercepting structure of the water conservancy construction of the utility model;

[0021] Figure 2 It is the disassembled view of the fence structure of the utility model;

[0022] Figure 3 It is the disassembled view of the control structure of the utility model;

[0023] Figure 4 It is the overall structure right view of the utility model; Figure 1

[0024] Figure 5 It is the structure activity view of the utility model. Figure 1

[0025] ​​In the figure, 1, the fence structure; 11, the mounting frame; 12, the fixed plate; 13, the connecting block; 14, the connecting piece; 15, the mounting block; 16, the cleaning block; 2, the control structure; 21, the mounting piece; 22, the control machine; 23, the control rod; 24, the connecting disc; 3, the threaded hole; 4, the reinforcing rod; 5, the communication hole; 6, the plug-in block; 7, the rectangular groove; 8, the protective cover; 9, the connecting plate; 10, the measuring rod. DETAILED DESCRIPTION

[0026] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the utility model.

[0027] Please refer to Figures 1-5 The utility model provides technical schemes:

[0028] A water conservancy construction's cut-off structure, including fence structure 1, the top of fence structure 1 is bolted with control structure 2;

[0029] Fence structure 1 includes mounting frame 11, fixed plate 12, connecting block 13, connecting piece 14, mounting block 15 and cleaning block 16, and the outer side of mounting frame 11 is fixedly connected with the inner side of fixed plate 12, the inner side of mounting frame 11 is slidably connected with the outer side of connecting block 13, the inner side of mounting frame 11 is slidably connected with the outer side of connecting piece 14, the inner side of mounting frame 11 is slidably connected with the outer side of mounting block 15, the top of connecting block 13 is bolted with the bottom of connecting piece 14, the top of connecting piece 14 is bolted with the bottom of mounting block 15, and the left side of connecting block 13 is bolted with the right side of cleaning net.

[0030] In the embodiment: by setting fence structure 1, first, the user installs mounting frame 11 to river channel, by fixing and mounting frame 11 both sides fixed plate 12, for fixing the position of mounting frame 11, increase the stability of mounting frame 11, by the connecting block 13, connecting piece 14 and mounting block 15 of mounting frame 11 inner side setting fence, can carry out cut-off to river channel water, and connecting block 13, connecting piece 14 and mounting block 15 can be split, convenient for user installation while convenient for replacing any part, by installing the cleaning block 16 of connecting block 13 left side, can be controlled by control structure 2 control connecting block 13 part in the inner side of mounting frame 11 and make cleaning block 16 move upwards, can lift the garbage of one side blockage of cut-off structure upwards, can conveniently user clean the garbage on cleaning block 16, make river channel more unobstructed.

[0031] Specifically, as Figure 3 ,Figure 4 、 Figure 5 As shown in the figure, the top of the installation frame 11 is bolted with the installation piece 21, the top of the installation piece 21 is bolted with the control machine 22, and the top of the installation piece 21 is provided with a threaded hole 3.

[0032] Specifically, as shown in the figure, Figure 3 、 Figure 4 、 Figure 5 The inner wall of the control machine 22 is threadedly connected with the control rod 23, and the outer wall of the control rod 23 is threadedly connected with the inner wall of the installation piece 21.

[0033] Specifically, as shown in the figure, Figure 3 、 Figure 4 、 Figure 5 The bottom of the control rod 23 is bolted with the top of the installation block 15, the bottom of the installation block 15 is movably connected with the bottom of the control machine 22, and the top of the control rod 23 is bolted with the connecting disc 24.

[0034] In this embodiment: by setting the control structure 2 installed on the fence structure 1, wherein the installation piece 21 is partially installed on the top of the installation frame 11, and the top of the control rod 23 is bolted with the top of the installation block 15, when the user needs to stop the river flow, the user starts the control machine 22 on the top of the installation piece 21, the operation of the control machine 22 will make the control rod 23 rise, and the rising of the control rod 23 will drive the installation block 15 to move upward on the inside of the installation frame 11, so that the river flow is smooth, when water conservancy construction treatment is needed, the control machine 22 is used to control the control rod 23, and the installation block 15 is partially translated downward to block the river, and the connecting disc 24 installed on the top of the control rod 23 is used to protect the top of the control rod 23.

[0035] Specifically, as shown in the figure, Figure 2 、 Figure 4 、 Figure 5 The inner side of the cleaning block 16 is fixedly connected with the reinforcing rod 4, the number of the reinforcing rod 4 is two, and the top of the cleaning block 16 is provided with a plurality of communication holes 5.

[0036] Specifically, as shown in the figure, Figure 2 The top of the connecting block 13 and the top of the connecting piece 14 are fixedly connected with the plug-in block 6, the bottom of the installation block 15 and the bottom of the connecting piece 14 are provided with a rectangular slot 7, and the outer side of the plug-in block 6 is inserted with the inner side of the rectangular slot 7.

[0037] In the embodiment, the two reinforcing rods 4 fixed in the inner side of the cleaning block 16 are arranged to increase the strength of the cleaning block 16, prevent the cleaning block 16 from being damaged when lifting more garbage, the plurality of communication holes 5 arranged on the top of the cleaning block 16 are arranged to filter the intercepted soil in the riverway when the cleaning block 16 is lifted, the plug-in block 6 fixed on the top of the connecting block 13 and the top of the connecting piece 14 and the bottom of the mounting block 15 and the bottom of the connecting piece 14 are arranged with the rectangular slot 7, and the connecting block 13, the connecting piece 14 and the mounting block 15 are arranged to be tightly connected.

[0038] Specifically, as shown in Figure 1 、 Figure 4 、 Figure 5 , the outer side of the connecting disc 24 is sleeved with the protective cover 8, and the bottom of the protective cover 8 is movably connected with the top of the control machine 22.

[0039] Specifically, as shown in Figure 1 、 Figure 5 , the left side of the mounting frame 11 is bolted with the connecting plate 9, and the left side of the connecting plate 9 is fixedly connected with the measuring rod 10.

[0040] In the embodiment, the protective cover 8 sleeved on the outer side of the connecting disc 24 is arranged to protect the control rod 23 and part of the control machine 22, and the measuring rod 10 arranged through the connecting plate 9 is arranged on the mounting frame 11 to measure the water level.

[0041] Working principle: in the use situation of water conservancy construction to cut off water, by setting the fence structure 1, first the user installs the frame 11 part to the river, through the fixed plate 12 on both sides of the installation frame 11, used for fixing the position of the installation frame 11, increase the stability of the installation frame 11, through the connecting block 13, connecting piece 14 and installation block 15 set in the inside of the installation frame 11, the fence can cut off the river water, and the connecting block 13, connecting piece 14 and installation block 15 can be disassembled, convenient for the user to install at the same time convenient for replacing any part, through the cleaning block 16 installed on the left side of the connecting block 13, the control structure 2 can be controlled by the connecting block 13 part in the inside of the installation frame 11 up translation makes the cleaning block 16 upward movement, can lift the garbage on the side of the cut-off structure, can conveniently use the user to clean the garbage on the cleaning block 16, make the river more unobstructed, by setting the control structure 2 installed on the fence structure 1, wherein the mounting piece 21 part is installed on the top of the installation frame 11, at the same time, the top of the control rod 23 is connected with the top of the installation block 15, when the user needs to stop the river water flow cut-off, the user starts the control machine 22 on the top of the mounting piece 21, the operation of the control machine 22 will make the control rod 23 rise, and the rising of the control rod 23 drives the installation block 15 part in the inside of the installation frame 11 up translation, makes the river water flow unobstructed, when needing to carry out water conservancy construction processing, again through the control machine 22 controls the control rod 23 part, makes the installation block 15 part downward translation to cut off the river.

[0042] The above is only the preferred embodiment of the present application, and is not used to limit the present application, any modification, equivalent replacement and improvement within the spirit and principle of the present application should be included in the protection scope of the present application.

Claims

1. A closure structure for waterway construction, comprising a containment structure (1), characterized in that: The top of the fence structure (1) is bolted with a control structure (2); The fence structure (1) comprises a mounting frame (11), a fixed plate (12), a connecting block (13), a connecting piece (14), a mounting block (15) and a cleaning block (16), the outer side of the mounting frame (11) is fixedly connected with the inner side of the fixed plate (12), the inner side of the mounting frame (11) is slidably connected with the outer side of the connecting block (13), the inner side of the mounting frame (11) is slidably connected with the outer side of the connecting piece (14), the inner side of the mounting frame (11) is slidably connected with the outer side of the mounting block (15), the top of the connecting block (13) is bolted with the bottom of the connecting piece (14), the top of the connecting piece (14) is bolted with the bottom of the mounting block (15), and the left side of the connecting block (13) is bolted with the right side of the cleaning net.

2. The closure structure for hydraulic construction according to claim 1, characterized in that: The top of the mounting frame (11) is bolted with a mounting piece (21), the top of the mounting piece (21) is bolted with a control machine (22), and a threaded hole (3) is formed in the top of the mounting piece (21).

3. A closure structure for a waterway construction according to claim 2, characterized in that: The inner wall of the control machine (22) is threadedly connected with a control rod (23), and the outer wall of the control rod (23) is threadedly connected with the inner wall of the mounting piece (21).

4. The cut-off structure for hydraulic construction according to claim 3, characterized in that: The bottom of the control rod (23) is bolted with the top of the mounting block (15), the bottom of the mounting block (15) is movably connected with the bottom of the control machine (22), and the top of the control rod (23) is bolted with a connecting disc (24).

5. The closure structure of claim 1, wherein: The inner side of the cleaning block (16) is fixedly connected with a reinforcing rod (4), the number of the reinforcing rod (4) is two, and a plurality of communication holes (5) are formed in the top of the cleaning block (16).

6. The closure structure of claim 1, wherein: The top of the connecting block (13) and the top of the connecting piece (14) are fixedly connected with a plug-in block (6), the bottom of the mounting block (15) and the bottom of the connecting piece (14) are provided with a rectangular groove (7), and the outer side of the plug-in block (6) is inserted into the inner side of the rectangular groove (7).

7. The closure structure of claim 4, wherein: The outer side of the connecting disc (24) is sleeved with a protective cover (8), and the bottom of the protective cover (8) is movably connected with the top of the control machine (22).

8. The closure structure of claim 1, wherein: The left side of the mounting frame (11) is bolted with a connecting plate (9), and the left side of the connecting plate (9) is fixedly connected with a measuring rod (10).

Citation Information

Patent Citations

  • Structure reinforcing device for water conservancy construction

    CN220551621U