Molten aluminum launder baffle of smelting furnace group
By designing baffles for aluminum molten flow channels made of high-temperature resistant materials, the problems of inconvenient handling and breakage of insulation cotton have been solved, improving service life and operational safety, and ensuring the quality of aluminum molten material and furnace guiding efficiency.
Patent Information
- Application Number
- CN202520780389.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-23
- Publication Date
- 2026-02-03
- Estimated Expiration
- 2035-04-23
AI Technical Summary
In the existing technology, the lack of a dedicated baffle during the furnace operation of aluminum scrap furnaces makes it inconvenient to remove and place the insulation cotton, which is easily broken, difficult to clean, affects the quality of molten aluminum, and increases safety risks.
An aluminum liquid flow channel baffle was designed, which includes a protective plate, a heat insulation cotton support plate, a positioning plate, and a handle. It is made of high-temperature resistant material and is connected by welding to ensure that the heat insulation cotton does not fall off during use and is easy to operate before and after the furnace.
It improves the service life of the insulation cotton, reduces the labor intensity of operators, avoids the safety hazards of handling insulation cotton at high temperatures, and ensures the quality of molten aluminum and the efficiency of furnace operation.
Smart Images

Figure CN223869824U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to mechanical assembly field, and particularly relates to a molten aluminum flow groove baffle of smelting furnace group. BACKGROUND
[0002] The aluminum scrap furnace is the main furnace group for melting aluminum scrap, in the actual production process, after the aluminum scrap is melted into molten aluminum, the molten aluminum cannot be directly used as finished product molten aluminum due to the high slag content in the aluminum scrap liquid, and needs to be statically placed for a period of time before being output. In order to ensure the static time, two static furnaces are matched with one aluminum scrap furnace, so that the aluminum scrap liquid is cyclically statically placed. In order to save space and cost, one Y-shaped flow groove is used between the aluminum scrap furnace and the two static furnaces for molten aluminum conveying. In order to ensure that the molten aluminum can be accurately introduced into the specified static furnace during each molten aluminum conveying process, the operator needs to use a baffle to block the other channel before each molten aluminum conveying, so as to prevent the molten aluminum from entering the other static furnace and affecting the static effect of the molten aluminum and the quality of the molten aluminum. If too much molten aluminum flows in, it will cause aluminum running, overflow and other phenomena, which will damage personnel and equipment.
[0003] Due to the lack of a special molten aluminum baffle, heat insulation cotton is usually used to block the flow groove, and the heat insulation cotton needs to be folded and repeatedly compacted in the flow groove before each use. However, since the heat insulation cotton is a fibrous material, part of the compacted heat insulation cotton will be broken and the slag will be removed when the molten aluminum conveying is completed. The operator needs to clean the broken slag, which is very time-consuming and will shorten the service life of the heat insulation cotton. If the broken slag is not cleaned thoroughly, it will enter the static furnace with the next molten aluminum conveying and pollute the molten aluminum in the furnace. During the repeated removal and placement of the heat insulation cotton, the high-temperature steam in the flow groove after the molten aluminum conveying will increase the risk of scalding the operator. UTILITY MODEL CONTENTS
[0004] In view of the above-mentioned problems, the utility model provides a molten aluminum flow groove baffle of smelting furnace group, which solves the problems of inconvenient removal and placement of the heat insulation cotton in the flow groove during the molten aluminum conveying of the aluminum scrap furnace, the difficulty in cleaning the broken heat insulation cotton during the removal process, improves the service life of the heat insulation cotton, reduces the labor intensity of the operator and avoids the safety hazards of the operator during the removal and placement of the heat insulation cotton in the high-temperature flow groove.
[0005] The utility model adopts the technical scheme that a molten aluminum flow groove baffle of smelting furnace group, including the guard, the heat insulation cotton support plate, the positioning plate, the handle, the limiting block. The shape of the guard is U-shaped structure, the guard and the heat insulation cotton support plate form the flow groove baffle loading hopper, be used for filling heat insulation cotton;The front part of the heat insulation cotton support plate has a small angle bending, ensure that the heat insulation cotton will not have the cotton wool fall into the flow groove and pollute the molten aluminum quality in the use process;The shape of the positioning plate is L-shaped, hang in the flow groove wall when using;The limiting block is placed in the fixed position above the flow groove wall, play the positioning effect to the whole flow groove baffle;The shape of the handle is U-shaped, be located on the positioning plate.
[0006] Further, the guard plate and the insulation cotton supporting plate are welded, the guard plate and the positioning plate are electrically welded, the handle and the positioning plate are electrically welded, and the limiting block and the flow groove are electrically welded.
[0007] Further, the guard plate and the insulation cotton supporting plate are made of cast steel, cast iron or other high-temperature-resistant materials, and the outer layer of the plate is coated with a high-temperature-resistant coating.
[0008] Further, the height of the guard plate should be slightly higher than the flow groove wall, the width of the insulation cotton supporting plate should be the same as the width of the flow groove, the bending length of the positioning plate should be equal to the width of the flow groove wall, and the width should be equal to the distance between the two limiting blocks on the same side of the flow groove, so as to ensure accurate and firm positioning.
[0009] Before the aluminum scrap furnace guide, fold the insulation cotton and put it into the flow groove baffle loading hopper, fill the loading hopper, then place the flow groove baffle in the flow groove, and the positioning plate is clamped in the limiting block on the flow groove during the placement process; then follow the normal steps to guide the furnace, and after the furnace is guided, the handle of the flow groove baffle can be pulled out by hand to take out the flow groove baffle as a whole, and if the insulation cotton needs to be replaced, the insulation cotton can be taken out from the flow groove baffle.
[0010] The utility model is suitable for the plugging work of the flow groove during the aluminum scrap furnace guide, solves the problems of inconvenient taking and placing of the insulation cotton in the flow groove during the aluminum scrap furnace guide, and the broken insulation cotton is not easy to clean during the taking process, improves the service life of the insulation cotton, improves the efficiency of each furnace guide, reduces the labor intensity of the operator, and avoids the safety hidden danger of the operator taking and placing the insulation cotton on the high-temperature flow groove. BRIEF DESCRIPTION OF DRAWINGS
[0011] Figure 1 It is a schematic view of the embodiment of the utility model.
[0012] Figure 2 It is a front view of the embodiment of the utility model.
[0013] Figure 3 It is a top view of the embodiment of the utility model.
[0014] The numbers in the figure represent as follows: 1. guard plate, 2. insulation cotton supporting plate, 3. positioning plate, 4. handle, 5. limiting block. DETAILED DESCRIPTION
[0015] The utility model will be further described in detail in combination with the embodiments and the drawings.
[0016] For example, Figure 1 , 2As shown in FIGS. 3, the utility model embodiment includes a molten aluminum flow groove baffle of smelting furnace group, including fender 1, heat insulation cotton supporting plate 2, locating plate 3, handle 4, limiting block 5. The shape of fender 1 is U type structure, fender 1 and heat insulation cotton supporting plate 2 constitute flow groove baffle charging hopper, be used to fill heat insulation cotton, the front part of heat insulation cotton supporting plate 2 has small angle bending, guarantee heat insulation cotton in the use process not to have cotton flock to fall into flow groove and pollute aluminum liquid quality, the shape of locating plate 3 is L type, hang in flow groove wall when using, limiting block 5 is placed in the fixed position above flow groove wall, play the positioning effect to whole flow groove baffle, the distance between two limiting blocks 5 on the same side flow groove is greater than the width of locating plate 3, the shape of handle 4 is U type, is located on locating plate 3. Fender 1 and heat insulation cotton supporting plate 2 are welded connection, fender 1 and locating plate 3 are electric welding connection, handle 4 and locating plate 3 are electric welding connection, limiting block 4 and flow groove are electric welding connection. The material of fender 1 and heat insulation cotton supporting plate 2 is cast steel, cast iron and other high-temperature resistant materials, and the outer layer of the plate is coated with a high-temperature resistant coating; the height of fender 1 should be slightly higher than the wall of the flow groove, the width of heat insulation cotton supporting plate 2 should be the same as the width of the flow groove, the bending length of locating plate 3 should be equal to the width of the flow groove wall, and the width should be equal to the distance between the two limiting blocks 4 to ensure accurate and firm positioning.
[0017] During operation, the heat insulation cotton is folded and placed in the flow groove baffle charging hopper before the aluminum scrap furnace guide, so that it fills the charging hopper, then the whole flow groove baffle is placed in the flow groove, and during the placement process, the locating plate is clamped in the limiting block on the flow groove, then the normal steps are followed to guide the furnace, and after the furnace guiding is completed, the handle of the flow groove baffle is pulled by hand to take out the whole flow groove baffle, and if the heat insulation cotton needs to be replaced, it can be taken out from the flow groove baffle. Thus, the problems of inconvenient taking and placing of the heat insulation cotton before and after the furnace guiding and the falling of debris during the taking and placing process are solved; the shape of the heat insulation cotton is relatively complete after the furnace guiding using the device, and it does not need to be frequently taken out and replaced. The service life of the heat insulation cotton is improved, and the labor intensity of the operator is also reduced.
[0018] The above describes the technical solutions provided by the embodiments of the utility model, and the principles and implementation manners of the embodiments of the utility model are described by applying specific examples; the above description of the embodiments is only applicable to helping understand the principles of the embodiments of the utility model; meanwhile, for those skilled in the art, according to the embodiments of the utility model, the specific implementation manners and application ranges will be changed, and the above description should not be understood as limiting the utility model.
Claims
1. A baffle for an aluminum molten metal flow channel in a smelting furnace, characterized in that: The flow channel baffle includes a protective plate, a heat insulation cotton support plate, a positioning plate, a handle, and a limiting block. The protective plate is U-shaped and together with the heat insulation cotton support plate form the flow channel baffle hopper for filling with heat insulation cotton. The front part of the heat insulation cotton support plate has a small-angle bend. The positioning plate is L-shaped and is hung on the flow channel wall during use. The limiting block is fixed in a position above the flow channel wall, and the handle is U-shaped and located on the positioning plate.
2. The aluminum molten metal flow channel baffle of the smelting furnace group as described in claim 1, characterized in that: The height of the guard plate should be higher than the wall of the flow channel, the width of the heat insulation cotton support plate should be the same as the width of the flow channel, the bending length of the positioning plate should be equal to the width of the flow channel wall, and the width should be equal to the distance between the two limiting blocks on the same side of the flow channel.