Grid type polymer waterproof coiled material with partitioned waterproof function
By introducing grid units and welded overlaps into the polymer waterproof membrane, a waterproof partition and three-dimensional locking structure are formed, which solves the problem of unobstructed diffusion of leakage in traditional membranes, and achieves fixed-point locking of leakage points and high bonding strength on the construction site.
Patent Information
- Application Number
- CN202520623385.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-03
- Publication Date
- 2026-02-24
- Estimated Expiration
- 2035-04-03
AI Technical Summary
Traditional pre-laid polymer waterproof membranes are susceptible to environmental factors during construction, which can lead to water seepage channels between the membrane and the subsequent poured structure, making it impossible to pinpoint the leak point and causing the leak to spread unimpeded.
The membrane is made of grid-type polymer waterproof membrane. It forms waterproof partitions on the substrate, increases the contact surface by using grid units and grout, and fixes adjacent membranes by welding the overlaps to form a three-dimensional locking structure, which enhances the waterproof effect.
It achieves point-to-point locking of leaking liquid, preventing its spread, improving the bonding strength and waterproofing safety at the construction site, and simplifying the construction process.
Smart Images

Figure CN223934325U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of waterproof membrane technology, specifically a grid-type polymer waterproof membrane with zoned waterproofing function. Background Technology
[0002] Traditional pre-laid polymer waterproof membranes consist of a polymer sheet coated with a polymer adhesive layer, and a layer of fine sand sprinkled on top of the adhesive layer, creating a slightly textured structure. The membrane adheres to the subsequently poured concrete through the adhesive layer and the fine sand.
[0003] However, during the on-site construction of traditional pre-laid polymer waterproof membranes, the adhesive layer on the surface of the membrane is particularly susceptible to environmental factors (such as ultraviolet radiation, rainwater immersion, and construction in low-temperature weather), which reduces the adhesiveness of the adhesive layer. This leads to water seepage channels between the membrane and the subsequently poured concrete structure. Because the surface of the membrane is flat, once leakage occurs between it and the subsequent pouring, it is an unobstructed, non-directional leakage, and the leakage point cannot be located. Utility Model Content
[0004] In view of the shortcomings of the existing technology, the purpose of this utility model is to provide a grid-type polymer waterproof membrane with zoned waterproofing function, which can solve the existing problems.
[0005] To achieve the above objectives, the technical solution of this utility model is as follows:
[0006] A grid-type polymer waterproof membrane with zoned waterproofing function, comprising a substrate;
[0007] The grid unit is tightly connected to the substrate to form several independent waterproof zones on top of the substrate; during the waterproof membrane laying stage, the waterproof zones are used to increase the contact surface between the waterproof membrane and the grout; during the waterproof membrane application stage, the waterproof zones are used to lock infiltrated liquids within the area they enclose.
[0008] The overlapping part is located on the side surface of the base, and no grid units are provided at the overlapping part.
[0009] Furthermore, the overlaps between adjacent waterproof membranes are fixed by welding.
[0010] Furthermore, the surface of the overlapping portion is coated with an adhesive layer, and a film is adhered to the surface of the adhesive layer.
[0011] Furthermore, the grid unit is thermally fused and fixed to the substrate as a single unit.
[0012] Furthermore, the grid unit includes a first rib and a second rib, which are arranged in a grid pattern.
[0013] Furthermore, the first and second reinforcing bars are arranged in a plane and intersecting each other; the thickness of the first reinforcing bar is the same as the thickness of the second reinforcing bar or the thickness of the first reinforcing bar is greater than the thickness of the second reinforcing bar.
[0014] Furthermore, the first rib is fixed to the surface of the base, and the second rib is cross-fixed to the top of the first rib; the thickness of the first rib is the same as the thickness of the second rib or the thickness of the first rib is greater than the thickness of the second rib.
[0015] Furthermore, the first rib is arranged parallel to the length of the base, the second rib is arranged parallel to the width of the base, and the first rib and the second rib intersect perpendicularly.
[0016] Furthermore, both the first and second reinforcing bars are arranged at an angle.
[0017] Furthermore, the side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.
[0018] Compared with the prior art, the beneficial effects of this utility model include:
[0019] 1. A waterproof partition can be formed on the top of the base through grid units. The waterproof partition confines the leakage liquid to an independent area to avoid spread. Compared with traditional pre-laid rolls, the leakage point is controllable. Once leakage occurs, it can be repaired at a fixed point without affecting adjacent partitions or the overall waterproof safety. There is no possibility of large-scale water seepage.
[0020] 2. When laying waterproof membrane, the grid unit can increase the connection surface between the base and the concrete. The grid unit and the concrete are physically interlocked and bonded, which is not affected by the environmental factors of the construction site. On-site pouring is simple and the bonding strength is high. Attached Figure Description
[0021] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0022] Figure 1 This is a top view structural diagram of an embodiment of the waterproof membrane of this utility model;
[0023] Figure 2 This is a side view structural diagram of an embodiment of the waterproof membrane of this utility model;
[0024] Figure 3This is a top view of the second embodiment of the waterproof membrane of this utility model;
[0025] Figure 4 This is a side view of the second embodiment of the waterproof membrane of this utility model.
[0026] Figure 5 This is a top view structural diagram of Embodiment 3 of the waterproof membrane of this utility model;
[0027] Figure 6 This is a side view structural diagram of Embodiment 3 of the waterproof membrane of this utility model;
[0028] Figure 7 This is a top view structural diagram of Embodiment 4 of the waterproof membrane of this utility model;
[0029] Figure 8 This is a side view structural diagram of Embodiment 4 of the waterproof membrane of this utility model;
[0030] Figure 9 Schematic diagrams of four embodiments of this utility model when the thickness of the first and second reinforcing bars are different;
[0031] The diagram is labeled as follows: 1. Base, 2. Overlap, 3. Grid unit, 31. First rib, 32. Second rib. Detailed Implementation
[0032] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions in the embodiments of this utility model are described clearly and completely. Obviously, the described embodiments are only some embodiments of this utility model, not all embodiments. Based on the embodiments of this utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of this utility model.
[0033] To address the technical problems raised in the background section, this utility model provides a grid-type polymer waterproof membrane with zoned waterproofing function, as shown in the following embodiment:
[0034] Example 1
[0035] like Figure 1 and Figure 2 As shown, a grid-type polymer waterproof membrane with zoned waterproofing function includes:
[0036] Substrate 1; Grid unit 3, which is tightly connected to the substrate to form several independent waterproof zones on the top of the substrate; during the waterproof membrane laying stage, the waterproof zones are used to increase the contact surface between the waterproof membrane and the grout; during the waterproof membrane application stage, the waterproof zones are used to lock infiltrated liquids within the areas they enclose. Overlap 2, which is located on the side surface of the substrate, and no grid unit is provided at the overlap.
[0037] The grid unit 3 includes a first rib 31 and a second rib 32, which are arranged in a grid pattern. The first rib is fixed to the base surface, and the second rib is intersected and fixed to the top of the first rib. Both the first and second ribs are arranged at an angle.
[0038] As one example, the overlap between adjacent waterproof membranes is welded.
[0039] As one embodiment, the surface of the overlapping portion is coated with an adhesive layer, and a film is adhered to the surface of the adhesive layer.
[0040] As one embodiment, the grid cells are thermally fused and fixed to the substrate as a single unit.
[0041] In this embodiment, the side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.
[0042] Specifically, the base is made of a high molecular polymer, such as modified polyethylene, polyvinyl chloride (PVC), or thermoplastic polyolefin (TPO); the thickness of the base is 0.7mm-1.5mm, providing the main body with waterproof performance;
[0043] Specifically, the spacing between adjacent first and second reinforcing bars is 1cm-8cm.
[0044] Specifically, the thickness of the first and second reinforcing bars is 2.0mm-3.0mm;
[0045] In this embodiment, the thickness of the first rib and the second rib can be the same or different; when they are different, such as... Figure 9 As shown in Figure c, the thickness of the first rib is greater than that of the second rib.
[0046] This embodiment has the following technical effects:
[0047] 1. A waterproof partition can be formed on the top of the base through grid units. The waterproof partition confines the leakage liquid to an independent area to avoid spread. Compared with traditional pre-laid rolls, the leakage point is controllable. Once leakage occurs, it can be repaired at a fixed point without affecting adjacent partitions or the overall waterproof safety. There is no possibility of large-scale water seepage.
[0048] 2. When laying waterproof membrane, the grid unit can increase the connection surface between the base and the concrete. The grid unit and the concrete are physically interlocked and bonded, which is not affected by the environmental factors of the construction site. On-site pouring is simple and the bonding strength is high.
[0049] 3. The grid unit has a double-layer, two-way grid structure, forming a three-dimensional locking structure, which further improves the zoned waterproofing effect of the grid unit.
[0050] Example 2
[0051] like Figure 3 and Figure 4 As shown, a grid-type polymer waterproof membrane with zoned waterproofing function includes:
[0052] Substrate; grid units, which are tightly connected to the substrate to form several independent waterproof zones on top of the substrate; during the waterproof membrane laying stage, the waterproof zones are used to increase the contact area between the waterproof membrane and the grout; during the waterproof membrane application stage, the waterproof zones are used to lock infiltrated liquids within the areas they enclose. Overlap, which is located on the side surface of the substrate, where no grid units are provided;
[0053] The grid unit includes a first rib and a second rib, which are arranged in a grid pattern. The first rib is fixed to the surface of the base, and the second rib is intersected and fixed to the top of the first rib. The first rib is arranged parallel to the length of the base, and the second rib is arranged parallel to the width of the base. The first rib and the second rib intersect perpendicularly.
[0054] As one example, the overlap between adjacent waterproof membranes is welded.
[0055] As one embodiment, the surface of the overlapping portion is coated with an adhesive layer, and a film is adhered to the surface of the adhesive layer.
[0056] As one embodiment, the grid cells are thermally fused and fixed to the substrate as a single unit.
[0057] In this embodiment, the side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.
[0058] Specifically, the base is made of a high molecular polymer, such as modified polyethylene, polyvinyl chloride (PVC), or thermoplastic polyolefin (TPO); the thickness of the base is 0.7mm-1.5mm, providing the main body with waterproof performance;
[0059] Specifically, the spacing between adjacent first and second reinforcing bars is 1cm-8cm;
[0060] Specifically, the thickness of the first and second reinforcing bars is 2.0mm-3.0mm;
[0061] In this embodiment, the thickness of the first rib and the second rib can be the same or different; when they are different, such as... Figure 9 As shown in Figure a, the thickness of the first rib is greater than that of the second rib.
[0062] Example 3
[0063] like Figure 5 and Figure 6 As shown, a grid-type polymer waterproof membrane with zoned waterproofing function includes:
[0064] Substrate; grid units, which are tightly connected to the substrate to form several independent waterproof zones on top of the substrate; during the waterproof membrane laying stage, the waterproof zones are used to increase the contact area between the waterproof membrane and the grout; during the waterproof membrane application stage, the waterproof zones are used to lock infiltrated liquids within the areas they enclose. Overlap, which is located on the side surface of the substrate, where no grid units are provided;
[0065] The grid unit includes a first rib and a second rib, which are arranged in a grid pattern; the first rib and the second rib are arranged in a planar pattern. Both the first rib and the second rib are arranged at an angle.
[0066] As one example, the overlap between adjacent waterproof membranes is welded.
[0067] As one embodiment, the surface of the overlapping portion is coated with an adhesive layer, and a film is adhered to the surface of the adhesive layer.
[0068] As one embodiment, the grid cells are thermally fused and fixed to the substrate as a single unit.
[0069] In this embodiment, the side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.
[0070] Specifically, the base is made of a high molecular polymer, such as modified polyethylene, polyvinyl chloride (PVC), or thermoplastic polyolefin (TPO); the thickness of the base is 0.7mm-1.5mm, providing the main body with waterproof performance;
[0071] Specifically, the spacing between adjacent first and second reinforcing bars is 1cm-8cm;
[0072] Specifically, the thickness of the first and second reinforcing bars is 2.0mm-3.0mm;
[0073] In this embodiment, the thickness of the first rib and the second rib can be the same or different; when they are different, such as... Figure 9As shown in Figure d, the thickness of the first rib is greater than that of the second rib, and the top surfaces of the first and second ribs are located on the same plane.
[0074] Example 4
[0075] like Figure 7 and Figure 8 As shown, a grid-type polymer waterproof membrane with zoned waterproofing function includes:
[0076] Substrate; grid units, which are tightly connected to the substrate to form several independent waterproof zones on top of the substrate; during the waterproof membrane laying stage, the waterproof zones are used to increase the contact area between the waterproof membrane and the grout; during the waterproof membrane application stage, the waterproof zones are used to lock infiltrated liquids within the areas they enclose. Overlap, which is located on the side surface of the substrate, where no grid units are provided;
[0077] The grid unit includes a first rib and a second rib, which are arranged in a grid pattern and intersecting each other; the first rib and the second rib are arranged in a plane and intersecting each other. The first rib is arranged parallel to the length of the base, and the second rib is arranged parallel to the width of the base, with the first rib and the second rib intersecting perpendicularly.
[0078] As one example, the overlap between adjacent waterproof membranes is welded.
[0079] As one embodiment, the surface of the overlapping portion is coated with an adhesive layer, and a film is adhered to the surface of the adhesive layer.
[0080] As one embodiment, the grid cells are thermally fused and fixed to the substrate as a single unit.
[0081] In this embodiment, the side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.
[0082] Specifically, the base is made of a high molecular polymer, such as modified polyethylene, polyvinyl chloride (PVC), or thermoplastic polyolefin (TPO); the thickness of the base is 0.7mm-1.5mm, providing the main body with waterproof performance;
[0083] Specifically, the spacing between adjacent first and second reinforcing bars is 1cm-8cm;
[0084] Specifically, the thickness of the first and second reinforcing bars is 2.0mm-3.0mm.
[0085] In this embodiment, the thickness of the first rib and the second rib can be the same or different; when they are different, such as... Figure 9As shown in Figure b, the thickness of the first rib is greater than that of the second rib, and the top surfaces of the first rib and the second rib are located on the same plane.
[0086] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0087] The above embodiments are only used to illustrate the technical solutions of this utility model, and are not intended to limit it. Although this utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this utility model.
Claims
1. A grid-type polymer waterproof membrane with zoned waterproofing function, characterized in that, include: Base; The grid unit is tightly connected to the substrate to form several independent waterproof zones on top of the substrate; During the waterproof membrane installation phase, waterproof zones are used to increase the contact area between the waterproof membrane and the grout. During the application of waterproof membranes, waterproof zones are used to contain infiltrated liquids within the areas they enclose. The overlapping part is located on the side surface of the base, and no grid units are provided at the overlapping part.
2. The grid-type polymer waterproof membrane with zoned waterproofing function according to claim 1, characterized in that: The overlap between adjacent waterproof membranes is fixed by welding.
3. The grid-type polymer waterproof membrane with zoned waterproofing function according to claim 1, characterized in that: The surface of the overlapping part is coated with an adhesive layer, and a film is bonded to the surface of the adhesive layer.
4. The grid-type polymer waterproof membrane with zoned waterproofing function according to claim 1, characterized in that: The grid cells are thermally fused to the substrate to form a single unit.
5. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 1, characterized in that: The grid unit includes a first rib and a second rib, which are arranged in a grid pattern.
6. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 5, characterized in that: The first and second ribs are arranged in a plane and intersecting each other. The thickness of the first rib is the same as the thickness of the second rib, or the thickness of the first rib is greater than the thickness of the second rib.
7. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 5, characterized in that: The first rib is fixed to the surface of the base, and the second rib is cross-fixed to the top of the first rib; the thickness of the first rib is the same as the thickness of the second rib or the thickness of the first rib is greater than the thickness of the second rib.
8. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 5, characterized in that: The first rib is arranged parallel to the length of the base, and the second rib is arranged parallel to the width of the base. The first rib and the second rib intersect perpendicularly.
9. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 5, characterized in that: Both the first and second reinforcing bars are arranged at an angle.
10. A grid-type polymer waterproof membrane with zoned waterproofing function according to claim 5, characterized in that: The side cross-sectional shape of the first rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle; the side cross-sectional shape of the second rib includes a circle, a rhombus, a rectangle, a solid shape, and a triangle.