Hoisting tool for vertical installation of cross beam protective cover of large vertical lathe

By designing a lifting tool that includes lifting lugs, brackets, round steel pipes, connecting blocks, and top screws, the interference problem during the vertical lifting of large crossbeam protective covers was solved, achieving an efficient and labor-saving installation process.

CN223950577UActive Publication Date: 2026-02-27QI ZHONG SHU KONG ZHUANG BEI GU FEN YOU XIAN GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423172439.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-23
Publication Date
2026-02-27
Estimated Expiration
2034-12-23

AI Technical Summary

Technical Problem

In existing technologies, large beam protective covers are prone to interference with the horizontal cable chain supports of the beams during vertical hoisting, resulting in low installation efficiency and high labor costs.

Method used

Design a lifting tool that includes lifting lugs, brackets, round steel pipes, connecting blocks, crossbars, and jacking screws. Through the cooperation of the brackets and connecting blocks, the protective cover can be easily installed vertically, avoiding interference.

Benefits of technology

It enables simple vertical installation of large beam protective covers, improves installation efficiency, saves time and labor costs, and is simple and quick to operate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223950577U_ABST
    Figure CN223950577U_ABST
Patent Text Reader

Abstract

The utility model discloses a hoisting tool for vertically installing a cross beam protective cover of a large vertical lathe, which comprises a lifting lug, a bracket, a circular steel tube, a connecting block, a cross rod and a jackscrew, the bracket is a C-shaped frame body and is formed by welding square tubes; in the opening direction of the support, lifting lugs are fixed to the ends of the outer sides of the two square pipes at the upper end of the support respectively, and a horizontal round steel pipe is fixed to the tops of the two square pipes at the lower end of the support. A horizontal cross rod is arranged below the round steel pipe, the two sides of the lower end of the support are each provided with a vertical connecting block, an upper through hole and a lower through hole are formed in each connecting block, and the connecting blocks penetrate through the round steel pipe and the cross rod through cooperation of the two through holes; the upper end and the lower end of one side of the connecting block are each in threaded connection with a horizontal jackscrew, and the jackscrews jack the round steel pipes and the transverse rods on the corresponding sides correspondingly, so that positioning of the round steel pipes and the transverse rods is achieved. According to the utility model, the large cross beam protective cover can be simply and vertically mounted, interference between the steel cable and the cross beam horizontal drag chain bracket is avoided, and the mounting efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a kind of hoisting tools for the vertical installation of large vertical lathe beam protective cover, belong to mechanical technical field. BACKGROUND

[0002] With the increasing demand of large vertical lathe, the number of large beam protective cover is also increasing, the original hoisting method of directly lifting beam protective cover using steel cable and horizontal pole has low installation efficiency, and gradually cannot meet the increasingly heavy production task, especially in the vertical lifting process of large protective cover, the steel cable often interferes with horizontal beam horizontal drag chain support, resulting in that beam protective cover cannot reach the specified installation position, and the phenomenon of consuming a lot of time and labor cost occurs by manual adjustment of protective cover position by installation personnel.

[0003] At present, the vertical lifting method of beam protective cover cannot realize simple and quick installation of large beam protective cover due to the interference of steel cable and horizontal beam horizontal drag chain support, causing a lot of time and labor cost waste. INVENTION CONTENTS

[0004] In order to overcome the deficiencies of the prior art, the utility model provides a kind of hoisting tool for the vertical installation of large vertical lathe beam protective cover, which can realize simple vertical installation of large beam protective cover, avoid the interference of steel cable and horizontal beam horizontal drag chain support, and has high installation efficiency, saves time and labor.

[0005] The utility model solves the technical scheme that the technical problem thereof adopts: a kind of simple hoisting tool for the vertical installation of large vertical lathe beam protective cover, including lifting lug, support, round steel pipe, connecting block, horizontal pole and top wire, the support is a C-shaped frame body, which is welded from square tube;In the opening direction of support, the end of the outer side of the upper end of the two square tubes of support is fixed with a lifting lug, and the top of the lower end of the two square tubes of support is fixed with a horizontal round steel pipe;A horizontal horizontal pole is arranged below the round steel pipe, a vertical connecting block is arranged on the lower side of the support, the connecting block is provided with two through holes, and the connecting block is passed through the round steel pipe and horizontal pole by two through holes;The upper and lower ends of one side of connecting block are both screw-connected with a horizontal top wire, and the top wire is respectively screwed with the round steel pipe and horizontal pole on the side of each, to realize the positioning of round steel pipe and horizontal pole.

[0006] Further, the round steel pipe and the horizontal pole are arranged at intervals, and the two connecting blocks and the support are arranged at intervals.

[0007] Further, the center line of the round steel pipe, the center line of the horizontal pole and the center line of the support are located on the same straight line.

[0008] Further, a reinforcing rib is fixed between the horizontal pipe and the vertical pipe of the upper end of the support and between the horizontal pipe and the vertical pipe of the lower end of the support.

[0009] Further, the distance between the two connecting blocks and the center line of the support is consistent.

[0010] The utility model discloses beneficial effect is: the utility model solves the problem that large crossbeam protection cover is easy to interfere with horizontal tow chain support in vertical assembly process, and the problem of adjusting protection cover position consumes a lot of time and manpower cost, through the use of this tool, can realize the simple vertical installation of large vertical lathe crossbeam protection cover, not only installation efficiency is high, but also save time and labour, simple and quick operation. BRIEF DESCRIPTION OF DRAWINGS

[0011] The utility model is further illustrated below in connection with the drawings and specific embodiment.

[0012] Figure 1 It is the structural schematic diagram of the utility model.

[0013] Figure 2 It is Figure 1 The side view of

[0014] Figure 3 It is the schematic diagram of using method of the utility model.

[0015] Mark in drawing:

[0016] 1, lifting lug, 2, support, 3, round steel pipe, 4, connecting block, 5, crossbar, 6, jackscrew, 7, reinforcing rib, 8, crossbeam protection cover, 9, horizontal tow chain groove support, 10, crossbeam. SPECIFIC EMBODIMENT

[0017] As Figure 1 -3 shows, a kind of for the vertical installation of large vertical lathe crossbeam protection cover hoisting tool, including lifting lug 1, support 2, round steel pipe 3, connecting block 4, crossbar 5 and jackscrew 6, the support 2 is a C-shaped frame body, is formed by square tube welding, and the horizontal pipe between the upper end of support 2 and stand pipe and the horizontal pipe between the lower end of support 2 and stand pipe are all fixed with a reinforcing rib;In the opening direction of support 2, the end of the outer side of two square tubes of the upper end of support 2 is all fixed with a lifting lug 1, and the top of the lower end of two square tubes of support 2 is fixed with a horizontal round steel pipe 3;Horizontal round steel pipe 3 is provided with a horizontal crossbar 5 below, and round steel pipe 3 and crossbar 5 are arranged at intervals;The lower end of support 2 is provided with a vertical connecting block 4 on both sides, and the distance between the two connecting blocks 4 and the center line of support 2 is consistent;Two through holes are arranged in connecting block 4, and connecting block 4 is passed through round steel pipe 3 and crossbar 5 by two through holes;The center line of round steel pipe 3, the center line of crossbar 5 and the center line of support 2 are all located on the same straight line;The upper and lower ends of one side of connecting block 4 are all screw-connected with a horizontal jackscrew 6, and jackscrew 6 respectively jackscrew round steel pipe 3 and crossbar 5 on each side, to realize the positioning of round steel pipe 3 and crossbar 5.

[0018] In use, first, the crossbar 5 is installed into the lifting hole of the beam guard cover 8; the lifting lug 1 at the upper end of the support 2 is used to lift the support 2 to the upper side of the beam guard cover 8; the lower end round steel tube 3 of the support 2 and the crossbar 5 are respectively installed into the connecting blocks 4, the position of the support 2 and the connecting blocks 4 is adjusted, the center line of the support 2 is aligned with the center line of the beam guard cover 8, and the distance between the two connecting blocks 4 and the center line of the support 2 is consistent; at the same time, the two connecting blocks 4 should be as close as possible to the beam guard cover 8, but cannot be close to the beam guard cover 8, so as not to scratch the beam guard cover 8 during assembly; the top screw 6 is fastened, and the support 2 and the beam guard cover 8 are lifted for installation.

Claims

1. A hoisting tool for vertical installation of a large vertical lathe cross beam guard shield, characterized in that: The utility model relates to a kind of steel pipe support, including lug (1), support (2), round steel pipe (3), connecting block (4), cross bar (5) and jackscrew (6), the support (2) is a C-shaped frame body, is welded from square tube;In the opening direction of support (2), the end of the outer side of two horizontal pipes of support (2) upper end is fixed with a lug (1), and the top of the horizontal pipe of two horizontal pipes of support (2) lower end is fixed with a round steel pipe (3) in horizontal direction;Round steel pipe (3) is provided with a horizontal direction cross bar (5) below, and support (2) lower end both sides are provided with a vertical direction connecting block (4), and two through holes are arranged in connecting block (4) and are passed through round steel pipe (3) and cross bar (5) by two through holes cooperation;The upper and lower ends of one side of connecting block (4) are respectively screw-connected with a horizontal direction jackscrew (6), and jackscrew (6) respectively jackscrew round steel pipe (3) and cross bar (5) of each side, realize the positioning of round steel pipe (3) and cross bar (5).

2. A lifting tool for vertical installation of a cross beam guard shield of a large vertical lathe according to claim 1, characterized in that: Round steel pipe (3) and cross bar (5) are arranged at intervals, and two connecting blocks (4) and support (2) are arranged at intervals.

3. A lifting tool for vertical installation of a cross beam guard shield of a large vertical lathe according to claim 1, characterized in that: The center line of round steel pipe (3), the center line of cross bar (5) and the center line of support (2) are located on the same straight line.

4. A lifting tool for vertical installation of a cross beam guard shield of a large vertical lathe according to claim 1, characterized in that: The horizontal pipe between the vertical pipe of support (2) upper end and the horizontal pipe between the vertical pipe of support (2) lower end are both fixed with a reinforcing rib (7).

5. A lifting tool for vertical installation of a cross beam guard shield of a large vertical lathe according to claim 1, characterized in that: The distance between two connecting blocks (4) and the center line of support (2) is consistent.