Steel pipe pile guide frame for multi-pile construction
By designing a steel pipe pile guide frame for multi-pile construction, the simultaneous driving of multiple steel pipe piles was achieved, solving the problem of low construction efficiency in existing technologies and improving construction efficiency.
Patent Information
- Application Number
- CN202520195806.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-07
- Publication Date
- 2026-02-27
- Estimated Expiration
- 2035-02-07
AI Technical Summary
Existing technologies for driving steel pipe piles have low efficiency, long construction time, and require frequent movement of the guide frame for single steel pipe pile construction.
Design a steel pipe pile guide frame for multi-pile construction, including several positioning columns, upper guide beam, guide frame and lower longitudinal beam, guide wheels and top support components, which can perform pile driving operations on multiple steel pipe piles at one time and reduce the number of times the guide frame moves.
By reducing the number of times the guide frame is moved, the overall construction time is shortened and the efficiency of pile driving is improved.
Smart Images

Figure CN223951774U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to wharf engineering construction technical field especially relates to a steel pipe pile guide frame for multi -pile construction. BACKGROUND
[0002] The wharf is the key facility that ship safe stop, also is playing the indispensable convenient function in the cargo loading and unloading and transportation process. Among them, the high-pile wharf adopts the pile foundation plus the upper structure to form, and its pile foundation generally selects the steel pipe pile and installs through the sinking pile construction technology. In the current steel pipe pile sinking pile operation practice, generally adopts the steel pipe pile guide frame as the auxiliary tool to ensure the accuracy and high efficiency of sinking pile process.
[0003] However, the sinking pile construction technology in the prior art has certain limitations: that is, each sinking pile operation can only be constructed for single steel pipe pile, after completing the construction of a steel pipe pile, the steel pipe pile guide frame needs to be moved to the next predetermined position as a whole, so as to continue the construction of the next steel pipe pile. This way of construction one by one, the steel pipe pile guide frame needs to be moved frequently, therefore a lot of time is consumed, which leads to the extension of the overall construction period and the low construction efficiency. Therefore, the steel pipe pile guide frame in the prior art has the problems of long construction time and low construction efficiency in the sinking pile construction. SUMMARY
[0004] The utility model aims at overcoming the problem of long construction time and low construction efficiency in the sinking pile construction in the prior art, and provides a steel pipe pile guide frame for multi-pile construction.
[0005] The utility model provides a steel pipe pile guide frame for multi-pile construction, which comprises:
[0006] A plurality of positioning columns are fixed in the foundation, and the plurality of positioning columns are arranged in a straight line.
[0007] An upper guide beam is horizontally arranged, and the top of each positioning column is connected to the upper guide beam.
[0008] A plurality of guide frames are arranged along the length direction of the upper guide beam, four corners of each guide frame are provided with guide wheels, the guide wheels are used to contact the steel pipe pile, each guide wheel is provided with a jacking part, and the jacking part can drive the guide wheel to approach or move away from the steel pipe pile.
[0009] A lower longitudinal beam is horizontally arranged, and the column body of each positioning column is connected to the lower longitudinal beam.
[0010] The utility model provides a steel pipe pile guide frame for many stake construction, two upper guide beams connect the top of a plurality of positioning columns together, two lower longitudinal beams connect the column body of a plurality of positioning columns together, and then form the main structure of the guide frame. A plurality of positioning columns are used for fixing the guide frame in the foundation, and play the role of supporting and fixing the whole guide frame. The guide wheels can form effective lateral constraint on the steel pipe pile from four directions respectively. The position of the corresponding guide wheel is adjusted by the bracing component, so that the guide wheel applies appropriate pressure on the steel pipe pile, the effect of correcting the perpendicularity of the steel pipe pile can be realized, and then the perpendicularity of the steel pipe pile is restored to the predetermined range.
[0011] When the steel pipe pile is in pile sinking construction, the bottom end of the steel pipe pile passes through the guide frame, the guide wheel is used for supporting the side wall of the steel pipe pile and can provide horizontal supporting force for the steel pipe pile. A plurality of guide frames are arranged along the length direction of the upper guide beam, so that after the guide frame is installed in place, a plurality of steel pipe piles arranged in a straight line can be subjected to pile sinking operation at one time, and after the pile sinking operation of the batch of steel pipe piles is completed, the guide frame is moved to the next position. By arranging a plurality of guide frames on the upper guide beam, a plurality of steel pipe piles can be constructed at one time after the guide frame is moved each time, the number of times of moving the guide frame is reduced, and then the construction time of the whole pile sinking is shortened, and the construction efficiency of the whole pile sinking is improved.
[0012] The construction form of the positioning column has diversity, which can be a column designed by adopting a truss structure, or a column made of a single circular steel pipe alone, and in addition, can be a column structure formed by combining a plurality of circular steel pipes.
[0013] The upper guide beam can be a single longitudinal beam, or can be combined by a plurality of longitudinal beams. When the upper guide beam is a single longitudinal beam, a plurality of guide frames are arranged on the same side of the longitudinal beam. When the upper guide beam is combined by a plurality of longitudinal beams, for example, the upper guide beam is composed of two longitudinal beams, and the plurality of guide frames are arranged between the two longitudinal beams.
[0014] The lower longitudinal beam can be a single longitudinal beam, or can be combined by a plurality of longitudinal beams. When the lower longitudinal beam is a single longitudinal beam, the longitudinal beam is connected on the same side of the column body of all the positioning columns. When the lower longitudinal beam is combined by a plurality of longitudinal beams, for example, the lower longitudinal beam is composed of two longitudinal beams, and all the positioning columns are located between the two longitudinal beams.
[0015] The upper guide beam and the lower longitudinal beam can be made of I-shaped steel or box girder.
[0016] The material of the guide wheel can be rubber or polyurethane.
[0017] The specific number and arrangement of the guide frames can be accurately determined according to the detailed planning in the construction drawing of the steel pipe pile. Each guide frame can be fixedly connected to the upper guide beam, or the connection position can be adjusted.
[0018] Preferably, the number of positioning columns is two, and the two positioning columns are respectively connected to positions 1 / 6-1 / 3 of the length of the two ends of the upper guide beam. The lengths of the two positioning columns from the two ends of the upper guide beam can be the same or different.
[0019] Preferably, the two positioning columns are both double steel pipe columns, which include two steel pipes with a diameter of 400-600 mm, the arrangement direction of the two steel pipes is perpendicular to the length direction of the upper guide beam, and a plurality of horizontal rods are connected between the two steel pipes. The horizontal rods are used to strengthen the integrity of the two steel pipes. The two steel pipes can increase the sectional moment of inertia of the positioning column in the direction perpendicular to the length direction of the upper guide beam, thereby effectively improving the anti-tilting ability of the entire guide frame in this direction, and further strengthening the lateral stability of the guide frame as a whole.
[0020] Preferably, the upper guide beam includes two first stringers, the two first stringers are arranged side by side and horizontally, a plurality of guide frames are arranged between the two first stringers, the top of each positioning column is connected to a first cross beam, the first cross beam is perpendicular to the length direction of the upper guide beam, the two ends of the first cross beam are respectively connected to the first stringers, the bottom surface of the first cross beam is connected to the top of the two steel pipes, and a first inclined brace is connected between the first cross beam and the two steel pipes. This scheme allows the opposite sides of the guide frame to be better supported, so that the guide frame can be better fixed. At the same time, this scheme can further strengthen the connection effect of the positioning column and the upper guide beam.
[0021] Preferably, the lower stringer includes two second stringers, the two second stringers are arranged side by side and horizontally, and the two second stringers are respectively located on the two sides of the positioning column. This scheme can strengthen the connection of all the positioning columns, and further strengthen the integrity of the guide frame.
[0022] Preferably, a plurality of clamps are arranged between the two second stringers, the clamps are grouped every two, and each group of clamps is used to clamp the steel pipe pile which has been constructed. In use, when the steel pipe pile corresponding to a guide frame is driven into place, a group of clamps is used to clamp the steel pipe pile, so that the guide frame can further improve its overall stability by means of the steel pipe pile which has been driven into place.
[0023] Preferably, the inner side of each group of the clamp is provided with a protruding block matching the cross-sectional shape of the steel pipe pile, which is used to contact the steel pipe pile. This scheme can increase the contact point or contact area of the clamp with the steel pipe pile, thereby reducing the stress concentration effect on the steel pipe pile when the clamp clamps the steel pipe pile, and ensuring that the clamping effect of the clamp on the steel pipe pile is more firm. The cross-sectional shape of the steel pipe pile is generally circular, so the position where the protruding block contacts the steel pipe pile can also be designed as a circular arc, and the radius of the circular arc is consistent with the radius of the circular cross-section of the steel pipe pile.
[0024] Preferably, each of the guide frames can move along the length direction of the upper guide beam. This scheme can flexibly adjust the spacing between two adjacent guide frames according to requirements. This scheme can make the guide frame adapt to steel pipe piles with different spacing requirements, thereby improving the flexibility and applicability of the guide frame.
[0025] Preferably, the guide wheel is a rigid rubber rolling pulley. The rigid rubber rolling pulley has moderate deformation ability and can effectively prevent damage to the wall of the steel pipe pile due to excessive pressure when contacting and being pressed by the steel pipe.
[0026] The rigid rubber rolling pulley can maintain a certain deformation ability when being pressed by the steel pipe, so that the wall of the steel pipe pile is not damaged due to excessive pressure.
[0027] Preferably, the number of guide frames is 5-8. This scheme is suitable for most steel pipe pile construction projects.
[0028] Compared with the prior art, the utility model has the beneficial effects that:
[0029] 1. The utility model provides a steel pipe pile guide frame for multiple pile construction, through a plurality of guide frames arranged on the upper guide beam, a plurality of steel pipe piles can be constructed at a time after each movement of the guide frame, the number of times of moving the guide frame is reduced, thereby the construction time of the whole pile sinking is shortened, and the construction efficiency of the whole pile sinking is improved. BRIEF DESCRIPTION OF DRAWINGS
[0030] Figure 1 It is a front view of a steel pipe pile guide frame for multiple pile construction.
[0031] Figure 2 It is a top view of a steel pipe pile guide frame for multiple pile construction.
[0032] Figure 3 It is a side view of a steel pipe pile guide frame for multiple pile construction.
[0033] Figure 4 Figure Figure 3 Figure
[0034] Figure 5 Figure
[0035] Figure 6 Figure
[0036] Figure 7 Figure Figure 1 Figure
[0037] Figure 8 Figure Figure 1 Figure
[0038] Figure
[0039] 1 - positioning column,
[0040] 2 - upper beam,
[0041] 3 - lower longitudinal beam,
[0042] 4 - guide frame
[0043] 401 - guide wheel, 402 - jacking part,
[0044] 5 - clamp,
[0045] 501 - protruding block
[0046] 6 - first cross beam,
[0047] 7 - first diagonal strut,
[0048] 8 - second cross beam,
[0049] 9 - second diagonal strut,
[0050] 10 - horizontal rod,
[0051] 11 - third cross beam,
[0052] 12 - steel pipe pile,
[0053] 13 - foundation,
[0054] 14 - first connecting rod,
[0055] 15 - second connecting rod,
[0056] 16 - first end plate,
[0057] 17 - second end plate. DETAILED DESCRIPTION
[0058] The utility model will be described in further detail below in combination with specific embodiments. However, this should not be understood as limiting the scope of the above-mentioned subject matter of the utility model to the following embodiments only, and any technology realized based on the content of the utility model falls within the scope of the utility model.
[0059] In the description of the embodiments of the utility model, the terms indicating the orientation or position relationship of "up", "down", "left", "right", "center", "inner", "outer", etc. are expressed based on the orientation or position relationship shown in the drawings, or the orientation or position relationship when the product / equipment / device of the utility model is usually used. These terms of orientation or position relationship are only used to facilitate the description of the utility model scheme or simplify the description in the embodiments, so as to facilitate the quick understanding of the scheme by the technicians, and therefore cannot be understood as indicating or implying that the specific device / component / element must have a specific orientation or be constructed and operated in a specific position relationship, and thus cannot be understood as limiting the utility model.
[0060] In addition, if the terms "horizontal", "vertical", "overhanging", "parallel", etc. appear, it does not mean that the corresponding device / component / element must be absolutely horizontal or vertical or overhanging or parallel, but can be slightly inclined or deviated. For example, "horizontal" only means that its direction is more horizontal relative to "vertical", and does not mean that the structure must be completely horizontal, but can be slightly inclined. Alternatively, it can be simply understood that the corresponding device / component / element is arranged in the direction of "horizontal", "vertical", "overhanging", "parallel", etc., and can have an error / deviation of ±10% relative to the corresponding direction arrangement, more preferably an error / deviation of ±8% or less, more preferably an error / deviation of ±6% or less, more preferably an error / deviation of ±5% or less, and more preferably an error / deviation of ±4% or less. As long as the corresponding device / component / element is within the error / deviation range, it can still achieve its role in the scheme of the utility model.
[0061] In addition, the terms "first", "second", "third", etc. appearing in the terms are only used to distinguish the description of the same or similar components, and should not be understood as emphasizing or implying the relative importance of the specific components.
[0062] In addition, in the description of the embodiments of the utility model, "several", "a plurality of", "several" represent at least 2. It can be 2, 3, 4, 5, 6, 7, 8, 9, etc. in any case, or even more than 9.
[0063] Furthermore, in the description of the technical scheme of the utility model, unless otherwise explicitly specified / limited / limited, the terms "set", "install", "connect", "connect", "set", "lay", "arrange" should be understood broadly, for example, it can be fixedly connected, or it can be detachably connected, or integrally connected, which can be welding, riveting, bolting, screw connection and other commonly used connection means in the art. This connection can be mechanical connection, electrical connection or communication connection; it can be directly connected, or indirectly connected through an intermediate medium, or the communication between two elements.
[0064] Embodiment 1
[0065] As Figures 1-6 shown, a steel pipe pile guide frame for multi-pile construction, comprising a plurality of positioning columns 1, an upper guide beam 2, a plurality of guide frames 4 and a lower longitudinal beam 3.
[0066] The bottoms of the plurality of positioning columns 1 are fixed in the foundation 13, and the plurality of positioning columns 1 are arranged in a straight line. The column body of the positioning column 1 has a portion of 1 / 3-1 / 2 that can be buried below the ground. The purpose of this is to ensure that the positioning column 1 can be stably fixed in the foundation 13, thereby achieving the effect of enhancing stability.
[0067] The upper guide beam 2 is horizontally arranged, and the top of each positioning column 1 is connected with the upper guide beam 2. The upper guide beam 2 and the positioning column 1 can be welded.
[0068] The plurality of guide frames 4 are arranged along the length direction of the upper guide beam 2, and the four corners of the guide frame 4 are respectively provided with guide wheels 401, which are used to contact the steel pipe pile 12. Each guide wheel 401 is provided with a jacking component 402, which can drive the guide wheel 401 to approach or move away from the steel pipe pile 12. The lower longitudinal beam 3 is horizontally arranged, and the column body of each positioning column 1 is connected with the lower longitudinal beam 3, which can be connected by welding. The jacking component 402 can be a hydraulic jack or a mechanical screw jack.
[0069] In an optional embodiment, the number of positioning columns 1 can be two, and the two positioning columns 1 can be respectively connected at positions 1 / 6-1 / 3 away from the two ends of the upper guide beam 2. The specific distance can be 1 / 6, 1 / 5, 1 / 4 or 1 / 3 of the length of the upper guide beam 2. For example, the length of the upper guide beam 2 is 36 meters, and the two positioning columns 1 can be respectively connected at positions 9 meters away from the two ends of the upper guide beam 2.
[0070] In an optional embodiment, both positioning posts 1 can be double steel pipe columns, each comprising two steel pipes with a diameter of 400mm-600mm, specifically 400mm, 450mm, 480mm, 500mm, 530mm, 580mm, or 600mm, and a wall thickness of 10mm, 12mm, or 15mm. The arrangement direction of the two steel pipes is perpendicular to the length direction of the upper guide beam 2, and several horizontal bars 10 are connected between the two steel pipes. The horizontal bars 10 are evenly spaced along the height direction of the steel pipes, with a specific spacing of 350mm, 400mm, or 450mm.
[0071] In an optional embodiment, the upper guide beam 2 may include two first longitudinal beams arranged horizontally side by side, and a plurality of guide frames 4 are disposed between the two first longitudinal beams. The top of each positioning post 1 is connected to a first crossbeam 6, the first crossbeam 6 is perpendicular to the length direction of the upper guide beam 2, the two ends of the first crossbeam 6 are respectively connected to the first longitudinal beam, the bottom surface of the first crossbeam 6 is connected to the top of the two steel pipes, and a first diagonal brace 7 is connected between the first crossbeam 6 and the two steel pipes.
[0072] The first longitudinal beam can be made of double-I-beams, with the following cross-sectional dimensions: height 700mm, flange width 300mm, flange thickness 12mm, and web thickness 10mm. The length of each first longitudinal beam is 36 meters. The net distance between two first longitudinal beams can be 1400mm.
[0073] Specifically, the bottom surface of the first crossbeam 6 is welded to the top surface of the positioning column 1, and both ends of the top surface of the first crossbeam 6 are welded to the two first longitudinal beams respectively. The first crossbeam 6 can be an I-beam with a length of 3.8 meters, a cross-sectional height of 500 mm, and a cross-sectional width of 250 mm. The first diagonal brace 7 can also be an I-beam, and both ends of the first diagonal brace 7 are welded to the bottom surface of the first crossbeam 6 and the column body of the positioning column 1 respectively.
[0074] The specific connection method between the first longitudinal beam and the first transverse beam 6 can also be as follows: Figure 7 As shown, the first longitudinal beam overlaps the first transverse beam 6, and is then connected to the first transverse beam 6 via a first connecting rod 14 and a first end plate 16. Specifically, the first connecting rod 14 has a screw and a hook at both ends, and the first end plate 16 spans across the first longitudinal beam. Both ends of the first end plate 16 are connected to the screw ends of the two first connecting rods 14, and the hook ends of the two first connecting rods 14 are hooked onto the flanges of the first transverse beam 6.
[0075] In an optional embodiment, the lower longitudinal beam 3 can comprise two second longitudinal beams, the two second longitudinal beams are arranged side by side horizontally, and the two second longitudinal beams are respectively located on two sides of the positioning column 1.
[0076] The second longitudinal beam can be made of double-spliced I-beams, and the cross-sectional size of the I-beam is specifically 700 mm in height, 300 mm in flange width, 12 mm in flange thickness, and 10 mm in web thickness. The length of the second longitudinal beam is 36 meters. The net spacing of the two second longitudinal beams can be 1400 mm.
[0077] In an optional embodiment, the two second longitudinal beams can be connected with each positioning column 1 through a second cross beam 8. Specifically, the second cross beam 8 is horizontally placed and perpendicular to the length direction of the second longitudinal beam. The end face of one end of the second cross beam 8 is connected with the column body of the positioning column 1 through welding, and the top face of the other end of the second cross beam 8 is connected with the bottom face of the second longitudinal beam through welding. The second cross beam 8 can be an I-beam with a length of 0.9 meters, a cross-sectional height of 500 mm, and a cross-sectional width of 250 mm. A second diagonal brace 9 can be arranged between the second longitudinal beam and the second cross beam 8, the second diagonal brace 9 can be an I-beam, and the two ends of the second diagonal brace 9 are respectively connected with the bottom face of the second cross beam 8 and the column body of the positioning column 1 through welding. This scheme can further strengthen the connection effect of the positioning column 1 and the lower longitudinal beam 3.
[0078] The specific connection mode of the second longitudinal beam and the second cross beam 8 can also be as shown in Figure 8 The second longitudinal beam is lapped on the second cross beam 8, and then the second longitudinal beam and the second cross beam 8 are connected through a second connecting rod 15 and a second end plate 17. Specifically, the two ends of the second connecting rod 15 are respectively provided with a screw rod and a hook, the second end plate 17 spans on the second longitudinal beam, the two ends of the second end plate 17 are respectively connected with the screw rod end of the two second connecting rods 15, and the other ends of the two second connecting rods 15 with the hook are hooked on the flange of the second cross beam 8.
[0079] In an optional embodiment, a plurality of clamps 5 can be arranged between the two second longitudinal beams, the clamps 5 are grouped every two, and each group of clamps 5 is used to clamp the completed steel pipe pile 12. Specifically, the clamp 5 is a long rod structure, the two ends of the clamp 5 are respectively connected with the two second longitudinal beams, and the position of the clamp 5 on the second longitudinal beam can be adjusted. Two clamps 5 are respectively placed on the two sides of the completed steel pipe pile 12, and then the two clamps 5 on the two sides are respectively moved towards the steel pipe pile 12 until they contact the steel pipe pile 12, and then the two ends of the two clamps 5 are fixed with the second longitudinal beam, and the fixing mode can be bolted, thereby achieving the effect of clamping the completed steel pipe pile 12.
[0080] In an optional embodiment, the inner side of each group of clamps 5 is provided with a protruding block 501 matching the cross-sectional shape of the steel pipe pile 12, which is used to contact the steel pipe pile 12. Specifically, as shown in Figure 6 each clamp 5 can be provided with two protruding blocks 501, each of which is a right-angled triangle structure, one of whose right-angled sides is connected to the clamp 5, and the hypotenuse thereof is an arc structure matching the cross-sectional shape of the steel pipe pile 12, which directly contacts the steel pipe pile 12. A rubber sheet can also be provided on the arc structure to increase the friction with the outer wall of the steel pipe pile 12. The diameter of the steel pipe pile 12 is 1200 mm, and the radius of the corresponding arc structure is 600 mm.
[0081] In an optional embodiment, the guide frames 4 can move along the length direction of the upper guide beam 2. Specifically, the two first longitudinal beams are each provided with a plurality of screw holes along the length direction thereof, and the interval between adjacent two screw holes can be 100 mm, thereby providing an accurate adjustment unit. Each guide frame 4 has two side lengths parallel to the first longitudinal beam, and the two side lengths are both 1700 mm, and screw holes are provided on the two side lengths at an interval of 1500 mm. Through such a design, the guide frame 4 can be connected to any two screw holes on the first longitudinal beam at an interval of 1500 mm through bolts. Whenever the position of the guide frame 4 needs to be adjusted, it only needs to be moved by 100 mm along the length direction of the first longitudinal beam, and then be fixedly connected to the corresponding screw holes on the first longitudinal beam.
[0082] In an optional embodiment, the guide wheel 401 can be a rigid rubber rolling pulley.
[0083] In an optional embodiment, the number of guide frames 4 can be 5-8, and specifically, the number of guide frames 4 can be 5, 6, 7 or 8. When the number of guide frames 4 is 7 and the number of positioning columns 1 is two, two guide frames 4 can be placed between the left end of the upper guide beam 2 and the left positioning column 1, and two guide frames 4 can also be placed between the right end of the upper guide beam 2 and the right positioning column 1, and the remaining three guide frames 4 are placed on the upper guide beam 2 and located in the region between the two positioning columns 1.
[0084] In an optional embodiment, a plurality of third cross beams 11 can be provided between the two first longitudinal beams, which are used to strengthen the connection of the first longitudinal beams and increase the integrity of the guide frame.
[0085] In an optional embodiment, a handrail can also be provided above the two upper guide beams 2, which can ensure the safety of the personnel moving along the upper guide beam 2. A steel staircase can also be provided between the upper guide beam 2 and the ground, which facilitates the personnel to move to the upper guide beam 2 through the steel staircase.
[0086] Embodiment 2
[0087] Take a specific project as an example, the project needs to construct ten rows of steel pipe piles 12, each row contains seven steel pipe piles 12. In order to efficiently assist the pile construction of these steel pipe piles 12, a steel pipe pile guide frame for multi-pile construction described in embodiment 1 is adopted. The guide frame is equipped with seven guide frames 4, which matches the number of steel pipe piles 12 to be constructed in each row.
[0088] The construction process is as follows: first, install the guide frame above the first row of the predetermined steel pipe pile 12 construction position. Then, align the bottom of the seven steel pipe piles 12 one by one and pass through the corresponding guide frame 4 until they stand stably on the ground. At this time, the construction work of the steel pipe pile 12 can be started, such as hammering and sinking.
[0089] When the seven steel pipe piles 12 of the first row are all constructed, the entire guide frame is translated to the construction position of the second row of the predetermined steel pipe pile 12 above, and the above construction process is repeated until the ten rows of steel pipe piles 12 are all constructed.
[0090] It is worth noting that during the entire construction process, the guide frame only needs to be moved ten times (once for each row), compared with the cumbersome process of moving the guide frame once for each steel pipe pile 12 in the traditional method. Using the guide frame described in the present application, the construction period can be shortened and the construction efficiency can be greatly improved.
[0091] The above only describes the preferred embodiments of the present application and is not intended to limit the present application. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present application shall be included in the protection scope of the present application.
Claims
1. A steel pipe pile leader for multi-pile construction, characterized by, The utility model relates to a kind of steel pipe pile construction device, including: Several positioning columns (1), the bottom of several described positioning columns (1) is fixed in foundation (13), several described positioning columns (1) are in a straight line arrangement; Upper beam (2), the upper beam (2) is horizontally arranged, the top of each described positioning column (1) is connected with the upper beam (2); Several guide frames (4), several described guide frames (4) are arranged along the length direction of the upper beam (2), four corners of the guide frame (4) are provided with guide wheel (401) respectively, the guide wheel (401) is used to contact with steel pipe pile (12), each described guide wheel (401) is provided with jacking part (402), the jacking part (402) can drive the guide wheel (401) close to or away from the steel pipe pile (12); Lower longitudinal beam (3), the lower longitudinal beam (3) is horizontally arranged, the column body of each described positioning column (1) is connected with the lower longitudinal beam (3).
2. A steel pipe pile leader for multi-pile construction according to claim 1, characterized in that, The number of the positioning column (1) is two, and the two positioning columns (1) are connected at positions 1 / 6-1 / 3 length from two ends of the upper beam (2).
3. A steel pipe pile leader for multi-pile construction according to claim 2, characterized in that, The two positioning columns (1) are both double steel pipe columns, the double steel pipe column includes two steel pipes with a diameter of 400mm-600mm, the arrangement direction of the two steel pipes is perpendicular to the length direction of the upper beam (2), and a plurality of horizontal rods (10) are connected between the two steel pipes.
4. A steel pipe pile leader for multi-pile construction according to claim 3, characterized in that, The upper beam (2) includes two first longitudinal beams, the two first longitudinal beams are horizontally arranged side by side, a plurality of guide frames (4) are arranged between the two first longitudinal beams, the top of each positioning column (1) is connected with a first cross beam (6), the first cross beam (6) is perpendicular to the length direction of the upper beam (2), the two ends of the first cross beam (6) are connected with the first longitudinal beams respectively, the bottom surface of the first cross beam (6) is connected with the top of the two steel pipes, and a first inclined brace (7) is connected between the first cross beam (6) and the two steel pipes.
5. The steel pipe pile leader for multi-pile construction according to claim 3, characterized in that, The lower longitudinal beam (3) includes two second longitudinal beams, the two second longitudinal beams are horizontally arranged side by side, and the two second longitudinal beams are located on the two sides of the positioning column (1) respectively.
6. A steel pipe pile leader for multi-pile construction according to claim 5, characterized in that, A plurality of clamps (5) are arranged between the two second longitudinal beams, the clamps (5) are grouped every two, and each group of clamps (5) is used for clamping the steel pipe pile (12) which has been constructed.
7. A steel pipe pile leader for multi-pile construction according to claim 6, characterized in that, The inner side of each group of clamps (5) is provided with a protruding block (501) matched with the cross-sectional shape of the steel pipe pile (12), and the protruding block (501) is used for contacting with the steel pipe pile (12).
8. A steel pipe pile guide frame for multi-pile construction according to any one of claims 1-7, characterized in that, A plurality of guide frames (4) can move along the length direction of the upper beam (2).
9. A steel pipe pile leader for multiple pile construction according to claim 8, characterized in that, The guide wheel (401) is a rigid rubber rolling pulley.
10. The steel pipe pile leader for multi-pile construction according to claim 8, characterized in that, The number of the guide frame (4) is 5-8.