Basement beam-slab-column structure
By using prefabrication and assembly technology for modular wall structures, the problem of low construction efficiency of basement beams and columns has been solved, achieving rapid construction and stable beam-slab-column structures.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-28
- Publication Date
- 2026-03-13
AI Technical Summary
The existing basement beam and column construction is inefficient, on-site brickwork is slow, and the splicing of structural beams, slabs, columns and walls is troublesome, which affects construction efficiency.
The system employs a modular wall structure, including modular support columns and connecting plates. It achieves rapid assembly and fixation by prefabricating concrete piles in the factory and assembling them on site, combined with grouting trenches and splicing positioning structures.
It improved construction efficiency, reduced on-site construction time, enhanced the overall strength and stability of beam-slab-column structures, and simplified the construction process.
Smart Images

Figure CN223991380U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building construction technology and relates to a basement beam-slab-column structure. Background Technology
[0002] Beams and slabs are the basic transverse load-bearing components of a frame structure. The slabs bear the weight and transfer it to the beams, which then transfer it to the columns at both ends. The columns are important vertical load-bearing components of the frame structure, bearing the weight transmitted from the beams and then transferring it to the foundation. Their essential function is to bear various weights. Currently, the beams and columns of the basement need to be constructed on-site with bricks, which is slow and inefficient. In addition, the current construction of beams, slabs, columns and walls may be quite troublesome and may affect the construction efficiency.
[0003] For example, a Chinese patent discloses a cantilevered, non-removable formwork beam-slab for a basement [application number: 201920734666.8]. A slab end connector is installed at the junction of the slab bottom formwork and the first basement level; the slab formwork tie bars are securely connected to the hanging rod connecting plate; an outer beam formwork is installed at the bottom beam level, and the outer beam formwork is securely connected to the backfill layer at the bottom of the beam through beam formwork support bars and support bar bottom plates; formwork reinforcement bars are installed at the junction of the outer beam formwork and the slab bottom formwork; a steel reinforcement support body connected to the slab's internal bolts is installed on the bottom slab formwork; rod end grooves and hanging beam grooves are respectively arranged on the outer wall of the first basement level, and a sliding connector is installed in the rod end groove; the two ends of the sliding hanging beam are respectively inserted into the corresponding hanging beam grooves; after the sliding hanging beam slides to the set position, the sliding hanging beam is used as a construction platform for the concrete pouring of the first basement bottom slab and bottom slab beam. Utility Model Content
[0004] The purpose of this utility model is to address the above-mentioned problems by providing a basement beam-slab-column structure.
[0005] To achieve the above objectives, the present invention adopts the following technical solution:
[0006] A basement beam-slab-column structure includes a basement main body composed of several composite walls. The composite walls include composite support columns and several connecting plates connected to the composite support columns. The composite support columns are formed by splicing together a No. 1 precast concrete pile, several No. 2 precast concrete piles, and a No. 3 precast concrete pile. Each of the No. 1, No. 2, and No. 3 precast concrete piles is provided with a connecting plate installation groove, and the connecting end of the connecting plate is inserted into the connecting plate installation groove.
[0007] In the aforementioned basement beam-slab-column structure, the combined support column is pre-installed with a pouring groove for concrete pouring.
[0008] In the aforementioned basement beam-slab-column structure, the combined support column is also equipped with a splicing and positioning structure.
[0009] In the aforementioned basement beam-slab-column structure, the splicing and positioning structure includes a positioning groove recessed at the bottom of the No. 1 and No. 2 precast concrete piles, and a positioning block protruding at the top of the No. 2 and No. 3 precast concrete piles.
[0010] In the aforementioned basement beam-slab-column structure, the positioning groove and positioning block have rectangular annular cross-sections.
[0011] In the aforementioned basement beam-slab-column structure, both the positioning groove and the positioning block are connected to the pouring groove.
[0012] In the aforementioned basement beam-slab-column structure, the opening of the grouting groove is located at the top of the No. 1 precast concrete pile.
[0013] In the aforementioned basement beam-slab-column structure, the end of the connecting plate abuts against the side of the combined support column, and the inner end of the connecting plate is connected to the grouting groove.
[0014] In the aforementioned basement beam-slab-column structure, the composite support column is also equipped with a steel reinforcement cage.
[0015] In the aforementioned basement beam-slab-column structure, the steel reinforcement cage is formed by welding together several horizontally arranged transverse and longitudinal steel bars and several vertical steel bars.
[0016] Compared with existing technologies, the advantages of this utility model are:
[0017] 1. The modular support columns that make up the main body of the basement can be prefabricated in the factory and assembled on site, which can greatly speed up the construction efficiency. The connecting plates and modular support columns can also be assembled on site, which can improve the construction efficiency. The No. 1, No. 2 and No. 3 precast concrete piles can be prefabricated in the factory and assembled on site, which can speed up the construction efficiency. The overall height of the modular support columns can be adjusted by increasing or decreasing the number of No. 2 precast concrete piles.
[0018] 2. Setting up a grouting groove inside the modular support column allows for on-site pouring after the modular support column is assembled on the construction site. This not only reduces the weight of the No. 1, No. 2, and No. 3 precast concrete piles, making transportation easier, but also allows for the overall fixing of the assembled modular support column on the construction site without the need for other fixing accessories.
[0019] Other advantages, objectives and features of this invention will be partly apparent from the following description, and partly understood by those skilled in the art through study and practice of this invention. Attached Figure Description
[0020] Figure 1 This is a floor plan of the main basement structure;
[0021] Figure 2 This is a structural diagram of a composite wall structure;
[0022] Figure 3 This is a sectional view of a composite wall structure.
[0023] In the diagram, 1 is the combined wall, 2 is the basement main body, 3 is the combined support column, 4 is the connecting plate, 5 is the No. 1 precast concrete pile, 6 is the No. 2 precast concrete pile, 7 is the No. 3 precast concrete pile, 8 is the connecting plate installation groove, 9 is the connecting end, 10 is the pouring groove, 11 is the splicing positioning structure, 12 is the positioning groove, 13 is the positioning block, 14 is the steel reinforcement cage, 15 is the longitudinal steel reinforcement, and 16 is the vertical steel reinforcement. Detailed Implementation
[0024] like Figures 1-3 As shown, a basement beam-slab-column structure includes a basement main body 2 composed of several composite walls 1. The composite walls 1 include composite support columns 3 and several connecting plates 4 connected to the composite support columns 3. The composite support columns 3 are formed by splicing a No. 1 precast concrete pile 5, several No. 2 precast concrete piles 6 and a No. 3 precast concrete pile 7. Each of the No. 1 precast concrete pile 5, No. 2 precast concrete pile 6 and No. 3 precast concrete pile 7 is provided with a connecting plate mounting groove 8. The connecting end 9 of the connecting plate 4 is inserted into the connecting plate mounting groove 8.
[0025] In this utility model, the combined support columns that make up the combined wall of the basement main body 2 can be prefabricated in the factory and assembled after being transported to the site, which can greatly speed up the construction efficiency. The connecting plate and the combined support columns can also be assembled on site, which can improve the construction efficiency.
[0026] Specifically, the No. 1 precast concrete pile 5, the No. 2 precast concrete pile 6, and the No. 3 precast concrete pile 7 can be pre-produced in the factory and assembled after being transported to the construction site, which can speed up the construction efficiency and adjust the overall height of the combined support column by increasing or decreasing the number of No. 2 precast concrete piles.
[0027] Specifically, the modular support column 3 has a pre-installed pouring trough 10 for concrete pouring. Setting up the pouring trough inside the modular support column allows for on-site pouring after the modular support column is assembled on-site. This not only reduces the weight of the No. 1 precast concrete pile 5, No. 2 precast concrete pile 6, and No. 3 precast concrete pile 7, facilitating transportation, but also allows for the overall fixing of the assembled modular support column on-site without the need for other fixing accessories.
[0028] Specifically, the modular support column 3 is also equipped with a splicing and positioning structure 11. The splicing and positioning structure 11 can be used for positioning during the assembly of the modular support column.
[0029] Specifically, the splicing positioning structure 11 includes a positioning groove 12 recessed into the bottom of the first precast concrete pile 5 and the second precast concrete pile 6, and a positioning block 13 protruding from the top of the second precast concrete pile 6 and the third precast concrete pile 7. The positioning groove 12 and the positioning block can be used to fix adjacent first precast concrete pile 5 and second precast concrete pile 6, second precast concrete pile 6 and second precast concrete pile 6, and second precast concrete pile 6 and third precast concrete pile 7.
[0030] Specifically, the positioning groove 12 and the positioning block 13 have rectangular annular cross sections, and both the positioning groove 12 and the positioning block 13 are connected to the pouring groove 10.
[0031] Specifically, the opening of the grouting groove 10 is located at the top of the No. 1 precast concrete pile 5.
[0032] Specifically, the end of the connecting plate 4 abuts against the side of the combined support column 3, and the inner end of the connecting end 9 of the connecting plate 4 is connected to the grouting groove 10.
[0033] Preferably, the composite support column 3 is further provided with a steel reinforcement cage 14, which is formed by welding together several horizontally arranged transverse and longitudinal steel bars 15 and several vertical steel bars 16. The steel reinforcement cage can increase the overall strength of the composite support column.
[0034] The specific embodiments described herein are merely illustrative examples illustrating the spirit of this utility model. Those skilled in the art to which this utility model pertains may make various modifications or additions to the described specific embodiments or use similar methods to substitute them, without departing from the spirit of this utility model or exceeding the scope defined by the appended claims.
[0035] Although this article frequently uses terms such as 1. composite wall, 2. basement main body, 3. composite support column, 4. connecting plate, 5. No. 1 precast concrete pile, 6. No. 2 precast concrete pile, 7. No. 3 precast concrete pile, 8. connecting plate installation groove, 9. connecting end, 10. grouting groove, 11. splicing positioning structure, 12. positioning groove, 13. positioning block, 14. steel reinforcement cage, 15. longitudinal steel reinforcement, 16. vertical steel reinforcement, etc., these terms are used merely to more conveniently describe and explain the essence of this utility model; interpreting them as any kind of additional limitation would be contrary to the spirit of this utility model.
Claims
1. A basement slab-column structure comprising a basement body (2) consisting of several combined walls (1), characterized in that, The combined wall (1) comprises a combined support column (3) and a plurality of connecting plates (4) connected with the combined support column (3), the combined support column (3) is formed by splicing a first prefabricated concrete pile (5), a plurality of second prefabricated concrete piles (6) and a third prefabricated concrete pile (7), the first prefabricated concrete pile (5), the second prefabricated concrete pile (6) and the third prefabricated concrete pile (7) are all provided with a connecting plate mounting groove (8), and the connecting end (9) of the connecting plate (4) is inserted into the connecting plate mounting groove (8).
2. The basement beam-slab-column structure according to claim 1, wherein The combined support column (3) is provided with a pouring groove (10) for pouring concrete.
3. The basement beam-slab-column structure according to claim 2, wherein The combined support column (3) is further provided with a splicing positioning structure (11).
4. The basement beam-slab-column structure according to claim 3, wherein The splicing positioning structure (11) comprises a positioning groove (12) recessed inwardly arranged at the bottom of the first prefabricated concrete pile (5) and the second prefabricated concrete pile (6) and a positioning block (13) protruding arranged at the top of the second prefabricated concrete pile (6) and the third prefabricated concrete pile (7).
5. The basement beam-slab-column structure according to claim 4, wherein The cross section of the positioning groove (12) and the positioning block (13) is a rectangular ring.
6. A basement beam-slab-column structure according to claim 5, wherein The positioning groove (12) and the positioning block (13) are connected with the pouring groove (10).
7. The basement beam-slab-column structure according to claim 2, wherein The opening of the pouring groove (10) is located at the top of the first prefabricated concrete pile (5).
8. The basement beam-slab-column structure according to claim 2, wherein The end of the connecting plate (4) abuts against the side of the combined support column (3), and the inner end of the connecting end (9) of the connecting plate (4) is connected with the pouring groove (10).
9. The basement beam-slab-column structure according to claim 1, wherein The combined support column (3) is further provided with a steel reinforcement framework (14).
10. The basement beam-slab-column structure according to claim 9, wherein The steel reinforcement framework (14) is formed by welding a plurality of horizontally arranged transverse steel bars and longitudinal steel bars (15) and a plurality of vertical steel bars (16).
Citation Information
Patent Citations
Basement cantilever non-dismantling formwork beam plate
CN210508372U