Straddle body equipment for sprinkling machine

By using modular, interconnected equipment, the problem of adapting sprinkler machines to different plots of land has been solved, enabling rapid assembly and efficient sprinkler operation, thus improving the equipment's efficiency and sprinkler effect.

CN224038102UActive Publication Date: 2026-03-27HENAN DANONG WATER SAVING TECH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-04-23
Publication Date
2026-03-27

AI Technical Summary

Technical Problem

Existing sprinkler irrigation equipment is difficult to adapt quickly to plots of different shapes and sizes, resulting in poor irrigation effects and low equipment assembly efficiency, which increases agricultural production costs.

Method used

The modular, cross-type equipment, connected by a first and second splicing truss and incorporating transfer pipes, positioning rods, and cables, enables rapid assembly and disassembly, adapting to the sprinkler irrigation needs of different plots of land.

Benefits of technology

It improved the equipment's assembly efficiency and utilization rate, ensured uniform irrigation of different plots of land, saved equipment disassembly and assembly time, and improved operational efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224038102U_ABST
    Figure CN224038102U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of agricultural machinery equipment, in particular to body-spanning equipment for a sprinkling machine, which comprises a first splicing truss and a second splicing truss, a connecting support is mounted at the joint of the first splicing truss and the second splicing truss, a switching pipeline is arranged on the upper portion of the connecting support, and a positioning rod is arranged on the switching pipeline. A first inhaul cable and a second inhaul cable which are connected with the first splicing truss and the second splicing truss correspondingly are arranged on the positioning rod, the first splicing truss, the second splicing truss and the connecting support can be quickly spliced into span-body equipment, the span-body equipment is connected with a center tower or parallel walking type sprinkling irrigation equipment to be used for sprinkling irrigation operation of land parcels, the structure is compact, and the splicing efficiency is high; the dismounting time of equipment is saved, and the operation efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to agricultural machinery equipment technical field, concretely relates to a kind of cross body equipment for sprinkler. BACKGROUND

[0002] In the field of agricultural irrigation, sprinkler is widely used in various farmland as efficient water-saving irrigation equipment. With the expansion of agricultural planting scale and the diversification of land shape, the existing sprinkler equipment has many limitations when dealing with different shapes and areas of land. Traditional sprinkler is designed with fixed structure, which is difficult to adapt to the irrigation needs of irregularly shaped land or large-area contiguous land. For special-shaped land such as long and narrow shape and polygon, it is difficult to carry out comprehensive and uniform sprinkling operation, which may cause irrigation dead angle and result in poor irrigation effect.

[0003] For example, Chinese patent (application number 201911384037.8) discloses a large-scale sprinkler plant protection system, which relates to the field of large-scale sprinkler. The sprinkler includes a tower and a cross body. The transportation system is provided on the cross body. The transportation system includes a driving component, a transportation track and a moving platform. The transportation track is erected on the cross body. The driving component is connected with the moving platform and drives the moving platform to move. The problem of the prior art sprinkler that can only realize irrigation operation is solved, and another set of equipment needs to be installed when spraying pesticide or fertilizing crops.

[0004] However, the connection method used in the assembly of the device is complex and not convenient for quick assembly. When different types of land need to be sprayed, a lot of time and manpower are often needed to disassemble and reassemble the equipment, which not only reduces the assembly efficiency of the equipment, but also makes the utilization rate of the sprinkler low between different lands, increasing the cost of agricultural production. Therefore, it is urgent to develop a sprinkler cross body device that can be connected by splicing to realize quick irrigation operation on different shapes and areas of land, improve the assembly efficiency and utilization rate of the device. UTILITY MODEL CONTENT

[0005] To solve the above problems, the utility model embodiment provides a cross body device for sprinkler, which can be connected by combination splicing to reasonably assemble when spraying different shapes and areas of land, realize quick irrigation operation on different types of land, and improve the assembly efficiency and utilization rate of the device.

[0006] The utility model discloses an embodiment for realizing the above -mentioned purpose, specifically adopts following technical scheme: a kind of cross body equipment for sprinkler, including first spliced truss and second spliced truss, the connecting place of first spliced truss and second spliced truss is provided with connecting support, the upper portion of the connecting support is provided with adapter pipeline, positioning rod is provided on the adapter pipeline, the positioning rod is provided with cable one and cable two respectively connected with first spliced truss and second spliced truss.

[0007] As further improvement of the above technical solution:

[0008] The first spliced truss includes water supply pipeline, one end of the water supply pipeline is connected with adapter pipeline, and the other end is provided with walking support module, and the water supply pipeline is provided with sprinkler head one.

[0009] The walking support module includes walking tower car, the upper portion of the walking tower car is provided with connecting short pipe, adapter hose is arranged between the connecting short pipe and the water supply pipeline, and the upper portion of the connecting short pipe and the water supply pipeline is provided with rotary joint.

[0010] The second spliced truss includes cantilever pipe, one end of the cantilever pipe is connected with adapter pipeline, and the other end is provided with terminal sprinkler gun, and the cantilever pipe is provided with sprinkler head two.

[0011] The adapter pipeline is provided with conveying pipeline connected with the terminal sprinkler gun, and the conveying pipeline is provided with booster pump at the connecting place with the adapter pipeline.

[0012] The adapter pipeline is obliquely arranged, and the lowest end is provided with sand discharge pipe connected with the second spliced truss.

[0013] The number of the first spliced truss is multiple, and the length is 30-80 meters.

[0014] The number of the second spliced truss is multiple, and the length is 0.5-12 meters.

[0015] The cross body equipment for sprinkler, including first spliced truss and second spliced truss, connecting support is installed at the connecting place of first spliced truss and second spliced truss, adapter pipeline is arranged on the upper portion of the connecting support, positioning rod is arranged on the adapter pipeline, cable one and cable two are arranged on the positioning rod and connected with first spliced truss and second spliced truss respectively, first spliced truss, second spliced truss and connecting support can be quickly spliced into cross body equipment, and the cross body equipment is connected with central tower or parallel walking type sprinkler equipment for land sprinkling operation, the structure is compact and the assembly efficiency is high, the disassembly and assembly time of equipment is saved, and the operation efficiency is improved.

[0016] The first splicing truss and the second splicing truss are combined to form the sprinkling cross equipment with different sizes, the sprinkling operation of the land with different areas can be performed, and the sprinkling cross equipment can be disassembled and stored after the use function is completed, and the corresponding size can be taken out for splicing again when used next time. BRIEF DESCRIPTION OF DRAWINGS

[0017] Figure 1 It is a whole structure schematic view of the utility model;

[0018] Figure 2 It is a structure schematic view of the first splicing truss in the utility model;

[0019] Figure 3 It is a structure schematic view of the connecting short pipe in the utility model;

[0020] Figure 4 It is a structure schematic view of the second splicing truss in the utility model;

[0021] Figure 5 It is Figure 1 A method structure schematic view in the utility model.

[0022] In the drawing: 1, first splicing truss; 2, second splicing truss; 3, connecting support; 4, switching pipeline; 5, positioning rod; 6, cable one; 7, cable two; 8, water delivery pipeline; 9, sprinkling head one; 10, walking tower car; 11, connecting short pipe; 12, switching hose; 13, cantilever pipe; 14, end sprinkling gun; 15, sprinkling head two; 16, conveying pipeline; 17, booster pump; 18, sand discharge pipe. DETAILED DESCRIPTION

[0023] The preferred embodiments of the utility model are described below with reference to the drawings. Those skilled in the art should understand that these embodiments are only used to explain the technical principles of the utility model, and are not intended to limit the protection scope of the utility model.

[0024] As Figure 1 shown, the cross equipment for the sprinkling machine of the embodiment includes a first splicing truss 1 and a second splicing truss 2, a connecting support 3 is installed at the connection of the first splicing truss 1 and the second splicing truss 2, a switching pipeline 4 is arranged on the upper part of the connecting support 3, a positioning rod 5 is arranged on the switching pipeline 4, a cable one 6 and a cable two 7 connected with the first splicing truss 1 and the second splicing truss 2 respectively are arranged on the positioning rod 5, the first splicing truss 1, the second splicing truss 2 and the connecting support 3 can be quickly spliced into the cross equipment, and the cross equipment is connected with the center tower or the parallel walking type sprinkling equipment for the sprinkling operation of the land, the structure is compact and the splicing efficiency is high, the disassembly and assembly time of the equipment is saved, and the operation efficiency is improved.

[0025] As Figures 2-3As shown, the number of first splicing trusses 1 is multiple, and the length is 30-80 meters, and the number of second splicing trusses 2 is multiple, and the length is 0.5-12 meters, in this embodiment, the first splicing trusses 1 are selected to have five different lengths of 37 meters, 43 meters, 48 meters, 54 meters and 65 meters, and the second splicing trusses 2 are selected to have five different lengths of 0.5 meters, 5 meters, 8 meters, 11 meters, 17 meters and 25 meters, in actual use, parallel walking type or center support type sprinkler equipment can be selected according to the shape of the land to be connected with the crossing body equipment to complete the sprinkling irrigation function, the crossing body equipment can be composed of first splicing trusses 1 and second splicing trusses 2 with any length during splicing, for example, when the land is rectangular, the width of the land is 44 meters, at this time, the length of the first splicing truss 1 is 43 meters, and the length of the second splicing truss 2 is 0.5 meters, and a crossing body equipment matching the size of the land is formed by splicing.

[0026] As shown in Figures 4-5 The first splicing truss 1 includes a water supply pipeline 8, one end of the water supply pipeline 8 is connected with the adapter pipeline 4, and the other end is provided with a walking support module, the walking support module includes a walking tower car 10, an upper portion of the walking tower car 10 is provided with a connecting short pipe 11, a connecting short pipe 11 and the water supply pipeline 8 are provided with an adapter hose 12, and the upper portions of the connecting short pipe 11 and the water supply pipeline 8 are provided with a rotary connecting piece, the rotary connecting piece includes a connecting ball head located above the connecting short pipe 11 and a connecting ball cavity located above the end of the water supply pipeline, the height and angle compensation can be performed during the walking of the walking tower car 10 through the rotary connecting piece and the adapter hose 12, and the stability of the end of the crossing body equipment during walking is improved, and the water supply pipeline 8 is provided with a sprinkling head I 9, the number of the sprinkling head I 9 is multiple and is uniformly distributed along the length direction of the water supply pipeline 8.

[0027] The second splicing truss 2 includes a cantilever pipe 13, one end of the cantilever pipe 13 is connected with the adapter pipeline 4, and the other end is provided with an end sprinkling gun 14, the cantilever pipe 13 is provided with a sprinkling head II 15, and the number of the sprinkling head II 15 is multiple and is uniformly distributed along the length direction of the cantilever pipe 13.

[0028] The adapter pipeline 4 is provided with a conveying pipeline 16 connected with the end sprinkling gun 14, and the connecting position of the conveying pipeline 16 and the adapter pipeline 4 is provided with a booster pump 17, the design of the booster pump 17 can supply pressure to the end sprinkling gun 14 alone, thereby realizing the separate control of the sprinkling distance, the sprinkling distance can be controlled according to the edge distance of the land, and the sprinkling of the edge area of the land is realized.

[0029] The adapter pipeline 4 is inclined, and the lowest end is provided with a sand discharge pipe 18 connected with the second splicing truss 2, the sand discharge pipe 18 is used to collect the granular impurities in the sprinkling liquid in the pipeline, and then is periodically discharged, and is located at the lowest end of the entire pipeline, thereby facilitating the collection of the impurities.

[0030] It should be noted that in the description of the present application, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer" and other terms indicating direction or positional relationship are based on the direction or positional relationship shown in the drawings, which is only for the convenience of description, and does not indicate or imply that the device or element must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first", "second", "third" are only for the purpose of description, and cannot be understood as indicating or implying relative importance.

[0031] In addition, it should also be noted that in the description of the present application, unless otherwise specified and limited, the terms "mounting", "connecting", "connection" should be understood broadly, for example, it can be fixed connection, or detachable connection, or integrally connected; it can be mechanical connection, or electrical connection; it can be directly connected, or indirectly connected through intermediate medium, or the communication between two elements inside. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.

[0032] The term "includes" or any other similar term is intended to cover non-exclusive inclusion, so that the process, article or equipment / device including a series of elements not only includes those elements, but also includes other elements not explicitly listed, or also includes the elements inherent in the process, article or equipment / device.

[0033] So far, the technical scheme of the present application has been described in combination with the preferred embodiments shown in the drawings, but those skilled in the art can easily understand that the protection scope of the present application is obviously not limited to these specific embodiments. Without deviating from the principles of the present application, those skilled in the art can make equivalent changes or replacements to related technical features, and the technical schemes after these changes or replacements will fall within the protection scope of the present application.

Claims

1. A cross-body apparatus for a sprinkler, comprising: The utility model provides a kind of water conservancy irrigation system, including first splicing truss (1) and second splicing truss (2), the connecting place of first splicing truss (1) and second splicing truss (2) is provided with connecting support (3), the upper portion of connecting support (3) is provided with adapter pipe (4), adapter pipe (4) is provided with positioning rod (5), positioning rod (5) is provided with cable one (6) and cable two (7) respectively connected with first splicing truss (1) and second splicing truss (2).

2. The cross-body apparatus for a sprinkler as recited in claim 1, wherein: First splicing truss (1) includes water supply pipe (8), one end of water supply pipe (8) is connected with adapter pipe (4), and the other end is provided with walking support module, and water supply pipe (8) is provided with sprinkler head one (9).

3. The cross-car apparatus for a sprinkler as set forth in claim 2, wherein: Walking support module includes walking tower car (10), the upper portion of walking tower car (10) is provided with connecting short pipe (11), connecting short pipe (11) and water supply pipe (8) are provided with adapter hose (12), and the upper portion of connecting short pipe (11) and water supply pipe (8) is provided with rotary connector.

4. The cross-car apparatus for a sprinkler as set forth in claim 1, wherein: Second splicing truss (2) includes cantilever pipe (13), one end of cantilever pipe (13) is connected with adapter pipe (4), and the other end is provided with terminal sprinkling gun (14), and cantilever pipe (13) is provided with sprinkler head two (15).

5. The cross-car apparatus for a sprinkler as set forth in claim 4, wherein: Adapter pipe (4) is provided with conveying pipe (16) connected with terminal sprinkling gun (14), and conveying pipe (16) is provided with booster pump (17) at the connecting place with adapter pipe (4).

6. The cross-car apparatus for a sprinkler as set forth in claim 5, wherein: Adapter pipe (4) is obliquely arranged, and the lowest end is provided with sand discharge pipe (18) connected with second splicing truss (2).

7. A span for a sprinkling machine according to any one of claims 1-6, characterized in that: The number of first splicing truss (1) is multiple, and the length is 30-80 meters.

8. The cross-car apparatus for a sprinkler as defined in claim 7, wherein: The number of second splicing truss (2) is multiple, and the length is 0.5-12 meters.

Citation Information

Patent Citations

  • Large-scale sprinkling machine plant protection system

    CN111066759A