Safety protection device for steel wire rope of shear wall of tunnel formwork structure
By pre-embedding fixed sleeves and connecting steel wire ropes in the shear wall openings of the tunnel formwork, a safety protection facility is formed, which solves the problem of lack of safety protection in tunnel formwork construction, realizes efficient and safe edge and high-altitude operations, reduces costs and improves construction efficiency.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-20
- Publication Date
- 2026-03-27
AI Technical Summary
During the construction of tunnel formwork, there is a lack of effective safety protection measures, especially during the masonry and plastering of the edges and high-altitude operations. Traditional external scaffolding increases costs and poses safety risks.
A safety protection device for steel wire ropes in shear walls of tunnel formwork structures is designed. By pre-embedding fixed sleeves in the openings of the shear wall and using connectors and locking components to connect the steel wire ropes to the shear wall, a reliable safety protection facility is formed.
It provides safety protection under the tunnel formwork construction system, avoids the erection of external scaffolding, reduces costs and improves construction efficiency, and ensures the safety of construction personnel when working near edges and at heights.
Smart Images

Figure CN224049203U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to construction safety technical field, concretely is tunnel mould structure shear wall steel wire rope safety device. BACKGROUND
[0002] Tunnel mould template construction system is a kind of efficient, economic building construction technology.Compared with traditional frame shear structure, tunnel mould template construction system has the advantages of low cost, short construction period, good fireproofing and soundproofing effect, superior seismic, moisture-proof and anti-leakage performance.
[0003] However, when the main structure is completed and enters the masonry and whitewashing edge and high-altitude operation stage, due to the particularity of the tunnel mould template construction operation system, there is no protective outer scaffolding around the main structure as in the traditional template assembly construction system. In the subsequent construction process, there is also a lack of effective means to utilize the outer scaffolding steel pipes as safety belt hanging points to ensure the safety of subsequent edge and high-altitude construction operations. If the outer scaffolding is set up according to the traditional construction mode, it will increase the personnel and material costs of the project, and there is also a certain safety risk in the later edge cleaning. CONTENT OF THE UTILITY MODEL
[0004] The utility model aims at providing tunnel mould structure shear wall steel wire rope safety device, which can provide safety protection for masonry and whitewashing edge and high-altitude operation under the tunnel mould template construction system.
[0005] The above-mentioned optimized structure of the utility model is realized by the following technical scheme: the tunnel mould structure shear wall steel wire rope safety device comprises a plurality of fixing sleeves, the fixing sleeves are embedded in the eye of the shear wall;
[0006] A connecting piece is detachably connected with the fixing sleeve;
[0007] A steel wire rope is fixedly connected with two connecting pieces of the same height at both ends;
[0008] A locking assembly is arranged at both ends of the steel wire rope.
[0009] In some embodiments, the connecting piece comprises a connecting rod, and the connecting rod is detachably connected with the fixing sleeve;
[0010] A plurality of locking rings are annularly arranged at one end of the connecting rod away from the fixing sleeve, and the steel wire rope passes through the plurality of locking rings in sequence.
[0011] In some embodiments, the fixing sleeve is screw-connected with the connecting rod.
[0012] In some embodiments, the rotation direction of the connecting rod is clockwise.
[0013] In some embodiments, the steel wire rope comprises a suspension zone;
[0014] A bending zone is arranged at both ends of the suspension zone, the bending zone is parallel to the suspension zone, and the locking assembly is arranged between the bending zone and the suspension zone.
[0015] In some embodiments, the locking assembly comprises at least one locking piece, and the locking piece comprises a U-shaped ring.
[0016] A locking plate is arranged at both ends of the U-shaped ring, and the U-shaped ring and the locking plate are arranged with the suspension zone and the bending zone therebetween.
[0017] A locking nut is screw-coupled with both ends of the U-shaped ring.
[0018] In some embodiments, the locking piece further comprises a clamping tooth arranged at the bottom of the locking plate and abutting the suspension zone or the bending zone.
[0019] In some embodiments, the locking piece is three, and the three locking pieces are arranged at equal intervals on the steel wire rope.
[0020] In summary, the utility model has the following beneficial effects:
[0021] The utility model discloses a steel wire rope and shear wall are connected through the fixed sleeve and connecting piece in the shear wall hole, and reliable safety protection facilities can be formed on the shear wall, the safety belt can be hung on the steel wire rope when the construction personnel is working at the edge and high altitude, the steel wire rope can bear the tension generated when the construction personnel is working at the edge and high altitude, the worker can be effectively prevented from falling when working at high altitude, thereby providing safety protection for the masonry and painting edge and high altitude operation under the tunnel formwork construction system, and the external scaffold does not need to be built, the project cost is reduced, and the construction efficiency is improved. BRIEF DESCRIPTION OF DRAWINGS
[0022] Figure 1 It is a structural schematic diagram of the utility model;
[0023] Figure 2 It is a structural schematic diagram of the utility model Figure 1 It is an enlarged view of A in the utility model;
[0024] Figure 3 It is a structural schematic diagram of the locking assembly of the utility model.
[0025] In the figure: 1, fixed sleeve, 2, connecting piece, 21, connecting rod, 22, locking ring, 3, steel wire rope, 31, suspension area, 32, bending area, 4, locking assembly, 41, U-shaped ring, 42, locking plate, 43, locking nut, 44, clamping tooth. DETAILED DESCRIPTION
[0026] The technical solutions in the novel embodiments of the system will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all the other embodiments obtained by the ordinary skilled in the art without creative labor belong to the scope of protection of the utility model.
[0027] Reference Figures 1-3 The tunnel formwork shear wall steel wire rope safety protection device comprises a plurality of fixed sleeves 1, connecting pieces 2, steel wire ropes 3 and locking assemblies 4. The fixed sleeves 1 are embedded in the eye of the shear wall, can ensure that the fixed sleeves 1 are closely combined with the shear wall concrete structure, thereby providing a fixed basis for the protection device, and can be made of high-strength steel to meet the stress requirements. The eye of the shear wall is a hole left in the shear wall construction process, can avoid the influence of additional punching on the strength of the established wall, can reduce the construction steps and improve the construction efficiency at the same time, the connecting pieces 2 are detachably connected with the fixed sleeves 1, facilitating the installation and dismounting of the connecting pieces 2, the two ends of the steel wire rope 3 are fixedly connected with two connecting pieces 2 of the same height respectively to realize the suspension of the steel wire rope 3 between the shear walls, so that the workers can be connected with the steel wire rope 3 through the safety rope, thereby realizing the provision of safety protection for the masonry and painting of the edge and high-altitude operation under the tunnel formwork construction system, the steel wire rope 3 can be made of high-strength galvanized steel wire, so that it has good tensile strength and corrosion resistance, and the locking assembly 4 is arranged at the two ends of the steel wire rope 3 to lock the steel wire rope 3 and ensure the stability of the steel wire rope 3.
[0028] In some embodiments, the connecting piece 2 comprises a connecting rod 21 and a plurality of locking rings 22. The connecting rod 21 is detachably connected with the fixed sleeve 1, facilitating the installation and dismounting of the connecting rod 21. The plurality of locking rings 22 are annularly arranged at the end of the connecting rod 21 away from the fixed sleeve 1, and the steel wire rope 3 passes through the plurality of locking rings 22 in sequence, which can reduce the gap between the steel wire rope 3 and the connecting piece 2, improve the stability of the connection between the steel wire rope 3 and the connecting piece 2, prevent the steel wire rope 3 from loosening or falling off during use, and the number of the locking rings 22 is at least three, but is not limited thereto, and the number of the locking rings 22 can be adjusted according to actual needs. The connecting rod 21 and the locking ring 22 can both be made of high-strength steel, and the surface is subjected to corrosion prevention treatment, so as to improve the service life and durability.
[0029] In some embodiments, the fixed sleeve 1 is screw-connected with the connecting rod 21, and the connecting rod 21 can be connected with and detached from the fixed sleeve 1 by rotating the connecting rod, which is simple and convenient to operate.
[0030] In some embodiments, the screwing direction of the connecting rod 21 is clockwise, and when the connecting rod 21 is subjected to a downward force, the connecting rod 21 has a tendency to screw into the fixed sleeve 1, thereby improving the connecting strength of the connecting rod 21 and the fixed sleeve 1 and improving the stability of the steel wire rope 3.
[0031] In some embodiments, the steel wire rope 3 includes a suspension zone 31 and a bending zone 32. The suspension zone 31 can be connected with a safety rope on a worker's body to bear the weight of the worker, thereby providing safety protection for masonry and painting edge and high-altitude operations. The bending zone 32 is arranged at both ends of the suspension zone 31, is parallel to the suspension zone 31, and is provided with a locking assembly 4 between the bending zone 32 and the suspension zone 31. The locking assembly 4 tightly fits the bending zone 32 and the suspension zone 31 of the steel wire rope 3, thereby realizing the fixed connection of the steel wire rope 3 and the connecting piece 2.
[0032] In some embodiments, the locking assembly 4 includes at least one locking piece, which can be three. The three locking pieces are arranged at equal intervals on the steel wire rope 3, so that the stress of the steel wire rope 3 is more dispersed, further improving the safety and stability of the device.
[0033] The locking piece includes a U-shaped ring 41, a locking plate 42, and a locking nut 43. The U-shaped ring 41 is arranged at both ends of the locking plate 42, and the suspension zone 31 and the bending zone 32 are arranged between the U-shaped ring 41 and the locking plate 42. The locking nut 43 is screw-connected with both ends of the U-shaped ring 41. By tightening the locking nut 43, the suspension zone 31 and the bending zone 32 can be clamped tightly between the locking plate 42 and the locking nut 43, thereby realizing the firm locking of the steel wire rope 3. The gap width of the U-shaped ring 41 is greater than the diameter of the steel wire rope 3 and less than 1.5 times the diameter of the steel wire rope 3. When the steel wire rope 3 passes through the U-shaped ring 41, the gap between the steel wire rope 3 and the U-shaped ring 41 is reduced, thereby improving the locking effect of the locking piece on the steel wire rope 3.
[0034] In some embodiments, the locking piece further includes a clamping tooth 44 arranged at the bottom of the locking plate 42 and tightly fitted with the suspension zone 31 or the bending zone 32. The clamping tooth 44 can increase the friction between the locking piece and the steel wire rope 3, prevent the steel wire rope 3 from sliding in the locking piece, and ensure the fixing effect of the steel wire rope 3.
[0035] The specific working principle is as follows:
[0036] In use, the connecting rod 21 is screwed with the fixing sleeve 1, the screwing direction is clockwise, and the connection is ensured to be tight. The steel wire rope 3 is sequentially threaded through the plurality of locking rings 22 on the connecting piece 2, and then the two ends of the steel wire rope 3 are respectively fixedly connected with two connecting pieces 2 of the same height. The locking assembly 4 is installed at the two ends of the steel wire rope 3, the suspension area 31 and the bending area 32 are tightly clamped between the locking plate 42 and the locking nut 43 by screwing the locking nut 43, and the firm fixing of the steel wire rope 3 is ensured. Finally, the installation quality of the whole device is checked, and the device can be put into use after it is ensured that the safety requirements are met.
[0037] During construction, the construction personnel can hang the safety belt hook on the steel wire rope 3 to realize the safety protection of the edge high-altitude operation.
[0038] The above examples are only used to illustrate the technical solutions of the present application, but not to limit it. Although the present application has been described in detail with reference to the foregoing examples, those skilled in the art should understand that the technical solutions recorded in the foregoing examples can be modified, or some technical features can be replaced by equivalents. The modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A tunnel form construction shear wall wire rope safety guard characterized by: It comprises a plurality of fixed sleeves (1) embedded in the hole of the shear wall; A connecting piece (2) is detachably connected with the fixed sleeve (1); A steel wire rope (3) is fixedly connected with two connecting pieces (2) at both ends; A locking assembly (4) is arranged at both ends of the steel wire rope (3).
2. The tunnel form construction shear wall wire rope safety guard of claim 1, wherein: The connecting piece (2) comprises a connecting rod (21) detachably connected with the fixed sleeve (1); A plurality of locking rings (22) are arranged at one end of the connecting rod (21) away from the fixed sleeve (1), and the steel wire rope (3) passes through the plurality of locking rings (22) in sequence.
3. The tunnel form construction shear wall wire rope safety guard of claim 2, wherein: The fixed sleeve (1) is screw-connected with the connecting rod (21).
4. The tunnel form construction shear wall wire rope safety guard of claim 3, wherein: The rotation direction of the connecting rod (21) is clockwise.
5. The tunnel form construction shear wall wire rope safety guard of claim 4, wherein: The steel wire rope (3) comprises a suspension area (31); A bending area (32) is arranged at both ends of the suspension area (31), the bending area (32) is parallel to the suspension area (31), and the locking assembly (4) is arranged between the bending area (32) and the suspension area (31).
6. The tunnel form construction shear wall wire rope safety guard of claim 5, wherein: The locking assembly (4) comprises at least one locking piece, the locking piece comprises a U-shaped ring (41); A locking plate (42) is provided with the U-shaped ring (41) at both ends, and the U-shaped ring (41) and the locking plate (42) are provided with the suspension area (31) and the bending area (32) therebetween; A locking nut (43) is screw-connected with both ends of the U-shaped ring (41).
7. The tunnel form construction shear wall wire rope safety guard of claim 6, wherein: The locking piece further comprises a clamping tooth (44), which is arranged at the bottom of the locking plate (42) and is in close contact with the suspension area (31) or the bending area (32).
8. The tunnel form construction shear wall wire rope safety guard of claim 6, wherein: The locking piece is three, and the three locking pieces are equally spaced on the steel wire rope (3).