Discharging hopper of hydrometallurgy pressure leaching reinforced concrete thickener

By designing the embedded steel plate and connecting structure of the hopper of the reinforced concrete thickener, the problem of the inability to replace the hopper when it is damaged in the traditional thickener has been solved, enabling rapid installation and maintenance and extending the service life of the equipment.

CN224270282UActive Publication Date: 2026-05-26JINCHUAN GROUP NICKEL COBALT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
JINCHUAN GROUP NICKEL COBALT CO LTD
Filing Date
2025-05-27
Publication Date
2026-05-26

Smart Images

  • Figure CN224270282U_ABST
    Figure CN224270282U_ABST
Patent Text Reader

Abstract

The utility model provides a hydrometallurgy pressure leaching reinforced concrete thickener blanking hopper which comprises a blanking hopper body, an embedded steel plate, an upper connecting plate and a lower connecting plate are sequentially arranged above the blanking hopper body, the lower connecting plate and the upper connecting plate are connected in a matched mode through a double-end stud and double nuts, and the lower connecting plate and the upper connecting plate are connected in a matched mode through the double-end stud and the double nuts. The blanking hopper main body is fixedly connected with the lower connecting plate; a second connecting pipe is arranged on the side portion of the discharging hopper body, a first connecting pipe is arranged at the bottom of the discharging hopper body, and the discharging hopper body is perpendicularly communicated with the second connecting pipe. The thickener is fast and convenient to install, convenient to maintain and replace and capable of prolonging the overall service life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the technical field of thickener equipment and relates to a feeding hopper for a hydrometallurgical pressure leaching reinforced concrete thickener. Background Technology

[0002] In nickel hydrometallurgy, solid-liquid separation of the reacted materials is often required. Thickeners, as important solid-liquid separation equipment, are used more frequently in nickel hydrometallurgy. Traditional concrete thickeners have a feed hopper that is cast as a single piece, fixed before the tank body is poured, and then cast as a whole with the concrete tank body. If the feed hopper is damaged during subsequent use, it cannot be replaced separately, and a new thickener must be built. This not only causes production system shutdown but also incurs high construction costs. Therefore, it is essential to develop a reinforced concrete thickener feed hopper that can be easily replaced separately. Utility Model Content

[0003] The purpose of this utility model is to address the problems existing in the prior art by providing a feeding hopper for a hydrometallurgical pressure leaching reinforced concrete thickener. This solves the problem that in traditional concrete thickeners, the feeding port is integrated with the concrete pool, making it impossible to replace the feeding hopper separately if it is damaged during subsequent use.

[0004] Therefore, the present invention adopts the following technical solution:

[0005] A hopper for a hydrometallurgical pressure leaching reinforced concrete thickener includes a hopper body. A pre-embedded steel plate, an upper connecting plate, and a lower connecting plate are sequentially arranged above the hopper body. The lower connecting plate and the upper connecting plate are connected by double-ended studs and double nuts. The hopper body and the lower connecting plate are fixedly connected. A second connecting pipe is provided on the side of the hopper body and a first connecting pipe is provided at the bottom. The hopper body and the second connecting pipe are vertically connected.

[0006] Furthermore, the upper connecting plate is provided with a plurality of plug welding holes arranged symmetrically, specifically, the plug welding holes are through holes; a first threaded hole is provided between adjacent plug welding holes, and the lower connecting plate is provided with a second threaded hole, the first threaded hole and the second threaded hole are connected by a double-ended stud.

[0007] Furthermore, a number of reinforcing ribs are provided at the connection between the hopper body and the lower connecting plate, with one end of the reinforcing ribs connected to the hopper body and the other end connected to the lower connecting plate.

[0008] Furthermore, the first connector is L-shaped.

[0009] Furthermore, the lower surface of the embedded steel plate is provided with a ring platform.

[0010] Furthermore, the upper connecting plate is provided with a tenon and the lower connecting plate is provided with a mortise, and the tenon and the mortise are connected by a sealing gasket; specifically, the sealing gasket is made of polytetrafluoroethylene.

[0011] The beneficial effects of this utility model are as follows:

[0012] In use, this utility model pre-embeds a steel plate at the bottom of the thickener, plugs and fillets welds the upper connecting plate to the pre-embedded steel plate, bolts the lower connecting plate to the upper connecting plate, and welds the lower connecting plate to the main body of the hopper. This makes the hopper quick and easy to install, and facilitates maintenance and replacement. It solves the problem of excessively long repair and replacement time when the hopper of the transmission thickener is damaged, and extends the overall service life of the thickener. Attached Figure Description

[0013] Figure 1 This is a schematic diagram of the structure of this utility model;

[0014] Figure 2 This is a schematic diagram of the connection structure between the upper connecting plate and the lower connecting plate in this utility model;

[0015] Figure 3 This is a schematic diagram of the upper connecting plate in this utility model;

[0016] Figure 4 This is a schematic diagram of the lower connecting plate in this utility model.

[0017] In the figure, 1-embedded steel plate, 2-upper connecting plate, 21-first threaded hole, 22-plug welding hole, 23-tenon, 3-lower connecting plate, 31-second threaded hole, 32-tenon groove, 4-stiffening plate, 5-hopper body, 6-first connecting pipe, 7-second connecting pipe, 8-double nut, 9-double-ended stud, 10-sealing gasket, 11-ring platform. Detailed Implementation

[0018] The technical solution of this utility model will be described below with reference to the accompanying drawings and implementation methods.

[0019] like Figure 1 As shown, a hopper for a hydrometallurgical pressure leaching reinforced concrete thickener includes a hopper body 5. Specifically, the hopper body 5 is conical in shape, with the diameter decreasing from top to bottom. The hopper body 5 has a second connecting pipe 7 on its side and a first connecting pipe 6 at its bottom. The first connecting pipe 6 is L-shaped, and the hopper body 5 and the second connecting pipe 7 are vertically connected.

[0020] Above the main body 5 of the hopper, there is a pre-embedded steel plate 1, an upper connecting plate 2, and a lower connecting plate 3 arranged in sequence. The lower surface of the pre-embedded steel plate 1 has a ring platform 11, located on the side of the upper connecting plate 2, which serves a positioning function; Figure 2As shown, the lower connecting plate 3 and the upper connecting plate 2 are connected by double-headed studs 9 and double nuts 8, and the hopper body 5 is fixedly connected to the lower connecting plate 3.

[0021] Several reinforcing ribs 4 are provided at the connection between the hopper body 5 and the lower connecting plate 3. One end of the reinforcing rib 4 is connected to the hopper body 5 and the other end is connected to the lower connecting plate 3.

[0022] like Figure 3 and 4 As shown, the upper connecting plate 2 has two symmetrically arranged plug welding holes 22 on both sides, and the plug welding holes 22 are through holes; a first threaded hole 21 is provided between adjacent plug welding holes 22, and a second threaded hole 31 is provided on the lower connecting plate 3. The first threaded hole 21 and the second threaded hole 31 are connected by a double-ended stud 9.

[0023] The upper connecting plate 2 is provided with a tenon 23 and the lower connecting plate 3 is provided with a mortise 32. The tenon 23 and the mortise 32 are connected by a sealing gasket 10, which is made of polytetrafluoroethylene.

[0024] The installation process of this utility model is as follows:

[0025] First, place the pre-embedded steel plate 1 at the bottom of the thickener; second, weld the upper connecting plate 2 to the pre-embedded steel plate 1 by plug welding and fillet welding; next, connect the lower connecting plate 3 to the upper connecting plate 2 using double-ended studs 9 and double nuts 8; finally, weld the lower connecting plate 3 to the hopper body 5 to complete the overall assembly.

Claims

1. A hydrometallurgical pressure leach reinforced concrete thickener underflow hopper characterised in that, The hopper includes a main body (5), on which a pre-embedded steel plate (1), an upper connecting plate (2) and a lower connecting plate (3) are arranged in sequence. The lower connecting plate (3) and the upper connecting plate (2) are connected by a double-headed stud (9) and a double nut (8). The main body (5) and the lower connecting plate (3) are fixedly connected. The main body (5) has a second pipe (7) on its side and a first pipe (6) at its bottom. The main body (5) and the second pipe (7) are vertically connected.

2. A pressure leach reinforced concrete thickener underflow hopper according to claim 1 characterised in that, The upper connecting plate (2) is provided with a plurality of symmetrically arranged plug welding holes (22), and a first threaded hole (21) is provided between adjacent plug welding holes (22). The lower connecting plate (3) is provided with a second threaded hole (31). The first threaded hole (21) and the second threaded hole (31) are connected by a double-ended stud (9).

3. A pressure leaching reinforced concrete thickener underflow hopper according to claim 1 characterised in that, The connection between the hopper body (5) and the lower connecting plate (3) is provided with several reinforcing plates (4). One end of the reinforcing plate (4) is connected to the hopper body (5), and the other end is connected to the lower connecting plate (3).

4. A pressure leach reinforced concrete thickener underflow hopper according to claim 1 characterised in that, The first connector (6) is L-shaped.

5. A pressure leach reinforced concrete thickener underflow hopper according to claim 1 characterised in that, The lower surface of the pre-embedded steel plate (1) is provided with a ring platform (11).

6. A pressure leach reinforced concrete thickener underflow hopper according to claim 1 characterised in that, The upper connecting plate (2) is provided with a tenon (23) and the lower connecting plate (3) is provided with a mortise (32). The tenon (23) and the mortise (32) are connected by a sealing gasket (10).

7. A pressure leach reinforced concrete thickener underflow hopper according to claim 6, characterised in that, The sealing gasket (10) is made of polytetrafluoroethylene.