A high mountain wind power transmission line engineering pile stable support mechanism
By setting a sand and gravel support pad and a concrete filling layer at the bottom of the wind power project pile foundation pit, combined with a U-shaped steel plate and support buffer components, a high-strength and high-rigidity support system is formed, which solves the stability and safety problems of wind power project piles in complex environments in high-altitude areas, effectively resists wind loads and earthquakes, and improves the safety and stability of wind power transmission lines.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- SINOHYDRO ENG BUREAU 4
- Filing Date
- 2025-08-20
- Publication Date
- 2026-08-04
AI Technical Summary
Traditional wind power engineering piles in mountainous areas are unable to effectively absorb and release external impact energy due to complex terrain, high wind speeds, and frequent gusts, leading to structural fatigue failure and overturning. Existing structural designs fail to meet the stability and safety requirements of complex mountainous environments.
A sand and gravel support cushion layer, a concrete filling layer, and a concrete smoothing support layer are set at the bottom of the foundation pit of the engineering pile body. Combined with the U-shaped steel plate, the steel cage and the concrete support column, a high-strength core support system is formed. Support buffer components, including I-shaped steel plates, hydraulic buffer dampers and buffer springs, are set around the U-shaped steel plate to achieve dynamic shock reduction and elastic support.
It improves the settlement resistance of the engineering piles and the overall structural stability, prevents resonance and overturning, enhances the resistance to wind loads and earthquakes, and ensures the safe and stable operation of wind power transmission lines in complex mountainous environments.
Smart Images

Figure CN224591480U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the technical field of wind power transmission line engineering, and in particular, it is a pile stabilization support mechanism for high-altitude wind power transmission line engineering. Background Technology
[0002] With the continuous advancement of my country's renewable energy development strategy, wind power construction is gradually expanding from plains to complex terrain areas such as mountains and hills. When constructing wind power projects in high-altitude areas, traditional engineering pile foundation structures often fail to meet the stability and safety requirements for long-term operation due to factors such as large terrain undulations, complex geological conditions, and frequent wind loads. Therefore, developing a stable support structure for engineering piles that can adapt to complex mountainous environments and possesses good overturning resistance and shock absorption performance has become a key technical problem that urgently needs to be solved in the construction of high-altitude wind power transmission lines.
[0003] Currently, most existing wind power engineering piles adopt single concrete cast-in-place piles or steel support structures, with relatively simple foundation treatment methods, typically fixed simply by direct pouring or driving into the ground. However, in high-altitude environments, this traditional structure has many shortcomings. For example, its design concept is mainly designed for the relatively stable geological conditions and smaller wind loads in plain areas. In high-altitude areas, due to complex terrain, high wind speeds, and frequent gusts, the dynamic external forces borne by the piles increase significantly, and existing structures lack any buffer structure, resulting in an inability to effectively absorb and release external impact energy. When strong winds or earthquakes occur, external forces act directly on the engineering piles and are rapidly transmitted to the foundation structure through rigid connections, causing the piles to resonate or sway violently. Due to the lack of buffer structure design, stress is concentrated at certain critical nodes (such as anchor points or connection parts), which can easily lead to structural fatigue failure, bolt loosening, or even overall overturning. Utility Model Content
[0004] The purpose of this utility model is to provide a stable support mechanism for high-altitude wind power transmission line engineering piles to solve the problems mentioned in the background art.
[0005] To achieve the above objectives, this utility model provides the following technical solution: a stabilizing support mechanism for high-altitude wind power transmission line engineering piles, comprising:
[0006] Construction area for wind power transmission lines.
[0007] In this preferred embodiment, a pile foundation pit is excavated in the area, and a sand and gravel support cushion layer, a concrete filling layer and a concrete smoothing support layer are laid sequentially at the bottom of the pile foundation pit. A foundation pit support component is provided on the inner wall of the pile foundation pit, which consists of an outer sand and gravel support edge layer and an inner concrete support edge layer.
[0008] In this preferred embodiment, a U-shaped steel plate is longitudinally embedded at the center of the pile foundation pit and arranged perpendicular to the concrete smoothing support layer. A steel cage is longitudinally installed inside the U-shaped steel plate, and concrete is poured into it to form a concrete support column. A second smoothing layer is installed on top.
[0009] In this preferred embodiment, the engineering piles are installed on the top surface of the second smoothing layer by multiple anchor rods and extend into the concrete support column.
[0010] In this preferred embodiment, a support and buffer assembly is symmetrically installed between the periphery of the U-shaped steel plate and the foundation pit support assembly. This assembly includes an I-shaped steel plate, a hydraulic buffer damper, and a buffer spring, which are used to provide elastic support and dynamic buffering for the U-shaped steel plate.
[0011] In this preferred embodiment, a first smoothing layer is set above the pile foundation pit and between the wind power transmission line construction area and the U-shaped steel plate. Both the sand and gravel support edge layer and the concrete support edge layer are set on the surface of the concrete smoothing support layer. Each hydraulic buffer damper is equipped with a hydraulic station on one side to control its buffering performance.
[0012] Compared with the prior art, the technical effects and advantages of this utility model are as follows:
[0013] The pile stabilization support mechanism for this high-altitude wind power transmission line project, through the design of setting a sand and gravel support pad, a concrete filling layer, and a concrete smoothing support layer at the bottom of the pile foundation pit, enables the foundation to have good drainage performance and bearing capacity, while improving the uniformity and stability of the foundation, realizing the effective support function for the engineering pile body, and achieving the effect of enhancing the overall structure's anti-settlement capacity and construction quality.
[0014] By embedding a U-shaped steel plate longitudinally into the center of the pile foundation pit and perpendicular to the concrete support layer, and setting a steel cage and pouring concrete support columns inside, the structure forms a high-strength, high-rigidity core support system. The steel cage enhances the tensile strength and seismic performance of the concrete columns, realizes the foundation stability function of the engineering pile, and achieves the effect of improving the overall structural bearing capacity and overturning resistance.
[0015] By symmetrically setting support and buffer components between the outer wall of the U-shaped steel plate and the inner wall of the foundation pit support component, the external vibration energy can be effectively absorbed and released. The hydraulic buffer damper and the buffer spring work together to achieve the functions of dynamic shock reduction and elastic support, thus preventing the engineering pile from resonating, displacing or being damaged due to external forces such as wind load and earthquake.
[0016] The entire high-altitude wind power transmission line engineering pile stabilization support mechanism not only has excellent load-bearing performance, but also good buffering and shock absorption capabilities and geological adaptability, realizing the function of safe and stable operation in complex mountainous environments, and achieving the comprehensive technical effect of improving the long-term stability and safety reliability of the wind power transmission line foundation structure. Attached Figure Description
[0017] To more clearly illustrate the specific embodiments of this utility model or the technical solutions in the prior art, the drawings used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of this utility model. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.
[0018] Figure 1 This is a schematic diagram of the structure of this utility model;
[0019] Figure 2 This is a schematic diagram of the foundation pit support component of this utility model;
[0020] Figure 3 This is a schematic diagram of the installation of the reinforcing cage of this utility model;
[0021] Figure 4 This is a schematic diagram of the installation structure of the hydraulic buffer damper and buffer spring of this utility model.
[0022] Explanation of reference numerals in the attached figures:
[0023] In the diagram: 1. Wind power transmission line construction area; 2. First leveling layer; 3. Engineering pile; 4. U-shaped steel plate; 5. Second leveling layer; 6. Anchor bolt; 7. Pile foundation pit; 8. Sand and gravel support edge layer; 9. Concrete support edge layer; 10. Foundation pit support components; 11. I-shaped steel plate; 12. Hydraulic buffer damper; 13. Buffer spring; 14. Sand and gravel support cushion layer; 15. Concrete filling layer; 16. Concrete leveling support layer; 17. Concrete support column; 18. Reinforcing cage. Detailed Implementation
[0024] In the following description, numerous specific details are set forth in order to provide a more thorough understanding of the present invention. However, it will be apparent to those skilled in the art that the present invention can be practiced without one or more of these details. In other instances, certain technical features well-known in the art have not been described in order to avoid confusion with the present invention.
[0025] Unless otherwise defined, the directions mentioned herein, such as up, down, left, right, front, back, inside, and outside, are based on the directions shown in the figures of this utility model, and are explained here together.
[0026] This embodiment provides, for example Figures 1 to 4 The illustrated high-altitude wind power transmission line engineering pile stabilization support mechanism includes: wind power transmission line construction area 1, pile foundation pit 7, foundation pit support component 10, U-shaped steel plate 4, and engineering pile body 3.
[0027] The pile foundation pit 7 is excavated in the wind power transmission line construction area 1. The inner bottom wall of the pile foundation pit 7 is filled with a layer of sand and gravel support cushion 14. A concrete filling layer 15 is poured into the gap of the sand and gravel support cushion 14. A concrete smoothing support layer 16 is poured on the sand and gravel support cushion 14.
[0028] The foundation pit support component 10 is installed on the inner wall of the pile foundation pit 7;
[0029] The U-shaped steel plate 4 is longitudinally lowered into the middle of the inner cavity of the pile foundation pit 7 and perpendicular to the concrete smoothing support layer 16. A steel cage 18 is longitudinally fixed in the middle of the inner cavity of the U-shaped steel plate 4. A concrete support column 17 is poured in the inner cavity of the U-shaped steel plate 4. A second smoothing layer 5 is poured on the top surface of the concrete support column 17 and located in the U-shaped steel plate 4.
[0030] The engineering pile 3 is installed on the top surface of the second smoothing layer 5 by multiple anchor rods 6, so that the anchor rods 6 extend into the concrete support column 17;
[0031] The support and buffer components are symmetrically arranged between the outer walls of the U-shaped steel plate 4 and the inner walls of the foundation pit support components 10. This allows the support and buffer components to not only support the U-shaped steel plate 4 in the pile foundation pit 7 and prevent it from tilting, but also to buffer the vibrations generated by external forces, preventing the engineering pile 3 from loosening, tilting, or misaligning, thereby improving the installation stability of the high-altitude wind power transmission line.
[0032] In this embodiment, the foundation pit support component 10 includes a ring of sand and gravel support edge layer 8 filled and stacked around the inner wall of the pile foundation pit 7, and a ring of concrete support edge layer 9 poured around the inner wall of the sand and gravel support edge layer 8.
[0033] In this embodiment, the support and buffer assembly includes I-shaped steel plates 11 symmetrically installed on each outer wall of the four sides of the U-shaped steel plate and multiple hydraulic buffer dampers 12 symmetrically installed between the inner walls at both ends of each I-shaped steel plate 11.
[0034] In this embodiment, each hydraulic buffer damper 12 has a connecting plate welded to both ends, and the two connecting plates are fixedly connected to the inner wall of the I-shaped steel plate 11 respectively.
[0035] In this embodiment, each hydraulic buffer damper 12 is fitted with a buffer spring 13 around its periphery, and the two ends of the buffer spring 13 elastically abut against the inner walls of two adjacent connecting discs.
[0036] In this embodiment, a first smoothing layer 2 is provided above the pile foundation pit 7 and between the wind power transmission line construction area 1 and the U-shaped steel plate 4.
[0037] In this embodiment, the engineering pile 3 is located in the middle position above the extension of the U-shaped steel plate 4.
[0038] In this embodiment, both the gravel support edge layer 8 and the concrete support edge layer 9 are constructed on the surface of the concrete smooth support layer 16.
[0039] In this embodiment, a hydraulic station is provided on one side of each hydraulic buffer damper 12 and on the inner wall of the I-shaped steel plate 11.
[0040] Working principle
[0041] The high-altitude wind power transmission line engineering pile stabilization support mechanism selects a suitable route for the construction of the wind power transmission line in the high-altitude area, conducts geological surveys and assessments of geological conditions such as rock type, soil density, and groundwater level, determines the pile layout location, and mechanically excavates a regular pile foundation pit 7 at the selected location according to the design drawings. The size of the pile foundation pit 7 is determined according to the size of the engineering pile and geological conditions, and is usually rectangular. The bottom of the foundation pit is cleared of gravel and debris to ensure foundation stability.
[0042] A layer of sand and gravel support pad 14 is laid at the bottom of the pile foundation pit 7 to serve as drainage, shock absorption and leveling. A concrete filling layer 15 is injected into the gaps of the sand and gravel support pad 14 to enhance the density and bearing capacity. The top layer of concrete is poured and the support layer 16 is smoothed to ensure a flat surface for easy subsequent structural installation.
[0043] A ring of sand and gravel support edge layer 8 is built around the inner wall of the pile foundation pit 7 to prevent the side wall of the foundation pit from collapsing. A ring of concrete support edge layer 9 is poured inside the sand and gravel support cushion layer 14 to further reinforce the slope of the foundation pit. The sand and gravel support cushion layer 14 and the concrete filling layer 15 together form a support structure that combines flexibility and rigidity, which is suitable for unstable geological environments.
[0044] The prefabricated U-shaped steel plate 4 is vertically embedded into the center of the foundation pit, and its bottom surface is tightly attached to the concrete support layer 16. A steel cage 18 is placed longitudinally inside the U-shaped steel plate 4 to enhance the structural strength. A concrete support column 17 is poured to make the U-shaped steel plate 4 tightly bonded to the concrete to form a rigid core. A second smoothing layer 5 is poured on top of the concrete support column 17 to ensure that the connection surface with the upper engineering pile is flat.
[0045] The engineering pile 3 is placed on the second smoothing layer 5, and multiple anchor rods 6 are used to firmly fix the engineering pile 3 in the concrete support column 17. The anchor rods 6 penetrate into the concrete support column 17 to provide a high-strength connection and prevent the engineering pile 3 from slipping or tilting. I-shaped steel plates 11 are symmetrically installed on the outer walls of the U-shaped steel plate 4. Multiple hydraulic buffer dampers 12 are installed between the inner walls of both ends of each I-shaped steel plate 11 and fixed by welding connecting plates. A buffer spring 13 is fitted on each hydraulic buffer damper 12 to achieve elastic support. One end of the buffer component is connected to the U-shaped steel plate, and the other end is connected to the inner wall of the foundation pit support component 10 to form all-round dynamic support. Each hydraulic buffer damper 12 has a hydraulic station on one side, which can adjust the buffer force to adapt to different external environments.
[0046] A first smoothing layer 2 is set above the pile foundation pit, between the wind power transmission line construction area 1 and the U-shaped steel plate 4. The first smoothing layer serves a protective function, while also improving the overall aesthetics and the cleanliness of the construction.
[0047] After installation, under normal conditions: the U-shaped steel plate 14 and the concrete support column 17 jointly bear the weight of the engineering pile 3, and the I-shaped steel plate 14 and the buffer assembly are in a pre-compression state to maintain structural stability.
[0048] When encountering strong winds or vibrations, external forces are transmitted to the engineering pile 3, which in turn acts on the U-shaped steel plate 14. The hydraulic buffer damper 12 in the support buffer assembly begins to compress, absorbing some kinetic energy. The buffer spring 13 further releases elastic energy to offset residual vibrations, keeping the overall structure stable and preventing the engineering pile 3 from tilting or loosening.
[0049] During long-term use: the concrete support column 17 and the steel cage 18 work together to resist the stress caused by soil settlement, the foundation pit support component 10 prevents slope instability and extends service life, and the buffer component can be inspected and replaced regularly as needed to ensure the continuous safety of the structure.
[0050] It should be noted that, in this document, relational terms such as "one" and "two" are used merely to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, the phrase "comprising an element defined as..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0051] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A stabilizing support mechanism for high-altitude wind power transmission line engineering piles, characterized in that, include: The pile foundation pit (7) has an inner bottom wall filled with a layer of sand and gravel support cushion (14), and a concrete filling layer (15) is poured into the gaps of the sand and gravel support cushion (14). A concrete smoothing support layer (16) is poured on the sand and gravel support cushion (14). The foundation pit support component (10) is installed on the inner wall of the pile foundation pit (7); A U-shaped steel plate (4) is longitudinally inserted into the middle of the inner cavity of the pile foundation pit (7) and perpendicular to the concrete smoothing support layer (16). A steel cage (18) is longitudinally fixed in the middle of the inner cavity of the U-shaped steel plate (4). A concrete support column (17) is poured in the inner cavity of the U-shaped steel plate (4). A second smoothing layer (5) is poured on the top surface of the concrete support column (17) and located in the U-shaped steel plate (4). The engineering pile (3) is installed on the top surface of the second smoothing layer (5) by multiple anchor rods (6), so that the anchor rods (6) extend into the concrete support column (17); The support and buffer components are symmetrically arranged between the outer wall of the U-shaped steel plate (4) and the inner wall of the foundation pit support component (10).
2. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 1, characterized in that: The foundation pit support assembly (10) includes a ring of sand and gravel support edge layer (8) filled and stacked around the inner wall of the pile foundation pit (7) and a ring of concrete support edge layer (9) poured around the inner wall of the sand and gravel support edge layer (8).
3. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 2, characterized in that: The support and buffer assembly includes I-beam steel plates (11) symmetrically installed on each outer wall of the U-shaped steel plate (4) and multiple hydraulic buffer dampers (12) symmetrically installed between the inner walls at both ends of each I-beam steel plate (11).
4. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 3, characterized in that: Each of the hydraulic buffer dampers (12) has a connecting plate welded to both ends, and the two connecting plates are respectively fixedly connected to the inner wall of the I-shaped steel plate (11).
5. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 4, characterized in that: Each of the hydraulic dampers (12) is fitted with a buffer spring (13) on its periphery, and the two ends of the buffer spring (13) elastically abut against the inner walls of two adjacent connecting discs.
6. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 5, characterized in that: A first smoothing layer (2) is provided above the pile foundation pit (7) and between the wind power transmission line construction area (1) and the U-shaped steel plate (4).
7. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 6, characterized in that: The engineering pile (3) is located in the middle position above the extension of the U-shaped steel plate (4).
8. The high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 7, characterized in that: Both the gravel support edge layer (8) and the concrete support edge layer (9) are constructed on the surface of the concrete smooth support layer (16).
9. A high-altitude wind power transmission line engineering pile stabilization support mechanism according to claim 8, characterized in that: A hydraulic station is provided on one side of each of the hydraulic buffer dampers (12) and on the inner wall of the I-beam steel plate (11).