Prefabricated teaching building corridor structure
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-08-30
- Publication Date
- 2026-08-11
AI Technical Summary
[0005]针对现有技术的不足,本申请提供了一种装配式教学楼连廊结构,克服了现有技术的不足,旨在解决现有的预制混凝土箱型连廊,通过整体浇筑成带肋板的箱型构件,运输至现场后通过后张预应力拼接,但是由于单构件重量大,需大型吊装设备,导致运输与吊装成本激增的问题
1.两组梁体均通过底部的两组定位机构与教学楼建筑体相连,然后依次对若干组预制板体机构进行吊装,将预制板体机构底部的两组限位块对应的限位槽对齐插入,形成机械咬合,然后通过两组预应力钢绞线穿过若干组预制板体机构内的穿孔,将若干组预制板体机构连接,形成连续受力体系,将两组端部封板对若干组预制板体机构的两端进行封闭,端部封板通过若干组高强度螺栓二与教学楼建筑体相连,然后预应力钢绞线的两端通过钢套进行端固定,本申请大大降低大跨度连廊构件的单件运输重量,从而减少了构件运输成本。
Smart Images

Figure CN224620795U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of building structure engineering technology, and in particular to a prefabricated teaching building corridor structure. Background Technology
[0002] Prefabricated building technology is now widely used in various public buildings such as schools, hospitals, and commercial complexes. Among them, the standardization of connecting corridors, as transitional spaces connecting different functional areas, directly affects construction efficiency. Traditional cast-in-place concrete connecting corridors have problems such as long curing cycles and large consumption of formwork. Existing prefabricated connecting corridors mostly adopt steel frame or precast concrete slab combination structures, which greatly shortens on-site operation time.
[0003] The existing precast concrete box-type corridors are constructed by casting ribbed box-type components as a whole, which are then transported to the site and spliced using post-tensioned prestressing. However, due to the large weight of each component, large hoisting equipment is required, which leads to a surge in transportation and hoisting costs.
[0004] Therefore, this application provides a prefabricated teaching building corridor structure. Utility Model Content
[0005] To address the shortcomings of existing technologies, this application provides a prefabricated teaching building corridor structure that overcomes the deficiencies of existing technologies. It aims to solve the problem that existing precast concrete box-type corridors, which are integrally cast into ribbed box-type components and then transported to the site for post-tensioning and splicing, suffer from the problem of soaring transportation and hoisting costs due to the large weight of each component and the need for large hoisting equipment.
[0006] To achieve the above objectives, this application provides the following technical solution: a prefabricated teaching building corridor structure, comprising two sets of beams, with two sets of far-away positioning mechanisms at the bottom of the beams, and a limiting groove at the top of the beams. Several sets of prefabricated slab mechanisms are arranged above the two sets of beams, with two sets of limiting blocks fixedly installed at the bottom of each prefabricated slab mechanism. The two sets of limiting blocks are respectively inserted into the corresponding limiting grooves. Two sets of through holes are provided inside each prefabricated slab mechanism, and the two sets of through holes in adjacent sets of prefabricated slab mechanisms are connected. Prestressed steel strands are threaded through several sets of connected through holes in the same row. End sealing plates are provided at both ends of each set of prefabricated slab mechanisms, and several sets of high-strength bolts are installed at the bottom of the end sealing plates. Steel sleeves are fixedly installed at both ends of the prestressed steel strands through the two sets of end sealing plates.
[0007] By adopting the above technical solution, both sets of beams are connected to the teaching building structure through two sets of positioning mechanisms at the bottom. Then, several sets of precast slab structures are hoisted in sequence, and the corresponding limiting slots of the two sets of limiting blocks at the bottom of the precast slab structures are aligned and inserted to form a mechanical engagement. Then, two sets of prestressed steel strands are passed through the perforations in the precast slab structures to connect the precast slab structures, forming a continuous force-bearing system. Two sets of end sealing plates are used to seal both ends of the precast slab structures. The end sealing plates are connected to the teaching building structure through several sets of high-strength bolts. Then, the two ends of the prestressed steel strands are fixed by steel sleeves. This application greatly reduces the single-piece transportation weight of the large-span corridor components, thereby reducing the component transportation cost.
[0008] As a preferred technical solution of this application, the top of the beam is provided with two sets of channels, and two sets of steel beams are welded to the channels, with a curtain wall inserted between the two sets of steel beams.
[0009] By adopting the above technical solution, rapid assembly can be achieved by installing two sets of steel beams in the channel and then installing the curtain wall between the two sets of symmetrically arranged steel beams.
[0010] As a preferred technical solution of this application, the positioning mechanism includes a bracket, which is fixedly installed at the bottom end of the beam. A fixing plate is fixedly installed at the bottom of the bracket, and a number of sets of high-strength bolts are threadedly connected to the outer circumference of the fixing plate.
[0011] By adopting the above technical solution, both ends of the beam extend into the interior of the teaching building, and the beam is supported by two sets of corbels. It is directly connected to the main building structure by high-strength bolts, which improves the support strength.
[0012] As a preferred technical solution of this application, the precast panel mechanism includes a panel, which is fixedly installed on the top of two sets of limiting blocks. A lower side protrusion is provided on one side of the panel, and an upper side protrusion is provided on the side of the panel away from the lower side protrusion. Two adjacent sets of panels are connected by the lower side protrusion and the upper side protrusion, and an anti-slip layer is fixedly connected to the top of the lower side protrusion.
[0013] By adopting the above technical solution, the two adjacent sets of plates are connected by the side lower convex plate and the side upper convex plate, which increases the contact area when the two sets of plates are connected. With the anti-slip layer, the stability of the two sets of plates when connected is improved.
[0014] As a preferred technical solution of this application, a sealing strip is fixedly installed at the installation end of the channel, and the sealing strip covers the bottom of the steel beam and the curtain wall.
[0015] By adopting the above technical solution, using EPDM rubber for the sealing strip, and using a hot-melt welding process to cover the joint between the steel beam and the bottom of the curtain wall, the tightness of the steel beam and curtain wall installed in the channel is improved.
[0016] As a preferred technical solution of this application, a shock-absorbing pad is fixedly installed at the bottom end of the fixing plate, and the shock-absorbing pad has a rubber layer.
[0017] By adopting the above technical solution, the shock-absorbing pads buffer the shear force, thereby enhancing the seismic resistance of the positioning mechanism.
[0018] As a preferred technical solution of this application, the curtain wall adopts lightweight ALC wall panels.
[0019] By adopting the above technical solutions, ALC wall panels have a better ability to bear structural loads, and the structural self-weight is reduced, further reducing transportation and hoisting costs.
[0020] The beneficial effects of this application are: 1. Both sets of beams are connected to the teaching building structure through two sets of positioning mechanisms at the bottom. Then, several sets of precast slab structures are hoisted in sequence. The corresponding limiting slots of the two sets of limiting blocks at the bottom of the precast slab structures are aligned and inserted to form a mechanical engagement. Then, two sets of prestressed steel strands are passed through the perforations in the precast slab structures to connect the precast slab structures and form a continuous force-bearing system. Two sets of end sealing plates are used to close the two ends of the precast slab structures. The end sealing plates are connected to the teaching building structure through several sets of high-strength bolts. Then, the two ends of the prestressed steel strands are fixed by steel sleeves. This application greatly reduces the single-piece transportation weight of the large-span corridor components, thereby reducing the component transportation cost.
[0021] 2. Rapid assembly is achieved by installing two sets of steel beams in the channel and then installing the curtain wall between the two symmetrically arranged steel beams. Attached Figure Description
[0022] Figure 1 This is a schematic diagram of the overall structure of this application; Figure 2 This is a schematic diagram of a partially separated structure of this application; Figure 3 This is a schematic diagram of the precast panel structure. Figure 4 for Figure 2 Enlarged structural diagram at point A in the middle.
[0023] In the diagram: 1. Beam; 2. Positioning mechanism; 201. Bracket; 202. Fixing plate; 203. High-strength bolt one; 3. Limiting groove; 4. Precast slab mechanism; 401. Slab; 402. Lower side protrusion plate; 403. Upper side protrusion plate; 404. Anti-slip layer; 5. Limiting block; 6. Perforation; 7. Prestressed steel strand; 8. End sealing plate; 9. High-strength bolt two; 10. Steel sleeve; 11. Channel; 12. Steel beam; 13. Curtain wall; 14. Sealing strip; 15. Vibration damping pad. Detailed Implementation
[0024] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0025] Reference Figure 1-4 A prefabricated teaching building corridor structure includes two sets of beams 1. Two sets of positioning mechanisms 2 are located at the bottom of each beam 1 and are spaced far apart. Limiting grooves 3 are formed at the top of each beam 1. Several sets of prefabricated slab mechanisms 4 are arranged above the two sets of beams 1. Two sets of limiting blocks 5 are fixedly installed at the bottom of each prefabricated slab mechanism 4, and the two sets of limiting blocks 5 are respectively inserted into the corresponding limiting grooves 3. Two sets of through holes 6 are formed inside each prefabricated slab mechanism 4. The two sets of through holes 6 of two adjacent sets of prefabricated slab mechanisms 4 are connected and located in the same row. Several sets of perforations 6 are filled with prestressed steel strands 7. Several sets of precast slab mechanisms 4 are provided with end sealing plates 8 at both ends. Several sets of high-strength bolts 9 are installed at the bottom of the end sealing plates 8. Two sets of end sealing plates 8 are used to fix steel sleeves 10 at both ends of the prestressed steel strands 7. The positioning mechanism 2 includes a bracket 201, which is fixedly installed at the bottom of the beam 1. A fixing plate 202 is fixedly installed at the bottom of the bracket 201. Several sets of high-strength bolts 203 are threadedly connected to the outer circumference of the fixing plate 202.
[0026] Both sets of beams 1 are connected to the teaching building structure through two sets of positioning mechanisms 2 at the bottom. Then, several sets of precast slab structures 4 are hoisted in sequence. The two sets of limiting blocks 5 at the bottom of the precast slab structures 4 are aligned and inserted into the corresponding limiting grooves 3 to form a mechanical engagement. Then, two sets of prestressed steel strands 7 are passed through the perforations 6 in the precast slab structures 4 to connect the precast slab structures 4 and form a continuous force system. Two sets of end sealing plates 8 are used to close the two ends of the precast slab structures 4. The end sealing plates 8 are connected to the teaching building structure through several sets of high-strength bolts 9. Then, the two ends of the prestressed steel strands 7 are fixed by steel sleeves 10. This application greatly reduces the single-piece transportation weight of the large-span corridor components, thereby reducing the component transportation cost. The two ends of the beams 1 extend into the interior of the teaching building structure and are supported by two sets of brackets 201. They are directly connected to the main building structure by high-strength bolts 203, which improves the support strength.
[0027] Reference Figure 2-4 The top of the beam 1 is provided with two sets of channels 11, and two sets of steel beams 12 are welded at the channels 11. A curtain wall 13 is inserted between the two sets of steel beams 12. The precast panel mechanism 4 includes a panel 401, which is fixedly installed on the top of two sets of limiting blocks 5. A side lower protrusion plate 402 is provided on one side of the panel 401, and a side upper protrusion plate 403 is provided on the side of the panel 401 away from the side lower protrusion plate 402. Two adjacent sets of panels 401 are connected by the side lower protrusion plate 402 and the side upper protrusion plate 403, and an anti-slip layer 404 is fixedly connected to the top of the side lower protrusion plate 402. By installing two sets of steel beams 12 in the channel 11, and then installing the curtain wall 13 between the two sets of symmetrically arranged steel beams 12, rapid assembly is achieved; the two adjacent sets of panels 401 are connected by the side lower protrusion plate 402 and the side upper protrusion plate 403, which increases the contact area when the two sets of panels 401 are connected, and with the anti-slip layer 404, the stability when the two sets of panels 401 are connected is improved.
[0028] Reference Figure 2-4 A sealing strip 14 is fixedly installed at the installation end of the channel 11, and the sealing strip 14 covers the bottom of the steel beam 12 and the curtain wall 13; the curtain wall 13 is made of lightweight ALC wall panel; the sealing strip 14 is made of EPDM rubber and is wrapped around the bottom joint of the steel beam 12 and the curtain wall 13 by hot melt welding process, which improves the tightness of the installation of the steel beam 12 and the curtain wall 13 in the channel 11; the curtain wall 13 is made of lightweight ALC wall panel.
[0029] Reference Figure 1-3 A shock-absorbing pad 15 is fixedly installed at the bottom of the fixed plate 202. The shock-absorbing pad 15 has a rubber layer. The shock-absorbing pad 15 buffers the shear force, thereby enhancing the shock resistance of the positioning mechanism 2.
[0030] Working principle: Both sets of beams 1 are connected to the teaching building structure through two sets of positioning mechanisms 2 at the bottom. Then, several sets of precast slab mechanisms 4 are hoisted in sequence. The two sets of limiting blocks 5 at the bottom of the precast slab mechanism 4 are aligned and inserted into the corresponding limiting grooves 3 to form a mechanical engagement. Then, two sets of prestressed steel strands 7 are passed through the perforations 6 in the precast slab mechanisms 4 to connect the precast slab mechanisms 4 and form a continuous force system. Two sets of end sealing plates 8 are used to seal the two ends of the precast slab mechanisms 4. The end sealing plates 8 are connected to the teaching building structure through several sets of high-strength bolts 9. Then, the two ends of the prestressed steel strands 7 are fixed by steel sleeves 10. This application greatly reduces the single-piece transportation weight of the large-span corridor components, thereby reducing the component transportation cost. By installing two sets of steel beams 12 in the channel 11 and then installing the curtain wall 13 between the two sets of symmetrically arranged steel beams 12, rapid assembly is achieved. The beam 1 extends into the interior of the teaching building at both ends and is supported by two sets of brackets 201. It is directly connected to the main building by high-strength bolts 203, which improves the support strength. The two adjacent sets of plates 401 are connected by side lower convex plates 402 and side upper convex plates 403, which increases the contact area when the two sets of plates 401 are connected. With the anti-slip layer 404, the stability of the two sets of plates 401 when connected is improved. Meanwhile, by using EPDM rubber for the sealing strip 14 and wrapping the bottom joint between the steel beam 12 and the curtain wall 13 through hot melt welding, the tightness of the steel beam 12 and the curtain wall 13 installed in the channel 11 is improved; and by using the shock-absorbing pad 15 to buffer the shear force, the seismic resistance of the positioning mechanism 2 is enhanced. In addition, curtain wall 13 uses lightweight ALC wall panels.
[0031] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
Claims
1. A prefabricated teaching building corridor structure, comprising two sets of beams (1), characterized in that, Two sets of positioning mechanisms (2) are provided at the bottom of the beam (1) and are far apart. A limit groove (3) is opened at the top of the beam (1). Several sets of precast slab mechanisms (4) are provided above the two sets of beams (1). Two sets of limit blocks (5) are fixedly installed at the bottom of the precast slab mechanism (4). The two sets of limit blocks (5) are respectively inserted into the corresponding limit groove (3). Two sets of through holes (6) are opened inside the precast slab mechanism (4). The two sets of through holes (6) of the two adjacent sets of precast slab mechanisms (4) are connected. Prestressed steel strands (7) are passed through several sets of through holes (6) in the same row. End sealing plates (8) are provided at both ends of several sets of precast slab mechanisms (4). Several sets of high-strength bolts (9) are installed at the bottom of the end sealing plates (8). Steel sleeves (10) are fixedly installed at both ends of the prestressed steel strands (7) through the two sets of end sealing plates (8).
2. The prefabricated teaching building corridor structure according to claim 1, characterized in that, The top of the beam (1) is provided with two sets of channels (11), and two sets of steel beams (12) are welded at the channels (11). A curtain wall (13) is inserted between the two sets of steel beams (12).
3. The prefabricated teaching building corridor structure according to claim 1, characterized in that, The positioning mechanism (2) includes a bracket (201), which is fixedly installed at the bottom end of the beam (1). A fixing plate (202) is fixedly installed at the bottom of the bracket (201), and a number of high-strength bolts (203) are threadedly connected to the outer periphery of the fixing plate (202).
4. The prefabricated teaching building corridor structure according to claim 1, characterized in that, The precast panel mechanism (4) includes a panel (401), which is fixedly installed on the top of two sets of limiting blocks (5). A side lower protrusion plate (402) is provided on one side of the panel (401), and a side upper protrusion plate (403) is provided on the side of the panel (401) away from the side lower protrusion plate (402). Two adjacent sets of panels (401) are connected by the side lower protrusion plate (402) and the side upper protrusion plate (403), and an anti-slip layer (404) is fixedly connected to the top of the side lower protrusion plate (402).
5. A prefabricated teaching building corridor structure according to claim 3, characterized in that, A sealing strip (14) is fixedly installed at the installation end of the channel (11), and the sealing strip (14) covers the bottom of the steel beam (12) and the curtain wall (13).
6. The prefabricated teaching building corridor structure according to claim 3, characterized in that, The bottom end of the fixed plate (202) is fixedly installed with a shock-absorbing pad (15), which is a rubber layer.
7. A prefabricated teaching building corridor structure according to claim 2, characterized in that, The curtain wall (13) is made of lightweight ALC wall panels.