A skid-mounted delayed coking flue gas treatment device

By combining skid-mounted delayed coking flue gas treatment devices, the problem of direct emission pollution from delayed coking flue gas is solved, achieving rapid installation and efficient purification, ensuring that flue gas emissions meet standards, and is suitable for air pollution control in petrochemical delayed coking processes.

CN224949883UActive Publication Date: 2026-11-10SINOSTEEL TIANCHENG ENVIRONMENTAL PROTECTION SCI&TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522366006.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-07
Publication Date
2026-11-10
Estimated Expiration
2035-11-07

AI Technical Summary

Technical Problem

During delayed coking, the flue gas collected in the enclosure poses a direct emission pollution problem, affecting the environment and working conditions.

Method used

The skid-mounted delayed coking flue gas treatment device consists of multiple skids, including an equipment control room, dehumidification room, alkali absorption room, washing room, defogging room, and purification room. It is assembled through flanges and interfaces and performs heat exchange dehumidification, acid removal, water washing, demisting, and purification treatment in sequence.

Benefits of technology

It achieves rapid installation, low cost, and efficient flue gas purification, reduces the concentration of white fog inside enclosed greenhouses, ensures gas emissions meet standards, has strong applicability, and solves the problem of difficult-to-effective treatment of delayed coking flue gas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224949883U_ABST
    Figure CN224949883U_ABST
Patent Text Reader

Abstract

This utility model discloses a skid-mounted delayed coking flue gas treatment device. It is assembled from multiple skids; skid one is an equipment control room (1), including pump equipment and an intelligent control box (8); skid two is a dehumidification room (2), including heat exchange equipment and a dehumidifier; skid three is an alkaline absorption room (3), including an alkaline washing spray layer (16); skid four is a washing room (4), including a water washing spray layer (17); skid five is a demister (5), including a flat plate demister (18), a wire mesh demister (19), and a rinsing layer (20); skid six is ​​a purification room (6), including a fine desulfurizer (21) and a UV ultraviolet purifier (22). This device occupies a small area, is simple to install, has low cost, strong applicability, and a short installation cycle, effectively solving the problem of difficult-to-treat flue gas in the delayed coking industry.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of air pollution control technology for delayed coking in petrochemical industry, specifically relating to a skid-mounted delayed coking flue gas treatment device. Background Technology

[0002] Delayed coking is a petrochemical processing technology that generates harmful pollutants during the process. These pollutants need to be contained and collected, and then treated by environmental protection facilities to meet emission standards.

[0003] After the crude heavy oil undergoes a high-temperature reaction, some organic matter remains. Furthermore, during the subsequent coking process, volatile organic compounds such as acids, hydrocarbons, or other organic matter are emitted in an unorganized manner, causing serious environmental pollution and affecting human health.

[0004] The tail-end flue gas collected by the enclosure of the delayed coking shed poses a problem of direct emission pollution. By enclosing the coking area of ​​the delayed coking tower with a shed, the multi-component flue gas collected in the enclosure can be treated in a targeted and efficient manner, which can greatly improve the on-site working conditions. Utility Model Content

[0005] The purpose of this invention is to provide a skid-mounted delayed coking flue gas treatment device to solve the problem of direct discharge pollution of tail-end flue gas collected in the enclosure of delayed coking sheds.

[0006] The technical solution of this utility model is: a skid-mounted delayed coking flue gas treatment device, which is assembled from skids. The skids include at least one or more combinations of skid one, skid two, skid three, skid four, skid five, and skid six. Each skid is arranged in sequence and assembled through flanges and interfaces. The skid is firstly an equipment control room, including pump equipment and intelligent control box; The second skid is a dehumidification room, including heat exchange equipment and dehumidifier; The third skid is an alkaline solution absorption chamber, including an alkaline washing spray layer; The fourth skid is a washing room, including a water spray layer; The fifth skid is a defogging chamber, including a flat plate demister, a wire mesh demister, and a rinsing layer; The sixth skid is a clean room, including a fine desulfurizer and a UV purifier; The equipment control room controls skid 1, skid 2, skid 3, skid 4, skid 5, and skid 6.

[0007] According to an embodiment of this utility model, the pump equipment includes an alkaline washing pump, a water washing pump, and a rinsing pump; the outlet of the alkaline washing pump is connected to the alkaline washing spray layer, and the inlet pipe is connected to the alkaline outlet pipe at the bottom of the alkaline absorption chamber, with an alkali replenishment port on the pipe; the outlet of the water washing pump is connected to the outlet pipe at the bottom of the washing chamber, with a water replenishment port on the pipe; the outlet of the rinsing pump is connected to the rinsing layer, and the inlet pipe is connected to the industrial water pipe in the plant area, with the outlet of the demister connected to a pipe that discharges into the ditch.

[0008] According to an embodiment of this utility model, the dehumidification chamber consists of a shell-and-tube heat exchanger, a coalescing dehumidifier, and a finned tube heat exchanger, arranged from top to bottom.

[0009] According to an embodiment of this utility model, each spray layer of the alkaline washing spray layer is a completely enclosed plate, with a spray pipe connected to the bottom of the plate. The spray pipe is connected to a spray head, and the flue gas rises and fully contacts the spray droplets, and then enters the next space through the unenclosed rising channel. The flue gas in the alkaline absorption chamber flows downward in an S-shape from top to bottom.

[0010] According to an embodiment of this utility model, each spray layer of the alkaline washing spray layer is a completely enclosed plate, with a spray pipe connected to the bottom of the plate. The spray pipe is connected to a spray head, and the flue gas rises and fully contacts the spray droplets, and then enters the next space through the unenclosed rising channel. The flue gas in the alkaline absorption chamber flows downward in an S-shape from top to bottom.

[0011] According to an embodiment of the present invention, the defoaming chamber includes two layers of flat plate demisters and one layer of wire mesh demister, with rinsing layers provided above and below the flat plate demisters and the wire mesh demisters.

[0012] According to an embodiment of this utility model, the packing of the fine desulfurizer is divided into two layers: an upper layer of activated carbon and a lower layer of metal oxide.

[0013] According to an embodiment of the present invention, the equipment control room is connected to the flue gas inlet; the purification room is connected to the flue gas outlet.

[0014] A skid-mounted delayed coking flue gas treatment method, characterized by the following steps: Step 1: The skid-mounted delayed coking flue gas treatment device is transported to the enclosed delayed coking shed area, placed on the civil engineering foundation and fixed. The skid blocks are selected according to the flue gas composition, concentration and emission requirements. The skid-mounted equipment is then arranged and assembled in sequence. Step 2: The flue gas inlet of the delayed coking flue gas treatment device is connected to the main flue of the delayed coking enclosure shed. The flue gas outlet is either directly discharged through the chimney or sent to the heating furnace for combustion and discharge according to different emission requirements. The outlet of the alkaline washing pump is connected to the alkaline washing spray layer, the water washing pump is connected to the water washing spray layer, and the flushing pump is connected to the flushing layer. After all pipeline connections are completed, the intelligent control box is connected to the equipment, valves, instruments, and cables, and the control system is in operation. Step 3: After the delayed coking flue gas treatment device is started, the flue gas enters the equipment control room, dehumidification room, alkali absorption room, washing room, defoaming room and purification room in sequence through the flue gas inlet and flue gas channel for flue gas treatment before being discharged.

[0015] This device consists of an equipment control room, a dehumidification room, an alkaline absorption room, a washing room, a defoaming room, and a purification room. The equipment control room controls all the modules in the control room to work together. Entering the latter five rooms is to more rationally treat the flue gas and sequentially realize the functions of heat exchange and dehumidification, acid removal, water washing, defoaming, and VOCs removal.

[0016] The beneficial technical effects of this utility model are: (1) The equipment is transported directly to the site and then skid-mounted as a whole; (2) The equipment has reserved relevant connection flanges and is equipped with quick interfaces, so the entire system has a short installation cycle and is easy to operate; (3) When some flue gas is circulated to the enclosed greenhouse, the dehumidification room plays a good role in reducing the white fog inside the enclosed greenhouse, which is conducive to visual operation and greatly shortens the time when the greenhouse is filled with water vapor in winter and the crane grab bucket cannot operate normally. (4) The high-efficiency purification room can effectively adsorb and remove VOCs gas, ensuring that the gas is discharged in compliance with standards; (5) Skid-mounted equipment can be selected to be used in single or multiple sets in parallel according to the amount of flue gas. Depending on whether flue gas needs to be circulated to the enclosed shed to eliminate white fog or whether VOCs concentration needs to be reduced, the appropriate skid-mounted equipment functional area can be selected independently to address the problem of flue gas emission pollution in a more targeted manner.

[0017] This utility model device is an integrated, mobile, skid-mounted unit. Its functional areas are modular, allowing for selection and assembly based on flue gas characteristics and emission requirements. This device has a small footprint, is simple to install, low-cost, highly adaptable, and has a short installation cycle, effectively solving the problem of ineffective flue gas treatment in the delayed coking industry. Attached Figure Description

[0018] Figure 1 This is a schematic diagram of a skid-mounted delayed coking flue gas treatment device.

[0019] Figure 2 This is a schematic diagram of the first skid-mounted delayed coking flue gas treatment device connected in parallel.

[0020] Figure 3 This is a schematic diagram of the second type of skid-mounted delayed coking flue gas treatment device connected in parallel.

[0021] Figure 4 This is a schematic diagram of the third type of skid-mounted delayed coking flue gas treatment device connected in parallel.

[0022] In the diagram: 1-Equipment control room, 2-Dehumidification room, 3-Alkali absorption room, 4-Washing room, 5-Demisting room, 6-High-efficiency purification room, 7-Flue gas inlet, 8-Intelligent control box, 9-Alkali washing pump, 10-Water washing pump, 11-Flushing pump, 12-Shell-tube heat exchanger, 13-Coalescing dehumidifier, 14-Finned tube heat exchanger, 15-Flue gas passage, 16-Alkali washing spray layer, 17-Water washing spray layer, 18-Flat plate demister, 19-Wire mesh demister, 20-Flushing layer, 21-Fine desulfurizer, 22-UV ultraviolet purifier, 23-Flue gas outlet. Detailed Implementation

[0023] The present invention device and method are described in detail below with reference to the accompanying drawings. Based on the technical solution of the present invention, specific implementation schemes are given.

[0024] A skid-mounted delayed coking flue gas treatment device is assembled from skids. The skids include at least one or more combinations of skid one, skid two, skid three, skid four, skid five, and skid six. Each skid is arranged in sequence and assembled through flanges and interfaces. The skid is firstly an equipment control room 1, including pump equipment and intelligent control box 8; The second skid is a dehumidification room 2, which includes heat exchange equipment and a dehumidifier; The third skid is the alkaline absorption chamber 3, which includes an alkaline washing spray layer 16; The fourth skid is a washing room 4, which includes a water washing spray layer 17; The skid five is a defogging chamber 5, which includes a flat plate demister 18, a wire mesh demister 19, and a rinsing layer 20. The skid six is ​​the purification room 6, which includes a fine desulfurizer 21 and a UV purifier 22; The equipment control room 1 controls skid 1, skid 2, skid 3, skid 4, skid 5, and skid 6.

[0025] The delayed coking flue gas treatment device is divided into six skids, namely equipment control room 1, dehumidification room 2, alkali absorption room 3, washing room 4, defoaming room 5, and purification room 6. The six skid sections can be selected according to the characteristics, composition, and emission requirements of the flue gas. For high flue gas volumes, multiple skid-mounted devices can be used in parallel.

[0026] The pump equipment includes an alkaline washing pump 9, a water washing pump 10, and a rinsing pump 11. The outlet of the alkaline washing pump 9 is connected to the alkaline washing spray layer 16, and its inlet pipe is connected to the alkaline outlet pipe at the bottom of the alkaline absorption chamber 3. The pipe has an alkali replenishment port, which is replenished by the plant's alkaline pipe. The outlet of the water washing pump 10 is connected to the bottom outlet pipe of the washing chamber 4, and the pipe has a water replenishment port, which is replenished by the plant's industrial pipe. The outlet of the rinsing pump 11 is connected to the rinsing layer 20, and its inlet pipe is connected to the plant's industrial water pipe. The outlet of the defoaming chamber 5 is connected to a pipe that discharges into the ditch.

[0027] The intelligent control box 8 is powered by the factory area and connects to relevant mechanical equipment, electrical equipment, control systems, instruments, etc., and performs real-time adjustment based on the system's operating status.

[0028] The dehumidification room 2 consists of a shell-and-tube heat exchanger 12, a coalescing dehumidifier 13, and a finned tube heat exchanger 14, arranged from top to bottom.

[0029] The shell-and-tube heat exchanger 12 utilizes the plant's circulating water pipes to exchange heat with the flue gas, lowering its temperature and causing water mist to condense and precipitate rapidly. When the flue gas carrying a large number of droplets enters the fiber layer filter element of the coalescing dehumidifier 13, surface tension and inertial collisions cause the tiny droplets to agglomerate and adsorb, forming larger droplets which are then separated by gravity and discharged into a drain or collector. Simultaneously, it also intercepts solid particles in the flue gas. After dehumidification, the flue gas passes through the finned tube heat exchanger 14, exchanging heat with other hot flue gas or steam provided by the plant. Once the temperature rises to a level similar to the flue gas inside the enclosed greenhouse, most of the flue gas is circulated back into the greenhouse, diluting the gas inside and reducing its humidity. This significantly reduces the generation of white mist inside the greenhouse, allowing for more controlled and orderly industrial production.

[0030] Each of the alkaline washing spray layers 16 is a fully enclosed plate, with spray pipes connected to the bottom of the plate and spray heads connected to the spray pipes. The flue gas rises and fully contacts the spray droplets, and then enters the next space through the unenclosed rising channel. In the alkaline absorption chamber 3, the flue gas flows downward in an S-shape from top to bottom.

[0031] Countercurrent contact has a higher relative flow rate, forming a concentration gradient, which enhances the absorption effect between gas and liquid, and effectively removes acidic substances from flue gas.

[0032] Each of the water washing spray layers 17 is a fully enclosed plate, with a spray pipe connected to the bottom of the plate. The spray pipe is connected to a spray head, and the flue gas is fully in contact with the spray droplets as it descends. Then, it enters the next space through an unenclosed descending channel. The flue gas in the water washing spray layer 17 flows down in an S-shape from top to bottom.

[0033] The pressure loss from downstream contact is relatively small, further removing acidic substances, droplets, and particulate matter, thus reducing corrosion and clogging in subsequent equipment.

[0034] The defogging room 5 includes two layers of flat plate demisters 18 and one layer of wire mesh demisters 19. The flat plate demisters 18 and the wire mesh demisters 19 are provided with rinsing layers 20 on both the top and bottom.

[0035] The flat plate demister 18 removes larger droplets by altering the gas flow direction and extending the gas path, causing droplets to gather, converge, and slide off. The wire mesh demister 19 intercepts smaller droplets in the airflow through its mesh structure. The droplets are captured by the mesh due to inertia, and due to surface tension, they gather into larger droplets and flow out through the edges of the mesh. The flushing layer 20 is connected to nozzles for periodic cleaning and maintenance of the demister surface.

[0036] The packing of the fine desulfurizer 21 is divided into two layers: an upper layer of activated carbon and a lower layer of metal oxide.

[0037] The activated carbon layer removes acidic substances through physical adsorption and chemical absorption, and can also absorb organic hydrocarbons. The metal oxide layer (metal oxides such as zinc oxide or iron oxide) can further reduce the concentration of sulfides. The UV purifier 22 generates ozone through high-energy ultraviolet light, which then breaks down the molecular chains of high-molecular malodorous compounds and degrades them into small molecular compounds, thereby effectively reducing VOCs in flue gas.

[0038] The equipment control room 1 is connected to the flue gas inlet 7; the purification room 6 is connected to the flue gas outlet 23.

[0039] A skid-mounted delayed coking flue gas treatment method includes the following steps: Step 1: The skid-mounted delayed coking flue gas treatment device is transported to the enclosed delayed coking shed area, placed on the civil engineering foundation and fixed. The skid blocks are selected according to the flue gas composition, concentration and emission requirements. The skid-mounted equipment is then arranged and assembled in sequence. Step 2: The flue gas inlet 7 of the delayed coking flue gas treatment device is connected to the main flue of the delayed coking enclosure shed. The flue gas outlet 23 is either directly discharged through the chimney or sent to the heating furnace for combustion and discharge according to different emission requirements. The outlet of the alkaline washing pump 9 is connected to the alkaline washing spray layer 16, the water washing pump 10 is connected to the water washing spray layer 17, and the flushing pump is connected to the flushing layer 20. After all pipeline connections are completed, the intelligent control box 8 is connected to the equipment, valves, instruments, and cables, and the control system is in operation. Step 3: After the delayed coking flue gas treatment device is started, the flue gas enters the equipment control room 1, dehumidification room 2, alkali absorption room 3, washing room 4, defoaming room 5, and purification room 6 in sequence through the flue gas inlet 7 and flue gas channel for flue gas treatment before being discharged.

[0040] Example 1: As Figure 1As shown, the delayed coking flue gas treatment unit transported to the site is fixed on the foundation. Flue gas inlet 7 is connected to the outlet flue of the delayed coking enclosure shed. Flue gas outlet 23 is connected to the heating furnace inlet or chimney via the flue. Alkali washing pump 9's outlet is connected to the alkali washing spray layer 16, and its inlet pipe is connected to the bottom alkali outlet pipe of the alkali absorption chamber. The pipe has an alkali replenishment port, replenished by the plant's alkali pipeline. Water washing pump 10's outlet is connected to the bottom outlet pipe of the washing room 4, and its water replenishment port, replenished by the plant's industrial pipeline. Flushing pump 11's outlet is connected to the flushing layer 20, and its inlet pipe is connected to the plant's industrial water pipeline. The outlet of the demister 5 is connected to a pipeline discharging into a ditch. All equipment interfaces, power supplies, and media energy pipelines, cables, instruments, etc., provided by the plant are fully connected. The equipment parameters and components are adjusted according to the characteristics of the flue gas. The flue gas from the enclosed greenhouse enters through the flue gas inlet 7 of the skid-mounted device, and undergoes heat exchange and dehumidification in the dehumidification chamber 2. Most of the flue gas is circulated back to the enclosed greenhouse, while a portion of the flue gas enters the alkaline absorption chamber 3 and flows upward to react with the sprayed alkaline solution in a countercurrent manner. Then, it enters the washing chamber through the flue gas channel 15, flows downward in the washing chamber 4, and comes into contact with the sprayed process water in a cocurrent manner. After passing through the flat plate demister 18 and the wire mesh demister 19 for multi-stage demisting, it enters the high-efficiency purification chamber 6, where it undergoes adsorption by the activated carbon layer and reaction by the metal oxide layer. It is then treated by the UV ultraviolet purifier 22 and finally discharged through the flue gas outlet 23.

[0041] Example 2: If the amount of flue gas produced by delayed coking is large, multiple sets of delayed coking flue gas treatment devices can be used in parallel, such as... Figure 2 As shown, the delayed coking enclosure shed outlet flue is divided into multiple branches that connect to the unit flue gas inlet 7. After treatment, the unit flue gas outlet merges back into the main flue pipe and can be directly discharged into the chimney.

[0042] Example 3: If the amount of flue gas generated by delayed coking is large and VOCs treatment is not required within the device, and the purified flue gas directly enters the heating furnace, then multiple sets of delayed coking flue gas treatment devices can be used in parallel after removing the high-efficiency purification room, such as... Figure 3 As shown, the delayed coking enclosure shed outlet flue is divided into multiple branches that connect to the unit flue gas inlet 7. After treatment, the unit flue gas outlet 23 merges back into the main flue pipe and enters the subsequent heating furnace for treatment and discharge.

[0043] Example 4: If the amount of flue gas generated by delayed coking is large, and the flue gas is not recirculated back to the enclosed shed, and equipment control room 1 controls multiple skid-mounted devices with a single unit, the multiple delayed coking flue gas treatment devices can be used in parallel after removing dehumidification room 2 and part of equipment control room 1, such as... Figure 4 As shown, the delayed coking enclosure shed outlet flue is divided into multiple branches that connect to the unit flue gas inlet 7. After treatment, the unit flue gas outlet 23 merges back into the main flue pipe, which can be directly discharged into the chimney or discharged into the subsequent heating furnace.

[0044] In summary, these specific embodiments are all different combinations of methods implemented under the design of this utility model. However, the scope of protection of this utility model patent is not limited thereto. Any combination, modification and adjustment of the design content by engineers skilled in the art should be included within the scope of protection of this utility model patent.

Claims

1. A skid-mounted delayed coking flue gas treatment device, assembled from skids, characterized in that... The skid block includes at least one or more combinations of skid block one, skid block two, skid block three, skid block four, skid block five, and skid block six. Each skid block is arranged in sequence and assembled through flanges and interfaces. The skid is firstly an equipment control room (1), including pump equipment and intelligent control box (8). The second skid is a dehumidification room (2), which includes heat exchange equipment and a dehumidifier; The third skid is an alkaline absorption chamber (3), which includes an alkaline washing spray layer (16). The fourth skid is a washing room (4), including a water washing spray layer (17). The skid five is a defogging chamber (5), which includes a flat plate demister (18), a wire mesh demister (19), and a rinsing layer (20). The skid six is ​​a clean room (6), including a fine desulfurizer (21) and a UV purifier (22). The equipment control room (1) controls pry bar 1, pry bar 2, pry bar 3, pry bar 4, pry bar 5, and pry bar 6.

2. The skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: The pump equipment includes an alkaline washing pump (9), a water washing pump (10), and a flushing pump (11). The outlet of the alkaline washing pump (9) is connected to the alkaline washing spray layer (16), and the inlet pipe is connected to the alkaline outlet pipe at the bottom of the alkaline absorption room (3). There is an alkali replenishment port on the pipe. The outlet of the water washing pump (10) is connected to the outlet pipe at the bottom of the washing room (4). There is a water replenishment port on the pipe. The outlet of the flushing pump (11) is connected to the flushing layer (20), and the inlet pipe is connected to the industrial water pipe in the plant area. The outlet of the defoaming room (5) is connected to the pipe that discharges into the ditch.

3. The skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: The dehumidification room (2) consists of a shell-and-tube heat exchanger (12), a coalescing dehumidifier (13), and a finned tube heat exchanger (14) from top to bottom.

4. The skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: Each layer of the alkaline washing spray layer (16) is a fully enclosed plate with a spray pipe fixed below the plate. The spray pipe is connected to the spray head, and the flue gas is fully in contact with the spray droplets as it rises. Then, it enters the next skid through the unenclosed rising channel. In the alkaline absorption chamber (3), the flue gas flows down in an S-shape from top to bottom.

5. A skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: Each spray layer of the water washing spray layer (17) is a whole plate closed, with spray pipes fixed below the plate. The spray pipes are connected to spray heads, and the flue gas is fully in contact with the spray droplets as it descends. Then, it enters the next skid through the unclosed descending channel. The flue gas in the water washing spray layer (17) flows down in an S-shape from top to bottom.

6. A skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: The demisting chamber (5) includes two layers of flat plate demisters (18) and one layer of wire mesh demisters (19). The flat plate demisters (18) and the wire mesh demisters (19) are provided with rinsing layers (20) on the top and bottom.

7. A skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that: The packing of the fine desulfurizer (21) is divided into two layers: the upper layer is an activated carbon layer and the lower layer is a metal oxide layer.

8. A skid-mounted delayed coking flue gas treatment device according to claim 1, characterized in that... The equipment control room (1) is connected to the flue gas inlet (7); the purification room (6) is connected to the flue gas outlet (23).