An adjustable positioning device for the installation of steel structure bridge segments.
By designing an adjustable positioning device, using bolts and nuts to transmit push and pull forces, and combining positioning bearings and limit blocks, precise positioning of steel structure bridge segments is achieved, solving the problems of low positioning accuracy and low construction efficiency in existing technologies, and improving construction efficiency and accuracy.
Patent Information
- Application Number
- CN202522334674.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-04
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-11-04
AI Technical Summary
Existing technologies for installing steel bridge segments suffer from problems such as difficulty in controlling positioning accuracy, high demand for construction personnel, and long placement time.
An adjustable positioning device is adopted, including a positioning sleeve and a telescopic rod. The horizontal pushing and pulling force is transmitted through the cooperation of bolts and nuts to adjust the sliding distance. The positioning bearing restricts the displacement of the bolt, and the limit block and end plate restrict the displacement of the pin shaft to achieve precise positioning.
It improves the accuracy and efficiency of steel structure bridge segment installation, reduces the need for construction personnel, shortens the placement time, and protects the steel structure surface from damage.
Smart Images

Figure CN224954976U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of building steel structure construction technology, and relates to an adjustable positioning device for the installation of steel structure bridge segments. Background Technology
[0002] Steel structure construction offers significant advantages, including reduced labor, shorter construction periods, lower resource consumption, and reduced construction waste and dust, thus improving production efficiency, construction safety, and project quality. However, steel structure construction also places higher demands on on-site construction precision. For example, the accuracy of positioning during the installation of steel structure bridges is a crucial factor in ensuring the overall quality and schedule of the steel structure project.
[0003] Due to errors in the construction of the concrete box girder, the spacing between the concrete box girder and the first segment of the steel bridge is inconsistent. Currently, the positioning of the first segment of the steel bridge is as follows: first, measurement control points are marked on the first segment of the steel bridge; during the positioning process, a total station is used to measure the coordinates of the control points; fine adjustments are made using hand-operated hoists for dragging and jacks for pushing into place. The problems with this method are: the high frequency of measurement and observation leads to excessively long positioning time; at least three people are needed for fine adjustments at one end of the steel bridge segment, two people are needed for dragging with hand-operated hoists on both sides, and one person is needed for pushing with jacks, resulting in a large number of construction personnel; the long positioning time is due to the fact that the installation accuracy of the first segment of the steel bridge changes constantly due to environmental factors during its lowering, requiring construction personnel to repeatedly fine-tune the positioning accuracy of the first segment of the steel bridge. Utility Model Content
[0004] To address the aforementioned problems in the existing technology, this application provides an adjustable positioning device for the installation of steel structure bridge segments.
[0005] The technical solution of this utility model is as follows: An adjustable positioning device for installing steel structure bridge segments includes a positioning sleeve and a telescopic rod. The positioning sleeve includes an end plate, the left side of which is fixed to the end of the concrete box girder of the approach bridge, and the right side of which is rigidly connected to the sleeve. The upper panel of the sleeve is provided with a sliding groove to guide the sliding of the telescopic rod. A fixed support is provided on the top left side of the sleeve. The support support has a through hole for the bolt shank to pass through freely and is provided on the top right side of the sleeve. A positioning bearing assembled on the fixed support is sleeved on the left side of the bolt. A limiting block limits the horizontal movement of the telescopic rod inside the positioning sleeve. The telescopic rod includes a nut, the right threaded section of the bolt is assembled on the nut, and the bottom of the nut is connected to a sliding rod through a connecting rod. The sliding rod performs unidirectional horizontal displacement inside the sleeve. The top of the sliding rod is provided with a head plate and a pin hole for connecting a pin shaft. The head plate restricts the radial displacement of the pin shaft. A rolling bearing is installed with an interference fit in the middle position of the pin shaft, and the outer cylinder of the rolling bearing contacts the end of the steel structure bridge segment.
[0006] In a preferred embodiment of this utility model, the left side of the end plate is fixed to the end of the approach bridge concrete box girder through a horizontal elongated hole and a vertical elongated hole.
[0007] In a preferred embodiment of this utility model, the through hole through which the bolt shank freely passes is a round hole.
[0008] In a preferred embodiment of this utility model, the bolt is a hexagonal head bolt.
[0009] In a preferred embodiment of this utility model, the transverse elongated hole and the vertical elongated hole are fixed to the end of the approach bridge concrete box girder by chemical anchors or expansion bolts.
[0010] In a preferred embodiment of this utility model, the number of end plates and pin holes are both two sets.
[0011] The beneficial effects of this utility model are: This utility model discloses an adjustable positioning device for the installation of steel structure bridge segments. Tightening the bolt transmits the horizontal push-pull force between the bolt and nut threads, which is then transmitted to the sliding rod to adjust the sliding distance and eliminate length deviation. The positioning bearing restricts the horizontal and radial displacement of the bolt, allowing it to rotate only in a fixed position. The limit stop restricts the horizontal movement of the telescopic rod inside the positioning sleeve. The provided pin hole and end plate restrict the radial displacement of the pin. The interference fit causes the outer cylinder of the rolling bearing to rotate relative to the pin. The outer cylinder of the rolling bearing rolls and slides on the contact surface with the end of the steel structure bridge segment, preventing damage to the surface paint of the steel structure. This utility model saves labor time, improves construction efficiency, enhances installation accuracy, and is easy to operate. Attached Figure Description
[0012] Figure 1 This is a schematic diagram illustrating an adjustable positioning device for installing steel structure bridge segments according to the present invention. Figure 2 This is an assembly drawing of the present utility model; Figure 3 Assembly drawing for the positioning sleeve; Figure 4 Exploded view of the positioning sleeve; Figure 5 This is an assembly drawing of the telescopic pole; Figure 6 This is an exploded view of the telescopic pole.
[0013] In the diagram: A - approach bridge concrete box girder; B - positioning sleeve; C - telescopic rod; D - steel structure bridge segment; 1 - end plate; 2 - sleeve; 3 - fixed support; 4 - bolt; 5 - positioning bearing; 6 - support support; 7 - limit block; 8 - nut; 9 - connecting rod; 10 - end plate; 11 - sliding rod; 12 - pin; 13 - rolling bearing. Detailed Implementation
[0014] The present invention will now be described in detail with reference to the accompanying drawings and embodiments. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0015] like Figure 1-6As shown, an adjustable positioning device for installing steel structure bridge segments includes a positioning sleeve B and a telescopic rod C. The positioning sleeve B includes an end plate 1, a sleeve 2, a fixed support 3, a bolt 4, a positioning bearing 5, a support support 6, and a limiting block 7. The left side of the end plate 1 is fixed to the end of the concrete box girder A of the approach bridge, and the right side of the end plate 1 is rigidly connected to the sleeve 2. The upper panel of the sleeve 2 is provided with a sliding groove, which guides the sliding of the telescopic rod C. The fixed support 3 is located on the top left side of the sleeve 2. The support support 6 has a through hole for the bolt 4 to pass through freely and is located on the top right side of the sleeve 2. The positioning bearing 5, assembled on the fixed support 3, is sleeved on the left side of the bolt 4. The limiting block 7 limits the horizontal movement of the telescopic rod C inside the positioning sleeve B. The telescopic rod C includes a nut 8, a connecting rod 9, a head plate 10, a sliding rod 11, a pin 12, and a rolling bearing 13. The right threaded section of the bolt 4 is assembled to the nut 8. The bottom of the nut 8 is connected to the sliding rod 11 through the connecting rod 9. The sliding rod 11 makes a unidirectional horizontal displacement inside the sleeve 2. The top of the sliding rod 11 is provided with a head plate 10 and a pin hole for connecting the pin 12. The head plate 10 restricts the radial displacement of the pin 12. The rolling bearing 13 is installed in the middle position of the pin 12 with an interference fit. The outer cylinder of the rolling bearing 13 is in contact with the end of the steel structure bridge segment D.
[0016] During operation, the hoisting and installation of the first steel bridge segment proceeds as follows: First, the deviation between the approach bridge concrete box girder A and the axis position at the installation location of the first steel bridge segment is measured. Then, the actual gap between the approach bridge concrete box girder A and the steel bridge segment D is calculated based on the theoretical values in the design drawings. The extension length of the sliding rod 11 is adjusted by turning bolt 4 to ensure that the total length between the side of the end plate 1 and the outer side of the outer cylinder of the rolling bearing 13 matches the actual gap value. The adjustable positioning device for the steel bridge segment is fixed to the end of the approach bridge concrete box girder A using chemical anchors or expansion bolts. After fixing, the total length of the adjustable positioning device and the actual gap between the approach bridge concrete box girder A and the steel bridge segment D are checked for consistency. If there is a deviation, it is adjusted by turning bolt 4. When the steel bridge segment D is hoisted into place, the end of the steel bridge segment D is tightly fitted with the outer cylinder of the rolling bearing 13, thereby limiting the unidirectional horizontal displacement of the steel bridge segment D during its slow descent, achieving the purpose of controlling the installation accuracy of the steel bridge. After the steel structure bridge segment D is in place, the telescopic rod C is retracted by turning the screw 4, and the adjustable positioning device for the steel structure bridge segment is removed.
[0017] This utility model discloses an adjustable positioning device for the installation of steel structure bridge segments. Tightening the bolt transmits the horizontal push-pull force between the bolt and nut threads, which is then transmitted to the sliding rod to adjust the sliding distance and eliminate length deviation. The positioning bearing limits the horizontal and radial displacement of the bolt, the limit block limits the horizontal movement of the telescopic rod inside the positioning sleeve, the pin hole and the end plate limit the radial displacement of the pin, and the interference fit causes the outer cylinder of the rolling bearing to rotate relative to the pin. The outer cylinder of the rolling bearing rolls and slides on the contact surface with the end of the steel structure bridge segment, avoiding damage to the surface paint of the steel structure, thereby saving time, improving construction efficiency, and enhancing installation accuracy.
[0018] Although the embodiments of this utility model have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for this utility model. For those skilled in the art, and for those of ordinary skill in the art, various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of this utility model. Therefore, without departing from the general concept defined by the claims and their equivalents, this utility model is not limited to the specific details.
Claims
1. An adjustable positioning device for installing steel structure bridge segments, characterized in that: The system includes a positioning sleeve (B) and a telescopic rod (C). The positioning sleeve (B) includes an end plate (1). The left side of the end plate (1) is fixed to the end of the concrete box girder (A) of the approach bridge. The right side of the end plate (1) is rigidly connected to the sleeve (2). The upper panel of the sleeve (2) is provided with a sliding groove, which guides the sliding of the telescopic rod (C). A fixed support (3) is provided on the top left side of the sleeve (2). A support (6) is provided with a through hole that allows the bolt (4) to pass freely through and is provided on the top right side of the sleeve (2). The positioning bearing (5) assembled on the fixed support (3) is sleeved on the left side of the bolt (4). A limiting block (7) restricts the telescopic rod (C) in the positioning sleeve. The horizontal movement inside the cylinder (B) is limited. The telescopic rod (C) includes a nut (8). The right threaded section of the bolt (4) is fitted to the nut (8). The bottom of the nut (8) is connected to the sliding rod (11) via a connecting rod (9). The sliding rod (11) makes a unidirectional horizontal displacement inside the sleeve (2). The top of the sliding rod (11) is provided with a head plate (10) and a pin hole for connecting the pin (12). The head plate (10) restricts the radial displacement of the pin (12). A rolling bearing (13) is installed in the middle position of the pin (12) with an interference fit. The outer cylinder of the rolling bearing (13) contacts the end of the steel structure bridge segment (D).
2. The adjustable positioning device for installing steel structure bridge segments according to claim 1, characterized in that: The left side of the end plate (1) is attached and fixed to the end of the approach bridge concrete box girder (A) through a transverse elongated hole and a vertical elongated hole.
3. The adjustable positioning device for installing steel structure bridge segments according to claim 1, characterized in that: The through hole through which the bolt (4) rod can freely pass is a round hole.
4. The adjustable positioning device for installing steel structure bridge segments according to claim 1, characterized in that: The bolt (4) is a hexagonal head bolt.
5. The adjustable positioning device for installing steel structure bridge segments according to claim 2, characterized in that: The transverse and vertical elongated holes are fixed to the ends of the approach bridge concrete box girder (A) by chemical anchors or expansion bolts.