A condensation preheater for coated asphalt
By using a combination of a semi-circular fixed shell and an insulation pad at the pipe joint of the preheater, the problem of heat loss at the connection point is solved, achieving more efficient heat energy utilization and reducing energy consumption.
Patent Information
- Application Number
- CN202522548687.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-01
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-12-01
AI Technical Summary
Existing preheating equipment suffers from heat loss at connection points, resulting in low thermal efficiency and increased energy consumption.
The design employs a condenser preheater, which enhances the insulation effect of the connection points by using a combination of a semi-circular fixed shell and an insulation pad at the pipe joint, and adds an insulation cover to the outer wall of the shell to reduce heat loss.
It improves the efficiency of thermal energy utilization, reduces energy consumption, and enhances the sealing and stability of the connection parts.
Smart Images

Figure CN224957263U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of preheating equipment technology, specifically to a condensation preheater applied to coated asphalt. Background Technology
[0002] In the preparation of lithium-ion secondary batteries, natural graphite is the main source of anode materials due to its high charge / discharge capacity, good charge / discharge platform, wide availability, and low cost. However, because natural graphite has a high degree of graphitization, the crystal structure and other physicochemical properties between the edges and bottom surfaces of its microcrystals differ significantly. The decomposition reaction with the electrolyte mainly occurs at the edges of the microcrystals, resulting in poor compactness of the purified film. During charging, co-intercalation of solvated lithium ions easily occurs, causing the graphite layer to expand and collapse, increasing the irreversible capacity. To improve the electrochemical performance of natural graphite materials, various methods are used to modify and surface-modify it. Currently, the main method is to coat the surface of natural graphite with pitch.
[0003] The preheater is a crucial heat exchange device in asphalt coating production units. Currently, existing preheating equipment typically insulates the circulating pipelines to effectively reduce heat loss during transmission and maintain stable temperatures. However, due to their unique structure, pipeline connections contain gaps and interfaces. Traditional integral pipeline insulation methods struggle to fully cover and tightly seal these areas, allowing heat to escape rapidly through these gaps. This not only reduces thermal efficiency but also increases energy consumption.
[0004] To address the aforementioned issues, we propose a condensation preheater for coated asphalt. Utility Model Content
[0005] The purpose of this invention is to provide a condenser preheater for coated asphalt to address the aforementioned shortcomings in the technology.
[0006] To achieve the above objectives, this utility model provides the following technical solution: a condenser preheater for asphalt coating, comprising a preheater shell, with heat medium circulation pipes connected to both ends of the preheater shell; a first pipe joint is fixedly welded to the outer wall of one end of each of the two heat medium circulation pipes; a matching second pipe joint is provided on the outer wall of one corresponding side of each of the two first pipe joints; a mating ring is fixedly provided on the outer wall of one corresponding end of each of the first and second pipe joints; a first semi-arc fixing shell and a second semi-arc mating shell are respectively sleeved on the outer walls of the first and second pipe joints; a semi-arc groove is opened at the center of each of the first and second semi-arc fixing shells; the mating ring is engaged inside the semi-arc groove; and a heat insulation pad is adhered to the inner wall of each of the first and second semi-arc fixing shells.
[0007] Preferably, a first fixing plate is fixedly provided on both outer walls of the first semi-arc fixed shell, and a positioning hole is opened on the outer wall of the first fixing plate. A second fixing plate is fixedly provided on both outer walls of the second semi-arc docking shell, and an internal thread hole is opened on the outer wall of the second fixing plate. A bolt is inserted into the inner wall of the positioning hole, and the bolt is screwed into the inner wall of the internal thread hole.
[0008] Preferably, the inner wall of the first pipe connector at one end relative to the second pipe connector has an annular inner groove, and the second pipe connector is fixedly provided with an inner extension tube relative to the outer wall of the first pipe connector. The outer wall of the inner extension tube is slidably connected to the inner wall of the annular inner groove.
[0009] Preferably, the second pipe connector has a slot on the outer wall of one end relative to the first pipe connector, and the outer wall of the first pipe connector relative to the second pipe connector is fixedly provided with an outer extension tube. The outer extension tube is inserted into the inner wall of the slot, and the inner wall of the outer extension tube is slidably connected to the outer wall of the inner extension tube.
[0010] Preferably, the outer wall of the preheater shell is further fitted with two semi-arc-shaped heat insulation covers. The outer walls of the two sides of the heat insulation covers are fixed with fixing plates. The outer walls of the fixing plates are provided with fixing holes, and the inner walls of the fixing holes are equipped with matching fixing bolts.
[0011] Preferably, the outer walls on both sides of the preheater shell are also connected to inlet and outlet liquid pipes.
[0012] The technical effects and advantages provided by this utility model in the above technical solution are as follows: By welding the second pipe joint to the external medium pipeline, then connecting the first pipe joint to the second pipe joint, and then connecting the first semi-circular fixing shell to the second semi-circular one, the connecting ring is secured inside the semi-circular groove. The insulation pad is securely wrapped around the connection part. The insulation pad can play a good role in heat insulation, reducing heat loss to the outside through the connection part, thereby improving the utilization efficiency of heat energy and reducing energy consumption. Attached Figure Description
[0013] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this utility model. For those skilled in the art, other drawings can be obtained based on these drawings.
[0014] Figure 1 This is a three-dimensional structural diagram of the present invention; Figure 2 This is a schematic diagram of the first pipe connector structure of this utility model; Figure 3 This is a schematic cross-sectional view of the first pipe connector of this utility model; Figure 4 This is a schematic diagram of the second pipe connector structure of this utility model; Figure 5 This is a schematic cross-sectional view of the second pipe connector of this utility model; Figure 6 This is a schematic diagram of the first semi-circular fixed shell structure of this utility model; Figure 7 This is a schematic diagram of the second semi-circular docking shell structure of this utility model.
[0015] Explanation of reference numerals in the attached figures: 1. Preheater shell, 2. Inlet and outlet liquid pipes, 3. Heat medium circulation pipe, 4. First pipe joint, 5. Second pipe joint, 6. Docking ring, 7. Annular inner groove, 8. Inner extension tube, 9. Slot, 10. Outer extension tube, 11. First semi-circular fixing shell, 12. Second semi-circular docking shell, 13. Semi-circular groove, 14. Insulation pad, 15. First fixing plate, 16. Positioning hole, 17. Second fixing plate, 18. Internal threaded hole, 19. Insulation cover, 20. Fixing plate. Detailed Implementation
[0016] The following drawings will disclose several embodiments of this utility model. For clarity, many physical details will be described in the following description. However, it should be understood that these physical details should not be used to limit this utility model. That is, in some embodiments of this utility model, these physical details are not essential. In addition, for the sake of simplicity, some conventional structures and components will be shown in the drawings in a simple schematic manner.
[0017] Furthermore, in this utility model, the use of terms such as "first" and "second" is for descriptive purposes only and does not specifically refer to any order or sequence, nor is it intended to limit the utility model. They are merely used to distinguish components or operations described with the same technical terms and should not be construed as indicating or implying their relative importance or implicitly specifying the number of indicated technical features. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of those features. Additionally, the technical solutions of various embodiments can be combined with each other, but only if they are feasible for those skilled in the art. If a combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed by this utility model. Example 1
[0018] Refer to the instruction manual appendix Figure 1-7 A condenser preheater for coating asphalt includes a preheater shell 1, with heat medium circulation pipes 3 connected to both ends of the preheater shell 1. A first pipe joint 4 is fixedly provided on the outer wall of one end of the two heat medium circulation pipes 3 by welding. A matching second pipe joint 5 is provided on the outer wall of the corresponding side of the two first pipe joints 4. The second pipe joint 5 is used for fixed connection with external pipes. Example 2
[0019] Based on Embodiment 1, a docking ring 6 is fixedly provided on the outer wall of one end corresponding to the first pipe joint 4 and the second pipe joint 5. The outer walls of the first pipe joint 4 and the second pipe joint 5 are respectively fitted with a first semi-arc fixed shell 11 and a second semi-arc docking shell 12. A semi-arc groove 13 is opened at the center of the first semi-arc fixed shell 11 and the second semi-arc docking shell 12. The docking ring 6 is engaged inside the semi-arc groove 13. The inner walls of the first semi-arc fixed shell 11 and the second semi-arc docking shell 12 are both bonded with heat insulation pads 14, which can effectively reduce heat loss from the connection part. Example 3
[0020] Based on Embodiment 1, a first fixing plate 15 is fixedly provided on both outer walls of the first semi-arc fixed shell 11. The outer wall of the first fixing plate 15 has a positioning hole 16. A second fixing plate 17 is fixedly provided on both outer walls of the second semi-arc docking shell 12. The outer wall of the second fixing plate 17 has an internal thread hole 18. A bolt is inserted into the positioning hole 16 and screwed onto the inner wall of the internal thread hole 18, thereby connecting the first semi-arc fixed shell 11 and the second semi-arc docking shell 12. Example 4
[0021] Based on Embodiment 1, in order to enhance the sealing and stability of the connection between the first pipe connector 4 and the second pipe connector 5, an annular inner groove 7 is formed on the inner wall of one end of the first pipe connector 4 relative to the second pipe connector 5, and an inner extension tube 8 is fixedly provided on the outer wall of the second pipe connector 5 relative to the first pipe connector 4. The outer wall of the inner extension tube 8 is slidably connected to the inner wall of the annular inner groove 7. A slot 9 is formed on the outer wall of one end of the second pipe connector 5 relative to the first pipe connector 4, and an outer extension tube 10 is fixedly provided on the outer wall of one end of the first pipe connector 4 relative to the second pipe connector 5. The outer extension tube 10 is inserted into the inner wall of the slot 9, and the inner wall of the outer extension tube 10 is slidably connected to the outer wall of the inner extension tube 8. Through this double insertion structure, the connection between the first pipe connector 4 and the second pipe connector 5 is made tighter. Example 5
[0022] Based on Embodiment 1, in addition, two semi-arc-shaped heat insulation covers 19 are fitted onto the outer wall of the preheater shell 1. Fixing plates 20 are fixedly provided on the outer walls of both sides of the heat insulation cover 19. Fixing holes are opened on the outer walls of the fixing plates 20. By inserting the fixing bolts into the fixing holes, the two heat insulation covers 19 can be fixed to the outer wall of the preheater shell 1 to insulate the preheater shell 1.
[0023] Working principle of this utility model: Refer to the instruction manual appendix Figure 1-7 When using this utility model, the heat medium is first injected into the preheater shell 1 through the inlet / outlet liquid pipe 2. After circulating in the preheater shell 1, the heat medium flows out through the heat medium circulation pipe 3. When it is necessary to connect the heat medium circulation pipe 3 to the external pipe, the second pipe connector 5 is welded to the external pipe and connected to the first pipe connector 4 at one end of the heat medium circulation pipe 3. At this time, the inner extension tube 8 on the second pipe connector 5 slides into the annular inner groove 7 of the first pipe connector 4, and at the same time, the outer extension tube 10 on the first pipe connector 4 is inserted into the slot 9 of the second pipe connector 5.
[0024] Next, the first semi-circular fixing shell 11 and the second semi-circular docking shell 12 are fitted over the connection between the first pipe joint 4 and the second pipe joint 5, so that the docking ring 6 is inserted into the semi-circular groove 13. Then, the bolt is passed through the positioning hole 16 of the first fixing plate 15 and screwed into the internal thread hole 18 of the second fixing plate 17 to fix the first semi-circular fixing shell 11 and the second semi-circular docking shell 12. The heat insulation pad 14 on its inner wall can reduce heat loss at the connection. At the same time, the heat insulation cover 19 on the outer wall of the preheater shell 1 is fixed to the fixing hole of the fixing plate 20 by the fixing bolt to insulate the preheater shell 1 and effectively reduce the heat loss when the heat medium flows.
[0025] The foregoing description only illustrates certain exemplary embodiments of the present invention. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of the present invention. Therefore, the above drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of the present invention.
Claims
1. A condensation preheater for coated asphalt, comprising a preheater shell (1), characterized in that: The preheater shell (1) is connected to two ends of a heat medium circulation pipe (3). The outer wall of one end of the two heat medium circulation pipes (3) is fixed with a first pipe joint (4) by welding. The outer wall of the two first pipe joints (4) is equipped with a matching second pipe joint (5). The outer wall of the first pipe joint (4) and the second pipe joint (5) is fixed with a docking ring (6). The outer walls of the first pipe joint (4) and the second pipe joint (5) are respectively fitted with a first semi-arc fixed shell (11) and a second semi-arc docking shell (12). The center of the first semi-arc fixed shell (11) and the second semi-arc docking shell (12) are both opened with a semi-arc groove (13). The docking ring (6) is engaged in the interior of the semi-arc groove (13). The inner walls of the first semi-arc fixed shell (11) and the second semi-arc docking shell (12) are both bonded with a heat insulation pad (14).
2. The condenser preheater for coated asphalt according to claim 1, characterized in that: The first semi-arc fixed shell (11) has a first fixed plate (15) fixed on both outer walls. The first fixed plate (15) has a positioning hole (16) on its outer wall. The second semi-arc docking shell (12) has a second fixed plate (17) fixed on both outer walls. The second fixed plate (17) has an internal thread hole (18) on its outer wall. The positioning hole (16) has a bolt inserted into its inner wall, and the bolt is screwed into the inner wall of the internal thread hole (18).
3. A condenser preheater for coated asphalt according to claim 1, characterized in that: The first pipe connector (4) has an annular inner groove (7) on the inner wall of one end relative to the second pipe connector (5). The second pipe connector (5) is fixedly provided with an inner extension tube (8) relative to the outer wall of the first pipe connector (4). The outer wall of the inner extension tube (8) is slidably connected to the inner wall of the annular inner groove (7).
4. A condenser preheater for coated asphalt according to claim 3, characterized in that: The second pipe connector (5) has a slot (9) on one end of its outer wall relative to the first pipe connector (4). The first pipe connector (4) has an outer extension tube (10) fixedly provided on one end of its outer wall relative to the second pipe connector (5). The outer extension tube (10) is inserted into the inner wall of the slot (9). The inner wall of the outer extension tube (10) is slidably connected to the outer wall of the inner extension tube (8).
5. A condenser preheater for coated asphalt according to claim 1, characterized in that: The outer wall of the preheater shell (1) is also fitted with two heat insulation covers (19) with a semi-arc structure. The outer walls of the heat insulation covers (19) are fixed with fixing plates (20). The outer walls of the fixing plates (20) are opened with fixing holes, and the inner walls of the fixing holes are equipped with matching fixing bolts.
6. A condenser preheater for coated asphalt according to claim 1, characterized in that: The two outer walls of the preheater shell (1) are also connected to inlet and outlet liquid pipes (2).