A multi-stage double-row bypass heating system for a reheat unit
The multi-stage double-row bypass heating system solves the problems of complexity and high investment in the bypass heating system of the secondary reheat unit, improves flexibility and reliability, reduces power generation loss, and ensures the safety and economy of the unit operation.
Patent Information
- Application Number
- CN202522412831.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-13
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-11-13
AI Technical Summary
Existing double reheat unit bypass heating technology suffers from system complexity, high initial investment, large workload for operation and commissioning, and poor adaptability to changing parameters, leading to difficulties in unit operation, especially in the field of residential heating.
A multi-stage double-row bypass heating system is adopted, which achieves flexible adjustment of the thermal system and flexible switching of heating mode through the coordinated action of the main steam system, primary reheat system, secondary reheat system, condenser and heating steam supply system, combined with first-stage, second-stage and third-stage double-row bypass.
It improves the flexibility and reliability of the unit, reduces the power loss of the steam turbine, avoids the problems of boiler reheater overheating and steam turbine axial thrust exceeding the limit, reduces the initial investment of the project, and enhances the adaptability to complex load conditions.
Smart Images

Figure CN224984148U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of heating technology, and in particular to a multi-stage double-row bypass heating system for a secondary reheat unit. Background Technology
[0002] The statements in this section merely refer to the background technology related to this utility model and do not necessarily constitute prior art.
[0003] With the continuous increase in residential heating demand, more and more large and medium-sized cogeneration units are facing the dual pressure of meeting peak-shaving tasks and ensuring urban heating. In particular, after the large-scale grid connection of new energy sources, the peak-shaving demand of large thermal power projects has further increased, and the safe, stable and economical operation of the units faces many challenges. It is urgent to solve the inherent problem of the thermal-electric decoupling depth of cogeneration units.
[0004] Commonly used thermoelectric decoupling technologies include electric boilers, hot water storage tanks, zero-output low-pressure cylinders, and bypass heating. The advantage of bypass heating thermoelectric decoupling technology is that it maximizes the use of existing unit bypass systems, resulting in relatively simple system modifications and lower project investment. However, bypass heating technology for secondary reheat units is more complex, facing problems such as boiler reheater overheating and excessive turbine axial thrust. For example, currently, different extraction points of the secondary reheat unit are connected via pressure matching devices to mix different steam to obtain heating steam with a wide range of parameters. The drawbacks of this method are: poor adaptability to varying parameters, leading to the system being broken down into multiple low-flow pressure matching devices, resulting in system complexity, high initial investment, and a large workload for operation and commissioning; the pressure matching device steam supply method has a significant impact on the original thermal system of the secondary reheat unit, causing difficulties in the operation of the main system; it is more suitable for industrial steam with high pressure parameters and performs poorly in the field of residential heating. Utility Model Content
[0005] To address the shortcomings of existing technologies, this utility model provides a multi-stage double-row bypass heating system for secondary reheat units. The purpose of this system is that, through the synergistic effect of the multi-stage double-row bypass, the three-stage combined bypass heating system for secondary reheat units can effectively improve the flexibility and peak-shaving capability of the unit while ensuring the amount of steam available for heating.
[0006] To achieve the above objectives, the present invention adopts the following technical solution: A multi-stage double-row bypass heating system for a double reheat unit includes a main steam system, a primary reheat system, a secondary reheat system, a condenser, and a heating steam supply system. The output of the main steam system is connected to the input of the primary reheat system, the output of the primary reheat system is connected to the input of the secondary reheat system, and the output of the secondary reheat system is connected to the condenser and the heating steam supply system, respectively. The heating and steam supply system also includes a multi-stage double-row bypass. The first-stage double-row bypass is connected to the main steam system, the second-stage double-row bypass is connected to the primary reheat system, and one end of the third-stage double-row bypass is connected to the secondary reheat system, while the other end is connected to the condenser and the heating and steam supply system, respectively.
[0007] In one embodiment, the main steam system includes a boiler superheater, a main steam pipeline, a turbine ultra-high pressure cylinder, and a primary reheat cold section pipeline; the outlet of the boiler superheater is connected to the first end of the turbine ultra-high pressure cylinder through the main steam pipeline, and the second end of the turbine ultra-high pressure cylinder is connected to the primary reheat system through the primary reheat cold section pipeline; the primary double-row bypass includes a first high-pressure bypass and a second high-pressure bypass, one end of the first high-pressure bypass and the second high-pressure bypass are connected to the main steam pipeline, and the other end is connected to the primary reheat cold section pipeline.
[0008] In one implementation, a first high-pressure bypass valve is provided on the first high-pressure bypass, and a second high-pressure bypass valve is provided on the second high-pressure bypass. The desuperheating water pipes of the first high-pressure bypass valve and the second high-pressure bypass valve are connected to the water supply system.
[0009] In one implementation, a first check valve is provided on the reheat cold section, and a first electric gate valve is provided between the first high-pressure bypass valve and the main steam pipeline.
[0010] In one embodiment, the primary reheat system includes a boiler high-pressure reheater, a primary reheat hot section pipeline, a turbine high-pressure cylinder, and a secondary reheat cold section pipeline. The inlet of the boiler high-pressure reheater is connected to the primary reheat cold section pipeline, and the outlet is connected to the first end of the turbine high-pressure cylinder through the primary reheat hot section pipeline. The second end of the turbine high-pressure cylinder is connected to the secondary reheat system through the secondary reheat cold section pipeline. The secondary dual-row bypass includes a first medium-pressure bypass and a second medium-pressure bypass. One end of the first medium-pressure bypass and the second medium-pressure bypass are connected to the hot section pipeline of the primary reheat, and the other end is connected to the cold section pipeline of the secondary reheat. In one implementation, a first medium-pressure bypass valve is provided on the first medium-pressure bypass, and a second medium-pressure bypass valve is provided on the second medium-pressure bypass. The desuperheating water pipes of the first and second medium-pressure bypass valves are connected to the water supply system.
[0011] In one implementation, a second check valve is provided on the secondary reheat cold section; a second electric gate valve is provided between the first medium-pressure bypass valve and the primary reheat hot section pipeline.
[0012] In one embodiment, the secondary reheat system includes a boiler low-pressure reheater, a secondary reheat hot section pipeline, and a turbine intermediate-pressure cylinder. The inlet of the boiler low-pressure reheater is connected to the secondary reheat cold section pipeline, and the outlet is connected to the turbine intermediate-pressure cylinder through the secondary reheat hot section pipeline. The three-stage double-row bypass includes a first low-pressure bypass and a second low-pressure bypass. One end of both the first and second low-pressure bypasses is connected to the secondary reheat hot section pipeline. The other end of the first low-pressure bypass is connected to the condenser and the heating steam supply system, and the other end of the second low-pressure bypass is connected to the condenser.
[0013] In one implementation, a first low-pressure bypass valve is provided on the first low-pressure bypass, and a second low-pressure bypass valve is provided on the second low-pressure bypass. The first low-pressure bypass valve is connected to the condenser and the heating steam supply system respectively, and the second low-pressure bypass valve is connected to the condenser.
[0014] In one implementation, a third electric gate valve is installed between the first low-pressure bypass valve and the secondary reheat hot section pipeline, and a fourth electric gate valve is installed between the first low-pressure bypass valve and the condenser.
[0015] Compared with the prior art, the beneficial effects of this utility model are: 1. This utility model, through the synergistic effect of the multi-stage double-row bypass, reduces the steam intake of each cylinder of the steam turbine, significantly reducing the turbine's power generation while ensuring maximum heating supply, thus greatly reducing the power plant's power generation losses during the negative electricity price period of the heating season. The synergistic effect of the multi-stage double-row bypass also ensures the thermal circulation effect of the steam turbine and boiler, avoiding problems such as boiler reheater overheating and excessive axial thrust of the steam turbine, ensuring the safe operation of the secondary reheat unit. Furthermore, it maximizes the use of the existing secondary reheat unit start-up bypass system, making system modification relatively simple and reducing initial project investment.
[0016] 2. Compared with the solution that relies on external thermoelectric decoupling equipment (such as electric boilers, thermal storage tanks, etc.) to achieve thermoelectric decoupling, the secondary reheat unit’s own thermal system is modified, and the low-pressure cylinder zero output and high, medium and low pressure three-stage combined bypass heating technology are coupled to deeply explore the thermoelectric decoupling capability of the thermal system itself, effectively reducing the investment in external thermoelectric decoupling equipment and lowering the initial investment of the project.
[0017] 3. The unit has multiple heating modes, such as independent intermediate exhaust steam extraction heating, independent low-pressure cylinder zero-output heating, and low-pressure cylinder zero-output coupled high, medium and low pressure three-stage combined bypass heating, etc. The bypass parameter regulation heating is further subdivided into multiple modes, which can realize flexible switching between heating modes. The adaptability to complex and ever-changing multi-source dispatch (electric load - heat load) situation is greatly improved, ensuring the flexibility and reliability of unit operation. Attached Figure Description
[0018] The accompanying drawings, which form part of this application, are used to provide a further understanding of this application. The illustrative embodiments of this application and their descriptions are used to explain this application and do not constitute an undue limitation of this application.
[0019] Figure 1 A schematic diagram of a multi-stage double-row bypass heating system for a secondary reheat unit is provided for an embodiment of this utility model; Among them, 1. Main steam system, 101. Boiler superheater, 102. Main steam pipeline, 103. Steam turbine ultra-high pressure cylinder, 104. Primary reheat cold section pipeline, 105. First check valve; 2. Primary reheat system, 201. Boiler high-pressure reheater, 202. Primary reheat hot section pipeline, 203. Steam turbine high-pressure cylinder, 204. Secondary reheat cold section pipeline, 205. Secondary check valve; 3. Secondary reheat system, 301. Boiler low-pressure reheater, 302. Secondary reheat hot section piping, 303. Steam turbine intermediate pressure cylinder; 4. Condenser; 5. Heating and steam supply system; 6. First-stage double-row bypass, 601, first high-pressure bypass, 6011, first high-pressure bypass valve, 6012, first electric gate valve, 602, second high-pressure bypass, 6021, second high-pressure bypass valve; 7. Secondary double-row bypass, 701. First medium-pressure bypass, 7011. First medium-pressure bypass valve, 7012. Second electric gate valve, 702. Second medium-pressure bypass, 7021. Second medium-pressure bypass valve; 8. Three-stage double-row bypass, 801, first low-pressure bypass, 8011, first low-pressure bypass valve, 8012, third electric gate valve, 8013, fourth electric gate valve, 8014, electric butterfly valve, 802, second low-pressure bypass, 8021, second low-pressure bypass valve. 9. Liaison tube. Detailed Implementation
[0020] It should be noted that the following detailed descriptions are exemplary and intended to provide further explanation of this application. Unless otherwise specified, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains.
[0021] It should be noted that this utility model is a structural solution. As for the individual devices involved, the specific structures for realizing their respective functions already exist in the prior art, as do the protocols, software, or programs involved in their operation. Those skilled in the art are fully aware of this. This utility model does not make any improvements to the individual devices, and therefore does not involve software content. Instead, it relies on the organic integration and consolidation of the components into a whole, that is, it provides a structural solution.
[0022] like Figure 1 The diagram shows a multi-stage double-row bypass heating system for a secondary reheat unit. The system includes a main steam system 1, a primary reheat system 2, a secondary reheat system 3, a condenser 4, and a heating steam supply system 5. The output of the main steam system 1 is connected to the input of the primary reheat system 2, the output of the primary reheat system 2 is connected to the input of the secondary reheat system 3, and the output of the secondary reheat system 3 is connected to both the condenser 4 and the heating steam supply system 5. The heating system also includes a multi-stage double-row bypass. The first-stage double-row bypass 6 is connected to the main steam system 1, the second-stage double-row bypass 7 is connected to the primary reheat system 2, and one end of the third-stage double-row bypass 8 is connected to the secondary reheat system 3, while the other end is connected to the condenser 4 and the heating steam supply system 5, respectively.
[0023] like Figure 1 As shown, the main steam system 1 includes a boiler superheater 101, a main steam pipeline 102, a turbine ultra-high pressure cylinder 103, and a primary reheat cold section pipeline 104; the outlet of the boiler superheater 101 is connected to the first end of the turbine ultra-high pressure cylinder 103 through the main steam pipeline 102, and the second end of the turbine ultra-high pressure cylinder 103 is connected to the primary reheat system 2 through the primary reheat cold section pipeline 104; The first-stage double-row bypass 6 includes a first high-pressure bypass 601 and a second high-pressure bypass 602. One end of the first high-pressure bypass 601 and the second high-pressure bypass 602 are connected to the main steam pipe 102, and the other end is connected to the primary reheat cold section pipe 104. Specifically, a first high-pressure bypass valve 6011 is provided on the first high-pressure bypass 601, and a second high-pressure bypass valve 6021 is provided on the second high-pressure bypass 602. The desuperheating water pipes of the first high-pressure bypass valve 6011 and the second high-pressure bypass valve 6021 are connected to the water supply system. Furthermore, a first check valve 105 is installed on the primary reheat cold section pipeline 104, which is used to prevent water from entering the ultra-high pressure cylinder of the steam turbine and to prevent overspeed. Furthermore, a first electric gate valve 6012 is provided between the first high-pressure bypass valve 6011 and the main steam pipeline 102. Its function is to strengthen the tightness of the first high-pressure bypass valve 6011 after it is closed during the non-heating season. like Figure 1As shown, the primary reheat system 2 includes a boiler high-pressure reheater 201, a primary reheat hot section pipe 202, a turbine high-pressure cylinder 203, and a secondary reheat cold section pipe 204. The inlet of the boiler high-pressure reheater 201 is connected to the primary reheat cold section pipe 204, and the outlet is connected to the first end of the turbine high-pressure cylinder 203 through the primary reheat hot section pipe 202. The second end of the turbine high-pressure cylinder 203 is connected to the secondary reheat system 3 through the secondary reheat cold section pipe 204. The secondary dual-row bypass 7 includes a first medium-pressure bypass 701 and a second medium-pressure bypass 702. One end of the first medium-pressure bypass 701 and the second medium-pressure bypass 702 are connected to the primary reheat hot section pipeline 202, and the other end is connected to the secondary reheat cold section pipeline 204. Specifically, a first medium-pressure bypass valve 7011 is provided on the first medium-pressure bypass 701, and a second medium-pressure bypass valve 7021 is provided on the second medium-pressure bypass 702. The desuperheating water pipes of the first medium-pressure bypass valve 7011 and the second medium-pressure bypass valve 7021 are connected to the water supply system. Furthermore, a second check valve 205 is installed on the secondary reheat cold section pipeline 204, which is used to prevent water from entering the high-pressure cylinder of the steam turbine and to prevent overspeed. Furthermore, a second electric gate valve 7012 is installed between the first medium-pressure bypass valve 7011 and the primary reheat hot section pipeline 202. Its function is to enhance the tightness of the first medium-pressure bypass valve 7011 after it is closed during the non-heating season.
[0024] like Figure 1 As shown, the secondary reheat system 3 includes a boiler low-pressure reheater 301, a secondary reheat hot section pipeline 302, and a turbine intermediate-pressure cylinder 303. The inlet of the boiler low-pressure reheater 301 is connected to the secondary reheat cold section pipeline 204, and the outlet is connected to the turbine intermediate-pressure cylinder 303 through the secondary reheat hot section pipeline 302. The three-stage double-row bypass 8 includes a first low-pressure bypass 801 and a second low-pressure bypass 802. One end of the first low-pressure bypass 801 and the second low-pressure bypass 802 are both connected to the secondary reheat hot section pipeline 302. The other end of the first low-pressure bypass 801 is connected to the condenser 4 and the heating steam supply system 5. The other end of the second low-pressure bypass 802 is connected to the condenser 4. Specifically, a first low-pressure bypass valve 8011 is provided on the first low-pressure bypass 801, and a second low-pressure bypass valve 8021 is provided on the second low-pressure bypass 802. The first low-pressure bypass valve 8011 is connected to the condenser 4 and the heating steam supply system 5, respectively, and the second low-pressure bypass valve 8021 is connected to the condenser 4. The desuperheating water pipes of the first low-pressure bypass valve 8011 and the second low-pressure bypass valve 8021 are connected to the condensate system. Furthermore, a third electric gate valve 8012 is installed between the first low-pressure bypass valve 8011 and the secondary reheat hot section pipeline 302; a fourth electric gate valve 8013 is installed between the first low-pressure bypass valve 8011 and the condenser 4; and an electric butterfly valve 8014 is installed between the first low-pressure bypass valve 8011 and the heating and steam supply system 5.
[0025] Furthermore, the main steam pipe 102, the primary reheat hot section pipe 202, and the secondary reheat hot section pipe 302 include two half-capacity pipes, and a connecting pipe 9 is provided between the two half-capacity pipes to ensure the pressure and flow of the two half-capacity pipes are balanced.
[0026] The working principle of this utility model is as follows: Working Principle 1: Working Principle of Double Reheat Unit Start-up Mode During the start-up of the secondary reheat unit, all four electric gate valves (6012, 7012, 8012, 8013, and 8014) are open; the first electric butterfly valve (8014) is closed; the first high-pressure bypass valve (6011, 6021, 7011, 7021, 7021, 7021, 8011, 8021, and 8021) are open and participate in flow regulation; the main steam produced by the boiler superheater 101 enters the first high-pressure bypass valve 6011 and the second high-pressure bypass valve 6021 through the main steam pipeline 102, and after desuperheating and pressure reduction, it enters the boiler high-pressure reheater 201 through the primary reheat cold section pipeline 104; the boiler high-pressure reheater 201... The primary reheat hot section steam produced by the unit enters the first intermediate pressure bypass valve 7011 and the second intermediate pressure bypass valve 7021 through the primary reheat hot section pipeline 202. After desuperheating and pressure reduction, it enters the boiler low-pressure reheater 301 through the secondary reheat cold section pipeline 204. The secondary reheat hot section steam produced by the boiler low-pressure reheater 301 enters the first low-pressure bypass valve 8011 and the second low-pressure bypass valve 8021 through the secondary reheat hot section pipeline 302. After desuperheating and pressure reduction, it is discharged into the condenser 4. The turbine ultra-high pressure cylinder 103, turbine high pressure cylinder 203, and turbine intermediate pressure cylinder 303 gradually increase the steam intake according to the start-up curve requirements of cold state, warm state, hot state, and extremely hot state. The synergistic effect of the multi-stage double-row bypass of the secondary reheat unit completes each start-up process of the secondary reheat unit.
[0027] Working Principle 2: Working Principle of the Secondary Reheat Unit in Heating Season with Independent Intermediate Exhaust Steam Extraction Heating and Independent Low-Pressure Cylinder Zero-Output Heating Mode During the heating season, when the secondary reheat unit operates under the conditions of independent intermediate exhaust steam extraction for heating and independent low-pressure cylinder zero-output heating, the multi-stage double-row bypass heating system of the secondary reheat unit does not participate in operation regulation. The first electric gate valve 6012, the second electric gate valve 7012, the third electric gate valve 8012, and the first electric butterfly valve 8014 are all closed; the first high-pressure bypass valve 6011, the second high-pressure bypass valve 6021, the first medium-pressure bypass valve 7011, the second medium-pressure bypass valve 7021, the first low-pressure bypass valve 8011, and the second low-pressure bypass valve 8021 are all closed; only the fourth electric gate valve 8013 is open to ensure that a small amount of internal leakage steam from the first low-pressure bypass valve 8011 can be discharged into the condenser 4 in a timely manner.
[0028] Working Principle 3: Working Principle of Low-Pressure Cylinder Zero Output Coupled with Low-Pressure Bypass Heating Mode during Heating Season In the heating season, under the low-pressure cylinder zero-output coupled low-pressure bypass heating mode, only the single-row low-pressure heating bypass in the multi-stage double-row bypass system of the secondary reheat unit participates in system regulation. That is, only the first low-pressure bypass valve 8011, the third electric gate valve 8012, and the first electric butterfly valve 8014 are open, while other related valves in this system are closed. Only a portion of the secondary reheat hot section steam produced by the boiler low-pressure reheater 301 enters the first low-pressure bypass valve 8011, and after being de-temperatured and depressurized, it enters the heating steam supply system 5. This ensures that the heating capacity of the unit remains unchanged while further reducing the unit's power generation. Example: In a certain secondary reheat project with a single unit heating steam extraction capacity of 960t / h, compared with the single low-pressure cylinder zero-output heating mode, the low-pressure cylinder zero-output coupled low-pressure bypass heating mode can reduce the unit's power generation by about 50MW.
[0029] Working Principle 4: Working Principle of Low-Pressure Cylinder Zero Output Coupled with Medium and Low Pressure Two-Stage Combined Bypass Heating Mode during Heating Season During the heating season, in the low-pressure cylinder zero-output coupling medium and low-pressure two-stage combined bypass heating mode, the single-row medium and low-pressure two-stage combined bypass in the multi-stage double-row bypass system of the secondary reheat unit jointly participates in system regulation. That is, the first medium-pressure bypass valve 7011, the first low-pressure bypass valve 8011, the second electric gate valve 7012, the third electric gate valve 8012, and the first electric butterfly valve 8014 are open, while the first high-pressure bypass valve 6011, the first electric gate valve 6012, the fourth electric gate valve 8013, the second high-pressure bypass valve 6021, the second medium-pressure bypass valve 7021, and the second low-pressure bypass valve 8021 are closed. Part of the primary heating output produced by the boiler high-pressure reheater 201 is... The reheat hot section steam enters the first medium-pressure bypass valve 7011, and after de-temperatureing and pressure reduction, it enters the secondary reheat cold section pipeline; part of the secondary reheat hot section steam produced by the boiler low-pressure reheater 301 enters the first low-pressure bypass valve 8011, and after de-temperatureing and pressure reduction, it enters the heating steam supply system 5; the two-stage single-row heating bypass of the secondary reheat unit works in concert to ensure that the heating capacity of the unit remains unchanged while further reducing the unit's power generation; Example: When the single-unit heating steam extraction capacity of a certain secondary reheat project is 960t / h, compared with the single low-pressure cylinder zero-output heating mode, the low-pressure cylinder zero-output coupled medium and low-pressure three-stage combined bypass heating mode can reduce the unit's power generation by about 110MW.
[0030] Working Principle 5: Working Principle of Low-Pressure Cylinder Zero Output Coupling High, Medium, and Low-Pressure Three-Stage Combined Bypass Heating Mode during Heating Season During the heating season, in the low-pressure cylinder zero-output coupling high, medium, and low-pressure three-stage combined bypass heating mode, the single-row high, medium, and low-pressure three-stage combined bypass in the multi-stage double-row bypass system of the secondary reheat unit jointly participates in system regulation. Specifically, the first high-pressure bypass valve 6011, the first medium-pressure bypass valve 7011, the first low-pressure bypass valve 8011, the first electric gate valve 6012, the second electric gate valve 7012, the third electric gate valve 8012, and the first electric butterfly valve 8014 are open, while the fourth electric gate valve 8013, the second high-pressure bypass valve 6021, the second medium-pressure bypass valve 7021, and the second low-pressure bypass valve 8021 are closed. Part of the main steam produced by the boiler superheater 101 enters the first high-pressure bypass valve 6011, and after desuperheating and pressure reduction, it enters the primary reheat. Cold section pipeline 104; Part of the primary reheat hot section steam produced by the boiler high-pressure reheater 201 enters the first medium-pressure bypass valve 7011, and after de-temperature and pressure reduction, enters the secondary reheat cold section pipeline; Part of the secondary reheat hot section steam produced by the boiler low-pressure reheater 301 enters the first low-pressure bypass valve 8011, and after de-temperature and pressure reduction, enters the heating steam supply system 5; The multi-stage single-row heating bypass of the secondary reheat unit works in concert to ensure that the heating capacity of the unit remains unchanged while further reducing the unit's power generation; Example: When the single heating steam extraction capacity of a secondary reheat project is 960t / h, compared with the single low-pressure cylinder zero-output heating mode, the low-pressure cylinder zero-output coupled high, medium and low-pressure three-stage combined bypass heating mode can reduce the unit's power generation by about 180MW.
[0031] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.
Claims
1. A multi-stage double-row bypass heat supply system of a double-reheat unit, comprising a main steam system (1), a primary reheat system (2), a secondary reheat system (3), a condenser (4) and a heating steam supply system (5), characterized in that, The output end of the main steam system (1) is connected to the input end of the primary reheat system (2), the output end of the primary reheat system (2) is connected to the input end of the secondary reheat system (3), and the output end of the secondary reheat system (3) is connected to the condenser (4) and the heating steam supply system (5) respectively. The heating system also includes a multi-stage double-row bypass. The first-stage double-row bypass (6) is connected to the main steam system (1), the second-stage double-row bypass (7) is connected to the primary reheat system (2), and one end of the third-stage double-row bypass (8) is connected to the secondary reheat system (3), while the other end is connected to the condenser (4) and the heating steam supply system (5).
2. A multi-stage double-row bypass heating system for a double-reheat unit as set forth in claim 1, characterized in that, The main steam system (1) includes a boiler superheater (101), a main steam pipeline (102), a turbine ultra-high pressure cylinder (103), and a primary reheat cold section pipeline (104). The outlet of the boiler superheater (101) is connected to the first end of the turbine ultra-high pressure cylinder (103) through the main steam pipeline (102), and the second end of the turbine ultra-high pressure cylinder (103) is connected to the primary reheat system (2) through the primary reheat cold section pipeline (104). The primary double-row bypass (6) includes a first high-pressure bypass (601) and a second high-pressure bypass (602). One end of the first high-pressure bypass (601) and the second high-pressure bypass (602) is connected to the main steam pipeline (102), and the other end is connected to the primary reheat cold section pipeline (104).
3. A multi-stage double-row bypass heating system for a double-reheat unit as set forth in claim 2, characterized in that, A first high-pressure bypass valve (6011) is provided on the first high-pressure bypass (601), and a second high-pressure bypass valve (6021) is provided on the second high-pressure bypass (602). The desuperheating water pipes of the first high-pressure bypass valve (6011) and the second high-pressure bypass valve (6021) are connected to the water supply system.
4. The multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 3, characterized in that, A first check valve (105) is installed on the reheat cold section pipeline (104), and a first electric gate valve (6012) is installed between the first high-pressure bypass valve (6011) and the main steam pipeline (102).
5. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 2, characterized in that, The primary reheat system (2) includes a boiler high-pressure reheater (201), a primary reheat hot section pipe (202), a turbine high-pressure cylinder (203), and a secondary reheat cold section pipe (204). The inlet of the boiler high-pressure reheater (201) is connected to the primary reheat cold section pipe (104), and the outlet is connected to the first end of the turbine high-pressure cylinder (203) through the primary reheat hot section pipe (202). The second end of the turbine high-pressure cylinder (203) is connected to the secondary reheat system (3) through the secondary reheat cold section pipe (204). The secondary dual-row bypass (7) includes a first medium-pressure bypass (701) and a second medium-pressure bypass (702). One end of the first medium-pressure bypass (701) and the second medium-pressure bypass (702) are connected to the primary reheat hot section pipeline (202), and the other end is connected to the secondary reheat cold section pipeline (204).
6. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 5, characterized in that, A first medium-pressure bypass valve (7011) is provided on the first medium-pressure bypass (701), and a second medium-pressure bypass valve (7021) is provided on the second medium-pressure bypass (702). The desuperheating water pipes of the first medium-pressure bypass valve (7011) and the second medium-pressure bypass valve (7021) are connected to the water supply system.
7. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 6, characterized in that, A second check valve (205) is installed on the secondary reheat cold section pipeline (204); a second electric gate valve (7012) is installed between the first medium-pressure bypass valve (7011) and the primary reheat hot section pipeline (202).
8. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 5, characterized in that, The secondary reheat system (3) includes a boiler low-pressure reheater (301), a secondary reheat hot section pipeline (302), and a turbine intermediate-pressure cylinder (303). The inlet of the boiler low-pressure reheater (301) is connected to the secondary reheat cold section pipeline (204), and the outlet is connected to the turbine intermediate-pressure cylinder (303) through the secondary reheat hot section pipeline (302). The three-stage double-row bypass (8) includes a first low-pressure bypass (801) and a second low-pressure bypass (802). One end of the first low-pressure bypass (801) and the second low-pressure bypass (802) are both connected to the secondary reheat hot section pipeline (302). The other end of the first low-pressure bypass (801) is connected to the condenser (4) and the heating and steam supply system (5), and the other end of the second low-pressure bypass (802) is connected to the condenser (4).
9. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 8, characterized in that, A first low-pressure bypass valve (8011) is provided on the first low-pressure bypass (801), and a second low-pressure bypass valve (8021) is provided on the second low-pressure bypass (802). The first low-pressure bypass valve (8011) is connected to the condenser (4) and the heating steam supply system (5) respectively, and the second low-pressure bypass valve (8021) is connected to the condenser (4).
10. A multi-stage double-row bypass heating system for a secondary reheat unit as described in claim 9, characterized in that, A third electric gate valve (8012) is provided between the first low-pressure bypass valve (8011) and the secondary reheat hot section pipeline (302), and a fourth electric gate valve (8013) is provided between the first low-pressure bypass valve (8011) and the condenser (4).