End leak detection device under simulated vacuum conditions

By using a vacuum-simulated end-point leak detection device, which combines a vacuum generator and a helium leak detector, the limitations of existing end-point leak detection technologies have been overcome. This enables precise detection of end-point sealing performance, ensuring the stability of coating production and product quality.

CN224985024UActive Publication Date: 2026-11-17CHANGXING QIBIN ENERGY SAVING GLASS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522644003.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-12-12
Publication Date
2026-11-17
Estimated Expiration
2035-12-12

AI Technical Summary

Technical Problem

In existing technologies, leak detection at the end of the coating production line is carried out in an atmospheric environment, which results in limited detection effectiveness, making it difficult to identify minute leaks and affecting the stability of coating production and product quality.

Method used

Design a terminal leak detection device that simulates a vacuum state, including a mounting plate, a cover, a leak detector and a vacuum generator. The vacuum generator simulates the real working environment of the terminal, and the helium leak detector captures helium signals to accurately identify the sealing performance of the terminal.

Benefits of technology

It improves the reliability of end leak detection, effectively identifies minute leaks, and ensures the stable operation of the coating production line and product quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224985024U_ABST
    Figure CN224985024U_ABST
Patent Text Reader

Abstract

This application discloses a terminal leak detection device under simulated vacuum conditions, relating to the field of glass coating technology. The device includes a mounting plate, a housing, a leak detector, and a vacuum generator. The housing is mounted on the mounting plate, and the housing and mounting plate together form a detection chamber. The detection chamber accommodates the terminal to be tested. The leak detector and the vacuum generator are connected to the detection chamber. In the technical solution provided by this application, the terminal leak detection device under simulated vacuum conditions uses replicating the actual vacuum conditions of the terminal as its core logic. First, the terminal to be tested is placed in the detection chamber enclosed by the mounting plate and the housing, ensuring the detection chamber itself is reliably sealed. Then, the vacuum generator creates and maintains a vacuum environment in the detection chamber consistent with the coating production line. Subsequently, helium is injected into the key sealing parts of the terminal, and the leak detector is used for leak detection, conforming to the actual working conditions of the terminal.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of glass coating technology, and in particular to a leak detection device for ends under simulated vacuum conditions. Background Technology

[0002] Driven by both technological advancements and evolving environmental concerns, the nation has imposed increasingly stringent requirements on the environmental and energy-saving indicators of various products, particularly in the architectural glass sector. Market demand has shifted from traditional single-function flat glass to eco-friendly composite glass integrating multiple properties such as environmental protection, energy saving, sound insulation, and aesthetics. Functionalization has become the core development direction of the architectural glass industry. In the process of realizing the functionality of architectural glass, coating technology plays an irreplaceable and crucial role. Through coating treatment, the glass's transmission and conversion characteristics of light, heat, and electricity can be effectively controlled, thereby endowing the glass with the aforementioned composite functions. Therefore, coating technology has become an essential step in the production of energy-saving glass.

[0003] The stable operation of a coating production line places extremely high demands on the vacuum environment. Not only must the vacuum level of the coating chamber be maintained within a specific process range, but significant fluctuations in vacuum level are also unacceptable throughout the entire production process; otherwise, the coating quality will be directly affected. The core prerequisite for meeting the process requirements for the vacuum level of the coating chamber is that all connecting parts and sealing rings within the chamber possess excellent sealing performance, ensuring no air or water leaks or other sealing failures. The end caps and hexagonal shafts are particularly critical sealing components, and their sealing reliability is especially important. If air leaks occur in critical components such as the end caps and hexagonal shafts, it will directly lead to fluctuations in the vacuum level of the coating chamber, causing a series of quality problems such as glass coating layer peeling, abnormal color and transmittance, severely impacting product yield. Therefore, to ensure production stability, the end caps of the coating production line must be included in the management scope of regular maintenance and replacement.

[0004] In existing technologies, leak detection at the ends of coating production lines is typically performed in an atmospheric environment by filling with helium. This method differs significantly from the actual working conditions of the ends, which are in a vacuum environment along with the target material during production line operation. This mismatch in operating conditions leads to significant limitations in detection effectiveness. While it can detect larger leaks at the ends, it often struggles to reliably detect minute leaks. Consequently, some ends with potential micro-leakage are not identified during the leak detection process, leading to micro-leakage during subsequent maintenance cycles and negatively impacting the stability of coating production and product quality. Utility Model Content

[0005] This application proposes a leak detection device for end caps under simulated vacuum conditions, aiming to provide a leak detection device that can simulate the real working environment of the end cap and detect leaks, thereby ensuring the reliability of the detection.

[0006] One embodiment of this application provides a leak detection device for end caps under simulated vacuum conditions, comprising: Mounting plate; A cover is provided on the mounting plate, and the cover and the mounting plate enclose a testing chamber, which is used to accommodate the end to be tested; The leak detector is connected to the detection chamber; A vacuum generator is connected to the detection chamber.

[0007] In one embodiment, the leak detector has a first valve for controlling the connection between the leak detector and the detection chamber.

[0008] In one embodiment, the vacuum generator includes a forepump and a molecular pump, and the vacuum generator also includes a main pipeline connected to the detection chamber; the forepump is connected to the main pipeline through a first branch pipeline, and the molecular pump is connected to the main pipeline through a second branch pipeline.

[0009] In one embodiment, the first branch pipe is equipped with a second valve, which is used to control the connection between the pre-pump and the detection chamber; and The second branch pipe is equipped with a third valve, which is used to control the connection between the molecular pump and the detection chamber.

[0010] In one embodiment, the main pipeline is equipped with a vacuum gauge.

[0011] In one embodiment, an exhaust pipe is provided on one side of the enclosure, and the exhaust pipe is provided with a fourth valve, which is used to control the connection between the detection chamber and the outside world.

[0012] In one embodiment, the periphery of the cover is provided with a skirt, and a sealing ring is provided on the skirt facing the mounting plate, the sealing ring abutting against the skirt and the mounting plate.

[0013] In one embodiment, the mounting plate is provided with a positioning pin facing the cover, and the skirt is provided with a positioning hole, through which the positioning pin passes.

[0014] In one embodiment, the mounting plate is provided with a first mounting port and a second mounting port, the first mounting port and the second mounting port are in communication with the outside, and the end cap is provided on the first mounting port and the second mounting port.

[0015] In one embodiment, the end leak detection device under simulated vacuum conditions further includes a mounting frame, the mounting plate is disposed on the mounting frame, and the mounting frame is provided with casters.

[0016] This application discloses a terminal leak detection device under simulated vacuum conditions. Specifically, the terminal leak detection device under simulated vacuum conditions includes a mounting plate, a cover, a leak detector, and a vacuum generator. The cover is mounted on the mounting plate and together with the mounting plate, forms a detection chamber for placing the terminal to be tested. The leak detector and the vacuum generator are respectively connected to the detection chamber. The end-cap leak detection device, designed to simulate the actual vacuum conditions of the end cap, first places the end cap to be tested in a detection chamber enclosed by a mounting plate and a housing, ensuring the chamber itself is reliably sealed. Then, a vacuum generator creates and maintains a vacuum environment within the detection chamber consistent with the coating production line. Next, helium is injected into the critical sealing areas of the end cap. If a leak is present, helium will seep into the detection chamber. A helium mass spectrometer leak detector connected to the chamber uses the properties of helium ions to capture the helium signal and convert it into an electrical signal. Operators use this electrical signal data to determine the end cap's sealing performance and can locate leaks by moving the helium injection point. After testing, the chamber is depressurized, and the end cap can be removed. Throughout the process, the vacuum generator and leak detector work together to effectively detect minute leaks, improving detection reliability and ensuring the stable operation of the coating production line. Attached Figure Description

[0017] To more clearly illustrate the technical solutions in the embodiments or prior art of this application, the drawings used in the description of the embodiments or prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.

[0018] Figure 1 A cross-sectional view of an embodiment of the end leak detection device under simulated vacuum conditions provided in this application; Figure 2 This is a schematic diagram of the end leak detection device simulating a vacuum condition; Figure 3 This is a gas path diagram for simulating a leak detection device at the end under vacuum conditions.

[0019] Explanation of icon numbers: 100. End-point leak detection device under simulated vacuum conditions; 1. Mounting plate; 11. Positioning pin; 2. Cover; 21. Skirt; 211. Sealing ring; 21a. Positioning hole; 22. Exhaust pipe; 221. Fourth valve; 2a. Leak detection chamber; 3. Leak detector; 31. First valve; 32. Leak detection pipeline; 4. Vacuum generator; 41. Foreboard pump; 411. Second valve; 412. First branch pipeline; 42. Molecular pump; 421. Third valve; 422. Second branch pipeline; 43. Main pipeline; 431. Vacuum gauge; 5. Mounting bracket; 6. Casters; 200, end; 210, drive end; 220, water and electricity end; 230, target tube. Detailed Implementation

[0020] The technical solutions of this application will be clearly and completely described below with reference to the accompanying drawings of several embodiments. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of the embodiments. Based on the embodiments of this application, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of this application.

[0021] It should be noted that if multiple embodiments of this application involve directional indicators (such as up, down, left, right, front, back, etc.), the directional indicators are only used to explain the relative positional relationship and movement of the components in a specific posture. If the specific posture changes, the directional indicators will also change accordingly.

[0022] Furthermore, if multiple embodiments of this application involve descriptions such as "first" or "second," these descriptions are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of those features. Additionally, the use of "and / or" or "and / or" throughout the text implies three parallel solutions. For example, "A and / or B" includes solution A, solution B, or a solution where both A and B are satisfied simultaneously. Furthermore, the technical solutions of various embodiments can be combined with each other, but this must be based on the ability of those skilled in the art to implement them. When the combination of technical solutions is contradictory or impossible to implement, it should be considered that such a combination of technical solutions does not exist and is not within the scope of protection claimed in this application.

[0023] The stable operation of a coating production line places extremely high demands on the vacuum environment. Not only must the vacuum level of the coating chamber be maintained within a specific process range, but significant fluctuations in vacuum level are also unacceptable throughout the entire production process; otherwise, the coating quality will be directly affected. The core prerequisite for meeting the process requirements for the vacuum level of the coating chamber is that all connecting parts and sealing rings within the chamber possess excellent sealing performance, ensuring no air or water leaks or other sealing failures. The end caps and hexagonal shafts are particularly critical sealing components, and their sealing reliability is especially important. If air leaks occur in critical components such as the end caps and hexagonal shafts, it will directly lead to fluctuations in the vacuum level of the coating chamber, causing a series of quality problems such as glass coating layer peeling, abnormal color and transmittance, severely impacting product yield. Therefore, to ensure production stability, the end caps of the coating production line must be included in the management scope of regular maintenance and replacement.

[0024] In existing technologies, leak detection at the ends of coating production lines is typically performed in an atmospheric environment by filling with helium. This method differs significantly from the actual working conditions of the ends, which are in a vacuum environment along with the target material during production line operation. This mismatch in operating conditions leads to significant limitations in detection effectiveness. While it can detect larger leaks at the ends, it often struggles to reliably detect minute leaks. Consequently, some ends with potential micro-leakage are not identified during the leak detection process, leading to micro-leakage during subsequent maintenance cycles and negatively impacting the stability of coating production and product quality.

[0025] To address the aforementioned problems, this application proposes a leak detection device 100 for end caps under simulated vacuum conditions, in order to solve or at least alleviate the aforementioned technical problems.

[0026] Please see Figure 1 In one embodiment of this application, the end leak detection device 100 under simulated vacuum conditions includes a mounting plate 1, a cover 2, a leak detector 3, and a vacuum generator 4. The cover 2 is disposed on the mounting plate 1, and the cover 2 and the mounting plate 1 enclose a detection chamber. The detection chamber is used to accommodate the end to be tested. The leak detector 3 is connected to the detection chamber, and the vacuum generator 4 is connected to the detection chamber.

[0027] Understandably, the specific working principle of the end leak detection device 100 under simulated vacuum conditions revolves around the core process of "operating condition simulation - leak point tracing - signal capture - result judgment," and the working mechanism and synergistic relationship of each link are as follows: The operation of the end leak detection device 100 under simulated vacuum conditions must strictly follow the process of "installation and commissioning - vacuum construction - segmented leak detection - pressure relief and completion", and be carried out in accordance with the specifications of each component of the device to ensure detection accuracy and operational safety. The specific steps are as follows: The first step is to install the end cap and the device foundation. The maintained end cap is precisely positioned at the first and second mounting ports of the mounting plate 1, ensuring a tight seal between the end cap and the mounting port sealing surfaces to avoid initial leakage risks due to misalignment. Then, the leak detection chamber 2a, consisting of the cover 2, is hoisted onto the mounting plate 1, ensuring precise engagement between the positioning holes 21a of the skirt 21 of the cover 2 and the positioning pins 11 of the mounting plate 1. This positioning structure guarantees the accuracy of the chamber's installation position. Simultaneously, it is confirmed that the sealing ring 211 inside the skirt 21 fully abuts against the mounting plate 1 and the skirt 21, completing the sealed installation of the leak detection chamber 2a and laying the foundation for establishing a stable vacuum environment.

[0028] The second step is to test and debug the pipeline and equipment connections. According to the device's pipeline layout, connect the main vacuum pipeline 43 and its branch pipelines sequentially. Connect the pre-pump 41 to the main pipeline 43 via the first branch pipeline 412, and the molecular pump 42 to the main pipeline 43 via the second branch pipeline 422, ensuring reliable sealing at the pipeline interfaces. Then install the second valve 411 of the pre-pump 41 branch pipeline, the third valve 421 of the molecular pump 42 branch pipeline, and the first valve 31 of the leak detector 3 connection pipe. Connect the leak detector 3 to the leak detection chamber 2a via the dedicated leak detection pipeline 32. Finally, install the vacuum gauge 431 on the main pipeline 43. After completion, check all connections to confirm there are no loose parts or missing seals.

[0029] The third step is staged vacuuming and operational preparation. Start the pre-pump 41 and slowly open its second valve 411 to begin initial vacuuming of the leak detection chamber 2a. The operator observes the vacuum gauge 431 reading in real time. When the reading drops to 0.8 Pa, immediately close the second valve 411 corresponding to the pre-pump 41 and stop its operation. Then, sequentially open the third valve 421 of the molecular pump 42 and the first valve 31 of the leak detector 3, starting the molecular pump 42 to perform deep vacuuming of the leak detection chamber 2a. Utilizing the high pumping speed of the molecular pump 42, the vacuum level of the leak detection chamber 2a is raised to a range consistent with the actual operating conditions of the coating production line. Simultaneously, the leak detector 3 is started for preheating and testing to ensure it is in normal detection condition.

[0030] Step 4: Sealing performance test of the water-electric terminal 220. After the vacuum level in the leak detection chamber 2a stabilizes, helium gas is injected into the water-electric terminal 220 through the water inlet pipe, controlling the helium pressure between 2.5 and 3 bar. Then, compressed air is connected to supplement the total internal pressure of the water-electric terminal 220 to 5.5 bar, so that the sealing surface of the water-electric terminal 220 is at its rated working pressure. The servo motor of the drive end 210 of the terminal is started, causing the motor to drive the terminal to rotate, simulating the dynamic working state of the terminal in the production line. During this process, the changes in the values ​​of the leak detector 3 are continuously observed. If abnormal fluctuations occur in the values, it indicates that there is a leak in the sealing part of the water-electric terminal 220. The rotation angle corresponding to the peak value of the fluctuation needs to be recorded to locate the leak.

[0031] Step 5: Pressure Holding and Leak Detection & Media Removal. After completing the dynamic test, maintain the pressure at the water / electricity terminal 220 and perform a static pressure holding leak test for 8-10 minutes. During this period, closely monitor the vacuum level on vacuum gauge 431 and the value on leak detector 3. If both show no significant change, the sealing performance of water / electricity terminal 220 is qualified. Then, close the helium and compressed air inlet valves and open the exhaust valve of water / electricity terminal 220 to completely remove any residual helium and compressed air, preventing residual media from affecting subsequent test results.

[0032] Step 6: Specific leak detection at the end seam. For this critical sealing area, the end seam, 3 bar of helium is injected into the seam area through a dedicated inflation port to ensure the helium fully fills the sealing gap. The leak detector 3 is restarted for a pressure test, and the numerical changes are continuously observed. If the value is stable and abnormal, the seam seal is reliable; if a helium signal is detected, the leak point in the seam is precisely marked. After the test is completed, the venting device at the seam is opened to completely remove the helium.

[0033] Step 7: Depressurization and Equipment Reset. Sequentially shut down molecular pump 42 and leak detector 3, closing each pipe valve in the order of first closing the third valve 421 of molecular pump 42, then the first valve 31 of leak detector 3. Next, open the fourth valve 221 of the exhaust pipe 22 of leak detection chamber 2a to slowly return the chamber to atmospheric pressure, preventing a sudden pressure surge from damaging the chamber's sealing structure. After the pressure is completely balanced, remove leak detection chamber 2a, remove the tested end, clean the sealing surfaces of mounting plate 1 and cover 2, and turn off the power to all equipment to complete the leak detection operation.

[0034] Throughout the operation, it is important to note that all valve opening and closing actions must be performed slowly to prevent sudden changes in vacuum or pressure from impacting the equipment. As helium is used as a tracer medium, it is necessary to ensure that the filling interface is well sealed to avoid interference from external helium in the test results. Data from vacuum gauge 431 and leak detector 3 must be recorded simultaneously at each step of the operation to form a complete test record and provide a basis for end-point quality assessment.

[0035] In some embodiments, please refer to Figure 1 The periphery of the cover 2 is provided with a skirt 21, and a sealing ring 211 is provided on the skirt 21 facing the mounting plate 1. The sealing ring 211 abuts against the skirt 21 and the mounting plate 1. This design can significantly improve the sealing integrity of the test chamber. The sealing ring 211, through its tight abutment with the skirt 21 and the mounting plate 1, can fully fill the gap between the cover 2 and the mounting plate 1, forming a continuous and uninterrupted sealing surface. This effectively prevents outside air from entering the test chamber and also prevents gas exchange between the vacuum environment inside the test chamber and the outside. A stable vacuum environment is the basis for simulating the actual working conditions of the end. If the seal fails here, the vacuum degree of the test chamber will not be able to reach the actual standard of the coating production line, and subsequent leak detection operations will lose their reference value.

[0036] Secondly, this structure enhances the fit and stability of the connection between the cover 2 and the mounting plate 1. The skirt 21 provides a fixed and precise mounting carrier for the sealing ring 211, ensuring that the sealing ring 211 is always in the critical contact area between the cover 2 and the mounting plate 1, avoiding sealing failure due to misalignment of the sealing ring 211. Simultaneously, the sealing ring 211 possesses elastic deformation characteristics; even if there are slight processing errors or assembly deviations in the cover 2 or the mounting plate 1, the sealing ring 211 can adapt to the gaps through its own deformation, further eliminating the risk of leakage caused by assembly gaps, making the structural connection of the testing chamber more stable. Furthermore, this design is crucial for ensuring the accuracy and reliability of leak detection results. The detection accuracy of the leak detector 3 is highly dependent on the sealing condition of the detection chamber. If there is a leak in the detection chamber itself, the infiltration of outside air will interfere with the capture of the helium signal, causing the leak detector 3 to be unable to accurately distinguish whether the helium comes from the end leak or the gap in the detection chamber, which may result in missed or false detections. The reliable contact between the sealing ring 211 and the skirt 21 and the mounting plate 1 eliminates the potential leakage of the detection chamber itself from the root, ensuring that the helium signal captured by the leak detector 3 comes only from the sealing defects at the end, thereby accurately identifying the tiny leaks at the end and providing a true basis for judging the sealing performance of the end.

[0037] This structure also extends the overall service life of the device. The elastic contact of the sealing ring 211 replaces the rigid contact between the skirt 21 of the cover 2 and the mounting plate 1, effectively avoiding direct collision and friction between metal parts and reducing wear and deformation of core components such as the mounting plate 1 and the cover 2. During long-term use, this flexible sealing structure can reduce the mechanical wear of the equipment. At the same time, the sealing ring 211 is easy to replace. During subsequent maintenance, only the sealing ring 211 needs to be replaced to restore the sealing performance. There is no need to carry out complex repairs or replacements of large components such as the mounting plate 1 and the cover 2, which reduces the equipment maintenance cost and ensures the continuous and stable operation of the device.

[0038] To achieve the installation and positioning of the cover 2, the mounting plate 1 is provided with a positioning pin 11 facing the cover 2, and the skirt 21 is provided with a positioning hole 21a, through which the positioning pin 11 passes. The engagement of the positioning pin 11 and the positioning hole 21a enables rapid and precise alignment of the cover 2 and the mounting plate 1, preventing misalignment during installation and ensuring that the shape and size of the test chamber formed by the cover 2 and the mounting plate 1 meet design requirements. This ensures uniform internal space within the test chamber, providing a stable and standardized environment for the end to be tested. Simultaneously, precise positioning allows the sealing ring 211 at the perimeter skirt 21 of the cover 2 to achieve uniform and tight contact with the mounting plate 1 and the skirt 21, preventing uneven stress on the sealing ring 211 due to cover 2 misalignment and resulting in sealing gaps. This further enhances the sealing reliability of the test chamber and prevents external air infiltration from interfering with the vacuum environment. Furthermore, this positioning structure simplifies the installation process of the cover 2, allowing workers to complete precise assembly without repeatedly adjusting its position, improving preparation efficiency before leak testing. In subsequent testing operations, it ensures consistency in the installation position of the cover 2 each time, reducing the impact of installation differences on leak test results and guaranteeing the stability and comparability of test data.

[0039] In the simulated vacuum leak detection device 100, the design of the mounting frame 5 and the casters 6 on the frame provides important support for the flexibility and ease of operation of the device. The mounting frame 5, as a load-bearing foundation, integrates the mounting plate 1 and its cooperating components such as the cover 2 and leak detector 3 into a stable whole, avoiding misalignment or uneven stress caused by the scattered placement of individual parts. Furthermore, adjusting the height of the mounting frame 5 allows operators to perform end-mounting and leak detection operations in a more comfortable posture, reducing labor intensity. The casters 6 completely break the fixed usage limitations of the device. Operators can easily move the device to a designated position according to the spatial layout of the production site and the adjustment needs of the leak detection station, without the need for lifting equipment or multiple people to move it. Especially when concentrated leak detection is required at the ends of multiple coating production lines, it can significantly improve the device's turnover efficiency and reduce the time cost of station switching. At the same time, the built-in braking function of the casters 6 can lock the wheels after the device reaches the target position, ensuring that the device remains stable during the leak detection process and does not affect the vacuum environment and leak detection accuracy of the testing chamber.

[0040] The above description is merely an exemplary embodiment of this application and does not limit the patent scope of this application. Any equivalent structural transformations made based on the technical concept of this application and the contents of the specification and drawings of this application, or direct / indirect applications in other related technical fields, are included within the patent protection scope of this application.

Claims

1. A leak detection device for an end cap under simulated vacuum conditions, characterized in that, include: Mounting plate; A cover is provided on the mounting plate, and the cover and the mounting plate enclose a testing chamber, which is used to accommodate the end to be tested; The leak detector is connected to the detection chamber; A vacuum generator is connected to the detection chamber; The leak detector has a first valve, which is used to control the connection between the leak detector and the detection chamber; The vacuum generator includes a forepump and a molecular pump, and also includes a main pipeline connected to the detection chamber; the forepump is connected to the main pipeline through a first branch pipeline, and the molecular pump is connected to the main pipeline through a second branch pipeline.

2. The end leak detection device under simulated vacuum conditions as described in claim 1, characterized in that, The first branch pipeline is equipped with a second valve, which is used to control the connection between the pre-pump and the detection chamber; and The second branch pipe is equipped with a third valve, which is used to control the connection between the molecular pump and the detection chamber.

3. The end leak detection device under simulated vacuum conditions as described in claim 1, characterized in that, The main pipeline is equipped with a vacuum gauge.

4. The end leak detection device under simulated vacuum conditions as described in claim 1, characterized in that, An exhaust pipe is provided on one side of the enclosure, and the exhaust pipe is equipped with a fourth valve, which is used to control the connection between the detection chamber and the outside world.

5. The end leak detection device under simulated vacuum conditions as described in any one of claims 1 to 4, characterized in that, The cover has a skirt around its perimeter, and a sealing ring is provided on the skirt facing the mounting plate. The sealing ring abuts against the skirt and the mounting plate.

6. The end leak detection device under simulated vacuum conditions as described in claim 5, characterized in that, The mounting plate is provided with a positioning pin facing the cover, and the skirt is provided with a positioning hole, through which the positioning pin passes.

7. The end leak detection device under simulated vacuum conditions as described in any one of claims 1 to 4, characterized in that, The mounting plate is provided with a first mounting port and a second mounting port, which are connected to the outside. The end cap is provided on the first mounting port and the second mounting port.

8. The end leak detection device under simulated vacuum conditions as described in any one of claims 1 to 4, characterized in that, The end leak detection device under simulated vacuum conditions also includes a mounting frame, the mounting plate is disposed on the mounting frame, and the mounting frame is equipped with casters.