A test apparatus for testing the water conductivity and water impermeability of faults
By installing multiple isolation airbags on the air supply pipe and water supply pipe, combined with an air pump and a high-pressure water pump, the problem of poor sealing of existing emboli is solved, enabling simultaneous detection in multiple areas and improving detection efficiency and sealing performance.
Patent Information
- Application Number
- CN202522300095.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-30
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-10-30
AI Technical Summary
The existing plugs have poor sealing performance, resulting in low detection efficiency. They can only block one area at a time for detection, requiring multiple changes in position, which further reduces detection efficiency.
It employs multiple flexible air and water supply pipes, and is equipped with a first, third, and second isolation airbag. Multi-zone isolation and pressurized water injection are achieved through air pumps and high-pressure water pumps. Flow and pressure are controlled by solenoid valves and pressure gauges to improve sealing and detection efficiency.
It enables simultaneous detection of multiple areas, improving detection efficiency, enhancing sealing performance, reducing the number of times the location needs to be changed, and improving the efficiency and accuracy of detection.
Smart Images

Figure CN224985283U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of coal mine construction technology, specifically to a test device for testing the water conductivity and water-tightness of faults. Background Technology
[0002] Coal mine construction refers to a series of comprehensive engineering activities carried out in order to extract coal resources. It covers the entire process from the discovery of a coalfield to the construction and commissioning of a coal mine. This process includes not only underground or open-pit mining operations, but also the construction of a large number of supporting facilities and systems.
[0003] In the early stages of mine construction, detailed exploration of the mining area is necessary. During this exploration, pumping or pressure testing of major faults is required to preliminarily evaluate their hydrogeological properties and predict the mine's water inflow. To improve the safety of coal mine construction, the current detection method typically involves sealing a section of the borehole containing the fault with a plug in the borehole that penetrates the fault, then pressurizing and injecting water into this section. By monitoring the water loss (flow rate) under different pressures, the permeability of the fault rock can be inferred. Plugs are needed for isolation during the detection process, but existing plugs have poor sealing performance and can only block one area at a time. Subsequent detections require changing the detection location and repeating the process multiple times, resulting in low detection efficiency. Therefore, improvements are needed. Utility Model Content
[0004] The purpose of this invention is to provide a test device for testing the water conductivity and water-tightness of faults, so as to solve the problems of low embolization efficiency and poor sealing performance mentioned in the background art.
[0005] To achieve the above objectives, this utility model provides the following technical solution: a test device for testing the water conductivity and water impermeability of a fault, comprising a mobile vehicle, on which a water tank and an equipment box are installed. A high-pressure water pump and an air pump are installed inside the equipment box. The inlet pipe of the high-pressure water pump is connected to the water tank, and multiple water delivery pipes are connected to the bottom of the outlet pipe of the high-pressure water pump. A first main control valve is installed on the outlet pipe of the high-pressure water pump, and a second main control valve is installed on the outlet pipe of the air pump. An air supply pipe is connected to the bottom. Both the air supply pipe and the water supply pipe are equipped with solenoid valves and pressure gauges. A main sleeve is fitted on the outer wall of the air supply pipe and the water supply pipe. A first isolation airbag, a third isolation airbag, and a second isolation airbag are fixedly connected to the outer wall of the main sleeve. A nozzle is installed on the water supply pipe. One end of the nozzle passes through the main sleeve and is located outside the main sleeve. One end of the main sleeve is inserted into the fault borehole. The outer walls of the first isolation airbag, the third isolation airbag, and the second isolation airbag are attached to the inner wall of the fault borehole.
[0006] Preferably, a lithium battery is fixedly connected inside the equipment box, and the air pump, the first main control valve, the second main control valve, the solenoid valve, the pressure gauge and the high-pressure water pump are all electrically connected to the lithium battery.
[0007] Preferably, the water delivery pipes are distributed longitudinally at equal intervals around the bottom of the outlet pipe of the high-pressure water pump, and there are at least two water delivery pipes.
[0008] Preferably, the air supply pipes are distributed longitudinally at equal intervals about the bottom of the air outlet pipe of the air pump, and there are at least two air supply pipes.
[0009] Preferably, the air supply pipe, water supply pipe, and main sleeve are all made of flexible material.
[0010] Preferably, the bottom of the mobile vehicle is equipped with self-locking casters, and a partition is fixedly connected to the bottom side of the mobile vehicle. The partition is used for storing the main sleeve between the mobile vehicle and the partition.
[0011] Preferably, handles are fixedly connected to both sides of the mobile vehicle, the mobile vehicle is integrally connected to the water tank and the equipment box, and the top of the water tank and the equipment box are provided with sealing covers.
[0012] Compared with the prior art, the beneficial effects of this utility model are: (1) This device can perform testing in multiple areas at a time, thereby reducing the number of times the testing location needs to be changed and improving testing efficiency.
[0013] (2) This device can isolate the borehole in multiple spaces by longitudinally distributing the first isolation airbag, the third isolation airbag and the second isolation airbag on the outer wall of the main casing. At the same time, the nozzles on the outer wall of the main casing can perform pressurized water injection. It can simultaneously carry out water guiding and water isolation tests at multiple locations, thereby improving the efficiency of the test.
[0014] (3) This device is equipped with an automatically expanding first partition airbag, a third partition airbag and a second partition airbag. The first partition airbag, the third partition airbag and the second partition airbag can be pressurized and tightly attached to the inner wall of the borehole to improve the sealing effect. Attached Figure Description
[0015] Figure 1 This is a schematic diagram of the test device for testing the water conductivity and water impermeability of a fault according to the present invention; Figure 2 This invention relates to a test device for testing the water conductivity and water-tightness of faults. Figure 1 Enlarged view of point A in the middle; Figure 3 This invention relates to a test device for testing the water conductivity and water-tightness of faults. Figure 1 Enlarged view at point B in the middle; Figure 4 This is a front view of the main sleeve of a test device for testing the water conductivity and water-tightness of a fault according to this utility model; Figure 5 This is a side view of the connection between the high-pressure water pump and the water delivery pipe of a test device for testing the water conductivity and water resistance of a fault, according to this utility model.
[0016] In the diagram: 1. Mobile vehicle; 2. Handle; 3. Partition; 4. Water tank; 5. Equipment box; 6. Lithium battery; 7. Air pump; 8. Main sleeve; 9. Self-locking casters; 10. First partition airbag; 11. Third partition airbag; 12. Second partition airbag; 13. First main control valve; 14. High-pressure water pump; 15. Air supply pipe; 16. Second main control valve; 17. Solenoid valve; 18. Pressure gauge; 19. Water supply pipe; 20. Nozzle. Detailed Implementation
[0017] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.
[0018] Please see Figure 1-5This utility model provides a technical solution: a test device for testing the water conductivity and water tightness of a fault, including a mobile cart 1, on which a water tank 4 and an equipment box 5 are mounted. The bottom of the mobile cart 1 is equipped with self-locking casters 9. A partition 3 is fixedly connected to the bottom side of the mobile cart 1, and the partition 3 is used to store the main sleeve 8 between the mobile cart 1 and the partition 3. This structure facilitates the storage of the main sleeve 8 after it is retracted, and also facilitates the movement of the mobile cart 1. At the same time, it ensures the stability of the mobile cart 1 when it is stopped. Handles 2 are fixedly connected to both sides of the mobile cart 1, facilitating its movement. The mobile cart 1, water tank 4, and equipment box 5 are integrally connected. The tops of the water tank 4 and equipment box 5 are equipped with sealing caps. This structure allows the water tank 4 and equipment box 5 to... For adding water and performing maintenance and cleaning, the equipment box 5 is internally connected to a lithium battery 6, an air pump 7, a first main control valve 13, a second main control valve 16, a solenoid valve 17, a pressure gauge 18, and a high-pressure water pump 14, all electrically connected to the lithium battery 6. This structure ensures the power requirements of the device. The equipment box 5 contains a high-pressure water pump 14 and an air pump 7. The inlet pipe of the high-pressure water pump 14 is connected to the water tank 4, and the bottom of the outlet pipe of the high-pressure water pump 14 is connected to multiple water delivery pipes 19. The water delivery pipes 19 are evenly spaced longitudinally about the bottom of the outlet pipe of the high-pressure water pump 14, and there are at least two water delivery pipes 19. This structure allows the water delivery pipes 19 to automatically supply water to the partition space formed between the first partition airbag 10, the third partition airbag 11, and the second partition airbag 12. The pressurized water injection system facilitates water conduction and isolation tests. The solenoid valve 17 and pressure gauge 18 on the water supply pipe 19 can detect water pressure and flow rate, allowing staff to infer the permeability of the underlying rock based on flow rate and pressure. A first main control valve 13 is installed on the outlet pipe of the high-pressure water pump 14, and a second main control valve 16 is installed on the outlet pipe of the air pump 7. An air supply pipe 15 is connected to the bottom of the air pump 7's outlet pipe, and the air supply pipes 15 are evenly spaced longitudinally about the bottom of the air pump 7's outlet pipe. There are at least two air supply pipes 15. This structure allows gas to be delivered to the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12 through multiple air supply pipes 15, thereby enabling the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12 to... The air bladder 12 inflates, and the solenoid valve 17 and pressure gauge 18 on the air supply pipe 15 control the gas flow rate and detect the pressure to ensure that the first partition air bladder 10, the third partition air bladder 11, and the second partition air bladder 12 are in a tight seal, while also preventing excessive pressure in the first partition air bladder 10, the third partition air bladder 11, and the second partition air bladder 12. The air supply pipe 15, the water supply pipe 19, and the main sleeve 8 are all made of flexible material, which facilitates the bending and storage of the main sleeve 8. Solenoid valves 17 and pressure gauges 18 are installed on both the air supply pipe 15 and the water supply pipe 19. The main sleeve 8 is fitted onto the outer wall of the air supply pipe 15 and the water supply pipe 19, and the first partition air bladder 10, the third partition air bladder 11, and the second partition air bladder 12 are fixedly connected to the outer wall of the main sleeve 8.A nozzle 20 is installed on the water supply pipe 19. One end of the nozzle 20 passes through the main casing 8 and is located outside the main casing 8. The other end of the main casing 8 is inserted into the fault borehole. The outer walls of the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12 are tightly fitted to the inner wall of the fault borehole. The experimental principle of this device is as follows: in the fault borehole, a section containing the fault is sealed with the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12. Then, water is injected into this section of the borehole under pressure. By monitoring the amount of water loss (flow rate) under different pressures, the permeability of the fault rock can be inferred. This application describes the work performed after drilling has already taken place.
[0019] Working principle: When using this testing device to test the water conductivity and water resistance of a fault, firstly, a fault hole is drilled using drilling equipment. Then, the moving vehicle 1 is moved to the top of the fault hole. Subsequently, the main sleeve 8 is unfolded and placed into the fault hole. Then, the air pump 7 is started. After the air pump 7 starts, air is supplied to the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12 through the air supply pipe 15, causing the first isolation airbag 10, the third isolation airbag 11, and the second isolation airbag 12 to inflate. 2. After expansion, it fits tightly against the inner wall of the fault cavity to achieve isolation. Then, the high-pressure water pump 14 is turned on, and the water inside the water tank 4 is transported through the water delivery pipe 19 and then injected from the nozzle 20 into the space between the first isolation airbag 10, the third isolation airbag 11 and the second isolation airbag 12 in sequence, so as to pressurize the space between the first isolation airbag 10, the third isolation airbag 11 and the second isolation airbag 12. Then, the staff can infer the permeability of the fault rock based on the pressure in the space between the first isolation airbag 10, the third isolation airbag 11 and the second isolation airbag 12.
[0020] Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A test device for testing the water conductivity and water tightness of a fault, comprising a mobile vehicle (1), characterized in that: The mobile vehicle (1) is equipped with a water tank (4) and an equipment box (5). The equipment box (5) is equipped with a high-pressure water pump (14) and an air pump (7). The inlet pipe of the high-pressure water pump (14) is connected to the water tank (4). The bottom of the outlet pipe of the high-pressure water pump (14) is connected to multiple water delivery pipes (19). The outlet pipe of the high-pressure water pump (14) is equipped with a first main control valve (13). The outlet pipe of the air pump (7) is equipped with a second main control valve (16). The bottom of the outlet pipe of the air pump (7) is connected to an air delivery pipe (15). Both the air delivery pipe (15) and the water delivery pipe (19) are equipped with solenoid valves. 17) and pressure gauge (18), the outer wall of the air supply pipe (15) and water supply pipe (19) is fitted with a main sleeve (8), the outer wall of the main sleeve (8) is fixedly connected with a first isolation airbag (10), a third isolation airbag (11) and a second isolation airbag (12), a nozzle (20) is provided on the water supply pipe (19), one end of the nozzle (20) passes through the main sleeve (8) and is located outside the main sleeve (8), one end of the main sleeve (8) is inserted into the fault borehole, and the outer walls of the first isolation airbag (10), the third isolation airbag (11) and the second isolation airbag (12) are attached to the inner wall of the fault borehole.
2. A test apparatus for testing the water conductivity and water tightness of a fault according to claim 1, characterized in that: The equipment box (5) is fixedly connected to a lithium battery (6). The air pump (7), the first main control valve (13), the second main control valve (16), the solenoid valve (17), the pressure gauge (18) and the high-pressure water pump (14) are all electrically connected to the lithium battery (6).
3. The test apparatus for testing the water conductivity and water tightness of a fault according to claim 1, characterized in that: The water delivery pipes (19) are distributed longitudinally at equal intervals at the bottom of the outlet pipe of the high-pressure water pump (14), and there are at least two water delivery pipes (19).
4. The test apparatus for testing the water conductivity and water impermeability of a fault according to claim 1, characterized in that: The air supply pipes (15) are distributed longitudinally at equal intervals about the bottom of the air outlet pipe of the air pump (7), and there are at least two air supply pipes (15).
5. The test apparatus for testing the water conductivity and water impermeability of a fault according to claim 1, characterized in that: The air supply pipe (15), water supply pipe (19) and main sleeve (8) are all made of flexible material.
6. The test apparatus for testing the water conductivity and water impermeability of a fault according to claim 1, characterized in that: The bottom of the mobile vehicle (1) is provided with self-locking casters (9), and a partition (3) is fixedly connected to the bottom side of the mobile vehicle (1). The partition (3) and the mobile vehicle (1) are used for storing the main sleeve (8).
7. The test apparatus for testing the water conductivity and water impermeability of a fault according to claim 1, characterized in that: The mobile vehicle (1) is fixedly connected to handles (2) on both sides. The mobile vehicle (1) is integrated with the water tank (4) and the equipment box (5). The top of the water tank (4) and the equipment box (5) are both equipped with sealing covers.