Component management system and management system, and component management method, and component management program

JP2023087511A5Active Publication Date: 2024-11-08MITSUBISHI HEAVY IND LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
JP2021201929
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2021-12-13
Publication Date
2024-11-08
Estimated Expiration
2041-12-13

AI Technical Summary

Technical Problem

Existing systems fail to adequately manage parts in thermal power plants, leading to potential operational risks due to the use of parts beyond their lifespan, as users face difficulties in timely ordering replacements, which can affect performance and safety.

Method used

A parts management system that estimates the remaining life of parts based on usage state and issues quotation requests in advance to ensure timely delivery, incorporating a life estimating unit and quotation request unit to manage part replacement effectively.

Benefits of technology

The system enables appropriate management of parts, ensuring timely replacement and maintaining equipment performance and safety by considering delivery dates, thereby reducing the risk of using parts beyond their lifespan.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 00000000_0000_ABST
    Figure 00000000_0000_ABST
Patent Text Reader

Abstract

To provide a component management system and management system, and a component management method, and a component management program capable of appropriately managing components.SOLUTION: A component management system 60 is a system including: a life time estimation unit 72 which estimates a residual life of an object component according to a usage state of the object component such as usage time; and a quotation requesting unit 62 which issues a quotation request for the object component when the residual life time becomes the delivery period or shorter on the basis of the residual life time and the delivery period being previously set as a delivery period required for delivering the object component.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to a parts management system, a management system, a parts management method, and a parts management program.

Background Art

[0002] Conventionally, solid fuels such as biomass fuels and coal are pulverized into fine powders within a predetermined particle size range by a pulverizer (hereinafter referred to as a "mill") and supplied to a combustion device. The mill sandwiches the solid fuel input to the pulverizing table between the pulverizing table and the pulverizing roller to pulverize it, and among the pulverized solid fuel that has become fine powder, the fine powder fuel within the predetermined particle size range is sorted by a classifier and conveyed to a boiler by a conveying gas (primary air) supplied from the outer periphery of the pulverizing table, and burned in a combustion device. In a thermal power generation plant, steam is generated by heat exchange with the combustion gas generated by burning fine powder fuel in a boiler, and the steam rotates a steam turbine to rotate a generator connected to the steam turbine, thereby generating electricity.

[0003] As described above, the mill is a device that pulverizes, dries, and classifies solid fuels. Therefore, regular maintenance such as replacement of parts (rollers, pulverizing tables, etc.) worn during operation is required. In addition, since there is a fatigue life in rotating parts such as bearings (especially rolling bearings), they cannot be used indefinitely, and regular maintenance is also required for these. Maintenance is performed, for example, as time-based maintenance (TBM) based on the usage time. In addition, condition-based maintenance (CBM) based on inspection results may also be performed. Regular maintenance is required not only for mills but also for various devices.

[0004] In Patent Document 1, it is described that the operating status of equipment is monitored to determine a maintenance inspection schedule. In Patent Document 2, it is described that when a purchase request email is received, a quotation is created based on a quotation database.

Prior Art Documents

Patent Documents

[0005] [Patent Document 1] Japanese Patent Publication No. 2001-7597 [Patent Document 2] Japanese Patent Publication No. 2002-374362 [Overview of the project] [Problems that the invention aims to solve]

[0006] Components have a limited lifespan in terms of performance and safety, and replacement should be considered once their lifespan is exceeded. This requires users (equipment users, etc.) to request quotes and place orders for the relevant components from manufacturers (equipment manufacturers, etc.). However, it can be difficult for users to properly manage components and request quotes and place orders at the appropriate time. Delays in requesting quotes and placing orders can result in insufficient preparation time for the manufacturer, potentially leading to components being used far beyond their lifespan without timely replacement. Using components far beyond their lifespan can result in suboptimal performance, damage to other components, and negatively impact the safe operation of the equipment. Therefore, proper management of components is essential.

[0007] Patent documents 1 and 2 do not take into account the manufacturer's preparation time, and there is room to further improve the manageability of parts.

[0008] This disclosure is made in view of these circumstances and aims to provide a parts management system and management system, as well as a parts management method and a parts management program that can appropriately manage parts. [Means for solving the problem]

[0009] A first aspect of this disclosure is a parts management system comprising: a life estimation unit that estimates the remaining lifespan of a target part according to its usage status; and a quotation request unit that issues a quotation request for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0010] A second aspect of this disclosure is a parts management method comprising the steps of: estimating the remaining lifespan of a target part according to its usage status; and issuing a request for quotation for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0011] A third aspect of this disclosure is a parts management program that causes a computer to perform the following processes: estimating the remaining lifespan of a target part according to its usage status; and issuing a request for quotation for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part. [Effects of the Invention]

[0012] According to this disclosure, the effect is that parts can be properly managed. [Brief explanation of the drawing]

[0013] [Figure 1] This figure shows a schematic configuration of a parts management system according to one embodiment of the present disclosure. [Figure 2] This is an example of the configuration of a management system according to one embodiment of the present disclosure. [Figure 3] This is a functional block diagram showing the functions of a parts management system according to one embodiment of the present disclosure. [Figure 4] This figure shows a specific example of a parts management function according to one embodiment of the present disclosure. [Figure 5] This figure shows a specific example of a quotation request function according to one embodiment of the present disclosure. [Figure 6] This figure shows a specific example of an electronic parts list function according to one embodiment of the present disclosure. [Figure 7] This figure shows a specific example of a document management function according to one embodiment of the present disclosure. [Figure 8] This figure shows a specific example of a data analysis function according to one embodiment of the present disclosure. [Figure 9]It is a schematic configuration diagram showing an example of the hardware configuration included in the component management system according to an embodiment of the present disclosure. [Figure 10] It is a flowchart showing an example of the procedure of the process according to an embodiment of the present disclosure. [Figure 11] It is a configuration diagram showing a solid fuel pulverizer and a boiler according to an embodiment of the present disclosure.

MODE FOR CARRYING OUT THE INVENTION

[0014] Hereinafter, an embodiment of a component management system, a management system, a component management method, and a component management program according to the present disclosure will be described with reference to the drawings.

[0015] (Overall Configuration of the System) FIG. 1 is a diagram showing a schematic configuration of a component management system 60 according to an embodiment of the present disclosure. As shown in FIG. 1, the component management system 60 according to the present embodiment has a component management function, an estimate request function, an electronic parts list function, a document management function, and a data analysis function. The component management system 60 is, for example, a system provided by a manufacturer to a user for component management.

[0016] FIG. 2 is a configuration example of a management system 70 including the component management system 60. As shown in FIG. 2, an information processing terminal 53 is connected to a network. The information processing terminal 53 is provided, for example, for each of a user and a manufacturer. A server 52 installed on the cloud or on the user side is connected to the network and can communicate with the information processing terminal 53. The server 52 has various functions of the component management system 60. By using the information processing terminal 53, it is possible to access the component management system 60 of the server 52 and view and input various information. Note that the location of each function is not limited to the case where the server 52 has it, and it can also be changed.

[0017] Figure 3 is a functional block diagram showing the functions of the parts management system 60. As shown in Figure 3, the parts management system 60 includes a parts management unit 61, a quotation request unit 62, an electronic parts list unit 63, a document management unit 64, and a data analysis unit 65.

[0018] (Parts management function) The parts management unit 61 has parts management functions. Figure 4 shows a specific example of the parts management functions in Figure 1. The parts management unit 61 manages various information about parts and products delivered to users. As shown in Figure 3, the parts management unit 61 includes a management unit 71 and a life estimation unit 72.

[0019] The management unit 71 manages information by associating each part with at least one of the following: product information, order information, location information, and time information, and creating a database (for example, 81 in Figure 4). Parts include those for which remaining life estimates are performed in order to request a quote. Parts (target parts) may include not only parts currently in use but also spare parts that the user has stored in a warehouse or elsewhere for replacement. By linking various types of information to parts, the various types of information on parts owned by the user are organized.

[0020] Product information is information relating to a product (part), and includes at least one of the following: part name, part number, drawing number, and revision number. The part name is the name of the part, and is set by the manufacturer, for example. The part number is a unique number corresponding to the part. The drawing number is the number of the drawing for the part. The revision number is a number added to the drawing number when the drawing is revised, indicating the number of revisions.

[0021] Order information is information related to an order (procurement) and includes at least one of the following: order details information and an order number. Order details information is information about the order details of the parts. The order number is a number related to the order of the parts. Order information is registered, for example, when a manufacturer receives an order for a product (part) by transferring it from the order data.

[0022] Location information refers to information relating to the location where a part (physical item) exists, and includes at least one of the following: place of use and place of storage. Place of use refers to information about the place where the part is actually used. The place of use may be, for example, information about the equipment in which the part is used. Place of storage refers to information about the place where the part is not actually used and is stored. Location information may be registered manually, or a transmitter such as an RFID may be attached to the part, and the location of each part may be obtained by a receiver (for example, 82 in Figure 4). In this case, for example, a signal containing the unique number of the part may be received from the RFID, and it may be determined that the part is near the receiving receiver.

[0023] Timing information is information related to timing and includes at least one of the following: delivery date, start of use date, start of storage date, lifespan information, and delivery date information. The delivery date is the date when the part was delivered to the user. The start of use date is the date when the part began to be used. The start of storage date is the date when the part began to be stored. Lifespan information is information about the lifespan (standard lifespan) of the part. Delivery date information is information about the delivery date (standard delivery date) of the part. Lifespan information and delivery date information are set by the manufacturer, for example.

[0024] The management unit 71 can also manage information other than that mentioned above by associating it with parts.

[0025] In particular, it is preferable that the management unit 71 associates the location of use with the usage time (operating time) for each component. The usage time may be the usage time of the component alone, or the usage time of the equipment in which the component is used. The usage time may be obtained, for example, from the control device of the equipment in question.

[0026] The life estimation unit 72 estimates the remaining life of the target component according to its usage status. Usage status refers to information managed by the management unit 71, for example, usage time (operating time). It is also possible to use other information as usage status if it is possible to estimate the remaining life. Remaining life is the time remaining until the component reaches its predetermined lifespan (limit value for usage time).

[0027] Specifically, the life estimation unit 72 obtains the lifespan (standard lifespan) and usage time of the target component from the management unit 71, and calculates the remaining lifespan by subtracting the usage time from the lifespan. However, the method for estimating the remaining lifespan is not limited to the above. In this way, the maintenance of TBM components can be made more reliable.

[0028] (Request a quote function) The quotation request unit 62 has a quotation request function. Figure 5 shows a specific example of the quotation request function in Figure 1. The quotation request unit 62 issues a quotation request for the target part. Specifically, as shown in Figure 5, it obtains various information from the parts management unit 61, etc., and automatically issues a quotation request to the manufacturer. The manufacturer uses the issued quotation request as a trigger to create and register a quotation and creates a quotation document as data. The created quotation document is sent to the user. Note that the created quotation may be sent to the user through an agent, etc., without going through the parts management system 60, if necessary. Note that not only quotation requests, but at least one of quotation creation, registration, and sending may also be automated.

[0029] Specifically, the quotation request unit 62 issues a quotation request for the target part based on the remaining lifespan and a predetermined delivery date (delivery date information) which is the period required for the delivery of the target part. Specifically, the delivery date is the period from when the manufacturer receives an order until the part is delivered to the user, and includes the period required for design, material procurement, manufacturing, transportation, etc., at the manufacturer, or a part thereof. It is preferable that the quotation request unit 62 starts processing so that the quotation request is issued from the point when the remaining lifespan of the target part becomes 0 until the delivery date.

[0030] The quotation request unit 62 issues a quotation request when the remaining lifespan falls below the delivery date. In other words, as the remaining lifespan decreases with use, a quotation request is automatically issued when it falls below the predetermined delivery date. This ensures that the delivery date is available before the end of the lifespan is reached.

[0031] When the Quotation Request Unit 62 acquires various information from the Parts Management Unit 61, etc., it is preferable to acquire information on whether or not a quotation request has been issued. For example, if a quotation request has already been issued when the remaining lifespan of the target part falls below the delivery date, the Quotation Request Unit 62 can prevent duplication of quotation requests by suspending (or canceling) the automatic issuance of the quotation request. The Quotation Request Unit 62 may also issue a follow-up email to the manufacturer inquiring about the progress of the work, such as the status of quotation creation, instead of issuing a quotation request.

[0032] Issuing a request for quotation is, for example, the process of issuing (sending) a request for quotation to a manufacturer. In this case, the user may be notified of the contents of the request for quotation issued to the manufacturer. Based on this request for quotation, the manufacturer performs the quotation work and creates a quotation. If an existing quotation system exists within the manufacturer, the system may be instructed to create the quotation. Since the request for quotation is automatically issued by the request for quotation unit 62, it is preferable that the request for quotation (request for quotation document) clearly indicates that it was automatically issued by the parts management system 60.

[0033] A request for quotation includes information such as the product to be quoted (part number, part name, drawing number, etc.), the required quantity, and the delivery date.

[0034] The timing for issuing a request for quotation is not limited to the above. For example, the time required for quotation work and ordering work (preparation period) may be considered in addition to the delivery date. In this case, the request for quotation unit 62 issues a request for quotation when the remaining lifespan is less than or equal to the sum of the delivery date, quotation period, and ordering period (procurement period) (delivery date + quotation period + ordering period). The quotation period is a predetermined period required to create a quotation, and is the period from the request for quotation until the quotation is sent to the user (the manufacturer's required period). The ordering period is a predetermined period for placing an order for the presented quotation, and is the period from when the quotation is sent to the user until the order is placed (the user's required period). This allows for issuing a request for quotation with sufficient lead time.

[0035] Furthermore, the timing of the user's budget application may also be taken into consideration. The budget application period is the time when the user applies for a budget for maintenance costs to be incurred over a certain period in the future (generally the next fiscal year) within their company, and is set in advance for each user. By taking the budget application period into consideration, problems such as budget shortages due to failure to apply for budgets for parts replacement can be suppressed. In this case, the quotation request unit 62 issues a quotation request when the timing of the user's budget application period is such that the period obtained by subtracting the period obtained by adding the delivery date, quotation period, and order period (delivery date + quotation period + order period) from the remaining lifespan is before the next budget application period. The timing of the budget application period is the timing when the set budget application period arrives. If a period is set as the budget application period, it is also possible to set the timing within the budget application period (period). In other words, if, at the time of budget application, the period obtained by subtracting the remaining lifespan (delivery date + quotation period + order period) is before the next budget application period, it can be assumed that by the time the next budget application period arrives, the remaining lifespan will not have enough leeway to cover the delivery date, etc. Therefore, issuing a request for quotation during the current budget application period makes it possible to more reliably secure the budget.

[0036] While delivery dates, quotation periods, and order periods are predetermined, they can be changed depending on the user's or manufacturer's business conditions (e.g., whether they are busy or not).

[0037] (Electronic parts list function) The electronic parts list unit 63 has an electronic parts list function. Figure 6 shows a specific example of the electronic parts list function in Figure 1. The electronic parts list unit 63 provides a list of various parts (electronic parts list). As shown in Figure 3, the electronic parts list unit 63 includes a supply unit 73 and a receiving unit 74.

[0038] The supply unit 73 provides information on the parts being supplied. That is, it provides the user with a list of parts data so that the user can check the information on each part. The information is provided, for example, by displaying the information on each part on the user's information processing terminal 53. The user can then select parts by operating the information processing terminal 53. Regarding the display of parts, as shown in Figure 6, it may be possible to narrow down the selection from large configurations in a hierarchical order. That is, the information on parts is linked in a hierarchical order from large configurations (groups of multiple parts) to small configurations (groups of fewer parts than large configurations). For example, the hierarchy may be divided in the order of boiler unit selection, mill unit selection, assembly selection, sub-assembly selection, sub-sub-assembly selection, and part selection. It is preferable to use bird's-eye views or 3D diagrams for the selection options to make them easier to visualize. The displayed diagrams do not necessarily show the exact shape of the product, but may represent the general shape of the product. Also, on the screen for selecting parts, it is preferable to display exploded views so that the installation location of the parts can be seen. When selecting parts, the user may click on the parts in the exploded view directly, or they may click on the numbers assigned to the parts. When selecting a part, it is desirable to be able to check information such as the part's "part name," "part number," "drawing number," "weight," "quantity used," and "unit."

[0039] In this way, users can access and verify information about the delivered parts through the system. The information about the provided parts may, for example, be linked to the manufacturer's system. That is, it is preferable that the part information be updated to the latest state.

[0040] The reception unit 74 accepts orders for parts (quote requests or procurement requests) based on the information provided by the supply unit 73. In other words, users can order parts through the system. Orders are placed by operating the user's information processing terminal 53. An order can be a purchase order (procurement request) or a quotation request. For example, it has a shopping cart function, allowing users to select parts, add them to the cart, and place an order. It may also be possible to set the quantity of parts, desired delivery date, and other information. Once an order is placed, the order details (e.g., quotation request) are sent to the manufacturer.

[0041] (Document management function) The document management unit 64 has document management functions. Figure 7 shows a specific example of the document management functions in Figure 1. The document management unit 64 manages electronic data of documents related to various parts. As shown in Figure 3, the document management unit 64 includes a document storage unit 75 and a document provision unit 76.

[0042] The document storage unit 75 stores electronic data of documents related to the parts being delivered. In other words, the document storage unit 75 holds document data such as drawings and instruction manuals. When revisions to documents occur, such as corrections to drawings, it is preferable that the electronic data is updated with the latest information. It is preferable that attribute information (for example, "drawing number" (which may be called a document number), "revision number," "name" (document name), "revision date," etc.) is registered along with the electronic data in the document.

[0043] The document provision unit 76 provides electronic data of the relevant document in response to a request to view a stored document. For example, if a document for a certain part is selected (i.e., a viewing request is made) by operating the user's information processing terminal 53, the electronic data of the document for that part is displayed (viewed) on the user's information processing terminal 53, thereby providing the data. When a viewing request is made, the document data may be downloaded from the cloud or from a server 52 installed on the manufacturer's side. Alternatively, a tag such as RFID or a QR code (registered trademark) may be attached to the product, and by reading the tag or QR code (registered trademark) with an information terminal, a list of documents related to that product may be displayed. A search function may also be used to narrow down the results. From an information management perspective, it is preferable that logs are kept when various processes such as viewing, downloading, copying, and printing of documents are performed.

[0044] (Data analysis function) The data analysis unit 65 has a data analysis function. Figure 8 shows a specific example of the data analysis function in Figure 1. The data analysis unit 65 performs data analysis based on the input data. In particular, it performs data analysis to estimate the remaining lifespan. For this reason, the data analysis unit 65 is equipped with a lifespan analysis unit 77.

[0045] The life analysis unit 77 estimates the remaining life of a target part based on measurement data related to the target part. For example, when a product (part) is inspected by a user or manufacturer and measurement data is registered as a result of the inspection, the remaining life is analyzed. The measurement data could be, for example, the wear amount of the grinding roller 13 of a mill. By linking the input wear amount with the operating time of the equipment, a graph of the wear amount trend is created, and the remaining life until the wear reaches a predetermined upper limit can be estimated from this approximate line or curve. Alternatively, a wear contour diagram (a diagram showing the current shape of the grinding roller 13 based on the wear amount measurement data) may be output. By comparing the output wear contour diagrams over time, it is possible to visually grasp the progress of wear. Note that the measurement data is not limited to wear amount data; other parameters can also be used.

[0046] Once the remaining lifespan is estimated by the lifespan analysis unit 77, the quotation request unit 62 issues a quotation request for the target part based on the remaining lifespan and delivery date, as described above. This makes it possible to request quotations for parts that are subject to CBM (Condition-Based Manufacturing).

[0047] Figure 9 is a schematic diagram showing an example of the hardware configuration of a parts management system 60 according to one embodiment of the present invention. The same applies to the hardware configuration of the information processing device. As shown in Figure 9, the parts management system 60 is a so-called computer and includes, for example, a CPU (Central Processing Unit) 1100, main memory 1200, storage unit 1300, external interface 1400, communication interface 1500, input unit 1600, and display unit 1700. These units are interconnected directly or indirectly via a bus and work together to perform various processes.

[0048] The CPU 1100 controls the entire components management system 60 using an OS (Operating System) stored in a memory unit 1300 connected via a bus, and also performs various processes by executing various programs stored in the memory unit 1300.

[0049] The main memory 1200 consists of writable memory such as cache memory and RAM (Random Access Memory), and is used as a work area for reading the CPU 1100's executable program and writing processing data by the executable program.

[0050] The storage unit 1300 is a non-transitory computer-readable storage medium, such as ROM (Read Only Memory), HDD (Hard Disk Drive), or flash memory. The storage unit 1300 stores, for example, an OS for controlling the entire device such as Windows®, iOS®, or Android®, a BIOS (Basic Input / Output System), various device drivers for hardware operation of peripheral devices, various application software, and various data and files. The storage unit 1300 also stores programs for implementing various processes and various data necessary for implementing those processes.

[0051] The external interface 1400 is an interface for connecting to external devices. Examples of external devices include external monitors, USB memory sticks, and external HDDs. Although only one external interface is shown in the example in Figure 1, the system may have multiple external interfaces.

[0052] The communication interface 1500 functions as an interface for connecting to a network, communicating with other devices, and sending and receiving information. For example, the communication interface 1500 communicates with other devices, for example, via wired or wireless connection. Examples of wireless communication include Bluetooth®, Wi-Fi, and communication using a dedicated communication protocol. An example of wired communication is a wired LAN (Local Area Network).

[0053] The input unit 1600 is a user interface for giving instructions, such as a keyboard, mouse, or touchpad.

[0054] The display unit 1700 may be, for example, a liquid crystal display, an organic EL (electroluminescence) display, or the like. Alternatively, the display unit 1700 may be a touch panel display with a touch panel superimposed on it.

[0055] Each of the aforementioned functions is implemented, for example, by processing circuitry. For example, a series of processes to implement the following functions are stored in the memory unit 1300 in the form of a program, and the CPU 1100 reads this program into the main memory 1200 and performs information processing and calculations to realize the various functions.

[0056] The program may be provided in various forms, such as being pre-installed in the storage unit 1300, stored on another computer-readable storage medium, or distributed via wired or wireless communication. Computer-readable storage media include magnetic disks, magneto-optical disks, CD-ROMs, DVD-ROMs, and semiconductor memory.

[0057] (Processing flow using the parts management system) Next, an example of the quotation request processing by the parts management system 60 described above will be explained with reference to Figure 10. Figure 10 is a flowchart showing an example of the procedure for the quotation request processing according to this embodiment. The flow shown in Figure 10 is executed repeatedly, for example, at a predetermined control cycle. It is preferable that the management unit 71 updates with the latest information.

[0058] First, the remaining lifespan is estimated based on the information managed by the management unit 71 (S101). Specifically, when the lifespan estimation unit 72 performs the processing, the remaining lifespan is calculated by subtracting the usage time from the lifespan. When the lifespan analysis unit 77 performs the processing, the remaining lifespan is estimated based on the measurement data.

[0059] Next, it is determined whether the remaining lifespan is less than or equal to the delivery date (S102). For S102, the estimation period may be considered as described above, or the budget application period may be considered.

[0060] If the remaining lifespan is not less than or equal to the delivery date (NO judgment in S102), the process is terminated.

[0061] If the remaining lifespan falls below the delivery date (YES judgment in S102), a request for quotation is issued (S103). The issued request for quotation is sent to the manufacturer.

[0062] In this way, the timing of issuing a quotation request is determined by considering the predetermined delivery date. This ensures that the required delivery period is secured before the part reaches the end of its lifespan, allowing for proper maintenance and thus enabling proper management of parts.

[0063] (Power plant configuration) Next, an example of a power plant 1 to which the parts management system 60 is applied will be described. The parts management system 60 can be applied, for example, to each part used in the power plant 1.

[0064] The power plant 1 according to this embodiment includes a solid fuel crushing device 100 and a boiler 200. In the following explanation, "upper" refers to the direction vertically upward, and "upper" in terms such as "top" or "upper surface" refers to the vertically upward part. Similarly, "down" refers to the vertically downward part, and the vertical direction is not strictly accurate and contains some margin of error.

[0065] The solid fuel crushing apparatus 100 of this embodiment is a device that crushes solid fuels such as biomass fuel or coal to produce fine fuel powder, which is then supplied to the burner (combustion device) 220 of the boiler 200. The power plant 1 shown in Figure 11, which includes a solid fuel grinder 100 and a boiler 200, is equipped with one solid fuel grinder 100, but it may also be a system equipped with multiple solid fuel grinders 100, each corresponding to one of the multiple burners 220 of a single boiler 200.

[0066] The solid fuel crushing apparatus 100 of this embodiment includes a mill (crushing section) 10, a bunker (storage section) 21, a coal feeder (fuel supply unit) 25, a blower (conveyor gas supply section) 30, a state detection unit 40, and a control unit 50.

[0067] The mill 10, which grinds solid fuels such as coal and biomass fuel supplied to the boiler 200 into finely powdered solid fuel, may be configured to grind only coal, only biomass fuel, or both coal and biomass fuel. Here, biomass fuel refers to renewable, biologically derived organic resources, such as thinned timber, waste wood, driftwood, grass, waste materials, sludge, tires, and recycled fuels (pellets and chips) made from these materials, and is not limited to those listed here. Because biomass fuels absorb carbon dioxide during the growth process of biomass, they do not emit carbon dioxide, which is a greenhouse gas, and are therefore considered carbon neutral, and their use is being explored in various ways.

[0068] The mill 10 comprises a housing 11, a grinding table 12, a grinding roller 13, a reduction gear (drive transmission unit) 14, a mill motor (drive unit) 15 connected to the reduction gear 14 and rotatingly driving the grinding table 12, a rotary classifier (classification unit) 16, a coal supply pipe (fuel supply unit) 17, and a classifier motor 18 that rotately drives the rotary classifier 16. The housing 11 is formed in a cylindrical shape extending vertically and is a casing that houses the crushing table 12, the crushing rollers 13, the rotary classifier 16, and the coal supply pipe 17. A coal supply pipe 17 is installed in the center of the ceiling portion 42 of the housing 11. This coal supply pipe 17 supplies solid fuel, which has been guided from the bunker 21 via the coal feeder 25, into the housing 11. It is positioned vertically at the center of the housing 11, and its lower end extends into the interior of the housing 11.

[0069] A reduction gear 14 is installed near the bottom surface 41 of the housing 11, and a grinding table 12, which rotates due to the driving force transmitted from a mill motor 15 connected to this reduction gear 14, is rotatably positioned there. The crushing table 12 is a circular member in plan view, and is positioned so that the lower ends of the coal supply pipe 17 face each other. The upper surface of the crushing table 12 may have a sloping shape, for example, with the center being lower and the outer surface becoming higher towards the outside, and the outer circumference being bent upward. The coal supply pipe 17 supplies solid fuel (for example, coal or biomass fuel in this embodiment) from above to the crushing table 12 below, and the crushing table 12 crushes the supplied solid fuel by sandwiching it between the crushing rollers 13.

[0070] When solid fuel is fed from the coal supply pipe 17 toward the center of the crushing table 12, the centrifugal force from the rotation of the crushing table 12 guides the solid fuel toward the outer periphery of the crushing table 12, where it is crushed between the crushing table 12 and the crushing rollers 13. The crushed solid fuel is blown upward by the conveying gas (hereinafter referred to as primary air) introduced from the conveying gas passage (hereinafter referred to as primary air passage) 110 and guided toward the rotary classifier 16. The outer circumference of the grinding table 12 is provided with an outlet (not shown) that allows primary air flowing in from the primary air passage 110 to flow out into the space above the grinding table 12 inside the housing 11. A swirling blade (not shown) is installed at the outlet, which imparts a swirling force to the primary air blown out from the outlet. The primary air, given a swirling force by the swirling blade, becomes an airflow with a swirling velocity component, which transports the solid fuel ground on the grinding table 12 to the rotary classifier 16 located above the housing 11. Of the ground solid fuel, those larger than a predetermined particle size are classified by the rotary classifier 16, or they fall without reaching the rotary classifier 16 and are returned to the grinding table 12, where they are ground again between the grinding table 12 and the grinding roller 13.

[0071] The crushing roller 13 is a rotating body that crushes the solid fuel supplied from the coal supply pipe 17 onto the crushing table 12. The crushing roller 13 is pressed against the upper surface of the crushing table 12 and works in cooperation with the crushing table 12 to crush the solid fuel. Although only one grinding roller 13 is shown as a representative example in Figure 11, multiple grinding rollers 13 are arranged at regular intervals in the circumferential direction to press against the upper surface of the grinding table 12. For example, three grinding rollers 13 are arranged at equal intervals in the circumferential direction with a 120° angle interval on the outer circumference. In this case, the parts of the three grinding rollers 13 that contact (press) the upper surface of the grinding table 12 are at equal distances from the rotational axis of the grinding table 12.

[0072] The crushing roller 13 is capable of vertical oscillation and displacement by the journal head 45 and is supported so as to be able to move closer to and further away from the upper surface of the crushing table 12. When the crushing table 12 rotates, the crushing roller 13 rotates along with the crushing table 12 as the crushing table 12 rotates, receiving a rotational force from the crushing table 12. When solid fuel is supplied from the coal supply pipe 17, the solid fuel is pressed and crushed between the crushing roller 13 and the crushing table 12. This pressing force is called the crushing load.

[0073] The support arm 47 of the journal head 45 is supported by a support shaft 48 whose intermediate portion is aligned horizontally, allowing the crushing roller 13 to swing and displace vertically around the support shaft 48 on the side surface of the housing 11. A pressing device (crushing load application unit) 46 is provided at the upper end of the support arm 47, which is vertically above it. The pressing device 46 is fixed to the housing 11 and applies a crushing load to the crushing roller 13 via the support arm, etc., so as to press the crushing roller 13 against the crushing table 12. The crushing load is applied, for example, by a hydraulic cylinder (not shown) that is operated by the pressure of hydraulic fluid supplied from a hydraulic device (not shown) installed outside the mill 10. Alternatively, the crushing load may be applied by the repulsive force of a spring (not shown).

[0074] The reduction gear 14 is connected to the mill motor 15 and transmits the driving force of the mill motor 15 to the grinding table 12, causing the grinding table 12 to rotate around its central axis.

[0075] The rotary classifier (classification unit) 16 is located on the upper part of the housing 11 and has a hollow, inverted conical outer shape. The rotary classifier 16 is equipped with a plurality of blades 16a extending vertically on its outer circumference. Each blade 16a is provided at a predetermined interval (equal intervals) around the central axis of the rotary classifier 16. The rotary classifier 16 is a device that classifies solid fuel crushed by the crushing table 12 and crushing rollers 13 (hereinafter, the crushed solid fuel will be referred to as "crushed fuel") into particles larger than a predetermined particle size (for example, 70-100 μm for coal) (hereinafter, crushed fuel with a particle size exceeding the predetermined particle size will be referred to as "coarse fuel") and particles smaller than the predetermined particle size (hereinafter, crushed fuel with a particle size smaller than the predetermined particle size will be referred to as "fine fuel"). The rotary classifier 16 is driven by a classifier motor 18 controlled by the control unit 50 and rotates around the coal supply pipe 17 around a cylindrical shaft (not shown) that extends vertically in the housing 11. Furthermore, a fixed classifier may be used as the classification unit, which has a fixed, hollow, inverted cone-shaped casing and a plurality of fixed swivel blades instead of blades 16a on the outer circumference of the casing.

[0076] The crushed fuel that reaches the rotary classifier 16 is subjected to a relative balance between the centrifugal force generated by the rotation of the blades 16a and the centripetal force from the airflow of the primary air. Larger diameter coarse fuel particles are knocked off by the blades 16a and returned to the crushing table 12 for further crushing, while the fine fuel particles are guided to the outlet port 19 located in the ceiling 42 of the housing 11. The fine fuel particles classified by the rotary classifier 16 are discharged along with the primary air from the outlet port 19 into the fine fuel supply channel (fine fuel supply pipe) 120 and supplied to the burner 220 of the boiler 200.

[0077] The coal supply pipe (fuel supply section) 17 is installed with its lower end extending vertically into the interior of the housing 11, penetrating the ceiling 42 of the housing 11, and supplies solid fuel fed from the top of the coal supply pipe 17 to the center of the crushing table 12. A coal feeder 25 is connected to the upper end of the coal supply pipe 17, and solid fuel is supplied to it.

[0078] The coal feeder 25 is connected to the bunker 21 by a downspout section 22, which is a pipe extending vertically from the lower end of the bunker 21. A valve (coal gate, not shown) for switching the discharge state of solid fuel from the bunker 21 may be provided in the middle of the downspout section 22. The coal feeder 25 includes a conveying section 26 and a coal feeder motor 27. The conveying section 26 is, for example, a belt conveyor, which, driven by the coal feeder motor 27, conveys the solid fuel discharged from the lower end of the downspout section 22 to the upper part of the coal supply pipe 17 and feeds it into the mill. The amount of solid fuel supplied to the mill 10 is controlled by a signal from the control unit 50, for example, by adjusting the moving speed of the belt conveyor of the conveying section 26.

[0079] Normally, primary air is supplied to the mill 10 to transport the fine fuel to the burner 220, and the pressure is higher than that of the coal feeder 25 and bunker 21. Inside the downspout section 22 connecting the bunker 21 and the coal feeder 25, the fuel is in a layered state. This solid fuel layer ensures a sealing effect (material seal) to prevent backflow of primary air and fine fuel from the mill 10 to the bunker 21.

[0080] The blower unit 30 is a device that blows primary air into the housing 11 to dry the crushed fuel and to transport it to the rotary classifier 16. In this embodiment, the blower unit 30 includes a primary air fan (PAF) 31, a hot gas passage 30a, a cold gas passage 30b, a hot gas damper 30c, and a cold gas damper 30d in order to appropriately adjust the flow rate and temperature of the primary air blown into the housing 11.

[0081] In this embodiment, the hot gas flow path 30a supplies a portion of the air sent from the primary air ventilator 31 as hot gas that has been heated by passing it through the air preheater (heat exchanger) 34. A hot gas damper 30c is provided in the hot gas flow path 30a. The opening degree of the hot gas damper 30c is controlled by the control unit 50. The flow rate of the hot gas supplied from the hot gas flow path 30a is determined by the opening degree of the hot gas damper 30c.

[0082] The cold gas passage 30b supplies a portion of the air discharged from the primary air ventilator 31 as cold gas at room temperature. A cold gas damper 30d is provided in the cold gas passage 30b. The opening degree of the cold gas damper 30d is controlled by the control unit 50. The opening degree of the cold gas damper 30d determines the flow rate of cold gas supplied from the cold gas passage 30b.

[0083] In this embodiment, the flow rate of the primary air is the sum of the flow rate of the hot gas supplied from the hot gas channel 30a and the flow rate of the cold gas supplied from the cold gas channel 30b. The temperature of the primary air is determined by the mixing ratio of the hot gas supplied from the hot gas channel 30a and the cold gas supplied from the cold gas channel 30b, and is controlled by the control unit 50. Furthermore, the oxygen concentration in the primary air blown into the housing 11 from the primary air passage 110 may be adjusted by introducing a portion of the combustion gas discharged from the boiler 200 by, for example, a gas recirculation ventilator (not shown) into the hot gas supplied from the hot gas passage 30a and mixing it. By adjusting the oxygen concentration in the primary air, for example, when using a highly ignitable (easily ignited) solid fuel, it is possible to suppress the ignition of the solid fuel in the path from the mill 10 to the burner 220.

[0084] In this embodiment, the state detection unit 40 of the mill 10 measures or detects data which is then transmitted to the control unit 50. The state detection unit 40 in this embodiment is, for example, a differential pressure measuring means which measures the differential pressure of the mill 10 between the pressure at the point where primary air flows from the primary air passage 110 into the inside of the housing 11 and the pressure at the outlet port 19 where primary air and fine fuel are discharged from the inside of the housing 11 into the fine fuel supply passage 120. The increase or decrease in this differential pressure of the mill 10 corresponds to an increase or decrease in the circulation amount of the grinding fuel circulating between the vicinity of the rotary classifier 16 and the vicinity of the grinding table 12 inside the housing 11 due to the classification effect of the rotary classifier 16. In other words, by adjusting the rotational speed of the rotary classifier 16 in accordance with the differential pressure of the mill 10, the amount and particle size range of the fine fuel discharged from the outlet port 19 can be adjusted. This allows for a stable supply of a quantity of fine fuel corresponding to the amount of solid fuel supplied to the mill 10 to the burner 220 in the boiler 200, while maintaining the particle size of the fine fuel within a range that does not affect the combustibility of the solid fuel in the burner 220. Furthermore, the state detection unit 40 in this embodiment is, for example, a temperature measuring means, which detects the temperature of the primary air supplied into the housing 11 (primary air temperature at the mill inlet) and the temperature of the mixed gas of primary air and pulverized fuel at the outlet port 19 (primary air temperature at the mill outlet), and controls the air blower 30 so that the respective upper limits of the temperatures do not exceed. Each upper limit of temperature is determined considering the possibility of ignition according to the properties of the solid fuel. Note that the primary air is cooled inside the housing 11 as the pulverized fuel is dried and transported, so the primary air temperature at the mill inlet is, for example, around 300 degrees Celsius from room temperature, and the primary air temperature at the mill outlet is, for example, around 90 degrees Celsius from room temperature.

[0085] The control unit 50 is a device that controls each part of the solid fuel crushing apparatus 100. The control unit 50 may, for example, transmit a drive command to the mill motor 15 to control the rotation speed of the grinding table 12. The control unit 50, for example, transmits a drive command to the classifier motor 18 to control the rotational speed of the rotary classifier 16 and adjust the classification performance, thereby maintaining the particle size of the fine fuel within a range that does not affect the combustibility of the solid fuel in the burner 220, and stably supplying an amount of fine fuel corresponding to the amount of solid fuel supplied to the mill 10 to the burner 220. Furthermore, the control unit 50 can adjust the amount of solid fuel supplied to the mill 10 (coal supply amount) by, for example, transmitting a drive instruction to the coal feeder motor 27. Furthermore, the control unit 50 can adjust the flow rate and temperature of the primary air by controlling the opening of the hot gas damper 30c and the cold gas damper 30d by transmitting an opening instruction to the blower unit 30. Specifically, the control unit 50 controls the opening of the hot gas damper 30c and the cold gas damper 30d so that the flow rate of the primary air supplied into the housing 11 and the temperature of the primary air at the outlet port 19 (mill outlet primary air temperature) are set to predetermined values ​​corresponding to the amount of coal supplied for each type of solid fuel. Note that the control of the primary air temperature may also be performed with respect to the temperature at the mill inlet (mill inlet primary air temperature).

[0086] The control unit 50 is composed of, for example, a CPU (Central Processing Unit), RAM (Random Access Memory), ROM (Read Only Memory), and a computer-readable storage medium. A series of processes for realizing various functions are stored in the storage medium in the form of a program, for example. The CPU reads this program into the RAM and performs information processing and calculations to realize the various functions. The program may be pre-installed in the ROM or other storage medium, provided in a state where it is stored in a computer-readable storage medium, or distributed via wired or wireless communication. Computer-readable storage media include magnetic disks, magneto-optical disks, CD-ROMs, DVD-ROMs, and semiconductor memory. HDDs may be replaced with solid-state disks (SSDs), etc.

[0087] Next, a boiler 200 that generates steam by burning fine fuel supplied from a solid fuel crushing device 100 will be described. The boiler 200 is equipped with a furnace 210 and a burner 220.

[0088] The burner 220 is a device that burns the pulverized fuel to form a flame using a mixture of pulverized fuel and primary air supplied from the pulverized fuel supply channel 120, and secondary air supplied by heating air (outside air) sent from the forced graft fan (FDF) 32 in the air preheater 34. The combustion of the pulverized fuel takes place in the furnace 210, and the high-temperature combustion gas is discharged to the outside of the boiler 200 after passing through heat exchangers such as evaporators, superheaters, and economizers (not shown).

[0089] The combustion gas discharged from the boiler 200 undergoes predetermined treatment in environmental equipment (denitrification equipment, dust collector, desulfurization equipment, etc., not shown), and heat exchange with primary and secondary air takes place in the air preheater 34. The gas is then guided to the chimney (not shown) via the induced draft fan (IDF) 33 and released into the outside air. The air heated by the combustion gas in the air preheater 34 and sent out from the primary air fan 31 is supplied to the aforementioned hot gas flow path 30a. The feedwater to each heat exchanger of the boiler 200 is heated in an economizer (not shown), then further heated in an evaporator (not shown) and a superheater (not shown) to generate high-temperature, high-pressure superheated steam, which is sent to a steam turbine (not shown), which is the power generation unit, to rotate the steam turbine, and then rotates a generator (not shown) connected to the steam turbine to generate electricity, thus constituting the power plant 1.

[0090] The solid fuels used are not limited to those disclosed herein, and may include coal, biomass fuels, petroleum coke (PC), etc. Furthermore, a combination of these solid fuels may be used.

[0091] Thus, power plant 1 is composed of numerous pieces of equipment and has a complex structure, with a vast number of parts used in each piece of equipment. Therefore, by applying the parts management system 60, it becomes possible to properly maintain each piece of equipment.

[0092] As described above, according to the parts management system, management system, parts management method, and parts management program of this embodiment, the remaining lifespan of the target part is estimated based on its usage status, and a quotation request is issued based on this remaining lifespan and the delivery date (the period required to deliver the target part), making it possible to make a quotation while taking the delivery date into consideration. As a result, even users who have difficulty grasping the delivery date can make a quotation request with sufficient remaining lifespan, and can carry out appropriate maintenance such as replacement of the target part.

[0093] For users, tasks such as requesting quotes and confirming component configurations, which were previously cumbersome, are now provided in an organized electronic database format through the component management system 60, thus simplifying component management. For manufacturers, the need to provide quotes and deliveries when components have little or no remaining lifespan remaining is reduced. Information is shared between both users and manufacturers, resulting in more efficient component management.

[0094] This disclosure is not limited to the embodiments described above, and various modifications are possible without departing from the spirit of the invention.

[0095] The parts management system 60 is preferably linked with the user's system (control system such as DCS) and the manufacturer's system (system such as BOM), and information is synchronized between them. For important data that should not be altered by the user or manufacturer, it is desirable to protect the data flow by providing a data diode function or the like to ensure a one-way flow.

[0096] The parts management function can also be used to manage the maintenance schedule for parts in storage. For example, by notifying users when it is time to reapply rust-preventive oil to machined surfaces or when it is time to manually turn rotating parts, sound storage management can be achieved. The parts management function could include a link to the electronic parts list. In other words, it would be possible to allow users to order spare parts before the maintenance period arrives. Regarding the quotation request function, it is desirable that the format of the quotation request be the same for all users. Furthermore, it is desirable that the format be the same as that of quotation requests from the electronic parts list. Regarding the quotation request function, a mechanism could be implemented where the manufacturer's relevant department periodically updates the standard delivery time and quotation period. Specifically, a system could be implemented where a blank quotation is issued to the manufacturer at any time, and the quotation period and delivery time are updated as the standard based on the results. To improve usability, the electronic parts list could include features such as "order history," "favorites list (bookmarks)," and "recommended related parts function (recommendations)." It is preferable that the electronic parts list be configured to allow users to request quotes (procurements) for assembled products as well as individual parts. This configuration is not limited to the drawing and can be freely determined. Furthermore, for set components that are not sold individually, the individual purchase function may be removed, and only the set can be selected. The document management function could, for example, detect the movement of a part from mill A to mill B using an RFID tag and a field receiver, and reflect this in the search results for the drawing. Regarding the document management function, it is also possible to embed links to owned documents in appropriate locations within other functions, allowing related documents to be accessed from those functions. For data analysis functions, it is desirable that data input be presented in a tabular format, with links to the data and a list of operating times during measurement. The output of the data analysis function can be, for example, a 3D contour plot (colored map), or a graph or other type of diagram. Alternatively, a function to output in report format may also be provided.

[0097] The parts management system and management system, as well as the parts management method and parts management program described in each embodiment above, can be understood, for example, as follows. The parts management system (60) relating to this disclosure includes a life estimation unit (72) that estimates the remaining lifespan of a target part according to its usage status, and a quotation request unit (62) that issues a quotation request for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0098] According to the parts management system (60) related to this disclosure, the remaining lifespan of the target part is estimated based on its usage status, and a request for quotation is issued based on this remaining lifespan and the delivery date (the period required for delivery of the target part). This makes it possible to make quotations while taking the delivery date into consideration. As a result, even users who have difficulty keeping track of delivery dates can make quotation requests with ample remaining lifespan, enabling them to properly perform maintenance such as replacing the target part, and thus enabling proper parts management.

[0099] The parts management system (60) relating to this disclosure may also have the quotation request unit (62) issue a quotation request when the remaining lifespan falls below the delivery date.

[0100] According to the parts management system (60) described herein, it is possible to ensure a sufficient period of time for delivery before the parts reach the end of their lifespan, thereby preventing the target parts from being operated far beyond their lifespan.

[0101] The parts management system (60) relating to this disclosure may also have the quotation request unit (62) issue a quotation request when the remaining lifespan is less than or equal to the sum of the delivery date, the quotation period set in advance as the period required to prepare the quotation, and the order period set in advance as the period for placing an order based on the quotation.

[0102] According to the parts management system (60) disclosed herein, it becomes possible to perform maintenance such as replacement of target parts more safely by ensuring quotation and ordering periods.

[0103] The parts management system (60) relating to this disclosure may also have the quotation request unit (62) issue the quotation request when it is the time when the user of the target parts submits a budget request, and the time obtained by subtracting from the remaining lifespan the delivery date, a predetermined quotation period for preparing a quotation, and a predetermined ordering period for placing an order based on the quotation is before the next budget request period.

[0104] According to the parts management system (60) disclosed herein, it is possible to request quotations at the same time as the budget application period, making it easier to align with the budget. Furthermore, by setting the period obtained by subtracting the delivery date, quotation period, and ordering period from the remaining lifespan to be before the next budget application period, it becomes possible to issue quotations at a budget application period that is close to the end of the product's lifespan.

[0105] The parts management system (60) relating to this disclosure includes a management unit (71) that manages information by associating at least one of product information, order information, location information, and timing information with the target parts, wherein the product information may be at least one of part name, part number, drawing number, and revision number; the order information may be at least one of order details information and order number; the location information may be at least one of usage location and storage location; and the timing information may be at least one of delivery time, start of use time, start of storage time, lifespan information, and delivery date information.

[0106] According to the parts management system (60) disclosed herein, it becomes possible to manage target parts in detail. By associating each piece of information with the target parts, information can be organized efficiently.

[0107] The parts management system (60) relating to this disclosure may include a supply unit (73) that provides information on parts being delivered, and a reception unit (74) that accepts orders for parts based on the provided information.

[0108] According to the parts management system (60) related to this disclosure, by providing information on parts being supplied and accepting orders based on the provided information, it is possible to facilitate parts selection at the customer's location.

[0109] The parts management system (60) relating to this disclosure may be configured such that the parts information provided by the supply unit (73) is linked in a hierarchical order from larger to smaller components.

[0110] According to the parts management system (60) related to this disclosure, parts become easier to find by linking them in a hierarchical order.

[0111] The parts management system (60) relating to this disclosure may also include a document storage unit (75) for storing electronic data of documents relating to parts being delivered, and a document provision unit (76) for providing the electronic data of the relevant documents in response to a request to view the stored documents.

[0112] According to the parts management system (60) related to this disclosure, it is possible to improve convenience compared to using actual paper documents by storing electronic data of documents relating to delivered parts and providing the electronic data of the relevant documents upon request.

[0113] The parts management system (60) relating to this disclosure includes a life analysis unit (77) that estimates the remaining life of the target parts based on measurement data of the target parts, and the quotation request unit (62) may issue the quotation request for the target parts based on the remaining life based on the measurement data and the delivery date.

[0114] According to the parts management system (60) related to this disclosure, the remaining lifespan is estimated based on measurement data, and a request for quotation is issued taking delivery time into consideration, thereby enabling the issuance of a request for quotation for condition-based maintenance (CBM) parts as well.

[0115] The parts management system (60) relating to this disclosure may also define the target parts as spare parts.

[0116] According to the parts management system (60) described herein, maintenance of spare parts can also be made easier. The parts management system (60) relating to this disclosure includes a life analysis unit (77) that estimates the remaining lifespan of a target part based on measurement data of the target part, and a quotation request unit (62) that issues a quotation request for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0117] According to the parts management system (60) related to this disclosure, the remaining lifespan is estimated based on measurement data, and a request for quotation is issued taking delivery time into consideration, thereby enabling the issuance of a request for quotation for condition-based maintenance (CBM) parts as well.

[0118] The management system (70) relating to this disclosure comprises an information processing terminal (53) connected to a network, and a server (52) that has the functions of the above-mentioned parts management system (60) and communicates with the information processing terminal (53) via the network.

[0119] According to the management system (70) related to this disclosure, the server has the functions of the parts management system (60), which improves the convenience of parts management using the information processing terminal (53).

[0120] The parts management method relating to this disclosure includes the steps of: estimating the remaining lifespan of a target part according to its usage status; and issuing a request for quotation for the target part based on the remaining lifespan and a predetermined delivery date for the period required for the delivery of the target part.

[0121] The parts management method relating to this disclosure includes the steps of: estimating the remaining lifespan of a target part based on measurement data of the target part; and issuing a request for quotation for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0122] The parts management program relating to this disclosure causes a computer to perform the following processes: estimating the remaining lifespan of a target part according to its usage status; and issuing a request for a quote for the target part based on the remaining lifespan and a predetermined delivery date for the period required for the delivery of the target part.

[0123] The parts management program relating to this disclosure causes a computer to perform the following processes: estimating the remaining lifespan of a target part based on measurement data of the target part; and issuing a request for quotation for the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part.

[0124] The parts management method relating to this disclosure includes the steps of: estimating the remaining lifespan of a target part according to the user's usage status of the target part; and issuing a request for a quote for the target part to the manufacturer of the target part based on the remaining lifespan and a delivery date predetermined as the period required for the delivery of the target part. [Explanation of symbols]

[0125] 1. Power plant 10 Mill (grinding section) 11 Housing 12 Grinding Tables 13 Crushing rollers 14. Reducer (drive transmission unit) 15. Mill motor (drive unit) 16 Rotary classifier (classifying section) 16a blade 17 Coal feed pipe (fuel supply section) 18 Classification motor 19 Exit Ports 21 Bunker (storage area) 22 Downspout section 25 Coal feeding machine (fuel supply machine) 26 Conveying section 27. Coal feeder motor 30. Air blower unit (gas supply unit for transport) 30a Hot gas flow path 30b Cold gas flow path 30C thermal gas damper 30d Cold Gas Damper 31. Primary Air Fan (PAF) 32 Forced draft fan (FDF) 33. Induced Draft Fan (IDF) 34. Air preheater (heat exchanger) 40 State detection unit (temperature detection means, differential pressure detection means) 41 Bottom part 42 Ceiling section 45 Journal Heads 46 Pressing device (crushing load application section) 47 Support Arm 48 Support shaft 50 Control Unit 52 servers 53 Information Processing Terminals 60 Parts Management System 61 Parts Management Department 62 Quotation Request Department 63 Electronic Parts List Section 64 Document Management Department 65 Data Analysis Department 70 Management Systems 71 Management Department 72 Life estimation section 73 Providing Department 74 Reception Department 75 Document Storage Department 76 Document provision department 77 Life analysis department 100 Solid Fuel Grinding Machine 110 Primary air passage (gas passage for transport) 120. Fine fuel supply channel (fine fuel supply pipe) 200 boilers 210 Furnace 220 burner (combustion device) 1100 CPU 1200 Main Memory 1300 Storage section 1400 External Interface 1500 communication interfaces 1600 Input Section 1700 Display

Claims

1. a life estimation unit that estimates a remaining life of the target part according to a usage state of the target part; an estimate request unit that issues an estimate request for the target part based on the remaining life and a delivery date that is set in advance as a period required for delivery of the target part; Equipped with the quotation request unit issues the quotation request when the remaining life is equal to or less than a period obtained by adding together the delivery date, an estimate period that is preset as a period required to create an estimate, and an order period that is preset as a period for placing an order for the estimate, A parts management system in which the delivery date, the estimate period, and the order period are changed according to the business status of a user or a manufacturer.

2. The parts management system according to claim 1 , wherein the quotation request unit issues the quotation request when the remaining life is equal to or shorter than the delivery date.

3. 2. The parts management system according to claim 1, wherein the quotation request unit issues the quotation request when a time when a user of the target part will apply for a budget, the time being prior to the next budget application time, is the remaining life minus the sum of the delivery date, an estimate period preset as the period required to create an estimate, and an order period preset as the period for placing an order for the estimate.

4. a management unit that manages information by associating at least one of product information, order information, location information, and time information with the target part; The product information is at least one of a part name, a part number, a drawing number, and a revision number, The order information is at least one of order content information and an order number, The location information is at least one of a location of use and a location of storage, 4. The parts management system according to claim 1, wherein the time information is at least one of delivery time, start of use time, start of storage time, life information, and delivery time information.

5. a provision department that provides information on delivered parts; a reception unit that receives an order for a part based on the provided information; The parts management system according to claim 1 , further comprising:

6. The parts management system according to claim 5 , wherein the parts information provided by the providing unit is linked in hierarchical order from a larger component to a smaller component.

7. a document storage unit that stores electronic data of documents related to delivered parts; a document providing unit that provides electronic data of the stored document in response to a request to view the document; The parts management system according to claim 1 , further comprising:

8. a life analysis unit that estimates a remaining life of the target part based on measurement data of the target part, The parts management system according to claim 1 , wherein the quotation request unit issues the quotation request for the target part based on the remaining life based on the measurement data and the delivery date.

9. The parts management system according to claim 1 , wherein the target parts are spare parts.

10. a lifespan analysis unit that estimates a remaining lifespan of a target part based on measurement data of the target part; an estimate request unit that issues an estimate request for the target part based on the remaining life and a delivery date that is set in advance as a period required for delivery of the target part; Equipped with the quotation request unit issues the quotation request when the remaining life is equal to or less than a period obtained by adding together the delivery date, an estimate period that is preset as a period required to create an estimate, and an order period that is preset as a period for placing an order for the estimate, A parts management system in which the delivery date, the estimate period, and the order period are changed according to the business status of a user or a manufacturer.

11. An information processing terminal connected to a network; a server having the functions of the parts management system according to any one of claims 1 to 10 and communicating with the information processing terminal via the network; A management system comprising:

12. estimating a remaining life of the target part according to a usage state of the target part; issuing a request for quotation for the target part based on the remaining life and a delivery date that is preset as a period required for delivery of the target part; having issuing the request for quotation when the remaining life is equal to or less than the period obtained by adding together the delivery date, an estimate period that is preset as the period required to create an estimate, and an order period that is preset as the period for placing an order for the estimate; A parts management method executed by a computer, wherein the delivery date, the estimate period, and the order period are changed depending on the business status of a user or a manufacturer.

13. estimating a remaining life of the target component based on measurement data of the target component; issuing a request for quotation for the target part based on the remaining life and a delivery date that is preset as a period required for delivery of the target part; having issuing the request for quotation when the remaining life is equal to or less than the period obtained by adding together the delivery date, an estimate period that is preset as the period required to create an estimate, and an order period that is preset as the period for placing an order for the estimate; A parts management method executed by a computer, wherein the delivery date, the estimate period, and the order period are changed depending on the business status of a user or a manufacturer.

14. A process of estimating a remaining life of the target part according to a usage state of the target part; issuing a request for quotation for the target part based on the remaining life and a delivery date that is set in advance as a period required for delivery of the target part; Run the following on your computer: issuing the request for quotation when the remaining life is equal to or less than the period obtained by adding together the delivery date, an estimate period that is preset as the period required to create an estimate, and an order period that is preset as the period for placing an order for the estimate; A parts management program in which the delivery date, the estimate period and the order period are changed according to the business status of a user or a manufacturer.

15. A process of estimating a remaining life of the target part based on measurement data of the target part; issuing a request for quotation for the target part based on the remaining life and a delivery date that is set in advance as a period required for delivery of the target part; Run the following on your computer: issuing the request for quotation when the remaining life is equal to or less than the period obtained by adding together the delivery date, an estimate period that is preset as the period required to create an estimate, and an order period that is preset as the period for placing an order for the estimate; A parts management program in which the delivery date, the estimate period and the order period are changed according to the business status of a user or a manufacturer.

16. estimating a remaining life of the target part according to a usage state of the target part by a user; issuing a request for quotation for the target part to a manufacturer of the target part based on the remaining life and a delivery date that is preset as a period required for delivery of the target part; having issuing the request for quotation when the remaining life is equal to or less than the period obtained by adding together the delivery date, an estimate period that is preset as the period required to create an estimate, and an order period that is preset as the period for placing an order for the estimate; A parts management method executed by a computer, wherein the delivery date, the estimate period, and the order period are changed depending on the business status of a user or a manufacturer.