Building construction method

By using space partitioning equipment as scaffolding within the building frame, the method addresses the inefficiencies of traditional scaffolding installation and removal, allowing for efficient construction and utilization of the space as part of the building.

JP2024143574APending Publication Date: 2024-10-11DAIWA HOUSE INDUSTRY CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023056324
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing building construction methods using scaffolding require a large number of man-hours for installation and removal, leading to inefficiencies in the construction process.

Method used

The method involves using space partitioning equipment within the building frame as scaffolding, which is placed inside the frame to reduce installation and removal time, and is later utilized as a space in the completed building.

Benefits of technology

This approach reduces the man-hours required for scaffolding installation and removal, enabling efficient construction of buildings by integrating the space partitioning equipment as a functional space within the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143574000001_ABST
    Figure 2024143574000001_ABST
Patent Text Reader

Abstract

To provide a building construction method that can reduce the number of work steps required for setting up and removing scaffolding and efficiently construct a building.SOLUTION: A building construction method performs a first step in which space partition equipment is placed which has side walls and ceiling walls and partitions the space enclosed by the side walls and ceiling walls from the outside of the space in the structure of the building under construction, a second step of using the space partition equipment placed within the structure as scaffolding, and a third step of placing the space partition equipment in a position within the building structure so that the space within the space partition equipment is used as one space after the building is completed.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for constructing a building, and more particularly to a method for constructing a building using scaffolding within the building framework. [Background technology]

[0002] Methods for constructing buildings using scaffolding have already been developed, and the technology described in Patent Document 1 is one example. Patent Document 1 discloses a temporary scaffolding used for a floor opening inside a steel-framed building constructed with a steel frame, the temporary scaffolding being characterized by comprising a plurality of supports connected to beams around the edge of the floor opening, a pair of horizontal members stretched across the supports so as to face each other, and a work floor stretched across the pair of horizontal members. This allows the floor opening to be used without hindrance to workers ascending and descending or the carrying in and out of materials, etc., even when the temporary scaffolding is set up. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2012-77544 A Summary of the Invention [Problem to be solved by the invention]

[0004] As described above, when using scaffolding within the framework of a building under construction, first, the scaffolding's constituent elements, such as supports, are carried into the framework of the building, and the supports are assembled within the framework to form the scaffolding. The scaffolding is then placed in a desired position within the framework and used. When use of the scaffolding is finished, the scaffolding is dismantled, and the constituent elements, such as supports, are carried out from within the framework. Thus, with the technology described in Patent Document 1, a large amount of work is required to set up and remove the scaffolding.

[0005] Therefore, the present invention has been made in consideration of the above problems, and an object of the present invention is to provide a building construction method that reduces the amount of work required for setting up and removing scaffolding, and enables efficient construction of buildings. [Means for solving the problem]

[0006] The above-mentioned object can be achieved by the building construction method of the present invention by carrying out the following steps: a first step of placing a space partition equipment having side walls and a ceiling wall and separating a space enclosed by the side walls and the ceiling wall from the outside of the space, within the structure of a building under construction; a second step of using the space partition equipment placed within the structure as scaffolding; and a third step of placing the space partition equipment at a position within the structure so that the space within the space partition equipment can be used as one space in the completed building.

[0007] In the building construction method of the present invention, in the first step, a space partition system used as a scaffold is placed inside a building structure. This reduces the number of man-hours required to set up the scaffold, compared to the temporary scaffold described in Patent Document 1, in which the scaffold's constituent elements, such as supports, are brought into the building structure and assembled inside the building structure. In the building construction method of the present invention, in the third step, the space partition equipment is arranged in a position within the building framework so that the space within the space partition equipment can be used as one space in the completed building. This reduces the man-hours required to remove the scaffolding, as compared with the temporary scaffolding described in Patent Document 1, in which the scaffolding is dismantled after use is completed and the supporting columns and other components of the scaffolding are removed from the building framework. In this way, according to the building construction method of the present invention, the amount of work required for setting up and removing scaffolding can be reduced, enabling buildings to be constructed efficiently.

[0008] In the second step, the space partition equipment may be used as a scaffold for installing the roof of the building. With the above configuration, the amount of work required to set up and remove scaffolding during roof installation is reduced, enabling buildings to be constructed efficiently.

[0009] The roof may also be a sloped roof. With the above configuration, the amount of work required to set up and remove scaffolding when installing a sloped roof is reduced, allowing buildings to be constructed efficiently.

[0010] In the second step, the spatial partition equipment may be used as a scaffold, temporary beams may be supported by temporary pillars erected on the upper end surface of the spatial partition equipment, and the roof slabs that make up the roof may be placed on the temporary beams. With the above configuration, the work of installing the roof slab can be carried out efficiently using the space partition equipment, temporary supports, and temporary beams.

[0011] In the first step, a space partition facility may be disposed in the space below the position where the roof is to be installed. With the above configuration, the work of installing the roof can be carried out more efficiently.

[0012] In the first step, a space partition equipment having a box-shaped main body and a moving mechanism attached to a lower part of the main body may be moved to a position to be used as a scaffolding by using the moving mechanism. With the above configuration, the space partition equipment can be easily moved within the framework, enabling the building to be constructed efficiently.

[0013] In addition, in the third step, a space partition equipment having a box-shaped main body and a moving mechanism attached to the lower part of the main body may be moved by the moving mechanism to a position for use as one space in the completed building. With the above configuration, the space partition equipment can be easily moved within the framework, enabling the building to be constructed efficiently.

[0014] Also, in the first step, a plurality of space partition equipments may be disposed within the building frame, and in the third step, the plurality of space partition equipments may be disposed within the building frame in a connected state. With the above configuration, the spaces within multiple connected space partition equipment can be used as a single space in the completed building.

[0015] Furthermore, a fourth step of arranging at least one of equipment and interior materials inside the spatial partition equipment according to the intended use of the spatial partition equipment after the completion of the building may be carried out before the first step. With the above-mentioned configuration, by arranging the equipment, interior materials, etc. inside the spatial partition facility in advance, the amount of work required in the subsequent finishing process is reduced, allowing the building to be constructed efficiently. Effect of the Invention

[0016] According to the present invention, a building construction method can be provided that reduces the amount of work required for setting up and removing scaffolding, enabling efficient construction of buildings. [Brief description of the drawings]

[0017] [Figure 1] 1 is a schematic diagram showing an example of a building constructed by a building construction method according to one embodiment of the present invention. [Diagram 2] 1 is a schematic diagram showing an example of a building constructed by a building construction method according to one embodiment of the present invention. [Diagram 3] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 4] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Diagram 5] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 6] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 7]FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 8] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 9] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 10] FIG. 1 is a schematic diagram for explaining a method for constructing a building according to one embodiment of the present invention. [Figure 11] FIG. 11 is a schematic diagram for explaining a modified example of a building construction method according to one embodiment of the present invention. [Figure 12] FIG. 11 is a schematic diagram for explaining a modified example of a building construction method according to one embodiment of the present invention. [Figure 13] FIG. 11 is a schematic diagram for explaining a modified example of a building construction method according to one embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention (hereinafter, the present embodiment) will be described in detail below with reference to the preferred embodiment shown in the accompanying drawings. In addition, the drawings show each component somewhat simplified and schematic in order to make the explanation easier to understand, and the size (dimensions) of each component and the intervals between components shown in the drawings are different from the actual ones. In addition, unless otherwise specified, the material and shape of each member used to implement the present invention can be arbitrarily set depending on the application of the present invention and the state of the art at the time of implementing the present invention. Furthermore, the present invention includes its equivalents.

[0019] <<About the building constructed by the building construction method according to this embodiment>> A building (hereinafter, building 1) constructed by the building construction method according to this embodiment will be described with reference to FIG. The building 1 includes buildings for various purposes, such as a house, an office, a store, a facility such as a hospital or a school, a building in a factory, etc. In the following, a one-story wooden house shown in FIG. 1 will be described as an example of the building 1.

[0020] The building 1 includes a skeleton 10 that constitutes the structural body of the building 1. The skeleton 10 is constructed, for example, using known construction techniques. Specifically, the skeleton 10 is constructed of a foundation, floors, walls, pillars, a truss 20, and the like.

[0021] The truss 20 is composed of a pair of eaves beams 21, a roof beam 22, a roof truss 23, and a ridge purlin 24. In the following description, of the two mutually orthogonal horizontal directions, one is referred to as the girder direction and the other as the beam direction, as shown in Fig. 1. The direction orthogonal to both the girder direction and the beam direction is referred to as the height direction. In addition, "orthogonal" includes the range of error permitted in the technical field to which the present invention pertains, and means, for example, within a range of less than ±10° from strictly orthogonal.

[0022] The pair of eaves beams 21 are disposed at an interval in the beam direction. Each of the eaves beams 21 extends along the girder direction. The roof beam 22 extends in the beam direction from one eaves beam 21 to the other eaves beam 21. Although only one roof beam 22 is shown in Fig. 1, a plurality of roof beams 22 are assumed to be arranged at intervals in the beam direction. The rafter 23 is attached to the center of the roof beam 22 in the beam direction and extends upward. More specifically, the rafter 23 is attached to the upper end surface of the roof beam 22 and extends upward. Although only one rafter 23 is shown in Fig. 1, it is assumed that one is disposed on each roof beam 22. In other words, multiple roof beams 22 are positioned at intervals in the girder direction. The ridge purlin 24 is disposed at the upper end of the rafter 23. More specifically, the ridge purlin 24 extends in the girder direction and is supported by a plurality of rafters 23 positioned at intervals in the girder direction.

[0023] The building 1 further includes a roof 31, which has a plurality of roof slabs 31a. The roof slab 31a is made of, for example, CLT (Cross Laminated Timber) having structural strength. Note that a known roof slab other than CLT may be used as the roof slab 31a, and for example, it may be a roof slab in which a plurality of rafters are attached to one side of a plywood board, or a roof slab in which plywood boards are attached to both sides of a heat-insulating material. The roof slab 31a is, for example, a rectangular flat plate. The roof slab 31a is installed straddling the eaves beam 21 and the ridge purlin 24 with the longitudinal direction of the rectangle aligned in the direction connecting the eaves beam 21 and the ridge purlin 24. The roof 31 is arranged with a slope relative to the horizontal direction, making it a so-called sloped roof. When the roof slab 31a is made of CLT, the distance between the eaves beam 21 and the ridge purlin 24 required to support the roof slab 31a is, for example, about 3.5 m to 4.9 m in the beam direction.

[0024] The building 1 further includes a space partition equipment 40. The space partition equipment 40 is disposed inside the building 1. More specifically, the space partition equipment 40 is disposed directly below the attic room R that utilizes the attic space S3. The space partition equipment 40 is fixed to the building frame 10 by a fixing device (not shown), and is utilized as one space S1 in the building 1. Note that, although one space partition equipment 40 is disposed in the building 1 in the example shown in FIG. 1, the present invention is not limited to this, and multiple space partition equipments 40 may be disposed in the building 1.

[0025] The space partition equipment 40 has a box-shaped main body 41 and a moving mechanism 42 attached to the lower part of the main body 41. The main body 41 has a bottom wall 43, a side wall 44 rising from an end of the bottom wall 43, and a ceiling wall 45 located at the upper end of the side wall 44. The main body 41 (space partition equipment 40) separates a space S1 surrounded by the bottom wall 43, the side wall 44, and the ceiling wall 45 from a space S2 outside the space S1. The space S2 is separated from the space S1 by the side wall 44, and is used as a space on the same floor as the space S1. The main body 41 (space partition equipment 40) also separates the space S1 surrounded by the bottom wall 43, the side wall 44, and the ceiling wall 45 from an attic space S3 outside the space S1. The attic space S3 is separated from the space S1 by the ceiling wall 45, and is used as an attic room, for example. The ceiling wall 45 forms the upper end surface of the space partition equipment 40, and is used as a scaffold in the building 1 under construction, as described later. The ceiling wall 45 is located below the eaves beam 21 and the roof beam 22. The main body 41 does not necessarily have to have a bottom wall 43. That is, the main body 41 may have a side wall 44 and a ceiling wall 45 located at the upper end of the side wall 44, and may separate a space S1 surrounded by the side wall 44 and the ceiling wall 45 from a space S2 outside the space S1 and an attic space S3.

[0026] An opening (not shown) is provided in the main body 41, and the size of the opening is set according to the strength required for the space partition equipment 40 to constitute a scaffold. In other words, the opening may be equivalent to a large window or door, so long as the space partition equipment 40 has the strength to constitute a scaffold.

[0027] The moving mechanism 42 includes, for example, a plurality of casters. Each of the plurality of casters is attached to the lower end of the bottom wall 43 (or the lower end of the side wall 44). The moving mechanism 42 including the plurality of casters is covered by floorboards so as not to be seen from both the space S1 and the space S2 in the building 1. The moving mechanism 42 is normally locked by a fixing device (not shown), but the space partition equipment 40 can be moved by removing the fixing device to release the lock.

[0028] The size of the space partition equipment 40 is set according to the size required for use as a scaffolding. For example, if the ceiling wall 45 is rectangular, it is preferable that the short side is 1.8 m or more and the long side is 3.6 m or more. The size of the space partition equipment 40 may be determined according to the size of the attic space S3 in the completed building 1. That is, the height of the side wall 44 may be determined according to the height of the attic space S3, and the area of ​​the ceiling wall 45 may be determined according to the floor area of ​​the attic space S3. The upper limit of the size of the space partition equipment 40 may be set according to, for example, the size of the container of the truck used for transporting the equipment to the construction site.

[0029] Inside the space partition equipment 40, equipment 51 and interior materials 52 are arranged according to the purpose of the space S1 inside the space partition equipment 40. For example, if the purpose of the space S1 is a bathroom vanity, the equipment 51 is a vanity unit, and the interior materials 52 are floor materials, wall materials, ceiling materials, and the like suitable for the bathroom vanity. Note that in the example shown in Fig. 1, only some of the interior materials 52 are illustrated. The exterior (external surface) of the space partition equipment 40 is finished using a finishing material or the like.

[0030] Although the above description has been given taking the example of a single-storey building 1, a building 1A having multiple floors may also be constructed as shown in FIG. In this case, the spatial partition equipment 40 may be disposed on the first floor of the building 1A, or may be provided on multiple floors of the building 1A. Also, multiple spatial partition equipment 40 may be disposed on each floor. During the construction of the building 1A, as described below, the space partition equipment 40 will be placed in the space below the location where the roof is planned to be installed. That is, during the construction of the building 1A, at least one of the space partition equipment 40 will be placed on the top floor (the second floor in the example shown in FIG. 2). For this reason, it is preferable that at least one space partition equipment 40 be installed on the top floor of the completed building 1A.

[0031] <<Building construction method according to this embodiment>> Hereinafter, a method for constructing a building according to this embodiment will be described on the premise of the building 1 shown in Fig. 1. Figs. 3 to 10 are schematic diagrams for explaining the method for constructing a building according to this embodiment. The building construction method according to the present embodiment can be applied to both new construction and remodeling. Also, the building construction method according to the present embodiment can be applied to both wooden and steel-framed buildings.

[0032] 3, a preparation process is carried out to prepare the space partition equipment 40, the equipment 51, and the interior material 52. Specifically, the space partition equipment 40, the equipment 51, and the interior material 52 are each manufactured in, for example, a manufacturing factory. The space partition equipment 40, the equipment 51, and the interior material 52 may each be manufactured in a different manufacturing factory. 4, a process (corresponding to a fourth process) is carried out in which at least one of the equipment 51 and the interior material 52 according to the use of the space partition equipment 40 after the completion of the building 1 is arranged inside the space partition equipment 40. More specifically, the space partition equipment 40, the equipment 51, and the interior material 52 are assembled in an assembly factory, and at least one of the equipment 51 and the interior material 52 are arranged inside the space partition equipment 40.

[0033] 5, a step (corresponding to a first step) of placing the space partition equipment 40 in the skeleton 10 of the building 1 under construction is carried out. A plurality of space partition equipment 40 may be placed in the skeleton 10. At this point, the structure 10 has been assembled with the foundation, floors, pillars, walls, eaves beams 21, and rafters 22. That is, after the first step, the rafters 23, ridge purlins 24, and roof 31 are assembled. More specifically, first, the space partition equipment 40 that has undergone the aforementioned fourth step is transported to the construction site of the building 1 under construction. After that, the space partition equipment 40 is carried into the skeleton 10 of the building 1 under construction using a crane or the like. More specifically, the space partition equipment 40 is transported above the skeleton 10 by a crane. After that, the space partition equipment 40 is lowered and carried into the skeleton 10 through an opening in the upper part of the skeleton 10, i.e., an opening surrounded by the eaves beams 21 and the rafters 22. Next, the space partition equipment 40 that has been carried into the framework 10 is moved using the moving mechanism 42 and placed in a position to be used as a scaffold. More specifically, the space partition equipment 40 is placed in the space S4 below the position where the roof 31 is to be installed. In the example shown in Fig. 1, the space S4 is the space below the position where the rafters 23 are to be installed.

[0034] Next, as shown in Fig. 6, a step (second step) of using the space partition equipment 40 arranged in the skeleton 10 as a scaffold is carried out. In the second step, the space partition equipment 40 is used as a scaffold for installing the roof 31 of the building 1, more specifically, a sloped roof. More specifically, after the space partition equipment 40 is temporarily fixed to the skeleton 10, a worker climbs onto the ceiling wall 45 of the space partition equipment 40 to perform the work. The temporary fixing may be performed, for example, by stopping the rotation of the casters of the moving mechanism 42 using stoppers provided on the casters. The worker climbs up to the ceiling wall 45 of the space partition equipment 40 using a ladder or the like (not shown) leaned against the space partition equipment 40, and then attaches the rafters 23 to the upper ends of the rafters 22 and the ridge purlin 24 to the upper ends of the rafters 23.

[0035] Thereafter, as shown in Fig. 7, a worker installs the roof slab 31a using a crane or the like. Specifically, the direction connecting the eaves beam 21 and the ridge purlin 24 is the longitudinal direction of the roof slab 31a, and the roof slab 31a is installed on the eaves beam 21 and the ridge purlin 24. The roof slab 31a is fixed to the eaves beam 21 and the ridge purlin 24 using metal fittings (not shown). Thereafter, as shown in FIG. 8, when the installation of the roof slabs 31a is completely completed, the worker gets off the space partition equipment 40 and ends the use of the space partition equipment 40 as a scaffold. In addition, the space partition equipment 40 may be used as scaffolding to perform ceiling finishing or wiring work on the ceiling side.

[0036] Next, as shown in Fig. 9, a process (corresponding to a third process) is carried out in which the space partition equipment 40 is disposed at an arrangement position P within the structural body 10 in order to utilize the space within the space partition equipment 40 as one space S1 in the completed building 1. More specifically, the temporary fixation of the space partition equipment 40 within the structural body 10 is released, and the moving mechanism 42 is used to move the space partition equipment 40 to an arrangement position P for use as one space S1 in the completed building 1. In the example shown in Fig. 9, the arrangement position P is set to one end within the structural body 10 in the beam direction.

[0037] Thereafter, as shown in Fig. 10, a finishing process is carried out inside the skeleton 10. More specifically, the space partition equipment 40 is fixed to the skeleton 10 by a fixing device (not shown), and finishing materials and the like are installed in each part inside the skeleton 10. When the finishing process is finished, the building 1 is completed.

[0038] <<Actions and Effects of This Embodiment>> As described above, in the building construction method according to this embodiment, in the first step, the space partition equipment 40 used as scaffolding is arranged inside the skeleton. Therefore, compared to the temporary scaffolding described in Patent Document 1, in which the scaffolding is constructed by carrying supports and the like, which are components of the scaffolding, inside the skeleton and assembling the supports and the like inside the skeleton, the labor hours required to set up the scaffolding can be reduced. In the building construction method according to this embodiment, in the third step, the space partition equipment 40 is disposed at the arrangement position P in the skeleton 10 in order to use the space inside the space partition equipment 40 as one space S1 in the completed building 1. This makes it possible to reduce the amount of work required to remove the scaffolding, as compared with the temporary scaffolding described in Patent Document 1, in which the scaffolding is dismantled after use is completed and the supporting columns and other components of the scaffolding are removed from the skeleton. In this way, according to the building construction method of this embodiment, the amount of work required for setting up and removing scaffolding can be reduced, making it possible to construct buildings efficiently.

[0039] Furthermore, in the building construction method according to this embodiment, the space inside the space partition equipment 40 is used as one space S1 in the completed building 1, so that it is possible to reduce the amount of work required to newly install walls or the like for partitioning the space S1 inside the framework 10. In other words, the amount of work required in the process after the third process is reduced, so that the building can be constructed more efficiently.

[0040] In the second step, the space partition equipment 40 is used as a scaffold for installing the roof 31 of the building 1. This reduces the amount of work required to set up and remove scaffolding when installing the roof 31, allowing the building to be constructed efficiently. In this regard, in the past, when a structural body such as CLT was applied to the roof slab 31a, the roof slab 31a itself was made to function as a structural body, and the number of beams constituting the truss was reduced to ensure a large attic space. However, by reducing the number of beams constituting the truss, the amount of scaffolding required for the work of installing the roof slab 31a was reduced, and temporary scaffolding had to be installed. This resulted in the expenditure of man-hours in installing and removing the scaffolding. In contrast, in the building construction method according to this embodiment, even when a structure such as CLT is installed as the roof slab 31a, the labor hours required for setting up and removing the scaffolding are reduced. In this way, in the building construction method according to this embodiment, the building 1 can be efficiently constructed while ensuring a large attic space S3.

[0041] Furthermore, the size of the space partition equipment 40 can be set according to the size of the attic space S3 in the completed building 1. That is, the height of the side wall 44 can be set according to the height of the attic space S3, and the area of ​​the ceiling wall 45 can be set according to the floor area of ​​the attic space S3. In this way, in the building construction method according to this embodiment, the size of the space partition equipment 40 can be set according to the size of the attic space S3 in the completed building 1, so that the attic space S3 can be effectively utilized.

[0042] Moreover, the roof 31 is a sloped roof. This reduces the amount of work required to set up and remove scaffolding when installing a sloped roof, allowing buildings to be constructed more efficiently. In addition, by using a sloped roof, a larger attic space S3 can be secured, allowing the attic space S3 to be utilized even more effectively.

[0043] In the first step, the space partition equipment 40 is placed in the space S4 below the position where the roof 31 is to be installed. This allows the work of installing the roof 31 to be carried out more efficiently.

[0044] In the first step, a space partition equipment 40 having a box-shaped main body 41 and a moving mechanism 42 attached to the lower part of the main body 41 is moved by the moving mechanism 42 to a position to be used as a scaffold. This makes it easier to move the space partition equipment 40 within the framework 10, enabling the building to be constructed efficiently.

[0045] In addition, in the third step, the space partition equipment 40, which has a box-shaped main body 41 and a moving mechanism 42 attached to the lower part of the main body 41, is moved by the moving mechanism 42 to a position for use as one space in the completed building. This makes it easier to move the space partition equipment 40 within the framework 10, enabling the building to be constructed efficiently.

[0046] In addition, a fourth step of arranging at least one of the equipment 51 and the interior material 52 inside the spatial partition equipment 40 according to the use of the spatial partition equipment 40 after the building 1 is completed is carried out before the first step. In this way, by arranging the equipment 51 and the interior materials 52, etc., inside the space partition equipment 40 in advance, the amount of work required in the subsequent finishing process is reduced, so that the building can be constructed efficiently.

[0047] <<Other embodiments>> Although one embodiment of the method for constructing a building of the present invention has been described above, the above embodiment is merely an example given to facilitate understanding of the present invention and does not limit the present invention. In other words, the configuration of the present invention may be modified or improved from the above embodiment without departing from the spirit of the present invention.

[0048] In the above-mentioned building construction method, as shown in Fig. 7, the roof slab 31a is installed on the eaves beam 21 and the ridge purlin 24 so that the direction connecting the eaves beam 21 and the ridge purlin 24 and the longitudinal direction of the roof slab 31a are aligned with each other. However, this is not limited to this, and as shown in Fig. 11, multiple roof slabs 31a may be installed side by side on the eaves beam 21 and the ridge purlin 24 so that the direction connecting the eaves beam 21 and the ridge purlin 24 and the transverse direction of the roof slab 31a are aligned with each other. In this case, rafters 25 may be placed between the eaves beam 21 and the ridge purlin 24. The rafters 25 function as support members for the roof slab 31a.

[0049] In addition, in the above-mentioned building construction method, the roof slab 31a is installed using the rafters 23 and the ridge purlins 24 as shown in FIG. 7, but this is not limited to this, and the roof slab 31a may also be installed using temporary supports C and temporary beams B as shown in FIG. 12. Specifically, as shown in FIG. 12, the space partition equipment 40 can be used as a scaffold, with a temporary beam B supported by a temporary support C erected on the upper end surface of the space partition equipment 40, and the roof slab 31a that constitutes the roof 31 can be placed on the temporary beam B. This allows the work of installing the roof slab 31a to be performed efficiently using the space partition equipment 40, the temporary supports C, and the temporary beams B. In the work of installing the roof slab 31a, a tie bar or tension rod (not shown) may be placed between the pair of eaves beams 21 to maintain the distance between the pair of eaves beams 21. Furthermore, the temporary beams B and temporary supports C are removed after the roof 31 is installed. For this reason, a larger attic space can be secured compared to building 1. That is, in a building constructed according to the example shown in Fig. 12, a ridge purlin 24 is not installed and the number of rafters 23 is reduced compared to building 1, so a larger attic space can be secured.

[0050] In the above-mentioned building construction method, as shown in Fig. 5, in the first step, one space partition equipment 40 is placed in the skeleton 10, and as shown in Fig. 9, in the third step, one space partition equipment 40 is placed at the placement position P in the skeleton 10. However, this is not limited to the above, and as shown in Fig. 13, multiple space partition equipments 40A, 40B may be placed in the skeleton 10 in the first step, and the multiple space partition equipments 40A, 40B may be placed in the skeleton 10 in a connected state in the third step. This allows the space of the multiple connected space partition equipments 40A, 40B to be used as one space in the completed building. In addition, in the third step, a plurality of space partition equipments may be arranged in the skeleton 10 without being connected. For example, in the third step, two space partition equipments may be arranged next to each other in the skeleton 10, and used as separate adjacent spaces in the completed building. In the third step, two space partition equipments may be disposed at positions separated from each other within the framework 10, and the upper ends of the two space partition equipments may be connected by a top plate. This allows the space above the two space partition equipments and the top plate to be used as an attic space. [Explanation of symbols]

[0051] 1,1A Building 10 skeleton 20 Roof Truss 21 Eave girder 22 Roof beam 23 Hut bundle 24 Main building 25 Rafters 31 Roof 31a Roof plate 40, 40A, 40B Space partition equipment 41 Main body 42 Moving mechanism 43 Bottom wall 44 Side wall 45 Ceiling Wall 51 Equipment 52 Interior materials B Temporary beam C Temporary Support P placement position R Attic room S1,S2 space S3 Attic space S4 Downward space

Claims

1. A first step of disposing a space partition facility having a side wall and a ceiling wall, the space partition facility separating a space surrounded by the side wall and the ceiling wall from the outside of the space, within a skeleton of a building under construction; A second step of using the space partition equipment arranged within the framework as a scaffold; a third step of placing the space partition equipment at a position within the building structure so that the space within the space partition equipment can be used as one space in the building after completion.

2. The method for constructing a building according to claim 1 , wherein in the second step, the space partition equipment is utilized as a scaffold for installing a roof of the building.

3. The method of claim 2, wherein the roof is a sloped roof.

4. 3. The method for constructing a building according to claim 2, wherein in the second step, the space partition equipment is used as a scaffold, temporary beams are supported by temporary pillars erected on the upper end surface of the space partition equipment, and the roof slabs constituting the roof are placed on the temporary beams.

5. The method for constructing a building according to claim 2 or 3, wherein in the first step, the space partition equipment is placed in a space below a position where the roof is to be installed.

6. 2. The building construction method according to claim 1, wherein in the first step, the space partition equipment, which has a box-shaped main body and a moving mechanism attached to a lower part of the main body, is moved to a position to be used as scaffolding by using the moving mechanism.

7. 2. The building construction method according to claim 1, wherein in the third step, the space partition equipment, which has a box-shaped main body and a moving mechanism attached to a lower part of the main body, is moved by the moving mechanism to a position for use as one space in the building after completion.

8. In the first step, a plurality of the space partition facilities are arranged within the building structure, 2. The method for constructing a building according to claim 1, wherein in the third step, the plurality of space partition facilities are arranged within the building frame in a connected state.

9. 2. The method for constructing a building according to claim 1, further comprising the step of: before the step 1, placing inside the space partition equipment at least one of equipment and interior materials according to the intended use of the space partition equipment after completion of the building.