Device, method, and program

The system optimizes generator control on ships using predicted power consumption and machine learning to prevent power shortages and fuel waste, enhancing energy management and operational efficiency.

JP2024143581AActive Publication Date: 2024-10-11YOKOGAWA ELECTRIC CORP
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2023056338
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11
Estimated Expiration
2043-03-30

AI Technical Summary

Technical Problem

Existing systems fail to efficiently manage power generation on ships with multiple generators, leading to potential power outages due to insufficient generation and excessive fuel consumption, especially when considering the power demands of equipment like cranes during port operations.

Method used

A system that acquires predicted power consumption values and controls generators to maintain power generation within a reference range, transitioning generators between states to meet demand, using machine learning models to forecast consumption based on ship status data.

Benefits of technology

Prevents power outages and reduces fuel waste by optimizing generator usage, ensuring sufficient power for operations and efficient energy management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143581000001_ABST
    Figure 2024143581000001_ABST
Patent Text Reader

Abstract

To provide a control device that efficiently operates multiple generators by predicting power consumption of a load.SOLUTION: In a system, a device 3 includes: an acquisition unit that acquires a predicted value of power consumption on an own ship equipped with multiple generators 2; and a control unit that controls each generator so that a power generation amount by the multiple generators is within a standard range of the predicted value of the power consumption acquired by the acquisition unit. The ship is a cargo ship equipped with a crane. The acquisition unit acquires a predicted value that includes the power consumption of the crane as a predicted value of the power consumption of the ship at a scheduled arrival time. The control unit transfers at least one of the multiple generators from a standby state or a stopped state to a power generation state in response to the predicted value of the power consumption acquired by the acquisition unit being greater than a rated output of each generator that is currently in the power generation state.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an apparatus, a method and a program. [Background technology]

[0002] Patent documents 1 to 6 state that "the electrical load to be used is predicted using at least a portion of the season, region, ambient temperature, and driving time zone, and the generated voltage is set taking into consideration the prediction result" (Claim 5 of cited document 1), etc. [Prior art document] [Patent documents] [Patent Document 1] JP 2003-095042 A [Patent Document 2] JP 2005-176592 A [Patent Document 3] JP 2007-143375 A [Patent Document 4] JP 2010-017076 A [Patent Document 5] JP 2015-008588 A [Patent Document 6] JP ​​2021-104771 A Summary of the Invention

[0003] In a first aspect of the present invention, an apparatus is provided that includes an acquisition unit that acquires a predicted value of power consumption on a ship equipped with multiple generators, and a control unit that controls each of the multiple generators so that the amount of power generated by the multiple generators is within a standard range of the predicted value of power consumption acquired by the acquisition unit.

[0004] In the above device, the ship may be a cargo ship equipped with a crane, and the acquisition unit may acquire a predicted value including the power consumption of the crane as a predicted value of the ship's power consumption at the scheduled arrival time.

[0005] In any of the above devices, the control unit may transition at least one of the multiple generators that is in a standby state or a stopped state to a power generating state in response to the predicted power consumption value acquired by the acquisition unit being greater than the rated output of each generator that is currently in a power generating state.

[0006] In any of the above devices, the acquisition unit may acquire a predicted value of power consumption after a reference time period that is required for a generator in a standby state or a stopped state to transition to a power generating state.

[0007] The above device may further include a memory unit that pre-stores predicted values ​​of the ship's power consumption at multiple times, and the acquisition unit may read out from the memory unit the predicted value of the power consumption from the current time to the reference time.

[0008] In the above-mentioned device having a memory unit, the multiple times may be set in advance within a period ranging from the scheduled departure time of the ship to the scheduled arrival time of the ship.

[0009] In the above device including a storage unit, the multiple times may be set in advance within a period of one day.

[0010] In the above-mentioned device in which a predicted value of power consumption after a reference time is acquired, the acquisition unit may include a first acquisition unit that acquires status data indicating the status of the ship, a supply unit that supplies the status data acquired by the first acquisition unit to a model that outputs a predicted value of power consumption after the reference time in response to input of status data, and a second acquisition unit that acquires the predicted value of power consumption output from the model in response to the supply of status data to the model by the supply unit as the predicted value of power consumption after the reference time.

[0011] In a second aspect of the present invention, a method is provided comprising an acquisition step of acquiring a predicted value of power consumption on a ship equipped with multiple generators, and a control step of controlling each generator so that the amount of power generated by the multiple generators falls within a standard range of the predicted value of power consumption acquired in the acquisition step.

[0012] In a third aspect of the present invention, there is provided a program that causes a computer to function as an acquisition unit that acquires predicted values ​​of power consumption on a ship equipped with multiple generators, and a control unit that controls each of the multiple generators so that the amount of power generated by the multiple generators falls within a standard range of the predicted values ​​of power consumption acquired by the acquisition unit.

[0013] The above summary of the invention does not list all of the necessary features of the present invention. Also, subcombinations of these features may also be inventions. [Brief description of the drawings]

[0014] [Figure 1] 1 shows a system 1 according to an embodiment. [Diagram 2] The operation of device 3 is shown. [Diagram 3] 1 shows a system 1A according to a modified example. [Figure 4] 22 illustrates an example computer 2200 in which aspects of the present invention may be embodied, in whole or in part. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0015] The present invention will be described below through embodiments of the invention, but the following embodiments do not limit the scope of the invention according to the claims. Furthermore, not all of the combinations of features described in the embodiments are necessarily essential to the solution of the invention.

[0016] <1. System 1> Fig. 1 shows a system 1 according to this embodiment. The system 1 includes a plurality of generators 2 mounted on a ship (also referred to as the own ship), and an apparatus 3. The own ship may be any of a passenger ship, a cargo ship (an LNG tanker or a container ship, for example), a fishing ship (a whaling ship or a trawler, for example), a work ship (a tugboat, for example), or a naval vessel. In this embodiment, as an example, the own ship may be a cargo ship having a crane (not shown).

[0017] <1.1. Generator 2> Each generator 2 generates electric power to be used on the ship and supplies it to each part of the ship. A part of the electric power generated by each generator 2 may be charged in a storage battery (not shown) and then supplied to each part of the ship, or may be supplied directly to each part of the ship without going through a storage battery.

[0018] Each generator 2 may be any type of generator. The multiple generators 2 installed on the ship may be of the same type or different types. At least some of the multiple generators 2 may be switchable between an operating state of a power generation state and at least one of a stopped state and a standby state. The power generation state may be a state in which power is generated, and the stopped state may be a state in which the generator is stopped. The standby state may be a state in which the generator is waiting while suppressing fuel consumption so as to transition to the power generation state earlier than the stopped state. At least some of the multiple generators 2 may be variable in the amount of power generated in the power generation state, that is, the amount of power generated per unit time. Each generator 2 may be independently controlled by the device 3.

[0019] <1.2.Device 3> The device 3 controls each generator, and includes an acquisition unit 30 and a control unit 31.

[0020] <1.2.1. Acquisition part 30> The acquisition unit 30 acquires a predicted value of the power consumption of the ship. For example, the acquisition unit 30 may acquire a predicted value including the power consumption of a crane mounted on the ship as the predicted value of the power consumption of the ship at the scheduled port arrival time. The power consumption may be the amount of power consumed on board the ship per unit time.

[0021] The acquisition unit 30 may acquire a predicted value of the power consumption after a reference time. The reference time may be a time (e.g., 10 minutes) required for the generator 2 to transition from a stopped state to a power generating state. In the present embodiment, as an example, the time required for the generator 2 to transition from a stopped state to a power generating state may be the same for each generator 2.

[0022] The acquisition unit 30 may predict the power consumption. The acquisition unit 30 may include a first acquisition unit 301, a model 302, a supply unit 303, and a second acquisition unit 304.

[0023] <1.2.1-1.First acquisition part 301> The first acquisition unit 301 acquires status data indicating the status of the ship. The status data may indicate the current status of power consumption and power generation on the ship.

[0024] The status regarding power consumption may include at least one of the power consumption of each device on board the ship or the overall power consumption of the ship. The status regarding power generation may indicate at least one of the power generation amount of each generator 2, the operating state of each generator 2, or the overall power generation amount of the ship (also referred to as total power generation amount). The power generation amount of each generator 2 may indicate the amount of power generation by the generator 2 in association with at least the identification information (also referred to as generator ID) of each generator 2 in its power generation state. The operating state of each generator 2 may indicate the operating state of the generator 2 in association with the generator ID of each generator 2.

[0025] The status data may further indicate a status that may affect the power consumption, and may indicate, for example, at least one of the current time, the time elapsed since departure, the temperature and humidity inside the ship, the environment outside the ship, etc. The environment outside the ship may be at least one of the weather (for example, the temperature, the air pressure, the wind direction, the wind speed, the amount of precipitation (snowfall), etc.) or the sea state (for example, the sea wind, the significant wave height, the wind wave, the ocean current, etc.).

[0026] The first acquisition unit 301 may acquire the status data from an external device (not shown) of the apparatus 3, and may, for example, acquire the status data from a sensor provided on the ship, from a server on land or the like via a communication device, or from a crew member via an input device. The first acquisition unit 301 may supply the acquired status data to the supply unit 303. The first acquisition unit 301 may supply the control unit 31 with status data regarding each generator 2, that is, status data indicating at least one of the power generation amount of each generator 2 or the operating state of each generator 2.

[0027] <1.2.1-2. Model 302> The model 302 outputs a predicted value of the amount of power consumption after a reference time (in this embodiment, as an example, the time required for the generator 2 to transition from a stopped state to a power generating state) in response to the input of the status data. The model 302 may be generated by a learning process. The learning process of the model 302 may use learning data that associates status data and power consumption acquired on the ship or on a ship of the same type as the ship. The learning process may be performed by a known machine learning algorithm such as a neural network, a random forest, gradient boosting, logistic regression, and a support vector machine (SVM).

[0028] <1.2.1-3. Supply section 303> The supply unit 303 supplies the state data acquired by the first acquisition unit 301 to the model 302. As a result, the model 302 outputs a predicted value of the amount of power consumption.

[0029] <1.2.1-4.Second acquisition part 304> The second acquisition unit 304 acquires, as a predicted value of power consumption after a reference time, a predicted value of power consumption output from the model 302 in response to the supply unit 303 supplying the state data to the model 302. The second acquisition unit 304 may supply the acquired predicted value of power consumption to the control unit 31.

[0030] <1.2.2. Control unit 31> The control unit 31 controls each of the multiple generators 2 mounted on the ship so that the amount of power generated by the multiple generators 2 falls within a reference range from the predicted value of the power consumption acquired by the acquisition unit 30. The amount of power generated by the multiple generators 2 may be the total amount of power generated by the ship. The control unit 31 may control so that the total amount of power generated at a time predicted by the predicted value (in this embodiment, as an example, a time after the present time by a reference time) falls within a reference range from the predicted value of the power consumption. The reference range may be any range, and may be, for example, a range whose lower limit is a value obtained by subtracting the reference fluctuation amount of the power consumption from the predicted value of the power consumption and whose upper limit is a value obtained by adding the reference fluctuation amount of the power consumption to the predicted value of the power consumption. The reference fluctuation amount may be the maximum amount of power consumption that can fluctuate within a reference time (in this embodiment, as an example, the time required for the generator 2 to transition from a stopped state to a power generating state).

[0031] The control unit 31 may increase or decrease the total amount of power generation by shifting the operating state of at least some of the generators 2 (in this embodiment, as an example, each generator 2) among the multiple generators 2 between a stopped state and a power generation state. The control unit 31 may increase or decrease the total amount of power generation by increasing or decreasing the amount of power generation of the generators 2 in the power generation state.

[0032] The control unit 31 may control each generator 2 based on the status data related to the generator 2 supplied from the first acquisition unit 301. For example, the control unit 31 may increase the amount of power generated by at least one generator 2 in a power generating state, or may shift at least one generator 2 in a standby state or a stopped state to a power generating state, in response to the current total amount of power generated being lower than the lower limit of the reference range. The control unit 31 may reduce the amount of power generated by at least one generator 2 in a power generating state, or may shift at least one generator 2 in a power generating state to a standby state or a stopped state, in response to the current total amount of power generated being higher than the upper limit of the reference range. The control unit 31 may maintain the state of each generator 2 in response to the current total amount of power generated being within the reference range.

[0033] The control unit 31 may store the rated output of each generator 2, and may control each generator 2 based on the rated output of the generator 2 in the power generation state. For example, the control unit 31 may transition at least one of the generators 2 in the standby state or the stopped state to the power generation state in response to the fact that the predicted value of the power consumption acquired by the acquisition unit 30 is greater than the rated output of each generator 2 currently in the power generation state. The rated output may be the maximum amount of power that can be stably output. The control unit 31 may add the generators 2 in the standby state or the stopped state to the transition candidates of the operation state one by one in order, calculate the sum of the rated output of each of the transition candidates and the sum of the rated output of each of the generators 2 already in the power generation state, and transition each of the transition candidates to the power generation state in response to the total value exceeding the predicted value of the power consumption. The order of the generators 2 added to the transition candidates may be in descending order of rated output or in descending order. The order of the generators 2 added to the transition candidates may be in descending order of the total time that the generator 2 has been in the power generation state, or in descending order. The order in which the generators 2 are added to the transfer candidates may be random.

[0034] According to the above-mentioned device 3, each generator 2 is controlled so that the amount of power generated by the multiple generators 2 falls within a standard range based on the predicted power consumption, thereby preventing power outages on the ship due to insufficient power generation and preventing fuel waste due to excessive power generation.

[0035] In addition, a predicted value including the power consumption of the crane installed on the ship is obtained as the predicted value of the ship's power consumption at the scheduled time of arrival, so that power to use the crane for loading or unloading can be secured, making work after arriving in port more efficient.

[0036] In addition, since a predicted value of the power consumption after a reference time required for the generator 2 to transition from a stopped state to a power generating state is obtained, even if the generator is in a standby state or a stopped state, the generator 2 can be transitioned to a power generating state according to the predicted power consumption. Therefore, power outages due to power shortages can be reliably prevented.

[0037] In addition, in response to the predicted power consumption being greater than the rated output of each generator 2 currently in a power generating state, at least one generator 2 among the multiple generators 2 that is in a standby state or a stopped state is transitioned to a power generating state, thereby making it possible to reliably prevent power outages due to power shortages.

[0038] Furthermore, in response to status data indicating the state of the ship being supplied to the model 302, a predicted value of power consumption output from the model 302 is obtained as a predicted value of power consumption after a reference time. Therefore, by supplying status data indicating the state of the ship to the model 302, a predicted value of power consumption according to the state of the ship can be obtained.

[0039] <2. Operation> 2 shows the operation of the device 3. The device 3 may control each generator 2 by performing the processes of steps S11 to S19.

[0040] In step S11, the first acquisition unit 301 acquires status data indicating the status of the ship, and in step S13, the supply unit 303 supplies the acquired status data to the model 302. As a result, in step S15, the model 302 predicts the power consumption of the ship. The model 302 may predict the power consumption after a reference time from the status indicated by the status data.

[0041] In step S17, the second acquisition unit 304 acquires a predicted value of the power consumption output from the model 302. Then, in step S19, the control unit 31 controls each of the multiple generators 2 so that the amount of power generated by the generators 2 falls within a reference range from the predicted value of the power consumption acquired in step S17. When the process of step S19 is completed, the process may proceed to step S11.

[0042] <3. Modifications> Fig. 3 shows a system 1A according to a modified example. Note that parts that are substantially the same as those in the system 1 shown in Fig. 1 are given the same reference numerals, and the description thereof will be omitted.

[0043] A device 3A of the system 1A acquires a predicted value of power consumption in a manner different from that of the system 1 in the above embodiment. The device 3A has a storage unit 33A, an acquisition unit 30A, and a control unit 31A.

[0044] The memory unit 33A prestores predicted values ​​of the ship's power consumption at a plurality of times. The plurality of times for which the power consumption is stored may be pre-set within a period ranging from the ship's scheduled departure time to the scheduled arrival time. For example, if the ship is scheduled to depart at 9:00 on January 1st and arrive at port at 21:00 on January 3rd, the plurality of times may be set for each reference time (in this modified example, the time required for the generator 2 to transition from a stopped state to a power generating state) within the period from 9:00 on January 1st to 21:00 on January 3rd. Alternatively, the plurality of times may be pre-set within a period of one day. For example, the plurality of times may be set for each reference time within a period from 0:00 to 24:00. The predicted value of the power consumption at each time may be calculated from the power consumption at each time during past voyages.

[0045] The acquisition unit 30A reads out from the storage unit 33A a predicted value of power consumption after a reference time from the current time. This allows the predicted value of power consumption after the reference time to be acquired. The acquisition unit 30A may acquire the current time from an external clock device (not shown) or the like, and may read out from the storage unit 33A a predicted value of power consumption associated with the acquired current time. The acquisition unit 30A may supply the read predicted value to the control unit 31.

[0046] The control unit 31A controls each of the multiple generators 2 mounted on the ship so that the amount of power generated by the generators 2 falls within a reference range based on the predicted value of the power consumption acquired by the acquisition unit 30A. The control unit 31A may differ from the control unit 31 in the above embodiment in that it acquires status data related to the generators 2 from outside the device 3A.

[0047] According to the above-mentioned device 3A, predicted values ​​of the ship's power consumption at multiple times are pre-stored, and a predicted value of the power consumption a reference time from the current time is read out, thereby simplifying the configuration for obtaining the predicted value of power consumption.

[0048] In addition, since the multiple times at which predicted power consumption values ​​are stored are set in advance within the period from the ship's scheduled departure time to the scheduled arrival time, predicted power consumption values ​​can be obtained that match the state of the ship at each time from departure to arrival.

[0049] In addition, since the multiple times at which predicted power consumption values ​​are stored are set in advance within a one-day period, predicted power consumption values ​​can be obtained that match the state of the ship at each time within a one-day cycle.

[0050] In the above modification, the device 3A is described as having the memory unit 33A, but it does not have to have the memory unit 33A. In this case, the device 3A may be externally connected to a storage device that stores in advance predicted values ​​of the ship's power consumption at multiple times. The acquisition unit 30A may read out the predicted values ​​of the power consumption from the storage device.

[0051] <4. Other Modifications> In the above embodiment and modified example, the time required for each generator 2 to transition from a stopped state to a power generating state has been described as the same time, but the time may be different from each other. In this case, the acquisition unit 30, 30A may set a different time according to the generator 2 to be transitioned from a stopped state to a power generating state as the reference time, and acquire a predicted value of the power consumption after the reference time. As an example, the acquisition unit 30, 30A may set the time required for the stopped generator 2 to transition to a power generating state as the reference time in response to being supplied with state data including the generator ID of the stopped generator 2. When multiple generators 2 are in a stopped state, the acquisition unit 30, 30A may use the longest time among multiple times required for each generator 2 to transition to a power generating state as the reference time.

[0052] Furthermore, the reference time has been described as the time required for the generator 2 to transition from a stopped state to a power generating state, but it may be the time required for the generator 2 to transition from a standby state to a power generating state.

[0053] Various embodiments of the present invention may also be described with reference to flow charts and block diagrams, where the blocks may represent (1) stages of a process in which operations are performed or (2) sections of an apparatus responsible for performing the operations. Particular stages and sections may be implemented by dedicated circuitry, programmable circuitry provided with computer readable instructions stored on a computer readable medium, and / or a processor provided with computer readable instructions stored on a computer readable medium. Dedicated circuitry may include digital and / or analog hardware circuitry and may include integrated circuits (ICs) and / or discrete circuits. Programmable circuitry may include reconfigurable hardware circuitry including logical AND, logical OR, logical XOR, logical NAND, logical NOR, and other logical operations, memory elements such as flip-flops, registers, field programmable gate arrays (FPGAs), programmable logic arrays (PLAs), and the like.

[0054] A computer-readable medium may include any tangible device capable of storing instructions that are executed by a suitable device, such that the computer-readable medium having instructions stored thereon comprises an article of manufacture that includes instructions that can be executed to create means for performing the operations specified in the flowcharts or block diagrams. Examples of computer-readable media may include electronic storage media, magnetic storage media, optical storage media, electromagnetic storage media, semiconductor storage media, and the like. More specific examples of computer-readable media may include floppy disks, diskettes, hard disks, random access memories (RAMs), read-only memories (ROMs), erasable programmable read-only memories (EPROMs or flash memories), electrically erasable programmable read-only memories (EEPROMs), static random access memories (SRAMs), compact disk read-only memories (CD-ROMs), digital versatile disks (DVDs), Blu-ray (RTM) disks, memory sticks, integrated circuit cards, and the like.

[0055] The computer readable instructions may include either assembler instructions, Instruction Set Architecture (ISA) instructions, machine instructions, machine-dependent instructions, microcode, firmware instructions, state setting data, or source or object code written in any combination of one or more programming languages, including object-oriented programming languages ​​such as Smalltalk®, JAVA®, C++, etc., and conventional procedural programming languages ​​such as the “C” programming language or similar programming languages.

[0056] Computer readable instructions may be provided to a processor or programmable circuitry of a general purpose computer, special purpose computer, or other programmable data processing apparatus, either locally or over a local area network (LAN), a wide area network (WAN), such as the Internet, etc., to execute the computer readable instructions to create means for performing the operations specified in the flowcharts or block diagrams. Examples of processors include computer processors, processing units, microprocessors, digital signal processors, controllers, microcontrollers, etc.

[0057] 4 illustrates an example of a computer 2200 in which aspects of the present invention may be embodied in whole or in part. Programs installed on the computer 2200 may cause the computer 2200 to function as or perform operations associated with an apparatus or one or more sections of the apparatus according to an embodiment of the present invention, and / or to perform a process or steps of the process according to an embodiment of the present invention. Such programs may be executed by the CPU 2212 to cause the computer 2200 to perform specific operations associated with some or all of the blocks of the flowcharts and block diagrams described herein.

[0058] The computer 2200 according to this embodiment includes a CPU 2212, a RAM 2214, a graphic controller 2216, and a display device 2218, which are connected to each other by a host controller 2210. The computer 2200 also includes input / output units such as a communication interface 2222, a hard disk drive 2224, a DVD-ROM drive 2226, and an IC card drive, which are connected to the host controller 2210 via an input / output controller 2220. The computer also includes legacy input / output units such as a ROM 2230 and a keyboard 2242, which are connected to the input / output controller 2220 via an input / output chip 2240.

[0059] The CPU 2212 operates according to a program stored in the ROM 2230 and the RAM 2214, thereby controlling each unit. The graphic controller 2216 retrieves image data generated by the CPU 2212 into a frame buffer or the like provided in the RAM 2214 or into the graphic controller 2216 itself, and causes the image data to be displayed on the display device 2218.

[0060] The communication interface 2222 communicates with other electronic devices via a network. The hard disk drive 2224 stores programs and data used by the CPU 2212 in the computer 2200. The DVD-ROM drive 2226 reads programs or data from the DVD-ROM 2201 and provides the programs or data to the hard disk drive 2224 via the RAM 2214. The IC card drive reads programs and data from an IC card and / or writes programs and data to an IC card.

[0061] The ROM 2230 stores therein a boot program or the like executed by the computer 2200 upon activation, and / or a program that depends on the hardware of the computer 2200. The input / output chip 2240 may also connect various input / output units to the input / output controller 2220 via a parallel port, a serial port, a keyboard port, a mouse port, and the like.

[0062] The programs are provided by a computer-readable medium such as a DVD-ROM 2201 or an IC card. The programs are read from the computer-readable medium, installed in the hard disk drive 2224, the RAM 2214, or the ROM 2230, which are also examples of computer-readable media, and executed by the CPU 2212. Information processing described in these programs is read by the computer 2200, and brings about cooperation between the programs and the various types of hardware resources described above. An apparatus or method may be constructed by realizing information manipulation or processing according to the use of the computer 2200.

[0063] For example, when communication is performed between the computer 2200 and an external device, the CPU 2212 may execute a communication program loaded in the RAM 2214 and instruct the communication interface 2222 to perform communication processing based on the processing described in the communication program. Under the control of the CPU 2212, the communication interface 2222 reads transmission data stored in a transmission buffer processing area provided in the RAM 2214, the hard disk drive 2224, the DVD-ROM 2201, or a recording medium such as an IC card, and transmits the read transmission data to the network, or writes reception data received from the network to a reception buffer processing area or the like provided on the recording medium.

[0064] Furthermore, the CPU 2212 may cause all or a necessary portion of a file or database stored in an external recording medium such as the hard disk drive 2224, the DVD-ROM drive 2226 (DVD-ROM 2201), an IC card, etc. to be read into the RAM 2214, and perform various types of processing on the data on the RAM 2214. The CPU 2212 then writes back the processed data to the external recording medium.

[0065] Various types of information, such as various types of programs, data, tables, and databases, may be stored in the recording medium and undergo information processing. The CPU 2212 may perform various types of processing on the data read from the RAM 2214, including various types of operations, information processing, conditional judgment, conditional branching, unconditional branching, information search / replacement, etc., as described throughout this disclosure and specified by the instruction sequence of the program, and write back the results to the RAM 2214. The CPU 2212 may also search for information in a file, database, etc. in the recording medium. For example, when a plurality of entries each having an attribute value of a first attribute associated with an attribute value of a second attribute are stored in the recording medium, the CPU 2212 may search for an entry that matches a condition, in which an attribute value of the first attribute is specified, from among the plurality of entries, read the attribute value of the second attribute stored in the entry, and thereby obtain the attribute value of the second attribute associated with the first attribute that satisfies a predetermined condition.

[0066] The above-described programs or software modules may be stored in a computer-readable medium on the computer 2200 or in the vicinity of the computer 2200. Also, a recording medium such as a hard disk or a RAM provided in a server system connected to a dedicated communication network or the Internet can be used as a computer-readable medium, thereby providing the programs to the computer 2200 via the network.

[0067] Although the present invention has been described above using the embodiments, the technical scope of the present invention is not limited to the scope described in the above embodiments. It is clear to those skilled in the art that various modifications and improvements can be made to the above embodiments. It is clear from the description of the claims that such modifications and improvements can also be included in the technical scope of the present invention.

[0068] It should be noted that the order of execution of each process, such as operations, procedures, steps, and stages, in the devices, systems, programs, and methods shown in the claims, specifications, and drawings is not specifically stated as "before," "prior to," etc., and may be realized in any order unless the output of a previous process is used in a later process. Even if the operational flow in the claims, specifications, and drawings is explained using "first," "next," etc. for convenience, it does not mean that it is essential to perform the process in this order. [Explanation of symbols]

[0069] 1 System 2. Generator 3 equipment 30 Acquisition Department 31 Control Unit 33A Storage section 301 First acquisition part 302 Model 303 Supply section 304 Second Acquisition Department 2200 Computer 2201 DVD-ROM 2210 Host Controller 2212 CPU 2214 RAM 2216 Graphics Controller 2218 Display Device 2220 Input / Output Controller 2222 Communication Interface 2224 Hard Disk Drive 2226 DVD-ROM drive 2230 ROM 2240 Input / Output Chip 2242 Keyboard

Claims

1. An acquisition unit that acquires a predicted value of power consumption of a ship equipped with multiple generators; a control unit that controls each of the plurality of generators so that the amount of power generated by the generators falls within a reference range based on the predicted value of the amount of power consumption acquired by the acquisition unit; An apparatus comprising:

2. the ship is a cargo ship having a crane, The device according to claim 1 , wherein the acquisition unit acquires a predicted value including the power consumption of the crane as the predicted value of the power consumption of the ship at the scheduled port arrival time.

3. The device according to claim 1, wherein the control unit transitions at least one of the plurality of generators that is in a standby state or a stopped state to a power generating state in response to a predicted value of power consumption acquired by the acquisition unit being greater than the rated output of each generator that is currently in a power generating state.

4. The device according to claim 1 , wherein the acquisition unit acquires a predicted value of power consumption after a reference time period required for a generator in a standby state or a stopped state to transition to a power generating state.

5. A storage unit that stores in advance predicted values ​​of power consumption of the ship at a plurality of times, The device according to claim 4 , wherein the acquisition unit reads out from the storage unit a predicted value of the amount of power consumption from a current time to the reference time.

6. The device according to claim 5 , wherein the plurality of times are preset within a period ranging from the scheduled departure time of the ship to the scheduled arrival time of the ship.

7. The apparatus of claim 5 , wherein the plurality of times are preset within a period of a day.

8. The acquisition unit is a first acquisition unit that acquires status data indicating a status of the ship; a supply unit that supplies the state data acquired by the first acquisition unit to a model that outputs a predicted value of the amount of power consumption after the reference time in response to input of the state data; a second acquisition unit that acquires, as a predicted value of power consumption after the reference time, a predicted value of power consumption output from the model in response to the supply unit supplying the state data to the model; 5. The apparatus of claim 4, further comprising:

9. An acquisition stage for acquiring a predicted value of the power consumption of a ship equipped with multiple generators; a control step of controlling each of the plurality of generators so that the amount of power generated by the plurality of generators falls within a reference range based on the predicted value of the amount of power consumption obtained by the obtaining step; A method for providing the above.

10. Computer, An acquisition unit that acquires a predicted value of power consumption of a ship equipped with multiple generators; A control unit that controls each of the plurality of generators so that the amount of power generated by the generators falls within a reference range based on the predicted value of the amount of power consumption acquired by the acquisition unit. A program that functions as a

Citation Information

Patent Citations

  • Method of determining optimum number of operating generators

    JP1988015634A

  • Crane control device

    JP2011157181A

  • Generator controller and generator control method

    JP2013258874A

  • Vessel speed control device, vessel speed control system, vessel speed control method, and vessel speed control program

    JP2015123806A