Injection management method and injection management system of infiltration solidification treatment method, and ground improvement method and computer program using these
By installing a water pressure gauge and creating a database to manage pore water pressure, the method accurately estimates effective injection pressure, preventing split injection and optimizing chemical injection speed to improve construction productivity.
Patent Information
- Application Number
- JP2023057216
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2024-10-15
AI Technical Summary
Current injection management methods for infiltration solidification treatment fail to accurately estimate effective injection pressure, leading to potential overestimation or underestimation of critical injection rates, resulting in split injection and decreased construction productivity due to variations in ground permeability and chemical solution viscosity over time.
Install a water pressure gauge within the improvement area to measure pore water pressure, create a database of the relationship between pore water pressure and effective injection pressure, and control the chemical injection speed to prevent split injection and optimize the injection process.
Accurately estimates effective injection pressure, prevents split injection, and enhances construction productivity by optimizing chemical injection speed.
Smart Images

Figure 2024145002000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to an injection management method for a permeation solidification treatment method, an injection management system, a ground improvement method using these, and a computer program. [Background technology]
[0002] As a countermeasure against liquefaction caused by earthquakes directly beneath existing structures, a well-known method is the infiltration solidification treatment method, in which holes are drilled from the ground surface and a chemical solution is injected and allowed to infiltrate to solidify and improve the ground. This infiltration solidification treatment method prevents liquefaction of the ground by replacing the interstitial water between the soil particles in the ground with a chemical solution. By carrying out infiltration injection without destroying the soil particle skeleton that constitutes the ground, it is possible to carry out high-quality ground improvement while preventing uplift of the ground and runaway of the chemical solution (see Non-Patent Document 2).
[0003] Patent Document 1 discloses a construction management method for a chemical injection method in which a measuring device for measuring electrical conductivity or salinity is placed as an expansion liquid detection means around the injection position where the chemical liquid and the chemical liquid penetration area expanding liquid are injected, outside the planned expansion radius of the chemical liquid penetration area, and when the expansion liquid detection means detects the chemical liquid penetration area expanding liquid, it is determined that the chemical liquid penetration area expanding liquid has leaked out from the chemical liquid penetration area, and the injection of the chemical liquid and the chemical liquid penetration area expanding liquid is managed based on that determination.
[0004] Patent Document 2 discloses a method for managing the outside of injection in a ground injection method using a non-alkaline silica grout, which corresponds to the injection hole interval, injection stage, injection amount, injection speed, and injection time, and reduces deviations outside the injection range, and accumulates any of the data such as injection ground data, drilling data, injection device data, measuring device and measurement data, and environmental data in an on-site centralized management device, analyzes data from the construction site together with existing data, and feeds back the results to the construction site. Environmental data includes groundwater pH, ground displacement, and the position and displacement of structures.
[0005] Patent Document 3 discloses that the ground injection device is provided with an outer injection pipe installed in the ground, and an injection device and a suction device connected to the outer injection pipe via an injection pipe and a suction pipe, and by repeatedly injecting and suctioning a plastic gel injection material by the outer injection pipe, the injection device and the suction device, the bonds between soil particles in the surrounding ground are released and the plastic gel injection material is injected into voids formed around the lumpy gel body, which gradually expands and compacts the surrounding ground. The device discloses that a water pressure gauge is provided in the injection pipe or in the ground near the improvement area to observe the increase in pore water pressure caused by the injection and suction of the plastic gel injection material, and to perform efficient improvement at an optimum injection speed and frequency. [Prior art documents] [Patent documents]
[0006] [Patent Document 1] JP 2017-155506 A [Patent Document 2] JP 2021-185301 A [Patent Document 3] JP 2017-119997 A [Non-patent literature]
[0007] [Non-Patent Document 1] Hiroyuki Yamazaki, Kenichi Maeda, Kunio Takahashi, Zenkouki and Kentaro Hayashi, "Development of a liquefaction countermeasure method using solution-type injection solidification material," Port and Harbor Engineering Research Institute, No. 905, pp. 6-7 (1998). [Non-Patent Document 2] Coastal Technology Research Center, "Infiltration and Solidification Treatment Method Technical Manual (revised edition)", pp. 44-45, 136-137 (2020) [Non-Patent Document 3] Geotechnical Society of Japan, "Soil Testing: Basics and Guidelines, Second Revised Edition," 100 pages (2010) Summary of the Invention [Problem to be solved by the invention]
[0008] The injection form of the chemical solution in the permeation solidification treatment method changes depending on the permeability of the ground and the injection speed and pressure, and as the injection speed increases, it progresses from permeation to fracturing permeation to fracturing. If the fracturing progresses significantly and the injection form becomes more like fracturing injection than permeation injection, the improvement body becomes less homogeneous and sufficient improvement effect cannot be obtained, so injection is generally performed at a slow injection speed up to fracturing permeation. Therefore, a limit injection speed test is conducted to determine the maximum injection speed at which permeation injection is possible and a nearly satisfactory solidification state can be obtained.
[0009] Fig. 1 shows a typical chemical injection system for implementing the penetration solidification treatment method. The chemical injection system in Fig. 1 includes a fully automatic mixer 1 for the chemical solution, a chemical injection pump 2, and a flow rate control circuit for controlling the chemical solution and the source pressure P pump The system is equipped with a flowmeter detection unit 3 that detects the flow rate of the water, a hose puller controller 4, and a hose puller 5. Using a grout hose 6, a packer hose 7, and a double-pipe injection hose 8, the chemical is injected into the ground from a chemical injection port 11 between injection packers 10, 10 of a double injection pipe 9 installed in the ground. The chemical is injected into the ground from a chemical injection pump 2 at a base pressure P pump The liquid is then pumped through the injection port 11 into the ground at an effective injection pressure P. In this injection route, the double-pipe injection hose 8 and the injection pipe 9, etc., reduce the pressure loss inside the pipe (loss pressure P loss ) occurs.
[0010] Theoretical background (see non-patent document 1) Fracture can be understood as a phenomenon in which soil cannot resist the pressure (effective injection pressure) applied to the tip of the injection hole and breaks. This phenomenon is called hydraulic fracturing, and occurs when the conditions of the following equation (1) are met.
[0011]
number
[0012] Here, P fh is the injection pressure in the ground at which fracturing occurs, P0 is the total vertical stress, σ tis the tensile strength of the soil, and m is a coefficient that depends on the fracturing conditions, etc. and takes a value of about 1 to 2. It is on the safe side to consider m to be 1, and in cases where the tensile resistance of sand can be ignored, the fracturing resistance can be considered to be the overburden pressure, including water pressure.
[0013] On the other hand, the theoretical optimum injection rate can be determined by applying the Maag approach. Assuming that the permeation injection occurs spherically as shown in Figure 1, the relationship between the effective injection pressure h and the injection rate q is defined by the following equation (2).
[0014]
number
[0015] Here, k is the permeability coefficient of the ground, r1 is the radius of the injection pipe, μ L is the viscosity coefficient of the grout, μ w is the viscosity coefficient of water.
[0016] The relationship between the penetration grouting and the fracturing limit can be represented diagrammatically in Figure 2 using the above formulas (1) and (2).
[0017] In practice, the limit injection pressure (P in Figure 2) fh (corresponding to 10 ... loss The source pressure P pump This is the value subtracted from
[0018]
number
[0019] In the injection management, the injection rate q below the limit injection rate determined in Figure 3 is control The chemical solution is injected at a constant rate according to the injection pressure limit P fh However, in the current management method, the effective injection pressure P cannot be measured directly, so the loss pressure P loss Assume that the source pressure P pump For example, in Non-Patent Document 2, the limit injection pressure P fh Based on this, P loss = 0.2MPa, the original pressure P pump In other words, the control standard is expressed by the following formula (4).
[0020]
number
[0021] Problems with the current management method Base pressure P including assumptions pump In addition, due to the two uncertainties of (1) and (2) below, it is possible that the effective injection pressure in the actual ground exceeds the fracturing limit (overestimation), or that the limit injection pressure is underestimated and extremely conservative injection management is being carried out.
[0022] Uncertainty (1) The relationship between the effective injection pressure P and the injection rate q (Pq relationship) shown in Figures 2 and 3 depends on the permeability coefficient of the ground (see formula (2)). Actual ground is heterogeneous, and the permeability coefficient of the ground is not unique within the construction area, and generally there is spatial variation. Figures 4(a) and (b) show the permeability coefficients estimated using the Maag formula and the results of the limit injection rate test for the As1 layer to be improved (see Figure 9 below) at multiple points A to J. It can be seen that there is a large variation in the permeability coefficients, even though the As1 layer is the same target for improvement.
[0023] On the other hand, since injection management assumes a single Pq relationship, if the effective injection pressure cannot be properly evaluated, there will be many locations where the critical injection rate is overestimated or underestimated if the permeability coefficient varies widely. In other words, as shown in Figure 5(a), in locations where the permeability coefficient k of the ground is small, the critical injection pressure P fh In addition, as shown in Figure 5(b), in areas where the permeability coefficient k of the ground is large, the critical injection pressure P fh This reduces construction productivity because the amount of concrete required is underestimated and the concrete is injected at a slower rate than would be possible.
[0024] Uncertainty (2) The Pq relationship shown in Figures 2 and 3 depends on the viscosity coefficient of the chemical solution as well as the permeability coefficient of the ground (see equation (2)). Figure 6 shows an example of the change in viscosity (viscosity coefficient) of a chemical solution over time. The chemical solution is made by mixing multiple agents so that it will gel when the entire designed injection amount has been injected. Here, the time required for gelation is called the gel time. The viscosity of the chemical solution increases over time even before gelation, but is characterized by a particularly rapid increase around the gel time. Meanwhile, injection management does not take into account the change in viscosity of the chemical solution over time.
[0025] With reference to Fig. 7(a) to (c), examples of problems in construction caused by changes in the viscosity of the chemical solution will be described. In construction, as shown in Fig. 7(b), the chemical solution is injected at an arbitrary injection rate q control The liquid is injected at a constant rate according to the formula: However, the viscosity of the liquid increases during injection, so the Pq relationship shifts to the left as shown in Figure 7(a), and the effective injection pressure gradually increases during injection as shown in Figure 7(c). At this time, the fracturing limit P fh Larger set limit injection pressure P pump-set (=P fh +0.2) when injection management is performed (P fh overestimation), P fh The above effective injection pressure will act on the ground, resulting in a fracturing injection mode, which is undesirable from the perspective of ensuring the quality of the improved body.
[0026] The construction management methods of the chemical grouting method in Patent Documents 1 and 2 do not take into consideration the influence of the above-mentioned changes over time in the permeability coefficient of the ground or the viscosity of the chemical solution on the relationship between the effective injection pressure P and the injection rate q. Patent Document 3 uses a water pressure gauge installed in the ground to observe the increase in pore water pressure caused by the injection and suction of the plastic gel injection material, but does not consider the influence of changes over time in the permeability coefficient of the ground or the viscosity of the chemical solution.
[0027] In view of the problems of the conventional technology as described above, the present invention aims to provide an injection management method and an injection management system for a permeation solidification treatment method, which can accurately estimate the effective injection pressure in the permeation solidification treatment method, prevent fracturing injection, optimize the chemical injection speed, and improve construction productivity, as well as a ground improvement method and a computer program using these. [Means for solving the problem]
[0028] The injection management method for the permeation solidification treatment method for achieving the above-mentioned object includes the steps of installing a water pressure gauge within the improvement area away from the chemical injection port of a chemical injection pipe installed in the ground to be improved using the permeation solidification treatment method, simulating and creating a database of the relationship between the pore water pressure during injection measured by the water pressure gauge and the effective injection pressure of the chemical at the chemical injection port, and starting the injection of the chemical into the ground to be improved, referring to the database for the pore water pressure during injection measured by the water pressure gauge, and estimating the effective injection pressure from the pore water pressure, and controlling the injection rate of the chemical so that the estimated effective injection pressure does not exceed a limit injection pressure.
[0029] According to the injection management method for this permeation solidification treatment method, the relationship between the pore water pressure during injection measured by a water pressure gauge installed within the improvement area away from the chemical injection port of the chemical injection pipe installed in the ground to be improved, and the effective injection pressure of the chemical at the chemical injection port is simulated and compiled into a database, and after the start of chemical injection into the ground to be improved, the effective injection pressure can be accurately estimated from the pore water pressure during injection measured by the water pressure gauge.By controlling the injection rate of the chemical so that this estimated effective injection pressure does not exceed the limit injection pressure, it is possible to prevent fracturing injection, optimize the chemical injection rate, and improve construction productivity.
[0030] In the injection management method for the above-mentioned permeation solidification treatment method, it is preferable to measure the change in viscosity of the chemical solution over time in the ground to be improved, and to estimate the effective injection pressure taking into account the measured change in viscosity of the chemical solution over time.
[0031] In addition, before installing the water pressure gauge, a field permeability test can be carried out using the hole for installing the water pressure gauge to determine the permeability coefficient of the ground to be improved.
[0032] In addition, when forming a hole for installing another water pressure gauge adjacent to the hole for installing the water pressure gauge, it is preferable to determine the position of the hole for installing the other water pressure gauge based on the determined permeability coefficient.
[0033] In addition, the estimated effective injection pressure P and the base pressure P of the pump that injects the liquid pump Therefore, the pipe loss (P pump -P) over time is recorded, and the effective injection pressure at the chemical injection port where the water pressure gauge is not installed can be estimated based on the loss in the pipe.
[0034] The injection management system for the permeation solidification treatment method for achieving the above-mentioned objective comprises: means for simulating and creating a database of the relationship between the pore water pressure during injection measured by a water pressure gauge installed within the improvement range away from the chemical injection port of a chemical injection pipe installed in the ground to be improved by the permeation solidification treatment method, and the effective injection pressure of the chemical solution at the chemical injection port; means for estimating the effective injection pressure from the pore water pressure by referring to the database the pore water pressure during injection measured by the water pressure gauge after the start of injection of the chemical solution into the ground to be improved; and means for controlling the injection rate of the chemical solution so that the estimated effective injection pressure does not exceed a limit injection pressure.
[0035] According to the injection management system for the above-mentioned permeation solidification treatment method, the relationship between the pore water pressure during injection measured by a water pressure gauge installed within the improvement area away from the chemical injection port of the chemical injection pipe installed in the ground to be improved and the effective injection pressure of the chemical at the chemical injection port is simulated and stored in a database, and after the start of chemical injection into the ground to be improved, the effective injection pressure can be accurately estimated from the pore water pressure during injection measured by the water pressure gauge.By controlling the injection speed of the chemical so that this estimated effective injection pressure does not exceed the limit injection pressure, it is possible to prevent fracturing injection, optimize the chemical injection speed, and improve construction productivity.
[0036] In the injection management system for the above-mentioned penetration solidification treatment method, it is preferable to provide a means for measuring the change in viscosity of the chemical solution over time in the ground to be improved, and to estimate the effective injection pressure taking into account the measured change in viscosity of the chemical solution over time.
[0037] In addition, the estimated effective injection pressure P and the base pressure P of the pump that injects the liquid pump Therefore, the pipe loss (P pump -P) with time, and the effective injection pressure at the chemical injection port where the water pressure gauge is not installed can be estimated based on the loss in the pipe.
[0038] The ground improvement method for achieving the above object involves improving the target ground by the permeation solidification treatment method using the injection management method for the permeation solidification treatment method described above or the injection management system for the permeation solidification treatment method described above.
[0039] According to this ground improvement method, when carrying out a permeation solidification treatment method, the effective injection pressure at the chemical injection port can be accurately estimated, fracturing injection can be prevented, the chemical injection speed can be optimized, and construction productivity can be improved.
[0040] A computer program for achieving the above object causes a computer to function as each of the means in the injection management system for the above-mentioned permeation solidification treatment method.
[0041] This computer program can operate an injection management system, and when carrying out a penetration solidification treatment method, it can accurately estimate the effective injection pressure at the chemical injection port, prevent fracturing injection, optimize the chemical injection speed, and improve construction productivity. Effect of the Invention
[0042] According to the present invention, it is possible to provide an injection management method and an injection management system for a permeation solidification treatment method, which can accurately estimate the effective injection pressure of the chemical solution at the chemical solution injection port in the permeation solidification treatment method, prevent fracturing injection, optimize the chemical solution injection speed, and improve construction productivity, as well as a ground improvement method and a computer program using these. [Brief description of the drawings]
[0043] [Figure 1] FIG. 1 is a diagram showing a schematic diagram of a general chemical injection system for carrying out a permeation solidification treatment method. [Diagram 2] FIG. 1 is a schematic diagram showing the relationship between penetration injection and fracturing limit. [Diagram 3] FIG. 2 is a schematic diagram showing the relationship between the injection rate q and the effective injection pressure P (Pq relationship) obtained by a limit injection rate test. [Figure 4]1 shows a table (a) and a graph (b) showing the permeability coefficients estimated by the Maag formula and the results of limit injection rate tests for multiple points A to J in the As1 layer to be improved. [Diagram 5] FIG. 1 shows a schematic diagram (a) to explain that the critical injection pressure Pfh is overestimated in areas where the permeability coefficient k of the ground is small when the conventional only Pq relationship is assumed, and FIG. 2 shows a schematic diagram (b) to explain that the critical injection pressure Pfh is underestimated in areas where the permeability coefficient k of the ground is large. [Figure 6] 1 is a graph showing an example of change in viscosity (viscosity coefficient) of a liquid medicine over time. [Figure 7] This is a schematic diagram (a) showing that the Pq relationship shifts to the left as the viscosity of the drug solution increases over time, a schematic diagram (b) showing that the drug solution is injected at a constant rate by qcontrol, which is an arbitrary injection rate less than the limit injection rate, and a schematic diagram (c) showing that the effective injection pressure increases over time. [Figure 8] 1 is a flowchart for explaining steps S01 to S09 of an injection management method for a permeation solidification treatment method according to the present embodiment. [Figure 9] This is a schematic diagram showing examples of representative N-values for each soil layer within the improvement range of the target ground. [Figure 10] 10(a) is a cross-sectional view showing a water pressure gauge installation hole installed within the improvement range of the target ground, and (b) is a cross-sectional view showing a water pressure gauge installed in the water pressure gauge installation hole of Figure 10(a). [Figure 11] 10(a) to (c) are graphs showing the results of simulating pore water pressure when the distance between the injection position and the water pressure gauge in FIG. 10(a) is 1 m, 2 m, and 3 m, and the effective injection pressure is 0.06 MPa, 0.09 MPa, and 0.12 MPa. [Figure 12] 9 is a block diagram illustrating an injection management system capable of implementing the injection management method of the permeation solidification treatment method of FIG. 8. [Figure 13] FIG. 2 is a plan view of the ground surface to explain the planar installation position of the water pressure gauge in this embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0044] Hereinafter, the injection management method of the permeation solidification treatment method according to the embodiment of the present invention will be described with reference to Figs. 8 to 12. Fig. 8 is a flow chart for explaining steps S01 to S09 of the injection management method of the permeation solidification treatment method according to the present embodiment. Fig. 9 is a schematic diagram showing an example of a representative value of N value for each soil layer in the improvement range of the target ground. Fig. 10 is a cross-sectional view (a) showing a water pressure gauge installation hole provided in the improvement range of the target ground, and a cross-sectional view (b) showing a water pressure gauge installed in the water pressure gauge installation hole of Fig. 10(a). Fig. 11 is a graph showing the results of simulating pore water pressure with effective injection pressures of 0.06 MPa, 0.09 MPa, and 0.12 MPa when the distance between the injection position and the water pressure gauge is 1 m, 2 m, and 3 m (a) to (c). Fig. 12 is a block diagram showing an injection management system capable of implementing the injection management method of the permeation solidification treatment method of Fig. 8.
[0045] As a preliminary step, the strata composition and physical properties (deformation coefficient E, Poisson's ratio μ, permeability coefficient k, etc.) of the target ground in existing structures such as airports, where measures against liquefaction due to earthquakes will be taken, are modeled using an FEM. The deformation coefficient E is estimated from the N value, and the permeability coefficient k can be determined by an on-site permeability test using a water pressure gauge installation hole, as described below (see Non-Patent Document 3, Chapter 11 "Soil Permeability Test"). However, it may also be estimated using the theoretical formula (Maag) and the results of a limit injection rate test. In this case, the N value to be used is set to a representative value (average value or minimum value, etc.) for each soil layer in the improvement range, as shown in Figure 9.
[0046] Various data values are inputted through an input device of a personal computer (PC) of the injection management system 30 in FIG. 12, and are recorded in a memory section comprised of a storage device such as an HDD or SSD built into the PC.
[0047] The permeation solidification treatment method according to this embodiment can be performed using the chemical injection system of FIG. 1. First, as shown in FIG. 10(a), a double injection pipe 9 (FIG. 1) having chemical injection ports 11a and 11b is installed vertically in the target ground (S01). Similarly, a double injection pipe 9 (FIG. 1) having chemical injection ports 11c and 11d, chemical injection ports 11e and 11f, chemical injection ports 11g and 11h, and chemical injection ports 11i and 11j is installed vertically in the target ground. Note that the injection pipe 9 (FIG. 1) is omitted in FIG. 10(a). Each injection pipe 9 (FIG. 1) may further have a chemical injection port.
[0048] 10(a) and 10(b), in order to indirectly measure the effective injection pressure, a hole 20 for installing a water pressure gauge is provided at a position away from the chemical injection port 11 within the improvement range (S02). The water pressure gauge installation hole 20 has an upper hole 20a having a diameter of, for example, 150 mm and a lower hole 20b having a diameter of, for example, 50 mm. The water pressure gauge installation holes 20 are formed at multiple locations according to the positions of the multiple injection pipes 9.
[0049] Next, before installing the water pressure gauges, an on-site permeability test is performed using each water pressure gauge installation hole 20 to determine the permeability coefficient k of the target ground (S03). The permeability coefficient k is input to the personal computer PC in FIG. 12 and recorded in the memory unit of the personal computer PC.
[0050] Next, a water pressure gauge 21 is installed near the bottom end of the lower hole 20b of the water pressure gauge installation hole 20 (S04), and a logger battery 23 is placed in the upper hole 20a so that pore water pressure can be measured based on the output signal from the water pressure gauge 21. Sand is filled within an area of, for example, 1 m from the bottom end of the lower hole 20b, and cement bentonite (CB) is filled within, for example, 1 m from the bottom end to prevent chemical leakage. Similarly, a water pressure gauge 22 is installed in another water pressure gauge installation hole 20, and the required number of water pressure gauges are installed.
[0051] Here, the installation position of each water pressure gauge will be explained. As shown in FIG. 11, the smaller the permeability coefficient of the ground, the shorter the propagation distance of the pore water pressure. In other words, since the measurable range of the water pressure gauge depends on the permeability coefficient of the ground, it is necessary to determine the installation position of the water pressure gauge according to the permeability coefficient. In the case of a ground with a permeability coefficient of 1.0E-05 (cm / s), which is the application limit of the permeation solidification treatment method, the propagation distance of the pore water pressure is about 1 m as shown in FIG. 11. Therefore, in terms of the plane, it is preferable to install the water pressure gauge at a position within 1 m from the outer injection pipe. In addition, in terms of the depth direction, the water pressure gauge is installed at approximately the same depth as the injection port. In addition, in the case of a ground with a permeability coefficient of 1.0E-04 (cm / s) as shown in FIG. 4, the propagation distance of the pore water pressure is about 3 m as shown in FIG. 11. Therefore, in terms of the plane, it is preferable to install the water pressure gauge at a position within 3 m from the outer injection pipe. In addition, in terms of the depth direction, the water pressure gauge is installed at approximately the same depth as the injection port. In addition, if the ground has a permeability coefficient of 1.0E-03 (cm / s) or more, it is preferable to set the installation position within 8 m in plan, and install the water pressure gauge at approximately the same depth as the injection port.
[0052] The distances between each of the liquid chemical injection ports 11a to 11c, which are injection positions, and the water pressure gauge 21, and the distances between each of the liquid chemical injection ports 11e to 11h and the water pressure gauge 22 are input into the personal computer PC and recorded in the memory unit of the personal computer PC.
[0053] In addition, it is preferable to first determine a representative water pressure gauge installation position and then determine surrounding installation positions based on the permeability coefficient. For example, as shown in the plan view of the ground surface in FIG. 13, a water pressure gauge installation hole 20 is first formed at one location on the ground surface. This formation position is, for example, a location with a high fine content that is likely to be uplifted by chemical injection or the center of the improvement range. Next, the permeability coefficient obtained from the on-site permeability test performed in the water pressure gauge installation hole 20 (step S03 in FIG. 8) determines the planar measurable range r of the water pressure gauge installed in the water pressure gauge installation hole 20 as described above. It is preferable to determine the installation positions of the water pressure gauge installation holes 201-202 so as to cover the injection outer pipes outside the planar measurable range of the water pressure gauge in the water pressure gauge installation hole 20 and to be arranged in a triangle or square. For example, as shown in Figure 13, if the spacing between the planar installation positions 101 to 130 of multiple injection outer pipes is the standard construction spacing of 2 m and the permeability coefficient is 1.0E-04 (cm / s), the measurable range r is 3 m, and the water pressure gauge in water pressure gauge installation hole 20 is responsible for measuring each of the injection outer pipes at planar installation positions 101, 102, 110, 11, 112, 113, and 114, the water pressure gauge in water pressure gauge installation hole 201 is responsible for measuring each of the injection outer pipes at planar installation positions 123, 124, 125, 126, and 127, and the water pressure gauge in water pressure gauge installation hole 202 is responsible for measuring each of the injection outer pipes at planar installation positions 115, 116, 117, 120, 121, and 122.
[0054] On the other hand, the pore water pressure (total head) measured by the water pressure gauges 21 and 22 during injection is simulated by assuming an effective injection pressure P using the model created in advance (S05). As an example, Fig. 11 (a) to (c) show the results of simulations in which the permeability coefficient k of the target ground is set to 1.0E-03 (cm / s), 1.0E-04 (cm / s), and 1.0E-05 (cm / s) for each distance of 1 m, 2 m, and 3 m between the chemical injection port (injection position) and the water pressure gauge, and the effective injection pressure P is set to 0.06 MPa, 0.09 MPa, and 0.12 MPa. From this, the effective injection pressure P can be back-calculated from the pore water pressure measured by the water pressure gauge according to the distance between the injection position (chemical injection port) and the water pressure gauge.
[0055] Such a simulation is performed by a simulation program stored in the memory of the personal computer PC in Fig. 12, and the results of the simulation are stored in the database DB in Fig. 12 in a predetermined format, such as a table or an approximate formula showing the relationship between pore water pressure and effective injection pressure. In this case, it is desirable to use data recorded in the memory of the personal computer PC for the distance between the chemical injection port (injection position) and the water pressure gauge and the permeability coefficient k of the target ground, and to simulate the pore water pressure by assuming as many data points as possible for the effective injection pressure. When estimating the effective injection pressure, as described below, if the pore water pressure is an intermediate value, it may be supplemented by interpolation, extrapolation, etc.
[0056] In addition, the change in viscosity of the on-site liquid over time is measured for each injection day using a liquid viscometer 25 (Fig. 12) provided in the fully automatic liquid mixer 1 of Fig. 1 (S06). The liquid is sampled from the fully automatic liquid mixer 1 immediately after preparation, and the viscosity of the liquid is measured using the viscometer 25. The viscometer 25 is preferably of the rotational vibration type. The measured change in viscosity (viscosity coefficient) of the liquid over time is entered into a personal computer PC, for example in table format, and recorded in the memory unit of the personal computer PC.
[0057] Next, chemical injection is started in the target ground (S07). Chemical injection is performed, for example, from the chemical injection port 11a in Fig. 10(a), and the pore water pressure measured by the water pressure gauge 21 during this chemical injection is input to the personal computer PC in Fig. 11, and the distance between the chemical injection port 11a and the water pressure gauge 21 is read from the memory unit and referenced in the database DB to estimate the effective injection pressure (S08). In this estimation, the change in the viscosity of the chemical solution over time is taken into consideration as follows. That is, the following relational equation 5 holds between the permeability coefficient k and the chemical solution viscosity η.
[0058]
number
[0059]
number
[0060] Therefore, the viscosity η of the chemical solution according to the chemical solution injection time can be found from a graph of the change over time in the viscosity (viscosity coefficient) of the chemical solution as shown in Figure 6, and the ratio x (= η / η0) to the initial viscosity η0 can be found from the following equation 7, which is then substituted into the relational equation of equation 5 above to obtain equation 8. By substituting equation 8 for η0 into equation 6, the relational equation of equation 9 can be obtained, and by solving this, the hydraulic conductivity after a certain amount of time has passed can be found.
[0061]
number
[0062]
number
[0063]
number
[0064] In the estimation step S08, the effective injection pressure P is estimated from the pore water pressure measured by the water pressure gauge 21 using the hydraulic conductivity estimated by the formulas 8 and 9, and the injection rate q of the chemical solution is controlled based on the estimation result. In other words, the estimated effective injection pressure P is equal to the limit injection pressure P fh Injection rate q not exceeding control 1 so as to inject the liquid medicine at an effective injection pressure P. This control can be performed by displaying the estimated effective injection pressure P on a monitor MI consisting of a liquid crystal panel or the like of a personal computer PC and operating the liquid medicine injection pump 2 based on this display, but it is also possible to output an electrical signal corresponding to the estimated effective injection pressure P from the personal computer PC to the liquid medicine injection pump 2, so that the liquid medicine injection pump 2 is automatically controlled.
[0065] As described above, the effective injection pressure P estimated from the pore water pressure measured by the water pressure gauge 21 is the limit injection pressure P fh Injection rate q should not exceed controlThe drug injection is continued while controlling and managing the above, and when a predetermined amount is injected, the injection is completed (S09).
[0066] If the next chemical injection is to be performed (Yes in S10), the process returns to step S06, and steps S07 to S09 are similarly performed, for example, by injecting chemical liquid from another chemical liquid injection port 11b in Fig. 10(a). In this case, the distance between the chemical liquid injection port 11b and the water pressure gauge 21 is used. Chemical liquid injection is continued in this manner, and when chemical liquid injection into the planned improvement range of the improvement target ground is completed (No in S10), construction is completed.
[0067] In step S08, the effective injection pressure P and the base pressure P estimated as described above are pump And the loss in the pipe P loss (P pump The time-dependent changes in the pressure (P) are recorded in the memory of the personal computer PC in FIG. 12 in table format, for example, and used to estimate the effective injection pressure at the chemical injection ports 11i and 11j in FIG. 10(a), for example, where no water pressure gauge is installed.
[0068] Conventionally, the pressure loss in the injection pipe is P loss Assume that the original pressure P pump From the assumed pressure loss P loss In the conventional method, the effective injection pressure P is calculated by subtracting the above from the effective injection pressure P, and it is not possible to take into account the variation in the effective injection pressure due to the variation in the permeability coefficient and the change in the viscosity of the chemical solution over time. However, according to the injection management method of the infiltration solidification treatment method of this embodiment, the effective injection pressure P during chemical solution injection can be accurately estimated by taking into account the variation in the effective injection pressure and the change in the viscosity of the chemical solution over time using the measurement data of the pore water pressure by a water pressure gauge and prior analysis. Therefore, the effective injection pressure P can be calculated by subtracting the above from the limit injection pressure P. fh The injection rate of the drug solution should not exceed q control As a result of being able to control the amount of concrete that can be injected, fracturing injection can be prevented, the injection speed can be optimized, and construction productivity can be improved.
[0069] The reason why the simulation of step S05 in FIG. 8 is necessary will be explained. As shown in FIG. 10(a), the pore water pressure measured by the water pressure gauges 21 and 22 is the pore water pressure at the positions of the water pressure gauges 21 and 22, while the effective injection pressure to be estimated is the pressure at the positions of the chemical injection ports 11a to 11j. The effective injection pressure is the largest at the positions of the chemical injection ports 11a to 11j, but it becomes smaller when the chemical solution reaches the water pressure gauges 21 and 22 while penetrating into the soil. For this reason, it is necessary to estimate the effective injection pressure at the chemical injection ports 11a to 11j from the pore water pressure measured by the water pressure gauges 21 and 22. For this reason, it is necessary to simulate the pore water pressure measured by the water pressure gauges 21 and 22 during injection assuming the effective injection pressure. Note that the degree to which the injection pressure becomes smaller depends on the permeability of the soil to be infiltrated and the distance, so in FIG. 11(a) to (c), calculation examples according to the hydraulic conductivity and distance are shown.
[0070] In addition to the simulation programs mentioned above, the PC in Figure 12 has programs stored in its memory for FEM modeling, estimating effective injection pressure, recording, controlling the injection rate, etc. These programs are read out as needed and function as each means of the injection management system.
[0071] In addition, the personal computer PC and its monitor MI may be installed in a control room near the fully automatic chemical mixer 1 and the chemical injection pump 2 in Figure 1, but various data may also be sent via the Internet or the like to a personal computer installed in a remote control office or the like.
[0072] Although the embodiments for carrying out the present invention have been described above, the present invention is not limited to these, and various modifications are possible within the scope of the technical concept of the present invention. For example, the present embodiment is an example in which the liquid injection pipe is installed vertically in the target ground, but the present invention is not limited to this, and can also be applied to a case in which the liquid injection pipe is installed horizontally in the target ground and liquid is injected.
[0073] Furthermore, the database DB in FIG. 12 can be constructed within the storage unit of the personal computer PC, but is not limited to this and may also be constructed in an external storage device, an external computer, a cloud computer, or the like. [Industrial Applicability]
[0074] According to the present invention, the effective injection pressure in the permeation solidification treatment method can be accurately estimated, fracturing injection can be prevented, the chemical injection rate can be optimized, and construction productivity can be improved, so that the ground improvement method using the permeation solidification treatment method can be carried out with high accuracy and ease of construction. [Explanation of symbols]
[0075] 2. Chemical injection pump 9 Double injection tube, injection tube 11, 11a to 11j: Chemical injection port of injection tube 20,201,202 Water pressure gauge installation hole 21,22 Water pressure gauge 25 Viscometer 30 Infusion Management System 101~130 Plane installation position of outer injection pipe r Plane measurement range of the water pressure gauge DB Database MI Monitor PC
Claims
1. A step of installing a water pressure gauge within the improvement target area away from a chemical injection port of a chemical injection pipe installed in the ground to be improved by the penetration solidification treatment method; A step of simulating the relationship between the pore water pressure during injection measured by the water pressure gauge and the effective injection pressure of the chemical solution at the chemical solution injection port and creating a database; The method includes a step of starting injection of the chemical solution into the ground to be improved, referring to the database the pore water pressure during injection measured by the water pressure gauge, and estimating an effective injection pressure from the pore water pressure, An injection management method for a penetration solidification treatment method, which controls the injection rate of the chemical solution so that the estimated effective injection pressure does not exceed a limit injection pressure.
2. Measure the change in viscosity of the solution over time in the ground to be improved; 2. The injection management method for a penetration solidification treatment method according to claim 1, wherein the effective injection pressure is estimated taking into consideration a change over time in the viscosity of the measured chemical solution.
3. 2. The injection management method for a permeation solidification treatment method according to claim 1, further comprising the steps of: conducting an on-site permeability test using a hole for installing the water pressure gauge before installing the water pressure gauge; and determining the permeability coefficient of the ground to be improved.
4. An injection management method for a permeation solidification treatment method as described in claim 3, wherein when forming a hole for installing another water pressure gauge adjacent to the hole for installing the water pressure gauge, the position of the hole for installing the other water pressure gauge is determined based on the determined permeability coefficient.
5. The estimated effective injection pressure P and the base pressure P of the pump that injects the liquid pump Therefore, the loss in the pipe (P pump 2. The injection management method for the penetration solidification treatment method according to claim 1, further comprising recording a time-dependent change in the pressure (-P) of the water pressure gauge and estimating an effective injection pressure at the chemical injection port where the water pressure gauge is not installed based on the loss in the pipe.
6. A means for simulating and compiling a database of the relationship between the pore water pressure during injection measured by a water pressure gauge installed within the improvement area away from the chemical injection port of a chemical injection pipe installed in the ground to be improved using the penetration solidification treatment method, and the effective injection pressure of the chemical at the chemical injection port; A means for estimating an effective injection pressure from the pore water pressure measured by the water pressure gauge during injection after the start of injection of the chemical solution into the ground to be improved by referring to the database; and a means for controlling the injection rate of the chemical solution so that the estimated effective injection pressure does not exceed a limit injection pressure.
7. A means for measuring the change in viscosity of the chemical solution over time in the ground to be improved is provided, 7. The injection management system for a penetration solidification treatment method according to claim 6, wherein the effective injection pressure is estimated taking into consideration a change over time in the viscosity of the measured chemical solution.
8. The estimated effective injection pressure P and the base pressure P of the pump that injects the liquid pump Therefore, the loss in the pipe (P pump - a means for recording the change over time of 7. The injection management system for a permeation solidification treatment method according to claim 6, wherein an effective injection pressure at the chemical injection port where the water pressure gauge is not installed is estimated based on the loss in the pipe.
9. A ground improvement method for improving a target ground by a permeation solidification treatment method, using the injection management method for the permeation solidification treatment method according to any one of claims 1 to 5 or the injection management system for the permeation solidification treatment method according to any one of claims 6 to 8.
10. A computer program for causing a computer to function as each of the means in the injection management system for the permeation solidification treatment method according to any one of claims 6 to 8.
Citation Information
Patent Citations
Ground improvement method
JP2017119997A
Construction management method of chemical injection method
JP2017155506A
Ground injection method and injection material
JP2021185301A