Announcing device, announcing system and announcing method

The notification device and system synchronize track closure and power outage notifications, enhancing work efficiency by addressing the oversight in existing systems and ensuring safe, coordinated work procedures.

JP2024145238APending Publication Date: 2024-10-15TAISEI CORP +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
JP2023057509
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Existing railway work notification systems do not account for work performed during temporary power outages alongside track closures, which can hinder efficient work management.

Method used

A notification device and system that includes a first and second reception unit to record and control notifications for track closures and power outages, ensuring synchronized work procedures and efficient communication with workers using visual and auditory mechanisms.

Benefits of technology

Enables effective notification of both track closures and power outages to workers, improving work efficiency by preventing misunderstandings and ensuring safe, uninterrupted work operations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024145238000001_ABST
    Figure 2024145238000001_ABST
Patent Text Reader

Abstract

To provide an announcing device capable of announcing both closed line and power failure to work related persons.SOLUTION: An announcing device 10 includes: a first reception part 11 for receiving work information about work accompanied with a closed line (line closing) and power failure; a first recording part 13 for recording the work information received by the first reception part 11; a second reception part 12 for receiving information about execution of each procedure including the start of line closing, the start of power failure, the release of line closing and the release of the power failure in each work information recorded in the first recording part 13; a second recording part 14 for recording the information recorded by the second reception part 12; a first notification part 15 for controlling a first notification mechanism 61 so as to notify work related persons in receiving the information about the execution of each procedure of the start of line closing and the release of line closing; and a second notification part 16 for controlling a second notification mechanism 62 so as to notify the work related persons in receiving the information about the execution of each procedure of the start of power failure and the release of power failure.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a known device, a known system, and a known method. [Background technology]

[0002] When work is performed near railroad tracks, a track closure is performed to prevent railroad vehicles from traveling on the tracks. When a track closure is performed, the fact that the track closure has occurred is notified to, for example, workers. A technology described in Patent Document 1 is known as an invention related to notifying workers of a track closure. The abstract of Patent Document 1 states that "a track closure release support device that supports the release of a closure after a railroad track is temporarily closed and a worker performs work on the track, the device comprises a main body unit carried by the worker, the main body unit comprising an input unit for inputting the work start time and the work end time from a main body terminal that accepts input of the work start time and the work end time, a storage unit for storing the work start time and the work end time input by the input unit, a notification unit for notifying the start or end of work, and a control unit for causing the notification unit to notify the start or end of work at the work start time and the work end time stored in the storage unit, respectively." [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2010-23574 A Summary of the Invention [Problem to be solved by the invention]

[0004] Patent Document 1 describes how a system can automatically notify workers of the start and end times of work, thereby providing guidance on closing and unlocking tracks (paragraph 0004). However, some work requires the supply of electricity used to run rail vehicles to be temporarily cut off. The technology described in Patent Document 1 does not take such work into consideration. The problem to be solved by the present disclosure is to provide a notification device, a notification system, and a notification method that can notify work-related personnel of both track closures and power outages. [Means for solving the problem]

[0005] The public notification device disclosed herein is a public notification device that notifies workers who are working near a railway track of a track closure and power outage when the railway track is temporarily closed and the supply of electricity used for running railway vehicles is temporarily stopped, and the public notification device includes a first reception unit that receives work information related to the work involving the track closure and the power outage, a first recording unit that records the work information received by the first reception unit, and a notification unit that notifies the start of the track closure, the start of the power outage, the lifting of the track closure, and the end of the power outage for each piece of work information recorded in the first recording unit. The system further comprises a second reception unit that receives information regarding the execution of each procedure including the start of the line closure and the release of the line closure, a second recording unit that records the information received by the second reception unit, a first notification unit that controls a notification device to notify the work-related personnel when information regarding the execution of each procedure of the start of the line closure and the release of the line closure is received from among the information, and a second notification unit that controls the notification device to notify the work-related personnel when information regarding the execution of each procedure of the start of the power outage and the release of the power outage is received from among the information. Other solutions will be described later in the description of the embodiment of the invention. Effect of the Invention

[0006] According to the present disclosure, it is possible to provide a notification device, a notification system, and a notification method capable of notifying work-related personnel of both track closures and power outages. [Brief description of the drawings]

[0007] [Figure 1] FIG. 1 is a block diagram showing a known system and device of the present disclosure. [Diagram 2] FIG. 4 is a diagram showing a specific structure of an alarm mechanism. [Diagram 3] 13A and 13B are diagrams showing a specific structure of an alarm mechanism according to another embodiment. [Figure 4]FIG. 2 is a block diagram showing hardware constituting the control device. [Diagram 5] 1 is a flowchart showing a known method of the present disclosure, which is a flow that is performed in advance before line closure and power outage are initiated. [Figure 6] 1 is a flowchart showing the well-known method of the present disclosure, which is a flow performed when a line closure operation and a power outage operation are started. [Figure 7] This is an image displayed on the display device when line closure begins. [Figure 8] 13 is an image displayed on the display device when a power outage begins. [Figure 9] 1 is a flowchart showing the well-known method of the present disclosure, which is a flow performed when the line closure is released and when the power outage is released. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0008] Hereinafter, a form for carrying out the present disclosure (referred to as an embodiment) will be described with reference to the drawings. In the following description of one embodiment, other embodiments applicable to the one embodiment will also be described as appropriate. The present disclosure is not limited to the following one embodiment, and different embodiments can be combined with each other or modified as desired without significantly impairing the effects of the present disclosure. In addition, the same symbols will be used for the same members, and duplicate descriptions will be omitted. Furthermore, the same names will be used for members having the same functions. The contents shown are merely schematic, and for the sake of illustration, changes may be made from the actual configuration within a range that does not significantly impair the effects of the present disclosure, and some members may be omitted or modified between drawings. In addition, the same embodiment does not necessarily need to have all the configurations.

[0009] FIG. 1 is a block diagram showing a notification system 100 and a notification device 10 of the present disclosure. The notification system 100 notifies workers who are performing predetermined work of track closures and power outages. The predetermined work is work performed in the vicinity of railway tracks, and is performed when the railway tracks are temporarily closed and the supply of power used for running railway vehicles is temporarily stopped. Work performed on railway tracks is also included in work performed in the vicinity of railway tracks. The work includes construction, inspection, and the like. In addition, the power used for running railway vehicles includes, for example, power supplied to vehicles through overhead lines, power supplied to vehicles through a third rail, and the like. The power used for running railway vehicles may further include power supplied to equipment used for running railway vehicles (i.e. equipment other than vehicles, such as signal equipment, etc.) as appropriate.

[0010] Track closure (line closure) is a state in which railway vehicles are prevented from entering at least the work section (work site such as on the tracks or near the tracks). Track closure can be executed, for example, by a line closure initiation procedure by a line closure manager who performs the track closure. That is, it can be executed by the line closure manager, for example, but not limited to this example, by performing a predetermined line closure operation in a vehicle operation system. This prevents railway vehicles from entering the work section. The line closure initiation procedure is executed as part of the line closure initiation.

[0011] On the other hand, the release of the track closure (track closure release) can be executed, for example, by a track closure release procedure by the track closure manager. That is, it can be executed, for example, but not limited to, by the track closure manager performing a predetermined track closure release operation in the vehicle operation system. This allows rail vehicles to enter the work section. The track closure release procedure is executed as part of the track closure release.

[0012] A power outage is a state in which the supply of power to at least the work section is temporarily stopped. The initiation of a power outage (power outage initiation) can be carried out, for example, by a power outage initiation procedure by a power outage manager who carries out procedures to confirm the power outage. That is, a power outage state is created in the work section when the power outage manager carries out a power outage initiation procedure, such as, but not limited to, contacting the power command center to confirm the power cut-off state. This allows those involved in the work to work freely in the work section. The power outage initiation procedure is carried out as part of the initiation of a power outage.

[0013] On the other hand, the power outage can be lifted (power outage release), for example, by a power outage release procedure by the person in charge of the power outage. That is, the power outage state in the work section is lifted when the person in charge of the power outage carries out a power outage release procedure, such as, but not limited to, contacting the power control center to inform them that the work section is in a state where power can be restored. This resumes the supply of power used for running railway vehicles in the work section. The power outage release procedure is executed as part of the power outage release. Note that, although details will be described later, in the example of the present disclosure, the start of the power outage is executed for the work section after the start of line closure work has been completed (the work section where the track is closed). Therefore, the start of the power outage is executed after the start of line closure work has been completed.

[0014] The notification system 100 includes a notification device 10 and an alarm mechanism 60. The notification device 10 notifies the work-related personnel who are performing the above-mentioned predetermined work of track closures and power outages. The "work-related personnel" includes workers who actually work at a work site including a work section, but may also include, for example, a work manager who instructs the workers to work in the work section. Furthermore, the "work-related personnel" may also include a work manager who instructs the workers to work in a place other than the work section (for example, a work site outside the work section). The alarm mechanism 60 notifies the work-related personnel based on an alarm command from the notification device 10.

[0015] The well-known device 10 includes an input device 1, a display device 2, a control device 20, and a camera 21. The well-known device 10 is, for example, a mobile communication terminal (such as a mobile phone, a smartphone, a tablet, or a portable personal computer).

[0016] The input device 1 inputs various instructions to the control device 20. The input device 1 can be configured with, for example, a keyboard, a mouse, a touch panel, etc., all of which are not shown. The display device 2 displays, for example, information recorded in the first recording unit 13 and the second recording unit 14, information input via the input device 1, etc. The display device 2 can be configured with, for example, a liquid crystal display, an organic EL display, a monitor, etc., all of which are not shown. The display device 2 may be a display with a touch sensor that is configured integrally with the input device 1. The camera 21 captures information to be input to the control device 20. Although details will be described later, an image captured by shooting using the camera 21 is input to the control device 20.

[0017] At least one of the input device 1, the display device 2, and the camera 21 may be configured separately from the control device 20. In the case where they are configured separately, the separately configured device and the control device 20 can be configured to be able to communicate with each other, for example, by a wireless communication function. The wireless communication function can use short-range wireless communication such as Bluetooth (registered trademark) and WiFi. The separately configured device and the control device 20 may communicate with each other by wire.

[0018] The publicizing device 10 includes a first receiving unit 11, a second receiving unit 12, a first recording unit 13, a second recording unit 14, a first notification unit 15, and a second notification unit 16.

[0019] The first reception unit 11 receives work information related to the above-mentioned predetermined work involving track closure and power outage. The work information includes the name of the work site where the above-mentioned predetermined work is performed, the name of the construction work where the above-mentioned predetermined work is performed, the line subject to the track closure and power outage (e.g., Yamanote Line, Saikyo Line, etc.), and the type of line subject to the track closure and power outage (outer loop, inner loop, up, down, etc.). In addition, the work information may include, for example, the work date and work time when the above-mentioned predetermined work is performed.

[0020] The work information is usually input in advance before the predetermined work is performed. The input can be performed, for example, by the input device 1. The work information received by the first reception unit 11 is recorded in the first recording unit 13. For example, when it is decided to perform the predetermined work, the setter can input the contents of the determined predetermined work as work information to the notification device 10. The setter here is a person who sets the notification device 10 by inputting work information to the notification device 10. Then, at the time of the predetermined work, the registrant may select the work information recorded in advance by the setter. The registrant here is a person who operates the notification device 10 at the time of the predetermined work, and is a person who registers the history leading up to the line closure and power outage, as will be described in detail later. The registrant is usually a work manager at a work site including a work section. However, the input may be performed by the registrant when the predetermined work is performed.

[0021] The input may be performed using an arbitrary input device (not shown) to a server (not shown) located at a different location from the well-known device 10. In this case, the work information can be received by connecting the well-known device 10 to the server via a network (not shown), for example.

[0022] The second reception unit 12 receives information on the execution of each procedure including the initiation of line closure (line closure initiation), the initiation of power outage (power outage initiation), the lifting of line closure (line closure lifting), and the lifting of power outage (power outage lifting) for each piece of work information recorded in the first recording unit 13. The information received by the second reception unit 12 is recorded in the second recording unit 14. The information includes, for example, information on procedures (line closure initiation procedure, power outage initiation procedure, line closure lifting procedure, power outage lifting procedure) performed when respectively executing line closure initiation, power outage initiation, line closure lifting, and power outage lifting, and information accompanying the procedures. The accompanying information includes, for example, information that the line closure initiation procedure has been started or completed, a communication history between the line closure manager and the registrant leading up to the initiation of line closure, and the like. The instruction can be executed, for example, by the registrant operating the input device 1.

[0023] The second reception unit 12 is configured not to receive information about the start of the power outage until the start of the track closure has been completed. Once the start of the track closure has been completed, railway vehicles cannot enter the work section. By starting the power outage in this state, work (line closure work) can be performed in the area of ​​the work section that is not affected by the power that is still being supplied, even before the start of the power outage is completed. This improves work efficiency.

[0024] In addition, the second reception unit 12 is configured not to receive information on the start of work to release the track closure until the power outage has been released. By doing so, although trains can run due to the start of power supply, the track closure can be maintained, so that the track closure work can be continued.

[0025] The second reception unit 12 is configured not to complete the start of track closure unless the history up to the start and completion of track closure by the track closure manager who executes the track closure is input. This makes it possible to prevent track closure from being started or not completed due to a mistake by a registered person. Also, by inputting the history to the notification device 10, it is possible to make the track closure manager bear part of the responsibility for the track closure.

[0026] The first notification unit 15 controls the notification mechanism 60 so as to notify those involved in the work when it receives information on the execution of each procedure, namely, starting track closure and releasing track closure, from the information received by the second reception unit 12. The information on execution includes, for example, information on the start and end of the track closure initiation procedure and the track closure release procedure, information indicating instructions on work to be performed prior to the start of the procedure, information indicating work to be performed in association with the procedure after the end of the procedure, and the like.

[0027] In the example of the present disclosure, the notification by the notification mechanism 60 is started when the line closure initiation procedure and the work associated with the line closure initiation procedure are completed. On the other hand, the notification by the notification mechanism 60 is ended when the line closure work (the work performed in the line closure state in the above-mentioned predetermined work) is completed and before the line closure release procedure is started.

[0028] The second notification unit 16 controls the notification mechanism 60 so as to notify those involved in the work when information on the execution of procedures for starting a power outage and lifting the power outage is received from the information received by the second reception unit 12. The information on the execution includes, for example, information on the start and end of the power outage initiation procedure and the power outage lift procedure, information indicating instructions on work to be performed prior to the start of the procedure, information indicating work to be performed in association with the procedure after the end of the procedure, and the like.

[0029] In the example of the present disclosure, the notification by the notification mechanism 60 is started when the power outage initiation procedure and the work associated with the power outage initiation procedure are completed. On the other hand, the notification by the notification mechanism 60 is ended when the power outage work (the work performed in a power outage state in the above-mentioned predetermined work) is completed and before the power outage release procedure is started.

[0030] 2 is a diagram showing a specific structure of the notification mechanism 60. As described above, the notification mechanism 60 notifies the workers based on a notification command from the notifying device 10 (FIG. 1). The notifying device 10 and the notification mechanism 60 can be configured to be able to communicate with each other, for example, by a wireless communication function. The wireless communication function can use short-range wireless communication such as Bluetooth (registered trademark) or WiFi. However, the notifying device 10 and the notification mechanism 60 may communicate with each other by wire, or the notifying device 10 may have the function of the notification mechanism 60.

[0031] The alarm mechanism 60 includes a first alarm mechanism 61 and a second alarm mechanism 62. The first alarm mechanism 61 issues an alarm when triggered by an alarm command from the first alarm unit 15 (FIG. 1). The second alarm mechanism 62 issues an alarm when triggered by an alarm command from the second alarm unit 16 (FIG. 1). The alarm mechanism 60 is installed, for example, in the work section. Therefore, workers in the work section can know whether the track is closed or not and whether there is a power outage through the alarm mechanism 60 also installed in the work section. In addition, if the alarm mechanism 60 is installed, for example, at the entrance to the work section, workers who are entering the work section can know whether the track is closed or not and whether there is a power outage.

[0032] The first alarm mechanism 61 and the second alarm mechanism 62 include, for example, light-emitting devices that emit light of different colors. By configuring the first alarm mechanism 61 and the second alarm mechanism 62 in this way, a worker who sees the alarm mechanism 60 can intuitively visually know whether a track is closed or there is a power outage. The first alarm mechanism 61 is, for example, a blue rotating light, and the second alarm mechanism 62 is, for example, a green rotating light.

[0033] In the example of the present disclosure, the alarm mechanism 60 is a standing signboard in which a first alarm mechanism 61 and a second alarm mechanism 62 are fixed to a support plate 63. However, the alarm mechanism 60 is not limited to a standing signboard as shown in the figure, and the first alarm mechanism 61 and the second alarm mechanism 62 may be placed on the ground or on any structure (for example, a pillar, wall, desk, stand, etc. installed in a work area). In addition, the first alarm mechanism 61 and the second alarm mechanism 62 are preferably installed as a set, but only one of them may be installed.

[0034] The first notification mechanism 61 starts to emit light and rotate when the line closing starts, and stops emitting light and rotating when the line closing ends. Therefore, the workers who visually recognize the first notification mechanism 61 can determine that the line closing work can be performed while the first notification mechanism 61 is emitting light and rotating. On the other hand, the workers can determine that the line closing work cannot be performed while the first notification mechanism 61 is emitting light and stopping rotating. The second notification mechanism 62 also starts to emit light and rotate when the power outage starts, and stops emitting light and rotating when the power outage ends. The workers who visually recognize the second notification mechanism 62 can determine that the power outage work can be performed while the second notification mechanism 62 is emitting light and rotating. On the other hand, the workers can determine that the power outage work cannot be performed while the second notification mechanism 62 is emitting light and stopping rotating.

[0035] Only one notification mechanism 60 may be installed, or two or more may be installed. In particular, when the work area is extensive, it is preferable to install two or more notification mechanisms 60, and it is particularly preferable to place them evenly throughout the entire work area. Furthermore, the notification mechanism 60 may be placed outside the work area in a work site that includes the work area, in addition to the work area. This makes it possible to inform workers who are outside the work area and who are scheduled to work in the work area of ​​the possibility of line closure work and power outage work.

[0036] Furthermore, the alarm mechanism 60 is not limited to the rotating light as described above, but may be, for example, a mobile terminal device (not shown) equipped with a screen capable of displaying a pop-up display, any sound generating device (not shown) capable of generating an alarm sound, etc.

[0037] Fig. 3 is a diagram showing a specific structure of an alarm mechanism 60 according to another embodiment. Fig. 3 shows a first alarm mechanism 61 as an example, but a second alarm mechanism 62 can also have the same structure as that shown in Fig. 3.

[0038] 3, the first notification mechanism 61 has a structure that can be carried by the worker. The term "carrying" here is not limited to the meaning of "holding" in the hand of the worker, but also includes a structure that can be worn by the worker.

[0039] In the illustrated example, the first alarm mechanism 61 is provided in a backpack 64 that can be carried on the shoulder of a worker. Specifically, the first alarm mechanism 61 is provided on the outer surface of the backpack 64 (the surface that is visible to other workers when the worker carries the backpack). In addition, a control device (not shown, including a power source) is disposed inside the backpack 64, for example, which is connected to the first alarm mechanism 61 and controls light emission of the first alarm mechanism 61 and communication with the public notification device 10 (FIG. 1).

[0040] Even if the work section is short, there are cases where the work site outside the work section is extremely large (for example, a large station with track construction within the station premises). In an extremely large work site, a very large number of alarm mechanisms 60 shown in Fig. 2 above need to be installed, and the installation costs tend to be enormous. Therefore, for example, by having the workers carry the first alarm mechanism 61 having the structure shown in Fig. 3 and having the workers patrol the work site, it is possible to both reduce the installation costs of the alarm mechanism 60 and to inform the workers.

[0041] 3, only the first alarm mechanism 61 is provided on the outer surface of the rucksack 64, but both the first alarm mechanism 61 and the second alarm mechanism 62 may be provided on the outer surface of the rucksack 64. Furthermore, the location of the first alarm mechanism 61 on the rucksack 64 is not limited to the example shown in FIG.

[0042] 4 is a block diagram showing hardware constituting the control device 20. The control device 20 is configured to include, for example, a CPU (Central Processing Unit) 1001, a RAM (Random Access Memory) 1002, and a ROM (Read Only Memory) 1003. The control device 20 is realized by a predetermined control program (for example, a well-known method of the present disclosure) stored in the ROM 1003 being expanded in the RAM 1002 and executed by the CPU 1001.

[0043] FIG. 5 is a flow chart showing the notification method of the present disclosure, which is a flow that is performed in advance before the start of a line closure and a power outage. The notification method of the present disclosure is a method for notifying the people involved in the work performing the above-mentioned specified work of a line closure and a power outage. As described above, the flow shown in FIG. 5 can be executed by, for example, a setting person (which may be a registrant) operating the input device 1 of the notification device 10 (FIG. 1) and registering each piece of information in the notification device 10. However, as described above, the flow shown in FIG. 5 may be performed on any server (not shown).

[0044] The publicizing method of the present disclosure includes steps S41 and S42. Step S41 (first reception step) is a step of receiving work information related to work involving line closure and pre-power outage. For example, step S41 can be executed by a setter operating the input device 1 to input the work information to the first reception unit 11. However, the setter may operate the publicizing device 10 (FIG. 1) to connect to an arbitrary server and read out the work information recorded in the server, so that the first reception unit 11 receives the read out work information. The matters described with reference to FIG. 1 above can be applied to the work information. Step S42 (first recording step) is a step of recording the work information received in step S41. Recording is performed in the first recording unit 13.

[0045] Fig. 6 is a flow chart showing the notification method of the present disclosure, which is a flow performed when a line closure operation and a power outage operation are started. The flow shown in Fig. 6 and Fig. 9 described later can be executed by a registrant (usually a work manager as described above) operating the notification device 10 (Fig. 1) and registering each piece of information in the notification device 10. In addition, the work information is pre-recorded in the notification device 10 via the first reception unit 11 in the above steps S41 and 52 (Fig. 5).

[0046] The registrant operates the notification device 10 and selects the name of the work site to be worked on from among the pre-recorded work site names (step S1).The registrant further operates the notification device 10 and selects the name of the construction work to be worked on from among the pre-recorded construction names (step S2).The registrant then operates the notification device 10 and selects the line name and line type to be the work target (subject to line closure and power outage) from among the pre-recorded line names and line types (step S3).

[0047] The registrant operates the notification device 10 to start the line closure procedure (step S4). The process is started by, for example, pressing the "Start line closure procedure" button displayed on the display device 2 (Fig. 1). Note that the line closure procedure has not been executed at the time of pressing the button. Next, the registrant requests (instructs) the line closure manager, who performs the line closure procedure (procedure to start track closure), to close the track. In response to this request, the line closure manager performs the line closure procedure for the work section and closes the work space. When the line closure procedure is completed, a "display corresponding to completion of track closure procedure" is displayed on the display device of a mobile communication terminal (not shown) carried by the line closure manager. After this request, the registrant presses a button (not shown) representing "check the operation of line closure start" displayed on the notification device 10 (step S5).

[0048] FIG. 7 shows an image 101 displayed on the display device 2 (FIG. 1) when starting line closure. The image 101 is displayed on the display device 2 in step S6 (FIG. 6) which is executed following step S5. The image 101 includes an item 102 indicating the line name and line type selected in step S3 (FIG. 6) and the currently operated item "line closure start procedure". The image 101 includes an item 103 including the time when the "confirmation conversation, double check execution" button representing "operation confirmation of line closure start" was pressed in step S5 (FIG. 6). The image 101 includes a photo taking button 104 for taking a photo using the camera 21 (FIG. 1) and a registration space 105 for registering the image obtained by taking the photo. The image 101 includes a button 106 for proceeding to the next screen, a button 107 for returning to the previous screen, and a button 108 for returning to the home screen.

[0049] Returning to FIG. 6, in step S6 executed following step S5, the registrant registers evidence that the line closure manager has started the line closure initiation procedure, which is executed by the registrant's action in step S4 (request to the line closure manager), in registration space 105 (FIG. 7) as a confirmation action associated with the line closure. The evidence registered here indicates the line closure initiation completion action, and is a history leading up to the completion of the initiation of track closure by the line closure manager (line closure initiation procedure). Therefore, in the example of the present disclosure, the evidence here is the above-mentioned "indication corresponding to the completion of the track closure procedure."

[0050] In step S6, specifically, the registrant activates the camera 21 (FIG. 1) by pressing the photographing button 104 (FIG. 7) on the image 101 (FIG. 7). The registrant then photographs the "display corresponding to the completion of the line closure initiation procedure" displayed on the display screen of a mobile communication terminal (not shown) carried by the line closure manager who is with the registrant. However, it may also be possible to select an image including the display photographed in advance by pressing the photographing button 104. The registrant then registers the image obtained by photographing in the public notification device 10 by uploading it to the registration space 105 (FIG. 7). Registration is performed through the second reception unit 12, and the registered image is recorded in the second recording unit 14.

[0051] The registration completes a series of operations for starting line closure. In the example of the present disclosure, the registration is used as a trigger for the second reception unit 12 to instruct the first notification unit 15 to complete the start of line closure. As a result, the first notification unit 15 transmits an instruction command for completing the start of line closure via the first notification mechanism 61, and notification by the first notification mechanism 61 is started (step S7).

[0052] The registration in step S6 is not limited to an image including a "display corresponding to the completion of the start of line closure." For example, an image captured by the camera 21 of a conversation between the registrant and the line closure manager regarding a line closure instruction, audio data of a conversation between the registrant and the line closure manager regarding a line closure instruction, or a copy of an email, short message, or the like that describes an exchange between the registrant and the line closure manager regarding a line closure instruction may be registered.

[0053] As described above, the notification device 10 does not accept an instruction to start a power outage until the start of line closure is completed. Therefore, after the start of line closure, which is executed in steps S1 to S6, is completed, steps S8 and thereafter regarding the start of a power outage are executed.

[0054] The registrant selects the line name and line type in the same manner as in step S3 above (step S8). The registrant operates the notification device 10 to start the power outage procedure (step S9). The start is performed, for example, by pressing the "Start power outage procedure" button displayed on the display device 2 (Fig. 1). Note that the power outage procedure has not been executed at the time the button is pressed.

[0055] Next, the registrant requests (instructs) the power outage manager who will be carrying out the power outage to carry out a power outage. In response to this request, the power outage manager carries out the power outage initiation procedure for the work section and checks the power outage status in the work section. After the power outage, the power outage manager completes the power outage initiation procedure by, for example, installing a voltage tester and earthing device at the work site. Meanwhile, after this request, the registrant presses a button (not shown) that indicates "Confirm operation to start power outage" displayed on the notification device 10 (step S10).

[0056] FIG. 8 is an image 110 displayed on the display device 2 (FIG. 1) when a power outage is started. The image 110 is displayed on the display device 2 in step S11 (FIG. 6) executed following step S10. The image 110 includes an item 112 indicating the line name and line type selected in step S8 (FIG. 6) and the currently operated item "procedure for starting a power outage". The image 110 includes an item 113 including the time when the "Installation of the earthing tester completed" button was pressed in step S10 (FIG. 6), which indicates "operation check for starting a power outage". The image 110 includes a photo taking button 114 for taking a photo using the camera 21 (FIG. 1) and a registration space 115 for registering the image obtained by taking the photo. The image 110 includes buttons 106, 107, and 108, similar to the image 101 (FIG. 7) described above.

[0057] Returning to FIG. 6, in step S11, which is executed following step S10, the registrant registers evidence that the power outage initiation procedure by the power outage manager, which is executed by the registrant's action in step S9 (request to the power outage manager), in the registration space 111 (FIG. 8) as a confirmation action associated with the power outage. The evidence registered here indicates the power outage initiation completion action, and is a history leading up to the initiation of the power outage (power outage initiation procedure) by the power outage manager. In the example of the present disclosure, therefore, the evidence here is an image taken at the work site of the above-mentioned earthing tester being installed at the work site.

[0058] In step S11, specifically, the registrant activates the camera 21 (FIG. 1) by pressing the photographing button 114 (FIG. 8) on the image 110 (FIG. 8). The registrant then photographs the installation of the earthing tester installed by the power outage manager. However, it may also be possible to select an image that includes the relevant display that has been previously photographed by pressing the photographing button 104. The registrant then registers the image obtained by photographing in the public notification device 10 by uploading it to the registration space 115 (FIG. 8). Registration is performed through the second reception unit 12, and the registered image is recorded in the second recording unit 14.

[0059] The registration completes the series of power outage initiation steps. In the example of the present disclosure, at this point, the second reception unit 12 instructs the second notification unit 16 to complete the power outage initiation steps. As a result, the second notification unit 16 transmits an instruction command to complete the power outage initiation steps via the second notification mechanism 62, and notification by the second notification mechanism 62 begins (step S12).

[0060] The registration in step S11 is not limited to an image including "the state of installation of the voltage tester grounding device." For example, an image captured by the camera 21 of the state of the conversation between the registrant and the power outage manager regarding the power outage instruction, audio data of the conversation between the registrant and the power outage manager regarding the power outage instruction, or a copy of an email, short message, or the like that describes the exchange between the registrant and the power outage manager regarding the power outage instruction may be registered.

[0061] In this way, both the line closing start and the power outage start are completed. When there are two or more line names and line classifications, the above steps S1 to S12 may be repeated according to the line name and line classification.

[0062] Steps S1 to S6 and S8 to S11 are steps (second reception steps) for receiving information on the execution of each procedure, including the start of track closure, the start of power outage, the lifting of track closure, and the lifting of power outage, for each piece of work information recorded in step S42. Also, in steps S1 to S6 and S8 to S11, the input information (including button presses) is recorded in the second recording unit 14 each time information is input to the second reception unit 12. Therefore, steps S1 to S6 and S8 to S11 are also steps (second recording steps) for recording the information received in steps S1 to S6 and S8 to S11.

[0063] Step S7 (first notification step) is a step of controlling the notification mechanism 60 to notify those involved in the work when information on the execution of the procedures of starting the track closure and lifting the track closure is received from the information received by the second reception unit 12. Step S12 (second notification step) is a step of controlling the notification mechanism 60 to notify those involved in the work when information on the execution of the procedures of starting a power outage and lifting the power outage is received from the above information.

[0064] Fig. 9 is a flow chart showing the well-known method of the present disclosure, and is the flow performed when the line closure is released and the power outage is released. After the line closure and power outage are started according to the flow shown in Fig. 6, the above-mentioned predetermined work is performed. Then, after the above-mentioned predetermined work is completed, the flow shown in Fig. 9 is executed. Execution of the flow shown in Fig. 9 allows the vehicle to travel through the work section again.

[0065] The registrant selects the line name and line type in the same manner as in step S3 above (step S21). Next, the registrant operates the notification device 10 to start power outage recovery (step S22). The process is started, for example, by pressing the "Start power outage recovery" button displayed on the display device 2 (FIG. 1). Note that the power outage recovery procedure has not been executed at the time the button is pressed.

[0066] Next, the registrant requests (instructs) the person in charge of the power outage, who will carry out the power outage removal procedure, to remove the power outage. In response to this request, the person in charge of the power outage carries out the power outage removal procedure for the work section and removes the power outage in the work section. This resumes the power supply in the work section. After the power supply is resumed, the person in charge of the power outage completes the power outage removal procedure by, for example, releasing (removing) a voltage tester earthing device at the work site. Meanwhile, after making this request, the registrant presses a button (not shown) that indicates "Confirm operation of starting line closure" displayed on the notification device 10 (step S23).

[0067] In the example of the present disclosure, the pressing operation is used as a trigger for the second reception unit 12 to instruct the second notification unit 16 that the power outage has been released (the start of power outage release has been completed). As a result, the second notification unit 16 transmits an instruction command for the power outage release completion via the second notification mechanism 62, and the notification by the second notification mechanism 62 ends (step S24).

[0068] Meanwhile, by pressing in step S23, an image (not shown) similar to image 110 (FIG. 8) displayed in step S11 above is displayed on the display device 2. Then, on the display device 2, the registrant uses the camera 21 to capture an image of the installation and opening (removal) of the voltage detector earthing device, and registers the obtained image in a registration space (not shown). The registered image is evidence showing the completion of the power outage release action by the power outage person in charge, and is a history up to the start and completion of the power outage release (power outage release procedure) by the power outage person in charge. Therefore, in the example of the present disclosure, the evidence here is an image showing the installation and opening (removal) of the voltage detector earthing device.

[0069] In this case, the image to be registered is not limited to an image including "the state of opening the installation of the voltage tester earthing device." For example, an image captured by the camera 21 of the state of the conversation between the registrant and the power outage manager instructing to release the power outage, audio data of the conversation between the registrant and the power outage manager instructing to release the power outage, or a copy of an email, short message, or the like that describes the exchange between the registrant and the power outage manager instructing to release the power outage may be registered.

[0070] This completes the series of power outage release steps. The notification device 10 does not accept an instruction to start the line close release step until the power outage is released. Therefore, after the power outage is released in steps S21 to S25, steps S26 and onwards related to the line close release step are executed.

[0071] The registrant selects the line name and line type in the same manner as in step S21 above (step S26). Next, the registrant operates the notification device 10 to start the line closure release (step S27). The process is started, for example, by pressing a "Start line closure release" button displayed on the display device 2 (Fig. 1). Note that the line closure release procedure has not been executed at the time the button is pressed.

[0072] In the example of the present disclosure, the pressing operation is used as a trigger to cause the second reception unit 12 to instruct the first notification unit 15 that the line closure release has been completed (the start of the line closure release has been completed). As a result, the first notification unit 15 transmits an instruction command for the completion of the line closure release via the first notification mechanism 61, and the notification by the first notification mechanism 61 ends (step S28).

[0073] On the other hand, after step S27, the registrant requests (instructs) the line closure manager who performs the line closure release procedure to release the line closure. In response to this request, the line closure manager performs the line closure release procedure for the work section and releases the track closure in the work space. When the line closure release procedure is completed, a "display corresponding to completion of line closure release procedure" is displayed on the display device of a mobile communication terminal (not shown) carried by the line closure manager. On the other hand, after this request, the registrant presses a button (not shown) indicating "confirmation of line closure release operation" displayed on the notification device 10 (step S29).

[0074] Pressing in step S29 causes an image (not shown) similar to image 101 (FIG. 7) displayed in step S6 above to be displayed on display device 2. Then, on display device 2, the registrant uses camera 21 to photograph the "display corresponding to completion of line closure release procedure" and registers the obtained image in a registration space (not shown) (step S30). The registered image is evidence showing the line closure release completion action by the line closure manager, and is a history leading up to the completion of the line closure release procedure by the line closure manager. Therefore, in the example of the present disclosure, the evidence here is the photographed image of the "display corresponding to completion of line closure release procedure".

[0075] In this case, the image to be registered is not limited to an image including "an indication corresponding to the completion of the line closure release procedure." For example, an image captured by the camera 21 of a conversation between the registrant and the line closure manager regarding the line closure release instruction, audio data of the conversation between the registrant and the line closure manager regarding the line closure release instruction, or a copy of an email, short message, or the like that describes the exchange between the registrant and the line closure manager regarding the line closure release instruction may be registered.

[0076] In this way, both the line closed state release and the power outage release are completed. When there are two or more line names and line classifications, the above steps S21 to S30 may be repeated according to the line name and line classification.

[0077] Steps S21 to S23, S25 to S27, S29, and S30 are steps (second reception steps) for receiving information on the execution of each procedure, including the start of track closure, the start of power outage, the lifting of track closure, and the lifting of power outage, for each piece of work information recorded in step S42. Also, in steps S21 to S23, S25 to S27, S29, and S30, the input information (including button presses) is recorded in the second recording unit 14 each time information is input to the second reception unit 12. Therefore, steps S21 to S23, S25 to S27, S29, and S30 are also steps (second recording steps) for recording the information received in steps S21 to S23, S25 to S27, S29, and S30.

[0078] Moreover, step S28 (first notification step) is a step of controlling the notification mechanism 60 to notify those involved in the work when information on the execution of the procedures of starting the track closure and lifting the track closure is received from the information received by the second reception unit 12. Step S24 (second notification step) is a step of controlling the notification mechanism 60 to notify those involved in the work when information on the execution of the procedures of starting a power outage and lifting the power outage is received from the above information.

[0079] According to the notification device 10, notification system 100, and notification method of the present disclosure, the start and end of work regarding track closure and power outage can be notified to those involved in the work. This improves workability and allows work to be done more efficiently because not only track closure but also power outages are notified. [Explanation of symbols]

[0080] 1 Input Device 10 Awareness device 100 Public Information System 11 First Reception Section 12 Second Reception Section 13 First Recording Section 14 Second Recording Section 15 First Notification Division 16 Second Notification Department 2 Display device 20 Control device 21 Camera 60 Notification Mechanism 61 First alarm mechanism 62 Second Notification Mechanism

Claims

1. A notification device that notifies workers who are working near a railway track of a temporary closure of the railway track and a power outage when the supply of power used for running railway vehicles is temporarily stopped, comprising: A first reception unit that receives work information related to the work involving the line closure and the power outage; a first recording unit that records the work information received by the first receiving unit; A second reception unit that receives information regarding the execution of each procedure, including the initiation of the line closure, the initiation of the power outage, the lifting of the line closure, and the lifting of the power outage, for each piece of work information recorded in the first recording unit; a second recording unit that records the information accepted by the second accepting unit; a first notification unit that controls a notification device to notify the person involved in the work when information related to the execution of each procedure of starting the track closure and lifting the track closure is received from among the information; A second notification unit that controls a notification device to notify the work-related persons when information regarding the execution of procedures for starting the power outage and canceling the power outage is received from among the information; Equipped The known device is characterized by:

2. The second reception unit is configured not to receive information regarding the start of the power outage until the start of the line closure is completed.

2. The known device according to claim 1 .

3. The second reception unit is configured not to complete the start of the track closure unless a history of the start of the track closure by a track closure manager who executes the track closure is input.

2. The known device according to claim 1 .

4. A notification system for notifying workers who are working near a railway track of a temporary closure of the railway track and a power outage when the supply of power used for running railway vehicles is temporarily stopped, comprising: a notification device and a notification mechanism for notifying the person involved in the work based on a notification command from the notification device, The known device comprises: A first reception unit that receives work information related to the work involving the line closure and the power outage; a first recording unit that records the work information received by the first receiving unit; A second reception unit that receives information regarding the execution of each procedure, including the initiation of the line closure, the initiation of the power outage, the lifting of the line closure, and the lifting of the power outage, for each piece of work information recorded in the first recording unit; a second recording unit that records the information accepted by the second accepting unit; a first notification unit that controls a notification device to notify the person involved in the work when information related to the execution of each procedure of starting the track closure and lifting the track closure is received from among the information; A second notification unit that controls a notification device to notify the work-related persons when information regarding the execution of procedures for starting the power outage and canceling the power outage is received from among the information; Equipped with The notification device includes: a first notification mechanism that performs notification using a notification command from the first notification unit as a trigger; a second notification mechanism that issues a notification using a notification command from the second notification unit as a trigger; Equipped The known system is characterized by:

5. The first and second notification mechanisms include light-emitting devices that emit light of different colors.

5. The known system according to claim 4.

6. A method for notifying workers who are working near a railway track of a temporary closure of the railway track and a power outage when the supply of power used for running railway vehicles is temporarily stopped, comprising the steps of: A first reception step of receiving work information related to the line closure and the work involving the power outage; a first recording step of recording the work information received in the first receiving step; A second reception step of receiving information regarding the execution of each procedure including the initiation of the line closure, the initiation of the power outage, the lifting of the line closure, and the lifting of the power outage for each piece of work information recorded in the first recording step; a second recording step of recording the information received in the second receiving step; a first notification step of controlling a notification device to notify the person involved in the work when information related to the execution of each procedure of starting the track closure and lifting the track closure is received from among the information; A second notification step of controlling a notification device to notify the work-related persons when information regarding the execution of procedures for starting the power outage and canceling the power outage is received from among the information; Includes The well-known method is characterized by:

Citation Information

Patent Citations

  • Work management system for railway facility

    JP2002032101A

  • Railroad maintaining operation support system

    JP2002132881A

  • Railroad maintaining operation support server and system

    JP2005029055A

  • Apparatus mislaying prevention method and system

    JP2006172368A

  • Signal switching construction work management support system

    JP2009015608A