The reverse beam structure with underfloor spaces and preliminary sleeve holes addresses the challenge of rearranging piping and wiring in apartment complexes, ensuring maintainability and compliance with 100-year lifespan standards.
Patent Information
- Application Number
- JP2023063328
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-10
- Publication Date
- 2024-10-23
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Conventional techniques fail to adequately address the rearrangement of piping and wiring due to future floor plan changes and maintainability of piping and wiring in apartment complexes aiming for a lifespan of 100 years.
A floor structure with a reverse beam system where beams protrude upward, supporting large bridges, and underfloor spaces are utilized for wiring and piping, with preliminary sleeve holes installed to facilitate future rearrangement and maintenance, adhering to specific installation criteria.
Enables flexible and maintainable rearrangement of piping and wiring in apartment complexes, ensuring maintainability and compliance with standards for a 100-year lifespan without causing issues like water leakage or poor drainage.
Smart Images

Figure 2024150089000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to apartment buildings. [Background technology]
[0002] The Ministry of Land, Infrastructure, Transport and Tourism of Japan recommends the skeleton infill method. There is a demand for the realization of collective housing that will have a lifespan of 100 years or more (hereinafter referred to as "100-year housing") by combining this skeleton infill method with an inverted beam underfloor structure (see, for example, Patent Document 1). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Patent No. 2990425 Summary of the Invention [Problem to be solved by the invention]
[0004] To make a house last 100 years, it is necessary to take into consideration future changes to the layout of pipes and wiring, as well as the maintainability of the pipes and wiring. However, conventional techniques including that of Patent Document 1 are unable to fully meet such demands.
[0005] The present invention has been made in consideration of these circumstances, and aims to provide an apartment building that takes into consideration the rearrangement of piping and wiring in response to future changes in the floor plan, etc., and the maintainability of the piping and wiring. [Means for solving the problem]
[0006] In order to achieve the above object, an apartment building according to one aspect of the present invention comprises: In an apartment building having a floor structure with a frame of an inverted beam structure in which an inverted beam is protruding upward from a slab, a plurality of joists are supported between the opposing inverted beams, and flooring materials are laid on the joists to form one or more underfloor spaces surrounded by the plurality of inverted beams, In each resident's private area, Wiring and piping used by the occupant are arranged in the underfloor space, At least a portion of the plurality of reverse beams is provided with a spare sleeve hole for passing the wiring and / or the piping to be disposed in the underfloor space when any future floor plan change is made; The underfloor space has a height necessary for workers to perform work on the wiring and / or the piping. Effect of the Invention
[0007] According to the present invention, it is possible to provide an apartment building that takes into consideration the rearrangement of piping and wiring in response to future changes in the floor plan, etc., and the maintainability of the piping and wiring. [Brief description of the drawings]
[0008] [Figure 1] This is a partially cutaway plan view of an apartment building that uses a reverse beam large sliding floor structure. [Diagram 2] FIG. 2 is a cross-sectional view taken along line 2-2 in FIG. [Diagram 3] FIG. 2 is a cross-sectional view showing the state of an underfloor space in the apartment building of FIG. 1. [Figure 4] 4 is a diagram for explaining installation standards for spare sleeve holes provided in a reverse beam that protrudes into the underfloor space in FIG. 3. FIG. [Diagram 5] 5 is a diagram for explaining a first reference and a second reference among installation references of the spare sleeve hole in FIG. 4. FIG. [Figure 6] 5 is a diagram for explaining a third reference among the installation references of the spare sleeve hole in FIG. 4. FIG. [Figure 7] 5 is a diagram for explaining a third reference among the installation references of the spare sleeve hole in FIG. 4. FIG. [Figure 8]5 is a diagram for explaining a fourth reference among the installation references of the spare sleeve hole in FIG. 4. FIG. [Figure 9] 9 is a diagram showing an example in which a plurality of spare sleeve holes are combined and installed based on the first to fourth criteria shown in FIGS. 4 to 8. FIG. [Figure 10] FIG. 11 is a perspective view showing an example in which a spare sleeve hole is provided in an underfloor space. [Figure 11] FIG. 11 is a plan view showing an example of a floor plan before modification in an apartment building according to an embodiment. [Figure 12] FIG. 2 is a plan view showing an example of an under-floor structure before modification in an apartment building according to an embodiment. [Figure 13] FIG. 11 is a plan view showing an example of a changed floor plan in an apartment building according to an embodiment. [Figure 14] 13 is a plan view showing an example of a modified under-floor structure in an apartment building according to an embodiment. FIG. [Figure 15] 1 is a perspective view showing an example of underfloor wiring and piping before and after modification in an apartment building according to an embodiment. FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. First, with reference to Figs. 1 to 3, an embodiment of an underfloor structure of the present invention to which a reverse beam sliding floor structure is applied will be described. Fig. 1 is a partially cutaway plan view of an apartment house to which a reverse beam large sliding floor structure is applied. Fig. 2 is a cross-sectional view taken along line 2-2 in Fig. 1. Fig. 3 is a cross-sectional view showing the state of the underfloor space in the apartment house in Fig. 1.
[0010] In Figures 1 to 3, the concrete structure F with an inverted beam structure forms the skeleton of the apartment building, and comprises horizontal structure parts Fh that extend horizontally and divide the building into multiple floors, and vertical structure parts Fv that extend vertically and connect the upper and lower horizontal structure parts Fh to each other.
[0011] On each floor separated by the horizontal structural portion Fh, multiple residential spaces H are arranged side by side, and each residential space H is separated by structural columns 1 erected at each of the four corners and connecting the upper and lower floor slabs Sf, as well as structural exterior walls 2 and structural partition walls 3 (load-bearing walls 3) that connect opposing structural columns 1 together.
[0012] Vertical and horizontal inverted girders 5L, 5T that divide the underfloor space Hd of each residential space H are integrally protruded upward from the floor slab Sf constituting the horizontal structural portion Fh. The lower ends of the structural partition walls 3 and the structural exterior walls 2 are integrally connected to these vertical and horizontal inverted girders 5L, 5T. The vertical and horizontal inverted girders 5L, 5T are also integrally connected to the structural columns 1 located at the four corners of the residential space H. A passage 7 is constructed on the outside of one of the structural exterior walls 2 (left side in Fig. 1) of the multiple residential spaces H arranged in parallel, and a veranda 8 is constructed on the outside of the other structural exterior wall 2 (right side in Fig. 1).
[0013] In each residential space H, vertical and horizontal inverted small beams 6L, 6T, which are lower than the inverted main beams 5L, 5T, are integrally provided upward on the floor slab Sf. These vertical and horizontal inverted small beams 6L, 6T cross each other, and their ends are integrally connected to the middle parts of the horizontal and vertical inverted main beams 5T, 5L, respectively.
[0014] Each residential space H is formed into a rectangular shape in plan view, and in the direction perpendicular to its longitudinal direction, i.e., the width direction of the residential space H, a number of beams 10 are supported between the relatively short spans of the vertical inverted main beams 5L and the vertical inverted small beams 6L. The beam 10 is one of the components that make up a double floor, and is called a Σ beam, for example, when it is made by bending a rust-resistant galvanized steel plate into a Σ-shaped cross section. A step-like extension portion, i.e., a floor support portion 14, at approximately the same level as the inverted sub-beams 6L, 6T is integrally formed on the side of the vertical inverted main beam 5L (integrally formed at the same time as the vertical inverted main beam 5L is formed using the formwork). Between the floor support portion 14 and the upper surface of the vertical inverted small beam 6L, the ends of a plurality of joists 10 are supported in a floating manner via adjustable underfloor support fittings FS.
[0015] A floor structure Fr is supported between the vertical and horizontal inverted main beams 5L, 5T and the vertical and horizontal inverted small beams 6L, 6T of each residential space H.
[0016] As shown in Fig. 3, the floor structure Fr shown in Fig. 2 is integrally formed of a plurality of joists 10, a plurality of joists 11 supported perpendicularly on the joists 10, and floorboards 12 made of wood-based flooring boards or the like laid on the joists 11. The floorboards 12 are formed by integrally laminating a finishing material on a base material. The joists 11 are wooden joists and steel joists. In the case of steel joists, it is preferable to interpose a shock-absorbing material (sound-proofing and vibration-proofing material) such as a rubber member between the joists and the beams 10. This floor structural body Fr divides the residential space H into an under-floor space Hd (storage space Hd) and an above-floor space Hu (living space Hu). The underfloor space Hd has a height H necessary for a worker to work on the wiring or piping. The height H of the underfloor space Hd is preferably set to, for example, 430 mm or more so that a worker can enter the underfloor space Hd to work.
[0017] Here, with reference to FIG. 4, a description will be given of installation standards for spare sleeve holes provided in the inverted beams that protrude into the underfloor space. FIG. 4 is a diagram for explaining installation standards for spare sleeve holes provided in the inverted beam protruding into the underfloor space in FIG.
[0018] As shown in Figures 1 to 3, the apartment building of this embodiment has a floor structure with a concrete frame F of an inverted beam structure, in which inverted beams (inverted main beams 5L, 5T, inverted small beams 6L, 6T, etc.) protrude upward from the floor slab Sf. In this floor structure, multiple joists 10 are supported between opposing inverted beams (between inverted main beams 5L, between inverted main beams 5T, between inverted main beams 5L and inverted sub beams 6L, between inverted main beams 5T and inverted sub beams 6T, etc.), and by laying floor panels 12 on these joists 10, one or more underfloor spaces Hd surrounded by multiple inverted beams are formed. The underfloor space Hd is provided in each of the occupants' private areas, and wiring and piping used by the occupants are arranged therein. At least some of the inverted beams such as the inverted main beams 5L, 5T and the inverted small beams 6L, 6T are provided with spare sleeve holes 101, 102 (see FIG. 10) for passing (penetrating) wiring and / or piping to be arranged in the underfloor space Hd when any future changes are made to the floor plan.
[0019] The spare sleeve holes 101 and 102 are not necessarily provided anywhere on the inverted beam, but are installed so as to satisfy installation criteria including the first criterion to the fourth criterion shown in FIG.
[0020] Hereinafter, the installation criteria including the first to fourth criteria will be described with reference to FIG. 4 to FIG. FIG. 4 is a diagram for explaining the installation reference of the spare sleeve hole provided in the reverse beam protruding into the underfloor space in FIG. 3. FIG. 5 is a diagram for explaining the first and second references among the installation references of the spare sleeve hole in FIG. 4. FIG. 6 is a diagram for explaining the third reference among the installation references of the spare sleeve hole in FIG. 4. FIG. 7 is a diagram for explaining the third reference among the installation references of the spare sleeve hole in FIG. 4. FIG. 8 is a diagram for explaining the fourth reference among the installation references of the spare sleeve hole in FIG. 4. FIG. 9 is a diagram showing an example in which a plurality of spare sleeve holes are combined and installed based on the first reference to the fourth reference shown in FIG. 4 to FIG. 8. FIG. 10 is a perspective view showing an example in which a spare sleeve hole is installed in the underfloor space.
[0021] 4 and 5, the first standard is that the through diameter (hole diameter) K of the spare sleeve holes 101, 102 is equal to or less than 1 / 3 of the beam depth D. Note that the beam depth refers to the height from the lower surface to the upper surface of the beam. The second standard, as shown in Figures 4 and 5, is that the positions of the spare sleeve holes 101, 102 in the vertical direction shall be near the center of the beam depth D, and no other spare sleeve holes shall be installed within 1 / 3 of the distance from the bottom ends of the spare sleeve holes 101, 102 to the bottom end of the beam. In other words, D / 3 of the beam surface shall be left below the spare sleeve hole 101. It is preferable that the upper and lower edge spaces are 175 mm to 250 mm or more from the surface of the inverted small beam 6T (inverted beam) to the spare sleeve holes 101 and 102. However, this regulation of the upper and lower edge spaces varies depending on the beam depth and hole diameter.
[0022] The third criterion is that the distance from the column surface to the hole center of the spare sleeve holes 101, 102 is at least twice the beam depth (2D), as shown in Figs. As shown in FIG. 7, it is preferable not to install the sash at a position that is 1 / 4 on either side of the span So, which indicates the length of the beam from the beam end, that is, the entire length of the beam. To sum up the above two conditions, it is desirable to install the spare sleeve holes 101, 102 near the center of the beam (see "Desired range" in Figure 7) and avoid the beam end. The beam end refers to the range within 1 / 10 of the span So, which is the total length of the inverted small beam 6T (inverted beam), from the column face and within twice the beam depth.
[0023] The fourth criterion is that, when there are multiple spare sleeve holes (spare sleeve holes 101, 102) as shown in Figures 4 and 8, the distance between the spare sleeve holes 101, 102 should be at least three times the distance obtained by adding up the hole diameters φ1, φ2 and dividing the sum by 2. If the diameters of the spare sleeve holes 101, 102 are different, the average diameter shall be used. In other words, the distance between the spare sleeve holes 101, 102 shall be at least three times the distance obtained by adding the diameters φ1 and φ2 and dividing the sum by two ((φ1+φ2) / 2×3). Note that Fig. 6 shows the hole distance in a case where the diameter φ of the spare sleeve hole 101 is 200 mm and the diameter φ of the spare sleeve hole 102 is 100 mm as a specific value (200+100 / 2×3=450).
[0024] In addition, the height of the spare sleeve holes 101, 102 from the surface of the floor slab Sf shall be set as follows. In order to ensure that the drain pipe 131 has a sufficient slope, it is assumed that the plumbing equipment (kitchen / unit bath (UB), etc.) will be installed at the position furthest from the piping source, such as the meter box (MB) or pipe space (PS), and a sufficient slope is ensured from that assumed position to the penetration position, and from the penetration position to the MB or PS. For example, if the depth of the beam is 450 mm, according to the fourth criterion above, the distance from the top of the floor slab Sf to the end of the hole must be at least 175 mm, 175 mm x 50 (with a slope of 1 / 50) = 8,750 mm, and the greater this value is compared with the distance from the spare sleeve holes 101, 102 to the MB or PS, the better. In this example, if the finishing top is slab top + 600 mm, then 600 mm - 175 mm x 50 (with a gradient of 1 / 50) = 21,250 mm. This value is compared with the distance from the assumed water supply position to the spare sleeve holes 101 and 102, and if it is larger, then it is good.
[0025] This makes it possible to configure an underfloor piping structure that does not cause problems such as water leaks or poor drainage even after changes to the floor plan. As a result, the underfloor structure of this embodiment can be applied to apartment buildings of average size, and can be more widely used in general newly built apartment buildings.
[0026] Here, an example in which a plurality of spare sleeve holes that meet the above-mentioned first to fourth criteria are combined and installed will be described. When multiple spare sleeve holes that meet the above-mentioned first to fourth criteria are installed in combination, as shown in FIG. 9, the diameter 91 of the spare sleeve hole 103 is 1 / 3 (1 / 3D) of the beam depth. The distance 92 from the column surface (wall surface) to the center of the spare sleeve hole 103 is set to twice the beam depth (2D). The distance 93 between the spare sleeve hole 103 and the spare sleeve hole 101 is set to three times (3K) the hole diameter. A distance 94 from the lower end of the spare sleeve hole 103 to the lower end of the beam is set to 1 / 3D, and if the beam depth is, for example, 600 mm, the distance 94 is set to 175 mm to 250 mm. A distance 94 from the upper end of the spare sleeve hole 101 to the upper end of the beam is set to 1 / 3D, and if the beam depth is, for example, 600 mm, the distance 94 is set to 175 mm to 250 mm. It is preferable that the distance 95 from the beam intersection or the inverted small beam 6L to the spare sleeve hole 102 is 100 mm to 200 mm or more from the hole edge to the beam surface.
[0027] 10 is a perspective view showing a specific example in which, for example, spare sleeve holes 101, 102 are installed in the inverted small beam 6T of the underfloor space Hd. In this example, if the spare sleeve holes 101, 102 are installed so as to comply with the above-mentioned first to fourth criteria, it can be seen that the spare sleeve holes 101, 102 are installed at a position slightly higher than the drain pipe 131 installed in the floor slab Sf.
[0028] Hereinafter, specific examples of changing the floor plan will be described with reference to Figs. Fig. 11 is a floor plan before the 2LDK floor plan was changed to 1LDK (before the floor plan was changed). Fig. 12 is a layout diagram of the underfloor space's back beams and piping before the floor plan was changed in Fig. 11. Fig. 13 is a floor plan after the floor plan was changed to 1LDK (after the floor plan was changed). Fig. 14 is a layout diagram of the underfloor space's back beams and piping after the floor plan was changed in Fig. 13.
[0029] As shown in Fig. 11, before the floor plan was changed, the floor plan was a 2LDK with Western-style rooms 1 and 2, a living room, dining room, and a kitchen. In the underfloor space before the floor plan was changed as shown in Fig. 11, the inverted joists 6T and 6L are arranged in a cross direction as shown in Fig. 12, and the inverted joists 6T only have spare sleeve holes 101 and 102 provided and are not used. In addition, the drain pipes 131 are respectively piped from the kitchen space 121 and the toilet to the piping source on the corridor side (for example, a meter box (MB, etc.) through sleeve holes (not shown) originally provided in the inverted joists 6T and 6L. The gas pipe 132 is also arranged from the MB to the kitchen space 121.
[0030] When the 2LDK floor plan of Fig. 11 is changed to a 1LDK, as shown in Fig. 13, Western-style room 2 is eliminated, the living space is enlarged, and the kitchen is moved to a part of the living space, resulting in a 1LDK floor plan with Western-style room 1, living room, dining room, and kitchen. In the underfloor space after the floor plan change in Fig. 13, as shown in Fig. 14, a drain pipe 131 and a gas pipe 132 (including a water supply pipe 133 and a hot water supply pipe 134 shown in Fig. 15(B)) are extended and piped to the kitchen space 122 in the upper left corner of the rearranged living room through spare sleeve holes 101, 102 that are provided in advance in the inverted beam 6T.
[0031] FIG. 15 is a perspective view showing an example of the layout of pipes and wires before and after the layout change in the above-mentioned floor plan. As shown in Fig. 15(A), before the floor plan was changed, there was no piping or wiring in the floor slab Sf, but after the floor plan was changed, as shown in Fig. 15(B), the drain pipe 131 on the Western-style room 1 side was passed through the floor slab Sf on the living / dining / kitchen side through a spare sleeve hole 101 that had been installed in advance in the inverted beam 6T. In addition, the gas pipe 132, water supply pipe 133, hot water supply pipe 134, etc. on the Western-style room 1 side were passed through the floor slab Sf on the living / dining / kitchen side through a spare sleeve hole 102 that had been installed in advance in the inverted beam 6T. It should be noted that the example of the spare sleeve holes 101, 102 and piping shown here is just one example, and various other piping configurations are possible by providing three or four spare sleeve holes.
[0032] According to this example of floor plan change, when a change in the floor plan occurs in which piping exceeds the reverse beam in the underfloor space, the drain pipe 131, gas pipe 132, etc. can be passed through the reverse beam 6T by utilizing the spare sleeve holes 101, 102 that have been pre-installed in the reverse beam 6T. This makes it possible to flexibly respond to floor plan changes without carrying out large-scale underfloor construction work, by having workers enter the underfloor space and simply rearrange the piping and wiring.
[0033] Although one embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within the scope that can achieve the object of the present invention are considered to be included in the present invention.
[0034] To summarise the above, it is sufficient for an apartment building to which the present invention is applicable to have the following configuration, and various embodiments can be adopted. That is, the apartment building to which the present invention is applied is as follows: In a floor structure having a frame of an inverted beam structure in which inverted beams (e.g., inverted main beams 5L, 5T and inverted small beams 6L, 6T in Figs. 1 and 2) are protruded upward on a slab (e.g., floor slab Sf in Figs. 1 and 2), a plurality of joists (e.g., joists 10 in Figs. 1 and 2) are supported between the opposing inverted beams, and flooring materials (e.g., floor boards 12 in Figs. 1 and 2) are laid on the joists (e.g., joists 10 in Figs. 1 and 2) to form one or more underfloor spaces (e.g., underfloor spaces Hd in Fig. 4) surrounded by a plurality of the inverted beams, In each resident's private area, Wiring and / or piping used by the occupant is arranged in the underfloor space (for example, the underfloor space Hd in FIG. 4 ), At least a portion of the plurality of reverse beams is provided with spare sleeve holes (e.g., spare sleeve holes 101, 102 in FIG. 4) for passing the wiring and / or the piping to be placed in the underfloor space when any future floor plan changes are made; The underfloor space (for example, the underfloor space Hd in FIG. 4) has a height (for example, height H in FIG. 4) necessary for a worker to carry out work on the wiring and / or the piping. With a floor structure configured in this manner, wiring and piping can be arranged in the underfloor space Hd of the exclusive area formed under the floor, spare sleeve holes can be formed in the reverse beams, and the height of the underfloor space can be maintained at a height that allows workers to work there. This makes it possible to realise apartment buildings that take into consideration the rearrangement of piping and wiring due to future changes in the layout, etc., and the maintainability of piping and wiring, and ultimately makes it possible to realise 100-year homes.
[0035] In the above-mentioned apartment complex, The spare sleeve holes (for example, spare sleeve holes 101 and 102 in FIG. 4) are The first criterion is that the through diameter (through diameter K) of the spare sleeve hole is 1 / 3 or less of the beam depth; The second criterion is that the vertical position of the spare sleeve hole shall be near the center of the beam, and no other spare sleeve holes shall be installed within 1 / 3 of the distance from the bottom end of the spare sleeve hole to the bottom end of the beam. The third criterion is that the distance from the column surface to the hole center (center of the hole) of the spare sleeve hole is more than twice the beam depth (preferably within 1 / 10 of the span (So) and more than twice the beam depth). A fourth criterion that, in the case where there are a plurality of spare sleeve holes, the interval between the spare sleeve holes is three times or more the hole diameter (for example, the through diameter K in FIG. 4) (in the case where the hole diameters are different, the average hole diameter); The installation conditions are stipulated in the IEC 61161-1. This means that the house complies with the standard for 11. Beam hole reinforcement in the reinforced concrete structural bar arrangement standard, making it eligible for certification as a 100-year house.
[0036] In the above-mentioned apartment complex, The height of the spare sleeve hole from the top surface of the slab is In order to ensure that the drain pipe has a sufficient gradient, it is assumed that a plumbing fixture (such as a kitchen or a unit bath) will be installed at the farthest position from the piping source (such as a meter box or pipe space), and a sufficient gradient is ensured from this assumed position to the penetration position, and from the penetration position to the piping source. It is set according to the following criteria. This makes it possible to configure an underfloor piping structure that does not cause problems such as water leaks or poor drainage even after changes to the floor plan. As a result, the underfloor structure of the embodiment can be applied to apartment buildings of average size, making it more widely used in general newly built apartment buildings.
[0037] In the above-mentioned apartment complex, The height of the underfloor space is 430 mm or more. This allows workers to easily enter the underfloor space and carry out work such as rearranging pipes and wiring in response to changes in the floor plan, or performing maintenance work. [Explanation of symbols]
[0038] 5L, 5T...inverted main beam, 6L, 6T...inverted small beam, 10...joist, 11...joist, 12...floor board, 101, 102, 103...spare sleeve hole, 121...kitchen space before layout change (old kitchen space), 122...kitchen space after layout change, 131...drain pipe, 132...gas pipe, 133...water supply pipe, 134...hot water pipe, Hd...underfloor space, H...height of underfloor space, Sf...floor slab
Claims
1. In an apartment building having a floor structure with a frame of an inverted beam structure in which an inverted beam is protruded upward from a slab, a plurality of joists are supported between the inverted beams facing each other, and flooring materials are laid on the joists to form one or more underfloor spaces surrounded by the plurality of inverted beams, In each resident's private area, Wiring and / or piping used by the occupant is arranged in the underfloor space, At least a portion of the plurality of reverse beams is provided with a spare sleeve hole for passing the wiring and / or the piping to be placed in the underfloor space when any future floor plan change is made; The underfloor space has a height necessary for a worker to perform work on the wiring and / or the piping. apartment complex.
2. The spare sleeve hole is The first criterion is that the through diameter of the spare sleeve hole is 1 / 3 or less of the beam depth; The second criterion is that the position of the spare sleeve hole in the vertical direction is near the center of the beam, and no other spare sleeve hole is provided within 1 / 3 of the distance from the bottom end of the spare sleeve hole to the bottom end of the beam; The third criterion is that the distance from the column surface to the center of the spare sleeve hole is at least twice the beam depth; A fourth criterion that, when there are a plurality of spare sleeve holes, the interval between the spare sleeve holes is three times or more the hole diameter; The installation conditions are stipulated by The apartment building of claim 1.
3. The height of the spare sleeve hole from the top surface of the slab is In order to ensure that the drain pipe has a sufficient gradient, it is assumed that the plumbing equipment will be installed at the position furthest from the piping source, and a sufficient gradient is ensured from the assumed position to the penetration position, and from the penetration position to the piping source. It is set by the criteria that The apartment building according to claim 1.
4. The height of the underfloor space is 430 mm or more. The apartment building according to claim 1.
Citation Information
Patent Citations
Building structure
JP2000291197A
Air conditioner utilizing underfloor space in reversed beam structure
JP2002206772A
Building floor structure
JP2990425B2