Concrete cooling system, control device for concrete cooling system, control method for concrete cooling system, and control program for concrete cooling system

The concrete cooling system extends cooling periods by using temperature sensors and alternating water supplies to manage temperature gradients, effectively preventing cracks.

JP2024150237APending Publication Date: 2024-10-23NISSAN RINKAI CONSTR
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023063553
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-10
Publication Date
2024-10-23

AI Technical Summary

Technical Problem

Existing concrete cooling systems are limited in cooling period and struggle to extend the cooling time beyond when the internal temperature of concrete approaches the external temperature, making it difficult to adjust and prevent temperature cracks.

Method used

A concrete cooling system that includes temperature sensors to detect internal and external concrete temperatures, alternating supply of first and second water supplies with different temperatures, and a control device to manage the water supply based on detected temperature peaks, allowing for extended cooling periods.

Benefits of technology

The system effectively extends the cooling period of concrete, reducing temperature differences and preventing cracks by dynamically adjusting water supply temperatures and flow rates.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024150237000001_ABST
    Figure 2024150237000001_ABST
Patent Text Reader

Abstract

To provide a concrete cooling system capable of adjusting a period for cooling placed concrete to be longer.SOLUTION: A concrete cooling system 100 has: a water passage that is arranged in at least one of the inside or the periphery of placed concrete; a temperature sensor that detects a concrete temperature which is a temperature of the concrete, and outputs a concrete temperature signal indicating the concrete temperature; a first water supply device that supplies first supply water to the water passage; a second water supply device that supplies second supply water having a higher temperature than the first supply water to the water passage; and a control device where the concrete temperature signal is input and that controls the first water supply device and the second water supply device to supply the first supply water and the second supply water to the water passage. The control device detects a peak value of the concrete temperature when the first supply water is supplied to the concrete, and after detecting the peak value, supplies the second supply water to the water passage so that the concrete temperature is lower than the peak value.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a concrete cooling system, a control device for a concrete cooling system, a control method for a concrete cooling system, and a control program for a concrete cooling system. [Background technology]

[0002] Various techniques are known for preventing thermal cracking caused by heat of hydration that occurs when the cast concrete solidifies, by arranging pipes in advance inside the concrete to be cast and supplying cooling water to the pipes arranged inside the cast concrete. For example, Patent Document 1 describes a technique for stopping the supply of cooling water to the pipes arranged inside the cast concrete after a predetermined time has elapsed since the temperature of the cast concrete reached its maximum temperature. The technique described in Patent Document 1 can prevent thermal cracking caused by a sudden drop in the temperature of the concrete by stopping the supply of cooling water after the temperature of the concrete starts to drop.

[0003] Furthermore, Patent Document 2 describes a technique for setting the path of the piping so that cooling water is supplied from the center of the concrete toward the periphery when cooling water is supplied to piping arranged inside the poured concrete. In the technique described in Patent Document 2, the path of the piping is set so that cooling water is supplied from the center of the concrete toward the periphery, and the heat of hydration in the center is distributed to the periphery, thereby easing the temperature gradient inside the concrete and suppressing the occurrence of thermal cracks.

[0004] Patent Document 3 also describes a technique for supplying hot water to piping arranged in a wall region arranged around a previously cast concrete, while supplying cold water to piping arranged in a wall region arranged around a later cast concrete. In the technique described in Patent Document 3, the concrete cast earlier is cooled and the concrete cast later is heated, thereby suppressing an increase in the internal temperature of the later cast concrete, thereby reducing the internal restraint stress. In addition, in the technique described in Patent Document 3, the temperature difference between the concrete cast earlier and the concrete cast later, i.e., the temperature gradient, is reduced, and the external restraint stress that the later cast concrete receives from the concrete cast earlier is reduced.

[0005] Furthermore, Patent Document 4 describes a technique for lowering the temperature of cooling water supplied to piping inside the concrete when the temperature difference between the inside and outside of the cast concrete increases, and for raising the temperature of the cooling water when the temperature difference between the inside and outside of the concrete decreases. In the technique described in Patent Document 4, the temperature of the cooling water is automatically controlled according to the temperature difference between the outside and inside of the cast concrete, thereby allowing the cast concrete to be cooled under desired conditions and suppressing the occurrence of thermal cracks.

[0006] Furthermore, Patent Document 5 describes a technique in which, after heating the existing concrete to the expected maximum temperature of the new concrete, when the temperature of the new concrete drops after pouring, cooling water that has been supplied to the piping inside the new concrete is supplied to the piping of the existing concrete. The technique described in Patent Document 5 adjusts the temperature of the existing concrete in accordance with the shrinkage of the new concrete, thereby preventing a difference in the amount of shrinkage between the existing concrete and the new concrete, thereby suppressing the occurrence of thermal cracks. [Prior art documents] [Patent documents]

[0007] [Patent Document 1] Patent No. 6473721 [Patent Document 2] Patent No. 4108544 [Patent Document 3] Patent No. 2940367 [Patent Document 4] Patent No. 6546388 [Patent Document 5] Patent No. 6347667 Summary of the Invention [Problem to be solved by the invention]

[0008] On the other hand, by extending the cooling period of the poured concrete, the external restraining force per unit time applied to the poured concrete is reduced, and the occurrence of thermal cracks is suppressed. However, in the techniques described in Patent Documents 1 to 5, the cooling of the poured concrete ends when the temperature inside the concrete approaches the temperature outside, and it is not easy to adjust the cooling period of the poured concrete to be longer.

[0009] The present invention is intended to solve such problems, and has an object to provide a concrete cooling system that can be adjusted to extend the period for cooling poured concrete. [Means for solving the problem]

[0010] The concrete cooling system of the present invention comprises a water passage arranged inside and / or around the poured concrete, a temperature sensor that detects the concrete temperature, which is the temperature of the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature, a first water supply device that supplies a first supply water having a first temperature to the water passage, a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, and a control device that receives the concrete temperature signal and controls the first water supply device and the second water supply device to supply at least one of the first supply water and the second supply water to the water passage, and the control device detects a peak value of the concrete temperature when the first supply water is supplied to the poured concrete, and after detecting the peak value of the concrete temperature, supplies the second supply water to the water passage so that the concrete temperature is lower than the peak value.

[0011] Furthermore, in the concrete cooling system of the present invention, it is preferable that the control device stops the supply of the first supply water after detecting the peak value, and when the second supply water is supplied to the poured concrete, determines whether the concrete temperature has reached a second peak value lower than the peak value, and after determining that the concrete temperature has reached the second peak value, resumes the supply of the first supply water to the water passage and stops the supply of the second supply water.

[0012] Furthermore, in the concrete cooling system of the present invention, it is preferable that the control device determines whether the concrete temperature has reached a third peak value lower than the second peak value when the second supply water is supplied to the poured concrete after the first supply water has been supplied, and after determining that the concrete temperature has reached the third peak value, resumes the supply of the second supply water to the water passage and stops the supply of the first supply water.

[0013] Furthermore, in the concrete cooling system of the present invention, it is preferable that the control device stores temperature profile information indicating temperature changes in the concrete temperature, and supplies mixed water obtained by mixing the first supply water and the second supply water to the water passage so that the concrete temperature corresponding to the concrete temperature signal matches the temperature change corresponding to the temperature profile.

[0014] Furthermore, the concrete cooling system of the present invention further includes a slab temperature sensor for detecting the slab temperature, which is the temperature of the slab supporting the poured concrete, and a slab water supply device for supplying slab supply water having a temperature higher than the first temperature to the surrounding area of ​​the slab, and it is preferable that the control device controls the temperature of the slab supply water so that the temperature difference between the concrete temperature and the slab temperature is not greater than the temperature difference between the concrete temperature and the slab temperature when the peak value of the concrete temperature is detected.

[0015] Furthermore, in the concrete cooling system of the present invention, it is preferable that the water passage is arranged at least one of inside and around the poured concrete, and the base plate water supply device supplies base plate supply water to the periphery of the poured concrete in addition to the base plate.

[0016] Furthermore, the concrete cooling system of the present invention further has a base slab water conduit to which base slab supply water is supplied from the base slab water supply device, and it is preferable that the base slab water conduit is detachable from the base slab and the poured concrete.

[0017] In addition, the control device of the concrete cooling system of the present invention includes a water passage arranged at least inside and around the poured concrete, a temperature sensor that detects the concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature, a first water supply device that supplies a first supply water having a first temperature to the water passage, and a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, and in the concrete cooling system, the control device receives the concrete temperature signal and controls the first water supply device and the second water supply device to supply at least one of the first supply water and the second supply water to the water passage, and detects a peak value of the concrete temperature when the first supply water is supplied to the poured concrete, and after detecting the peak value of the concrete temperature, supplies the second supply water to the water passage so that the concrete temperature is lower than the peak value.

[0018] In addition, a control method for a concrete cooling system according to the present invention is a control method for a concrete cooling system having a water passage arranged at least inside and around the poured concrete, a temperature sensor that detects the concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature, a first water supply device that supplies a first supply water having a first temperature to the water passage, and a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, wherein a peak value of the concrete temperature is detected when the first supply water is supplied to the poured concrete, and after detecting the peak value of the concrete temperature, the second supply water is supplied to the water passage so that the concrete temperature is lower than the peak value.

[0019] In addition, the control program for the concrete cooling system of the present invention is a control program for a concrete cooling system having a water passage arranged at least inside and around the poured concrete, a temperature sensor that detects the concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature, a first water supply device that supplies a first supply water having a first temperature to the water passage, and a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, and when the first supply water is supplied to the poured concrete, a peak value of the concrete temperature is detected, and after the peak value of the concrete temperature is detected, the second supply water is supplied to the water passage so that the concrete temperature is lower than the peak value. Effect of the Invention

[0020] The concrete cooling system of the present invention can be adjusted to provide a longer period for cooling the poured concrete. [Brief description of the drawings]

[0021] [Figure 1] FIG. 1 is a diagram showing a concrete cooling system according to a first embodiment. [Diagram 2] FIG. 2 is a plan view of the wall water supply device shown in FIG. [Diagram 3] FIG. 2 is a block diagram of a control device shown in FIG. [Figure 4] 2 is a flowchart showing a concrete cooling process performed by the control device shown in FIG. 1. [Diagram 5] FIG. 5 is a diagram showing the change over time in concrete temperature in the concrete cooling process shown in FIG. 4. [Figure 6] FIG. 11 is a diagram showing a concrete cooling system according to a second embodiment. [Figure 7] FIG. 7 is a plan view of the wall water-supply device shown in FIG. [Figure 8] FIG. 7 is a block diagram of the control device shown in FIG. [Figure 9]7 is a flowchart showing a concrete cooling process performed by the control device shown in FIG. 6. [Figure 10] FIG. 10 is a diagram showing the change over time in concrete temperature in the concrete cooling process shown in FIG. [Figure 11] FIG. 11 is a diagram showing a concrete cooling system according to a third embodiment. [Figure 12] FIG. 12 is a block diagram of the control device shown in FIG. [Figure 13] 12 is a flowchart showing a concrete cooling process performed by the control device shown in FIG. [Figure 14] 14 is a graph showing changes in concrete temperature over time in the concrete cooling process shown in FIG. 4 and the bottom slab cooling process shown in FIG. 13. FIG. [Figure 15] FIG. 10(a) is a diagram showing a concrete cooling system according to a fourth embodiment, and (b) is a cross-sectional view taken along line AA in (a). [Figure 16] FIG. 13(a) is a diagram showing a concrete cooling system according to a fifth embodiment, and FIG. 13(b) is a cross-sectional view taken along line BB in FIG. 13(a). [Figure 17] FIG. 11 is a diagram showing a concrete cooling system according to a first modified example. [Figure 18] FIG. 18 is a plan view of the wall water supply device shown in FIG. [Figure 19] FIG. 11 is a plan view of a water supply device according to a modified example. [Figure 20] FIG. 11 is a diagram showing a concrete cooling system according to a second modified example. [Figure 21] FIG. 1 is a diagram showing an example of a water passage arranged around poured concrete. [Figure 22] FIG. 13 is a diagram showing another example of a water passage arranged around poured concrete. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0022] Hereinafter, a concrete cooling system according to the present invention will be described with reference to the drawings. However, it should be noted that the technical scope of the present invention is not limited to the embodiments described above, but extends to the inventions described in the claims and their equivalents.

[0023] (Configuration and Function of the Concrete Cooling System According to the First Embodiment) FIG. 1 is a diagram showing a concrete cooling system according to a first embodiment.

[0024] The concrete cooling system 100 includes a wall water supply device 101a, a top plate water supply device 101b, a wall piping 102a, a top plate piping 102b, a wall temperature sensor 103a, a top plate temperature sensor 103b, a wall water temperature sensor 104a, a top plate water temperature sensor 104b, and a control device 1. The concrete cooling system 100 cools a wall 107 and a top plate 108, which are concrete poured on a bottom plate 106.

[0025] FIG. 2 is a plan view of the wall-mounted water-supply device 101a.

[0026] The wall water supply device 101a has a recovery tank 110, a first water supply device 111, a second water supply device 112, a three-way water inlet valve 113, a three-way water outlet valve 114, and a flow meter 115, and alternately supplies the first supply water or the second supply water to the wall piping 102a arranged inside the wall 107.

[0027] The recovery tank 110 is formed of a material such as iron or fiber reinforced plastics (FRP), and recovers water supplied from the first water supply device 111 or the second water supply device 112 to the wall piping 102a.

[0028] The first water supply device 111 has a chiller unit 116 and a cold water tank 117, generates first supply water having a low first temperature, and supplies the generated first supply water to the wall piping 102a. The chiller unit 116 cools water received from the recovery tank 110 via the three-way water inlet valve 113 to a desired temperature to generate first supply water, which is cooling water. The cold water tank 117 is formed of a material such as iron or FRP, similar to the recovery tank 110, and stores the first supply water generated by the chiller unit 116. The cold water tank 117 has a water supply pump, and discharges the first supply water stored in the cold water tank 117 to the wall piping 102a.

[0029] The second water supply device 112 has a water heater 118 and a hot water tank 119, generates second supply water having a second temperature higher than the first temperature, and supplies the generated second supply water to the wall piping 102a. The water heater 118 heats water received from the recovery tank 110 via the three-way water inlet valve 113 to a desired temperature to generate heated water, i.e., hot water, which is the second supply water. The hot water tank 119 is formed of a material such as iron or FRP, similar to the recovery tank 110, and stores the second supply water generated by the water heater 118. The hot water tank 119 has a water supply pump, and discharges the first supply water stored in the hot water tank 119 to the wall piping 102a.

[0030] The water inlet three-way valve 113 connects the recovery tank 110 to either the chiller unit 116 or the water heater 118 in accordance with a control signal input from the control device 1. The water inlet three-way valve 113 connects the recovery tank 110 to the chiller unit 116 when a first feedwater supply signal is input from the control device 1. The water inlet three-way valve 113 connects the recovery tank 110 to the water heater 118 when a second feedwater supply signal is input from the control device 1.

[0031] The water outflow three-way valve 114 connects the wall piping 102a to either the cold water tank 117 or the hot water tank 119 in accordance with a control signal input from the control device 1. When a first feedwater supply signal is input from the control device 1, the water outflow three-way valve 114 connects the wall piping 102a to the cold water tank 117. When a second feedwater supply signal is input from the control device 1, the water outflow three-way valve 114 connects the wall piping 102a to the hot water tank 119.

[0032] The flow meter 115 is disposed between the wall piping 102a and the three-way water outlet valve 114, measures the amount of the first supply water or the second supply water supplied to the wall piping 102a, and outputs a flow rate signal indicating the measured flow rate to the control device 1.

[0033] The top plate water supply device 101b supplies the first supply water or the second supply water to the top plate piping 102b arranged inside the top plate 108. Since it has the same configuration as the wall water supply device 101a, a detailed description thereof will be omitted here.

[0034] The wall piping 102a is made of polyvinyl chloride or the like, is arranged inside the wall 107, and is a water passage for passing either the first supply water or the second supply water supplied from the wall water supply device 101a. The top plate piping 102b is made of polyvinyl chloride or the like, is arranged inside the top plate 108, and is a water passage for passing either the first supply water or the second supply water supplied from the top plate water supply device 101b.

[0035] Wall temperature sensor 103a is a contact-type temperature sensor such as a thermocouple type or thermistor type, which is arranged inside wall 107, detects the wall temperature, which is the temperature of wall 107, and outputs a wall temperature signal indicating the detected wall temperature to control device 1. Top plate temperature sensor 103b is a contact-type temperature sensor such as a thermocouple type or thermistor type, which is arranged inside top plate 108, detects the top plate temperature, which is the temperature of top plate 108, and outputs a top plate temperature signal indicating the detected top plate temperature to control device 1. The wall temperature signal and top plate temperature signal are examples of concrete temperature signals that indicate the concrete internal temperature, which is the temperature inside the poured concrete.

[0036] The wall water temperature sensor 104a is disposed so as to be in contact with the pipe connecting the wall water supply device 101a and the wall pipe 102a, detects the temperature of the water supplied to the wall pipe 102a, and outputs a wall water temperature signal indicating the detected temperature to the control device 1. The top plate water temperature sensor 104b is disposed so as to be in contact with the pipe connecting the top plate water supply device 101b and the top plate pipe 102b, detects the temperature of the water supplied to the top plate pipe 102b, and outputs a top plate water temperature signal indicating the detected temperature to the control device 1.

[0037] FIG. 3 is a block diagram of the control device 1.

[0038] The control device 1 has a communication unit 11, a memory unit 12, an input unit 13, an output unit 14, and a processing unit 20, and executes a concrete cooling process by the concrete cooling system 100. The control device 1 receives a wall temperature signal and a top plate temperature signal, and controls the first water supply device 111 and the second water supply device 112 to supply at least one of the first supply water and the second supply water to the wall pipe 102a and the top plate pipe 102b. The control device 1 is a computer in one example, but may be formed by combining a computer with a programmable logic controller (PLC), also called a sequencer. The communication unit 11, the memory unit 12, the input unit 13, the output unit 14, and the processing unit 20 are connected to each other via a bus 15.

[0039] The communication unit 11 has a wired communication interface circuit such as Ethernet (registered trademark). The communication unit 11 communicates with the components of the concrete cooling system 100 via a communication network such as the Internet and a local area network (LAN). The communication unit 11 communicates with the wall temperature sensor 103a, the top plate temperature sensor 103b, the wall water temperature sensor 104a, the top plate water temperature sensor 104b, the water outlet three-way valve 114, the water outlet three-way valve 114, and the like.

[0040] The storage unit 12 includes, for example, at least one of a semiconductor storage device, a magnetic tape device, a magnetic disk device, and an optical disk device. The storage unit 12 stores an operating system program, a driver program, an application program, data, and the like used for processing in the processing unit 20. For example, the storage unit 12 stores a concrete cooling program and the like for causing the processing unit 20 to execute a concrete cooling process for cooling poured concrete. The concrete cooling program may be installed in the storage unit 12 from a computer-readable portable storage medium, such as a CD-ROM or a DVD-ROM, using a known setup program or the like.

[0041] The input unit 13 may be any device capable of inputting data, such as a touch panel or a keyboard. An operator using the control device 1 can input letters, numbers, symbols, and the like using the input unit 13. When the input unit 13 is operated by the operator, it generates a signal corresponding to the operation. The generated signal is then supplied to the processing unit 20 as an instruction from the operator.

[0042] The output unit 14 may be any device capable of displaying video, images, etc., such as a liquid crystal display or an organic EL display. The output unit 14 displays video corresponding to video data supplied from the processing unit 20, images corresponding to image data, etc. The output unit 14 may also be an output device that prints video, images, characters, etc. on a display medium such as paper.

[0043] The processing unit 20 has one or more processors and their peripheral circuits. The processing unit 20 centrally controls the overall operation of the control device 1, and is, for example, a CPU. The processing unit 20 executes processing based on programs (driver programs, operating system programs, application programs, etc.) stored in the storage unit 12. The processing unit 20 can also execute multiple programs (application programs, etc.) in parallel.

[0044] The processing unit 20 has a first supply water supply unit 21, a second supply water supply unit 22, a concrete temperature acquisition unit 23, a peak value determination unit 24, and a timing unit 25. Each of these units is a functional module realized by a program executed by a processor included in the processing unit 20. Alternatively, each of these units may be implemented in the processing unit 20 as firmware.

[0045] (Concrete cooling process using the control device according to the first embodiment) FIG. 4 is a flow chart showing the concrete cooling process by the control device 1, and FIG. 5 is a diagram showing the change over time in the concrete cooling process shown in FIG.

[0046] 4 is executed mainly by the processing unit 20 in cooperation with each element of the control device 1, based on a control program previously stored in the storage unit 12. The concrete cooling process will be described using the wall 107 as an example, but the concrete cooling process is also executed on the top slab 108 in the same manner.

[0047] In Fig. 5, the horizontal axis indicates time, and the vertical axis indicates concrete temperature. Waveform W101 indicates the change over time of concrete temperature when the concrete cooling process shown in Fig. 4 is performed, and waveform W102 indicates the change over time of concrete temperature when the concrete cooling process shown in Fig. 4 is not performed. The arrow indicated by "1" indicates the period when the first supply water is supplied, and the arrow indicated by "2" indicates the period when the second supply water is supplied.

[0048] First, the first feedwater supply unit 21 outputs a first feedwater supply signal indicating that the first feedwater is to be supplied to the wall water supply device 101a (S101). In response to the first feedwater supply signal being input to the wall water supply device 101a, the chiller unit 116 generates the first feedwater and stores the generated first feedwater in the cold water tank 117. The cold water tank 117 discharges the stored first feedwater to the wall piping 102a. The water inlet three-way valve 113 connects the recovery tank 110 and the chiller unit 116, and the water outlet three-way valve 114 connects the wall piping 102a and the cold water tank 117.

[0049] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a (S102). The concrete temperature acquisition unit 23 stores in the storage unit 12 wall temperature information indicating the acquired wall temperature.

[0050] Next, the peak value determination unit 24 determines whether or not the wall temperature acquired in the process of S102 has reached a peak value (S103). The processes of S102 and S103 are repeated until the peak value determination unit 24 determines that the wall temperature acquired in the process of S102 has reached a peak value (S103-YES).

[0051] At time t1 shown in FIG. 5, when it is determined that the wall temperature acquired in the processing of S102 has reached a peak value (S103-YES), the timing unit 25 measures time from the time when it is determined that the wall temperature has reached the peak value until a predetermined elapsed time has elapsed (S104).

[0052] When the timer 25 has timed the elapsed time, at time t2 shown in Fig. 5, the first feedwater supply unit 21 outputs a first feedwater stop signal to the wall water supply device 101a to stop the supply of the first feedwater (S105). The chiller unit 116 stops generating the first feedwater in response to the first feedwater stop signal being input to the wall water supply device 101a.

[0053] Next, second supply water supply unit 22 outputs a second supply water supply signal indicating that the second supply water is to be supplied to wall water supply device 101a (S106). In response to input of the second supply water supply signal to wall water supply device 101a, water heater 118 generates second supply water and stores the generated second supply water in hot water tank 119. Hot water tank 119 discharges the stored second supply water to wall piping 102a. Water inlet three-way valve 113 connects recovery tank 110 and water heater 118, and water outlet three-way valve 114 connects wall piping 102a and hot water tank 119.

[0054] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a, similar to the process of S102 (S107). Next, the peak value determination unit 24 determines whether or not the wall temperature acquired in the process of S107 has reached a second peak value (S108). The second peak value is a temperature lower than the peak value determined by the peak value determination unit 24 in the process of S103. In one example, the temperature difference Δt1 between the peak value and the second peak value is 2°C. The processes of S107 and S108 are repeated until the peak value determination unit 24 determines that the wall temperature acquired in the process of S107 has reached the second peak value (S108-YES).

[0055] 5, when it is determined that the wall temperature acquired in the process of S107 has reached the second peak value (S108-YES), the second feedwater supply unit 22 outputs a second feedwater stop signal to the wall water supply device 101a to stop the supply of the second feedwater (S109). In response to the second feedwater stop signal being input to the wall water supply device 101a, the water heater 118 stops generating the second feedwater.

[0056] Next, the first feedwater supply unit 21 outputs a first feedwater supply signal to the wall water supply device 101a indicating that the first feedwater is to be supplied (S110). In response to the first feedwater supply signal being input to the wall water supply device 101a, the chiller unit 116 generates the first feedwater and stores the generated first feedwater in the cold water tank 117. The cold water tank 117 discharges the stored first feedwater to the wall piping 102a. The water inlet three-way valve 113 connects the recovery tank 110 to the chiller unit 116, and the water outlet three-way valve 114 connects the wall piping 102a to the cold water tank 117. The water outlet three-way valve 114 connects the wall piping 102a to the cold water tank 117, thereby restarting the supply of the first feedwater to the wall piping 102a.

[0057] Next, the timer 25 measures a predetermined time from the time when it is determined that the wall temperature has reached the second peak value (S111). When the timer 25 measures the time, the first feedwater supply unit 21 outputs a first feedwater stop signal to the wall water supply device 101a to stop the supply of the first feedwater at time t4 shown in Fig. 5 (S112). In response to the first feedwater stop signal being input to the wall water supply device 101a, the chiller unit 116 stops generating the first feedwater.

[0058] Next, the second supply water supply unit 22 outputs a second supply water supply signal indicating that the second supply water is to be supplied to the wall water supply device 101a (S113). In response to the second supply water supply signal being input to the wall water supply device 101a, the water heater 118 generates the second supply water and stores the generated second supply water in the hot water tank 119. The hot water tank 119 discharges the stored second supply water to the wall piping 102a. The water inlet three-way valve 113 connects the recovery tank 110 and the water heater 118, and the water outlet three-way valve 114 connects the wall piping 102a and the hot water tank 119. The water outlet three-way valve 114 connects the wall piping 102a and the hot water tank 119, thereby restarting the supply of the second supply water to the wall piping 102a.

[0059] Next, the timer unit 25 starts timing a predetermined supply time (S114). The supply time timed by the timer unit 25 is, for example, 14 days. Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a, similar to the process of S102 (S115). Next, the peak value determination unit 24 determines whether the wall temperature acquired in the process of S115 has reached a third peak value (S116). The third peak value is a temperature lower than the peak value determined by the peak value determination unit 24 in the process of S108. In one example, the temperature difference between the second peak value and the third peak value is 2°C.

[0060] When the peak value determination unit 24 determines that the wall temperature acquired in the processing of S115 has reached the third peak value (S115-YES), the first supply water and the second supply water are sequentially supplied to the wall piping 102a in the same manner as in the processing of S109 to S113 (S116).

[0061] When the peak value determination unit 24 determines that the wall temperature acquired in the process of S115 has not reached the third peak value (S115-NO), the timer unit 25 determines whether or not the supply time for which timing was started in the process of S114 has elapsed (S117). The processes of S115 to S117 are repeated until the timer unit 25 determines that the supply time has elapsed (S117-YES). The temperature difference between the peak value and the second peak value at time t5, indicated by Δt2 in FIG. 5, is greater than 2° C., and the peak value determination unit 24 does not determine that the wall temperature acquired in the process of S115 has reached the third peak value (S115-NO).

[0062] When the timer 25 determines that the supply time has elapsed (S117-YES), the second supply water supply unit 22 outputs a second supply water stop signal to the wall water supply device 101a to stop the supply of the second supply water (S118). In response to the second supply water stop signal being input to the wall water supply device 101a, the water heater 118 stops generating the second supply water. Then, the concrete cooling process ends.

[0063] (Actions and Effects of the Concrete Cooling System According to the First Embodiment) In the concrete cooling system 100, the peak values ​​of the wall temperature and top plate temperature are detected when the first supply water is supplied, and then the second supply water is supplied to the wall piping and top plate piping, thereby adjusting the period for cooling the wall and top plate to be longer.

[0064] In addition, in the concrete cooling system 100, by supplying the second supply water so that the wall temperature and top plate temperature become lower than the peak value, the difference between the wall temperature and top plate temperature and the external temperature becomes large, and the occurrence of thermal cracks in the wall and top plate can be prevented.

[0065] (Configuration and Function of the Concrete Cooling System According to the Second Embodiment) FIG. 6 is a diagram showing a concrete cooling system according to the second embodiment.

[0066] The concrete cooling system 200 differs from the concrete cooling system 100 in that it has a wall water supply device 201a, a top plate water supply device 201b, and a control device 2 instead of the wall water supply device 101a, the top plate water supply device 101b, and the control device 1. The configurations and functions of the components of the concrete cooling system 200 other than the wall water supply device 201a, the top plate water supply device 201b, and the control device 2 are the same as the configurations and functions of the components of the concrete cooling system 100 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0067] FIG. 7 is a plan view of the wall water-supply device 201a.

[0068] The wall water supply apparatus 201a differs from the wall water supply apparatus 101a in that it has a first water inlet flow adjustment valve 211, a second water inlet flow adjustment valve 212, a first water outflow flow adjustment valve 213, and a second water outflow flow adjustment valve 214 instead of the water inlet three-way valve 113 and the water outflow three-way valve 114. The wall water supply apparatus 201a also differs from the wall water supply apparatus 101a in that it has a first check valve 215, a second check valve 216, and a junction pipe 217. The configurations and functions of the components of the wall water supply apparatus 201a other than the first water inlet flow adjustment valve 211 to the junction pipe 217 are the same as those of the wall water supply apparatus 101a with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0069] The first water inlet flow adjustment valve 211 is disposed between the recovery tank 110 and the first water supply device 111, and adjusts the flow rate of water flowing from the recovery tank 110 to the first water supply device 111 in response to a first flow adjustment signal input from the control device 2. The second water inlet flow adjustment valve 212 is disposed between the recovery tank 110 and the second water supply device 112, and adjusts the flow rate of water flowing from the recovery tank 110 to the second water supply device 112 in response to a second flow adjustment signal input from the control device 2.

[0070] The first outflow flow adjustment valve 213 is disposed between the first water supply device 111 and the first check valve 215, and adjusts the flow rate of the first supply water supplied from the first water supply device 111 to the wall piping 102a in response to a first flow adjustment signal input from the control device 2. The second outflow flow adjustment valve 214 is disposed between the second water supply device 112 and the second check valve 216, and adjusts the flow rate of the second supply water supplied from the second water supply device 112 to the wall piping 102a in response to a second flow adjustment signal input from the control device 2.

[0071] The first check valve 215 is disposed between the first outflow flow adjustment valve 213 and the junction pipe 217, and prevents the second supply water supplied from the second water supply device 112 from flowing back to the first water supply device 111 through the junction pipe 217. The second check valve 216 is disposed between the second outflow flow adjustment valve 214 and the junction pipe 217, and prevents the second supply water supplied from the first water supply device 111 from flowing back to the second water supply device 112 through the junction pipe 217. The junction pipe 217 is disposed between the flowmeter 115, and the first check valve 215 and the second check valve 216. The junction pipe 217 supplies mixed water, which is a mixture of the first supply water supplied through the first check valve 215 and the second supply water supplied through the second check valve 216, to the wall pipe 102a through the flowmeter 115.

[0072] FIG. 8 is a block diagram of the control device 2.

[0073] The control device 2 differs from the control device 1 in that the control device 2 has a storage unit 16 and a processing unit 30 instead of the storage unit 12 and the processing unit 20. The configurations and functions of the components of the control device 2 other than the storage unit 16 and the processing unit 30 are the same as those of the components of the control device 1 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0074] The storage unit 16 differs from the storage unit 12 in that it stores temperature profile information 160. The configuration and functions of the storage unit 16 other than storing the temperature profile information 160 are the same as those of the storage unit 12, and therefore a detailed description thereof will be omitted here.

[0075] Temperature profile information 160 stores the time-based changes in the wall temperature and top plate temperature after the wall temperature detected by wall temperature sensor 103a and the top plate temperature detected by top plate temperature sensor 103b reach their peak values. Temperature profile information 160 stores the temperature drops from the wall temperature and top plate temperature in association with the elapsed time after the wall temperature and top plate temperature each reach their peak value.

[0076] Processing unit 30 differs from processing unit 20 in that processing unit 30 has a flow rate adjustment unit 31. The configurations and functions of the components of processing unit 30 other than the flow rate adjustment unit 31 are the same as those of processing unit 20 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0077] (Concrete cooling process by the control device according to the second embodiment) FIG. 9 is a flow chart showing the concrete cooling process by the control device 2, and FIG. 10 is a diagram showing the change in concrete temperature over time in the concrete cooling process shown in FIG.

[0078] 9 is executed mainly by the processing unit 30 in cooperation with each element of the control device 2, based on a control program previously stored in the storage unit 16. The concrete cooling process will be described using the wall 107 as an example, but the concrete cooling process is also executed on the top slab 108 in a similar manner.

[0079] In Fig. 10, the horizontal axis indicates time, and the vertical axis indicates concrete temperature. Waveform W201 indicates the change in concrete temperature over time when the concrete cooling process shown in Fig. 4 is performed, and waveform W202 indicates an example of outside air temperature. An arrow marked "1" indicates a period during which the first supply water is supplied, and an arrow marked with both "1" and "2" indicates a period during which the first and second supply waters are supplied.

[0080] First, the first feedwater supply unit 21 outputs a first feedwater supply signal indicating that the first feedwater is to be supplied to the wall water supply device 101a (S201). In response to the first feedwater supply signal being input to the wall water supply device 101a, the chiller unit 116 generates the first feedwater and stores the generated first feedwater in the cold water tank 117. The cold water tank 117 discharges the stored first feedwater.

[0081] Next, the flow rate adjustment unit 31 outputs a first flow adjustment signal to the wall water supply device 101a indicating that the opening degree of the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 is to be 100% (S202). In response to the first flow adjustment signal being input to the wall water supply device 101a, the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 are set to an opening degree of 100%. With the opening degree of the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 being 100%, the first supply water is supplied to the wall piping 102a.

[0082] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a (S203). Next, the peak value determination unit 24 determines whether or not the wall temperature acquired in the process of S203 has reached a peak value, similar to the process of S103 (S204). The processes of S202 to S204 are repeated until the peak value determination unit 24 determines that the wall temperature acquired in the process of S203 has reached a peak value (S204-YES).

[0083] At time t1 shown in FIG. 10, when the peak value determination unit 24 determines that the wall temperature acquired in the processing of S203 has reached the peak value (S204-YES), the timing unit 25 starts timing the elapsed time from the time when it was determined that the wall temperature had reached the peak value (S205).

[0084] Next, the second supply water supply unit 22 outputs a second supply water supply signal indicating that the second supply water is to be supplied to the wall water supply device 101a (S206). In response to the second supply water supply signal being input to the wall water supply device 101a, the water heater 118 generates the second supply water and stores the generated second supply water in the hot water tank 119. The hot water tank 119 discharges the stored second supply water.

[0085] Next, the flow rate adjustment unit 31 outputs a first flow adjustment signal indicating that the opening degree should be 50% to the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 (S207). In response to the input of the first flow adjustment signal, the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 set the opening degree to 50%.

[0086] Next, the flow rate adjustment unit 31 outputs a second flow adjustment signal indicating that the opening degree should be 50% to the second water inlet flow adjustment valve 212 and the second water outflow flow adjustment valve 214 (S208). In response to the input of the second flow adjustment signal, the second water inlet flow adjustment valve 212 and the second water outflow flow adjustment valve 214 set the opening degree to 50%.

[0087] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a (S209). Next, the flow rate adjustment unit 31 acquires wall temperature information indicating the wall temperature stored in the temperature profile information 160 in association with a time corresponding to the elapsed time measured by the timer unit 25 (S210).

[0088] Next, the flow rate adjustment unit 31 judges whether the wall temperature detected in the process of S209 is higher than the wall temperature corresponding to the wall temperature information acquired in the process of S210 (S211). When the flow rate adjustment unit 31 judges that the wall temperature detected in the process of S209 is higher than the wall temperature corresponding to the wall temperature information acquired in the process of S210 (S211-YES), it increases the first supply water and decreases the second supply water (S212). The flow rate adjustment unit 31 outputs a first flow adjustment signal indicating an increase in the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213, and a second flow adjustment signal indicating a decrease in the opening degree of the second water inlet flow adjustment valve 212 and the second water outlet flow adjustment valve 214 to the wall water supply device 101a. In one example, the flow rate adjuster 31 increases the opening of the first water inlet flow adjustment valve 211 and the first water outflow adjustment valve 213 by 5%, and decreases the opening of the first water inlet flow adjustment valve 211 and the first water outflow adjustment valve 213 by 5%. By the flow rate adjuster 31 increasing the first supply water and decreasing the second supply water, the temperature of the mixed water supplied to the wall piping 102a decreases.

[0089] When the flow rate adjusting unit 31 determines that the wall temperature detected in the process of S209 is lower than the wall temperature corresponding to the wall temperature information acquired in the process of S210 (S211-NO), it decreases the first supply water and increases the second supply water (S213). The flow rate adjusting unit 31 outputs a first flow adjustment signal indicating to decrease the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213, and a second flow adjustment signal indicating to increase the opening degree of the second water inlet flow adjustment valve 212 and the second water outlet flow adjustment valve 214 to the wall water supply device 101a. In one example, the flow rate adjusting unit 31 increases the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213 by 5% and decreases the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213 by 5%. The flow rate regulator 31 reduces the first supply water and increases the second supply water, so that the temperature of the mixed water supplied to the wall pipe 102a increases.

[0090] Next, the flow rate adjustment unit 31 determines whether or not the elapsed time measured by the timer 25 is within the range of the time stored in the temperature profile information 160 (S214). The processes of S209 to S214 are repeated until the flow rate adjustment unit 31 determines that the elapsed time is outside the range of the time stored in the temperature profile information 160 (S214-NO).

[0091] When it is determined that the elapsed time is outside the range of the time stored in the temperature profile information 160 (S214-NO), the first feedwater supply unit 21 outputs a first feedwater stop signal to the wall water supply device 101a to stop the supply of the first feedwater (S215). Then, the second feedwater supply unit 22 outputs a second feedwater stop signal to the wall water supply device 101a to stop the supply of the second feedwater (S216), and the concrete cooling process ends.

[0092] (Actions and Effects of the Concrete Cooling System According to the Second Embodiment) In the concrete cooling system 300, the wall 107 and the top plate 108 can be cooled according to the desired temperature profile by supplying mixed water to the wall piping 102a and the top plate piping 102b so that the wall temperature and the top plate temperature match the temperature changes corresponding to the temperature profile information 160.

[0093] (Configuration and Function of the Concrete Cooling System According to the Third Embodiment) FIG. 11 is a diagram showing a concrete cooling system according to the third embodiment.

[0094] The concrete cooling system 300 differs from the concrete cooling system 100 in that it has a bottom slab water supply device 301 and a bottom slab piping 302 instead of the top slab water supply device 101b and the top slab piping 102b. The concrete cooling system 300 also differs from the concrete cooling system 100 in that it has a bottom slab temperature sensor 303, a bottom slab water temperature sensor 304, and a control device 3 instead of the top slab temperature sensor 103b, the top slab water temperature sensor 104b, and the control device 1. The configurations and functions of the components of the concrete cooling system 300 other than the bottom slab water supply device 301 to the bottom slab water temperature sensor 304 and the control device 3 are the same as those of the components of the concrete cooling system 100 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0095] The bottom slab water supply device 301 has a similar configuration to the wall water supply device 201a. The bottom slab water supply device 301 supplies a mixture of the first supply water and the second supply water to the bottom slab piping 302 arranged inside the bottom slab 306 while adjusting the openings of the first inlet flow regulation valve 211 to the second outlet flow regulation valve 214 in response to the input of the first flow regulation signal and the second flow regulation signal from the control device 3.

[0096] The bottom plate temperature sensor 303 has a configuration similar to that of the wall temperature sensor 103a, is arranged inside the bottom plate 306, detects the bottom plate temperature, which is the temperature of the bottom plate 306, and outputs a bottom plate temperature signal indicating the detected temperature to the control device 3. The bottom plate water temperature sensor 304 is arranged so as to be in contact with the piping connecting the bottom plate water supply device 301 and the bottom plate piping 302, detects the temperature of the water supplied to the bottom plate piping 302, and outputs a bottom plate water temperature signal indicating the detected temperature to the control device 3.

[0097] FIG. 12 is a block diagram of the control device 3.

[0098] The processing section 40 differs from the processing section 20 in that it has a bottom plate temperature adjustment section 41. The configurations and functions of the components of the processing section 30 other than the bottom plate temperature adjustment section 41 are the same as those of the components of the processing section 20 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0099] (Bottom slab cooling process by the control device according to the third embodiment) FIG. 13 is a flow chart showing the bottom slab cooling process by the control device 3, and FIG. 14 is a diagram showing the change in concrete temperature over time in the concrete cooling process shown in FIG. 4 and the bottom slab cooling process shown in FIG.

[0100] 13 is executed mainly by the processing unit 40 in cooperation with each element of the control device 3 based on a control program previously stored in the storage unit 12. The base slab cooling process is executed simultaneously with the concrete cooling process described with reference to FIG.

[0101] In Fig. 14, the horizontal axis indicates time, and the vertical axis indicates concrete temperature. Waveform W301 indicates the change over time of the wall temperature when the concrete cooling process shown in Fig. 4 is performed, and waveform W302 indicates the change over time of the wall temperature when the concrete cooling process shown in Fig. 4 is not performed. Waveform W303 indicates the change over time of the bottom slab temperature when the bottom slab cooling process shown in Fig. 13 is performed. The arrow indicated by "1" indicates the period during which the first supply water is supplied to the wall piping 102a, and the arrow indicated by "2" indicates the period during which the second supply water is supplied to the wall piping 102a. The dashed arrows indicated by "1" and "2" indicate the period during which mixed water obtained by mixing the first supply water and the second supply water is supplied to the bottom slab piping 302 as bottom slab supply water.

[0102] First, the first feedwater supply unit 21 outputs a first feedwater supply signal to the bottom slab water supply device 301 indicating that the first feedwater is to be supplied (S301). Next, the second feedwater supply unit 22 outputs a second feedwater supply signal to the bottom slab water supply device 301 indicating that the second feedwater is to be supplied (S301). Next, the flow rate adjustment unit 31 outputs a first flow adjustment signal to the bottom slab water supply device 301 indicating that the opening degree of the first water inlet flow adjustment valve 211 and the first water outflow flow adjustment valve 213 is to be 50% (S303). Next, the flow rate adjustment unit 31 outputs a second flow adjustment signal to the bottom slab water supply device 301 indicating that the opening degree of the second water inlet flow adjustment valve 212 and the second water outflow flow adjustment valve 214 is to be 50% (S304). By the processing of S301 to S304, the bottom slab water supply device 301 supplies mixed water obtained by mixing the first supply water and the second supply water as bottom slab supply water to the bottom slab piping 302 via the first outflow flow control valve 213 and the second outflow flow control valve 214, which are opened by 50%. The temperature of the bottom slab supply water supplied to the bottom slab piping 302 is higher than the temperature of the first supply water supplied to the wall piping 102a.

[0103] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a (S305). Next, the peak value determination unit 24 determines whether or not the wall temperature acquired in the process of S305 has reached a peak value (S306), similar to the process of S103 shown in Fig. 4. The processes of S305 and S306 are repeated until it is determined that the wall temperature acquired by the peak value determination unit 24 has reached a peak value (S306-YES).

[0104] 14, when the peak value determination unit 24 determines that the wall temperature acquired in the process of S305 has reached a peak value (S306-YES), the timing unit 25 starts timing a predetermined supply time (S307). Next, the concrete temperature acquisition unit 23 acquires a bottom slab temperature corresponding to the bottom slab temperature signal input from the bottom slab temperature sensor 303 (S308). The concrete temperature acquisition unit 23 stores bottom slab temperature information indicating the acquired bottom slab temperature in the storage unit 12.

[0105] Next, the bottom plate temperature adjustment unit 41 subtracts the bottom plate temperature acquired in the process of S308 from the peak value wall temperature of the wall temperature acquired in the process of S305 to calculate the peak temperature difference (S309). The bottom plate temperature adjustment unit 41 stores peak temperature difference information indicating the calculated peak temperature difference in the memory unit 12.

[0106] Next, the concrete temperature acquisition unit 23 acquires a wall temperature corresponding to the wall temperature signal input from the wall temperature sensor 103a (S310). Next, the concrete temperature acquisition unit 23 acquires a bottom slab temperature corresponding to the bottom slab temperature signal input from the bottom slab temperature sensor 303 (S311).

[0107] Next, the bottom plate temperature adjustment unit 41 judges whether the bottom plate temperature acquired in the process of S310 is higher than the wall temperature acquired in the process of S309 (S312). When the bottom plate temperature adjustment unit 41 judges that the bottom plate temperature is higher than the wall temperature (S312-YES), it increases the first supply water and decreases the second supply water in the bottom plate supply water supplied from the bottom plate water supply device 301 (S313). The flow rate adjustment unit 31 outputs to the bottom plate water supply device 301 a first flow adjustment signal indicating a decrease in the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213, and a second flow adjustment signal indicating an increase in the opening degree of the second water inlet flow adjustment valve 212 and the second water outlet flow adjustment valve 214. In one example, the flow rate adjustment unit 31 reduces the opening degree of the first water inlet flow control valve 211 and the first water outflow flow control valve 213 by 5%, and increases the opening degree of the first water inlet flow control valve 211 and the first water outflow flow control valve 213 by 5%.

[0108] When the bottom slab temperature adjustment unit 41 determines that the bottom slab temperature is lower than the wall temperature (S312-NO), it subtracts the bottom slab temperature acquired in the process of S311 from the wall temperature acquired in the process of S310 to calculate the bottom slab-wall temperature difference, which is the temperature difference between the wall 107 and the bottom slab 306 (S314). The bottom slab temperature adjustment unit 41 stores the calculated bottom slab-wall temperature difference in the memory unit 12.

[0109] Next, the bottom plate temperature adjustment unit 41 judges whether the bottom plate-wall temperature difference calculated in the process of S314 is greater than the peak temperature difference calculated in the process of S309 (S315). When the bottom plate temperature adjustment unit 41 judges that the bottom plate-wall temperature difference is greater than the peak temperature difference (S315-YES), it decreases the first supply water and increases the second supply water in the bottom plate supply water supplied from the bottom plate water supply device 301 (S316). The bottom plate temperature adjustment unit 41 outputs to the bottom plate water supply device 301 a first flow adjustment signal indicating an increase in the opening degree of the first water inlet flow adjustment valve 211 and the first water outlet flow adjustment valve 213, and a second flow adjustment signal indicating a decrease in the opening degree of the second water inlet flow adjustment valve 212 and the second water outlet flow adjustment valve 214. In one example, the flow rate adjustment unit 31 increases the opening degree of the first water inlet flow control valve 211 and the first water outflow flow control valve 213 by 5%, and decreases the opening degree of the first water inlet flow control valve 211 and the first water outflow flow control valve 213 by 5%.

[0110] When the bottom plate temperature adjustment unit 41 determines that the bottom plate-wall temperature difference is smaller than the peak temperature difference (S315-NO), the timer unit 25 determines whether the supply time has elapsed (S317), similar to the process shown in S117 in Fig. 4. The processes of S310 to S317 are repeated until the timer unit 25 determines that the supply time has elapsed (S317-YES).

[0111] When the timer 25 determines that the supply time has elapsed (S317-YES), the first feedwater supply unit 21 outputs a first feedwater stop signal to the bottom slab water supply device 301 indicating that the supply of the first feedwater is to be stopped (S318). Next, the second feedwater supply unit 22 outputs a second feedwater stop signal to the bottom slab water supply device 301 indicating that the supply of the second feedwater is to be stopped (S319). In response to the first feedwater stop signal and the second feedwater stop signal being input to the bottom slab water supply device 301, the chiller unit 116 and the water heater 118 of the bottom slab water supply device 301 stop generating the first feedwater and the second feedwater. Then, the bottom slab cooling process ends.

[0112] (Actions and Effects of the Concrete Cooling System According to the Third Embodiment) In the concrete cooling system 300, the temperature difference between the wall temperature and the slab temperature is controlled so that it is smaller than the temperature difference between the wall temperature and the slab temperature when the peak value is detected, thereby reducing the temperature difference between the wall temperature and the slab temperature and suppressing the occurrence of thermal cracks.

[0113] (Configuration and Function of Concrete Cooling System According to Fourth Embodiment) FIG. 15(a) is a diagram showing a concrete cooling system according to a fourth embodiment, and FIG. 15(b) is a cross-sectional view taken along line AA in FIG. 15(a).

[0114] The concrete cooling system 400 differs from the concrete cooling system 300 in that it has a pair of bottom slab pipes 402 instead of the bottom slab pipes 302. The configurations and functions of the components of the concrete cooling system 400 other than the pair of bottom slab pipes 402 are the same as the configurations and functions of the components of the concrete cooling system 300 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0115] Each of the pair of bottom plate piping 402 has a base 403 formed of a flexible material such as polyester, and a plurality of pipes 404 arranged inside the base 403, and is removably arranged on the side of the bottom plate 406.

[0116] In the concrete cooling system 400, a pair of base slab pipes 402 are removably arranged on the side of the base slab 406, so that the pipes for heating the base slab can be reused without being fixed in place, thereby reducing the cost of pouring concrete.

[0117] (Configuration and Function of Concrete Cooling System According to Fifth Embodiment) FIG. 16(a) is a diagram showing a concrete cooling system according to a fifth embodiment, and FIG. 16(b) is a cross-sectional view taken along line BB in FIG. 16(a).

[0118] The concrete cooling system 500 differs from the concrete cooling system 400 in that it has a pair of wall heating pipes 502. The configurations and functions of the components of the concrete cooling system 500 other than the pair of wall heating pipes 502 are the same as the configurations and functions of the components of the concrete cooling system 400 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0119] Each of the pair of wall heating pipes 502 has a base 503 formed of a flexible material such as polyester, and a plurality of pipes 504 arranged inside the base 503, and is removably arranged on the side of the wall 507.

[0120] In the concrete cooling system 500, a pair of base slab pipes 402 are removably arranged on the side of the base slab 406, so that the pipes for heating the base slab can be reused without being fixed in place, thereby reducing the cost of pouring concrete.

[0121] (Modification of concrete cooling system according to embodiment) In the concrete cooling system described above, the first water supply device has a chiller unit and a cold water tank, but in the concrete cooling system according to the embodiment, the chiller unit and the cold water tank may be integrated. Also, the second water supply device has a water heater and a hot water tank, but in the concrete cooling system according to the embodiment, the water heater and the hot water tank may be integrated.

[0122] In addition, in the concrete cooling system described above, the first water supply device includes a chiller unit and the second water supply device includes a water heater. However, in the concrete cooling system according to the embodiment, the first water supply device may be a device that generates a first supply water having a low first temperature, and the second supply water may be a device that generates a second supply water having a high second temperature that is higher than the first temperature.

[0123] In addition, in the concrete cooling system according to the embodiment, the control device may be configured to supply the first supply water and the second supply water to a water passage formed inside the concrete so that the temperature inside the concrete becomes lower than the peak value of the detected temperature inside the concrete. For example, in the concrete cooling system according to the embodiment, the control device may adjust the flow rate of the first supply water and the second supply water to adjust the temperature inside the concrete.

[0124] Moreover, the concrete cooling system according to the embodiment includes a temperature sensor that detects the temperature inside the poured concrete. However, the concrete cooling system according to the embodiment only needs to include a detection sensor that detects the concrete temperature that indicates the temperature of the concrete, such as the temperature of the surface of the poured concrete.

[0125] In addition, in the concrete cooling systems 300, 400 and 500, the base plate water supply device 301 is a separate device from the wall water supply device 101a, but in the concrete cooling system according to the embodiment, the base plate water supply device 301 may be integrated with the wall water supply device 101a.

[0126] FIG. 17 is a diagram showing a concrete cooling system according to a first modified example.

[0127] The concrete cooling system 600 differs from the concrete cooling system 300 in that it has a water supply device 601 instead of the wall water supply device 101 and the bottom slab water supply device 301. The concrete cooling system 600 also differs from the concrete cooling system 300 in the connection relationship between the wall piping 102a and the bottom slab piping 302. The configurations and functions of the components of the concrete cooling system 600 other than the water supply device 601 and the connection relationship between the wall piping 102a and the bottom slab piping 302 are the same as those of the components of the concrete cooling system 300 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0128] FIG. 18 is a plan view of the water supply device 601.

[0129] The water supply device 601 integrally has a bottom plate water supply section 602 and a wall water supply section 603, and sequentially supplies water to the bottom plate piping 302 and the wall piping 102a.

[0130] The bottom plate water supply unit 602 has the same structure as the wall water supply device 201a, heats and cools the water received from the wall piping 102a, and supplies it to the bottom plate piping 302. The wall water supply unit 603 has a structure obtained by removing the recovery tank 110 from the wall water supply device 101a, heats and cools the water received from the bottom plate piping 302, and supplies it to the wall piping 102a.

[0131] In the concrete cooling system 600, water supplied from the base plate water supply section 602 to the base plate piping 302 is heated and cooled by the wall water supply section 603 and supplied to the wall piping 102a, thereby improving energy efficiency by reusing the heat contained in the water supplied to the base plate piping 302.

[0132] In addition, in the concrete cooling system 600, the base slab water supply section 602 and the wall water supply section 603 are integrated, so the recovery tank 110 is omitted, making it possible to reduce the size of the water supply device.

[0133] In addition, in the concrete cooling system 600, the base plate water supply section 602 has a first water supply device 111 having a chiller unit 116 and a cold water tank 117, but in the concrete cooling system of the embodiment, the first water supply device 111 may be omitted.

[0134] FIG. 19 is a plan view of a water supply apparatus according to a modified example.

[0135] The water supply device 611 differs from the water supply device 601 in that it has a bottom plate water supply section 612 instead of the bottom plate water supply section 602. The bottom plate water supply section 612 differs from the bottom plate water supply section 602 in that it does not have the first water supply device 111, the first water inlet flow regulation valve 211, the first water outflow flow regulation valve 213, the first check valve 215, and the junction pipe 217. The configuration and function of the water supply device 611 are the same as those of the water supply device 601, except that the bottom plate water supply section 612 does not have the first water supply device 111, the first water inlet flow regulation valve 211, the first water outflow flow regulation valve 213, the first check valve 215, and the junction pipe 217, so detailed explanations will be omitted here.

[0136] By omitting first water supply device 111, water supply device 611 can have a smaller number of components than water supply device 601, and therefore can be made even smaller than water supply device 601.

[0137] Also, in the concrete cooling system described above, the wall piping 102a and the top slab piping 102b to which the first and second supply waters are supplied are disposed inside the wall 107 and the top slab 108, which are cast concrete. However, in the concrete cooling system according to the embodiment, for example, when the cast concrete is a narrow wall, the water channels to which the first and second supply waters are supplied may be disposed around the cast concrete.

[0138] FIG. 20 is a diagram showing a concrete cooling system according to a second modified example, and FIG. 21 is a diagram showing an example of a water passage arranged around poured concrete.

[0139] Concrete cooling system 700 differs from concrete cooling system 100 in that it has a water supply tank 105 and a pair of water passages 702a and 702b instead of top plate water supply device 101b, top plate piping 102b, top plate temperature sensor 103b, and top plate water temperature sensor 104b. The configurations and functions of the components of concrete cooling system 700 other than water supply device 105 and a pair of water passages 702a and 702b are the same as those of the components of concrete cooling system 700 with the same reference numerals, and therefore detailed description thereof will be omitted here.

[0140] The water supply tank 105 is formed from a material such as FRP, similar to the recovery tank 110, and supplies water to the recovery tank 110.

[0141] 21, a pair of water passages 702a and 702b are arranged along the upper end of a wall 207 made of concrete poured on a base 106, and first and second supply waters are supplied from a wall water supply device (not shown) via a supply pipe 702c. A plurality of nozzles directed toward the wall 207 are arranged in the pair of water passages 702a and 702b, and the first and second supply waters supplied from the wall water supply device 101a are sprayed toward the wall 207 via the nozzles. The first and second supply waters sprayed toward the wall 207 are allowed to flow away without returning to the recovery tank 110.

[0142] FIG. 22 is a diagram showing another example of a water passage arranged around poured concrete.

[0143] In Fig. 22, a pair of water passages 802a and 802b are arranged along the upper end of a wall 207 made of concrete poured on a base slab 106, and a first supply water and a second supply water are supplied from a wall water supply device 101a (not shown) through a supply pipe 802c. A plurality of water outlet holes are formed in the pair of water passages 802a and 802b so as to discharge water toward the side surface of the wall 207, and the first supply water and the second supply water supplied from the wall water supply device are sprayed toward the wall 207 through the plurality of water outlet holes. Note that, as described in Japanese Patent No. 7067747, when a concrete curing sheet having a water-permeable layer is used, the pair of water passages 802a and 802b are arranged so as to spray the first supply water and the second supply water into the water-permeable layer of the concrete curing sheet. [Explanation of symbols]

[0144] 1~3 Control device 100, 200, 300, 400, 500, 600, 700 Concrete Cooling System 101a, 201a Wall water supply device 101b, 201b Top plate water supply device 102a Wall piping 102b Top plate piping 103a Wall temperature sensor 103b Top plate temperature sensor 301 Bottom plate water supply device 302, 402 Bottom plate piping 303 Bottom plate temperature sensor 502 Wall heating piping

Claims

1. A water channel disposed inside and / or around the poured concrete; a temperature sensor that detects a concrete temperature, which is the temperature of the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature; a first water supply device that supplies a first supply water having a first temperature to the water passage; a second water supply device that supplies second supply water having a second temperature higher than the first temperature to the water passage; a control device to which the concrete temperature signal is input and which controls the first water supply device and the second water supply device so as to supply at least one of the first supply water and the second supply water to the water passage; The control device detects a peak value of the concrete temperature when the first supply water is supplied to the poured concrete, and after detecting the peak value of the concrete temperature, supplies the second supply water to the water passage so that the concrete temperature becomes lower than the peak value. A concrete cooling system comprising:

2. The control device includes: After detecting the peak value, the supply of the first supply water is stopped; determining whether or not the concrete temperature reaches a second peak value lower than the peak value when the second supply water is supplied to the poured concrete; After it is determined that the concrete temperature has reached the second peak value, the supply of the first supply water to the water passage is resumed and the supply of the second supply water is stopped.

10. The concrete cooling system of claim 1.

3. The control device includes: determining whether or not the concrete temperature reaches a third peak value lower than the second peak value when the second supply water is supplied to the poured concrete after the first supply water is supplied; After it is determined that the concrete temperature has reached the third peak value, the supply of the second supply water to the water passage is resumed and the supply of the first supply water is stopped.

3. The concrete cooling system of claim 2.

4. The control device includes: storing temperature profile information indicating a temperature change of the concrete temperature; supplying mixed water obtained by mixing the first supply water and the second supply water to the water passage such that the concrete temperature corresponding to the concrete temperature signal coincides with a temperature change corresponding to a temperature profile; 10. The concrete cooling system of claim 1.

5. A bottom slab temperature sensor that detects a bottom slab temperature, which is the temperature of the bottom slab that supports the poured concrete; and a bottom plate water supply device that supplies bottom plate supply water having a temperature higher than the first temperature to the periphery of the bottom plate, The control device controls the temperature of the bottom slab supply water so that the temperature difference between the concrete temperature and the bottom slab temperature does not become larger than the temperature difference between the concrete temperature and the bottom slab temperature when the peak value of the concrete temperature is detected.

10. The concrete cooling system of claim 1.

6. The water passage is disposed inside and / or around the poured concrete, The concrete cooling system according to claim 5 , wherein the base slab water supply device supplies the base slab supply water to a periphery of the poured concrete in addition to the base slab.

7. The water supply device further includes a water passage through which the water supply is supplied from the water supply device. The concrete cooling system according to claim 6 , wherein the base slab water passage is detachable from the base slab and the poured concrete.

8. A water channel disposed inside and / or around the poured concrete; a temperature sensor that detects a concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature; a first water supply device that supplies a first supply water having a first temperature to the water passage; a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage; and a control device in a concrete cooling system that receives the concrete temperature signal and controls the first water supply device and the second water supply device to supply at least one of the first supply water and the second supply water to the water passage, When the first supply water is supplied to the poured concrete, a peak value of the concrete temperature is detected, and after the peak value of the concrete temperature is detected, the second supply water is supplied to the water passage so that the concrete temperature becomes lower than the peak value. A control device comprising:

9. A water channel disposed inside and / or around the poured concrete; a temperature sensor that detects a concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature; a first water supply device that supplies a first supply water having a first temperature to the water passage; A method for controlling a concrete cooling system having a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, Detecting a peak value of the concrete temperature when the first supply water is supplied to the poured concrete; After detecting the peak value of the concrete temperature, the second supply water is supplied to the water passage so that the concrete temperature becomes lower than the peak value.

23. A control method comprising the steps of:

10. A water channel disposed inside and / or around the poured concrete; a temperature sensor that detects a concrete temperature, which is the temperature inside the poured concrete, and outputs a concrete temperature signal indicating the detected concrete temperature; a first water supply device that supplies a first supply water having a first temperature to the water passage; A control program for a concrete cooling system having a second water supply device that supplies a second supply water having a second temperature higher than the first temperature to the water passage, Detecting a peak value of the concrete temperature when the first supply water is supplied to the poured concrete; After detecting the peak value of the concrete temperature, the second supply water is supplied to the water passage so that the concrete temperature becomes lower than the peak value. A control program that causes a computer to execute a process.

Citation Information

Patent Citations

  • Method and apparatus for inputting comment

    JP1988047667A

  • Charged particle beam exposure device

    JP1989073721A

  • Concrete placing method

    JP2940367B2

  • Mass concrete pipe cooling method

    JP4108544B2

  • Pipe cooling system and pipe cooling method

    JP6546388B2