RKY (risk assessment hazard prediction) sheet creation support system

The RKY sheet creation support system addresses the limitations of existing systems by providing a comprehensive risk assessment and hazard prediction tool for diverse field work scenarios, enhancing risk management through detailed RKY sheet creation.

JP2024151013AActive Publication Date: 2024-10-24HIATACHI POWER SOLUTIONS CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023064118
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-11
Publication Date
2024-10-24
Estimated Expiration
2043-04-11

AI Technical Summary

Technical Problem

Existing group confirmation activity support systems are limited to specific work locations and contents, failing to adequately address risk assessment and hazard prediction for diverse objects and environments in field work.

Method used

An RKY sheet creation support system that includes an input section for target equipment information, field work name, and work procedure, with a control section that identifies risks and countermeasures, creating a comprehensive RKY sheet for various objects and environments.

Benefits of technology

Enables comprehensive risk assessment and hazard prediction in field work for various objects and environments, facilitating detailed risk management and countermeasure planning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024151013000001_ABST
    Figure 2024151013000001_ABST
Patent Text Reader

Abstract

To enable risk assessment hazard prediction for various objects in fieldwork.SOLUTION: An RKY sheet creation support system 10 includes: an input unit (terminal 400) which receives an input of target equipment information, fieldwork name, and input operation procedure information; and a control unit 110. The control unit 110 extracts necessary operation procedure information on the basis of the input operation procedure information acquired by the input unit, specifies the contents of a risk that may occur on the work procedure information, specifies the contents of measures against the contents of the risk, and creates a sheet including the tarte equipment information, the fieldwork name, the input operation procedure information, the specified contents of the risk, and the specified contents of the measures.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an RKY sheet creation support system that supports the creation of an RKY sheet related to on-site work. [Background technology]

[0002] In order to safely proceed with work at work sites such as construction work and maintenance work, hazard prediction activities, including risk assessment, are carried out before the work begins. Patent Document 1 describes a group confirmation activity support system used in group confirmation activities in which a group including multiple scheduled workers confirms precautions corresponding to the work content to be performed by the group. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2019-174945 A Summary of the Invention [Problem to be solved by the invention]

[0004] The group confirmation activity support system described in Patent Document 1 is based on the premise that the work location and work content are input and used only for risk prediction activities for specific work. Risk assessment and hazard prediction (RKY) is desired for work on different work targets (facilities, equipment, parts) rather than limited to specific work. The present invention has been made in view of the above background, and an object of the present invention is to provide an RKY sheet creation support system that enables risk assessment and hazard prediction in on-site work for various objects. [Means for solving the problem]

[0005] In order to solve the above-mentioned problems, an RKY sheet creation support system according to the present invention has an input unit that accepts input of target equipment information, an on-site work name, and input work procedure information, and a control unit, and the control unit extracts necessary work procedure information based on the input work procedure information acquired from the input unit, identifies possible risk content for the work procedure information, identifies countermeasure content for the risk content, and creates a sheet that describes the target equipment information, the on-site work name, the input work procedure information, the identified risk content, and the identified countermeasure content. Effect of the Invention

[0006] According to the present invention, it is possible to provide an RKY sheet creation support system that enables risk assessment and hazard prediction in on-site work for various objects. Problems, configurations, and effects other than those described above will become clear from the following description of the embodiments. [Brief description of the drawings]

[0007] [Figure 1] 1 is an overall configuration diagram of an RKY sheet creation support system according to an embodiment of the present invention. [Diagram 2] FIG. 2 is a functional block diagram of a terminal according to the embodiment. [Diagram 3] 4 shows data stored in a storage unit according to the present embodiment. [Figure 4] FIG. 2 is a data configuration diagram of a field work database according to the embodiment. [Diagram 5] FIG. 2 is a data configuration diagram of a first risk database according to the present embodiment. [Figure 6] FIG. 4 is a data configuration diagram of a first countermeasure database according to the present embodiment. [Figure 7] FIG. 4 is a data configuration diagram of a second risk database according to the present embodiment. [Figure 8] FIG. 11 is a data configuration diagram of a second countermeasure database according to the present embodiment. [Figure 9] FIG. 4 is a data configuration diagram of a first dictionary table according to the embodiment. [Figure 10] FIG. 11 is a data configuration diagram of a second dictionary table according to the embodiment. [Figure 11] 3 shows functional units included in a control unit according to the present embodiment. [Figure 12] 13 is a flowchart of an RKY sheet creation process according to the present embodiment. [Figure 13] 13 is a flowchart of an RKY sheet creation process according to the present embodiment. [Figure 14] 13 is a flowchart of an RKY sheet creation process according to the present embodiment. [Figure 15] 13 is a flowchart of an RKY sheet creation process according to the present embodiment. [Figure 16] FIG. 13 is a diagram showing a search screen on which input information is input according to the embodiment. [Figure 17] FIG. 13 is a diagram showing a search screen on which risk details are displayed according to the present embodiment. [Figure 18] FIG. 13 is a diagram showing a search screen on which countermeasures according to the present embodiment are displayed. [Figure 19] FIG. 13 is a diagram showing a search screen on which selected risk details and countermeasure details are displayed according to the present embodiment. [Figure 20] FIG. 13 is a diagram showing an RKY sheet display screen according to the present embodiment. [Figure 21] FIG. 13 is a diagram showing a risk / countermeasure addition screen according to the present embodiment. [Figure 22] FIG. 13 is a diagram showing an RKY sheet display screen on which added risk contents and countermeasure contents according to the present embodiment are displayed. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0008] An RKY sheet creation support system in a form (embodiment) for carrying out the present invention will be described below. The RKY sheet creation support system is configured to include an RKY sheet creation support server and a terminal. A worker who is a user of the RKY sheet creation support system inputs target facility information that is the subject of on-site work, the on-site work name, and input work procedure information into the terminal as input information. The terminal transmits the input information to the RKY sheet creation support server.

[0009] The RKY sheet creation support server extracts work procedure information based on input work procedure information, identifies the risk content and the danger index of the risk content in the work procedure indicated by the work procedure information, and further identifies the countermeasure content and importance index for the risk content.The RKY sheet creation support server creates an RKY sheet (also simply referred to as a sheet) that includes the target facility information, on-site work name, input work procedure information, risk content, danger index, countermeasure content, importance index, and reevaluation risk score (the difference between the danger index and the importance index), and sends it to the terminal.The terminal displays the RKY sheet.

[0010] With this RKY sheet creation support system, users can check the risk details and countermeasure details for on-site work. In addition, workers can add risk details and countermeasure details that are not included in the extracted risk details and countermeasure details. The added risk details and countermeasure details are accumulated and organized, and then added to the database of the RKY sheet creation support server.

[0011] <Overall configuration of the RKY sheet creation support system> 1 is an overall configuration diagram of an RKY sheet creation support system 10 according to this embodiment. The RKY sheet creation support system 10 includes an RKY sheet creation support server 100 and a terminal 400. The RKY sheet creation support server 100 and the terminal 400 can communicate with each other via a network. There may be multiple terminals 400.

[0012] <Device configuration> 2 is a functional block diagram of the terminal 400 according to this embodiment. The terminal 400 is a computer, and includes a control unit 410, a storage unit 420, a communication unit 480, an operation unit 491, and a display unit 492. The control unit 410 includes a CPU (Central Processing Unit), and controls the terminal 400. The storage unit 120 includes storage devices such as a ROM (Read Only Memory), a RAM (Random Access Memory), and an SSD (Solid State Drive). The communication unit 480 includes a communication device, and transmits and receives communication data to and from the RKY sheet creation support server 100.

[0013] The operation unit 491 accepts an operation by a worker who is a user of the terminal 400, and outputs the operation content to the control unit 410. The input unit 411 included in the control unit 410 transmits input information input by the worker to the RKY sheet creation support server 100 via the communication unit 480. The input information includes target facility information that is the target of on-site work performed by the worker, the on-site work name, and input work procedure information. The input information may also include input environmental factor information that indicates the environment of the work site. The display unit 492 displays the RKY sheet received from the RKY sheet creation support server 100. Note that the terminal 400 may be in a form including a touch panel display in which the operation unit 491 and the display unit 492 are integrated.

[0014] As described above, the RKY sheet creation support system 10 includes the terminal 400, and the terminal 400 includes the input unit 411 that accepts input of target facility information, field work name, and input work procedure information. The input unit 411 accepts input of input environmental factor information, which is environmental factors including weather information related to weather and the like that affect input work procedure information.

[0015] <Configuration of RKY sheet creation support server> Returning to Fig. 1, a description will be given of the functional configuration of the RKY sheet creation support server 100. The RKY sheet creation support server 100 is a computer, and includes a control unit 110, a storage unit 130, and a communication unit 180. The communication unit 180 includes a communication device, and is capable of transmitting and receiving data to and from the terminal 400.

[0016] <RKY sheet creation support server: memory section> 3 shows data stored in the storage unit 130 according to this embodiment. The storage unit 130 includes storage devices such as a ROM, a RAM, and an SSD. The storage unit 120 stores an on-site operation database 210, a first risk database 230, a first measure database 240, a second risk database 250, a second measure database 260, a first dictionary table 270, a second dictionary table 280, an additional database 290, and a program 138.

[0017] There are one or more on-site work database 210, first risk database 230, first measure database 240, second risk database 250, and second measure database 260 for each facility that is the target of work (target facility information). Program 138 includes a description of the processing of RKY sheet creation support server 100 in the RKY sheet creation processing (see Figs. 12 to 15) described later.

[0018] <Memory section: On-site work database> Fig. 4 is a data configuration diagram of the on-site work database 210 according to this embodiment. The on-site work database 210 stores an on-site work table 211 and a work procedure table 221. Note that the on-site work table 211 and the work procedure table 221 shown in Fig. 4 are examples for a wind power generation facility.

[0019] The on-site work table 211 is data in tabular format, with one row (record) indicating an on-site work. A record in the on-site work table 211 includes columns (attributes) of work identification information 212 (shown as "work ID" in FIG. 4) and on-site work name 213. The work identification information 212 is identification information for the on-site work (related to the wind power generation facility). The on-site work name 213 is the name of the on-site work.

[0020] The work procedure table 221 is data in tabular format, with one row (record) indicating a work procedure for on-site work. A record in the work procedure table 221 includes columns (attributes) of work identification information 222 (referred to as "work ID" in FIG. 4), work procedure identification information 223 (referred to as "work procedure ID" in FIG. 4), and work procedure information 224. The work identification information 222 corresponds to the work identification information 212 in the on-site work table 211. The work procedure identification information 223 is identification information of a work procedure included in the on-site work (see on-site work name 213) corresponding to the work identification information 222. The work procedure information 224 indicates the contents of the work procedure. In the example of Figure 4, the field work called "master maintenance" is shown to include the work procedures "inside rotor inspection," "inside nacelle inspection," and "blade bolt tightening."

[0021] <Memory section: First risk database> Fig. 5 is a data configuration diagram of the first risk database 230 according to this embodiment. The first risk database 230 shown in Fig. 5 is an example for a wind power generation facility. The first risk database 230 is data in a table format, and one row (record) indicates a risk. The record of the first risk database 230 includes columns (attributes) of work procedure identification information 231 (described as "work procedure ID" in FIG. 5), risk identification information 232 (described as "risk ID" in FIG. 5), risk content 233 (also referred to as first risk content), possibility 234, severity 235, and risk index 236 (also referred to as first risk index). The work procedure identification information 231 corresponds to the work procedure identification information 223 of the work procedure table 221 (see FIG. 4), and indicates which work procedure the risk indicated by the record is related to.

[0022] Risk identification information 232 is information for identifying a risk. Risk content 233 is the content of the risk. Possibility 234 indicates the degree (probability) of risk occurrence, and the higher the degree of occurrence, the higher the numerical value. Severity 235 indicates the severity of the risk, and the higher the numerical value, the higher the severity. Risk index 236 indicates the degree of risk of the risk, and in this embodiment, is the sum of possibility 234 and severity 235. In the example of FIG. 5, the work procedure "inside rotor inspection" has a risk of "being caught in a rotating body," and the likelihood 234, severity 235, and risk index 236 are shown to be 3, 5, and 8, respectively.

[0023] <Memory section: First countermeasure database> Fig. 6 is a data configuration diagram of the first countermeasure database 240 according to this embodiment. The first countermeasure database 240 shown in Fig. 6 is an example for a wind power generation facility.

[0024] The first countermeasure database 240 is data in a table format, and one row (record) indicates a countermeasure for dealing with a risk. A record of the first countermeasure database 240 includes columns (attributes) of risk identification information 241 (written as "risk ID" in FIG. 6), countermeasure content 242 (also referred to as first countermeasure content), and importance index 243 (also referred to as first importance index).

[0025] The risk identification information 241 corresponds to the risk identification information 232 in the first risk database 230 (see FIG. 5), and indicates what risk the measure indicated by the record corresponds to. The measure content 242 is the content of the measure. The importance index 243 is a numerical value indicating the importance of the measure. In the example of FIG. 6, there are countermeasures for the risk of "being caught in a rotating body", namely "performing rotor lock" and "ensuring posture", and the importance index 243 for both of these is shown to be 5.

[0026] In this way, the on-site work name 213 and the work procedure information 224 are associated via the work identification information 212, 222 (see FIG. 4). The work procedure information 224 and the risk content 233 are associated via the work procedure identification information 223, 231 (see FIG. 4 and FIG. 5). Furthermore, the risk content 233 and the countermeasure content 242 are associated via the risk identification information 232, 241 (see FIG. 5 and FIG. 6). Based on the work procedure information 224, the related risk content 233 and countermeasure content 242 can be obtained.

[0027] As described above, the RKY sheet creation support server 100 provided in the RKY sheet creation support system 10 has the on-site work database 210 including the on-site work name 213 and work procedure information 224 based on the target facility information. The RKY sheet creation support server 100 has a first risk database 230 including a first risk content (see risk content 233) which is a risk content. The first risk database 230 includes, together with the first risk content, a first risk level index (see risk level index 236) indicating the magnitude of the risk according to the risk content. The RKY sheet creation support server 100 has a first measure database 240 including a first measure content (see measure content 242) which is a measure content. The first measure database 240 includes a first importance index (see importance index 243) indicating the magnitude of importance according to the measure content, together with the first measure content.

[0028] <<Memory unit: second risk database and second countermeasure database>> Fig. 7 is a data configuration diagram of the second risk database 250 according to this embodiment. The second risk database 250 shown in Fig. 7 is an example for a wind power generation facility. The second risk database 250 has a similar configuration to the first risk database 230 (see Fig. 5), but stores weather-related risks indicated by weather information as environmental factor information. For example, in the example of Fig. 7, risk content 253 (also referred to as second risk content) includes words such as "high temperature," "high humidity," "wind," and "gusts of wind."

[0029] Fig. 8 is a data configuration diagram of the second countermeasure database 260 according to this embodiment. The second countermeasure database 260 shown in Fig. 8 is an example for a wind power generation facility. The second countermeasure database 260 has a similar configuration to the first countermeasure database 240 (see Fig. 6), and stores countermeasures corresponding to weather-related risks (see second risk database 250 in Fig. 7).

[0030] The work procedure information 224 and the risk content 253 are associated with each other via the work procedure identification information 223, 251 (see Figs. 4 and 7). Furthermore, the risk content 253 and the countermeasure content 262 (also referred to as the second countermeasure content) are associated with each other via the risk identification information 252, 261 (see Figs. 7 and 8). Based on the work procedure information 224, the risk content 253 and the countermeasure content 262 related to the related weather can be obtained.

[0031] As described above, the RKY sheet creation support server 100 has the second risk database 250 including the second risk content (see risk content 253), which is the risk content. The second risk database 250 includes, together with the second risk content, a second risk index (see risk index 256) indicating the magnitude of the risk according to the risk content. The RKY sheet creation support server 100 has a second measure database 260 including second measure contents (see measure contents 262) which are measure contents. The second measure database 260 includes, together with the second measure contents, a second importance index (see importance index 263) indicating the magnitude of importance according to the measure contents.

[0032] <Memory section: First dictionary table> Fig. 9 is a data configuration diagram of the first dictionary table 270 according to this embodiment. The first dictionary table 270 stores words related to the target work parts to be worked on and the on-site work contents for the target work parts, which are included in the on-site work name 213 (see Fig. 4) and the work procedure information 224. The first dictionary table 270 is used to acquire related work procedure information from the input work procedure information input by the worker.

[0033] <Memory section: second dictionary table> Fig. 10 is a data configuration diagram of the second dictionary table 280 according to this embodiment. The second dictionary table 280 stores the codes related to the environment during work at the site, which are included in the risk contents 253 of the second risk database 250 (see Fig. 7). The second dictionary table 280 is used to acquire the risks related to the environment of the work site input by the worker.

[0034] As described above, the RKY sheet creation support server 100 provided in the RKY sheet creation support system 10 has the first dictionary table 270 including work target parts and on-site work contents for the work target parts. The RKY sheet creation support server 100 has a second dictionary table 280 including environmental factors.

[0035] <RKY sheet creation support server: control unit> 11 shows the functional units of the control unit 110 according to this embodiment. The control unit 110 includes a CPU. Based on the target equipment information transmitted from the terminal 400, the control unit 110 determines which of the on-site operation database 210, the first risk database 230, the first countermeasure database 240, the second risk database 250, and the second countermeasure database 260 is to be used to determine the work procedure information 224, the risk contents 233, 253, and the countermeasure contents 242, 262, from among the multiple on-site operation databases 210, the first risk database 230, the first countermeasure database 240, the second risk database 250, and the second countermeasure database 260. The control unit 110 includes a work procedure extraction unit 111, a risk identification unit 112, a countermeasure identification unit 113, a sheet creation unit 114, a judgment unit 115, and a billing unit .

[0036] As described above, the control unit 110 selects the site operation database 210, the first risk database 230, and the first measure database 240 based on the target facility information acquired from the input unit 411. The control unit 110 also includes a work procedure extraction unit 111, a risk identification unit 112, a countermeasure identification unit 113, and a sheet creation unit 114, and as described below, extracts necessary work procedure information 224 based on input work procedure information acquired from the input unit 411, identifies possible risk contents 233, 253 for the work procedure information 224, identifies countermeasure contents 242, 262 for the risk contents 233, 253, and creates a sheet that lists the target equipment information, the on-site work name, the input work procedure information, the identified risk contents 233, 253, and the identified countermeasure contents 242, 262.

[0037] <Control unit: Work procedure extraction unit> The work procedure extraction unit 111 includes a first extraction unit 121, a second extraction unit 122, a third extraction unit 123, and a fourth extraction unit 124. The first extraction unit 121 compares words included in the input work procedure information transmitted from the terminal 400 with words included in the first dictionary table 270, and extracts matching words. The second extraction unit 122 extracts work procedure information 224 (see FIG. 4) including the words extracted by the first extraction unit 121.

[0038] When input information transmitted from the terminal 400 includes input environmental factor information, which is information related to the environment of the work site, the third extraction unit 123 compares the words included in the input environmental factor information with the words included in the second dictionary table 280, and extracts matching words. The fourth extraction unit 124 extracts work procedure information 224 including the words extracted by the first extraction unit 121 from the work procedure information 224 corresponding to the risk content 253 (see FIG. 7) including the words extracted by the third extraction unit 123.

[0039] An example is shown below. Assume that the input work procedure information is "Inspect the rotor inside the nacelle." The first extraction unit 121 extracts "nacelle," "rotor," and "inspection" using the first dictionary table 270. Next, the second extraction unit 122 extracts "inside rotor inspection" and "inside nacelle inspection" from the work procedure information 224 in the on-site work database 210 selected by the control unit 110.

[0040] As described above, the control unit 110 includes the work procedure extraction unit 111 that extracts the work procedure information 224 corresponding to the input work procedure information from the multiple pieces of work procedure information 224 contained in the site work database 210. The work procedure extraction unit 111 includes a first extraction unit 121 that compares words included in the input work procedure information with words included in the work target parts or on-site work details for the work target parts in the first dictionary table 270, and extracts matching words. The work procedure extraction unit 111 includes a second extraction unit 122 that compares the words extracted by the first extraction unit 121 with work procedure information 224 in the on-site work database 210 and extracts work procedure information 224 that includes the extracted words.

[0041] The work procedure extraction unit 111 includes a third extraction unit 123 that compares words included in the input environmental factor information with words included in the environmental factors of the second dictionary table 280 and extracts matching words. The work procedure extraction unit 111 includes a fourth extraction unit 124 that compares the words extracted by the third extraction unit 123 with the second risk content (see risk content 253) corresponding to the work procedure information 224 extracted from the on-site work database 210, and extracts the work procedure information 224 that includes the matching words. The work procedure extraction unit 111 extracts work procedure information corresponding to the input work procedure information from the work procedure information 224 included in the on-site work database 210, and further extracts work procedure information corresponding to the input environmental factor information from the extracted work procedure information.

[0042] <Control Department: Risk Identification Department> First, the process of the risk identification unit 112 will be described when the information (input information) input to the input unit 411 (see FIG. 2) does not include input environmental factor information. The risk identification unit 112 identifies the risk content 233, which is the same work procedure identification information 231 as the work procedure identification information 223 of the work procedure information 224 identified by the work procedure extraction unit 111, from the first risk database 230 (see FIG. 5). In the example of FIG. 5, "getting caught in a rotating body" is identified as the risk content 233 corresponding to "inside roll inspection". Also, "getting an electric shock from touching a live part" is identified as the risk content 233 corresponding to "inside nacelle inspection". The risk identification unit 112 also identifies the possibility 234, the severity 235, and the danger index 236 in addition to the risk content 233.

[0043] Next, the process of the risk identification unit 112 when the input information includes input environmental factor information will be described. The risk identification unit 112 identifies risk content 253 that is the same work procedure identification information 251 as the work procedure identification information 223 of the work procedure information 224 identified by the work procedure extraction unit 111 and that includes the identified word from the second risk database 250 (see FIG. 7). If the input environmental factor information includes "high temperature", in the example of FIG. 7, "heatstroke will occur due to high temperature and humidity inside the rotor" is identified as the risk content 253 corresponding to "inside roll inspection". The risk identification unit 112 also identifies a possibility 254, a seriousness 255, and a risk index 256 in addition to the risk content 253.

[0044] As described above, the control unit 110 is equipped with a risk identification unit 112 that identifies a first risk content (see risk content 233) corresponding to the work procedure information 224 extracted by the work procedure extraction unit 111 from the multiple risk contents 233 contained in the first risk database 230. The risk identification unit 112 identifies the second risk content corresponding to the work procedure information 224 extracted by the work procedure extraction unit 111 from the second risk content (see risk content 253 ) included in the second risk database 250 .

[0045] <Control Unit: Countermeasure Identification Unit> First, the process of the countermeasure identification unit 113 in the case where the input information does not include input environmental factor information will be described. The countermeasure identification unit 113 identifies countermeasure contents 242 of risk identification information 241 that is the same as risk identification information 232 of risk contents 233 (see FIG. 5) from the first countermeasure database 240 (see FIG. 6). In the example of FIG. 6, "perform rotor lock" and "secure posture" are identified as countermeasure contents 242 corresponding to "get caught in a rotating body". Also, "voltage detection", "check current-carrying parts", and "use protective equipment" are identified as countermeasure contents 242 corresponding to "get electric shock by touching a current-carrying part". The countermeasure identification unit 113 also identifies an importance index 243 in addition to the countermeasure contents 242.

[0046] When the input information includes input environmental factor information, the countermeasure identification unit 113 identifies countermeasure contents 262 from the second countermeasure database 260 (see FIG. 8) in place of the first countermeasure database 240. In response to "heatstroke may occur due to high temperature and humidity inside the rotor", "wear an ice vest" and "replenish fluids" are identified as countermeasure contents 262.

[0047] As described above, the control unit 110 is equipped with a countermeasure identification unit 113 that identifies a first countermeasure content (see countermeasure content 242) corresponding to the first risk content (see risk content 233) identified by the risk identification unit 112 from the multiple countermeasure contents 242 included in the first countermeasure database 240. The countermeasure identification unit 113 identifies a second countermeasure content corresponding to the second risk content (see risk content 253) identified by the risk identification unit 112 from the second countermeasure content (see countermeasure content 262) included in the second countermeasure database 260.

[0048] <Control unit: Sheet creation unit> The sheet creation unit 114 creates an RKY sheet including the target facility information included in the input information, the field work name, the input work procedure information, the risk content identified by the risk identification unit 112, and the countermeasure content identified by the countermeasure identification unit 113, and transmits the RKY sheet to the terminal 400. The terminal 400 displays the received RKY sheet (see FIG. 20 described later).

[0049] <<Control unit: judgment unit and billing unit>> The determination unit 115 determines whether the input information input to the input unit 411 includes input environmental factor information. The billing unit 116 bills the worker, who is the user of the terminal 400, according to the number of times an RKY sheet is transmitted to the terminal 400. The billing unit 116 may also bill according to the period of use of the RKY sheet creation support server 100.

[0050] As described above, the control unit 110 is equipped with a sheet creation unit 114 that creates a sheet that describes the target equipment information, on-site work name, and input work procedure information acquired from the input unit 411, the first risk content (see risk content 233) identified by the risk identification unit 112, and the first countermeasure content (countermeasure content 242) identified by the countermeasure identification unit 113. The control unit 110 includes a determination unit 115 that determines whether or not input environmental factor information is present. The control unit 110 has a billing unit 116 that charges according to the number of times a sheet (RKY sheet) is sent to the terminal 400, or charges according to the period of use of the RKY sheet creation support system 10.

[0051] <RKY sheet creation process> 12 to 15 are flowcharts of the RKY sheet creation process according to this embodiment. The RKY sheet creation process is a process that starts with a search for risk contents and countermeasure contents using a search screen 520 (see FIG. 16) described later, and is a process that is repeated every time a search for risk contents and countermeasure contents is performed.

[0052] In step S11, the input unit 411 of the terminal 400 acquires, as input information from the worker who is the user of the terminal 400, target facility information that is the target of the on-site work, the on-site work name, input work procedure information, and input environmental factor information, and transmits the input information to the RKY sheet creation support server 100. This input information will be described below.

[0053] 16 is a diagram showing a search screen 520 on which input information according to this embodiment has been input. The search screen 520 is displayed on top of the RKY sheet display screen 510 displayed on the display unit 492 (see FIG. 2) of the terminal 400. The user inputs target facility information, which is the facility to be worked on, a site work name, which is the name of the work, input work procedure information, which includes the parts to be worked on and the work content, and input environmental factor information, which indicates the environment of the work site, in the "target facility", "work", "work content", and "environment" columns on the search screen 520.

[0054] Although no input environmental factor information is entered in Fig. 16, the worker may enter environmental information such as weather (climate) in the "Environment" column and include it in the input information. For example, regarding weather, the worker may check the temperature, humidity, precipitation, wind speed, heat index, etc. on the day of work (work time period) and enter risk factors such as "rain", "wind", "high temperature", and "high humidity". When the “Risk / Countermeasure Search” button is pressed after the input information is entered, the input information is transmitted to the RKY sheet creation support server 100.

[0055] Returning to FIG. 12, the description of the RKY sheet creation process will be continued. In step S12, the control unit 110 of the RKY sheet creation support server 100 determines, based on the target equipment information included in the input information, which of the multiple on-site work databases 210, first risk database 230, first countermeasure database 240, second risk database 250, and second countermeasure database 260 (see Figure 3) to refer to.

[0056] In step S13, if the input information includes input environmental factor information (step S13→YES), the determination unit 115 proceeds to step S31 (see FIG. 14), and if the input environmental factor information is not included (step S13→NO), the determination unit 115 proceeds to step S14. In step S14, the work procedure extraction unit 111 identifies the work procedure information 224 (see FIG. 4) based on the input work procedure information included in the input information.

[0057] In step S15, the risk identification unit 112 identifies the risk content 233, the possibility 234, the severity 235, and the risk index 236 corresponding to the work procedure information 224 identified in step S14. Since the input information does not include input environmental factor information (step S13→none), the risk identification unit 112 refers to the first risk database 230 (see FIG. 5).

[0058] In step S16, the countermeasure identification unit 113 identifies the countermeasure content 242 and the importance index 243 corresponding to the risk content 233 identified in step S15. Since the input information does not include input environmental factor information (step S13→none), the countermeasure identification unit 113 refers to the first countermeasure database 240 (see FIG. 6).

[0059] In step S17, the control unit 110 transmits to the terminal 400 the risk content 233, the possibility 234, the severity 235, the danger index 236, the countermeasure content 242, and the importance index 243 identified in steps S15 and S16. In step S18, control unit 410 of terminal 400 displays the risk details and countermeasure details received in step S17, and accepts the user's selection of the risk details and countermeasure details.

[0060] 17 is a diagram showing a search screen 530 on which risk details according to this embodiment are displayed. On the search screen 530, the risk details are displayed in parentheses along with the numerical values ​​of possibility 234, severity 235, and danger index 236 in the format of "likelihood + severity = danger index." From the displayed risk details, the worker selects a risk detail that is highly likely to occur during on-site work. In the following explanation, it is assumed that "being caught in a rotating body (3 + 5 = 8)" has been selected.

[0061] On the right side of the search screen 530, there are columns for "(A) Risk Content", "(B) Countermeasure Content", "(C) Reevaluation Risk Score", and "Work Permission Judgment". The "(A) Risk Content" column displays the danger index of the selected risk. The "(B) Countermeasure Content" column displays the importance index of the selected countermeasure. The "(C) Reevaluation Risk Score" column displays the reevaluation risk score, which will be described later. The "Work Permission Judgment" column displays the work permission judgment result (OK or NG). Since no risk or countermeasure has been selected on the search screen 530, the "(A) Risk Content", "(B) Countermeasure Content", and "(C) Reevaluation Risk Score" columns are left blank, and the "Work Permission Judgment" column displays the default value of "NG".

[0062] Fig. 18 is a diagram showing a search screen 540 on which countermeasure contents according to this embodiment are displayed. In the "Risk" field, "Being caught in a rotating body (3+5=8)" selected in the search screen 530 (see Fig. 17) is displayed. In addition, in the "(A) Risk Content" field, the danger level index (8) of the selected risk is displayed. The worker selects the countermeasures to be implemented in the work at the site from the countermeasures displayed corresponding to the selected risk. The search screen 540 displays the importance index value in parentheses along with the countermeasures. In the following explanation, we will assume that all of the displayed "Use rotor lock (5)," "Check rotation direction (5)," and "Thorough use of signals (5)" have been selected.

[0063] 19 is a diagram showing a search screen 550 displaying selected risk details and countermeasure details according to this embodiment. In the "Countermeasures" field, "Use of rotor lock (5)," "Checking rotation direction (5)," and "Comprehensive use of signals (5)," which were selected on search screen 540 (see FIG. 18), are displayed.

[0064] Additionally, the "(B) Measures content" column displays the sum of the importance indices of the measures. The "(C) Reevaluation risk score" column displays the reevaluation risk score obtained by subtracting the sum of the importance indices of the measures displayed in the "(B) Measures content" column from the risk danger index displayed in the "(A) Risk content" column. If the reevaluation risk score is 0 or less, it will be set to 1. The "Work permission judgment" column displays "OK" because the reevaluation risk score is 5 or less and the risk is deemed to be low.

[0065] The reevaluation risk score is calculated by the control unit 110 of the RKY sheet creation support server 100. To explain in detail, the control unit 410 transmits a risk danger index and a countermeasure importance index to the RKY sheet creation support server 100. The control unit 110 calculates the reevaluation risk score and transmits it to the terminal 400, and the control unit 410 displays the received reevaluation risk score in the "(C) Reevaluation risk score" column. After checking the selected risk content and countermeasure content, the operator presses the "Set" button, whereupon the control unit 410 proceeds to step S19 (see FIG. 12).

[0066] Returning to FIG. 12, the description of the RKY sheet creation process will be continued. In step S19, the control unit 410 transmits the selected risk content and countermeasure content to the RKY sheet creation support server 100.

[0067] In step S20, the sheet creation unit 114 creates an RKY sheet. The sheet creation unit 114 includes the target facility information, the field work name, and the input work procedure information included in the input information in the RKY sheet. The sheet creation unit 114 also includes the risk content 233 and the measure content 242 selected by the worker in step S18 from among the risk content 233 and the measure content 242 identified in steps S15 and S16 in the RKY sheet. The sheet creation unit 114 also includes the possibility 234, the severity 235, the risk index 236 corresponding to the risk content 233, and the importance index 243 corresponding to the measure content 242 in the RKY sheet. As described later, the sheet creation unit 114 calculates a reevaluation risk score and includes it in the RKY sheet (see FIG. 20).

[0068] In step S21, the control unit 110 transmits the RKY sheet created in step S20 to the terminal 400. In step S22, the control unit 410 displays the RKY sheet received in step S21.

[0069] FIG. 20 is a diagram showing an RKY sheet display screen 560 according to this embodiment. In the RKY sheet display screen 560, not only the risk factors (see the risk content 233 in FIG. 5) but also the values ​​of the possibility 234, the seriousness 235, and the risk index 236 (described as "total" in FIG. 20) are displayed. In addition, not only the measures (see the measure content 242 in FIG. 6) but also the value of the importance index 243 is displayed in parentheses. Furthermore, a reevaluation risk score obtained by subtracting the sum of the importance index 243 from the total (risk index 236) is displayed. If the reevaluation risk score is 0 or less, it is set to 1. In the example of FIG. 20, 8-(5+5+5)=-7, and the reevaluation risk score is 1. The reevaluation risk score is calculated by the sheet creation unit 114 (see step S20).

[0070] Moving to FIG. 13, the explanation of the RKY sheet creation process will continue. If there are no anticipated risks or measures on the RKY sheet display screen 560, the operator instructs them to be added. If there are no additions, the RKY sheet creation process related to the input information (see step S11) ends. Below, the explanation will continue assuming that there are additions. In step S23, if there is an instruction from the operator to add a risk or a measure, the control unit 410 displays a risk / measure addition screen 570 (see FIG. 21 described later) and receives the risk details and measure details to be added.

[0071] 21 is a diagram showing a risk and countermeasure addition screen 570 according to this embodiment. The operator inputs the risk content, possibility, and severity to be added, the countermeasure content for the risk, and the importance, and presses the "Set" button. Then, the control unit 410 proceeds to step S24.

[0072] Returning to FIG. 13, the explanation of the RKY sheet creation process will be continued. In step S24, the control unit 410 transmits the added risk details, countermeasure details, possibility, and the like to the RKY sheet creation support server 100.

[0073] In step S25, the control unit 110 associates the added risk content, countermeasure content, possibility, etc., and stores them in the additional database 290. The risk content and countermeasure content added to the additional database 290 are also referred to as set information. The set information may include the possibility, seriousness, and danger index corresponding to the risk content, and the importance index corresponding to the countermeasure content. The control unit 110 may store the set information in association with the target facility information, on-site work name, and input work procedure information included in the input information (see step S11).

[0074] In step S26, the sheet creation unit 114 creates an RKY sheet by adding the additional risk details and countermeasure details received in step S24 to the RKY sheet created in step S20 (see FIG. 12). In step S27, control unit 110 transmits the RKY sheet created in step S26 to terminal 400, and ends the RKY sheet creation process related to the input information (see step S11). In step S28, the control unit 410 displays the RKY sheet received in step S27.

[0075] 22 is a diagram showing an RKY sheet display screen 580 on which added risk contents and countermeasure contents according to this embodiment are displayed. The RKY sheet display screen 580 displays the reevaluation risk score calculated by the sheet creation unit 114 in addition to the risk contents, possibility, seriousness, countermeasure contents for the risk contents, and importance input on the risk / countermeasure addition screen 570 (see FIG. 21).

[0076] As described above, after the control unit 110 transmits the first risk content and the first countermeasure content, or the second risk content and the second countermeasure content to the terminal 400 (see steps S21, S38), if the control unit acquires a set of new risk content and countermeasure content from the terminal (see steps S24, S41), the control unit 110 transmits a sheet containing the set information to the terminal (see steps S27, S44), and registers the set information in the additional database 290 in association with the target equipment information, the on-site work name, and the input work procedure information.

[0077] Turning now to FIG. 14, the RKY sheet creation process in the case where there is input environmental factor information (YES in step S13) will be described. In step S31, the work procedure extraction unit 111 identifies the work procedure information 224 that corresponds to the input work procedure information and the input environmental factor information included in the input information (see step S11).

[0078] Steps S32 to S45 are the same as steps S15 to S28. However, in step S32, the risk identification unit 112 refers to the second risk database 250 (see FIG. 7) instead of the first risk database 230. Also, in step S33, the measure identification unit 113 refers to the second measure database 260 (see FIG. 8) instead of the first measure database 240.

[0079] <Features of the RKY sheet creation support system> The RKY sheet creation support system 10 identifies work procedure information based on input information including target facility information that is the subject of on-site work and on-site work name, identifies risk content related to the work procedure information, and further identifies countermeasure content. When input information includes input environmental factor information, the RKY sheet creation support system 10 extracts risk content related to the input environmental factor information, and further extracts countermeasure content.

[0080] The user selects risk contents and countermeasure contents from the extracted risk contents and countermeasure contents according to the on-site work. Risk contents are assigned a danger index, and countermeasure contents are assigned an importance index. The RKY sheet creation support system 10 calculates a reevaluation risk score by subtracting the numerical value of the importance index 243,263 of the selected countermeasure content from the numerical value of the danger index 236,256 of the selected risk content. By referring to this reevaluation risk score, the worker can know how much risk remains.

[0081] According to such an RKY sheet creation support system 10, the user can confirm the risk contents and countermeasure contents in the on-site work related to the facility. The user can also add risk contents and countermeasure contents that are not included in the extracted risk contents and countermeasure contents (see step S23 in FIG. 13 and step S40 in FIG. 15). The added risk contents and countermeasure contents are added to the first risk database 230, the second risk database 250, the first countermeasure database 240, and the second countermeasure database 260 after being accumulated and organized.

[0082] The first risk database 230, the second risk database 250, the first countermeasure database 240, and the second countermeasure database 260 are separated by the equipment (device) that is the target of on-site work. Therefore, when adding a target equipment, it is only necessary to add these databases, and it is possible to easily accommodate the new equipment. Also, since the databases are separated by equipment, it is possible to store risks and countermeasures corresponding to the equipment, and it becomes possible to perform appropriate risk assessment. Another advantage is that the maintenance of the databases is made easier.

[0083] <<Variation: User Authentication>> When receiving input information from the terminal 400, the RKY sheet creation support server 100 may authenticate the worker who is the user of the terminal 400, for example, by using a password. In such a case, the management ID and password of the worker are set in advance and stored in the storage unit 130. Note that the worker may be authenticated by using biometric information or encryption technology in addition to the password. Also, the terminal 400 may be authenticated instead of the worker. The terminal 400 (input unit 411) may perform the authentication instead of the RKY sheet creation support server 100. When setting new target equipment information, the control unit 110 may construct a field work database 210, a first risk database 230, a first countermeasure database 240, a second risk database 250, and a second countermeasure database 260 linked to the management ID.

[0084] As described above, when the input unit 411 accepts input of the target equipment information, the field work name, the input work procedure information, and the input environmental factor information, it requests input of a preset management ID and a password corresponding to the management ID. When setting new target facility information, the RKY sheet creation support system 10 constructs an on-site work database 210, a first risk database 230, a first countermeasure database 240, a second risk database 250, and a second countermeasure database 260 linked to the management ID.

[0085] <<Variation: Environmental Information>> In the above embodiment, the environmental information is the weather (climate), but it is not limited to this. For example, it may include the worker's work experience, physical strength, physical condition, etc. It may also be the presence or absence and type of other on-site work in the vicinity of the work site (for example, there is a risk of falling objects due to work on the upper floors, etc.).

[0086] Other variations Although several embodiments of the present invention have been described above, these embodiments are merely examples and do not limit the technical scope of the present invention. For example, the RKY sheet creation support server 100 and the terminal 400 may be integrated into one unit.

[0087] The present invention can take various other embodiments, and furthermore, various modifications such as omissions and substitutions can be made without departing from the gist of the present invention. These embodiments and modifications are included in the scope and gist of the invention described in this specification, etc., and are included in the scope of the invention described in the claims and their equivalents. [Explanation of symbols]

[0088] 10 RKY sheet creation support system 100 RKY sheet creation support server 110 Control section 111 Work procedure extraction unit 112 Risk Identification Department 113 Countermeasures Identification Department 114 Sheet Creation Department 115 Judgment Department 116 Billing Department 121 1st extraction part 122 Second extraction part 123 Third extraction part 124 4th extraction part 210 Field Work Database 224 Work procedure information 230 First Risk Database 233 Risk Content (First Risk Content) 236 Risk Index (First Risk Index) 240 First Countermeasures Database 242 Measures (First Measure) 243 Importance Index (First Importance Index) 250 Second Risk Database 253 Risk Content (Second Risk Content) 256 Risk Index (Second Risk Index) 260 Second Countermeasures Database 262 Measures (Second Measures) 263 Importance Index (Second Importance Index) 270 First Dictionary Table 280 Second Dictionary Table 290 additional databases 400 terminals 410 Control section 411 Input section 560 RKY sheet display screen (RKY sheet, sheet)

Claims

1. an input unit for receiving input of target facility information, a site work name, and input work procedure information; A control unit, The control unit is Extracting necessary work procedure information based on the input work procedure information acquired from the input unit; Identifying possible risk content for the work procedure information; Identify countermeasures for the risk, A sheet is created that describes the target equipment information, the on-site work name, the input work procedure information, the identified risk content, and the identified countermeasure content. The RKY sheet creation support system is characterized by the above.

2. 2. The RKY sheet creation support system according to claim 1, an on-site work database including the on-site work name and the work procedure information based on the target equipment information; a first risk database including a first risk content, which is the risk content; a first countermeasure database including a first countermeasure content, the first countermeasure content being the countermeasure content; The control unit is a work procedure extraction unit that extracts work procedure information corresponding to the input work procedure information from a plurality of pieces of work procedure information included in the on-site work database; a risk identification unit that identifies a first risk content corresponding to the work procedure information extracted by the work procedure extraction unit from a plurality of risk contents included in the first risk database; a countermeasure identification unit that identifies a first countermeasure content corresponding to a first risk content identified by the risk identification unit from a plurality of countermeasure contents included in the first countermeasure database; a sheet creation unit that creates a sheet on which the target facility information, the site work name, and the input work procedure information acquired from the input unit, the first risk content identified by the risk identification unit, and the first countermeasure content identified by the countermeasure identification unit are described. The RKY sheet creation support system is characterized by the above.

3. 3. The RKY sheet creation support system according to claim 2, the first risk database includes, together with the first risk content, a first risk index indicating a degree of risk corresponding to the risk content; The first countermeasure database includes, together with the first countermeasure content, a first importance index indicating a level of importance according to the countermeasure content. The RKY sheet creation support system is characterized by the above.

4. 4. The RKY sheet creation support system according to claim 3, The on-site operation database, the first risk database, and the first countermeasure database are selected based on the target facility information acquired from the input unit. The RKY sheet creation support system is characterized by the above.

5. 5. The RKY sheet creation support system according to claim 4, a first dictionary table including work target parts and on-site work contents for the work target parts; The work procedure extraction unit includes: a first extraction unit that compares a word included in the input work procedure information with a word included in the work target parts or the field work content for the work target parts in the first dictionary table, and extracts a matching word; a second extraction unit that compares the words extracted by the first extraction unit with work procedure information in the on-site work database and extracts work procedure information including the extracted words. The RKY sheet creation support system is characterized by the above.

6. 6. The RKY sheet creation support system according to claim 5, a second risk database including a second risk content, which is the risk content; a second countermeasure database including second countermeasure contents, the second countermeasure contents being the countermeasure contents; the input unit accepts input of input environmental factor information, which is an environmental factor including weather information related to weather or the like that affects the input work procedure information; The control unit includes a determination unit for determining whether or not the input environmental factor information is present, When the determination unit determines that input environmental factor information is present, The work procedure extraction unit includes: extracting work procedure information corresponding to the input work procedure information from the work procedure information included in the site work database, and further extracting work procedure information corresponding to the input environmental factor information from the extracted work procedure information; The risk identification unit identifies a second risk content corresponding to the work procedure information extracted by the work procedure extraction unit from the second risk content included in the second risk database, The measure identification unit identifies a second measure content corresponding to the second risk content identified by the risk identification unit from the second measure content included in the second measure database. The RKY sheet creation support system is characterized by the above.

7. 7. The RKY sheet creation support system according to claim 6, the second risk database includes, together with the second risk content, a second risk level index indicating a degree of risk corresponding to the risk content; The second countermeasure database includes, together with the second countermeasure content, a second importance index indicating a degree of importance according to the countermeasure content. The RKY sheet creation support system is characterized by the above.

8. The RKY sheet creation support system according to claim 7, a second dictionary table including environmental factors; The work procedure extraction unit includes: a third extraction unit that compares words included in the input environmental factor information with words included in the environmental factors of the second dictionary table and extracts matching words; a fourth extraction unit that compares the word extracted by the third extraction unit with the second risk content corresponding to the work procedure information extracted from the on-site work database, and extracts the work procedure information including the matching word. The RKY sheet creation support system is characterized by the above.

9. 9. The RKY sheet creation support system according to claim 1, A terminal including the input unit, The control unit transmits the created sheet to the terminal. The RKY sheet creation support system is characterized by the above.

10. The RKY sheet creation support system according to claim 9, The input unit requests input of a preset management ID and a password corresponding to the management ID when accepting input of the target equipment information, the field work name, the input work procedure information, and the input environmental factor information. The RKY sheet creation support system is characterized by the above.

11. The RKY sheet creation support system according to claim 9, The control unit has a charging unit that charges according to the number of times a sheet is sent to the terminal, or charges according to the period of use of the RKY sheet creation support system. The RKY sheet creation support system is characterized by the above.

12. The RKY sheet creation support system according to claim 9, An RKY sheet creation support system characterized by constructing a field work database linked to a management ID, a first risk database, a first countermeasure database, a second risk database, and a second countermeasure database when the target equipment information is newly set.

13. The RKY sheet creation support system according to claim 9, When the control unit acquires a set of new risk content and countermeasure content from the terminal after transmitting the first risk content and the first countermeasure content, or the second risk content and the second countermeasure content to the terminal, The control unit transmits a sheet on which the set information is described to the terminal, and registers the set information in an additional database in association with the target equipment information, the on-site work name, and the input work procedure information. The RKY sheet creation support system is characterized by the above.

Citation Information

Patent Citations

  • Information management system, information management method, and information management program

    JP2017045321A

  • Group confirmation activity support system, group confirmation activity support method, and group confirmation activity support program

    JP2019174945A

  • Head mount device, server device and work support system

    JP2020013192A

  • Danger prediction method and danger prediction device

    JP2020177380A

  • Risk information extraction system and risk information extraction model

    JP2022180150A