Tunnel progress output system

The tunnel progress output system automates the monitoring of tunnel excavation progress and cycle times using power operation data from construction machinery, enhancing accuracy and reducing CO2 emissions by optimizing ventilation equipment.

JP2024156313AActive Publication Date: 2024-11-06HAZAMA ANDO CORP +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023070672
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-04-24
Publication Date
2024-11-06
Estimated Expiration
2043-04-24

Smart Images

  • Figure 2024156313000001_ABST
    Figure 2024156313000001_ABST
Patent Text Reader

Abstract

To solve the problems associated with the conventional technology, that is, to provide a tunnel progress output system that can grasp the tunnel progress by determining individual processes (work types) more easily and with higher accuracy than the conventional technology.SOLUTION: A tunnel progress output system of the present invention is a system that selects one individual process from among multiple different individual processes performed in tunnel excavation based on a power supply operation of electric equipment provided on a construction machine, and outputs the progress status of the tunnel excavation based on an excavation cycle consisting of a series of multiple types of individual processes, and comprises trigger signal receiving means, selection means, and cycle number counting means. The cycle number counting means counts the number of cycles when a series of individual processes constituting an excavation cycle is selected.SELECTED DRAWING: Figure 3
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a technology for grasping the progress of tunnel excavation, and more specifically, to a tunnel progress output system that determines the type of work being carried out based on the power operation of electric equipment installed on construction machinery, thereby making it possible to grasp the progress of the tunnel. [Background technology]

[0002] It is said that roughly two-thirds of Japan's land area is mountainous, and as a result, roads and railway tracks (hereafter referred to as "roads, etc.") almost always have sections that pass through mountainous areas. To build roads, etc. in mountainous areas, it is common to employ either the cut earth method, which excavates part of the slope, or the tunnel method, which hollows out the interior of the natural ground. While the tunnel method tends to have a higher construction cost (construction cost per length of road, etc.) than the cut earth method, it also tends to require less excavated soil (i.e., the amount of soil discharged), and has the advantage of allowing greater freedom in the linear planning of roads, etc. (for example, shortcuts can be taken), and it is said that more than 10,000 tunnels have been constructed in Japan to date.

[0003] Until the 1970s, the main construction method for mountain tunnels was the "sheet pile method," which combined steel arch supports with wooden sheet piles to support the natural ground, but now the New Austrian Tunnelling Method (NATM), which actively utilizes the strength of the natural ground, has become mainstream. NATM's main feature is its design philosophy that relies on the strength of the natural ground (arch effect), which makes it possible to reduce the scale of the tunnel supports compared to the conventional sheet pile method, and also reduces construction costs because construction speed is improved.

[0004] In Japan, since NATM was first fully implemented, excavation technology has made great strides, and various auxiliary methods have been developed to enable it to handle a variety of ground conditions. Furthermore, advances in excavation machinery (particularly open-face excavators) have made it possible to choose mechanical excavation in addition to blasting excavation. Mechanical excavation generally requires the use of relatively low-strength concrete (for example, a uniaxial compressive strength of 49 N / mm 2 On the other hand, when the target ground contains bedrock, blasting excavation is often used.

[0005] Here, we will briefly explain the excavation procedure using NATM. First, the tunnel face is excavated. In the case of blasting excavation, a drill jumbo is used to drill a hole and load explosives (dynamite), and the workers and the drill jumbo evacuate before blasting. On the other hand, in the case of mechanical excavation, the tunnel face is cut by a free-profile excavator. The excavation length (1 span length) of one cycle varies depending on the support pattern set according to the strength of the ground, but generally excavation is performed with a span length of 1.0 to 2.0 m. After one span length is excavated, the debris is removed (debris removed) by a dump truck (or rail method) while "scrambling" is performed to remove unstable ground parts (loose stones, etc.). After the debris is removed, mirror spraying or primary concrete spraying is performed, and then steel supports are erected as necessary (depending on the support pattern), secondary concrete spraying is performed, and then rock bolts are installed. The primary concrete spraying work, secondary concrete spraying work, and rock bolting work will be carried out on the inner surface of the tunnel (the surface from the side wall to the top) for the length of the excavated span.

[0006] In this way, NATM is a construction method in which a series of processes (hereinafter referred to as "individual processes" for convenience) such as rock drilling (for example, drilling holes at the face and blasting), removal of debris, erection of steel supports, spraying concrete, and placing rock bolts are repeated to excavate one span (1.0 to 2.0 m) at a time. The flow of these individual processes is called the "excavation cycle," and the timetable for one excavation cycle is called the "cycle time." Each individual process that makes up the excavation cycle is a critical path. Therefore, understanding the work time required for these individual processes and analyzing the cycle time are extremely important for the efficiency of tunnel excavation. In other words, by analyzing the cycle time, it is possible to understand the excessiveness and waste in tunnel excavation, and as a result, it becomes possible to carry out appropriate cost management and schedule management based on actual results. For this reason, cycle time surveys are carried out at many tunnel excavation sites.

[0007] Conventionally, when investigating cycle time, that is, when measuring the construction time for each individual process (rock drilling, removal of debris, erection of steel supports, spraying concrete, placing rock bolts), investigators around the tunnel face would visually observe while measuring the time with a stopwatch or the like and record it in a field notebook, etc. In most cases, this investigation is carried out by construction managers or excavation workers (so-called miners), but this requires them to carry out the investigation while also working on other tasks and work, and there are also cases where data is not collected or is collected incorrectly, so checking and correction are necessary, which is a considerable burden of labor.

[0008] One way to deal with this is to automatically obtain the cycle time without having to station an investigator at the tunnel face. For example, by attaching an IC tag (such as RFID) to heavy machinery and obtaining log information from that IC tag, the cycle time can be obtained automatically. However, this method of using IC tags requires the installation of new equipment on the heavy machinery that will actually be in operation, and even if it can be implemented at a model site, it is not easy to apply it to all tunnel excavation sites in terms of installation costs and maintenance.

[0009] Another possible method for automatically obtaining cycle time is to use images. In other words, by automatically recognizing video and images of the tunnel face, the work situation at the tunnel face (by individual process) can be understood, and the time required for that work can be determined based on the time of the image. Machine learning such as deep learning can be used to automatically recognize images of the tunnel face, but with the current level of technology, it is not possible to correctly recognize construction machinery and other items when there is variation in the position and size within the image, and as a result, there is a problem in that the cycle time cannot be obtained accurately.

[0010] In addition, it is also possible to automatically obtain the cycle time based on the operating status of the construction machinery used in each individual process. For example, Patent Document 1 does not obtain the cycle time of tunnel excavation, but proposes a technology for grasping the operating history of construction machinery (e.g., a tire roller) based on the engine speed. [Prior art documents] [Patent documents]

[0011] [Patent Document 1] Patent Publication No. 2021-56938 Summary of the Invention [Problem to be solved by the invention]

[0012] The technology disclosed in Patent Document 1 considers that the tire roller is operating when the engine speed exceeds a threshold, and the continuous time exceeding this threshold is regarded as the operating time of the tire roller. In other words, the accuracy of the operating time to be estimated depends heavily on the threshold set in advance, in other words, the correct operating time cannot be obtained unless the threshold is set appropriately. In addition, when the technology of Patent Document 1 is applied to the acquisition of cycle time in tunnel excavation, different construction machines are used for each individual process, so it is necessary to set appropriate thresholds for each construction machine. However, it is more difficult to set appropriate thresholds for multiple types of construction machines, and even if the thresholds are set after performing tests in advance, it is difficult to think that the effect is worth the effort and cost. Furthermore, it is not uncommon for construction machines in tunnel excavation to be repeatedly operated and stopped even during work, and therefore the technology of Patent Document 1 may have the disadvantage of dividing one individual process (i.e., as two or more individual processes) and determining the operating time.

[0013] Since tunnel excavation progresses daily, the degree of tunnel excavation progress (hereinafter simply referred to as "tunnel progress") is constantly being checked. For example, the construction manager visits the tunnel face every morning and measures the excavation length using the numbers marked on the steel supports, and then returns to the management building or construction site office on the outskirts of the tunnel to record the tunnel progress, thereby sharing it within the construction site. Note that tunnel progress can be expressed as the cumulative number of excavation cycles repeated since the start of excavation, or as the tunnel excavation distance from the portal to the face (so-called Tunnel Distance: TD).

[0014] In this way, tunnel progress measurement, like cycle time investigation, is carried out by humans such as construction managers, which increases the workload and can lead to missed or incorrect measurements on a given day. Therefore, there was a demand for technology that could automatically measure tunnel progress without relying on construction managers.

[0015] In addition, the ventilation equipment consumes the most electricity during tunnel excavation, but it has been rare to operate the ventilation equipment while appropriately adjusting its output to reduce power consumption. For example, the ventilation equipment is designed to anticipate the resistance of the wind pipe against the maximum extension during tunnel excavation, and it was mainstream to operate it at approximately maximum output even if the length of the wind pipe (hereinafter simply referred to as the "wind pipe length") was still short. In recent years, there is a demand for reducing CO2 emissions due to the increasing enthusiasm for SDGs, and it is urgent to reduce CO2 emissions by reducing power consumption. Therefore, there was a demand for technology that can reduce CO2 emissions by estimating the wind pipe length by measuring the tunnel progress and operating the ventilation equipment while automatically adjusting the output appropriately after considering the pressure loss in the wind pipe length.

[0016] The object of the present invention is to solve the problems associated with the conventional technology, i.e., to provide a tunnel progress output system that can grasp the progress of a tunnel by determining individual processes (types of work) more easily and with greater accuracy than the conventional technology. [Means for solving the problem]

[0017] The present invention was made with a focus on determining the type of work for each individual process based on the power operation of the electric equipment installed on the construction machine, and is an invention based on an unprecedented idea.

[0018] The tunnel progress output system of the present invention is a system that selects one individual process from among a plurality of different individual processes performed in tunnel excavation based on the power operation of the electric equipment installed in the construction machine, and outputs the progress status of the tunnel excavation based on an "excavation cycle" consisting of a series of a plurality of types of individual processes, and is equipped with a trigger signal receiving means, a selection means, and a cycle number counting means. Among them, the trigger signal receiving means is a means for receiving a "trigger signal" related to the power operation of the electric equipment installed in the construction machine used for the individual process, and the selection means is a means for selecting an individual process based on the trigger signal received by the trigger signal receiving means. In addition, the cycle number counting means is a means for counting the number of cycles of one when a series of individual processes constituting the excavation cycle is selected, and counting the "accumulated cycle number" which is the cumulative total of the cycle numbers. In addition, the trigger signal receiving means receives a "start trigger signal" when a predetermined "specific electric equipment" among the electric equipment installed in the construction machine is turned on, and receives (detects) a "stop trigger signal" when the power ON of the specific electric equipment is released. In addition, the selection means selects an individual process based on the construction machine related to the trigger signal receiving means that received the trigger signal. This makes it possible to determine that the individual process selected by the selection means is the individual process currently being carried out at the tunnel face. Then, the cumulative number of cycles is output as the progress of the tunnel excavation.

[0019] The tunnel progress output system of the present invention may further include a support pattern estimation means and a pattern-specific excavation length setting means. The support pattern estimation means is a means for estimating a "support pattern", which is a type of excavation cycle, when a series of individual processes constituting an excavation cycle are selected. The pattern-specific excavation length setting means is a means for setting a "pattern-specific excavation length" according to the support pattern estimated by the support pattern estimation means. The support pattern estimation means estimates the support pattern based on the order of the support patterns planned in advance and the cumulative number of cycles. In this case, the "tunnel excavation distance" is output as the tunnel progress based on the pattern-specific excavation length set by the pattern-specific excavation length setting means.

[0020] The tunnel progress output system of the present invention may further include a cycle time calculation means, a support pattern estimation means, and a pattern-specific excavation length setting means. The cycle time calculation means is a means for calculating an "excavation cycle time" for an excavation cycle based on the work time for each individual process that constitutes the excavation cycle when a series of individual processes that constitute the excavation cycle are selected. In this case, the cycle number counting means counts one cycle number when a series of individual processes that constitute the excavation cycle are selected, and the selection means selects an individual process based on the construction machine related to the trigger signal receiving means that received the trigger signal, and calculates the work time for the individual process based on the reception time of the start trigger signal and the reception time of the stop trigger signal. The support pattern estimation means estimates the support pattern by comparing the excavation cycle time with the "standard excavation cycle time" for each support pattern set in advance. In this case, the "tunnel excavation distance" is output as the tunnel progress based on the pattern-specific excavation length set by the pattern-specific excavation length setting means.

[0021] The tunnel progress output system of the present invention may further include a schedule output means for outputting a "diagonal line schedule" showing the cumulative number of cycles and tunnel excavation distance (degree of progress of tunnel excavation) according to time on a graph consisting of a first axis (indicating the degree of progress of tunnel excavation) and a second axis (axis showing time).

[0022] The tunnel progress output system of the present invention may further include a wind duct length calculation means and an equipment control means. The wind duct length calculation means is a means for calculating the wind duct length, which is the length of the ventilation duct, based on the tunnel excavation distance. The equipment control means is a means for controlling a blower that blows air into the ventilation duct. The equipment control means calculates the pressure loss associated with the blowing of air based on the wind duct length, and adjusts the output of the blower in accordance with the pressure loss.

[0023] The tunnel progress output system of the present invention may further include an operation time measurement means and a CO2 emission calculation means. The operation time measurement means is a means for measuring the operation time of the blower that operates under the control of the equipment control means. The CO2 emission calculation means is a means for calculating the amount of CO2 emission associated with the operation of the blower by multiplying the operation time for each output of the blower by the CO2 emission amount per unit time that is preset for each output. Effect of the Invention

[0024] The tunnel progress output system of the present invention has the following advantages. (1)Without having to constantly station a cycle time inspector at the tunnel face, and even with a two-shift system, the cycle time can be obtained at any time, and the tunnel progress can be automatically output. As a result, the burden on construction managers and others is reduced, and the tunnel progress can always be grasped accurately and up-to-date. (2) When the output of the blower is adjusted taking into consideration the pressure loss calculated based on the air duct length, the power consumption of the blower can be reduced, which means that CO2 emissions can be reduced and environmental awareness of those involved in the construction can be raised. (3) When the support pattern is estimated and the excavation length for each pattern is selected according to the support pattern, the tunnel excavation distance can be output as the tunnel progress. (4) If the output of the ventilation equipment is adjusted taking into account the pressure loss calculated based on the air duct length, the power consumption of the ventilation equipment can be reduced, which means that CO2 emissions can be reduced and environmental awareness of those involved in the construction can be raised. (5) Conventionally, the type of face work was identified by phone or other means, or judged based on images or videos taken inside the mine. According to the present invention, the situation can be grasped in real time at a display position outside the mine. As a result, work that is easily affected by face work can be carried out smoothly inside the mine. For example, if the air pipe becomes an obstacle when moving the center (casting formwork), it is necessary to stop the ventilation equipment, but since the face situation can be grasped in real time, work can be carried out without unnecessary waiting time. [Brief description of the drawings]

[0025] [Figure 1] A model diagram that shows the relationship between individual processes, the machines used, and specific electric equipment. [Diagram 2] A model diagram showing the individual processes carried out in tunnel excavation, the machines used in each process, and examples of specific electric equipment set up for the machines. [Diagram 3] FIG. 1 is a block diagram showing the main configuration of a tunnel progress output system according to the present invention. [Figure 4] A model diagram showing the relationship between usage time, correction time, and work time. [Diagram 5] A model diagram showing the relationship between five pre-set support patterns, the work times for five individual processes, and the standard excavation cycle time. [Figure 6] A model diagram showing the pre-set "excavation progress length for each support pattern." [Figure 7] A model diagram showing a "diagonal line schedule." [Figure 8] FIG. 4 is a flow chart showing the flow of main processes until the tunnel progress output system of the present invention calculates the work time. [Figure 9] FIG. 2 is a flow chart showing the main process flow up to when the tunnel progress output system of the present invention calculates the amount of CO2 emissions. [Figure 10]1(a) is a model diagram that shows a schematic representation of the "operating state" and "idle state" of a specific electrically-driven device, and 1(b) is a model diagram that shows a schematic representation of an individual process being selected according to a combination of the operating state and the idle state. [Figure 11] A model diagram showing the selection of individual processes according to a combination of trigger signals from different machines used. [Figure 12] 1 is a flow diagram showing the main steps of a tunnel progress output method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0026] An embodiment of the tunnel progress output system of the present invention will be described with reference to the drawings.

[0027] 1.Overview The present invention focuses on the fact that different types of construction machines are used for each "individual process" such as excavating the face, removing debris, erecting steel supports, spraying concrete, and driving rock bolts, and also focuses on the power supply operation of the electric equipment installed on the construction machines. Note that a construction machine may be equipped with multiple types of electric equipment, and the electric equipment to be focused on is set in advance. For convenience, the electric equipment to be focused on will be referred to as "specific electric equipment" and the construction machine used for an individual process will be referred to as "machine used."

[0028] FIG. 1 is a model diagram showing the relationship between an individual process, a using machine, and a specific electric device. In this diagram, three individual processes (individual processes 01 to 03) are shown. For example, in the individual process 01, a using machine A is used, and a specific electric device A is set among the electric devices provided in this using machine A. The using machine A is equipped with a trigger signal receiving means A that receives a signal (hereinafter referred to as a "trigger signal") when the specific electric device A is turned on. More specifically, the trigger signal receiving means A connected to the specific electric device A receives a trigger signal (hereinafter particularly referred to as a "start trigger signal") when the specific electric device A is turned on, and detects the timing when the power ON of the specific electric device A is released, that is, the situation when the power is switched from ON to OFF. Note that the information detected by the trigger signal receiving means when the power ON of the specific electric device is released (the power is turned OFF) is particularly referred to as a "stop trigger signal", and for convenience, the detection of this stop trigger signal by the trigger signal receiving means is referred to as "receiving" the stop trigger signal.

[0029] In the individual process 01, one specific electric device A is set for the using machine A, but it is not limited to this and two or more types of specific electric devices can be set for one using machine. For example, in the individual process 02, the using machine B is used, and specific electric devices B1 and B2 are set among the electric devices provided on the using machine B. The using machine B is equipped with trigger signal receiving means B1 that receives a trigger signal from the specific electric device B1, and trigger signal receiving means B2 that receives a trigger signal from the specific electric device B2.

[0030] In addition, in individual process 01 and individual process 02, one user machine (user machine A or user machine B) is used in one individual process, but two or more types of user machines may be used depending on the type of work in the individual process. In this case, it is advisable to set a specific electric device for each user machine. For example, in individual process 03, user machine C and user machine D are used, specific electric device C is set among the electric devices provided on user machine C, and specific electric device D is set among the electric devices provided on user machine D. Then, user machine C is equipped with trigger signal receiving means C that receives a trigger signal from specific electric device C, and user machine D is equipped with trigger signal receiving means D that receives a trigger signal from specific electric device D.

[0031] In this way, one trigger signal receiving means is connected to one specific electric device. Therefore, if the trigger signal receiving means can be identified, the specific electric device can be identified, that is, the machine in which the specific electric device is installed can be identified, and as a result, the individual process related to the machine in which the specific electric device is installed can be determined. In identifying the trigger signal receiving means, an identifier (ID: IDentification) that can be distinguished from others can be given to the trigger signal receiving means in advance, and a trigger signal that combines this identifier can be handled. The trigger signal receiving means is connected to an electric cord related to the power supply operation of the specific electric device, and is thus in a state in which it can receive an ON / OFF (on / off) trigger signal from a relay on the specific electric device side. In this case, since the trigger signal is an analog signal, the trigger signal receiving means converts it into a digital signal (A / D conversion), and at this time, it is preferable to give the identifier of the trigger signal receiving means to the digital signal.

[0032] As described above, the trigger signal receiving means receives the start trigger signal and the stop trigger signal as trigger signals. Therefore, by using the start trigger signal and the stop trigger signal, it is possible to estimate the time that a specific electric device has been operating, that is, the time that a used machine in which the specific electric device is installed has been operating, and as a result, it is possible to estimate the time that an individual process related to that used machine has been performed (hereinafter referred to as "work time"). In other words, by using the trigger signal received by the trigger signal receiving means, it is possible to determine the individual process being performed (or has been performed) at the tunnel face, and also to estimate the work time of that individual process.

[0033] Figure 2 is a model diagram showing an example of individual processes performed in tunnel excavation, the machines used in each individual process, and the specific electric equipment set for the machines used. In this example, an "excavation cycle" is shown, which is composed of a combination of "face excavation", "slide removal", "primary concrete spraying", "steel support construction", "secondary concrete spraying", and "rock bolt installation", and is performed in the order shown in the figure. In the face excavation, in the case of mechanical excavation, a "twin header (free cross-section excavator)" is set as the machine used and its "headlight" is set as the specific electric equipment, and in the case of blasting excavation, a "drill jumbo" is set as the machine used and its "hydraulic pump" is set as the specific electric equipment. In addition, in the case of drift removal, a "side dump" for loading drift is set as the machine used and its "headlight" is set as the specific electric equipment. In other words, the machines used and the specific electric equipment are set for the face excavation and drift removal shown in this figure in the pattern of "individual process 01" shown in Figure 1.

[0034] In addition, for the first concrete spraying, steel shoring erection, and second concrete spraying, a "concrete spraying machine (with erector)" is set as the machine to be used, and its "compressor" and "hydraulic pump" are set as specific electric equipment. The compressor of the concrete spraying machine is used when spraying the concrete, while the hydraulic pump is used both when spraying the concrete (moving the boom) and when erecting the steel shoring (moving the erector). In other words, for the first concrete spraying, steel shoring erection, and second concrete spraying shown in this figure, the machines to be used and specific electric equipment are set in the pattern of "individual process 02" shown in Figure 1. Of course, this is not the only example, and it is also possible to set only the "compressor" as the specific electric equipment for the first concrete spraying and second concrete spraying, and only the "hydraulic pump" as the specific electric equipment for the steel shoring erection.

[0035] Furthermore, in rock bolting, a "jumbo drill" and a "mortar injection pump" are set as the machines to be used, and the "hydraulic pump" of the jumbo drill is set as the specific electric equipment, and the "electric motor" of the mortar injection pump is set as the specific electric equipment. In rock bolting, the jumbo drill is used to drill holes for the rock bolts and insert them, while the mortar injection pump is used to inject mortar into the rock bolt holes. In other words, the rock bolting shown in this figure has the machines to be used and the specific electric equipment set in the pattern of "individual process 03" shown in Figure 1. Of course, this is not the only example, and in rock bolting, the "jumbo drill" can be set as the only machine to be used, and its "hydraulic pump" can be set as the specific electric equipment.

[0036] 2.Tunnel progress output system Next, the tunnel progress output system of the present invention will be described in detail.

[0037] 3 is a block diagram showing the main components of the tunnel progress output system 100 of the present invention. As shown in this figure, the tunnel progress output system 100 of the present invention is configured to include trigger signal receiving means 101, selection means 102, and cycle number counting means 103, and can also be configured to include support pattern estimating means 104, pattern-specific excavation length setting means 105, cycle time calculation means 106, process table output means 107, wind pipe length calculation means 108, equipment control means 109, operation time measurement means 110, CO2 emission calculation means 111, output means 112, communication device 113, process display control means 114, process display means 115, correction time storage means 116, support pattern storage means 117, standard cycle time storage means 118, excavation length storage means 119, etc.

[0038] Among the main elements constituting the tunnel progress output system 100, the selection means 102, the cycle counting means 103, the support pattern estimation means 104, the excavation length setting means by pattern 105, the cycle time calculation means 106, the schedule output means 107, the wind pipe length calculation means 108, the equipment control means 109, the operation time measurement means 110, the CO2 emission calculation means 111, and the schedule display control means 114 can be manufactured as dedicated means or can use general-purpose computer devices. That is, the computer devices execute arithmetic processing by a predetermined program, thereby performing processing specific to each means. The computer devices include a processor such as a CPU, memories such as a ROM and a RAM, and some further include input means such as a mouse and a keyboard, and a display, and can be configured, for example, by a personal computer (PC) or a server. If the computer device includes a display, the display can also be used as the output means 112.

[0039] In addition, the correction time storage means 116 for storing the "correction time" described later, the support pattern storage means 117, the standard cycle time storage means 118, and the excavation length storage means 119 can use a storage device of a general-purpose computer or can be built in a database server. When built in a database server, they can be placed in a local network (LAN: Local Area Network) or can be a cloud server that stores data via the Internet (i.e., wireless communication).

[0040] Below, each of the main components of the tunnel progress output system 100 will be described in detail.

[0041] (Trigger signal receiving means) As described above, the trigger signal receiving means 101 is mounted on the machine to be used and connected to the specific electric device to receive trigger signals (start trigger signal and stop trigger signal) from the specific electric device. More specifically, by connecting the trigger signal receiving means to an electric cord related to the power supply operation of the specific electric device, the trigger signal receiving means detects the presence or absence of current caused by the opening and closing of a relay on the specific electric device side, thereby receiving a trigger signal for turning the power supply ON / OFF (on / off) on the specific electric device side. The trigger signal receiving means 101 also converts the received analog trigger signal into a digital signal (A / D conversion), assigns an identifier of the trigger signal receiving means 101 to the digital signal, and can also temporarily (or non-volatilely) store the trigger signal and the identifier.

[0042] (Communication Equipment) The communication device 113 is installed in the tunnel and transmits the trigger signal received by the trigger signal receiving means 101 to the selection means 102, and is a so-called access point using WiFi (registered trademark) or the like. Therefore, the communication device 113 and the selection means 102 are connected wirelessly (or wired), and the communication device 113 and the trigger signal receiving means 101 are also connected wirelessly (or wired). Therefore, when the communication device 113 is installed, the selection means 102 can receive the trigger signal in real time, and the subsequent processing (for example, selection of an individual process) can also be performed in real time. It is also possible to omit the communication device 113 and store the trigger signal and the identifier in the trigger signal receiving means 101, but in that case, it is difficult to perform processing such as selection of an individual process in real time, and it is judged after the fact. In other words, if the communication device 113 is installed, it is possible to grasp the individual process currently being performed at the tunnel face, but if the communication device 113 is omitted, the cost can be reduced, but it is only possible to grasp the individual process after it has been performed.

[0043] (Selection method) The selection means 102 is a means for receiving a trigger signal and selecting an individual process using the received trigger signal, and can also calculate the work time of the individual process based on the received start trigger signal and stop trigger signal. More specifically, the selection means 102 identifies a specific electric device by an identifier included in the trigger signal, identifies a machine to which the specific electric device is attached, and selects an individual process related to the machine to be used from among a plurality of individual processes constituting the excavation cycle. At this time, since the order of execution of the individual processes constituting the excavation cycle is determined, it is also possible to select an individual process based on the immediately preceding individual process. Furthermore, the selection means 102 calculates a part (or all) of the period from the start point to the end point as the work time of the individual process, taking the time when the start trigger signal is received as the starting point and the time when the stop trigger signal is received as the end point. The selection means 102 can be installed inside the tunnel, but it is preferable to install it in a relatively well-equipped environment such as a management building or a construction site office on the outskirts of the tunnel.

[0044] (Process display control means) The process display control means 114 displays the individual process selected by the selection means 102 on the process display means 115. The process display means 115 is installed around the tunnel entrance and is, for example, an electronic bulletin board that displays the individual process currently being carried out at the tunnel face. Alternatively, it can be designed to display the individual process of the previous process and the subsequent process together with the individual process being carried out. By displaying the individual process being carried out, it is possible to guide people other than those involved, such as visitors, so that in the case of dangerous work, entry into the tunnel is avoided, thereby improving safety. In addition, workers waiting outside the tunnel can make appropriate preparations for the subsequent process and can efficiently work on the next process. The process display control means 114 is preferably installed in the same place as the selection means 102 (for example, in a management building or a construction site office).

[0045] (Correction time storage means) As described above, the selection means 102 takes the time when the start trigger signal is received as the starting point and the time when the stop trigger signal is received as the ending point, and calculates a part (or all) of the period from the starting point to the ending point as the working time of the individual process. However, depending on the individual process, there may be a time period that is not suitable as working time for the individual process, such as the time when the machine used is moved or the time required for various preparations. Therefore, it is preferable to set the "inappropriate time" for each individual process in advance as a "correction time (can be set positive or negative)" and store this correction time in the correction time storage means 116. In this case, the selection means 102 calculates the working time after taking the correction time into consideration. More specifically, the selection means 102 queries the correction time storage means 116 for the individual process selected by the selection means 102, and reads out the correction time related to the individual process from the correction time storage means 116. As shown in Figure 4, the time from when the start trigger signal is received (starting point) to when the stop trigger signal is received (ending point) is regarded as the "usage time" of the machine in use, and the "operation time" is calculated by subtracting the correction time from this usage time. Of course, a different correction time can be set for each individual process, and it is also possible not to set a correction time for a specific individual process.

[0046] (Method of counting cycles) The cycle count counting means 103 is a means for counting the "cycle count" of 1 when a series of individual processes constituting an excavation cycle is selected, and can also count the "accumulated cycle count" which is the cumulative total of the cycle counts from the start of excavation. As described above, an excavation cycle is composed of a series of multiple types of individual processes, and of course the order in which they are performed is also predetermined. For example, the excavation cycle shown in FIG. 2 is composed of the individual processes of "face excavation", "sludge removal", "primary concrete spraying", "steel shoring construction", "secondary concrete spraying", and "rock bolt installation", and is performed in that order. Therefore, when a series of individual processes are selected by the selection means 102, the cycle count counting means 103 counts the cycle count of 1 and counts the cumulative cycle count. For example, in the case of FIG. 2, when "face excavation" to "rock bolt installation" are selected by the selection means 102, the cycle count counting means 103 counts the cycle count and the cumulative cycle count. The cycle number counting means 103 may be designed to count the cycle number automatically as described above, or may be designed to count the cycle number through an operator's operation.

[0047] (Cycle time calculation means) The cycle time calculation means 106 is a means for calculating an "excavation cycle time" when a series of individual processes constituting an excavation cycle is selected (i.e., when the cycle number counting means 103 counts one cycle number). Here, the excavation cycle time means the construction time required for one excavation cycle, that is, the sum of the work times related to the individual processes constituting the excavation cycle. The cycle time calculation means 106 calculates the excavation cycle time based on the work times related to the individual processes calculated by the selection means 102.

[0048] (Support pattern estimation means) The support pattern estimation means 104 is a means for estimating the "support pattern (i.e., the type of excavation cycle)" of an excavation cycle when a series of individual processes constituting the excavation cycle is selected (i.e., when the cycle number counting means 103 counts the cycle number of 1). When carrying out tunnel excavation, a geological survey and detailed design are carried out in advance, and a tunnel plan longitudinal section showing the length of each support pattern is created. In other words, the support pattern for each excavation cycle arranged in order from the tunnel portal is set in advance, and if the cumulative cycle number is known, the support pattern in the plan corresponding to that excavation cycle (the excavation cycle added last) can be grasped. More specifically, a table (hereinafter referred to as the "support pattern table") in which combinations of "excavation cycle and support pattern" are arranged in order from the tunnel portal is stored in the support pattern storage means 117 (FIG. 3), and the cumulative cycle number counted by the cycle number counting means 103 is referred to the support pattern storage means 117 to read the support pattern corresponding to the cumulative cycle number. Of course, if any design changes are made during tunnel excavation, the support pattern table can be modified by the operator each time.

[0049] The support pattern estimation means 104 can estimate the support pattern based on the "excavation cycle time" instead of (or in addition to) estimating the support pattern based on the cumulative cycle number. A standard excavation cycle time (hereinafter simply referred to as "standard excavation cycle time") for each support pattern can be set based on the past construction records of other tunnels of the same scale and the records up to the middle of the tunnel. For example, in Fig. 5, the relationship between five types of support patterns (D2 pattern, D1 pattern, C2 pattern, C1 pattern, B pattern), the work time for five types of individual processes (face excavation and removal of piles, primary concrete spraying, steel support construction, secondary concrete spraying, rock bolt installation), and the standard excavation cycle time is preset.

[0050] In this case, if the excavation cycle time can be obtained, the support pattern can be estimated from the standard excavation cycle time that is close to (or coincides with) the excavation cycle time. More specifically, a table consisting of combinations of "support patterns and standard excavation cycle times" (hereinafter referred to as the "standard time table") is stored in the standard cycle time storage means 118 (Fig. 3), and the excavation cycle time calculated by the cycle time calculation means 106 is referenced to the standard cycle time storage means 118 to extract the standard excavation cycle time that is close to (or coincides with) the excavation cycle time, and the support pattern corresponding to the standard excavation cycle time is read out. Of course, whenever the standard time table is reviewed during tunnel excavation, the standard time table should be revised by the operator.

[0051] (Means for setting excavation length by pattern) The pattern-specific excavation length setting means 105 is a means for setting a "pattern-specific excavation length" according to the support pattern estimated by the support pattern estimation means 104. Here, the pattern-specific excavation length is the excavation progress length (one span length) of one excavation cycle (one cycle), and is the excavation progress length for each support pattern. This pattern-specific excavation length is generally set to 1.0 to 2.0 m as shown in FIG. 6. In other words, when the support pattern is estimated by the support pattern estimation means 104, the pattern-specific excavation length corresponding to the excavation cycle can be grasped. More specifically, a table (hereinafter referred to as a "standard excavation length table") consisting of "excavation progress length for each support pattern (i.e., excavation length for each pattern)" as shown in FIG. 6 is stored in the excavation length storage means 119 (FIG. 3), and the support pattern estimated by the support pattern estimation means 104 is referred to in the excavation length storage means 119 to read out the pattern-specific excavation length corresponding to the support pattern. Then, the pattern-specific excavation length setting means 105 calculates the "tunnel excavation distance", which is the pattern-specific excavation length accumulated from the start of excavation (that is, the distance from the tunnel portal to the current tunnel face).

[0052] (Process table output means) The schedule output means 107 is a means for outputting the "diagonal line schedule" to the output means 112 (FIG. 3) such as a display. Here, the diagonal line schedule is a graph consisting of two orthogonal axes, which shows the tunnel excavation distance as a function of time. For example, in FIG. 7, the horizontal axis shows the tunnel excavation distance, and the vertical axis shows the elapsed time from the start of excavation, and the diagonal line schedule is generated by plotting the tunnel excavation distance as a function of the elapsed time. In addition to the tunnel excavation distance, the diagonal line schedule in FIG. 7 also shows the invert construction distance, waterproofing construction distance, and lining concrete construction distance. Note that, considering that both the tunnel excavation distance and the cumulative cycle count are values ​​that indicate the progress of tunnel excavation, the diagonal line schedule can also be generated using the cumulative cycle count instead of the tunnel excavation distance.

[0053] (Wind pipe length calculation means) The wind duct length calculation means 108 is a means for calculating the "wind duct length" based on the tunnel excavation distance calculated by the pattern-specific excavation length setting means 105. Here, the wind duct length is the current length of the ventilation wind duct installed. Therefore, as the tunnel face advances, the wind duct length also changes sequentially. When the wind duct length calculation means 108 calculates the wind duct length, the tunnel excavation distance calculated by the pattern-specific excavation length setting means 105 is used as a reference, and the tunnel excavation distance can be used as the wind duct length as is, or the wind duct length can be calculated by subtracting a predetermined length (e.g., 10 m) from the tunnel excavation distance.

[0054] (Facility Control Means) The equipment control means 109 adjusts the output of the blower that sends air to the air pipe inside the tunnel and the dust collector installed inside the tunnel. At the tunnel face, which is the main work area for miners, the environment (especially the air environment) varies greatly depending on the type of work. For example, the environment is not so bad when erecting steel supports, but on the other hand, when excavating the face or spraying concrete, a lot of dust is generated and the environment becomes poor. In other words, it is desirable to operate the blower and dust collector with varying strength according to the type of work. Therefore, the equipment control means 109 adjusts the output of the blower and dust collector according to the individual process selected by the selection means 102. For example, when the selection means 102 selects steel support construction as an individual process, the equipment control means 109 may operate the blower and dust collector at a relatively low output, and when the selection means 102 selects face excavation or concrete spraying as an individual process, the equipment control means 109 may operate the blower and dust collector at a relatively high output. Note that the equipment control means 109, like the process display control means 114, may be installed in the same place as the selection means 102 (for example, in an administration building or a construction site office).

[0055] The equipment control means 109 can also adjust the output of the ventilation equipment (particularly, the blower such as a blower) based on the air duct length calculated by the air duct length calculation means 108. The longer the air duct length, the greater the pressure loss. Naturally, the size of the blower is planned based on the air duct length just before the tunnel is penetrated, and therefore, when the air duct length reaches a considerable extent, the blower operates at nearly maximum output. In other words, when the air duct length is still short, it is not necessary to operate the blower at such a high output. Therefore, the equipment control means 109 may calculate the pressure loss associated with blowing air based on the air duct length and adjust the output of the blower according to the pressure loss. For example, when a blower that operates at three levels of output is used, the equipment control means 109 selects one of the three levels in consideration of the calculated pressure loss and operates the blower.

[0056] (Method of measuring operating time) The operation time measurement means 110 is a means for measuring the operation time of the blower, which is attached to the blower and operates under the control of the equipment control means 109. The operation time measurement means 110 can measure the operation time by dividing it into the magnitude of the blower's output (for example, three levels of output). Alternatively, the operation time measurement means 110 can be attached to various devices and equipment used in the construction site other than the blower to measure the operation time of these devices, etc.

[0057] (Method of calculating CO2 emissions) The CO2 emission calculation means 111 is a means for calculating the amount of CO2 emission accompanying the operation of the blower by multiplying the operation time of the blower measured by the operation time measurement means 110 by the "amount of CO2 emission per unit time". This amount of CO2 emission per unit time is set in advance for each output (e.g., three levels of output) of the blower. Therefore, the CO2 emission calculation means 111 multiplies the operation time for each output (e.g., three levels of output) measured by the operation time measurement means 110 by the amount of CO2 emission per unit time corresponding to that output, and calculates the CO2 emission by summing them up. In addition, when the operation time of various devices, etc. is measured by the operation time measurement means 110, the amount of CO2 emission accompanying the operation of the devices, etc. can also be calculated by multiplying the operation time of these devices, etc. by the "amount of CO2 emission per unit time". In this case, however, it is advisable to set the amount of CO2 emission per unit time for each device or equipment.

[0058] The main process flow when using the tunnel progress output system 100 of the present invention will be described with reference to Figures 8 and 9. Figure 8 is a flow diagram showing the main process flow up to when the tunnel progress output system 100 calculates the work time, and Figure 9 is a flow diagram showing the main process flow up to when the tunnel progress output system 100 calculates the CO2 emission amount. In Figures 8 and 9, the central column shows the process to be performed, the left column shows the input information required for that process, and the right column shows the output information resulting from that process.

[0059] For example, when a miner turns on the power supply of the headlights of a twin header (or road header), the trigger signal receiving means 101 receives a start trigger signal (Step 201 in FIG. 8). The selection means 102 can select an individual process at the timing when the start trigger signal is received, but it is preferable to wait for a certain period of time after receiving the start trigger signal in order to eliminate noise such as operational errors (Step 202 in FIG. 8). Then, when a predetermined certain period of time has passed (Yes in Step 203 in FIG. 8), the process proceeds to the subsequent process, and if the certain period of time has not passed (No in Step 203 in FIG. 8), the process continues to wait.

[0060] When a certain period of time has elapsed after receiving the start trigger signal, the selection means 102 selects an individual process from among the multiple individual processes that make up the excavation cycle based on the trigger signal (start trigger signal) (Step 204 in FIG. 8). At this time, it is advisable to make the selection by referring to the individual process selected as the previous process. For example, when a start trigger signal related to the headlights (specific electric equipment) of a side dump (machine used) is received, it is confirmed that face excavation has been selected as the previous process, and then sludge removal is selected as an individual process. Incidentally, in the case of the pattern of "individual process 01" shown in FIG. 1, the selection means 102 can identify 1 specific electric equipment and 1 machine used, but in the patterns of "individual process 02" and "individual process 03" shown in FIG. 1, multiple pieces of information are obtained, so that the individual process can be selected by various methods.

[0061] For example, in the pattern of individual process 02, multiple specific electric devices are set for the machine to be used in 1, so multiple trigger signals can be used. In this case, it is advisable to select an individual process after determining the "operating state" and "pause state" of each specific electric device. Figure 10(a) is a model diagram that shows the "operating state" and "pause state" of a specific electric device, and Figure 10(b) is a model diagram that shows the selection of an individual process according to a combination of the operating state and the pause state. As shown in this figure, the period from the reception time of a start trigger signal to the reception time of a stop trigger signal related to the same specific electric device is considered to be an "operating state," and the period from the reception time of a stop trigger signal to the reception time of the next start trigger signal related to the same specific electric device is considered to be an "pause state." The selection means 102 selects, for example, “construction of steel support” as an individual process if the hydraulic pump (specific electric equipment) of a concrete sprayer (machine in use) is in operation and the compressor (specific electric equipment) is idle, and selects “spraying of concrete” as an individual process if both the hydraulic pump and compressor of the concrete sprayer are in operation.

[0062] In addition, in the pattern of individual process 03, multiple machines are set for individual process 1, so multiple trigger signals can be used. In this case, it is preferable to determine the start and end points of the work time by the trigger signals of different machines. Figure 11 is a model diagram that shows the selection of an individual process according to a combination of trigger signals of different machines. In the case of blasting excavation, since face excavation is performed after rock bolt driving, it is possible to receive a start trigger signal related to the hydraulic pump (specific electric equipment) of the drill jumbo (machine used) at the start of rock bolt driving, and then receive a stop trigger signal related to the hydraulic pump of the drill jumbo at the end of face excavation. In other words, no trigger signal is received as a delimiter between rock bolt driving and face excavation, and rock bolt driving and face excavation are determined to be a series of individual processes (in this case, rock bolt driving is continuous), and rock bolt driving and face excavation cannot be appropriately selected.

[0063] Therefore, as shown in FIG. 11, the selection means 102 uses a trigger signal related to a machine (mortar injection pump) other than the drill jumbo. For example, the selection means 102 determines that "rock bolt driving" has started when it receives a start trigger signal related to the hydraulic pump of the drill jumbo, and determines that "rock bolt driving" has ended and "face excavation" has started when it receives a stop trigger signal related to the mortar injection pump. Then, it determines that "face excavation" has ended when it receives a stop trigger signal related to the hydraulic pump of the drill jumbo. That is, the selection means 102 selects "rock bolt driving" from the time when it receives a start trigger signal related to the hydraulic pump of the drill jumbo to the time when it receives a stop trigger signal related to the mortar injection pump, and selects "face excavation" from the time when it receives a stop trigger signal related to the mortar injection pump to the time when it receives a stop trigger signal related to the hydraulic pump of the drill jumbo. Here, the trigger signal receiving means 101 receives a start trigger signal related to the mortar injection pump after receiving a start trigger signal related to the hydraulic pump of the drill jumbo, and at that time it determines that "rock bolt driving" is continuing. In addition, when it is determined that "face excavation" has started when a stop trigger signal for the mortar injection pump is received, there is a possibility that a work time that is longer than the actual time will be calculated. In this case, it is advisable to adjust the work time by subtracting the "correction time".

[0064] When an individual process is selected by the selection means 102, the process display control means 114 causes the process display means 115 to display the individual process (Step 205 in FIG. 8), and the equipment control means 109 adjusts the output of the blower and dust collector in accordance with the individual process (Step 206 in FIG. 8).

[0065] When an individual process being carried out ends and, for example, a miner turns off the power to the headlights of the twin header (or road header), the trigger signal receiving means 101 receives a stop trigger signal (Step 207 in FIG. 8). Then, the selection means 102 calculates the operation time of the individual process, taking the time when the start trigger signal was received as the start point and the time when the stop trigger signal was received as the end point (Step 208 in FIG. 8). At this time, as described above, the operation time can be found by using the "correction time".

[0066] When an individual process is selected and its working time is calculated, it is determined whether the excavation cycle has ended (Step 209 in FIG. 9). That is, when an individual process in the middle of the excavation cycle is selected (No in Step 209 in FIG. 9), it is determined that the excavation cycle has not ended, and the selection of the individual process (Step 204 in FIG. 8) is continued. On the other hand, when a series of individual processes constituting the excavation cycle have all been selected (Yes in Step 209 in FIG. 9), it is determined that the excavation cycle has ended, and the number of cycles is counted as 1, and the cumulative number of cycles is counted (Step 210 in FIG. 9).

[0067] When the number of cycles and the cumulative number of cycles are counted, the support pattern estimation means 104 estimates the "support pattern" of that excavation cycle (the excavation cycle for which the number of cycles has been counted) (Step 211 in Figure 9), and the pattern-specific excavation length setting means 105 sets the "pattern-specific excavation length" related to that support pattern and calculates the "tunnel excavation distance" (Step 212 in Figure 9).

[0068] When the tunnel excavation distance is obtained, the schedule output means 107 updates the "diagonal line schedule" and outputs the diagonal line schedule to the output means 112 such as a display (Step 213 in FIG. 9). In addition, the wind duct length calculation means 108 calculates the wind duct length based on the tunnel excavation distance calculated by the pattern-specific excavation length setting means 105 (Step 214 in FIG. 9), and the equipment control means 109 calculates the pressure loss associated with the blowing based on the wind duct length and adjusts the output of the blower according to the pressure loss (Step 215 in FIG. 9).

[0069] The operation time measurement means 110 continuously or periodically measures the operation time of the blower, etc. (Step 216 in FIG. 9). Then, the CO2 emission calculation means 111 continuously (or periodically) or in response to an operator operation, calculates the CO2 emission amount associated with the operation of the blower, etc. (Step 217 in FIG. 9).

[0070] 3. Tunnel progress output method Next, the tunnel progress output method will be described with reference to Fig. 12. Note that the tunnel progress output method is a method for outputting the degree of tunnel progress (the cumulative number of cycles and the tunnel excavation distance) using the tunnel progress output system 100 described so far, and therefore, explanations that overlap with the contents described in the tunnel progress output system 100 will be avoided, and only the contents unique to the tunnel progress output method will be described. In other words, the contents not described here are the same as those described in "2. Tunnel progress output system".

[0071] Fig. 12 is a flow diagram showing the main steps of the tunnel progress output method. As shown in this figure, first, the trigger signal receiving means 101 receives a start-up trigger signal (Step 301 in Fig. 12). For example, when a miner turns on the power supply of the headlight of a side dump, the trigger signal receiving means 101 receives a start-up trigger signal related to the headlight of the side dump.

[0072] When a start-up trigger signal is received, the selection means 102 selects an individual process corresponding to the trigger signal (start-up trigger signal) (Step 302 in FIG. 12). Then, the process display control means 114 causes the process display means 115 to display the individual process (Step 303 in FIG. 12), and the equipment control means 109 adjusts the output of the blower and dust collector according to the individual process (Step 304 in FIG. 12).

[0073] When an individual process being performed ends and, for example, a miner turns off the power supply to the headlights of the side dump truck, the trigger signal receiving means 101 receives a stop trigger signal. Then, the selection means 102 calculates the operation time of the individual process, taking the time when the start trigger signal was received as the start point and the time when the stop trigger signal was received as the end point (Step 305 in FIG. 12).

[0074] When an individual process is selected and it is determined that an excavation cycle has ended, the number of cycles is counted as 1, and the cumulative number of cycles is counted (Step 306 in FIG. 12). Then, the "support pattern" of that excavation cycle is estimated (Step 307 in FIG. 12), and the "excavation length by pattern" related to that support pattern is set, and the "tunnel excavation distance" is calculated (Step 308 in FIG. 12). When the tunnel excavation distance is obtained, the "diagonal line schedule" is updated, and the diagonal line schedule is output to the output means 112 such as a display (Step 309 in FIG. 12).

[0075] On the other hand, during construction, the operating time of the blower, etc. is measured continuously or periodically (Step 310 in FIG. 12), and the amount of CO2 emissions associated with the operation of the blower, etc. is calculated based on the operating time of the blower, etc. (Step 311 in FIG. 12). [Industrial Applicability]

[0076] The tunnel progress output system of the present invention can be used at construction sites where multiple different individual processes, such as tunnel excavation, earthworks, concrete work, etc., are carried out in shifts. The present invention can efficiently analyze the cycle time of construction work, which in turn enables appropriate cost management based on past performance, and ultimately reduces the costs of construction infrastructure. Considering this, the invention is not only applicable to industry, but is also expected to make a great contribution to society. [Explanation of symbols]

[0077] 100 Tunnel progress output system of the present invention 101 (Tunnel Progress Output System) Trigger Signal Receiving Means 102 (Tunnel Progress Output System) Selection Method 103 (Tunnel Progress Output System) Cycle Counting Means 104 (Tunnel Progress Output System) Support Pattern Estimation Method 105 (Tunnel progress output system) pattern-specific excavation length setting means 106 (Tunnel Progress Output System) Cycle Time Calculation Means 107 (Tunnel Progress Output System) Schedule Output Means 108 (Tunnel Progress Output System) Wind Tube Length Calculation Method 109 Equipment control means (of tunnel progress output system) 110 (Tunnel Progress Output System) Operating Time Measurement Means 111 (Tunnel Progress Output System) CO2 Emissions Calculation Method 112 (Tunnel Progress Output System) Output Means 113 Communication equipment (tunnel progress output system) 114 (Tunnel Progress Output System) Process Display Control Means 115 (Tunnel Progress Output System) Process Indication Means 116 (tunnel progress output system) correction time storage means 117 (Tunnel Progress Output System) Support Pattern Storage Means 118 (Tunnel Progress Output System) Standard Cycle Time Storage Means 119 (Tunnel Progress Output System) Excavation Length Memory Means

Claims

1. A system for selecting one individual process from among a plurality of different individual processes carried out in tunnel excavation based on power supply operation of an electric device provided on a construction machine, and outputting a progress status of the tunnel excavation based on an excavation cycle consisting of a series of a plurality of types of the individual processes, a trigger signal receiving means mounted on the construction machine used in the individual process, for receiving a trigger signal related to a power supply operation of the electrically-powered device; a selection means for selecting the individual process based on the trigger signal received by the trigger signal receiving means; and a cycle number counting means for counting one cycle number when a series of the individual steps constituting the excavation cycle is selected, and counting a cumulative cycle number which is a cumulative total of the cycle numbers, the trigger signal receiving means receives a start trigger signal when a power source of a predetermined specific electric device among the electric devices provided on the construction machine is turned on, and receives a stop trigger signal when the power source of the specific electric device is released from being turned on; The selection means selects the individual process based on the construction machine associated with the trigger signal receiving means that has received the trigger signal, outputting the cumulative number of cycles as a progress status of tunnel excavation; A tunnel progress output system comprising:

2. A system for selecting one individual process from among a plurality of different individual processes carried out in tunnel excavation based on power supply operation of an electric device provided on a construction machine, and outputting a progress status of the tunnel excavation based on an excavation cycle consisting of a series of a plurality of types of the individual processes, a trigger signal receiving means mounted on the construction machine used in the individual process, for receiving a trigger signal related to a power supply operation of the electrically-powered device; a selection means for selecting the individual process based on the trigger signal received by the trigger signal receiving means; a cycle number counting means for counting one cycle number when a series of the individual steps constituting the excavation cycle is selected, and counting a cumulative cycle number which is a cumulative total of the cycle numbers; a support pattern estimation means for estimating a support pattern, which is a type of the excavation cycle, when a series of the individual processes constituting the excavation cycle is selected; and a pattern-specific excavation length setting means for setting a pattern-specific excavation length according to the support pattern estimated by the support pattern estimation means, the trigger signal receiving means receives a start trigger signal when a power source of a predetermined specific electric device among the electric devices provided on the construction machine is turned on, and receives a stop trigger signal when the power source of the specific electric device is released from being turned on; The selection means selects the individual process based on the construction machine associated with the trigger signal receiving means that has received the trigger signal, The support pattern estimation means estimates the support pattern based on a sequence of the support patterns related to the excavation cycle planned in advance and the cumulative number of cycles, outputting a tunnel excavation distance based on the pattern-specific excavation length set by the pattern-specific excavation length setting means; A tunnel progress output system comprising:

3. A system for selecting one individual process from among a plurality of different individual processes carried out in tunnel excavation based on power supply operation of an electric device provided on a construction machine, and outputting a progress status of the tunnel excavation based on an excavation cycle consisting of a series of a plurality of types of the individual processes, a trigger signal receiving means mounted on the construction machine used in the individual process, for receiving a trigger signal related to a power supply operation of the electrically-powered device; a selection means for selecting the individual process based on the trigger signal received by the trigger signal receiving means; a cycle number counting means for counting the number of cycles when a series of the individual steps constituting the excavation cycle is selected; a cycle time calculation means for calculating an excavation cycle time relating to the excavation cycle when a series of the individual processes constituting the excavation cycle is selected; a support pattern estimation means for estimating a support pattern, which is a type of the excavation cycle, based on the excavation cycle time calculated by the cycle time calculation means; A pattern-specific excavation length setting means for setting a pattern-specific excavation length according to the support pattern estimated by the support pattern estimation means, the trigger signal receiving means receives a start trigger signal when a power source of a predetermined specific electric device among the electric devices provided on the construction machine is turned on, and receives a stop trigger signal when the power source of the specific electric device is released from being turned on; the selection means selects the individual process based on the construction machine associated with the trigger signal receiving means that has received the trigger signal, and calculates a work time for the individual process based on a receiving time of the start trigger signal and a receiving time of the stop trigger signal; The cycle time calculation means calculates the excavation cycle time based on the work times associated with the individual processes constituting the excavation cycle, the support pattern estimation means estimates the support pattern by comparing a standard excavation cycle time for each of the support patterns set in advance with the excavation cycle time, outputting a tunnel excavation distance based on the pattern-specific excavation length set by the pattern-specific excavation length setting means; A tunnel progress output system comprising:

4. The present invention further includes a schedule output means for outputting a diagonal line schedule showing the degree of progress of the tunnel excavation according to time on a graph consisting of a first axis showing the degree of progress of the tunnel excavation and a second axis showing time.

4. A tunnel progress output system according to claim 1, wherein the tunnel progress output system is a system for outputting a tunnel progress signal.

5. a wind duct length calculation means for calculating a wind duct length, which is a length of a ventilation duct installed, based on the tunnel excavation distance; and an equipment control means for controlling a blower that blows air to the ventilation duct, The equipment control means calculates a pressure loss associated with the blowing of air based on the air duct length, and adjusts the output of the blower in accordance with the pressure loss.

4. The tunnel progress output system according to claim 2 or 3.

6. an operation time measurement means for measuring an operation time of the fan which is operated under the control of the equipment control means; During the operation time for each output of the blower, the amount of CO per unit time set in advance for each output is 2 By multiplying the emission amount, the CO 2 Calculate CO emissions 2 An emission calculation means, 6. The tunnel progress output system according to claim 5.

Citation Information

Patent Citations

  • Laying structure of signal cable for blower

    JP1999303600A

  • Teacher data generation device and teacher data generation method

    JP2021105962A

  • Process discrimination system and process discrimination method

    JP2021131738A

  • Individual process determination system and individual process determination method

    JP2023084810A

  • Operation history data management system for construction machine

    JP2021056938A