The protection coordination curve creation device automates the generation of protection coordination curves using predetermined information, addressing the inefficiencies of manual trial and error, thereby enhancing the speed and accuracy of protective relay settings.
Patent Information
- Application Number
- JP2023072447
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-26
- Publication Date
- 2024-11-08
AI Technical Summary
Creating a protection coordination curve for protective relays in power receiving and transforming equipment requires significant trial and error, leading to lengthy processing times.
A protection coordination curve creation device that includes an equipment information acquisition unit, an a priori data acquisition unit, and a protection coordination curve creation unit, which automatically generates the curve using predetermined information about equipment and relay characteristics.
Facilitates rapid and accurate creation of protection coordination curves, reducing the time and effort required for setting values in protective relays.
Smart Images

Figure 2024157841000001_ABST
Abstract
Description
[Technical field]
[0001] An embodiment of the present invention relates to a protection coordination curve creation device. [Background technology]
[0002] Traditionally, protective relays have been installed in the substation equipment that transmits and distributes electricity to each facility. When a short circuit or ground fault occurs in the substation equipment, the protective relay quickly detects the point of the fault and opens the switch (circuit breaker, disconnector, etc.) to prevent the fault from spreading to other distribution systems and to prevent damage to equipment due to the fault current.
[0003] In this regard, engineers create a protection coordination curve using software for creating a protection coordination curve that holds the specification data of each type of protection relay. A protection coordination curve is a graph including the operating characteristic curves of each of a plurality of protection relays that are created to enable protection coordination, and is, for example, a double logarithmic graph with time on the vertical axis and current value on the horizontal axis. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2017-163689 A [Patent Document 2] JP 2014-220865 A [Patent Document 3] Japanese Patent Application Publication No. 6-22438 Summary of the Invention [Problem to be solved by the invention]
[0005] However, in the above-mentioned conventional technology, when engineers consider protection coordination, they need to determine the setting values for the operating characteristic curves of each protective relay through repeated trial and error. Therefore, it takes a long time to create the protection coordination curves, and an improvement is desired.
[0006] Therefore, an object of an embodiment of the present invention is to provide a protection coordination curve creation device that is capable of creating a protection coordination curve for substation equipment by providing predetermined information. [Means for solving the problem]
[0007] The protection coordination curve creation device of the embodiment includes an equipment information acquisition unit that acquires equipment information, which is information regarding equipment including a plurality of switches and a plurality of protective relays installed in a substation equipment, an advance data acquisition unit that acquires specified advance data required to create a protection coordination curve including operating characteristic curves of each of the plurality of protective relays, and a protection coordination curve creation unit that creates the protection coordination curve based on the equipment information and the advance data. [Brief description of the drawings]
[0008] [Figure 1] FIG. 1 is a block diagram showing a functional configuration of a protection coordination curve creation device according to an embodiment. [Diagram 2] FIG. 2 is a diagram illustrating an example of a single-line diagram according to the embodiment. [Diagram 3] FIG. 3 is a diagram illustrating an example of a protection coordination curve according to the embodiment. [Figure 4] FIG. 4 is a flowchart showing the processing performed by the protection coordination curve creation device of the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] Hereinafter, an embodiment of a protection coordination curve creation device of the present invention will be described with reference to the accompanying drawings.
[0010] 1 is a block diagram showing a functional configuration of a protection coordination curve creation device 1 according to an embodiment. The protection coordination curve creation device 1 is a computer device (for example, a general PC (Personal Computer)) and includes a processing unit 2, a storage unit 3, an input unit 4, an output unit 5, and a communication unit 6.
[0011] The processing unit 2 is an information processing means such as a CPU (Central Processing Unit) that executes an operation program stored in the storage unit 3. The processing unit 2 includes, as functional components, an equipment information acquisition unit 21, a prior data acquisition unit 22, and a protection coordination curve creation unit 23. Note that all or part of these functional components may be realized using hardware such as an ASIC (Application Specific Integrated Circuit), a PLD (Programmable Logic Device), or an FPGA (Field Programmable Gate Array).
[0012] Below, Figures 2 and 3 will also be referred to as appropriate. Figure 2 is a diagram showing an example of a single-line diagram of an embodiment. Figure 2 shows an example of a single-line diagram of a specific distribution system in a substation facility. The substation facility converts power received from a higher-level power system managed by a power company or the like into a voltage suitable for load equipment, and protects the load equipment to prevent a cascading accident to the load equipment in the event of an accident on a distribution line. Specifically, the substation facility includes a switch, a transformer, a protective relay, and the like.
[0013] The switch is, for example, a circuit breaker or a disconnecting switch, and opens and closes an electric circuit. The switch works in conjunction with a paired protective relay, and cuts off the electric circuit in response to a cutoff command from the protective relay. The switch also transmits a signal including its own open / closed state and the presence or absence of a fault to a monitoring control device (not shown).
[0014] A transformer converts the power received from an upper power system into a voltage suitable for the load equipment.
[0015] A protective relay is a device that protects an electric circuit from sudden changes in current or voltage. Examples of protective relays include overcurrent relays, earth fault relays, and overvoltage relays. There are several types of protective relays, each with different setting values. Specifically, a protective relay is composed of a computer that includes a CPU and memory and runs on specific application software, or a dedicated electronic circuit.
[0016] 2 will be described in order from the top. The switch 52R is provided at a position adjacent to the upper power system. A protective relay 51R is provided corresponding to the switch 52R.
[0017] Below that, a switch 52P and a corresponding protective relay 51P are provided. Below the protective relay 51P, a transformer TR is provided.
[0018] A switch 52S and a corresponding protective relay 51S are provided below the transformer TR. A switch 52F and a corresponding protective relay 51F are provided below the protective relay 51S.
[0019] In addition, in FIG. 2, a single-line diagram without branches is shown for the sake of simplicity of explanation and illustration, but the present invention is not limited to this and may be a single-line diagram with branches.
[0020] Fig. 3 is a diagram showing an example of a protection coordination curve of an embodiment. Fig. 3 corresponds to Fig. 2. In the graph of Fig. 3, the vertical axis is time (logarithmic scale) and the horizontal axis is current value (logarithmic scale). Fig. 3 illustrates the protection coordination curves of protective relays 51F, 51S, 51P, and 51R. The short circuit current region R is a range from the TR primary short circuit current value TR1 (maximum short circuit current value) to the TR secondary short circuit current value TR2 (minimum short circuit current value) due to a short circuit accident occurring at any accident point.
[0021] In this short circuit current region R, the protective relay 51F is set to operate in a shorter time than the protective relay 51S. In this way, it is preferable that the protective coordination curve is set so that the protective relays are tripped in the order from the downstream protective relay to the upstream protective relay. When the protective coordination curves of multiple protective relays intersect with each other, there are cases in which the upstream protective relay is tripped first depending on the short circuit current. This state can be considered as a lack of protective coordination.
[0022] In addition, for the most upstream protective relay 51R, the setting value is often determined in advance by, for example, the power company, and the setting values of the other protective relays must be determined based on that setting value. Details of Fig. 3 will be described later. In addition, hereinafter, determining the setting value may be referred to as "setting".
[0023] 1, the device information acquisition unit 21 acquires device information, which is information about devices including a plurality of switches and a plurality of protective relays installed in the power receiving and transforming equipment. For example, the device information acquisition unit 21 acquires the device information by performing image recognition processing on a scanned image obtained from the scanner 7 that has scanned a single-line diagram of the power receiving and transforming equipment.
[0024] For example, when acquiring device information by image recognition processing of a scanned image, the device information acquiring unit 21 acquires at least the connection configuration of the device and the type information of the protective relay. For single-line diagrams, there are generally predetermined drawing rules (for example, industry standard drawing rules). In the predetermined drawing rules, for example, in "51R" described for a protective relay, "51" means that it is a predetermined type of overcurrent relay, and "R" means the installation location. When two such protective relays are provided in parallel, they are described as "51R1" and "51R2". Furthermore, "52R" means that it is a switch corresponding to the protective relay "51R". Furthermore, "TR" means a transformer.
[0025] Therefore, by storing such drawing rules in advance in the storage unit 3, the device information acquisition unit 21 can acquire information such as the connection configuration of the devices and the type of protective relay from the character information recognized by the image recognition process on the scanned image. In this case, the device information acquisition unit 21 may also use information on the connection lines of each device recognized by the image recognition process on the scanned image.
[0026] Furthermore, if there is an error in the device information acquired by the device information acquisition unit 21, the user uses the input unit 4 to manually correct it.
[0027] The advance data acquisition unit 22 acquires predetermined advance data necessary for creating a protection coordination curve including the operation characteristic curves of each of the multiple protection relays. For example, the advance data acquisition unit 22 acquires multiple patterns (e.g., all patterns) of the operation characteristic curves of the protection relays as advance data.
[0028] Further, for example, the advance data acquisition unit 22 acquires, as advance data, at least the setting value of the protective relay 51R installed at a position adjacent to the upper power system, the magnetizing inrush current value of the transformer TR, and specification information of each of the multiple protective relays 51R, 51P, 51S, and 51F. These advance data are input by an engineer using the input unit 4, for example.
[0029] The protection coordination curve creation unit 23 creates a protection coordination curve based on the device information and the advance data. In addition, the protection coordination curve creation unit 23 outputs the created protection coordination curve in a double logarithmic graph in which both axes of time and current value are on a logarithmic scale.
[0030] The processing of the protection coordination curve creation unit 23 will be described in detail with reference to Fig. 3. In Fig. 3, the symbol U denotes a setting value of a protective relay in an upper-level power system, and information on this setting value is obtained in advance from the power company and stored in the storage unit 3.
[0031] (timed element) The protection coordination curve generator 23 settles the time-limit element (the curve portion on the left side of FIG. 3) as follows. <Protective relay 51R> The value is set to the value specified by the power company that manages the upper-level power grid.
[0032] <Protective relay 51P, 51S> The capacity of the transformer TR (rated current value: symbol TRC in FIG. 3) is set at 120% to 130% (symbol A2 in FIG. 3).
[0033] <Protection relay 51F> The load capacity (load current value: LC in FIG. 3) is set to 120% to 130% (A1 in FIG. 3).
[0034] (instantaneous element) The protection coordination curve creation unit 23 settles the instantaneous element (short circuit current region R on the right side of FIG. 3) as follows. <Protective relay 51R> The value is set to the value specified by the power company that manages the upper-level power grid.
[0035] <Protective relay 51P> The TR primary short circuit current value is set at 80% of TR1 (see FIG. 3) (reference symbol A7 in FIG. 3).
[0036] <Protective relay 51S> It is locked to coordinate with protective relay 51F.
[0037] <Protection relay 51F> The TR secondary short circuit current value is set at 80% of TR2 (Figure 3) (symbol A4 in Figure 3).
[0038] (time setting) The protection coordination curve creation unit 23 executes the time setting (adjustment in the vertical direction in FIG. 3) as follows. <Protective relay 51R> The value is set to the value specified by the power company that manages the upper-level power grid.
[0039] <Protective relay 51P> The TR excitation inrush current value TR3 (Figure 3) is coordinated for 0.2 seconds (symbol A3 in Figure 3). At the TR secondary short circuit current value TR2 (FIG. 3), coordination with the protective relay 51R is performed for 0.2 seconds (reference symbol A5 in FIG. 3). In addition, since there is a one-to-one relationship with the protective relay 51S, no coordination is required.
[0040] <Protective relay 51S> At the TR secondary short circuit current value TR2 (Figure 3), coordination with protective relay 51F is achieved for 0.2 seconds (symbol A6 in Figure 3).
[0041] <Protection relay 51F> At the TR secondary short circuit current value TR2 (Figure 3), coordination with the protective relay 51S is achieved for 0.2 seconds (symbol A6 in Figure 3).
[0042] 1, the storage unit 3 is a storage means such as a RAM (Random Access Memory), a ROM (Read Only Memory), an HDD (Hard Disk Drive), an SSD (Solid State Drive), etc., and stores various information. The storage unit 3 stores, for example, device information 31, advance data 32, protection coordination curve information 33, etc.
[0043] The device information 31 is device information acquired by the device information acquisition unit 21 .
[0044] The prior data 32 is prior data acquired by the prior data acquisition unit 22 .
[0045] The protection coordination curve information 33 is information on the protection coordination curve created by the protection coordination curve creation unit 23.
[0046] The input unit 4 is a means for a user to input information, and is configured by, for example, a keyboard, a pointing device (mouse, tablet, etc.), a touch panel, buttons, and the like.
[0047] The output unit 5 is an information output means, and is configured by, for example, a display device and an audio output device. Examples of the display device include a liquid crystal display, an organic EL (Electro Luminescence) display, and a CRT (Cathode Ray Tube) display. The display device displays, for example, the protection coordination curve ( FIG. 3 ) created by the protection coordination curve creation unit 23. Examples of the audio output device include a speaker.
[0048] The communication unit 6 is a communication interface for communicating with an external device.
[0049] Next, the processing by the protection coordination curve creation device 1 will be described with reference to Fig. 4. Fig. 4 is a flowchart showing the processing by the protection coordination curve creation device 1 of the embodiment.
[0050] First, in step S1, the equipment information acquisition unit 21 acquires equipment information on equipment including multiple switches and multiple protective relays by performing image recognition processing on a scanned image obtained from the scanner 7 that scans a single-line diagram (Figure 2) of the power receiving and transforming equipment.
[0051] Next, in step S2, the advance data acquisition unit 22 acquires advance data necessary for creating a protection coordination curve, such as multiple patterns of operating characteristic curves of the protective relays, the setting value of the protective relay 51R installed at a position adjacent to the upper-level power system, the excitation inrush current value of the transformer TR, and specification information of each of the multiple protective relays 51R, 51P, 51S, and 51F.
[0052] Next, in step S3, the protection coordination curve creation unit 23 creates a protection coordination curve (FIG. 3) based on the device information acquired in step S1 and the advance data acquired in step S2.
[0053] Next, in step S4, the protection coordination curve creation unit 23 outputs the protection coordination curve created in step S3 in a double logarithmic graph (FIG. 3).
[0054] In this way, according to the protection coordination curve creation device 1 of the present embodiment, by providing device information and advance data as predetermined information, it is possible to automatically create an appropriate protection coordination curve for the power receiving and transforming equipment.
[0055] Furthermore, when acquiring device information, it is possible to reduce the labor required by using a scanned image of a single-line diagram that is always created at the substation facility. In this case, image recognition processing of the scanned image can be performed to acquire at least the device connection configuration and protective relay type information, which are specifically required for creating a protection coordination curve.
[0056] In addition, the specific information required to create a protection coordination curve, such as multiple patterns of operating characteristic curves of protective relays, setting values of protective relays installed in positions adjacent to the upper-level power system, excitation inrush current values of transformers, and specification information for each of multiple protective relays, can be obtained as advance data.
[0057] In addition, the protection coordination curve that is created can be output in a double logarithmic graph similar to that of the conventional technology, making it easy to use the protection coordination curve.
[0058] The program executed by the protection coordination curve creation device 1 of this embodiment can be provided by recording it in an installable or executable file format on a recording medium readable by a computer device, such as a CD (Compact Disc)-ROM (Read Only Memory), a flexible disk (FD), a CD-R (Recordable), or a DVD (Digital Versatile Disk). The program may also be provided or distributed via a network, such as the Internet.
[0059] Although the embodiment of the present invention has been described, this embodiment is presented as an example and is not intended to limit the scope of the invention. This novel embodiment can be implemented in various other forms, and various omissions, substitutions, and modifications can be made without departing from the gist of the invention. These embodiments and their modifications are included in the scope and gist of the invention, and are included in the scope of the invention and its equivalents described in the claims.
[0060] For example, in the above embodiment, the device information acquiring unit 21 acquires the device information using a scanned image of a single-line diagram, but this is not limited to this. The device information acquiring unit 21 may also acquire the device information using information in another format, such as text data corresponding to symbol information (51R, 52R, etc.) for each device (protective relay, switch, etc.) input by the user using the input unit 4.
[0061] In addition, the "0.2 seconds" for the time setting is an example and is not limited to this. Any other time length may be used as long as it is an appropriate value for achieving protection coordination. [Explanation of symbols]
[0062] 1... protection coordination curve creation device, 2... processing unit, 3... memory unit, 4... input unit, 5... output unit, 6... communication unit, 7... scanner, 21... equipment information acquisition unit, 22... advance data acquisition unit, 23... protection coordination curve creation unit, 31... equipment information, 32... advance data, 33... protection coordination curve information
Claims
1. an equipment information acquisition unit that acquires equipment information that is information about equipment including a plurality of switches and a plurality of protective relays installed in the power receiving and transforming equipment; a pre-data acquisition unit for acquiring predetermined pre-data necessary for creating a protection coordination curve including an operation characteristic curve of each of the plurality of protective relays; a protection coordination curve creation unit that creates the protection coordination curve based on the equipment information and the advance data.
2. The protection coordination curve creation device according to claim 1 , wherein the device information acquisition unit acquires the device information by performing image recognition processing on a scanned image obtained by scanning a single-line diagram of the power receiving and transforming equipment.
3. The protection coordination curve creation device according to claim 1 , wherein the advance data acquisition unit acquires a plurality of patterns of the operation characteristic curve of the protective relay as the advance data.
4. The protection coordination curve creation device according to claim 2 , wherein the equipment information acquisition unit acquires at least a connection configuration of the equipment and type information of the protective relay when acquiring the equipment information by image recognition processing of the scanned image.
5. 2. The protection coordination curve creation device according to claim 1, wherein the advance data acquisition unit acquires, as the advance data, at least a setting value of the protective relay installed at a position adjacent to an upper power system, an excitation inrush current value of a transformer, and specification information of each of the multiple protective relays.
6. 2. The protection coordination curve creation device according to claim 1, wherein the protection coordination curve creation unit outputs the created protection coordination curve as a double logarithmic graph in which both axes of time and current value are logarithmic scales.
Citation Information
Patent Citations
Protective relay
JP1994022438A
Protective device for power distribution board
JP2014220865A
Monitoring control device
JP2017163689A