Lighting fixture
The lighting fixture automates battery inspection by alternately charging and discharging the battery at set intervals, reducing workload and preventing deterioration, while ensuring accurate battery health assessment.
Patent Information
- Application Number
- JP2023075221
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-28
- Publication Date
- 2024-11-08
AI Technical Summary
Conventional emergency lighting devices require manual inspection of storage batteries, which is burdensome for workers due to the need for periodic checks over several minutes to an hour, increasing workload and potential human error.
A lighting fixture equipped with a replaceable storage battery, charging and lighting circuit sections, and an inspection mechanism that automatically initiates battery inspection at predetermined intervals, alternately charging and discharging the battery to determine its quality based on voltage changes, eliminating the need for manual intervention.
Reduces the workload required for battery inspection, suppresses temperature rise during inspection, and prevents battery deterioration by automating the process, ensuring accurate and timely detection of battery health.
Smart Images

Figure 2024159315000001_ABST
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a lighting fixture, and more particularly to a lighting fixture equipped with a storage battery for providing emergency lighting. [Background technology]
[0002] As a conventional example, an illumination device described in Patent Document 1 is exemplified. The illumination device described in Patent Document 1 (hereinafter, referred to as the conventional example) is an emergency illumination device that is turned on by power from a built-in emergency power source (storage battery) when the external power source is cut off during a power outage or other such event.
[0003] In the conventional example, it is necessary to periodically inspect the storage battery. During inspection, an operator operates a terminal such as a remote control below the lighting device to be inspected and transmits an inspection signal to the lighting device. When the lighting device receives the inspection signal, it goes into inspection mode and turns on the light source using power from the storage battery to determine the life of the storage battery. After completing the inspection, the lighting device notifies the inspection result with a monitor lamp and transmits the inspection result to the terminal such as a remote control. The operator visually checks the monitor lamp and also checks the inspection result received on the terminal to understand the condition of the storage battery. [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2021-111458 A Summary of the Invention [Problem to be solved by the invention]
[0005] However, in conventional examples, a person (worker) had to operate a terminal to start an inspection, and then check the inspection results reported by the lighting device after a predetermined time (several tens of minutes to an hour) had elapsed since the start of the inspection, which placed a heavy burden on the worker performing the inspection.
[0006] An object of the present disclosure is to provide a lighting fixture that can reduce the workload required for inspection. [Means for solving the problem]
[0007] A lighting device according to an aspect of the present disclosure includes a light source, a replaceable storage battery, a charging circuit unit, a lighting circuit unit, an inspection unit, and a timer unit that measures an elapsed time. The charging circuit unit charges the storage battery with normal power supplied from a normal power source. The lighting circuit unit lights the light source with emergency power supplied from the storage battery. The inspection unit controls the charging circuit unit and the lighting circuit unit to inspect the storage battery. The timer unit outputs an inspection start signal to cause the inspection unit to start the inspection when the elapsed time reaches a predetermined interval. The inspection unit starts the inspection upon receiving the inspection start signal, and alternately operates the lighting circuit unit and the charging circuit unit to repeatedly charge and discharge the storage battery. The inspection unit determines whether the storage battery is good or bad based on the battery voltage of the storage battery after the cumulative time of discharging the storage battery reaches a predetermined inspection time. Effect of the Invention
[0008] The lighting fixture of the present disclosure has the advantage of being able to reduce the workload required for inspection. [Brief description of the drawings]
[0009] [Figure 1] FIG. 1 is a circuit block diagram of a lighting device in a lighting fixture according to an embodiment of the present disclosure. [Diagram 2] FIG. 2 is a perspective view of the above lighting fixture. [Diagram 3] FIG. 3 is an exploded perspective view of the above lighting fixture. [Figure 4] FIG. 4 is a diagram illustrating the discharge characteristics of the storage battery in the lighting fixture. [Diagram 5] FIG. 5 is a time chart for explaining the inspection operation of the lighting fixture according to the above embodiment. [Figure 6]FIG. 6 is a time chart for explaining the inspection operation of the lighting fixture according to the above embodiment. [Figure 7] FIG. 7 is a time chart for explaining the inspection operation of the lighting fixture according to the above embodiment. [Figure 8] FIG. 8 is a time chart for explaining the inspection operation of the lighting fixture according to the above embodiment. [Figure 9] FIG. 9 is a time chart for explaining the inspection operation of the lighting fixture according to the modified example. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0010] The lighting device A1 according to the embodiment will be described in detail below with reference to the drawings. However, each figure described in the following embodiment is a schematic diagram, and the ratio of the size and thickness of each component does not necessarily reflect the actual dimensional ratio. Note that the configuration described in the following embodiment is merely an example of the present disclosure. The present disclosure is not limited to the following embodiment, and various modifications are possible depending on the design, etc., as long as the effects of the present disclosure can be achieved.
[0011] (1) Overview The lighting fixture A1 according to the embodiment includes a light source, a replaceable storage battery 30, a charging circuit unit 401, a lighting circuit unit 402, an inspection unit, and a timer unit that measures elapsed time (see FIG. 1). The light source is, for example, an LED 20. The storage battery 30 is, for example, a nickel-metal hydride storage battery. However, the light source may be an organic electroluminescence element, a semiconductor laser, or the like. The storage battery 30 may also be, for example, a lithium ion storage battery.
[0012] The charging circuit unit 401 charges the storage battery 30 with normal power supplied from a normal power source. The normal power source is, for example, the power system P1. The lighting circuit unit 402 lights up the light source (LED 20) with emergency power supplied from the storage battery 30.
[0013] The inspection unit controls the charging circuit unit 401 and the lighting circuit unit 402 to inspect the storage battery 30. The clock unit outputs an inspection start signal to the inspection unit to start inspection when the elapsed time reaches a predetermined interval. The inspection unit starts inspection when it receives the inspection start signal, and alternately operates the lighting circuit unit 402 and the charging circuit unit 401 to repeatedly charge and discharge the storage battery 30. The inspection unit judges whether the storage battery 30 is good or bad based on the battery voltage of the storage battery 30 after the accumulated time of discharging the storage battery 30 reaches the predetermined inspection time. The inspection unit and the clock unit are preferably realized by causing a processor of a microcontroller provided in the control circuit unit 404 to execute an inspection program and a clock program.
[0014] Thus, when the elapsed time measured by the timer unit reaches the interval time, the lighting fixture A1 according to the embodiment outputs an inspection start signal to the inspection unit to start the inspection, eliminating the need for manual work to start the inspection as in the conventional example. As a result, the lighting fixture A1 according to the embodiment can reduce the workload required for inspection compared to the conventional example. Furthermore, in the lighting fixture A1 according to the embodiment, the inspection unit alternately operates the lighting circuit unit 402 and the charging circuit unit 401 to repeatedly charge and discharge the storage battery 30, and determines whether the storage battery 30 is good or bad based on the battery voltage of the storage battery 30 after the cumulative time of discharging the storage battery 30 reaches a predetermined inspection time. In other words, the lighting fixture A1 according to the embodiment can suppress a temperature rise of the storage battery 30 during inspection, and suppress deterioration of the storage battery 30 caused by the temperature rise.
[0015] (2) Details The lighting fixture A1 according to the embodiment (hereinafter, abbreviated as lighting fixture A1) is an emergency light, which is a type of battery-powered emergency lighting fixture. An emergency light is an emergency lighting fixture for general lighting to illuminate evacuation routes in the event of a power outage caused by a disaster such as a fire. Although the lighting fixture A1 is a dedicated emergency lighting fixture that provides only emergency lighting, it may be a combined battery-powered emergency lighting fixture that provides both normal lighting and emergency lighting. Alternatively, the lighting fixture A1 may be a battery-powered emergency lighting fixture other than an emergency light, for example, an emergency exit light.
[0016] (2-1) Structure of lighting fixtures (emergency lights) The lighting fixture A1 is a so-called ceiling-mounted emergency light that is attached directly to the underside (ceiling surface) of the ceiling finish material 9 (see FIG. 2). However, the lighting fixture A1 may be a so-called recessed emergency light that is attached so as to be recessed into the ceiling (ceiling finish material 9) through a hole provided in the ceiling finish material 9.
[0017] The lighting device A1 includes a main body unit 1, a light source unit 2, a battery unit 3, and a lighting unit 4 (see FIGS. 2 and 3).
[0018] (2-1-1) Main unit The main unit 1 has a disk-shaped mounting plate 10, a bucket-shaped cover 11, and a pair of mounting springs 12 (see FIG. 3).
[0019] The mounting plate 10 is made of a metal material and formed into a disk shape. A circular lead-in hole 100 is opened in the center of the mounting plate 10 (see FIG. 3). The power system P1 and the lighting device 40 of the lighting unit 4 are electrically connected via a power cable inserted into the lead-in hole 100 (see FIG. 1). The mounting plate 10 is fixed to the ceiling surface by being screwed to the ceiling finish material 9.
[0020] The pair of mounting springs 12 are each formed into a substantially diamond shape by a metal wire, and are attached to the peripheral portions of the mounting plate 10, facing each other across the center thereof.
[0021] The cover 11 is formed in a truncated cone shape (bucket shape) with an open top (see FIG. 3). However, the diameter of the top of the cover 11 is slightly larger than the diameter of the mounting plate 10. A circular window hole 110 is provided in the center of the lower surface (bottom surface) of the cover 11. A lens 21 of the light source unit 2, which will be described later, is inserted through this window hole 110. Furthermore, four holes (a first hole 111, a second hole 112, a third hole 113, and a fourth hole 114) are provided in two rows and columns near the window hole 110 on the bottom surface of the cover 11.
[0022] A pair of spring receiving members (not shown) are provided on the inner peripheral surface of the cover 11. The pair of spring receiving members are arranged at positions facing each other across the window hole 110. Each spring receiving member has a groove into which the mounting spring 12 is inserted. Thus, the cover 11 is detachably attached to the mounting plate 10 by inserting the pair of mounting springs 12 one by one into the grooves of the pair of spring receiving members (see FIGS. 2 and 3).
[0023] (2-1-2) Light source unit As shown in FIG. 3, the light source unit 2 includes an LED 20, a lens 21, a holder 22, a heat sink 23, and the like.
[0024] The LED 20 is, for example, a packaged white LED for lighting. The lens 21 is, for example, made of glass and formed in a roughly hemispherical shape. The holder 22 is, for example, made of synthetic resin such as polycarbonate resin and formed in a frame shape with an opening in the center. The heat sink 23 is formed in a U-shape from a plate material made of aluminum or an aluminum alloy. The holder 22 is screwed to the heat sink 23 with the lens 21 protruding from the opening in the center and the LED 20 and the lens 21 sandwiched between the holder 22 and the heat sink 23.
[0025] (2-1-3) Battery unit The battery unit 3 has a plurality of storage batteries 30 (three in the illustrated example) and a battery case 31 that houses the plurality of storage batteries 30 (see Figs. 1 and 3). The storage batteries 30 are cylindrical nickel-metal hydride batteries. However, the storage batteries 30 may be cylindrical or rectangular nickel-metal hydride batteries or lithium-ion batteries. The number of storage batteries 30 may be two or less or four or more, as long as the number satisfies the standard value for the lighting time required for the emergency light.
[0026] The battery case 31 is formed in a cylindrical shape with horseshoe-shaped (U-shaped) bottom surfaces on both the upper and lower sides. The multiple storage batteries 30 are housed in the battery case 31 with their axial directions aligned in the vertical direction and lined up in a row along the radial direction. A connector section 32 is provided at one end of the lower side of the battery case 31. The connector section 32 is configured to electrically connect the multiple storage batteries 30 electrically connected in series in the battery case 31 to a lighting device 40 of the lighting unit 4, which will be described later.
[0027] (2-1-4) Lighting unit The lighting unit 4 has a lighting device 40, a housing 41 that houses the lighting device 40, and a terminal block case 42 (see Figs. 1 and 3). The lighting device 40 is composed of a printed circuit. The housing 41 is made of a synthetic resin material and formed into a box shape, and is attached to the underside of the mounting plate 10 by an appropriate method such as crimping or screwing.
[0028] Terminal block case 42 is made of synthetic resin and is formed into a box shape, and is attached to housing 41 so as to cover the terminal block attached to the outer surface of housing 41. The terminal block is electrically connected to lighting device 40, and is connected to a power cable that is drawn in from lead-in hole 100 in a removable manner. In other words, lighting device 40 is electrically connected to the power cable via the terminal block.
[0029] (2-2) Circuit configuration of lighting fixtures Next, the circuit configuration of the lighting fixture A1 (lighting device 40) will be described in detail with reference to Fig. 1. Although only one storage battery 30 is shown in Fig. 1, in reality, a plurality of storage batteries 30 (e.g., three storage batteries 30) are electrically connected in series.
[0030] The lighting device 40 includes a power supply circuit section 400 , a charging circuit section 401 , a lighting circuit section 402 , a power failure detection section 403 , a control circuit section 404 , an operation input reception section 405 , and a notification section 406 .
[0031] The power supply circuit unit 400 is configured, for example, by a self-excited switching power supply circuit such as a ringing choke converter, and converts the AC voltage supplied from the power system P1 into a DC voltage lower than the effective value of the AC voltage. However, the power supply circuit unit 400 may also be configured by a power factor correction circuit and a buck converter.
[0032] The charging circuit unit 401 operates when power is supplied from the power system P1, and is configured to cause a constant charging current to flow from the power supply circuit unit 400 to the storage battery 30.
[0033] The lighting circuit unit 402 converts the direct current supplied from the storage battery 30 into a constant current and supplies it to the LED 20 .
[0034] The power failure detection unit 403 is configured to detect a power failure in the power system P1 from the output voltage of the power supply circuit unit 400 and notify the control circuit unit 404 of the detection.
[0035] The operation input acceptance unit 405 has one or more pushbutton switches and an infrared receiving module that receives a control signal using infrared rays as a medium. The operation input acceptance unit 405 accepts an operation input when the pushbutton switch is pressed, and outputs an operation input signal corresponding to the accepted operation input to the control circuit unit 404. The operation input acceptance unit 405 also accepts an operation input signal (control command) by receiving a control signal transmitted from a remote controller with the infrared receiving module, and outputs the accepted operation input signal (control command) to the control circuit unit 404. The control signal (infrared signal) is received by the infrared receiving module through a fourth hole 114 provided on the bottom surface of the cover 11.
[0036] The notification unit 406 has, for example, a green LED for display. However, the notification unit 406 may have a display device such as a liquid crystal display together with or instead of the LED for display. Furthermore, the notification unit 406 may have a piezoelectric buzzer or the like, and may notify by sound as well as light.
[0037] As explained in (1) Overview, the control circuit unit 404 includes a microcontroller having one or more processors and a memory. The control circuit unit 404 causes the one or more processors to execute programs for normal operation (charging the storage battery 30 and turning on the LED 20 in an emergency). The control circuit unit 404 also executes programs for inspection and timing, thereby realizing the functions of an inspection unit and a timing unit. The control circuit unit 404 utilizes a timer (counter) included in the microcontroller to realize the function of the timing unit.
[0038] The control circuit unit 404 operates the charging circuit unit 401 to charge the storage battery 30 with normal power supplied from the normal power source (power system P1). The control circuit unit 404 notifies that the storage battery 30 is being charged by turning on the LED of the notification unit 406. The green light emitted from the LED of the notification unit 406 is emitted to the outside of the cover 11 through a third hole 113 provided in the bottom surface of the cover 11.
[0039] Furthermore, when the control circuit unit 404 is notified by the power failure detection unit 403 that the power system P1 has experienced a power failure, it stops the charging circuit unit 401 and operates the lighting circuit unit 402 to light up the LED 20 with the emergency power supplied from the storage battery 30. Note that the control circuit unit 404 turns off the LED of the notification unit 406 while the lighting circuit unit 402 is operating.
[0040] (2-3) Inspection of lighting fixtures Next, the inspection performed on the lighting fixture A1 will be described. Emergency lights are required by law (Building Standards Act) to be switched to emergency lighting and their lighting time (time during which the light is on during an emergency) checked (inspected) once every six months. If the result of the inspection shows that the emergency lighting does not turn on or the light is turned off before the statutory emergency lighting rated time (30 minutes or 60 minutes) has elapsed, appropriate measures, such as replacing the storage battery 30 with a new one, must be taken.
[0041] (2-3-1) Basic inspection operations An inspection unit (hereinafter abbreviated as inspection unit) realized by the control circuit unit 404 controls the lighting circuit unit 402 and inspects the storage battery 30. A timing unit (hereinafter abbreviated as timing unit) realized by the control circuit unit 404 outputs an inspection start signal to cause the inspection unit to start inspection when the elapsed time reaches a predetermined interval time. The inspection unit starts inspection when it receives the inspection start signal. However, the inspection unit may also start inspection in response to an operation input signal and a control command output from the operation input receiving unit 405.
[0042] Here, the nickel-metal hydride battery used in the storage battery 30 in the embodiment has a characteristic (discharge characteristic) in which the battery voltage decreases almost linearly with respect to the discharge time, except for the period immediately after the start of discharge from full charge and immediately before the end of discharge (see FIG. 4). Therefore, during the period in which the discharge characteristic of the storage battery 30 can be considered linear, the subsequent battery voltage can be estimated from the battery voltage at any point in time.
[0043] The inspection unit stops the charging circuit unit 401 from the start of the inspection (time t=t1 in FIG. 5), and causes the lighting circuit unit 402 to light the LED 20 with emergency power supplied from the storage battery 30. Therefore, the battery voltage of the storage battery 30 decreases over time (see FIG. 5). The inspection unit stops the lighting circuit unit 402 when a first hour (e.g., 5 minutes) has elapsed from the start of the inspection (time t=t2 in FIG. 5), and operates the charging circuit unit 401 to charge the storage battery 30. Therefore, the battery voltage of the storage battery 30 increases over time (see FIG. 5). However, it is assumed that the rate of increase in the battery voltage due to charging is smaller than the rate of decrease in the battery voltage due to discharging.
[0044] Next, the inspection unit stops the charging circuit unit 401 at a point (time t=t3 in FIG. 5) when a second time (e.g., 10 minutes) has elapsed since the charging start point (time t=t2 in FIG. 5) and operates the lighting circuit unit 402 to light the LED 20. Therefore, the battery voltage of the storage battery 30 decreases over time (see FIG. 5). The inspection unit stops the lighting circuit unit 402 at a point (time t=t4 in FIG. 5) when a first time has elapsed since the operation of the lighting circuit unit 402 resumes (time t=t3 in FIG. 5) and operates the charging circuit unit 401 to charge the storage battery 30. Therefore, the battery voltage of the storage battery 30 increases over time (see FIG. 5).
[0045] Here, the inspection unit stores the measured values of the battery voltage at each of times t1, t2, t3, and t4. For example, the inspection unit estimates the battery voltage at the time (time t=t5) when the rated time of emergency lighting (e.g., 60 minutes) has elapsed from the measured value of the battery voltage of the storage battery 30 after the cumulative time of two discharges (twice the first time) has reached the inspection time. In other words, assuming that the discharge characteristic of the storage battery 30 is linear (dashed line in FIG. 5), it is possible to estimate the battery voltage at time t=t5 when the rated time has elapsed from the start of inspection based on the measured value of the battery voltage after each discharge.
[0046] Thus, the inspection unit judges whether the storage battery 30 is good or bad based on the estimated value of the battery voltage at time t=t5 when the rated time has elapsed since the start of inspection, which is estimated as described above. Specifically, the inspection unit compares the estimated value of the battery voltage at time t=t5 with a predetermined threshold value, and judges that there is no abnormality in the storage battery 30 if the estimated value is equal to or greater than the threshold value, and judges that there is an abnormality in the storage battery 30 if the estimated value is less than the threshold value. For example, when the storage battery 30 is nearing the end of its life, if the battery voltage of the storage battery 30 falls below the lower limit voltage of the lighting circuit unit 402 (the minimum voltage required to supply current to the LED 20) before the rated time is reached, current will no longer be supplied to the LED 20.
[0047] The control circuit unit 404 causes the notification unit 406 to notify the inspection result of the inspection unit (presence or absence of an abnormality in the storage battery 30). If the inspection result of the inspection unit shows that there is no abnormality in the storage battery 30, the control circuit unit 404 turns on the LED of the notification unit 406 and resumes charging by the charging circuit unit 401. On the other hand, if the inspection result of the inspection unit shows that there is an abnormality in the storage battery 30, the control circuit unit 404 notifies the abnormality in the storage battery 30 by blinking the LED of the notification unit 406 while keeping the charging circuit unit 401 stopped.
[0048] Thus, the inspection unit repeatedly charges and discharges the storage battery 30 by alternately operating the lighting circuit unit 402 and the charging circuit unit 401, and determines whether the storage battery 30 is good or bad based on the battery voltage of the storage battery 30 after the accumulated time (first time) for discharging the storage battery 30 reaches a predetermined inspection time. Therefore, the lighting device A1 can suppress the temperature rise of the storage battery 30 during inspection and suppress deterioration of the storage battery 30 caused by the temperature rise, compared to a case in which the lighting circuit unit 402 continuously lights the LED 20 up to the rated time.
[0049] (2-3-2) Automatic inspection start operation Next, the operation of the inspection unit to automatically start inspection will be described in detail with reference to Figs.
[0050] First, after the lighting fixture A1 is installed, power supply from the power system P1 is started, or after power supply from the power system P1 is started, the battery unit 3 is attached to the mounting plate 10 and electrically connected to the lighting device 40, and the lighting device 40 starts operating.
[0051] When the lighting device 40 starts operating, the timing unit starts measuring the elapsed time (the elapsed time is set to zero when the lighting device 40 starts operating) (time point S1-1 in FIG. 6). The timing unit outputs the first inspection start signal when the elapsed time reaches a first interval time T1 (e.g., 60 days) (time point S1-2 in FIG. 6). The inspection unit starts inspection when it receives the inspection start signal. Note that the timing unit stops measuring the elapsed time after outputting the inspection start signal, and starts measuring the elapsed time again after the inspection unit completes its inspection.
[0052] The timing unit outputs a second inspection start signal when the elapsed time after restart reaches a second interval time T2 (e.g., 180 days) (time point S1-3 in FIG. 6). The inspection unit starts the inspection when it receives the inspection start signal. Note that the timing unit stops counting the elapsed time after outputting the inspection start signal, and starts counting the elapsed time again after the inspection unit completes its inspection.
[0053] Furthermore, the timing unit outputs a third inspection start signal when the elapsed time after restart reaches the second interval time T2 (e.g., 180 days) (time point S1-4 in Figure 6). The inspection unit starts inspection when it receives the inspection start signal. The timing unit stops counting the elapsed time after outputting the inspection start signal, and starts counting the elapsed time again after the inspection unit completes its inspection. Thereafter, the timing unit outputs a third, fourth, fifth, ... inspection start signal each time the elapsed time after restart reaches the second interval time T2 (e.g., 180 days).
[0054] Thus, when the elapsed time measured by the timer unit reaches the interval time (first interval time T1 and second interval time T2), the lighting device A1 outputs an inspection start signal to the inspection unit to start the inspection. Therefore, the lighting device A1 does not require manual work to start the inspection as in the conventional example, and therefore can reduce the workload required for inspection compared to the conventional example. Furthermore, the lighting device A1 can detect initial defects in the storage battery 30 at an early stage by performing the first inspection in a shorter period of time than the second and subsequent inspections.
[0055] If the inspection determines that there is an abnormality in the storage battery 30, the battery unit 3 of the lighting fixture A1 is replaced. The worker performing the replacement removes the cover 11 from the mounting plate 10 while continuing the power supply from the power system P1, and replaces the battery unit 3. If the supply of charging current from the charging circuit unit 401 is stopped and then resumed, the control circuit unit 404 determines that the battery unit 3 has been replaced, and resets the elapsed time measured by the timer unit. Furthermore, when the battery unit 3 is replaced and a new storage battery 30 is connected to the charging circuit unit 401, the control circuit unit 404 causes the charging circuit unit 401 to start supplying a charging current.
[0056] Alternatively, after installing a new battery unit 3, an operator may press an operation member 4050 (see FIG. 2) protruding from the first hole 111 of the cover 11 to cause the operation input receiving unit 405 to receive an operation input. The operation input receiving unit 405 outputs an operation input signal corresponding to the received operation input to the control circuit unit 404. The control circuit unit 404 resets the elapsed time of the timer unit based on the operation input signal received from the operation input receiving unit 405.
[0057] When the storage battery 30 (battery unit 3) is replaced, the timer starts measuring the time that has elapsed since the replacement (time point S2-1 in FIG. 7). When the elapsed time reaches a predetermined charging time T3 (e.g., 48 hours), the timer resets the elapsed time and starts measuring from zero again (time point S2-2 in FIG. 7). The charging time T3 is the time required to fully charge a new battery unit 3 (storage battery 30).
[0058] The timing unit outputs the first inspection start signal when the elapsed time since the completion of charging of the storage battery 30 reaches the second interval time T2 (e.g., 180 days) (time point S2-3 in FIG. 7). The timing unit stops timing the elapsed time after outputting the inspection start signal, and restarts timing the elapsed time after the inspection unit completes inspection. Thereafter, the timing unit outputs a second, third, fourth, ... inspection start signal each time the elapsed time since resumption reaches the second interval time T2 (e.g., 180 days).
[0059] Thus, after charging of the replaced storage battery 30 is completed, the lighting fixture A1 causes the timer unit to resume timing of the elapsed time until the start of inspection, thereby making it possible to avoid starting inspection when the storage battery 30 is not fully charged.
[0060] Incidentally, in lighting device A1, if a power outage occurs before the elapsed time reaches second interval time T2 (time point S3-1 in FIG. 8), control circuit unit 404 operates lighting circuit unit 402 to emergency light LED 20. Note that control circuit unit 404 causes the timer unit to measure the time during which LED 20 is turned on (hereinafter referred to as lighting time).
[0061] When the power system P1 is restored, the control circuit unit 404 compares the lighting time Ton measured by the timer unit with an upper limit time (e.g., 30 minutes) (times S3-2 and S3-4 in FIG. 8). When the lighting time Ton exceeds the upper limit time, the timer unit resets the elapsed time and restarts timing from zero. Then, the timer unit outputs an inspection start signal when the elapsed time after the power recovery reaches a second interval time T2 (e.g., 180 days) (time S3-3 in FIG. 8). The timer unit stops timing the elapsed time after outputting the inspection start signal, and starts timing the elapsed time anew after the inspection by the inspection unit is completed. In other words, when the lighting time of the LED 20 exceeds the upper limit time, the timer unit does not output an inspection start signal until the elapsed time reaches the second interval time T2. That is, when the lighting time Ton of the LED 20 exceeds the upper limit time, it is practically the case that the storage battery 30 has been inspected, so that unnecessary inspections can be avoided and deterioration of the storage battery 30 can be suppressed. The timing unit outputs an inspection start signal every time the elapsed time after restart reaches a second interval time T2 (for example, 180 days).
[0062] On the other hand, if the lighting time Ton does not exceed the upper limit time, the timing unit continues timing without resetting the elapsed time (time point S3-4 in FIG. 8). Then, the timing unit outputs an inspection start signal when the elapsed time since the completion of the previous inspection reaches a second interval time T2 (e.g., 180 days) (time point S3-5 in FIG. 8). The timing unit stops timing the elapsed time after outputting the inspection start signal, and starts timing the elapsed time anew after the inspection of the inspection unit is completed. Thereafter, the timing unit outputs an inspection start signal every time the elapsed time reaches the second interval time T2 (e.g., 180 days).
[0063] Thus, if the lighting time Ton does not exceed the upper limit time, the timer unit outputs an inspection start signal each time the elapsed time reaches the second interval time T2. In other words, if the lighting time Ton does not exceed the upper limit time, inspection is not actually performed, so regular inspection can be performed automatically by having the timer unit continue to count the elapsed time.
[0064] Here, the timer unit may set a plurality of interval times according to the operation input received by operation input receiving unit 405. For example, operation input receiving unit 405 may be configured to have a DIP switch that allows six interval times from one month to six months to be selected by the DIP switch. This allows lighting device A1 to have a greater degree of freedom in setting the inspection period (interval time), thereby improving usability.
[0065] Furthermore, the timer unit may reset the measurement of the elapsed time in response to operation input received by operation input receiving unit 405. In other words, if lighting device A1 is able to reset the elapsed time by the timer unit by operating operation input receiving unit 405, it is possible to avoid unnecessary inspections being performed due to, for example, an incorrect setting of the interval time.
[0066] Furthermore, if the normal power source (power system P1) fails during inspection and then is restored, the inspection unit resumes the inspection after charging of the storage battery 30 by the charging circuit unit 401 is completed. In this case, however, the duration of the normal power source failure is longer than a so-called momentary power failure (a power failure lasting from a few seconds to about one minute) and shorter than the rated time of emergency lighting (for example, from a few minutes to a dozen minutes). Note that, when resuming inspection, the inspection unit preferably resets the accumulated time due to repeated charging and discharging performed before the power failure occurred.
[0067] Thus, if a relatively long power outage occurs during inspection of the lighting device A1, the inspection can be resumed after the storage battery 30 is fully charged, thereby improving the accuracy of determining whether the storage battery 30 is good or bad.
[0068] On the other hand, when the inspection unit resumes inspection after a momentary power outage, it is preferable that the inspection unit continue the inspection without resetting the accumulated time due to repeated charging and discharging performed up until the momentary power outage occurred when power is restored from the momentary power outage.
[0069] In the case of a momentary power outage, the time for which the lighting circuit unit 402 provides emergency lighting is extremely short, so it is preferable that, after power is restored from the momentary power outage, the lighting device A1 has the inspection unit continue the inspection without recharging the storage battery 30. As a result, the lighting device A1 can reliably perform the inspection.
[0070] Incidentally, lighting device 40 of lighting fixture A1 may have a determination unit instead of a clock unit. However, like the clock unit, the determination unit is preferably realized by causing a processor of a microcontroller included in control circuit unit 404 to execute a determination program.
[0071] The determination unit (hereinafter, abbreviated as the determination unit) realized by the control circuit unit 404 determines whether the scheduled time when the inspection unit is to perform the inspection matches or does not match the current time. For this reason, the determination unit keeps track of the current time (date and time) using the RTC (real-time clock) function installed in the microcontroller. Note that the current time kept by the determination unit is preferably set according to the operation input received by the operation input receiving unit 405. Also, it is preferable that the determination unit sets the inspection start time to a fixed time (for example, midnight) every six months, starting from the time when the current time is set.
[0072] When the current time coincides with the scheduled time, the determination unit outputs an inspection start signal to the inspection unit to cause the inspection unit to start inspection. Upon receiving the inspection start signal, the inspection unit starts inspection.
[0073] As described above, lighting fixture A1 automatically performs inspections according to a predetermined schedule, eliminating the need for manual intervention to start the inspection as in the conventional example. This reduces the workload required for inspection compared to the conventional example.
[0074] (3) Modifications of the embodiment Next, modified examples of the lighting fixture A1 according to the embodiment will be described. However, the basic configuration of the lighting fixture A1 of the modified example described below is the same as the basic configuration of the lighting fixture A1 according to the embodiment. Therefore, the same reference numerals will be used to designate configurations that are common to the basic configuration of the lighting fixture A1 according to the embodiment, and illustrations and descriptions thereof will be omitted as appropriate. In the following description, "substantially common configuration" refers to configurations that are slightly different in shape, size, etc., but have the same function.
[0075] The inspection unit in the modified example is characterized in that the time (inspection time) during which the lighting circuit unit 402 and the charging circuit unit 401 are alternately operated to repeatedly charge and discharge the storage battery 30 is set to a time equal to the rated time for emergency lighting.
[0076] The inspection unit in the modified example stops the charging circuit unit 401 from the start of inspection (time t=t1 in FIG. 9), and causes the lighting circuit unit 402 to light the LED 20 with emergency power supplied from the storage battery 30. The inspection unit in the modified example also stops the lighting circuit unit 402 when a first hour (e.g., 5 minutes) has elapsed from the start of inspection (time t=t2 in FIG. 9), and operates the charging circuit unit 401 to charge the storage battery 30. Then, the inspection unit in the modified example intermittently repeats charging and discharging the storage battery 30 until the accumulated time of the first hour reaches the inspection time (rated time for emergency lighting) (time t=t13 in FIG. 9).
[0077] When the cumulative time exceeds the inspection time, the inspection unit in the modified example estimates the battery voltage at the time when the actual rated time (e.g., 60 minutes) has elapsed (time t=t9 in FIG. 9) from the measured value of the battery voltage of the storage battery 30 when the inspection time is reached (time t=t13 in FIG. 9). In other words, assuming that the discharge characteristic of the storage battery 30 is linear (dashed line in FIG. 9), the battery voltage at time t=t9 when the rated time has elapsed from the start of inspection can be estimated based on the measured value of the battery voltage after each discharge. Therefore, the inspection unit can determine the quality of the storage battery 30 based on the estimated value of the battery voltage at time t=t9 when the rated time has elapsed from the start of inspection, which is estimated as described above.
[0078] Thus, lighting fixture A1 of the modified example sets the inspection time by the inspection unit (the accumulated time of the first hour for discharging storage battery 30) to be equal to the rated time for turning on LED 20 during a power outage. Therefore, lighting fixture A1 of the modified example can improve the accuracy of determining whether storage battery 30 is good or bad while suppressing the temperature rise of storage battery 30 during inspection and suppressing deterioration of storage battery 30.
[0079] (4) Summary The lighting fixture (A1) according to the first aspect of the present disclosure includes a light source (LED 20), a replaceable storage battery (30), a charging circuit unit (401), a lighting circuit unit (402), an inspection unit (control circuit unit 404), and a timer unit (control circuit unit 404) that measures an elapsed time. The charging circuit unit (401) charges the storage battery (30) with normal power supplied from a normal power source (power system P1). The lighting circuit unit (402) lights the light source with emergency power supplied from the storage battery (30). The inspection unit controls the charging circuit unit (401) and the lighting circuit unit (402) to inspect the storage battery (30). The timer unit outputs an inspection start signal to the inspection unit to start inspection when the elapsed time reaches a predetermined interval. Upon receiving the inspection start signal, the inspection unit starts inspection and alternately operates the lighting circuit unit (402) and the charging circuit unit (401) to repeatedly charge and discharge the storage battery (30). The inspection unit determines whether the storage battery (30) is good or bad based on the battery voltage of the storage battery (30) after the accumulated time of discharging the storage battery (30) reaches a predetermined inspection time.
[0080] The lighting fixture (A1) according to the first aspect outputs an inspection start signal to the inspection unit to start the inspection when the elapsed time measured by the timer unit reaches the interval time, eliminating the need for manual work to start the inspection as in the conventional example. As a result, the lighting fixture (A1) according to the first aspect can reduce the workload required for inspection compared to the conventional example. Furthermore, in the lighting fixture (A1) according to the first aspect, the inspection unit alternately operates the lighting circuit unit (402) and the charging circuit unit (401) to repeatedly charge and discharge the storage battery (30), and determines whether the storage battery (30) is good or bad based on the battery voltage of the storage battery (30) after the accumulated time of discharging the storage battery (30) reaches a predetermined inspection time. Therefore, the lighting fixture (A1) according to the first aspect can suppress a temperature rise of the storage battery (30) during inspection, and suppress deterioration of the storage battery (30) caused by the temperature rise.
[0081] A lighting device (A1) according to a second aspect of the present disclosure can be realized by combining it with the first aspect. In the lighting device (A1) according to the second aspect, it is preferable that the inspection unit repeatedly operates the lighting circuit unit (402) for a first time and then operates the charging circuit unit (401) for a second time that is longer than the first time.
[0082] In the lighting fixture (A1) according to the second aspect, the charging time (second time) is made longer than the discharging time (first time), so that the storage battery (30) is less likely to become insufficiently charged when emergency lighting is performed during inspection.
[0083] A lighting fixture (A1) according to a third aspect of the present disclosure can be realized in combination with the lighting fixture (A1) according to the first or second aspect. In the lighting fixture (A1) according to the third aspect, the inspection time is preferably shorter than a rated time for which the light source should be turned on during a power outage.
[0084] The lighting fixture (A1) according to the third aspect can reduce the time required for inspection.
[0085] A lighting fixture (A1) according to a fourth aspect of the present disclosure can be realized in combination with the lighting fixture (A1) according to the first or second aspect. In the lighting fixture (A1) according to the fourth aspect, it is preferable that the inspection time is equal to a rated time for which the light source should be turned on during a power outage.
[0086] The lighting device (A1) according to the fourth aspect can improve the accuracy of determining whether the storage battery (30) is good or bad.
[0087] A lighting device (A1) according to a fifth aspect of the present disclosure can be realized by combining with any one of the first to fourth aspects. In the lighting device (A1) according to the fifth aspect, it is preferable that the timer unit starts measuring the elapsed time from the time when the charging circuit unit (401) and the storage battery (30) are electrically connected.
[0088] In the lighting fixture (A1) according to the fifth aspect, when the storage battery (30) is replaced, the timer unit starts measuring the elapsed time from the time of replacement, so that the replaced storage battery (30) can also be automatically inspected. As a result, the lighting fixture (A1) according to the fifth aspect can further reduce the workload required for inspection.
[0089] A lighting device (A1) according to a sixth aspect of the present disclosure can be realized in combination with the fifth aspect. In the lighting device (A1) according to the sixth aspect, when the storage battery (30) is replaced, it is preferable that the timing unit starts measuring the elapsed time from the time when charging of the new storage battery (30) after replacement is completed.
[0090] The lighting fixture (A1) according to the sixth aspect can prevent inspection from being started when the storage battery (30) is not fully charged.
[0091] A lighting fixture (A1) according to a seventh aspect of the present disclosure can be realized by combining it with any one of the first to sixth aspects. In the lighting fixture (A1) according to the seventh aspect, when the utility power source is interrupted during inspection and then restored, the inspection unit preferably resumes the inspection after charging of the storage battery (30) by the charging circuit unit (401) is completed.
[0092] The lighting fixture (A1) according to the seventh aspect can avoid inspection of the storage battery (30) when it is insufficiently charged, and can improve the accuracy of determining whether the storage battery (30) is good or bad.
[0093] A lighting device (A1) according to an eighth aspect of the present disclosure can be realized in combination with the seventh aspect. In the lighting device (A1) according to the eighth aspect, when restarting inspection, it is preferable that the inspection unit resets the accumulated time of repeated charging and discharging performed before the power outage.
[0094] The lighting fixture (A1) according to the eighth aspect can improve the accuracy of determining whether the storage battery (30) is good or bad by restarting the inspection from the beginning.
[0095] A lighting fixture (A1) according to a ninth aspect of the present disclosure can be realized by combining it with any one of the first to eighth aspects. In the lighting fixture (A1) according to the ninth aspect, if the utility power source experiences a momentary power outage during inspection, it is preferable that the inspection unit continues the inspection when power is restored from the momentary power outage.
[0096] The lighting fixture (A1) according to the ninth aspect allows inspection to be carried out reliably.
[0097] A lighting device (A1) according to a tenth aspect of the present disclosure may be realized by combining it with any one of the first to ninth aspects. The lighting device (A1) according to the tenth aspect preferably further includes an operation input receiving unit (405) that receives an operation input. The timer unit preferably sets a plurality of interval times in response to the operation input received by the operation input receiving unit (405).
[0098] The lighting fixture (A1) according to the tenth aspect can increase the degree of freedom in setting the period (interval time) for inspection, thereby improving usability. [Explanation of symbols]
[0099] A1 Lighting equipment P1 Power system (regular power supply) 20 LEDs (light source) 30 Storage battery 400 Power supply circuit section 401 Charging circuit section 402 Lighting circuit section 404 Control circuit section (inspection section, timing section) 405 Operation input reception unit
Claims
1. A light source; A replaceable battery, A charging circuit unit that charges the storage battery with normal power supplied from a normal power source; a lighting circuit unit that lights up the light source with emergency power supplied from the storage battery; an inspection unit that controls the charging circuit unit and the lighting circuit unit to inspect the storage battery; A timing unit that measures an elapsed time; Equipped with the timer unit outputs an inspection start signal to the inspection unit when the elapsed time reaches a predetermined interval time, to cause the inspection unit to start the inspection; the inspection unit starts the inspection when it receives the inspection start signal, alternately operates the lighting circuit unit and the charging circuit unit to repeatedly charge and discharge the storage battery, and determines whether the storage battery is good or bad based on the battery voltage of the storage battery after a cumulative time of discharging the storage battery reaches a predetermined inspection time. Lighting fixtures.
2. the inspection unit repeatedly operates the lighting circuit unit for a first time period and then operates the charging circuit unit for a second time period that is longer than the first time period; 2. The lighting device of claim 1.
3. The inspection time is shorter than a rated time for which the light source should be turned on during a power outage.
3. A lighting fixture according to claim 1 or 2.
4. The inspection time is equal to the rated time for which the light source should be turned on during a power outage.
3. A lighting fixture according to claim 1 or 2.
5. the timer unit starts measuring the elapsed time from a point in time when the charging circuit unit and the storage battery are electrically connected to each other.
3. A lighting fixture according to claim 1 or 2.
6. when the storage battery is replaced, the timer starts measuring the elapsed time from a point in time when charging of the new storage battery after replacement is completed.
6. A lighting device according to claim 5.
7. When the normal power supply is powered off during the inspection and then restored, the inspection unit resumes the inspection after charging of the storage battery by the charging circuit unit is completed.
3. A lighting fixture according to claim 1 or 2.
8. When the inspection unit resumes the inspection, the inspection unit resets the accumulated time due to the repetition of charging and discharging performed up until the power outage.
8. A lighting device according to claim 7.
9. When the normal power supply is momentarily interrupted during the inspection, the inspection unit continues the inspection when power is restored from the momentary interruption.
3. A lighting fixture according to claim 1 or 2.
10. Further comprising an operation input receiving unit for receiving an operation input, the timekeeping unit sets a plurality of the interval times in response to the operation input accepted by the operation input accepting unit.
3. A lighting device according to claim 1 or 2.
Citation Information
Patent Citations
Power failure recovery processing method and device therefor
JP1997325836A
Emergency illumination automatic check system
JP2007035428A
Emergency lighting device
JP2007188790A
Lighting apparatus and system
JP2007200911A
Emergency lighting device and emergency lighting apparatus
JP2012113877A