The control system optimizes power distribution and consumption in AC/DC hybrid wiring systems by measuring current values and adjusting charging and discharging power, addressing complex control issues in systems with EV normal chargers, EV quick chargers, storage batteries, and V2X devices.

JP2024161830APending Publication Date: 2024-11-20KAWAMURA ELECTRIC INC
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2023076899
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-08
Publication Date
2024-11-20

AI Technical Summary

Technical Problem

Existing AC/DC hybrid wiring systems with EV normal chargers, EV quick chargers, storage batteries, and V2X devices face complex charging and discharging control due to the need to manage power distribution based on measured values at a power receiving point, leading to complicated charging control.

Method used

A control system that includes a control unit, multiphase transformer, and rectifier unit to simplify charging control by measuring current values and deriving power supply based on target values, adjusting charging and discharging power accordingly.

Benefits of technology

The system simplifies charging and discharging control by optimizing power distribution and consumption based on current measurements, reducing power consumption and enhancing efficiency in AC/DC hybrid wiring systems.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024161830000001_ABST
    Figure 2024161830000001_ABST
Patent Text Reader

Abstract

To provide a control system and a control method capable of simplifying charging control.SOLUTION: A control system includes: a first electrical installation that supplies power to a first charger; a second electrical installation to which power is supplied from at least a power generation system and which supplies the power to a second charger; a first current measuring unit that measures a first current value supplied to the second electrical installation; and a control unit that creates control information for the first charger and the second charger to control the charging power value based on the first current value measured by the first current measuring unit.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a control system and a control method. [Background technology]

[0002] There is a known technology for limiting the power received from a commercial power source to a target while making effective use of both an on-board battery and a stationary battery when both batteries are provided (see, for example, Patent Document 1). This technology is provided with a control device that controls the charging and discharging power of the on-board battery and the stationary battery in a power supply system in which the on-board battery, the stationary battery, and the commercial power source are connected to a load, and controls the power received from the commercial power source. The on-board battery and the stationary battery are connected to the commercial power source on the distal side of the receiving point of the commercial power source via a power conversion device, and the control device determines the power distribution of the charging power and discharging power between the on-board battery and the stationary battery according to the charging state of the on-board battery. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] JP 2020-202623 A Summary of the Invention [Problem to be solved by the invention]

[0004] In an AC / DC hybrid wiring system that distributes AC power and DC power, charging and discharging are controlled based on, for example, the power receiving point and the measured values ​​of the EV power. For example, in an AC / DC hybrid wiring system, an EV normal charger is installed in the AC power distribution, and a PV, EV quick charger, storage battery, and V2X (EV charger / discharger) are installed in the DC power distribution. In this case, charging and discharging control of the EV normal charger, EV quick charger, storage battery, and V2X is performed based on the measured values ​​of the power receiving point and the EV, making the charging and discharging control complicated. If charging control of the EV normal charger and EV quick charger were to be performed, the charging control would be complicated. An object of the present invention is to provide a control system and a control method that can simplify charging control. [Means for solving the problem]

[0005] (1) One aspect of the present invention is a control system comprising: a first electrical equipment that supplies power to a first charger; a second electrical equipment that receives power from at least a power generation system and supplies power to a second charger; a first current measuring unit that measures a first current value supplied to the second electrical equipment; and a control unit that creates control information for the first charger and the second charger to control a charging power value based on the first current value measured by the first current measuring unit.

[0006] (2) In one aspect of the present invention, in the control system described in (1) above, the first electrical equipment supplies AC power to the first charger, and the second electrical equipment supplies DC power to the second charger.

[0007] (3) In one aspect of the present invention, the control system described in (1) above further includes a polyphase transformer that converts a system into polyphase AC, and a rectifier unit that converts the polyphase AC into a DC voltage, wherein the first electrical equipment is supplied with AC voltage from the polyphase transformer, and the second electrical equipment is supplied with DC voltage from the rectifier unit.

[0008] (4) In one aspect of the present invention, in the control system described in (1) above, the control unit derives a first supply power to be supplied to the second electrical equipment based on the first current value, creates control information including information indicating the derived first supply power and information indicating a predetermined target value of power to be supplied to the second electrical equipment, and the second charger reduces charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electrical equipment based on the information indicating the first supply power and the information indicating the target value of power to be supplied to the second electrical equipment.

[0009] (5) In one aspect of the present invention, in the control system described in (3) above, the control system further includes a second current measuring unit that measures a second current value supplied to the multi-phase transformer, and the control unit creates control information for the first charger and the second charger to control the charging power value based on the second current value.

[0010] (6) In one aspect of the present invention, in the control system described in (5) above, the control unit derives a second power consumption of the control system based on the second current value, and creates control information including information indicating the derived second power consumption and information indicating a predetermined target value of power consumption of the control system, and the second charger reduces charging power when the second power consumption is equal to or greater than the target value of power consumption of the control system based on the information indicating the second power consumption and the information indicating the target value of power consumption of the control system.

[0011] (7) One aspect of the present invention is the control system described in (1) above, wherein a storage battery is connected to the second electrical equipment, and the control unit derives a first supply power to be supplied to the second electrical equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a predetermined target value of power to be supplied to the second electrical equipment, and when the storage battery is charging, increases the charging power when the first supply power is less than the target value of power to be supplied to the second electrical equipment, and reduces the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electrical equipment, and when the storage battery is discharging, increases the discharging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electrical equipment, and reduces the discharging power when the first supply power is less than the target value of power.

[0012] (8) In one aspect of the present invention, in the control system described in (1) above, an EV charger / discharger is connected to the second electric equipment, and the control unit derives a first supply power to be supplied to the second electric equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a predetermined target value of power to be supplied to the second electric equipment, and the EV charger / discharger, when charging, increases the charging power when the first supply power is less than the target value of power to be supplied to the second electric equipment and decreases the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and when discharging, increases the discharging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment and decreases the discharging power when the first supply power is less than the target value of power to be supplied to the second electric equipment.

[0013] (9) In one aspect of the present invention, in the control system described in (1) above, the control system further includes a third current measuring unit that measures a third current value supplied by the power generation system, and the control unit creates control information for the first charger and the second charger to control the charging power value based on the third current value.

[0014] (10) One aspect of the present invention is the control system described in (1) above, wherein the control unit derives a third generated power supplied from the power generation system to a second electrical equipment based on the third current value measured by the third current measuring unit, creates control information including information indicating the derived third generated power and information indicating a preset threshold value of the generated power of the power generation system, and the second charger reduces charging power when the third generated power is equal to or less than the threshold value of the generated power of the power generation system based on the information indicating the third generated power and the information indicating the threshold value of the generated power of the power generation system included in the control information.

[0015] (11) One aspect of the present invention is a control method executed by a control system including a first electrical equipment that supplies power to a first charger, a second electrical equipment that receives power from at least a power generation system and supplies power to a second charger, and a first current measuring unit that measures a first current value supplied to the second electrical equipment, the control method including the steps of: creating control information for the first charger and the second charger to control a charging power value based on the first current value measured by the first current measuring unit; and outputting the control information created in the creating step. Effect of the Invention

[0016] According to the present invention, it is possible to provide a control system and a control method that can simplify charging control. [Brief description of the drawings]

[0017] [Figure 1] 1 is a diagram illustrating an example of a control system 1 according to an embodiment of the present invention. [Diagram 2] 4 is a flowchart showing an example of the operation of the control system 1 according to the present embodiment. [Diagram 3] 4 is a flowchart showing an example of the operation of the control system 1 according to the present embodiment. [Figure 4] 4 is a flowchart showing an example of the operation of the control system 1 according to the present embodiment. [Diagram 5] FIG. 13 is a diagram illustrating an example of a control system 1a according to a modified example of the embodiment. [Figure 6] 13 is a flowchart showing an example of the operation of a control system 1a according to a modified example of the embodiment. [Figure 7] 13 is a flowchart showing an example of the operation of a control system 1a according to a modified example of the embodiment. [Figure 8] 13 is a flowchart showing an example of the operation of a control system 1a according to a modified example of the embodiment. [Figure 9] 13 is a flowchart showing an example of the operation of a control system 1a according to a modified example of the embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] Next, the control system and the control method of the present embodiment will be described with reference to the drawings. The embodiment described below is merely an example, and the embodiment to which the present invention is applied is not limited to the following embodiment. In all the drawings for explaining the embodiment, the same reference numerals are used for the parts having the same functions, and the repeated description will be omitted. In addition, "based on XX" in this application means "based on at least XX," and includes cases where it is based on other elements in addition to XX. Furthermore, "based on XX" is not limited to cases where XX is used directly, but also includes cases where it is based on XX that has been calculated or processed. "XX" is any element (for example, any information).

[0019] (Embodiment) (Control System) FIG. 1 is a diagram showing an example of a control system 1 according to an embodiment of the present invention. An example of the control system 1 is a system that controls an AC / DC hybrid wiring system that distributes AC power and DC power. The control system 1 includes a control unit 100, a transformer 200, a rectifier unit 300, a current measurement unit 50-A, a breaker 60-1 for an electric vehicle (EV) normal charger, a breaker 60-2 for an electric vehicle normal charger, a DC breaker 60-3 for a photovoltaic (PV) charger, a DC breaker 60-4 for an EV rapid charger, a DC breaker 60-5 for an EV rapid charger, a DC breaker 60-6 for an EV rapid charger, a DC breaker 60-7 for a vehicle to X (V2X), and a DC breaker 60-8 for a storage battery. The control unit 100, the transformer 200, and the rectifier unit 300 are included in a power supply facility device PE.

[0020] An example of the transformer 200 is a polyphase transformer that is connected to the commercial grid CS by a power line and converts the commercial grid CS into an AC voltage (e.g., AC 200V) and outputs it to a single-phase three-wire power line (transmission line). The power line is connected to an EV normal charger breaker 60-1 and an EV normal charger breaker 60-2 included in an AC distribution board ACDB.

[0021] An EV normal charger 80-1 is connected to the EV normal charger breaker 60-1 by a power line, and a terminal 70-1 is connected to the EV normal charger 80-1. An EV normal charger 80-2 is connected to the EV normal charger breaker 60-2 by a power line, and a terminal 70-2 is connected to the EV normal charger 80-2. The AC distribution board ACDB branches the AC power and supplies it to a normal EV charger 80-1 and a normal EV charger 80-2 via a normal EV charger breaker 60-1 and a normal EV charger breaker 60-2, respectively. An electric vehicle EV can be connected to each of the normal EV charger 80-1 and the normal EV charger 80-2.

[0022] Moreover, the transformer 200 is connected to the rectifier unit 300 by a power line, and converts the commercial system CS into a polyphase alternating current voltage (polyphase AC) and outputs it to the rectifier unit 300. The rectifier unit 300 converts the polyphase AC output by the transformer 200 into a direct current voltage (e.g., DC 380V). The rectifier unit 300 is connected to the current measuring unit 50-A by a power line, and is connected via the current measuring unit 50-A to a DC breaker 60-3 for PV, a DC breaker 60-4 for EV quick charger, a DC breaker 60-5 for EV quick charger, a DC breaker 60-6 for EV quick charger, a DC breaker 60-7 for V2X, and a DC breaker 60-8 for the storage battery, which are included in the DC distribution board DCDB, by power lines.

[0023] A PV DC (direct current)-PCS (Power Conditioning Subsystem) 90-3 is connected to the PV DC breaker 60-3 via a power line. A power generation system is connected to the PV DC-PCS 90-3. One example of the power generation system is one that utilizes renewable energy such as solar cells (PV).

[0024] An EV quick charger 80-4 is connected to the EV quick charger DC breaker 60-4 by a power line, and a terminal 70-4 is connected to the EV quick charger 80-4. An EV quick charger 80-5 is connected to the EV quick charger DC breaker 60-5 by a power line, and a terminal 70-5 is connected to the EV quick charger 80-5. An EV quick charger 80-6 is connected to the EV quick charger DC breaker 60-6 by a power line, and a terminal 70-6 is connected to the EV quick charger 80-6.

[0025] A V2X device 80-7 is connected to the V2X DC breaker 60-7 via a power line, and a terminal 70-7 is connected to the V2X device 80-7. A storage battery PCS 90-8 is connected to the storage battery DC breaker 60-8 via a power line, and a terminal 70-8 and a storage battery SB are connected to the storage battery PCS 90-8. The DC distribution board DCDB branches the DC power and supplies it to EV quick charger 80-4, EV quick charger 80-5, EV quick charger 80-6, V2X equipment 80-7 and PCS 90-8 for the storage battery via DC breaker 60-4 for EV quick charger, DC breaker 60-5 for EV quick charger, DC breaker 60-6 for EV quick charger, DC breaker 60-7 for V2X and DC breaker 60-8 for the storage battery, respectively.

[0026] A PV DC breaker 60-3, an EV quick charger DC breaker 60-4, an EV quick charger DC breaker 60-5, an EV quick charger DC breaker 60-6, a V2X DC breaker 60-7 and a storage battery DC breaker 60-8 are connected to the current measurement unit 50-A by power lines. An electric vehicle EV can be connected to each of EV rapid charger 80-4, EV rapid charger 80-5, EV rapid charger 80-6, and V2X device 80-7. Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-8 are connected to control unit 100 by communication lines. The current measuring unit 50-A measures the value of a current supplied from the rectifier unit 300 to the DC distribution board DCDB (hereinafter referred to as a "first current value"). The control unit 100 acquires a first current value from the current measurement unit 50-A. Based on the acquired first current value, the control unit 100 creates control information for the EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6, V2X device 80-7, and storage battery PCS 90-8 to control the charging power value or discharging power value.

[0027] Specifically, the control unit 100 acquires an output voltage value of the power supply equipment device PE. For example, a voltage measurement unit (not shown) that measures the output voltage value of the power supply equipment device PE may be provided, and the control unit 100 may acquire the output voltage value of the power supply equipment device PE from the voltage measurement unit. The control unit 100 derives the power (hereinafter referred to as the "first supply power") to be supplied to the DC distribution board DCDB based on the output voltage value and the first current value.

[0028] The control unit 100 has a target value of the power to be supplied to the DC distribution board DCDB set in advance. An example of the target value of the power to be supplied to the DC distribution board DCDB is determined based on the power that can be supplied from the transformer 200 to the DC distribution board DCDB. For example, an example of the target value of the power to be supplied to the DC distribution board DCDB may be any ratio that is greater than 0% and less than 100% of the power that can be supplied from the transformer 200 to the DC distribution board DCDB. More specifically, an example of the target value of the power to be supplied to the DC distribution board DCDB may be 20% or more and 80% or less, or 40% or more and 60% or less, of the power that can be supplied to the DC distribution board DCDB. The control unit 100 creates control information including information indicating the first supply power and information indicating the target value of the power to be supplied to the DC distribution board DCDB. The control unit 100 transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8. In the control unit 100, a current value (offset current value) for causing a current to flow from the rectifier unit 300 to the DC distribution board DCDB is set in the current measuring unit 50-A based on the number of devices connected to the DC distribution board DCDB. This current value is set by a terminal device such as a smartphone or a tablet computer when the control system 1 is installed.

[0029] Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-8 are realized by devices such as personal computers, servers, smartphones, tablet computers, industrial computers, or dedicated devices having a communication function with a control unit and control devices. Here, the control devices are EV normal charger 80-1, EV normal charger 80-2, EV quick charger 80-4 to EV quick charger 80-6, V2X device 80-7, and storage battery PCS 90-8. The terminals 70-1 and 70-2 receive the control information transmitted by the control unit 100. The terminals 70-1 and 70-2 acquire information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, which are included in the received control information. Based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, the terminals 70-1 and 70-2 continue charging with the charging power requested by the electric vehicles EV connected to the EV normal charger 80-1 and EV normal charger 80-2, respectively, when the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, and reduce the charging power supplied to the electric vehicles EV connected to the EV normal charger 80-1 and EV normal charger 80-2, respectively, when the first supply power is equal to or greater than the target value of the power supplied to the DC distribution board DCDB.

[0030] The terminals 70-4 to 70-6 receive the control information transmitted by the control unit 100. The terminals 70-4 to 70-6 acquire information indicating the first supply power and information indicating a target value of the power supplied to the DC distribution board DCDB, which are included in the received control information. Based on the acquired information indicating the first supply power and information indicating the target value of the power to be supplied to DC distribution board DCDB, if the first supply power is less than the target value of the power to be supplied to DC distribution board DCDB, terminals 70-4 to 70-6 continue charging at the charging power requested by electric vehicles EV connected respectively to EV rapid charger 80-4 to EV rapid charger 80-6, and if the first supply power is equal to or greater than the target value of the power, reduce the charging power supplied to electric vehicles EV connected respectively to EV rapid charger 80-4 to EV rapid charger 80-6.

[0031] The terminal 70-7 receives the control information transmitted by the control unit 100. The terminal 70-7 acquires information indicating the first supply power and information indicating a target value of the power supplied to the DC distribution board DCDB, which are included in the received control information. The terminal 70-7 increases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, and decreases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the first supply power is equal to or greater than the target value of the power supplied to the DC distribution board DCDB.

[0032] Based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, the terminal 70-7 reduces the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, and increases the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the first supply power is equal to or greater than the target value of the power supplied to the DC distribution board DCDB.

[0033] The terminal 70-8 receives the control information transmitted by the control unit 100. The terminal 70-8 acquires information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, which are included in the received control information. The terminal 70-8 increases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, based on the acquired information indicating the first supply power and the information indicating the target value of the power supplied to the DC distribution board DCDB, and decreases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the first supply power is equal to or greater than the target value of the power supplied to the DC distribution board DCDB.

[0034] Based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, the terminal 70-8 reduces the discharge power of the storage battery SB connected to the storage battery PCS90-8 when the storage battery PCS90-8 is discharging and the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, and increases the discharge power of the storage battery SB connected to the storage battery PCS90-8 when the storage battery PCS90-8 is discharging and the first supply power is equal to or greater than the target value of the power supplied to the DC distribution board DCDB.

[0035] (Control system operation) Fig. 2 is a flowchart showing an example of the operation of the control system 1 according to this embodiment. With reference to Fig. 2, a process from when the control system 1 measures the first current value to when it transmits control information will be described. (Step S1-1) The current measuring unit 50-A measures the value of a first current supplied from the rectifier unit 300 to the DC distribution board DCDB.

[0036] (Step S2-1) The control unit 100 acquires the first current value from the current measurement unit 50-A. The control unit 100 acquires the output voltage value of the power supply equipment device PE. (Step S3-1) The control unit 100 derives a first supply power to be supplied to the DC distribution board DCDB based on the output voltage value and the first current value.

[0037] (Step S4-1) The control unit 100 creates control information including information indicating the first supply power and information indicating a target value of power to be supplied to the DC distribution board DCDB. The control unit 100 transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8.

[0038] Fig. 3 is a flowchart showing an example of the operation of the control system 1 according to this embodiment. With reference to Fig. 3, the process in which EV normal charger 80-1, EV normal charger 80-2, and EV rapid chargers 80-4 to 80-6 charge electric vehicle EV will be described. (Step S1-2) Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine whether or not to control EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6. Here, we will continue with the explanation of the case where terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine to control EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6.

[0039] (Step S2-2) Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine whether or not the EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are charging. Among terminals 70-1, 70-2, and terminals 70-4 to 70-6, those which have determined that the EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are not charging return to step S1-2. Here, as an example, the explanation will be continued for the case where terminals 70-1, 70-2, and terminals 70-4 to 70-6 respectively determine that the EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are charging.

[0040] (Step S3-2) When terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 respectively determine that EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6 are charging (step S2-2: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-2.

[0041] (Step S4-2) When the terminals 70-1, 70-2, and 70-4 to 70-6 each receive control information (step S3-2: YES), the terminals 70-1, 70-2, and 70-4 to 70-6 acquire information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, which are included in the control information. The terminals 70-1, 70-2, and 70-4 to 70-6 determine whether the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB.

[0042] (Step S5-2) If terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 determine that the first supply power is less than the target value of power supplied to the DC distribution board DCDB (step S4-2: YES), they continue charging with the charging power requested by the electric vehicles EV connected to EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6, respectively.

[0043] (Step S6-2) If terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 determine that the first supply power is equal to or greater than the target power value (step S4-2: NO), they each reduce the charging power supplied to the electric vehicles EV connected to EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6.

[0044] Fig. 4 is a flowchart showing an example of the operation of the control system 1 according to this embodiment. A process in which the control system 1 charges and discharges the V2X device 80-7 and the storage battery PCS 90-8 will be described with reference to Fig. 4. (Step S1-3) The terminal 70-7 and the terminal 70-8 respectively determine whether the V2X device 80-7 and the storage battery PCS 90-8 are charging.

[0045] (Step S2-3) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the storage battery PCS 90-8 are charging (step S1-3: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-3. (Step S3-3) When the terminal 70-7 and the terminal 70-8 each receive the control information (step S2-3: YES), the terminal 70-7 and the terminal 70-8 acquire information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, which are included in the control information. The terminal 70-7 and the terminal 70-8 determine whether the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB.

[0046] (Step S4-3) When terminal 70-7 and terminal 70-8 determine that the first supply power is less than the target value of power supplied to the DC distribution board DCDB (step S3-3: YES), they increase the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively. (Step S5-3) When terminal 70-7 and terminal 70-8 determine that the first supply power is equal to or greater than the target value of power supplied to the DC distribution board DCDB (step S3-3: NO), they reduce the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively.

[0047] (Step S6-3) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the PCS for the storage battery 90-8 are not charging (step S1-3: NO), they respectively determine whether the V2X device 80-7 and the PCS for the storage battery 90-8 are discharging. When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the PCS for the storage battery 90-8 are not discharging, they return to step S1-3.

[0048] (Step S7-3) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the storage battery PCS 90-8 are discharging (step S6-3: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-3. (Step S8-3) When the terminal 70-7 and the terminal 70-8 each receive the control information (step S7-3: YES), the terminal 70-7 and the terminal 70-8 acquire information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB, which are included in the control information. The terminal 70-7 and the terminal 70-8 determine whether the first supply power is less than the target value of the power supplied to the DC distribution board DCDB, based on the acquired information indicating the first supply power and information indicating the target value of the power supplied to the DC distribution board DCDB.

[0049] (Step S9-3) When the terminal 70-7 and the terminal 70-8 determine that the first supply power is less than the target value of power supplied to the DC distribution board DCDB (step S8-3: YES), they respectively reduce the discharge power of the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8. (Step S10-3) When terminal 70-7 and terminal 70-8 determine that the first supply power is equal to or greater than the target value of power supplied to the DC distribution board DCDB (step S8-3: NO), they increase the discharge power of the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively.

[0050] In the above embodiment, as an example, the AC distribution board ACDB includes the EV normal charger breaker 60-1 and the EV normal charger breaker 60-2, but the present invention is not limited to this example. For example, the AC distribution board ACDB may include one EV normal charger breaker, or may include three or more EV normal charger breakers.

[0051] In the above-described embodiment, as an example, the DC distribution board DCDB includes the DC breaker for PV 60-3, the DC breakers for EV quick charger 60-4 to 60-6, the DC breaker for V2X 60-7, and the DC breaker for storage battery 60-8. However, this is not limiting. For example, the DC distribution board DCDB may include at least one type of breaker among a DC breaker for PV, a DC breaker for EV quick charger, a DC breaker 60-7 for V2X, and a DC breaker 60-8 for storage battery.

[0052] In addition, the DC distribution board DCDB may include a plurality of DC breakers for PV, may include one to two DC breakers for EV quick chargers, may include four or more DC breakers for EV quick chargers, may include a plurality of DC breakers 60-7 for V2X, or may include a plurality of DC breakers 60-8 for the storage battery. In the above-described embodiment, the control system 1 may be configured to include a plurality of AC distribution boards ACDB, or may be configured to include a plurality of DC distribution boards DCDB.

[0053] According to the control system 1 of this embodiment, the control system 1 includes a first electrical equipment as an AC distribution board ACDB that supplies power to a first charger as an ordinary EV charger, a second electrical equipment as a DC distribution board DCDB that receives power from at least a power generation system as a PV and supplies power to a second charger as an EV rapid charger, a first current measuring unit as a current measuring unit 50-A that measures a first current value supplied to the second electrical equipment, and a control unit 100 that creates control information for the first charger and the second charger to control the charging power value based on the first current value measured by the first current measuring unit.

[0054] With this configuration, the control system 1 can create control information for the first charger to which the first electrical equipment supplies power and the second charger to which the second electrical equipment supplies power to control the charging power value based on the first current value supplied to the second electrical equipment, thereby simplifying charging control compared to a case in which control information for the first charger to control the charging power value and control information for the second charger to control the charging power value are separately created. Also, the control system 1 can create control information for the first charger to which the first electrical equipment supplies power and the second charger to which the second electrical equipment supplies power to control the charging power value based on the first current value supplied to the second electrical equipment to which power is supplied from the power generation system, thereby making it possible to effectively utilize the power supplied from the power generation system.

[0055] In the control system 1, the first electrical equipment supplies AC power to the first charger, and the second electrical equipment supplies DC power to the second charger. By configuring in this manner, the control system 1 can create control information for the first charger to which the first electrical equipment that supplies AC power supplies power based on a first current value supplied to the second electrical equipment that supplies DC power, and the second charger to which the second electrical equipment supplies power, to control the charging power value.This simplifies charging and discharging control compared to a case in which control information for the first charger to control the charging power value and control information for the second charger to control the charging power value are created separately.

[0056] The control system 1 further includes a polyphase transformer as a transformer 200 that converts the system into polyphase AC, and a rectifier unit 300 that converts the polyphase AC into a DC voltage. The first electrical equipment is supplied with an AC voltage from the polyphase transformer, and the second electrical equipment is supplied with a DC voltage from the rectifier unit 300. With this configuration, the polyphase transformer and the rectifier unit 300 can supply AC voltage to the first electrical equipment, and DC voltage to the second electrical equipment.

[0057] In the control system 1, the control unit 100 derives a first supply power to be supplied to the second electrical equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a predetermined target value of power to be supplied to the second electrical equipment, and the second charger reduces the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electrical equipment based on the information indicating the first supply power and the information indicating the target value of power to be supplied to the second electrical equipment. With this configuration, the control unit 100 can derive the first supply power to be supplied to the second electric equipment based on the first current value, and create control information including information indicating the derived first supply power and information indicating a target value of power to be supplied to the second electric equipment. The second charger can reduce the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment based on the information indicating the first supply power and the information indicating the target value of power to be supplied to the second electric equipment, and therefore can limit the power in the consumption direction.

[0058] (Modification of the embodiment) (Control System) FIG. 5 is a diagram showing an example of a control system 1a according to a modified example of the embodiment. An example of the control system 1a is a system that controls an AC / DC hybrid wiring system that distributes AC power and DC power. The control system 1a includes a current measurement unit 50-B and a current measurement unit 50-C in the control system 1, and includes a control unit 100a instead of the control unit 100. The current measurement unit 50-B measures a current value (hereinafter referred to as a "second current value") supplied to the transformer 200. The current measurement unit 50-C measures a current value (hereinafter referred to as a "third current value") supplied from the PV DC-PCS 90-3.

[0059] The control unit 100a has the following functions in addition to the functions of the control unit 100. The control unit 100a acquires a second current value from the current measurement unit 50-B. Based on the acquired second current value, the control unit 100a creates control information for the EV normal charger 80-1, EV normal charger 80-2, EV rapid chargers 80-4 to 80-6, V2X device 80-7, and battery PCS 90-8 to control the charging power value or discharging power value. Specifically, the control unit 100a acquires an input voltage value of the transformer 200. For example, a voltage measurement unit (not shown) that measures the input voltage value of the transformer 200 may be provided, and the control unit 100a may acquire the input voltage value of the transformer 200 from the voltage measurement unit. The control unit 100a derives the power consumption of the control system 1a (hereinafter referred to as "second power consumption") based on the input voltage value and the second current value.

[0060] The control unit 100a has a target value of the power consumption of the control system 1a set in advance. An example of the target value of the power consumption of the control system 1a is determined based on the power consumption of the control system 1a. For example, an example of the target value of the power consumption of the control system 1a may be any percentage that is greater than 0% and less than 100% of the power consumption of the control system 1a. More specifically, an example of the target value of the power consumption of the control system 1a may be 20% or more and 80% or less, or 40% or more and 60% or less, of the power consumption of the control system 1a. The control unit 100a creates control information including information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a. The control unit 100a transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8.

[0061] For example, the control unit 100a may switch between a process of creating control information based on a first current value and a process of creating control information based on a second current value under a predetermined condition. An example of the predetermined condition may be the amount of power generated by the power generation system. The control unit 100a may also switch between a process of creating control information based on a first current value and a process of creating control information based on a second current value based on a priority indicating the priority order of the processes. For example, the control unit 100a may set the priority of the process of creating control information based on the first current value higher or lower than the priority of the process of creating control information based on the second current value.

[0062] The terminal 70-1 and the terminal 70-2 receive the control information transmitted by the control unit 100a. The terminal 70-1 and the terminal 70-2 acquire information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a included in the received control information. Based on the acquired information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, if the second power consumption is less than the target value of the power consumption of the control system 1a, the terminal 70-1 and the terminal 70-2 continue charging with the charging power requested by the electric vehicle EV connected to the EV normal charger 80-1 and the EV normal charger 80-2, respectively, and if the second power consumption is equal to or greater than the target value of the power consumption of the control system 1a, the terminal 70-1 and the terminal 70-2 reduce the charging power supplied to the electric vehicle EV connected to the EV normal charger 80-1 and the EV normal charger 80-2, respectively.

[0063] The terminals 70-4 to 70-6 receive the control information transmitted by the control unit 100a. The terminals 70-4 to 70-6 acquire information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, which are included in the received control information. Based on the acquired information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, the terminals 70-4 to 70-6 continue charging with the charging power requested by the electric vehicle EV connected to the EV rapid charger 80-4 to the EV rapid charger 80-6 when the second power consumption is less than the target value of the power consumption of the control system 1a, and reduce the charging power supplied to the electric vehicle EV connected to the EV rapid charger 80-4 to the EV rapid charger 80-6 when the second power consumption is equal to or greater than the target value of the power consumption of the control system 1a.

[0064] The terminal 70-7 receives the control information transmitted by the control unit 100a. The terminal 70-7 acquires information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, which are included in the received control information. Based on the acquired information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, the terminal 70-7 increases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the first supply power is less than the target value of the power consumption of the control system 1a, and decreases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the second power consumption is equal to or greater than the target value of the power consumption of the control system 1a.

[0065] Based on the acquired information indicating the second power consumption and the information indicating the target value of power consumption of the control system 1a, the terminal 70-7 reduces the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the second power consumption is less than the target value of power consumption of the control system 1a, and increases the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the second power consumption is equal to or greater than the target value of power consumption of the control system 1a.

[0066] The terminal 70-8 receives the control information transmitted by the control unit 100a. The terminal 70-8 acquires information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, which are included in the received control information. Based on the acquired consumption information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a, the terminal 70-8 increases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the second power consumption is less than the target value of the power consumption of the control system 1a, and decreases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the second power consumption is equal to or greater than the target value of the power consumption of the control system 1a.

[0067] Based on the acquired information indicating the second power consumption and the information indicating the target value of power consumption of the control system 1a, the terminal 70-8 reduces the discharge power of the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is discharging and the second power consumption is less than the target value of power consumption of the control system 1a, and increases the discharge power of the storage battery SB connected to the V2X device 80-7 when the storage battery PCS 90-8 is discharging and the second power consumption is equal to or greater than the target value of power consumption of the control system 1a.

[0068] The control unit 100a acquires a third current value from the current measurement unit 50-C. Based on the acquired third current value, the control unit 100a creates control information for the EV normal charger 80-1, the EV normal charger 80-2, the EV rapid chargers 80-4 to 80-6, the V2X device 80-7, and the storage battery PCS 90-8 to control the charging power value or the discharging power value. Specifically, the control unit 100a acquires the output voltage of the PV. For example, a voltage measurement unit (not shown) that measures the output voltage value of the PV may be provided, and the control unit 100 may acquire the output voltage value of the PV from the voltage measurement unit. The control unit 100a derives the generated power of the PV (hereinafter referred to as "third generated power") based on the output voltage value and the third current value.

[0069] The control unit 100a is preset with a threshold value of the power generated by the PV. An example of the threshold value of the power generated by the PV is determined based on the power generated by the PV. For example, an example of the target value of the power generated may be any percentage greater than 0% and equal to or less than 100% of the power generated by the PV. More specifically, an example of the target value of the power generated may be 20% or more and 80% or less, or 40% or more and 60% or less, of the power generated by the PV. The control unit 100a creates control information including information indicating the third power generated and information indicating the threshold value of the power generated by the PV. The control unit 100a transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8.

[0070] For example, the control unit 100a may switch between a process of creating the control information based on the first current value, a process of creating the control information based on the second current value, and a process of creating the control information based on the third current value under a predetermined condition. One example of the predetermined condition may be the amount of power generated by the power generation system. Furthermore, the control unit 100a may switch between a process of creating control information based on a first current value, a process of creating control information based on a second current value, and a process of creating control information based on a third current value based on a priority indicating the priority order of the processes. For example, the control unit 100a may increase or decrease any one of the priority of the process of creating control information based on the first current value, the priority of the process of creating control information based on the second current value, and the priority of the process of creating control information based on the third current value.

[0071] The terminal 70-1 and the terminal 70-2 receive the control information transmitted by the control unit 100a. The terminal 70-1 and the terminal 70-2 acquire information indicating the third generated power and information indicating the threshold value of the PV generated power included in the received control information. Based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power, if the third generated power is higher than the threshold value of the PV generated power, the terminal 70-1 and the terminal 70-2 continue charging with the charging power requested by the electric vehicle EV connected to the EV normal charger 80-1 and the EV normal charger 80-2, respectively, and if the third generated power is equal to or lower than the threshold value of the PV generated power, the terminal 70-1 and the terminal 70-2 reduce the charging power supplied to the electric vehicle EV connected to the EV normal charger 80-1 and the EV normal charger 80-2, respectively.

[0072] Terminals 70-4 to 70-6 receive the control information transmitted by control unit 100a. Terminals 70-4 to 70-6 acquire information indicating the third generated power and information indicating the threshold value of the PV generated power included in the received control information. Based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power, if the third generated power is higher than the threshold value of the PV generated power, terminals 70-4 to 70-6 continue charging with the charging power requested by electric vehicles EV connected respectively to EV rapid charger 80-4 to EV rapid charger 80-6, and if the third generated power is equal to or lower than the threshold value of the PV generated power, reduce the charging power supplied to electric vehicles EV connected respectively to EV rapid charger 80-4 to EV rapid charger 80-6.

[0073] The terminal 70-7 receives the control information transmitted by the control unit 100a. The terminal 70-7 acquires information indicating the third generated power and information indicating the threshold value of the PV generated power included in the received control information. Based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power, the terminal 70-7 increases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the third generated power is higher than the threshold value of the PV generated power, and decreases the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is charging and the third generated power is equal to or lower than the threshold value of the PV generated power.

[0074] Based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power, the terminal 70-7 reduces the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the third generated power is higher than the threshold value of the PV generated power, and increases the discharge power of the electric vehicle EV connected to the V2X device 80-7 when the V2X device 80-7 is discharging and the third generated power is equal to or lower than the threshold value of the PV generated power.

[0075] The terminal 70-8 receives the control information transmitted by the control unit 100a. The terminal 70-8 acquires information indicating the third generated power and information indicating the threshold value of the generated power of the PV, which are included in the received control information. Based on the acquired power generation information indicating the third generated power and information indicating the threshold value of the PV power, the terminal 70-8 increases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the third generated power is higher than the threshold value of the generated power of the PV, and decreases the charging power supplied to the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is charging and the third generated power is equal to or lower than the threshold value of the generated power of the PV.

[0076] Based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power, the terminal 70-8 reduces the discharge power of the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is discharging and the third generated power is higher than the threshold value of the PV generated power, and increases the discharge power of the storage battery SB connected to the storage battery PCS 90-8 when the storage battery PCS 90-8 is discharging and the third generated power is equal to or lower than the threshold value of the PV generated power.

[0077] (Control system operation) Fig. 6 is a flowchart showing an example of the operation of the control system 1a according to the modified example of the embodiment. With reference to Fig. 6, a process from when the control system 1a measures the second current value to when it transmits control information will be described. (Step S1-4) The control unit 100a acquires the value of the second current supplied to the transformer 200 from the current measuring unit 50-B.

[0078] (Step S2-4) The control unit 100a derives the second power consumption of the control system 1a based on the input voltage value and the second current value.

[0079] (Step S3-4) The control unit 100a creates control information including information indicating the second power consumption and information indicating a target value of the power consumption of the control system 1a. The control unit 100a transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8.

[0080] Fig. 7 is a flowchart showing an example of the operation of the control system 1a according to the modified example of the embodiment. With reference to Fig. 7, a process from when the control system 1a measures the third current value to when it transmits control information will be described. (Step S1-5) The control unit 100a obtains the third current value from the current measuring unit 50-C.

[0081] (Step S2-5) The control unit 100a derives a third generated power of the PV based on the output voltage value and the third current value of the PV.

[0082] (Step S3-5) The control unit 100a creates control information including information indicating the third generated power and information indicating a threshold value of the PV generated power. The control unit 100a transmits the created control information to the terminals 70-1, 70-2, and 70-4 to 70-8.

[0083] Fig. 8 is a flowchart showing an example of the operation of the control system 1a according to the modified embodiment. With reference to Fig. 8, a process in which the EV normal charger 80-1, the EV normal charger 80-2, and the EV rapid chargers 80-4 to 80-6 charge the electric vehicle EV will be described. (Step S1-7) Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine whether or not to control EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6. Here, we will continue with the explanation of the case where terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine to control EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6.

[0084] (Step S2-7) Terminal 70-1, terminal 70-2, and terminals 70-4 to 70-6 respectively determine whether or not EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are charging. Among terminals 70-1, 70-2, and terminals 70-4 to 70-6, those which have determined that EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are not charging return to step S1-7. Here, as an example, the explanation will continue for the case where terminals 70-1, 70-2, and terminals 70-4 to 70-6 respectively determine that EV normal charger 80-1, EV normal charger 80-2, and EV rapid charger 80-4 to EV rapid charger 80-6 are charging.

[0085] (Step S3-7) When terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 respectively determine that EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6 are charging (step S2-7: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-7.

[0086] (Step S4-7) When terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 each receive control information (step S3-7: YES), terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 determine whether the control information includes information indicating the second power consumption and information indicating the target value of power consumption of control system 1a. (Step S5-7) If the terminals 70-1, 70-2, and 70-4 to 70-6 determine that the control information includes information indicating the second power consumption and information indicating the target value of power consumption of the control system 1a (step S4-7: YES), the terminals 70-1, 70-2, and 70-4 to 70-6 acquire the information indicating the second power consumption and information indicating the target value of power consumption of the control system 1a included in the control information. The terminals 70-1, 70-2, and 70-4 to 70-6 determine whether the second power consumption is less than the target value of power consumption of the control system 1a based on the acquired information indicating the second power consumption and information indicating the target value of power consumption of the control system 1a.

[0087] (Step S6-7) If the terminals 70-1, 70-2, and 70-4 to 70-6 determine that the control information does not include information indicating the second power consumption and information indicating the power consumption of the control system 1a (step S4-7: NO), the terminals 70-1, 70-2, and 70-4 to 70-6 acquire information indicating the third generated power and information indicating the threshold value of the PV generated power included in the control information. The terminals 70-1, 70-2, and 70-4 to 70-6 determine whether the third generated power is higher than the threshold value of the PV generated power based on the acquired information indicating the third generated power and information indicating the threshold value of the PV generated power.

[0088] (Step S7-7) If terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 determine that the second power consumption is less than the target power consumption value of the control system 1a (step S5-7: YES), or if they determine that the third generated power is higher than the threshold value of the PV generated power (step S6-7: YES), they continue charging at the charging power requested by the electric vehicles EV connected to EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6, respectively. (Step S8-7) When terminal 70-1, terminal 70-2, terminal 70-4 to terminal 70-6 determine that the second power consumption is equal to or greater than the power consumption threshold of the control system 1a (step S5-7: NO), or when they determine that the third generated power is equal to or less than the PV generated power threshold (step S6-7: NO), they reduce the charging power supplied to the electric vehicles EV connected to EV normal charger 80-1, EV normal charger 80-2, EV rapid charger 80-4 to EV rapid charger 80-6, respectively.

[0089] Fig. 9 is a flowchart showing an example of the operation of the control system 1a according to the modified example of the embodiment. A process in which the control system 1a charges and discharges the V2X device 80-7 and the storage battery PCS 90-8 will be described with reference to Fig. 9. (Step S1-8) The terminal 70-7 and the terminal 70-8 respectively determine whether the V2X device 80-7 and the storage battery PCS 90-8 are charging.

[0090] (Step S2-8) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the storage battery PCS 90-8 are charging (step S1-8: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-8. (Step S3-8) When terminal 70-7 and terminal 70-8 each receive control information (step S2-8: YES), terminal 70-7 and terminal 70-8 determine whether the control information includes information indicating the second power consumption and information indicating the target value of power consumption of control system 1a.

[0091] (Step S4-8) If terminal 70-7 and terminal 70-8 determine that the control information includes information indicating the second power consumption and information indicating the target value of power consumption of control system 1a (step S3-8: YES), terminal 70-7 and terminal 70-8 determine whether the second power consumption is less than the target value of power consumption of control system 1a based on the information indicating the second power consumption and the information indicating the target value of power consumption of control system 1a. (Step S5-8) If terminal 70-7 and terminal 70-8 determine that the control information does not include information indicating the second power consumption and information indicating the target value of power consumption of control system 1a (step S3-8: NO), terminal 70-7 and terminal 70-8 determine whether the third generated power is higher than the threshold of power generation of control system 1a based on the information indicating the third generated power and the information indicating the threshold of power generation of control system 1a.

[0092] (Step S6-8) When the terminal 70-7 and the terminal 70-8 determine that the second power consumption is less than the target value of power consumption of the control system 1a (step S4-8: YES), or when they determine that the third generated power is higher than the threshold value of the PV generated power (step S5-8: YES), they increase the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively. (Step S7-8) When the terminal 70-7 and the terminal 70-8 determine that the second power consumption is equal to or greater than the target power consumption value of the control system 1a (step S4-8: NO), or when they determine that the third generated power is equal to or less than the threshold value of the PV generated power (step S5-8: NO), they reduce the charging power supplied to the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively.

[0093] (Step S8-8) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the PCS for the storage battery 90-8 are not charging (step S1-8: NO), they respectively determine whether the V2X device 80-7 and the PCS for the storage battery 90-8 are discharging. When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the PCS for the storage battery 90-8 are not discharging, they return to step S1-8.

[0094] (Step S9-8) When the terminal 70-7 and the terminal 70-8 respectively determine that the V2X device 80-7 and the storage battery PCS 90-8 are discharging (step S8-8: YES), they determine whether or not they have received control information. If they have not received control information, they return to step S1-8. (Step S10-8) When terminal 70-7 and terminal 70-8 each receive control information (step S9-8: YES), terminal 70-7 and terminal 70-8 determine whether the control information includes information indicating the second power consumption and information indicating the target value of power consumption of control system 1a.

[0095] (Step S11-8) If terminal 70-7 and terminal 70-8 determine that the control information includes information indicating the second power consumption and information indicating the target value of power consumption of control system 1a (step S10-8: YES), terminal 70-7 and terminal 70-8 determine whether the second power consumption is less than the target value of power consumption of control system 1a based on the acquired information indicating the second power consumption and information indicating the target value of power consumption of control system 1a.

[0096] (Step S12-8) If terminal 70-7 and terminal 70-8 determine that the control information does not include information indicating the second power consumption and information indicating the target value of the power consumption of the control system 1a (step S10-8: NO), terminal 70-7 and terminal 70-8 determine whether the third generated power is higher than the threshold value of the PV generated power based on the information indicating the third generated power and the information indicating the threshold value of the PV generated power. (Step S13-8) When the terminal 70-7 and the terminal 70-8 determine that the second power consumption is less than the target value of power consumption of the control system 1a (step S11-8: YES), or when they determine that the third generated power is higher than the threshold value of the PV generated power (step S12-8: YES), they reduce the discharge power of the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively.

[0097] (Step S14-8) When the terminal 70-7 and the terminal 70-8 determine that the second power consumption is equal to or greater than the target power consumption value of the control system 1a (step S11-8: NO), or when they determine that the third generated power is equal to or less than the threshold value of the PV generated power (step S12-8: NO), they increase the discharge power of the electric vehicle EV connected to the V2X device 80-7 and the storage battery SB connected to the storage battery PCS 90-8, respectively.

[0098] In the above-described modified example of the embodiment, as an example, the control unit 100a switches between the process of creating control information based on the first current value and the process of creating control information based on the second current value under a predetermined condition, and the control unit 100a switches between the process of creating control information based on the first current value, the process of creating control information based on the second current value, and the process of creating control information based on the third current value under a predetermined condition. However, the present invention is not limited to this example. For example, the control unit 100a may switch between the process of creating control information based on the first current value and the process of creating control information based on the third current value under a predetermined condition. One example of the predetermined condition may be the amount of power generated by the power generation system. Furthermore, the control unit 100a may switch between the process of creating the control information based on the first current value and the process of creating the control information based on the third current value based on a priority indicating the priority order of the processes. For example, the control unit 100a may set the priority of the process of creating the control information based on the first current value higher or lower than the priority and the priority of the process of creating the control information based on the third current value.

[0099] According to a control system 1a according to a modified example of the embodiment, the control system 1 further includes a second current measuring unit serving as a current measuring unit 50-B that measures a second current value supplied to the multi-phase transformer. The control unit 100a creates control information for the first charger and the second charger to control the charging power value based on the second current value. By configuring in this manner, the control system 1a can create control information for the first charger to which the first electrical equipment supplies power and the second charger to which the second electrical equipment supplies power to control the charging power value based on the second current value supplied to the multi-phase transformer, thereby simplifying charging and discharging control compared to a case in which control information for the first charger to control the charging power value and control information for the second charger to control the charging power value are created separately.

[0100] In the control system 1a, the control unit 100a derives a second power consumption of the control system 1a based on the second current value, and creates control information including information indicating the derived second power consumption and information indicating a preset target value of power consumption of the control system 1a. The second charger reduces charging power when the second power consumption is equal to or greater than the target value of power consumption of the control system 1a based on the information indicating the second power consumption and the information indicating the target value of power consumption of the control system 1a. With this configuration, the control unit 100a can derive the second power consumption of the control system 1a based on the second current value, and create control information including information indicating the derived second power consumption and information indicating a target value of the power consumption of the control system 1a. The second charger can reduce the charging power when the second power consumption is equal to or greater than the target value of the power consumption of the control system 1a based on the information indicating the second power consumption and the information indicating the target value of the power consumption of the control system 1a, and therefore can limit the power in the consumption direction.

[0101] In the control system 1a, a storage battery SB is connected to the second electric equipment, and a control unit 100a derives a first supply power to be supplied to the second electric equipment based on a first current value, and creates control information including information indicating the derived first supply power and information indicating a preset target value of power to be supplied to the second electric equipment. When charging, the storage battery SB increases the charging power when the first supply power is less than the target value of power to be supplied to the second electric equipment, and decreases the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and when discharging, increases the discharging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and decreases the discharging power when the first supply power is less than the target value of power.

[0102] With this configuration, the control unit 100a can derive the first supply power to be supplied to the second electrical equipment based on the first current value, and generate control information including information indicating the derived first supply power and information indicating a target value of the power to be supplied to the second electrical equipment. When the storage battery SB is charging, if the first supply power is less than the target value of the power to be supplied to the second electrical equipment, the storage battery SB can increase the power in the consumption direction by increasing the charging power, and if the first supply power is equal to or greater than the target value of the power to be supplied to the second electrical equipment, the storage battery SB can limit the power in the consumption direction by reducing the charging power. When the storage battery SB is discharging, if the first supply power is equal to or greater than the target value of the power, the storage battery SB can limit the power in the consumption direction by increasing the discharging power, and if the first supply power is less than the target value of the power to be supplied to the second electrical equipment, the storage battery SB can increase the power in the consumption direction by reducing the discharging power.

[0103] In the control system 1a, an EV charger / discharger serving as a V2X device is connected to the second electric equipment. The control unit 100a derives a first supply power to be supplied to the second electric equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a preset target value of power to be supplied to the second electric equipment. When charging, the EV charger / discharger increases the charging power when the first supply power is less than the target value of power to be supplied to the second electric equipment, and decreases the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and when discharging, increases the discharging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and decreases the charging power when the first supply power is less than the target value of power to be supplied to the second electric equipment.

[0104] With this configuration, the control unit 100a can derive a first supply power to be supplied to the second electric equipment based on the first current value, and create control information including information indicating the derived first supply power and information indicating a target value of power to be supplied to the second electric equipment. When charging, the EV charger / discharger can increase the power in the consumption direction by increasing the charging power when the first supply power is less than the target value of power to be supplied to the second electric equipment, and can limit the power in the consumption direction by reducing the charging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment. When discharging, the EV charger / discharger can limit the power in the consumption direction by increasing the discharging power when the first supply power is equal to or greater than the target value of power to be supplied to the second electric equipment, and can increase the power in the consumption direction by reducing the discharging power when the first supply power is less than the target value of power to be supplied to the second electric equipment.

[0105] The control system 1a further includes a third current measuring unit as a current measuring unit 50-C that measures a third current value supplied by the power generation system as a PV. The control unit 100a creates control information for the first charger and the second charger to control the charging power value based on the third current value. By configuring in this manner, the control system 1a can create control information for the first charger to which the first electrical equipment supplies power and the second charger to which the second electrical equipment supplies power to control the charging power value based on the third current value supplied by the power generation system, thereby simplifying charging control compared to a case in which control information for the first charger to control the charging power value and control information for the second charger to control the charging power value are created separately.

[0106] In the control system 1a, the control unit 100a derives a third generated power supplied from the power generation system to the second electrical equipment based on the third current value measured by the third current measurement unit, and creates control information including information indicating the derived third generated power and information indicating a preset threshold value of the generated power of the power generation system. The second charger reduces charging power when the third generated power is equal to or less than the power threshold value based on the information indicating the third generated power and the information indicating the threshold value of the generated power of the power generation system included in the control information.

[0107] With this configuration, the control unit 100a can derive the third generated power to be supplied to the second electric equipment based on the third current value, and create control information including information indicating the derived third generated power and information indicating a threshold value of the generated power of the power generation system. The second charger can reduce the charging power when the third generated power is equal to or less than the threshold value of the generated power of the power generation system based on the information indicating the third generated power and the information indicating the threshold value of the generated power of the power generation system, and therefore can limit the power in the consumption direction.

[0108] Although the embodiment of the present invention has been described in detail above with reference to the drawings, the specific configuration is not limited to this embodiment, and design changes and the like within the scope of the present invention are also included. For example, a computer program for implementing the functions of each device such as the above-mentioned control unit 100 and control unit 100a may be recorded on a computer-readable recording medium, and the computer program recorded on this recording medium may be read into a computer system and executed. Note that the "computer system" referred to here may include hardware such as an OS and peripheral devices.

[0109] In addition, "computer-readable recording media" refers to writable non-volatile memories such as flexible disks, optical magnetic disks, ROMs, and flash memories, portable media such as DVDs (Digital Versatile Discs), and storage devices such as hard disks built into computer systems. Furthermore, "computer-readable recording media" also includes those that hold programs for a certain period of time, such as volatile memory (e.g., DRAM (Dynamic Random Access Memory)) inside computer systems that act as servers or clients when a computer program is transmitted via a network such as the Internet or a communication line such as a telephone line.

[0110] The program may be transmitted from a computer system in which the program is stored in a storage device or the like to another computer system via a transmission medium, or by a transmission wave in the transmission medium. Here, the "transmission medium" that transmits the program refers to a medium that has a function of transmitting information, such as a network (communication network) such as the Internet or a communication line (communication line) such as a telephone line. The program may be for realizing part of the functions described above. Furthermore, the above-mentioned functions may be realized in combination with a program already recorded in the computer system, that is, a so-called differential file (differential program). [Explanation of symbols]

[0111] 1, 1a...control system, 50-A, 50-B, 50-C...current measurement unit, 60-1, 60-2...breaker for EV normal charger, 60-3...DC breaker for PV, 60-4 to 60-6...DC breaker for EV quick charger, 60-7...DC breaker for V2X, 60-8...DC breaker for storage battery, 70-1, 70-2, 70-4 to 70-8...terminal, 80-1, 80-2...EV normal charger, 80-4 to 80-6...EV quick charger, 80-7...V2X device, 90-3...DC-PCS for PV, 90-8...PCS for storage battery, 100, 100a...control unit, 200...transformer, 300...rectifier unit

Claims

1. a first electrical device that supplies power to the first charger; a second electrical device that is supplied with power from at least the power generation system and supplies power to a second charger; A first current measuring unit that measures a first current value supplied to the second electrical equipment; a control unit that creates control information for controlling charging power values ​​of the first charger and the second charger based on the first current value measured by the first current measurement unit; A control system comprising:

2. the first electrical device supplies AC power to the first charger; The second electrical device supplies DC power to the second charger. The control system of claim 1 .

3. A polyphase transformer that converts the system into polyphase AC; a rectification unit for converting the multi-phase AC into a DC voltage; Further equipped with The first electrical equipment is supplied with an AC voltage from the polyphase transformer, The control system of claim 1 , wherein the second electrical equipment is supplied with a DC voltage from the rectifier unit.

4. the control unit derives a first supply power to be supplied to the second electrical equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a preset target value of power to be supplied to the second electrical equipment; 2. The control system according to claim 1, wherein the second charger reduces charging power when the first supply power is equal to or greater than the target value of power supplied to the second electrical equipment based on information indicating the first supply power and information indicating the target value of power supplied to the second electrical equipment.

5. A second current measuring unit that measures a second current value supplied to the multi-phase transformer. Further equipped with The control system according to claim 3 , wherein the control unit creates control information for controlling charging power values ​​of the first charger and the second charger based on the second current value.

6. the control unit derives a second power consumption of the control system based on the second current value, and creates control information including information indicating the derived second power consumption and information indicating a preset target value of the power consumption of the control system; The control system of claim 5, wherein the second charger reduces charging power when the second power consumption is equal to or greater than the target value of the power consumption of the control system based on information indicating the second power consumption and information indicating the target value of the power consumption of the control system.

7. A storage battery is connected to the second electrical equipment, the control unit derives a first supply power to be supplied to the second electrical equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a preset target value of power to be supplied to the second electrical equipment; The storage battery is When charging, if the first supply power is less than the target value of the power supplied to the second electrical equipment, the charging power is increased, and if the first supply power is equal to or greater than the target value of the power supplied to the second electrical equipment, the charging power is decreased; 2. The control system of claim 1, wherein, during discharging, the discharge power is increased when the first supply power is equal to or greater than the target value of power supplied to the second electrical equipment, and the discharge power is decreased when the first supply power is less than the target value of power.

8. An EV charger / discharger is connected to the second electrical equipment, the control unit derives a first supply power to be supplied to the second electrical equipment based on the first current value, and creates control information including information indicating the derived first supply power and information indicating a preset target value of power to be supplied to the second electrical equipment; The EV charger / discharger includes: When charging, if the first supply power is less than the target value of the power supplied to the second electrical equipment, the charging power is increased, and if the first supply power is equal to or greater than the target value of the power supplied to the second electrical equipment, the charging power is decreased; 2. The control system of claim 1, wherein, during discharging, the discharge power is increased when the first supply power is equal to or greater than the target value of power supplied to the second electrical equipment, and the discharge power is decreased when the first supply power is less than the target value of power supplied to the second electrical equipment.

9. a third current measuring unit that measures a third current value supplied by the power generation system; Further equipped with The control system according to claim 1 , wherein the control unit creates control information for controlling charging power values ​​of the first charger and the second charger based on the third current value.

10. the control unit derives a third generated power supplied from the power generation system to a second electrical equipment based on the third current value measured by the third current measurement unit, and creates control information including information indicating the derived third generated power and information indicating a preset threshold value of the generated power of the power generation system; The control system of claim 9, wherein the second charger reduces the charging power when the third generated power is equal to or less than the threshold of the generated power of the power generation system based on information indicating the third generated power included in the control information and information indicating a threshold of the generated power of the power generation system.

11. a first electrical device that supplies power to the first charger; a second electrical device that is supplied with power from at least the power generation system and supplies power to a second charger; a first current measuring unit that measures a first current value supplied to the second electrical equipment; A control method executed by a control system comprising: creating control information for controlling charging power values ​​of the first charger and the second charger based on the first current value measured by the first current measurement unit; a step of outputting the control information created in the creating step; The control method includes:

Citation Information

Patent Citations

  • Charging system

    JP2013243114A

  • Power generation device

    JP2014230366A

  • Charging Method and Charging System

    JP2017500836A

  • Power management system

    JP2020202623A

  • Power control device and power control system provided with same

    WO2016059853A1