Information processing device, information processing method and program

The information processing device analyzes sensor data from mobile objects to verify if transportation infrastructure repairs adhere to work plans, ensuring accurate repair execution.

JP2024168874APending Publication Date: 2024-12-05NEC CORP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
JP2023085897
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-05-25
Publication Date
2024-12-05

AI Technical Summary

Technical Problem

Existing systems fail to accurately verify whether repairs to transportation infrastructure, such as roads and bridges, are performed according to the specified work plan, leading to potential discrepancies between planned and actual repair locations.

Method used

An information processing device that collects and analyzes vibration and audio data from mobile objects like trains or cars before and after a repair period to determine if the repairs align with the work plan by comparing sensor data changes.

Benefits of technology

Enables accurate estimation of whether repairs have been correctly executed, allowing managers to identify deviations and take corrective actions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024168874000001_ABST
    Figure 2024168874000001_ABST
Patent Text Reader

Abstract

To provide a mechanism for estimating whether or not a traffic infrastructure has been correctly repaired according to a work plan.SOLUTION: An acquisition part (11) acquires a work plan including a period in which a traffic infrastructure is repaired; a collection part (12) collects sensor data including at least one of vibration data and voice data detected by a moving body when the moving body travels in the traffic infrastructure before and after the period in which the traffic infrastructure is repaired; and an estimation part (13) estimates whether or not the traffic infrastructure is repaired according to the work plan based upon change of the sensor data before and after the period in which the traffic infrastructure is repaired.SELECTED DRAWING: Figure 5
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to an information processing device, an information processing method, and a program, and more particularly to an information processing device, an information processing method, and a program for estimating whether repairs to a transportation infrastructure have been properly carried out in accordance with a work plan. [Background technology]

[0002] Transportation infrastructure (e.g., roads, bridges, and railroad tracks) is inspected daily by workers to ensure that moving objects (e.g., trains and automobiles) can pass safely. In addition, repairs to transportation infrastructure are carried out as necessary. Necessary repairs include, for example, replacing railroad ties, retightening bolts, straightening rail distortions, repairing cracks in bridges, and reinforcing cables.

[0003] Patent Document 1 describes a measurement system that associates measurement data acquired from objects such as rails and sleepers of a railway line with information indicating an object class assigned to the object and stores the data in a database. The measurement data stored in the database is compared with target state data and used to plan and execute maintenance procedures for the object. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] Special Publication No. 2019-525862 Summary of the Invention [Problem to be solved by the invention]

[0005] Repairs to transportation infrastructure are usually carried out according to a work plan. However, there are cases where the locations where repairs are actually carried out are outside the locations that are specified as requiring repair in the work plan. Or, there are cases where repairs are not carried out according to the work plan. There is a demand for a system that allows managers, etc. to easily check whether repairs to transportation infrastructure have been carried out correctly according to the work plan.

[0006] The present disclosure has been made in consideration of the above-mentioned problems, and its purpose is to provide a mechanism for estimating whether repairs to transportation infrastructure have been carried out correctly in accordance with a work plan. [Means for solving the problem]

[0007] An information processing device according to one aspect of the present disclosure includes an acquisition means for acquiring a work plan including a period during which repairs to a transportation infrastructure were carried out, a collection means for collecting sensor data including at least one of vibration data and voice data detected by a mobile body while the mobile body passes through the transportation infrastructure before and after the period, and an estimation means for estimating whether repairs to the transportation infrastructure were carried out in accordance with the work plan based on a change in the sensor data between before and after the period.

[0008] An information processing method according to one embodiment of the present invention includes obtaining a work plan including a period during which repairs to a transportation infrastructure were carried out, collecting sensor data including at least one of vibration data and voice data detected by a mobile body while the mobile body is passing through the transportation infrastructure before and after the period, and estimating whether repairs to the transportation infrastructure were carried out in accordance with the work plan based on changes in the sensor data between before and after the period.

[0009] A program according to one embodiment of the present invention causes a computer to obtain a work plan including a period during which repairs to a transportation infrastructure were carried out, collect sensor data including at least one of vibration data and voice data detected by a mobile body while the mobile body passes through the transportation infrastructure before and after the period, and estimate whether repairs to the transportation infrastructure were carried out in accordance with the work plan based on changes in the sensor data between before and after the period. Effect of the Invention

[0010] According to one aspect of the present invention, it is possible to estimate whether repairs to transportation infrastructure have been performed correctly according to a work plan. [Brief description of the drawings]

[0011] [Figure 1] FIG. 1 is a diagram showing an example of a work management system including an information processing device according to first to third embodiments. [Diagram 2] 1 shows an example of sensor data acquired from a vehicle when the transportation infrastructure is operating normally. [Diagram 3] 1 shows an example of sensor data acquired from a vehicle when an abnormality occurs in the transportation infrastructure. [Figure 4] An example of a work plan stored in a work plan database (DB) of a server is shown. [Diagram 5] 1 is a block diagram showing a configuration of an information processing device according to a first embodiment. [Figure 6] 4 is a flowchart showing the operation of the information processing device according to the first embodiment. [Figure 7] FIG. 11 is a block diagram showing a configuration of an information processing device according to a second embodiment. [Figure 8] 10 is a flowchart showing the operation of the information processing device according to the second embodiment. [Figure 9] FIG. 11 is a block diagram showing a configuration of an information processing device according to a third embodiment. [Figure 10]FIG. 11 is a diagram showing an example of information presented by an information processing device according to a third embodiment. [Figure 11] 11 is a flowchart showing the operation of an information processing device according to the third embodiment. [Figure 12] FIG. 1 is a diagram illustrating an example of a hardware configuration of an information processing device according to first to third embodiments. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0012] (Work Management System 1) An example of a work management system 1 including any one of information processing devices 10, 20, and 30 according to first to third embodiments described below will be described with reference to FIGS. 1 to 4.

[0013] Fig. 1 is a diagram showing an example of the configuration of a work management system 1. As shown in Fig. 1, the work management system 1 includes an information processing device 10 (20, 30), a vehicle 100, and a server 200. Here, "information processing device 10 (20, 30)" refers to "any of the information processing devices 10, 20, 30."

[0014] The vehicle 100, the server 200, and the information processing device 10 (20, 30) are communicatively connected to each other via any communication network (for example, a wired or wireless LAN (Local Area Network), and the Internet).

[0015] The vehicle 100 travels through a transportation infrastructure (not shown). The vehicle 100 is an example of a moving body. Here, the transportation infrastructure means railroad tracks, railway bridges, viaducts, roads, tunnels, and the like. For example, the vehicle 100 is a train (electric train or steam locomotive) or an automobile. The vehicle 100 is equipped with a sensor. The sensor outputs sensor data including at least one of vibration data and audio data. For example, when the vehicle 100 travels on a railroad track, the vehicle 100 is subjected to vibration and impact. The sensor mounted on the vehicle 100 detects the vibration and impact received by the vehicle 100 and outputs vibration data.

[0016] The server 200 includes a work plan DB (Data Base). The work plan DB stores data on work plans related to repairs to transportation infrastructure. The work plan includes a period during which the repairs to the transportation infrastructure are carried out. The work plan may include a location where the repairs to the transportation infrastructure are to be carried out, a scheduled date and time when the repairs are to start, a start date and time when the repairs actually started, and a completion date and time when it is reported that the repairs have been completed.

[0017] The information processing device 10 (20, 30) acquires sensing data detected by a sensor from the vehicle 100. In addition, the information processing device 10 (20, 30) acquires, from the server 200, data of a work plan stored in a work plan DB.

[0018] The information processing device 10 (20, 30) collects sensor data detected by the vehicle 100 while the vehicle 100 is passing through the transportation infrastructure before and after a period in which the transportation infrastructure was repaired. Then, the information processing device 10 (20, 30) estimates whether the transportation infrastructure was repaired in accordance with a work plan based on a change in the sensor data before and after the period in which the transportation infrastructure was repaired.

[0019] For example, the information processing device 10 (20, 30) calculates the difference between the peak value of the sensor data before the period during which the transportation infrastructure was repaired and the peak value of the sensor data after the period during which the transportation infrastructure was repaired.

[0020] If the calculated difference is equal to or greater than the threshold, the information processing device 10 (20, 30) estimates that the transportation infrastructure has been repaired in accordance with the work plan. On the other hand, if the calculated difference is less than the threshold, the information processing device 10 (20, 30) estimates that the transportation infrastructure has not been repaired in accordance with the work plan.

[0021] The information processing device 10 (20, 30) outputs the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan to an external device. Alternatively, the information processing device 10 (20, 30) may notify an alert to a communication terminal of a manager or the like when it estimates that the transportation infrastructure has not been repaired according to the work plan.

[0022] The configuration and operation of the information processing device 10 (20, 30) will be described in the following first to third embodiments.

[0023] (Example of sensor data) A specific example of sensor data acquired by the information processing device 10 (20, 30) from the vehicle 100 (FIG. 1) will be described with reference to FIGS. 2 and 3. FIG.

[0024] A vehicle 100 runs on a railroad track. While the vehicle 100 travels through a traffic infrastructure, a sensor mounted on the vehicle 100 detects the shaking and impacts occurring to the vehicle 100, thereby obtaining time-series vibration data.

[0025] 2 and 3 show an example of vibration data (sensor data) obtained from a vehicle 100 (FIG. 1) traveling through a traffic infrastructure. Fig. 2 shows an example of vibration data obtained when the traffic infrastructure is normal. Fig. 3 shows an example of vibration data obtained when there is an abnormality in the traffic infrastructure.

[0026] As shown in Fig. 3, when there is an abnormality somewhere in the transportation infrastructure, a vibration pattern different from the normal one (Fig. 2) occurs in part of the vibration data. The time when the vibration pattern different from the normal one occurs corresponds to the location of the abnormality in the transportation infrastructure on which the vehicle 100 is traveling. For example, when the sleepers of the railroad tracks are corroded, the vehicle 100 shakes strongly, causing a vibration pattern different from the normal one.

[0027] The information processing device 10 (20, 30) can estimate whether there is an abnormality in the transportation infrastructure by comparing the vibration data obtained when the transportation infrastructure is normal (Figure 2) with the vibration data acquired from the vehicle 100.

[0028] The information processing device 10 (20, 30) can estimate whether the transportation infrastructure has been properly repaired by comparing the vibration data (FIG. 3) obtained when the transportation infrastructure was abnormal with the vibration data acquired from the vehicle 100. Furthermore, the information processing device 10 (20, 30) can identify the location of the transportation infrastructure that has been repaired.

[0029] In addition, based on the difference between vibration data acquired before the period during which repairs to the transportation infrastructure were carried out and vibration data acquired after that period, the information processing device 10 (20, 30) can estimate whether repairs to the transportation infrastructure were carried out in accordance with the work plan.

[0030] (Example of a work plan) Fig. 4 is a diagram showing an example of a work plan stored in the work plan DB of the server 200 (Fig. 1). In the example shown in Fig. 4, for each work plan for repairing a transportation infrastructure, the location where the work will be performed, the scheduled start date, the start date and time, and the completion date and time are shown.

[0031] Here, the planned start date is the date and time when the work is scheduled to start in the work plan, the start date and time is the date and time when the work actually started, and the completion date and time is the date and time when the work is reported to be completed. In Figure 4, the period during which the transportation infrastructure repairs were carried out corresponds to the start date and time to the completion date and time.

[0032] [Embodiment 1] The first embodiment will be described with reference to FIGS.

[0033] (Configuration of information processing device 10) 5 is a block diagram showing the configuration of the information processing device 10 according to the embodiment 1. As shown in FIG.

[0034] The acquisition unit 11 acquires a work plan including a period during which repairs to the transportation infrastructure were carried out. The acquisition unit 11 is an example of an acquisition means.

[0035] For example, the acquisition unit 11 accesses the server 200 (FIG. 1) via a communication network, and acquires a work plan including a period during which repairs to the transportation infrastructure were carried out from the work plan DB (FIG. 2) of the server 200.

[0036] The acquisition unit 11 outputs, to the collection unit 12, information indicating the period during which the transportation infrastructure repairs were carried out.

[0037] The collection unit 12 collects sensor data including at least one of vibration data and voice data detected by the vehicle 100 while the vehicle 100 is passing through the transportation infrastructure before and after a period in which the transportation infrastructure is repaired. The collection unit 12 is an example of a collection means.

[0038] For example, the collection unit 12 receives information indicating a period during which repairs were performed on the transportation infrastructure from the acquisition unit 11. The collection unit 12 acquires, from the vehicle 100, sensor data detected by the vehicle 100 passing through the transportation infrastructure before the period during which the transportation infrastructure was repaired. The collection unit 12 also acquires, from the vehicle 100, sensor data detected by the vehicle 100 passing through the transportation infrastructure after the period during which the transportation infrastructure was repaired.

[0039] The collection unit 12 may refer to the traffic records of the multiple vehicles 100, identify among the multiple vehicles 100 the vehicles 100 that passed through the transportation infrastructure before and after a period in which repairs were carried out on the transportation infrastructure, and collect sensor data from the identified vehicles 100.

[0040] The collection unit 12 outputs the collected sensor data to the estimation unit 13.

[0041] The estimation unit 13 estimates whether the repair of the transportation infrastructure has been carried out in accordance with the work plan based on a change in the sensor data between before and after the period in which the repair of the transportation infrastructure has been carried out. The estimation unit 13 is an example of an estimation means.

[0042] For example, the estimation unit 13 receives from the collection unit 12 sensor data detected by the vehicle 100 before the period during which repairs to the transportation infrastructure were carried out, and sensor data detected by the vehicle 100 after the period during which repairs to the transportation infrastructure were carried out.

[0043] The estimation unit 13 compares sensor data detected by the vehicle 100 before the period during which the transportation infrastructure repairs were carried out with sensor data detected by the vehicle 100 after the period during which the transportation infrastructure repairs were carried out.

[0044] In one example, the estimation unit 13 calculates the difference between the peak value of the sensor data for a certain period of time before the period in which the transportation infrastructure repairs were carried out and the peak value of the sensor data for a certain period of time after the period in which the transportation infrastructure repairs were carried out.

[0045] Specifically, the certain period before the period in which the transportation infrastructure repairs were implemented is from X o'clock to Y o'clock on the day before the period in which the transportation infrastructure repairs were implemented, and the certain period after the period in which the transportation infrastructure repairs were implemented is from X o'clock to Y o'clock on the day after the period in which the transportation infrastructure repairs were implemented (X and Y are arbitrary times). However, the certain period is not limited to this example.

[0046] If the calculated difference is equal to or greater than the threshold, the estimation unit 13 estimates that the transportation infrastructure has been repaired in accordance with the work plan. On the other hand, if the calculated difference is less than the threshold, the estimation unit 13 estimates that the transportation infrastructure has not been repaired in accordance with the work plan.

[0047] In another example, the estimation unit 13 compares (matches) a pattern of sensor data for a certain period before the period in which the repair of the transportation infrastructure was carried out with a pattern of sensor data for a certain period after the period in which the repair of the transportation infrastructure was carried out. Any well-known technique for matching time-series data can be used for matching the sensor data.

[0048] If the matching fails (i.e., the patterns do not match), the estimation unit 13 estimates that the transportation infrastructure has been repaired in accordance with the work plan. On the other hand, if the matching is successful (i.e., the patterns match), the estimation unit 13 estimates that the transportation infrastructure has not been repaired in accordance with the work plan.

[0049] The estimation unit 13 outputs the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan to an external device. Alternatively, the estimation unit 13 may store the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan in a storage device (not shown).

[0050] (Operation of information processing device 10) The operation of the information processing device 10 according to the first embodiment will be described with reference to FIG.

[0051] 6, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure was repaired from the server 200 (FIG. 1) (S101). The acquisition unit 11 outputs information indicating the period during which the transportation infrastructure was repaired to the collection unit 12.

[0052] Next, the collection unit 12 collects sensor data including at least one of vibration data and voice data detected by the moving body while the moving body passes through the transportation infrastructure before and after the period in which the transportation infrastructure was repaired from the vehicle 100 (FIG. 1) (S102). The collection unit 12 outputs the collected sensor data to the estimation unit 13.

[0053] Thereafter, the estimation unit 13 estimates whether or not repairs to the transportation infrastructure have been carried out in accordance with the work plan, based on changes in the sensor data between before and after the period in which the repairs to the transportation infrastructure were carried out (S103).

[0054] The estimation unit 13 outputs the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan to an external device. Alternatively, the estimation unit 13 may store the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan in a storage device (not shown).

[0055] This is the end of the operation of the information processing device 10 according to the first embodiment.

[0056] (Effects of this embodiment) According to the configuration of this embodiment, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure was repaired. The collection unit 12 collects sensor data including at least one of vibration data and voice data detected by a mobile object while the mobile object passes through the transportation infrastructure before and after the period during which the transportation infrastructure was repaired. The estimation unit 13 estimates whether the transportation infrastructure was repaired according to the work plan based on a change in the sensor data before and after the period during which the transportation infrastructure was repaired.

[0057] If there is a change in the sensor data, it is presumed that the transportation infrastructure was repaired at the date and time specified in the work plan. On the other hand, if there is no change in the sensor data, it is presumed that the transportation infrastructure was not repaired at the date and time specified in the work plan. This allows managers, etc. to estimate whether the transportation infrastructure was repaired correctly in accordance with the work plan.

[0058] [Embodiment 2] A second embodiment will be described with reference to Figs. 7 and 8. In the second embodiment, a configuration for notifying a manager's terminal or the like when it is estimated that a transportation infrastructure has not been repaired at the date and time set in a work plan will be described. In the second embodiment, components common to the first embodiment are given the same reference numerals as in the first embodiment, and descriptions of these components will be omitted.

[0059] (Configuration of information processing device 20) Fig. 7 is a block diagram showing a configuration of an information processing device 20 according to embodiment 2. As shown in Fig. 7, the information processing device 20 includes an acquisition unit 11, a collection unit 12, and an estimation unit 13. The information processing device 20 further includes a notification unit 24.

[0060] The notification unit 24 issues a notification when it is estimated that the transportation infrastructure repairs have not been carried out in accordance with the work plan. The notification unit 24 is an example of a notification means.

[0061] For example, the notification unit 24 receives an estimation result from the estimation unit 13 as to whether or not repairs to the transportation infrastructure have been carried out in accordance with the work plan. When the notification unit 24 receives an estimation result that the transportation infrastructure has been repaired in accordance with the work plan, the notification unit 24 does not perform any action. On the other hand, when the notification unit 24 receives an estimation result that the transportation infrastructure has not been repaired in accordance with the work plan, the notification unit 24 notifies a terminal of a manager or the like. In one example, the notification unit 24 issues an alert from the terminal of the manager or the like.

[0062] (Operation of information processing device 20) The operation of the information processing device 20 according to the second embodiment will be described with reference to FIG.

[0063] 8, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure repair was carried out from the server 200 (FIG. 1) (S201). The acquisition unit 11 outputs information indicating the period during which the transportation infrastructure repair was carried out to the collection unit 12.

[0064] Next, the collection unit 12 collects sensor data including at least one of vibration data and voice data detected by the moving body while the moving body passes through the transportation infrastructure before and after the period in which the transportation infrastructure was repaired from the vehicle 100 (FIG. 1) (S202). The collection unit 12 outputs the collected sensor data to the estimation unit 13.

[0065] Thereafter, the estimation unit 13 estimates whether or not repairs to the transportation infrastructure have been carried out in accordance with the work plan based on changes in the sensor data between before and after the period in which the repairs to the transportation infrastructure were carried out (S203).

[0066] The estimation unit 13 outputs the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan to an external device. Alternatively, the estimation unit 13 may store the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan in a storage device (not shown).

[0067] Furthermore, the estimation unit 13 outputs to the notification unit 24 the estimation result as to whether or not the transportation infrastructure repairs have been carried out in accordance with the work plan.

[0068] The notification unit 24 estimates whether the repairs to the transportation infrastructure have been properly carried out in accordance with the work plan based on the estimation result by the estimation unit 13 (S204).

[0069] If the estimation result by the estimation unit 13 indicates that the transportation infrastructure has been repaired in accordance with the work plan, the flow ends. On the other hand, if the estimation result by the estimation unit 13 indicates that the transportation infrastructure has not been repaired in accordance with the work plan, the notification unit 24 notifies the manager's terminal or the like (S205).

[0070] This is the end of the operation of the information processing device 20 according to the second embodiment.

[0071] (Effects of this embodiment) According to the configuration of this embodiment, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure was repaired. The collection unit 12 collects sensor data including at least one of vibration data and voice data detected by a mobile object while the mobile object passes through the transportation infrastructure before and after the period during which the transportation infrastructure was repaired. The estimation unit 13 estimates whether the transportation infrastructure was repaired according to the work plan based on a change in the sensor data before and after the period during which the transportation infrastructure was repaired.

[0072] If there is a change in the sensor data, it is presumed that the transportation infrastructure was repaired at the date and time specified in the work plan. On the other hand, if there is no change in the sensor data, it is presumed that the transportation infrastructure was not repaired at the date and time specified in the work plan. This allows managers, etc. to estimate whether the transportation infrastructure was repaired correctly in accordance with the work plan.

[0073] Furthermore, according to the configuration of this embodiment, the notification unit 24 notifies when it is estimated that the transportation infrastructure repairs have not been carried out in accordance with the work plan. This allows the manager or the like to know that the transportation infrastructure repairs have not been carried out in accordance with the work plan and to take prompt action.

[0074] [Embodiment 3] A third embodiment will be described with reference to Figs. 9 to 11. In the third embodiment, a configuration will be described in which information indicating a work plan is presented based on a work plan and an estimation result as to whether repairs to the transportation infrastructure have been carried out. In the third embodiment, components common to the first or second embodiment are given the same reference numerals as the first or second embodiment, and descriptions of these components will be omitted.

[0075] (Configuration of information processing device 30) Fig. 9 is a block diagram showing a configuration of an information processing device 30 according to the present embodiment 3. As shown in Fig. 9, the information processing device 30 includes an acquisition unit 11, a collection unit 12, and an estimation unit 13. The information processing device 30 further includes a presentation unit 34.

[0076] The presentation unit 34 presents information indicating the work plan based on the work plan and the estimation result as to whether or not the transportation infrastructure repair has been carried out. The presentation unit 34 is an example of a presentation means.

[0077] For example, the presentation unit 34 receives an estimation result as to whether or not repairs to the transportation infrastructure have been carried out in accordance with the work plan from the estimation unit 13. Furthermore, the presentation unit 34 accesses from the server 200 (FIG. 1) and acquires a work plan including a period during which the repairs to the transportation infrastructure have been carried out from the work plan DB (FIG. 2) of the server 200. The presentation unit 34 presents the estimation result as to whether or not repairs to the transportation infrastructure have been carried out together with information indicating the work plan.

[0078] (Presentation of work plan and estimated results) An example of information presented by the presentation unit 34 will be described with reference to Fig. 10. In the example shown in Fig. 10, four progress statuses for transportation infrastructure repairs, "Not yet done" (not started), "Working", "Work completed (change in sensor data)", and "Work completed? (no change in sensor data)", are displayed on a one-dimensional graph. In the figure, triangles simulate the positions of locations P1 to P4 where transportation infrastructure repairs are being implemented.

[0079] For example, at location P5, the progress status of transportation infrastructure repairs is "not done." This means that, according to the work plan, the transportation infrastructure repairs will be carried out in the future at location P5. On the other hand, at locations P2 and P3, the progress status of transportation infrastructure repairs is "work in progress." This means that, according to the work plan, transportation infrastructure repairs are currently being carried out at locations P2 and P3.

[0080] At location P4, the progress status of the traffic infrastructure repair is "Work completed? (no change in sensor data)." This indicates that, according to the work plan, the period during which the traffic infrastructure was repaired at location P4 has passed, and the sensor data has not changed between before and after the period during which the traffic infrastructure was repaired. In other words, this indicates that the traffic infrastructure at location P4 may not have been repaired correctly according to the repair plan.

[0081] At location P1, the progress status of the traffic infrastructure repair is "Work completed (change in sensor data)." This indicates that, according to the work plan, the period during which the traffic infrastructure was repaired at location P1 has passed, and the sensor data has changed between before and after the period during which the traffic infrastructure was repaired. In other words, it indicates that there is a high possibility that the traffic infrastructure was properly repaired at location P1 according to the repair plan.

[0082] (Operation of information processing device 30) The operation of the information processing device 30 according to the third embodiment will be described with reference to FIG.

[0083] 11, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure repair was carried out from the server 200 (FIG. 1) (S301). The acquisition unit 11 outputs information indicating the period during which the transportation infrastructure repair was carried out to the collection unit 12.

[0084] Next, the collection unit 12 collects sensor data including at least one of vibration data and voice data detected by the moving body while the moving body passes through the transportation infrastructure before and after the period in which the transportation infrastructure was repaired from the vehicle 100 ( FIG. 1 ) (S302). The collection unit 12 outputs the collected sensor data to the estimation unit 13.

[0085] Thereafter, the estimation unit 13 estimates whether or not repairs to the transportation infrastructure have been carried out in accordance with the work plan based on changes in the sensor data between before and after the period in which the repairs to the transportation infrastructure were carried out (S303).

[0086] The estimation unit 13 outputs the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan to an external device. Alternatively, the estimation unit 13 may store the estimation result as to whether or not the transportation infrastructure has been repaired according to the work plan in a storage device (not shown).

[0087] Furthermore, the estimation unit 13 outputs to the presentation unit 34 an estimation result as to whether or not the transportation infrastructure has been repaired in accordance with the work plan.

[0088] The presentation unit 34 presents the estimation result as to whether or not repairs have been carried out on the transportation infrastructure together with information indicating the work plan (S304).

[0089] This is the end of the operation of the information processing device 30 according to the third embodiment.

[0090] (Effects of this embodiment) According to the configuration of this embodiment, the acquisition unit 11 acquires a work plan including a period during which the transportation infrastructure was repaired. The collection unit 12 collects sensor data including at least one of vibration data and voice data detected by a mobile object while the mobile object passes through the transportation infrastructure before and after the period during which the transportation infrastructure was repaired. The estimation unit 13 estimates whether the transportation infrastructure was repaired according to the work plan based on a change in the sensor data before and after the period during which the transportation infrastructure was repaired.

[0091] If there is a change in the sensor data, it is presumed that the transportation infrastructure was repaired at the date and time specified in the work plan. On the other hand, if there is no change in the sensor data, it is presumed that the transportation infrastructure was not repaired at the date and time specified in the work plan. This allows managers, etc. to estimate whether the transportation infrastructure was repaired correctly in accordance with the work plan.

[0092] Furthermore, according to the configuration of this embodiment, the presentation unit 34 presents the estimated result of whether or not the transportation infrastructure has been repaired together with the information indicating the work plan, so that the manager or the like can easily check whether or not the transportation infrastructure has been repaired correctly according to the work plan.

[0093] (Hardware configuration) Each of the components of the information processing devices 10, 20, and 30 described in the first to third embodiments is represented by a functional block. Some or all of these components are realized by an information processing device as shown in Fig. 12. Fig. 12 is a block diagram showing an example of the hardware configuration of the information processing device.

[0094] 12, the computer 110 includes a CPU (Central Processing Unit) 111, a main memory 112, a storage device 113, an input interface 114, a display controller 115, a data reader / writer 116, and a communication interface 117. These components are connected to each other via a bus 121 so as to be able to communicate data with each other. Note that the computer 110 may include a GPU (Graphics Processing Unit) or an FPGA (Field-Programmable Gate Array) in addition to the CPU 111 or instead of the CPU 111.

[0095] The CPU 111 loads the programs (codes) in this embodiment stored in the storage device 113 into the main memory 112 and executes them in a predetermined order to perform various calculations. The main memory 112 is typically a volatile storage device such as a dynamic random access memory (DRAM). The programs in this embodiment are provided in a state stored in a computer-readable recording medium 120. The programs in this embodiment may be distributed over the Internet connected via a communication interface 117.

[0096] Specific examples of the storage device 113 include a hard disk drive and a semiconductor storage device such as a flash memory. The input interface 114 mediates data transmission between the CPU 111 and input devices 118 such as a keyboard and a mouse. The display controller 115 is connected to a display device 119 and controls the display on the display device 119.

[0097] Data reader / writer 116 mediates data transmission between CPU 111 and recording medium 120, reads programs from recording medium 120, and writes processing results in computer 110 to recording medium 120. Communication interface 117 mediates data transmission between CPU 111 and other computers.

[0098] Specific examples of recording medium 120 include general-purpose semiconductor storage devices such as CF (Compact Flash (registered trademark)) and SD (Secure Digital), magnetic recording media such as a flexible disk, or optical recording media such as a CD-ROM (Compact Disk Read Only Memory).

[0099] A part or all of the above-described embodiments can be described as, but is not limited to, the following supplementary notes.

[0100] (Appendix 1) an acquisition means for acquiring a work plan including the period during which repairs to the transportation infrastructure were performed; a collection means for collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before and after the period; and an estimation means for estimating whether repairs to the transportation infrastructure have been performed in accordance with the work plan based on a change in the sensor data between before the period and after the period. Information processing device.

[0101] (Appendix 2) When a peak value of the amount of change in the sensor data between the period before and the period after which repairs to the transportation infrastructure are carried out is equal to or greater than a threshold value, the estimation means estimates that repairs to the transportation infrastructure have been carried out. 2. The information processing device according to claim 1 .

[0102] (Appendix 3) When a peak value of the amount of change in the sensor data between before the period during which the transportation infrastructure is repaired and after the period is below a threshold value, the estimation means estimates that the transportation infrastructure is not repaired. 2. The information processing device according to claim 1 .

[0103] (Appendix 4) The estimation means estimates whether repairs to the transportation infrastructure have been carried out based on a change in a pattern of the sensor data in a time series between before the period during which repairs to the transportation infrastructure are carried out and after the period. 2. The information processing device according to claim 1 .

[0104] (Appendix 5) The method further includes a notification means for notifying the user when it is estimated that repairs to the transportation infrastructure have not been carried out in accordance with the work plan. 2. The information processing device according to claim 1 .

[0105] (Appendix 6) The collection means refers to traffic records of a plurality of mobile objects, identifies, among the plurality of mobile objects, a mobile object that has passed through the transportation infrastructure before and after the period during which the transportation infrastructure is repaired, and collects the sensor data from the identified mobile object. 2. The information processing device according to claim 1 .

[0106] (Appendix 7) a presentation means for presenting an estimate of whether the transportation infrastructure has been repaired together with information indicating the work plan; Further equipped 7. The information processing device according to claim 1,

[0107] (Appendix 8) The information indicating the work plan includes at least a location where the repair of the transportation infrastructure is to be performed and a progress status of the repair of the transportation infrastructure. 8. The information processing device according to claim 7.

[0108] (Appendix 9) Obtain a work plan including the period during which repairs to transportation infrastructure were carried out; collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before and after the period; Inferring whether repairs to the transportation infrastructure were performed according to the work plan based on a change in the sensor data between before the time period and after the time period. Information processing methods.

[0109] (Appendix 10) Obtaining a work plan that includes the period during which repairs to transportation infrastructure were performed; collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before the period and after the period; Inferring whether repairs to the transportation infrastructure were performed according to the work plan based on changes in the sensor data between before the time period and after the time period; A program for causing a computer to execute the following.

[0110] The present invention has been described above with reference to several embodiments. However, the present invention is not limited to the above embodiments. Various modifications that can be understood by those skilled in the art can be made to the configurations and details of the above embodiments within the scope of the present invention. [Industrial Applicability]

[0111] The present invention can be used in a work management system that manages work for the safe maintenance and repair of transportation infrastructure. [Explanation of symbols]

[0112] 1 Work Management System 10. Information processing device 11 Acquisition Department 12 Collection Department 13 Estimation part 20 Information processing device 24 Notification Department 30 Information processing device 34 Presentation part 100 vehicles

Claims

1. an acquisition means for acquiring a work plan including the period during which repairs to the transportation infrastructure were performed; a collection means for collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before and after the period; and an estimation means for estimating whether repairs to the transportation infrastructure have been performed in accordance with the work plan based on a change in the sensor data between before the period and after the period. Information processing device.

2. When a peak value of the amount of change in the sensor data between the period before and the period after which repairs to the transportation infrastructure are carried out is equal to or greater than a threshold value, the estimation means estimates that repairs to the transportation infrastructure have been carried out.

2. The information processing apparatus according to claim 1,

3. When a peak value of the amount of change in the sensor data between before the period during which the transportation infrastructure is repaired and after the period is below a threshold value, the estimation means estimates that the transportation infrastructure is not repaired.

2. The information processing apparatus according to claim 1,

4. The estimation means estimates whether repairs to the transportation infrastructure have been carried out based on a change in a pattern of the sensor data in a time series between before the period during which repairs to the transportation infrastructure are carried out and after the period.

2. The information processing apparatus according to claim 1,

5. The method further includes a notification means for notifying the user when it is estimated that repairs to the transportation infrastructure have not been carried out in accordance with the work plan.

2. The information processing apparatus according to claim 1,

6. The collection means refers to traffic records of a plurality of mobile objects, identifies, among the plurality of mobile objects, a mobile object that has passed through the transportation infrastructure before and after the period during which the transportation infrastructure is repaired, and collects the sensor data from the identified mobile object.

2. The information processing apparatus according to claim 1,

7. a presentation means for presenting an estimate of whether the transportation infrastructure has been repaired together with information indicating the work plan; Further equipped 7. The information processing apparatus according to claim 1,

8. The information indicating the work plan includes at least a location where the repair of the transportation infrastructure is to be performed and a progress status of the repair of the transportation infrastructure.

8. The information processing apparatus according to claim 7,

9. Obtain a work plan including the period during which repairs to transportation infrastructure were carried out; collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before and after the period; Inferring whether repairs to the transportation infrastructure were performed according to the work plan based on a change in the sensor data between before the time period and after the time period. Information processing methods.

10. Obtaining a work plan that includes the period during which repairs to transportation infrastructure were performed; collecting sensor data including at least one of vibration data and voice data detected by a moving object while the moving object is passing through the transportation infrastructure before the period and after the period; Inferring whether repairs to the transportation infrastructure were performed according to the work plan based on changes in the sensor data between before the time period and after the time period; A program for causing a computer to execute the following.

Citation Information

Patent Citations

  • Method and system for railroad vehicle track maintenance

    JP2019525862A