Joint member, installation structure of scaffolding board, and method of placing slab
The joining member system addresses the inefficiency and safety issues of conventional scaffolding by enabling reusable connections between scaffolding boards and concrete, facilitating rapid setup and teardown for concrete pouring operations.
Patent Information
- Application Number
- JP2023086820
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-26
- Publication Date
- 2024-12-06
AI Technical Summary
Conventional scaffolding boards are flat and pose a risk of slipping, requiring frequent disassembly and reassembly for each concrete pouring site, which is time-consuming and inefficient.
A joining member with a first and second joint part allows rod-shaped members to be connected to scaffolding boards and inserted into concrete, enabling efficient reuse and safe working conditions by allowing the scaffold to be easily assembled and disassembled.
The solution provides a safe and efficient scaffold system that can be reused across multiple concrete pouring sites, reducing setup time and effort while ensuring worker safety.
Smart Images

Figure 2024169945000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a joint member, a scaffolding board installation structure, and a slab casting method. [Background technology]
[0002] Conventionally, mat slabs formed of concrete in a flat plate shape have been known as building foundations (see Patent Document 1 below). In some cases, reinforcing bars are laid out in a grid pattern or the like on the upper side of the ground surface, and concrete is poured to bury the reinforcing bars to form a mat slab. Scaffolding boards are set up on the upper side of the reinforcing bars, and workers stand on the scaffolding boards to pour concrete. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2022-184328 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, the scaffolding boards installed on the top of the reinforcing bars, etc., are flat, and there is a possibility that a foot may slip off the flat scaffolding board. Even if the scaffolding is assembled and set up, it is necessary to dismantle it when the concrete pouring work is completed, and to assemble a new scaffolding at the next concrete pouring work site, which is a problem that takes time and effort.
[0005] Therefore, the present invention has been made in consideration of the above circumstances, and provides a connecting member, a scaffolding board installation structure, and a slab pouring method that enable scaffolding to be installed safely and that allows efficient use of components. [Means for solving the problem]
[0006] The connecting member in the first aspect comprises a first connecting portion joined to one end of a rod-shaped member connected to a scaffolding board, and a second connecting portion joined to one end of a rod-shaped material to be inserted into pre-hardened concrete, and the first connecting portion and the second connecting portion are arranged on the same straight line as the rod-shaped member and the rod-shaped material.
[0007] In the joint member configured in this manner, one end of a rod-shaped member connected to a scaffolding board is joined to a first joint of the joint member. One end of a rod-shaped member to be inserted into unhardened concrete is joined to a second joint of the joint member. Therefore, each member including the joint member can be reused at the next concrete pouring location, and the members constituting the scaffolding can be used efficiently. In addition, workers can use scaffolding to carry out their work, enabling them to work safely.
[0008] In the joint member according to the second aspect, a female thread may be formed on an inner circumferential surface of the second joint portion.
[0009] In the joining member thus configured, one end of the rod-shaped material having a male thread is screwed into the second joining portion having a female thread formed on the inner circumferential surface, so that the rod-shaped material can be easily joined to the second joining portion.
[0010] The installation structure for a scaffolding board in the third aspect comprises the above-mentioned connecting member, a support member having a rod-shaped member connected to the first connecting portion and a rod-shaped member connected to the second connecting portion, and a scaffolding board supported by the support member.
[0011] In the scaffolding board installation structure configured in this manner, one end of a rod-shaped member connected to the scaffolding board is joined to a first joint of the joint member. One end of a rod-shaped material to be inserted into pre-hardened concrete is joined to a second joint of the joint member. The scaffolding board can be supported by the support member constructed in this way to construct the scaffolding. After using the scaffolding, the support member can be removed from the scaffolding board, and the rod-shaped members and rod-shaped materials can be removed from the joint member, allowing each component to be reused, and the components that make up the scaffolding can be used efficiently. In addition, workers can use scaffolding to carry out their work, enabling them to work safely.
[0012] In the joining member according to the fourth aspect, a peelable tape may be wound around the outer circumferential surface of the bar-shaped material.
[0013] In the joining member configured in this manner, a removable tape is wound around the outer periphery of the rod-shaped material, so that the tape touches the concrete rather than the rod-shaped material touching the concrete directly, making it easier to pull the rod-shaped material out of the poured concrete.
[0014] A fifth aspect of the slab pouring method is a slab pouring method using the above-mentioned scaffolding board installation structure, in which a scaffolding unit is installed so that the scaffolding board is supported by a plurality of the support members, a pump truck hose is lowered downward from the scaffolding board, concrete is poured, the support members are removed from the concrete before the concrete hardens, and the scaffolding unit is transported.
[0015] In the slab casting method configured in this way, before the concrete hardens, the support members are pulled out of the concrete and the scaffolding unit is transported. At the next concrete casting location, the scaffolding boards and support members can be reused, and the members that make up the scaffolding board installation structure can be used efficiently. In addition, workers can use the scaffolding board installation structure to pour concrete, allowing them to work safely. Effect of the Invention
[0016] The connecting members, scaffolding board installation structure, and slab pouring method of the present invention enable scaffolding to be installed for safe work and enable efficient use of members. [Brief description of the drawings]
[0017] [Figure 1]1 is a schematic perspective view showing an installation structure of a scaffolding board according to one embodiment of the present invention; FIG. [Diagram 2] FIG. 2 is a front view of a support member according to an embodiment of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0018] The connecting members, the scaffolding board installation structure, and the slab casting method according to one embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a schematic perspective view showing a scaffolding board installation structure according to one embodiment of the present invention. The scaffolding board installation structure 1 according to this embodiment shown in Fig. 1 is used, for example, when pouring a large-area slab. The scaffolding board installation structure 1 includes a scaffolding unit (scaffolding) 2. The scaffolding unit 2 includes a lower structure portion 21, an upper structure portion 26, and a support member 3.
[0019] The lower structure 21 has a lower support member 22 formed, for example, in a frame shape, and a plurality of scaffolding boards 23 supported by the lower support member. A hose hole 24 is formed between adjacent scaffolding boards 23, penetrating in the vertical direction.
[0020] The upper structure 26 has a plurality of upper and lower members 27 and a handrail portion 28. The lower ends of the upper and lower members 27 are connected so as to be supported by the lower support member 22. The handrail portion 28 connects the plurality of upper and lower members 27 together and extends in the horizontal direction. The configurations of the lower structure 21 and the upper structure 26 can be set as appropriate.
[0021] An upper portion of the support member 3 is connected to the lower support member 22. The support member 3 is connected to support the scaffolding board 23 via the lower support member 22. Note that the support member 3 may be directly connected to the scaffolding board 23.
[0022] FIG. 2 is a front view of the support member 3. As shown in FIG. The support member 3 includes a rod-shaped member 31, a joint member 36, and a bolt member (rod-shaped member) 50.
[0023] The support member 3 will be described based on the orientation of the support member 3 in an installed state. 3, the rod-shaped member 31 is formed in a cylindrical shape with its axial direction being the up-down direction (one direction). The rod-shaped member 31 is made of a metal member. The rod-shaped member 31 is, for example, a single tube pipe.
[0024] The joining member 36 has a first joining portion 37, an intermediate portion 41, and a nut (second joining portion) 47.
[0025] The first joint portion 37 is located at the upper end (first end) of the joint member 36. The first joint portion 37 is formed in a cylindrical shape with the vertical direction as the axial direction. The inner diameter of the inner circumferential surface of the first joint portion 37 is slightly larger than the outer diameter of the outer circumferential surface of the rod-shaped member 31. The lower end portion (one end) 31d of the rod-shaped member 31 is inserted into the first joint portion 37 from above.
[0026] The first joint portion 37 is formed with mounting holes 37h penetrating in the radial direction. The mounting holes 37h are formed at three locations spaced apart in the circumferential direction. Although it is preferable that the mounting holes 37h are formed at a plurality of locations, it is sufficient that the mounting holes 37h are formed at one or more locations.
[0027] The screw 38 is inserted through the mounting hole 37h and screwed into a screw hole formed in the lower end 31d of the rod-shaped member 31. When the screw 38 is removed, the lower end 31d of the rod-shaped member 31 is removed from the first joint portion 37. In this manner, the rod-shaped member 31 is detachably joined to the joint member 36.
[0028] The intermediate portion 41 is formed in a flat plate shape. The plate surface of the intermediate portion 41 faces the vertical direction. When viewed from the vertical direction, the outer shape of the intermediate portion 41 is a circle having a diameter larger than the diameter of the first joint portion 37. A through hole (not shown) is formed in the intermediate portion 41 so as to penetrate in the vertical direction. The shape of the intermediate portion 41 can be set as appropriate.
[0029] The nut 47 is located at the lower end (second end) of the joining member 36. The nut 47 is joined to the upper part of the intermediate part 41. An internal thread is formed on the inner circumferential surface of the nut 47.
[0030] The bolt member 50 has a rod-shaped portion 51 and a screw-type portion 56. In this embodiment, the bolt member 50 is a fully threaded bolt.
[0031] The rod-shaped portion 51 extends in the vertical direction. The rod-shaped portion 51 has a cylindrical shape with the vertical direction as the axial direction. The screw-type portion 56 is a male screw formed on the outer peripheral surface of the rod-shaped portion 51. The screw-type portion 56 is formed over the entire length of the rod-shaped portion 51 in the vertical direction. It is sufficient that the screw-type portion 56 is formed only on at least the upper end portion (one end portion in one direction) 56u of the rod-shaped portion 51.
[0032] An upper end 56u of the screwing portion 56 is inserted into a through hole in the intermediate portion 41 and screwed into a nut 47 of the joining member 36. Two nuts 57 are screwed into the screwing portion 56 at a position below the intermediate portion 41. This makes it possible to suppress loosening between the screwing portion 56 and the nuts 47. Note that the nuts 57 do not necessarily have to be provided.
[0033] By loosening the nut 57 from the bolt member 50 and loosening the screw engagement between the bolt member 50 and the nut 47, the bolt member 50 can be removed from the nut 47. In this manner, the bolt member 50 is detachably joined to the joining member .
[0034] With the rod-shaped member 31 joined to the first joint portion 37 of the joint member 36 and the bolt member 50 joined to the nut 47, the rod-shaped member 31 and the bolt member 50 are arranged on the same straight line. The first joint portion 37 and the nut 47 are also arranged on the same straight line as the straight line on which the rod-shaped member 31 and the bolt member 50 are arranged.
[0035] A removable tape 59 is wound around the outer circumferential surface of the rod-shaped portion 51 over substantially the entire length below the nut 57 .
[0036] Next, a method for pouring a slab will be described. The support member 3 is assembled in advance. The lower end 31d of the rod-shaped member 31 is inserted into the first joint portion 37 of the joint member 36 and screwed in place with the screw 38. The upper end 56u of the threaded portion 56 of the bolt member 50 is inserted into the through-hole of the intermediate portion 41 of the joint member 36 and screwed into the nut 47. Furthermore, the nut 57 is screwed into the threaded portion 56 of the bolt member 50 at a position below the intermediate portion 41. A tape 59 is wound around the outer circumferential surface of the rod-shaped portion 51.
[0037] Next, the scaffolding board installation structure (scaffolding) 1 is installed. A plurality of support members 3 are installed on the installation surface, and the support members 3 are connected to the lower support members 22 of the scaffolding unit 2. As a result, the scaffolding boards 23 are supported by the support members 3, and the scaffolding unit 2 is installed. When installing the support members 3, if a plurality of reinforcing bars S are arranged in a lattice pattern above the installation surface, the support members 3 are installed so as not to interfere with the reinforcing bars S.
[0038] Next, the concrete is poured. A hose connected to the pump truck is extended to the scaffolding unit 2, and the hose is lowered downward from the hose hole 24 between adjacent scaffolding boards 23 to pour concrete. A worker can pour concrete while standing on the scaffolding boards 23.
[0039] Next, before the concrete hardens, the scaffolding unit 2 including the support member 3 is lifted as a whole by a crane.
[0040] Next to the area where the concrete has been poured, the scaffolding unit 2 is set up in the same manner as above, and the concrete is poured. This is repeated, and the scaffolding unit 2 is moved next to each of the areas where the concrete has been poured, and concrete is poured. Once all the concrete has been poured, the scaffolding unit 2 is temporarily placed on the ground by a crane, and the supporting members 3 with the concrete attached are washed with water in preparation for the next concrete pour.
[0041] The support member 3 and slab pouring method configured in this manner enable efficient utilization of the scaffolding unit 2.
[0042] In addition, workers can use the scaffolding board installation structure 1 to pour concrete, allowing them to work safely.
[0043] Further, the upper end portion 56u of the bolt member 50, on which a male thread is formed, is screwed into the nut 47, on whose inner circumferential surface a female thread is formed. Therefore, the bolt member 50 can be easily joined to the nut 47 of the joining member 36.
[0044] In addition, a peelable tape 59 is wound around the outer circumferential surface of the rod-shaped portion 51 of the support member 3. Therefore, by having the tape 59 touch the concrete rather than having the rod-shaped portion 51 directly touch the concrete, it is possible to make it easier to pull out the rod-shaped portion 51 from the poured concrete.
[0045] Although one embodiment of the present invention has been described above, the technical scope of the present invention is not limited to the above embodiment, and it is possible to change the combination of components, add various modifications to each component, or delete components without departing from the spirit of the present invention. Some modifications are illustrated below, but these are not all inclusive, and other modifications are also possible. In addition, two or more of these modifications may be appropriately combined.
[0046] For example, in the embodiment described above, the tape 59 is wound around the rod-shaped portion 51 of the bolt member 50, but the present invention is not limited to this. The tape 59 does not have to be wound around the rod-shaped portion 51. [Explanation of symbols]
[0047] 1. Scaffolding board installation structure 3 Supporting member 23 Scaffolding Board 31 Rod-shaped member 36 Joining materials 37 First joint 47 Nut (second joint) 50 Bolt material (rod material) 51 Rod-shaped part 56 Threaded joint 59 Tape
Claims
1. A first joint portion joined to one end of a rod-shaped member connected to the scaffolding board; and a second joint portion to which one end of the rod-shaped material to be inserted into the unhardened concrete is joined, The first joint portion and the second joint portion are joint members that are arranged on the same straight line as the rod-shaped member and the rod-shaped material.
2. The joining member according to claim 1 , wherein an internal thread is formed on an inner circumferential surface of the second joining portion.
3. A support member including the joining member according to claim 1 or 2, a rod-shaped member joined to the first joining portion, and a rod-shaped member joined to the second joining portion; A scaffolding board installation structure comprising: a scaffolding board supported by the support member.
4. The scaffolding board installation structure according to claim 3, wherein a peelable tape is wound around the outer peripheral surface of the rod-shaped material.
5. A method for pouring a slab using the scaffolding board installation structure according to claim 3, A scaffold unit is installed so as to support the scaffold board with a plurality of the support members, The hose of the pump truck is lowered downward from the scaffolding board, and concrete is poured. A slab pouring method comprising: extracting the support member from the concrete before the concrete hardens; and transporting the scaffolding unit.