Wind Turbine Operation Transition

The method and control system for wind turbines manage power consumption by activating energy storage only under favorable conditions, ensuring operational readiness and preventing energy depletion during grid disconnection, thus facilitating efficient energy harvesting.

JP2024540361AActive Publication Date: 2024-10-31SIEMENS GAMESA RENEWABLE ENERGY AS
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2024526850
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Priority Date
2021-11-08
Filing Date
2022-11-07
Publication Date
2024-10-31
Estimated Expiration
2042-11-07

AI Technical Summary

Technical Problem

Wind turbines face challenges in efficiently transitioning to energy harvesting mode, particularly when disconnected from the grid, due to high energy consumption during startup, which can deplete energy storage systems, especially in weak or extreme wind conditions, leading to repeated restart failures.

Method used

A method and control system that activates the wind turbine's energy storage system to power auxiliary systems only when wind conditions meet predetermined criteria, allowing the turbine to operate in a sleep mode with reduced power consumption until conditions are suitable for energy harvesting, ensuring sufficient energy generation to avoid depletion.

Benefits of technology

This approach ensures the wind turbine remains operational and avoids energy depletion by optimizing power consumption based on environmental data and predictions, enabling reliable and repeated startups without depleting energy storage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024540361000001_ABST
    Figure 2024540361000001_ABST
Patent Text Reader

Abstract

A method is provided for transitioning operation of a wind turbine (100) to an energy harvesting mode in which the wind turbine (100) operates to generate electrical power from wind energy. An energy storage system (50) associated with the wind turbine (100) is configured to provide electrical power to the auxiliary system (10) when the wind turbine is not generating or receiving sufficient electrical power to power the auxiliary system (10). The method includes operating the wind turbine (100) in a first operating mode (72) that stops providing electrical power to one or more auxiliary power consumers (12, 13, 14) of a first group (11) of the auxiliary system (10), acquiring environmental data including at least one of wind data and weather data, and determining whether the acquired environmental data satisfies a predetermined condition. Operation of the wind turbine (100) is transitioned to an energy harvesting mode (74) when predetermined conditions are met, where transitioning operation to the energy harvesting mode (74) includes supplying power from the energy storage system (50) to one or more auxiliary power consumption devices (12, 13, 14) of the first group (11).
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a method for transferring the operation of a wind turbine into an energy harvesting mode, and further to a corresponding control system and a computer program for controlling the operation of a wind turbine.

[0002] background Wind turbines extract energy from moving wind currents and generate electricity that is typically fed into a power grid. In weak wind conditions or to perform service work, the wind turbine can be shut down and restarted using power from the power grid. Similarly, in strong wind conditions that exceed the wind speeds for which the wind turbine was designed, the operation of the wind turbine can be stopped or moved to an operating state that minimizes the load on the structure due to the respective environmental conditions. This can also occur in offshore wind turbines that experience excessively high wave loads or extreme wind conditions.

[0003] A wind turbine may be disconnected from the power grid, for example due to a grid failure or failure of any intermediate system. Also, some wind turbines may not be connected to the grid and may operate, for example, in an island mode. It is known to provide such wind turbines with devices for generating electrical energy to facilitate the starting of the wind turbine after it has been stopped. A typical example is a generator coupled to a diesel engine that generates the power required for starting. A large amount of power is required for starting a wind turbine, since several wind turbine systems, including large power consumers, must be operated. For example, the yaw drive and the pitch drive may consume a significant amount of power. In particular, the wind turbine rotor must be brought into alignment with respect to the wind direction by the operation of the yaw drive. To prepare the pitch system of the wind turbine for operation, the hydraulic pitch system needs to be pressurized, and the electric pitch system may need energy recovery for the emergency pitch system. Furthermore, the power conversion hardware of the wind turbine must be prepared for operation, for example by charging the DC bus of the power converter, which may include a relatively large size capacitor. It is also necessary to start the operation of the cooling system, which may include operating a fan and circulating a cooling fluid.

[0004] Thus, since a significant amount of energy is consumed during start-up, the respective system supplying electrical energy may become depleted after start-up or after a certain small number of starts. Further start-up attempts may therefore be impossible. This may be problematic, particularly in situations where the wind turbine needs to be shut down again immediately after start-up. Energy levels in the system supplying electrical energy for start-up must then be restored, which in some situations may not be possible or may only be possible after a significant delay and may require significant efforts (e.g. refueling diesel generators of offshore wind turbines). It is therefore desirable to avoid such a reduction in the energy available for start-up in wind turbines. It is also desirable to avoid excessive energy consumption, which may quickly deplete such energy storage systems, particularly in the case of wind turbines that are disconnected from the grid.

[0005] The document WO 2021 / 069045 relates to a method for transitioning a wind turbine from a sleep state to an active state when the measured wind speed exceeds a wake-up threshold, where before comparing the measured wind speed with the wake-up threshold, either the wind speed or the wake-up threshold is adjusted based on the outcome of at least one previous transition of the wind turbine from a sleep state.

[0006] overview There is therefore a need to improve the operation of such wind turbines by mitigating at least some of the above mentioned drawbacks, in particular to reduce the likelihood of depletion of the respective energy storage systems provided in the wind turbines.

[0007] The above requirements are met by the features of the respective independent claims. The respective dependent claims describe embodiments of the invention.

[0008] According to one aspect, a method is provided for transitioning the operation of a wind turbine to an energy harvesting mode in which the wind turbine operates to generate power from wind energy. An energy storage system associated with the wind turbine is configured to supply power to the auxiliary system when the wind turbine is not generating or receiving sufficient power to power its auxiliary system, for example when the wind turbine is not connected to the grid (e.g. when there is no grid connection or when it is disconnected from the power grid or when it can only receive a portion of the required power from the power grid). The method can include operating the wind turbine in a first operating mode (e.g., which can be referred to as a sleep mode) in which the wind turbine does not generate power from the wind energy. In the first operating mode, power supply to one or more auxiliary power consumers of a first group of the auxiliary power system is stopped. Furthermore, in the first operating mode, power is supplied from the energy storage system to one or more auxiliary power consumers of a second group of the auxiliary power system. The method further includes acquiring environmental data including at least one of wind data and weather data, and determining whether the acquired environmental data satisfies a predetermined condition, where the predetermined condition includes at least one of a wind speed threshold, a wind speed range in which the wind turbine is operable to generate electrical power, a wind speed trend threshold, or a predetermined energy threshold for expected energy production. The method includes transitioning operation of the wind turbine to an energy harvesting mode if the predetermined condition is met, where transitioning operation to the energy harvesting mode includes supplying power from the energy storage system to a first group of one or more auxiliary power consumers.

[0009] In this way, stored energy is saved, since operation in particular in the first operating mode results in only one group of auxiliary power consumers receiving power, while another group, which may include a larger load, does not. The power consumption of the first group of power consumers may in particular be (significantly) greater than the power consumption of the second group of power consumers. At the same time, the wind turbine remains operational, which allows an automatic transition to the energy harvesting mode. Furthermore, by performing such a transition based on predefined conditions, it can be ensured that the transition is only performed if the wind conditions are such that sufficient power can be generated. For example, the above conditions can be selected such that at least one amount of electrical energy is generated (i.e. the transition is performed) that is greater than the amount of electrical energy required for starting the wind turbine. The generated power can for example be used to recharge the energy storage system, so that the energy storage system is not depleted and repeated start-ups are possible. In particular, relatively quickly repeated failed restarts or restart attempts can be avoided for a return to energy harvesting for a long period of time.

[0010] The energy harvesting mode may in particular be an autonomous operating mode, in which the auxiliary systems of the wind turbine may be powered from the power generated by the wind turbine. Thus, the wind turbine may operate without a grid connection, i.e., grid-disconnected, which may be due to the absence of a grid connection or the wind turbine being disconnected from the power grid. In some examples, in the first operating mode or during the transition to the energy harvesting mode, there may still be a small auxiliary source of power from the power grid. However, during the first operating mode and during the transition, the main source of power (e.g., more than 50%, more than 75% or more than 90% of the power) is provided by the energy storage system. Preferably, during the first operating mode and during the transition to the energy harvesting mode, all of the power source is provided by the energy storage system. If the condition is not met, the wind turbine may continue to operate in the first operating mode. It is clear that the first operating mode may itself comprise different operating modes, for example a sleep mode in which only the second group of auxiliary power consumers is powered and another operating mode in which only a part of the second group of auxiliary power consumers is powered or none of the second group of auxiliary power consumers is powered. Furthermore, the transition from the first operating mode to the energy harvesting mode may be made via an intermediate operating mode, which may for example be called a "local power mode", in which the first group of auxiliary power consumers and the second group of auxiliary power consumers are supplied with power from the energy storage system (for example all auxiliary power consumers are powered) but the wind turbine is not yet generating power from the wind.

[0011] A wind turbine may include an energy storage system, for example, the energy storage system may be included within the wind turbine or may be located adjacent to the wind turbine tower.

[0012] A (signal) trend of a system parameter and / or an environmental parameter, e.g. wind speed trend, may be a parameter that represents the magnitude and / or direction in which a system parameter and / or an environmental parameter, e.g. wind speed, is occurring or changing. The trend may indicate whether the system parameter and / or the environmental parameter is increasing or decreasing with respect to time. Thus, the trend may indicate the direction and / or magnitude of the occurrence / change of the system parameter and / or the environmental parameter. In certain embodiments, a prediction or forecast of the system parameter and / or the environmental parameter may be determined based on the trend of the system parameter and / or the environmental parameter. Preferably, the prediction or forecast may be further based on current or actual indicators of the system parameter and / or current or actual indicators of the environmental parameter.

[0013] A trend threshold may be a threshold related to such a trend. A trend threshold may, for example, indicate a maximum and / or minimum value of such a trend.

[0014] In one example, determining whether the predetermined condition is met includes determining an indication of expected energy production during operation of the wind turbine in the energy harvesting mode when the transition is made.

[0015] In one example, the wind speed thresholds of the predefined conditions may include a minimum cut-in wind speed threshold that is equal to or greater than the wind speed value at which the wind turbine is operable to generate power, and / or a maximum cut-in wind speed threshold that is equal to or less than the wind speed value at which the wind turbine is operable to generate power. These thresholds can thus determine whether the current conditions are within the operating range of the wind turbine based on the acquired environmental data, thereby increasing the chance of a successful start-up of the wind turbine, and in particular the chance of generating a sufficient amount of power after the start-up of the wind turbine. The minimum cut-in wind speed threshold (also abbreviated as minimum threshold) may be smaller than the maximum cut-in wind speed threshold (also abbreviated as maximum threshold in this specification). The maximum and minimum thresholds define the operating wind speed range of the wind turbine (relative to the cut-in wind speed), and in particular the wind speed range of each condition.

[0016] In one example, acquiring environmental data (particularly in the form of wind data) can include acquiring wind speed data and time filtering the wind speed data. Determining whether the predetermined condition is met can include comparing the time filtered wind speed data with a wind speed threshold (e.g. a maximum threshold and / or a minimum threshold) and / or a wind speed range. The predetermined condition can be met if the time filtered wind speed is above a minimum threshold and below a maximum threshold or within a wind speed range, but additional conditions can also be applied, such as those described below. Such conditions can be specifically referred to as "wind speed conditions". Using the respective time filtered data can have the advantage that it can be more reliable to determine that sufficient power generation has been achieved by start-up. The time filtering can be performed, for example, by averaging. For example, a moving average with a predefined window length, for example between 1 s and 10000 s, preferably between 100 s and 5000 s, for example between 100 s and 1000 s, can be applied to the wind speed data. The wind speed data can be acquired by measuring the data, and the wind turbine can have a respective wind sensor. The wind speed data may also be obtained by receiving data from a data source, such as an external data source providing respective wind speed data, or from a local controller, such as a wind farm controller or a wind turbine controller of another wind turbine. Furthermore, such time filtering may prevent the wind turbine from responding to sudden changes in wind speed that may cause the wind turbine to start up in an unreliable manner, i.e. when a short gust of wind occurs or when the wind speed temporarily falls below a maximum threshold during strong wind conditions.

[0017] According to some examples, the predefined condition may include a wind speed trend threshold. Determining whether the predefined condition is met may include comparing a wind speed trend derived from the acquired wind data to the wind speed trend threshold. The trend may in particular be in the direction in which the wind speed is occurring, i.e. whether the wind speed is increasing or decreasing with respect to time. Taking such a trend into account may further increase the chances of the wind turbine generating a sufficient amount of energy in the harvesting mode. Deriving the wind speed trend may include, for example, comparing the wind speed data time-filtered with a first time constant and the wind speed data time-filtered with a second time constant, for example by subtracting the current wind speed filtered with a moving average with a longer time window from the current wind speed filtered with a moving average with a shorter window. The moving average may use, for example, two different window lengths, for example a first window length of 1 s to 500 s and a second window length of 500 s to 1000 s. A wind speed trend can also be derived by comparing an average wind speed obtained from wind speed data at a first time point (e.g. by subtracting wind speeds averaged for two different time points) with an average wind speed obtained from wind speed data at a second time point different from the first time point. When observing two different time points, they may have a time difference of e.g. 100s-5000s, e.g. 100s-1000s, e.g. 500s.

[0018] The condition for using the wind speed trend threshold can be called the wind speed trend condition. The wind speed trend condition is fulfilled, for example, when the minimum wind speed threshold is reached from a weaker wind speed and the wind speed trend shows an upward trend, i.e., the derived trend is higher than the wind speed trend threshold (e.g., 0 m / s). It can also be fulfilled when the maximum wind speed threshold is reached from a stronger wind condition and the wind speed trend shows a downward wind speed, i.e., the derived wind speed trend is lower than the wind speed trend threshold (e.g., 0 m / s). As mentioned above, the maximum or minimum threshold is related to the cut-in threshold. It is to be noted that the threshold of 0 m / s is merely an example of a wind speed trend threshold, and it is clear that this threshold can be set when a stronger trend is required, for example, above 2 m / s, above 3 m / s, above 4 m / s or more for an increasing wind speed, and for example, −1 m / s, −2 m / s, −3 m / s or more for a decreasing wind speed. The wind speed trend thresholds can be different for light and strong wind conditions, both of which may require different trends, and such different trend thresholds can be used in predefined conditions.

[0019] In one example, the predetermined condition includes a wind speed condition including a wind speed threshold and / or a wind speed range, and a wind speed trend condition further including a wind speed trend threshold. The predetermined condition may be met if both the wind speed condition and the wind speed trend condition are met (wind speed and wind speed trend condition combined). Thus, by requiring both of these conditions to be met, the chance of the energy storage system being depleted may be further reduced and the chance of a sufficient amount of energy being generated in the energy harvesting mode may be increased.

[0020] If the (time-filtered) wind speed is sufficiently inside the operating range of the wind turbine, the predetermined condition can be determined to be fulfilled. In one example, the predetermined condition can include a first wind speed condition, for example including a wind speed threshold (i.e. a first minimum threshold and a first maximum threshold) and / or a wind speed range. The predetermined condition can further include a second wind speed condition (e.g. referred to as a "sufficient wind speed condition") including a second wind speed threshold and / or a second wind speed range. The second threshold or range can in particular be stricter than the first threshold or range. For example, the second wind speed threshold can include a second minimum cut-in wind speed threshold that is greater than the first minimum threshold, can include a second maximum cut-in wind speed threshold that is less than the first maximum cut-in wind speed threshold, and / or the second wind speed range can be narrower and can be located within the first wind speed range that is referred to. If the second wind speed condition is fulfilled, the predetermined condition can be fulfilled. Such second wind speed condition thus likely allows the wind turbine to start up to generate the desired amount of electrical energy without needing to check for additional conditions if the wind speed is sufficiently inside the operating range. Since the second wind speed condition is more severe, the first wind speed condition is also met. In particular, the second wind speed condition may be met if the (time-filtered) wind speed represented by the acquired wind data is above or below a respective second wind speed threshold or within a second wind speed range.

[0021] In one example, the wind speed threshold and / or wind speed range can be variable and determined based on the amount of energy stored in the energy storage system, thus ensuring that in cases where there is little energy remaining in the storage system, the wind turbine is only transitioned into energy harvesting mode if there is a high enough chance that a sufficient amount of electrical energy will be generated.

[0022] For example, if a smaller amount of energy is stored, the wind speed threshold can be set to a stricter value and / or the wind speed range can be set to a narrower range. If a larger amount of energy is stored, the wind speed threshold can be set to a less strict value and / or the wind speed range can be set to a wider range. A stricter value may mean, for example, that the minimum threshold is set to a higher value (i.e., a higher wind speed is required before transitioning the wind turbine's operating mode) and / or that the maximum threshold is set to a lower value (transition only occurs at lower wind speeds). Thus, the thus adapted minimum and maximum thresholds may correspond to a narrower range. The time-filtered wind speed data may be compared to such adapted thresholds / ranges to determine whether the wind speed condition is met.

[0023] The wind speed threshold and / or wind speed range may, for example, be a function of the amount of energy stored in the energy storage system, and thus, as the amount of stored energy changes, the threshold or range may be adapted according to the function.

[0024] The function may be, for example, a linear function that depends linearly on the amount of stored energy. For example, the thresholds or range boundaries may vary linearly between a minimum and a maximum value for each threshold or boundary depending on the amount of stored energy. As an example, the minimum cut-in wind speed threshold may vary linearly from a lower predefined value for a larger amount of stored energy, e.g. 3m / s-4m / s, to a higher predefined value for a smaller amount of stored energy, e.g. 5m / s-7m / s. However, for the maximum cut-in wind speed threshold, a corresponding linear change may occur in the opposite direction. Thus, if there is a high level of available stored energy, if a start attempt fails (e.g. the wind speed drops below the minimum cut-out threshold again), there is still a sufficient amount of energy remaining and a start can be attempted at the earliest possible time. If there is a low level of available stored energy, start-up, i.e. a transition to harvesting mode, can only be attempted if there is a good chance of a successful start, i.e. if there is a certainty that a sufficient amount of energy will be generated. The function determining the dependency of each threshold or range on the amount of stored energy may be based on the amount of energy consumed upon transition to harvesting mode for each wind turbine and may also take into account additional safety margins.

[0025] In one example, obtaining weather data can include obtaining a forecast of wind conditions for a future period, e.g., by forecasting wind conditions, modeling future wind conditions, obtaining a forecast of wind conditions from an external data source, etc. For example, wind speed, temperature, air pressure and / or other environmental parameters can be measured and used to model, predict or forecast individual wind conditions. This can be done locally at the wind turbine, e.g., by the respective wind turbine controller, or at the wind farm level (wind farm controller), or at an external processing facility. Wind conditions can include wind speed and possibly wind direction.

[0026] Determining whether the predetermined condition is satisfied can include, for example, comparing the predicted wind conditions with a wind speed threshold and / or a wind speed range. Preferably, the predetermined condition is satisfied if, at a future time, the predicted wind conditions satisfy the wind speed threshold (above a minimum threshold or below a maximum threshold) and / or are within a wind speed range (which can be referred to as a "predicted wind speed condition"). Thus, a transition of the wind turbine can be prepared in time, for example by supplying power to the respective auxiliary power consumer before the respective wind speed is reached. For example, transitioning the operation of the wind turbine to an energy harvesting mode can include performing this transition before or at a future time. The transition can be initiated, for example, at a future time minus the time required for a transition procedure of the wind turbine to the energy harvesting mode.

[0027] Furthermore, the prediction or modeling can take into account the wind direction, time of day, date, solar irradiance, precipitation level and any historical trends of the disclosed parameters, for example of any sensors available for measuring the respective parameters. Furthermore, it can be based on weather forecasts obtained from external data sources. The prediction of the wind conditions can be based, for example, on measured wind speeds, obtained meteorological information, information obtained from external services, for example from a weather service, etc., and in particular can be model-based.

[0028] In one example, obtaining weather data can include predicting ice conditions, each of which can be a condition in which icing of the rotor blades may occur, and predicting ice conditions can be using any of the prediction methods described above and / or using dedicated sensors and / or load monitoring methods adapted to detect the presence or absence of ice on the rotor blades.

[0029] Determining whether the acquired environmental data satisfies the predetermined condition may include adjusting a wind speed threshold and / or a wind speed range when the presence or absence of ice conditions is detected or predicted. Additionally or alternatively, determining whether the acquired environmental data satisfies the predetermined condition when ice conditions are detected or predicted may include determining that the condition is not met if the respective ice formation is detected or predicted, i.e., determining that the wind turbine operation is not transitioned to the energy harvesting mode.

[0030] According to the above implementation, if the forecast predicts a return of the wind speed to the operating range in the future period, the wake-up of the individual wind turbines can be scheduled based on the time required to reach generation after being started (e.g., 5 minutes) and the expected arrival time of the wind conditions in the operating range. Thus, the wind turbines can be ready to start up without delay as the wind conditions arrive. For example, at the wind farm level, the individual wind turbines can be scheduled for start-up at different times depending on when the respective wind conditions reach the respective wind turbines.

[0031] In one example, the acquired environmental data can be local to the location of the wind turbine or the location of the wind turbine group. The transition can be performed individually for the wind turbine or the wind turbine group based on the local environmental data for each wind turbine or each wind turbine group. The wind turbine group can comprise, for example, two, three, four or more wind turbines, which can be arranged adjacent to each other. In particular, the wind turbines of a group can experience similar wind conditions.

[0032] The method may include, for example, first transitioning an operation mode of the wind turbines of the wind farm to an energy harvesting mode for those wind turbines located closest to an upcoming change in wind conditions predicted to meet a predetermined criterion, and subsequently transitioning operation of further wind turbines away from the location where the upcoming change in wind conditions first occurred. The time difference between the wake-ups may correspond to the time required for the wind speed change to travel through the wind farm from the first location to the second location.

[0033] In a further example, determining whether the predetermined condition is met can include determining a continuous period during which the predicted wind conditions are (substantially) within a wind speed range. Determining whether the predetermined condition is met can further include estimating an amount of energy predicted to be generated by the wind turbine within the continuous period and comparing the estimated amount of energy with a predetermined energy threshold. The predetermined energy threshold can be greater than an amount of energy required to transition the operation of the wind turbine from the first operation mode to the energy harvesting mode. The condition can be met if the estimated amount of energy meets or exceeds the predetermined energy threshold (which can be referred to as a "predicted energy generation condition"). Thus, by ensuring that the predicted energy generation is greater than the amount of energy consumed during start-up, it can be ensured that the energy storage system is not depleted. The predicted continuous period can, among other things, allow recovery of the energy used for start-up. The energy threshold may further comprise an additional energy margin, for example between 20% and 100%, such as between 40% and 60%, of the amount of energy required to transition the wind turbine operation to harvesting mode. It will also be apparent that the predicted wind conditions may be time filtered or smoothed so that small and short-term outliers in the forecast data do not cause interruptions in the predicted continuous period. If the period is too short to generate a sufficient amount of energy, the condition will not be met and no transition will be made.

[0034] As a further example, the predetermined condition may be determined to be met if the continuous period exceeds a predetermined duration threshold (which may be referred to as a "predicted harvesting period condition"). Such a duration threshold may similarly ensure that a sufficient amount of energy is generated after starting up the wind turbine, but is less accurate as it depends on the predicted wind speed but does not take into account the amount of energy actually generated.

[0035] It is clear that the predetermined condition may include one or a combination of the various conditions disclosed herein, for example, the predetermined condition may be satisfied if one of the general conditions herein is satisfied. The predetermined condition may include, for example, at least one of a combined wind speed condition or wind speed trend condition, a sufficient wind speed condition, a predicted wind speed condition, a predicted energy generation condition, and a predicted harvesting period condition, and preferably at least two, three, or more of these conditions. In some examples, the predetermined condition may include at least a combination of a wind speed condition or wind speed trend condition and a sufficient wind speed condition. In other examples, the predetermined condition may include at least a predicted energy generation condition and optionally a predicted wind speed condition and / or a predicted harvesting period condition. Thus, if one or more of these conditions included in the predetermined condition are satisfied, the wind turbine may be transitioned to an energy harvesting mode.

[0036] Determining whether the predetermined condition is met can be performed external to the wind turbine, for example by a wind farm controller or by a computing system external to the wind farm, but can also be performed by the wind turbine controller. In the former case, the transition of the operation of the wind turbine can be performed by communicating a respective control command to the wind turbine.

[0037] In one example, if the wind turbine is operating in an energy harvesting mode and the second predetermined condition is satisfied, the method may include transitioning the operation of the wind turbine to the first operating mode. The second predetermined condition may be similar to the first predetermined condition described above, but may also use, for example, a cut-out threshold and / or a cut-out wind speed range, such as a minimum cut-out wind speed below which the second criterion is satisfied or a maximum cut-out wind speed above which the second criterion is satisfied. The cut-out wind speed threshold and / or the cut-out wind speed range of the second predetermined condition may be different from the first predetermined condition described above, in particular a hysteresis is obtained so that the number of transitions between the first operating mode and the energy harvesting mode is reduced. In other words, the minimum cut-out wind speed threshold may be smaller than the minimum cut-in wind speed threshold, the maximum cut-out wind speed threshold may be larger than the maximum cut-in wind speed threshold, and / or the cut-out wind speed range may be wider than the first wind speed range mentioned.

[0038] In one example, obtaining weather data may include obtaining a forecast of wind conditions for a future period of time, and determining whether the second predetermined condition is met may include comparing the forecasted wind conditions with a cut-out wind speed range and determining a second (continuous) period during which the forecasted wind conditions are outside the cut-out wind speed range. If the wind turbine is operating in an energy harvesting mode and the second period of time is shorter than the predetermined maintenance period, operation of the wind turbine is maintained in the energy harvesting mode for the second period of time. Thus, if the forecast predicts a short duration of wind speed outside the operating range, shutting down the wind turbine, i.e., introducing the first operating mode, may be prevented if the period is short enough. In particular, the predetermined maintenance period may be determined based on the amount of energy consumed during start-up that would be required if the wind turbine were to transition to the first operating mode. In particular, the period can be selected such that energy is saved by transitioning to a first operating mode in which less energy is consumed, and that if operation is maintained in the harvesting mode during a second period in which low wind speeds prevail, the energy transferred back to the harvesting mode is less than the energy consumed. By such measures, further depletion of the energy storage system can thus be avoided.

[0039] Obviously, such operations can also be performed when the wind speed is below or above the operating range of the wind turbine. If the wind speed is above the operating range and the wind turbine continues to operate in energy harvesting mode, conventional measures can be taken to protect the wind turbine from rotor blade pitch-out etc. at high wind speeds, but the first group of auxiliary power consumers remains powered and active.

[0040] The method may further comprise increasing the amount of energy stored in the energy storage system when operating in the energy harvesting mode, As described above, in the energy harvesting mode, the first group of auxiliary power consumers are powered on and operate using the generated electrical energy (autonomous operation), for example to align a wind turbine with respect to the wind direction, control blade pitch, etc.

[0041] The first group of auxiliary power consumers may include components that are not critical to determining sufficient wind conditions for return to operation and / or components that provide command and control capabilities (which may be included in the second group). For example, the first group of auxiliary power consumers may include one or more actuators or drives configured to operate components of the wind turbine. The first group of auxiliary power consumers may include one or a combination of a wind turbine yaw system, a wind turbine pitch system, a wind turbine hoisting system, a wind turbine work lift, a wind turbine cooling system, and a wind turbine environmental management system (which may include, for example, a temperature control and a humidity control).

[0042] The second group of auxiliary power consumers may include one or more devices configured for communication and control of the wind turbine and for obtaining wind conditions. For example, the consumers may include wind sensors of the wind turbine, a wind turbine control device and / or a wind turbine communication device (which may for example provide for communication with the outside, e.g. receiving data such as environmental data and receiving control commands from an external site). Thus, in the first operating mode, the control and communication system and possibly the sensor system may be operated, which allows the wind turbine to determine the time for transition back to the energy harvesting mode with low energy consumption.

[0043] The first group of auxiliary power consumers may have a combined power requirement of more than 100 kW, e.g. between 100 kW and 1000 kW, or between 200 kW and 500 kW, e.g. between 250 kW and 400 kW. The second group of auxiliary power consumers may have a combined power requirement of less than 50 kW, preferably less than 10 kW, e.g. between 0.1 kW and 10 kW, or between 0.2 kW and 5 kW, e.g. less than 2 kW. Thus, significant power consumption savings are achievable when operating in the first operating mode (e.g. sleep mode).

[0044] The first group of auxiliary power consumers may have an operating voltage above 300V, in particular between 300V and 1000V. They can be powered from a three-phase supply. The second group of auxiliary power consumers may have an operating voltage below 300V, for example between 100V and 250V. They can be powered by a single-phase supply, as they do not need to drive particularly large motors. The above values ​​may be referred to as the nominal rated power and nominal rated voltage of the respective consumer.

[0045] The energy storage system may preferably be a rechargeable energy storage system. The system may include at least one of a battery energy storage system (BESS), a hydrogen storage system including a hydrogen storage device and a hydrogen conversion system configured to generate electrical energy from the stored hydrogen, a flywheel energy storage system, a capacitor (e.g., supercapacitor) energy storage system, or a thermal storage system including a heat storage device and a conversion system configured to generate electrical power from the stored thermal energy. Preferably, a BESS or a hydrogen storage system is provided. In some examples, the energy storage system may include a fossil fuel-driven generator in which energy is stored in the form of a generator (e.g., a diesel generator) driven by a fossil fuel, which is less preferred because the energy storage system is not rechargeable.

[0046] According to another aspect, a wind turbine control system is configured to, among other things, control the operation of the wind turbine into an energy harvesting mode in which the wind turbine operates to generate power from wind energy. An energy storage system associated with the wind turbine is configured to provide power to the auxiliary systems when the wind turbine is not generating or receiving sufficient power to power the auxiliary systems. The control system can be configured to perform a method according to any of the configurations and embodiments described herein.

[0047] According to another aspect, there is provided a wind turbine having such a control system and further an energy storage system, which may be located within the tower of the wind turbine, for example on a tower platform within the tower or adjacent to the tower.

[0048] According to another aspect, there is provided a computer program for controlling operation of a wind turbine, the computer program comprising control instructions, when executed by a processing unit of a control system for controlling operation of the wind turbine, for causing the processing unit to perform a method having any of the configurations described herein, the computer program being configured to provide power to an auxiliary system when the wind turbine is not generating or receiving sufficient power to provide power to the auxiliary system.

[0049] The method can be performed by a control system or a wind turbine having any of the configurations described herein. The method can further include any of the steps described herein with respect to the control system or the wind turbine. Similarly, the control system can be configured to perform any of the method embodiments and examples disclosed herein.

[0050] It is to be understood that the features mentioned above and described below can be used not only in the respective combinations shown, but also in other combinations, or alone, without departing from the scope of the invention. In particular, unless stated to the contrary, the features of the various aspects and embodiments of the invention can be combined with each other.

[0051] The above and other features and advantages of the present invention will become more apparent from the following detailed description taken in conjunction with the accompanying drawings, in which like reference numerals refer to like elements and in which: [Brief description of the drawings]

[0052] [Figure 1] 1 is a schematic diagram illustrating a wind turbine including a control system according to an embodiment. [Diagram 2] FIG. 2 is a schematic diagram illustrating transitions between different operational modes of a wind turbine according to one embodiment. [Diagram 3] FIG. 13 is a schematic diagram illustrating graphs when wind speed, wind speed trend and wind force trend conditions are met according to one embodiment. [Figure 4] FIG. 2 is a schematic diagram illustrating a graph of the dependency of a wind speed threshold on the amount of energy stored in an energy storage system of a wind turbine, according to one embodiment. [Diagram 5] 4 is a first portion of a flowchart illustrating a method for controlling a wind turbine according to an embodiment. [Figure 6] 6 is a second part of the flowchart of FIG. 5.

[0053] Detailed Description Hereinafter, embodiments and / or examples of the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the following description of each embodiment is provided for illustrative purposes only and should not be construed in a limiting sense. It should be noted that the drawings should be considered as schematic representations only, and that the elements in the drawings are not necessarily drawn to scale relative to each other. Rather, the representations of the various elements have been selected so that their functions and general purpose will be apparent to those skilled in the art. As used herein, the singular forms "a", "an", and "the" are intended to include the plural forms unless the context clearly dictates otherwise. Terms such as "comprising", "having", "including", and "containing" should be construed as open-ended terms (i.e., meaning "including, but not limited to") unless specifically stated otherwise.

[0054] In Fig. 1, a wind turbine 100 according to an embodiment is shown in a schematic manner, which may include a wind turbine power system 110 including a generator 111 and a power conditioning system 112. The power system 110 may have any known configuration and topology, such as a full converter topology or a doubly fed induction generator (DFIG) topology, in which a power conditioning device 112, in particular a power converter, may be connected to the rotor winding of the generator in order to condition the generated power. Furthermore, a wind turbine transformer 115 may be provided to convert the generated power to a desired voltage level before being fed to an external power supply network 200 or, alternatively, before being fed to one or more local consumers. In the embodiment of Fig. 1, the wind turbine 100 is connected to an external power supply network 200, for example a power grid, which in this case may be a grid capable of feeding the wind turbine 100 with power, in particular for operating the wind turbine 100 during periods of low winds or for maintenance work or other situations in which the wind turbine itself does not generate power. By using the respective switches, in particular the switchgear 201, the wind turbine 100 can be disconnected from the external power grid 200, for example in response to the occurrence of a grid fault or other event causing the grid connection to be unavailable. In other embodiments, there may be no connection to the external power grid 200 at all (i.e. the external power grid 200 is optional). Such a wind turbine may for example supply power to one or more local consumers, but may not supply power to the wind turbine 100 via its own connection to the local consumers. Such an operation may also be referred to as island operation.The solution provides for a transition of the wind turbine to an autonomous operation (energy harvesting mode) for a wind turbine that is normally connected to the grid but is disconnected from the grid for a given reason (e.g. by opening the switch 201), or for a wind turbine that is not normally connected to the grid and operates to supply power to power consumers (local power consumers) inside or in its vicinity, or for a wind turbine for which the power grid cannot provide sufficient power to operate the auxiliary systems of the wind turbine. Such an autonomous operation avoids damage or possible damage associated with a long shutdown of the wind turbine and can achieve avoidance of exposure of the wind turbine components to external humidity and temperature, which is particularly important for offshore wind turbines.

[0055] In the absence of a grid connection or when the grid connection is disconnected, the wind turbine 100 can operate in an energy harvesting mode in which the power system 110 supplies power to the auxiliary system 10, including the auxiliary power grid 40 and the auxiliary power consumers 12-14; 22-25. It is noted that a challenge in operating a wind turbine in a grid disconnected condition is that power from the wind is not always available to keep the auxiliary system 10 powered, for example when environmental conditions are outside the operating range of the wind turbine or when a fault occurs in any of the wind turbine systems required for generating electricity. Environmental conditions that may affect the operation of the wind turbine include excessively high or low wind speeds, or excessively high or low ambient temperatures. Faults may include a failure of the wind turbine's pitch system, yaw system, monitoring system, control system, or power conversion system.

[0056] The auxiliary system 10 may include an energy storage system 50 configured to provide electrical energy for operating (at least a part of) the auxiliary system 10 when no or insufficient power is available from the external grid 200 and when no power is available from the power system 110. The energy storage system 50 may provide power to the auxiliary power grid 40, which distributes the power to the auxiliary power consumers. For example, a switch (not shown), e.g., a three-way switch, may be used to control the power source for the auxiliary power grid 40. Such a switch may be switchable to transfer the power supply between the wind turbine power system 110 and the energy storage system 50, and may also be switchable to disconnect the two power sources from the auxiliary system depending on the operating mode of the wind turbine.

[0057] The auxiliary power consumers can be divided into at least a first group 11 and a second group 21. The power supply to at least the first group 11, preferably to the two groups 11, 21, can be controlled separately. The consumers of the first group 11 are generally not important for determining sufficient wind conditions to return the wind turbine to operation and / or for determining command and control capabilities. The first group 11 can include, for example, relatively large power consumers, for example having a relatively high power rating, and can include in particular one or more devices. By way of example, the yaw system 12, the pitch system 13 and the cooling system 14 can be mentioned. Other systems included in the first group 11 can include a crane hoist, a work lift, a high power outlet and an environmental system, including an AC system for controlling temperature and humidity in the wind turbine. The combined power rating of the auxiliary power consumers of the first group 11 can be, for example, in the range of 250 kW to 400 kW. Typically, each consumer can receive a three-phase AC voltage supply in the voltage range of 300 V to 1000 V, e.g. at 400 V or 690 V. These consumers thus consume large amounts of power, which is needed to keep the wind turbine 100 in operation, e.g. to track the wind direction using the yaw drive 12, to control the rotational speed of the rotor using the pitch system 13, etc.

[0058] The auxiliary power consumers of the second group 21 may include consumers that are important for determining the presence of sufficient wind conditions to return the wind turbine 100 to operation and / or for command formation and control capabilities. The second group 21 may include low power consumers, i.e. having a relatively low nominal power rating, such as the wind turbine controller 25 and the communication interface 23. The system may further include a wind turbine monitoring system 22, which may include a wind sensor, but the controller 25 may also obtain the respective wind information from a sensor external to the wind turbine 100 via the communication interface 23. The second group 21 may include auxiliary power consumers that receive a single-phase power supply, in particular with a voltage in the range of 100V to 300V, for example with a voltage of 110V or 230V. The consumers of the second group 21 may have a composite nominal power rating of 0.1 kW to 10 kW, for example 0.3 kW to 5 kW, preferably with a composite nominal power rating of less than 2 kW or less than 1 kW. The auxiliary power consumers of the second group 21 are able to control the operation of the wind turbine 100 and communicate with the outside world, for example to receive control commands (e.g. from a wind farm controller) and / or to receive environmental data and / or to provide monitoring data, even when none of the main mechanical systems of the wind turbine can actually be operated.

[0059] The wind turbine controller 25 may form part of the control system 20 and may include a processing unit 26 which may include a microprocessor, an application specific integrated circuit, a digital signal processor, etc. The wind turbine controller 25 may further include a memory 27 coupled to the processing unit 26 and storing control instructions which, when executed by the processing unit 26, cause the processing unit 26 to perform any of the methods described herein. The memory 27 may include volatile and non-volatile memories, in particular hard disk drives, flash memories, RAMs, ROMs, EEPROMs, etc. The wind turbine controller 25 may further include other components not explicitly shown, such as respective input / output interfaces to the components to be controlled, shown in dashed lines in FIG. 1, a user interface including a display and input means, as well as other components common to computer systems. The communication interface 23 and / or the monitoring unit 22 may also form part of the control system 20.

[0060] In the embodiment of Figure 1, a switch 42 in the form of a circuit breaker can be connected between the energy storage system 50 and the first group 11 such that the power supply to the consumers of the first group 11 is controlled independently from the consumers of the second group 21. Thus, the power supply from the energy storage system 50 to the auxiliary power consumers of the first group 11 can be stopped (discontinued) to reduce energy consumption. As will be explained in more detail below, the controller 25 can operate the wind turbine 100 in various operating modes that can selectively activate or cut off the power supply to the consumers of the first group 11.

[0061] Optionally, a separate second storage device in the form of an uninterruptible power supply (UPS) 45 may be connected in-line on the power supply path from the energy storage system 50 to the consumers of the second group 21. Such a UPS may ensure that short-term power interruptions, such as a transition between power sources (e.g. via a respective switch) or a failure in any of the available power systems, do not lead to an immediate loss of control, monitoring and / or communication capabilities of the wind turbine.

[0062] The energy storage system 50 can be realized in several different forms. Realizations can include, among others, a battery energy storage system (BESS) and a hydrogen storage system as shown in FIG. 1. However, other realizations or embodiments are also conceivable, such as a flywheel storage system, a (super)capacitor storage system, a thermal storage system, etc., or a diesel generator. The system 50 is preferably rechargeable. The description provided herein is applicable to any of these possible realizations or embodiments. When realized as a hydrogen storage system, the wind turbine 100 can include a hydrogen production system that uses power provided by the power system 110 to produce hydrogen gas during operation of the wind turbine 100. Such a hydrogen production system can receive water from a water source and produce hydrogen gas by electrolysis. The produced hydrogen gas can then be stored in a hydrogen reservoir within the wind turbine and / or in an external hydrogen collection tank (not shown). The energy storage system 50 can also include a fuel cell that produces electrical energy from the hydrogen stored in the reservoir and supplies it to the auxiliary grid 40.

[0063] The control system 20 of the wind turbine 100 may include a wind turbine controller 25 capable of controlling and / or communicating with several components of the wind turbine, including the communication interface 23, the monitoring unit 22, the energy storage system 50, the power system 110, the switches 42, the UPS 45 and the auxiliary system 10, in particular the consumers of the first group 11 and the consumers of the second group 21. The control system 20 may furthermore control a switch 201 for isolating the wind turbine from the external grid 200, the wind turbine transformer 115 and other components of the wind turbine 100, although the respective control and communication connections are not shown in FIG.

[0064] It will be apparent that topologies other than that shown in Figure 1 can be used with the solutions disclosed herein, for example, energy storage system 50 can be connected as an online UPS and include a bypass (avoiding the need for UPS 45), or can be connected to feed UPS 45 (as switch 42 is not required when only second group 21 is powered), or other configurations are contemplated and are within the scope of the present disclosure.

[0065] The control system 20 can operate the wind turbine 100 in an energy harvesting mode, in which the power system 110 provides all or a large part (more than 50%, more than 70% or more than 90%) of the power required to operate the auxiliary system 10, i.e. generates power from wind energy. In said operating mode, both groups 11 and 21 and preferably all auxiliary power consumers are supplied with power. The energy harvesting mode may in particular be an autonomous operating mode.

[0066] If conditions for operating the wind turbine 100 in such a harvesting mode (e.g. wind speed is outside the operating range) are not given, the control system 20 can operate the wind turbine 100 in a first operating mode, which can be or include a sleep mode. In said first operating mode, the power supply to the first group 11 can be stopped and the second group 21 can receive all or a large part (more than 50%, more than 70% or more than 90%) of the power from the energy storage system 50. In particular, the power system 110 may not supply or receive power from the power grid 200 (if such a power grid even exists). Thus, the above-mentioned operating mode allows the monitoring and control functions of the wind turbine 100 to be kept active, while the energy consumption can be kept low since the main auxiliary loads of the group 11 are not supplied with power.

[0067] The control system 20 can operate the wind turbine 100 in different operating modes, as shown in FIG. 2. When the wind turbine 100 is connected to a grid 200 (if present), the wind turbine can operate in a grid mode 75, which may include a conventional operating state of a wind turbine connected to a grid. In the grid mode 75, the energy storage system 50 can be charged to or maintained in a fully charged state using power from the grid or generated power. The grid mode 75 is optional and cannot be used in wind turbines where there is no grid connection. The monitoring unit 22 can monitor the state of the grid and, if it is detected that the grid is no longer available or has been disconnected, the operation of the wind turbine can be transitioned to a grid-disconnected operation, as described below. In the mode 75, the wind turbine can operate in an area 83 where the auxiliary system 10 is supplied with power from an external power supply network.

[0068] The wind turbine 100 may further be operable in the energy harvesting mode 74 described above, in which the generator 111 converts rotational mechanical power from the wind turbine rotor into electrical power supplied to the auxiliary systems 10, including the energy storage system 50, and possibly to local loads (autonomous operating area 82).

[0069] In the operating region 81, the auxiliary system 10 or at least its components can be supplied with power from the energy storage system 50. In the operating region 81, the power system 110 does not generate power and the wind turbine may not receive power from the grid 200 (if present) or at least may not have a sufficient amount of power available to power the auxiliary system 10 (e.g. less than 50%, less than 20% or less than 10% of the required power). The operating modes in said region 81 may include a first operating mode 72 (sleep mode) and may further include a so-called local power mode 71 (second operating mode). In the local power mode, the two groups 11, 21 of auxiliary power consumers, preferably all of them, may be supplied with power from the energy storage system 50. Furthermore, the wind turbine may operate in a sleep mode 73 (third operating mode), in which no power is supplied to the auxiliary system 10 and the wind turbine may be substantially completely shut down.

[0070] The arrows in Fig. 2 illustrate possible transitions between these operating modes. Even without connection to an external power grid and before starting energy harvesting, the wind turbine can operate in a local power mode 71. This mode may be provided to start the operation of the wind turbine or to keep the wind turbine ready for energy generation. For example, wind tracking can be performed (operation of the yaw system) to establish the alignment of the wind turbine rotor to the wind, system cooling (circulation of cooling fluid), heating and dehumidification can be performed as well. Furthermore, the power conditioning device 112 can be prepared for operation (for example to charge the DC link capacitors) and for example the hydraulic system of the pitch system can be put under a certain pressure. When the start-up of the wind turbine is to be started, the pitch system 13 of the wind turbine can be operated to allow the rotor speed to accelerate. When the wind turbine rotor reaches the cut-in rotor speed, the operation can be transferred to the energy harvesting mode 74. Thus, in case of a transition from the sleep mode 72 to the energy harvesting mode 74, the transition may be made via the local power mode 71, i.e. the transition may involve operating the wind turbine in the second operating mode 71. It is clear that the transition involves a significant consumption of energy from the storage system 50, due to the need to operate a large number of loads of the group 21.

[0071] A transition to hibernate mode 73 may occur in response to the amount of energy in storage system 50 reaching a minimum level to ensure that the energy storage system is not further depleted and sufficient energy is available for manual start-up. A transition from grid-connected operating mode 75 to standalone operating mode 74, which is not connected to the grid, may similarly occur via local power mode 71.

[0072] To reduce the energy consumption of the storage system 50 and thus the risk of depleting the available energy, the transition from the sleep mode 72 to the energy harvesting mode 74 can occur when the control system 20 determines that a predetermined condition is met. Thus, a failed start-up attempt can be avoided. In particular, the predetermined condition can be selected to increase the likelihood that more energy is recovered in the harvesting mode than is required for the start-up attempt (i.e., for the transition). The wake-up sequence, i.e., the transition to mode 74, can consume a range of 15 kWh to 20 kWh of stored energy depending on the size and type of turbine.

[0073] The wind turbine may be prevented from operating in the energy harvesting mode 74 due to a command from a user to stop power generation, the occurrence of a fault, a wind speed that is too low to generate power, a wind speed that is too high to generate power, and / or other environmental conditions that prevent such operation. If any of these occur, the control system may transition the operation of the wind turbine to a sleep mode 72, thereby ensuring that a low level of power is consumed by the energy storage system 50 while maintaining the power supply to the systems required to resume operation. If the wind turbine is stopped during the sleep mode due to a fault or a user command, the fault must be cleared and any user command must be released to allow the return to operation. If the wind turbine is stopped due to a wind speed (too high or too low), the monitoring unit 22 may continue to monitor the wind conditions or may obtain the wind conditions via the communication interface 23, while the wind turbine controller 25 may decide when to attempt to restart the wind turbine in the sleep mode.

[0074] Time filtering of the measured or received wind speed data can be used to make the turbine unresponsive to sudden changes in wind speed that may be unreliable and to start up (if shut down due to low wind) or to detach (if shut down due to high wind) from short gusts of wind. The time filtered wind speed may be an average, in particular a moving average, for example a moving window average with a window length of 1 s to 10000 s, preferably 50 s to 1000 s, for example 100 s to 200 s.

[0075] The filtered wind speed v filter is the minimum cut-in wind speed threshold thresh min_cut-in (min threshold for low wind speed shutdowns) above which the wind turbine can be restarted. Similarly, if the turbine is shut down due to high wind speed, the maximum cut-in wind speed threshold thresh max_cut-in (abbreviated as maximum threshold) can be used. v filter >thresh min_cut-in (low wind speed) or v filter <thresh max_cut-in (due to high wind speed) It can be defined that the wind speed condition is satisfied when

[0076] Thus, a wind speed range for the cut-in wind speed may be defined by these thresholds, and the wind speed condition shall be met if the filtered wind speed falls within the cut-in wind speed range here.

[0077] Furthermore, to avoid short-term exceedances of the respective thresholds resulting in start-up attempts, the historical wind speed trends v trend Historical trend wind speed can be taken into account. Historical trend wind speed can be obtained from a combination of time-filtered wind speeds. For example, historical trend wind speed can be calculated by the difference between the current values ​​of time-filtered wind speeds, each filtered with a different window length: v trend=v filter(length1) -v filter(length2) It can be determined as: Here, the filter lengths can be, for example, length1=120s and length2=600s. It is clear that instead of using different filter lengths, any other known method for determining trends can be used, such as the difference between two average values ​​of the same length at two different times or curve fitting. In this way, a wind speed trend condition can be defined, which can be expressed as: v trend >thresh trend_min (low wind speed) or v trend <thresh trend_max (due to high wind speed) It may be considered that the requirement is met when

[0078] The trend threshold can be set to any wind speed in the range 0 m / s to 99 m / s or 0 m / s to -99 m / s, respectively.

[0079] For example, the limits for the minimum and maximum wind speed thresholds are: thresh min_cut-in =3.5m / s thresh max_cut-in =22m / s and the wind speed trend threshold can be set to thresh trend_min =0m / s thresh trend_max =0m / s can be set to.

[0080] A trend threshold of 0 m / s means that when entering the operating range from a low wind speed, the wind speed trend must be positive, and when entering the operating range from a high wind speed, the wind speed trend must be negative (i.e., the wind speed decreases in history). A higher or lower value for the trend threshold, e.g. thresh trend_min=1m / s, 2m / s or 3m / s and thresh trend_max It is clear that the trend conditions can be set more stringently by selecting =-1m / s, -2m / s or -3m / s.

[0081] If both the wind speed condition and the wind speed trend condition are met, it may be determined that a predetermined condition for transitioning to the energy harvesting mode is met.

[0082] Furthermore, a second wind speed condition can be defined that includes a second threshold value having a sufficient safety margin relative to the threshold value of the first wind speed condition described above, i.e., the respective range defined by the second threshold value is narrower and is within the range defined by the first threshold value described above, if the time-filtered wind speed is sufficiently inside the operating range. If the second wind speed condition (which can be referred to as a "sufficient wind speed criterion") is met, the historical wind speed trend does not need to be taken into account. The second wind speed condition can be used, for example, after a shutdown period (operation in sleep mode) due to a user command or a turbine failure scenario. The second wind speed condition can be: v fi1ter >thresh_suff min_cut-in (low wind speed) or v fi1ter <thresh_suff max_cut-in (due to high wind speed) can be said to be satisfied if where thresh_suff min_cut-in is the second minimum cut-in wind speed threshold (sufficient wind conditions), thresh_suff max_cut-in is the second maximum cut-in wind speed threshold (sufficient wind conditions). Each threshold is stricter (i.e., closer to the inside of the operating range) than the first threshold mentioned above, e.g., thresh_suff min_cut-in =6m / s thresh_suff max_cut-in =20m / s It can be set as follows.

[0083] Thus, if the time-filtered wind speed rises above the second minimum threshold or falls below the second maximum threshold, the second wind speed condition, and thus the predetermined condition, may be satisfied, thereby causing the control system 20 to transition the wind turbine into the energy harvesting mode 74.

[0084] The top graph 300 of FIG. 3 shows an example wind speed filtered with a window length of 120 s (curve 301) and an example wind speed filtered with a window length of 600 s (curve 302). Additionally, a second wind speed threshold (thresh_suff min_cut-in ) is shown (curve 303). A second graph 304 shows the wind speed trend values ​​(curve 305) determined as shown above from the curves of the first graph 300. Additionally, a wind speed trend threshold 306 (threshold trend_min ) are also shown.

[0085] A third graph 308 shows a Boolean value for whether a combination of a first wind speed condition and a wind speed trend condition is met based on the data in graphs 300 and 304 (minimum wind speed threshold of 3.5 m / s). Here, it can be seen from graph 304 that the trend condition is met (Boolean value is 1) for only a part of the curve, while the minimum threshold is always met. It is clear that as soon as the Boolean value is 1, the wind turbine transitions to the energy harvesting mode and then continues to operate in that mode until the wind speed falls below the minimum cutout threshold (or exceeds the maximum cutout threshold). In other words, the change in the Boolean value shown in graph 308 is not a transition of operation modes.

[0086] The energy consumed by the transition to the energy harvesting mode (wake-up attempt) may be an important factor that may be justified in order to be able to recover the energy consumed by the wake-up execution when the wind turbine starts to operate for power generation. When the level of energy stored in the storage system 50 is low, the wind conditions should be well inside the operating wind speed range to ensure the occurrence of a long operating period after wake-up. This can be taken into account for determining the wind speed threshold mentioned above by using the energy available in the energy storage system 50. Threshold thresh min_cut-in and thresh max_cut-in can for example be selected depending on, and in particular as a function of, the amount of energy stored in the storage system 50. An example of a function here is shown in FIG. 4, which shows a curve 401 for a wake-up situation in low wind, i.e. the minimum threshold. The x-axis shows the amount of available energy and the y-axis shows the value of the minimum threshold. The value of the minimum threshold can vary from 3.5 m / s when the available energy is maximum to 6 m / s when the available energy is minimum.

[0087] Thus, when the available energy is at a high level, a start-up can be attempted at the earliest possible time, since there is a sufficient amount of energy remaining if the start-up attempt fails. When the available energy is at a low level, a start-up is attempted only if a successful start is assured. Curve 401 can be defined based on the amount of energy consumed in a wake-up attempt for a given type of turbine, with a safety margin added. It will be appreciated that these are merely example values, and the values ​​can be selected depending on the desired operating characteristics and operating conditions.

[0088] Besides the above mentioned combined or trend wind speed condition and sufficient wind speed condition, the control system 20 can also use further conditions as part of the predefined conditions to shift the operation to the energy harvesting mode. For example, a weather forecast can be used and in particular the wind conditions can be predicted. Such a prediction can be based on local measurements made at the wind turbine using the unit 22 and / or on meteorological information obtained via the communication interface 23. The monitoring unit 22 can include sensors for monitoring the wind speed and direction as well as temperature and air pressure. Based on these signals, a weather forecast model can be used by the control system 20 to make a prediction and / or form a forecast of the future wind conditions. Such a model can be executed using the wind turbine controller 25 and / or using a wind farm controller (not shown) external to the wind turbine 100, which may be part of the control system 20. Other signals, such as time of day, date of the month, solar irradiance, precipitation levels and any available sensor data or external data historical trends can also be used as inputs to such a model.

[0089] The prediction or the obtained prediction data may also take into account the risk of icing on the rotor blades, which may reduce the reliability of the above mentioned conditions. Ice detection may be performed using the sensors of unit 22 or a load monitoring method may be performed by unit 22 to detect the presence or absence of ice. If icing on the rotor is detected, control system 20 may for example prevent wake-up from sleep mode 72 or modify the required wind speed for wake-up, i.e. set stricter values ​​for the respective wind speed thresholds or wind speed ranges (e.g. set a higher minimum threshold or a lower maximum threshold).

[0090] Alternatively or in combination with model-based predictions, weather information from available weather services can be obtained via the communication interface 23 and used to predict wind and / or icing conditions. This predicted information can be communicated from the wind farm controller to the wind turbine controller 25 or can be processed outside the wind turbine controller (e.g. by the wind farm controller) and only basic command signals (e.g. signals for transitioning operation modes) can be communicated to the wind turbine 100. If the weather forecast information is processed outside the wind turbine controller 25, e.g. by checking if the respective conditions are fulfilled, further benefits can be obtained, e.g. by coordinating the wake-up of the wind turbine from a sleep mode.

[0091] If the forecast predicts that the wind speed will return to the operating range at a given future time or for a given future period, it can be checked by comparing the predicted wind speed (which can be filtered or already smoothed with a respective time constant depending on the model used) with the respective wind speed threshold value, e.g. the minimum and / or maximum threshold value mentioned above. The forecast data further allows an estimation as to how long, e.g. for how many consecutive periods, the wind speed is expected to remain within the operating range, i.e. not to drop below the minimum cut-out wind speed or not to rise above the maximum cut-out wind speed. That is, wind speed trends may not be taken into account in the predicted wind speed data. The transition to the energy harvesting mode (wake-up) can be scheduled for the individual wind turbines based on the time required to start and reach generation (e.g. 5 minutes) and the expected time of arrival of the respective wind conditions that allow the transition. In this way, the wind turbines can be ready to start without delay when the wind conditions allow. Also, in large wind farms, the control system may command the wind turbines of the farm closest to the incoming wind conditions to wake up from sleep mode early, and then wake up subsequent wind turbines based on the predicted speed at which the wind speed change (i.e., the wind speed that meets the conditions) is expected to progress through the wind farm.

[0092] In addition to checking whether the predicted wind speed falls within the respective wind speed thresholds, the amount of expected energy production can also be taken into account. If the prediction predicts that the wind speed will return to the operating range for a short period at a given future time, the amount of energy consumed during start-up can be compared with the expected amount of energy the wind turbine will generate during that period when energy production is possible. If the expected energy production allows the recovery of the energy used for the operation transition (i.e. the energy to recharge the energy storage system at least to the previous level) plus a certain margin (e.g. at least 30%, 40% or 50% of the energy required for the transition), the wind turbine can be commanded by the control system 20 to perform a wake-up and transition, for example as described above. For the purposes here, the expected amount of generated energy can be compared with the respective energy thresholds, which may include the amount required for recovery and a margin, and the transition is performed if the expected amount is greater than the threshold. If the period is too short and the expected energy production is not sufficient to recover the energy consumed during start-up, no wake-up command is issued. Such an action can thus ensure that the energy storage system 50 is not depleted.

[0093] If the wind turbine is already operating in the energy harvesting mode 74 and the forecast predicts that wind speeds outside the operating range will occur for a certain period of time, and operation continues without transitioning to sleep mode 72 (i.e., operation continues in local power mode 71) for that period, the amount of energy consumed by the wind turbine can be estimated. This estimated amount of energy can be compared with the amount of energy required to operate the wind turbine in sleep mode for that period and transition operation to and from sleep mode. If it is estimated that the required energy is insufficient to transition to sleep mode, operation can continue without such transition to sleep mode 72 for that period (the wind turbine can, for example, transition to mode 71 for a short time when wind conditions are outside the operating range and then return to energy harvesting mode 74). Avoiding such transitions to sleep mode for a short period of time can result in further energy savings.

[0094] The flow charts of Fig. 5 and Fig. 6 provide an overview of the respective operation of the wind turbine 100, where a method can be executed by the control system 20 controlling the operation of the wind turbine 100. In step S10, the wind turbine is enabled to operate in a sleep mode. In step S11, environmental data can be acquired, for example by measuring wind speed and optionally other data, for example meteorological data using the monitoring unit 22 and / or by receiving the respective data via the communication interface 23. Furthermore, a storage status of the energy storage system 50 can be acquired to estimate the amount of available energy. In step S12, a prediction regarding the wind speed can be acquired, for example by modeling the wind speed based on the acquired meteorological data or by receiving the respective prediction data via the interface 23. In step S13, a minimum and a maximum threshold value (or a corresponding respective cut-in wind speed range) can be determined based on the amount of energy stored in the storage system 50, for example as described above with reference to Fig. 4.

[0095] In step S14, it can be checked whether a predetermined condition is fulfilled. As detailed above, this can include checking a number of conditions, the predetermined condition being fulfilled if one of these conditions is fulfilled. Such checks can include, for example, checking a combined wind speed condition or a wind speed trend condition, checking a sufficient wind speed condition (narrower second wind speed range), checking a future wind speed condition, i.e. whether the predicted wind speed meets the respective wind speed threshold or wind speed range, whether the estimated amount of energy to be generated in a future period (where the wind conditions are predicted to be within the operating range) is greater than the respective predetermined energy threshold, etc. In step S15, it can be determined whether one of these conditions, and thus the predetermined condition, is fulfilled. If not, operation can continue in sleep mode in step S10.

[0096] If one of the conditions is met in step S15, the control device can transition the operation to the energy harvesting mode in step S16. Step S16 can include, for example, operation in local power mode 71 to supply power to the wind turbine system as required, start tracking the wind using the yaw drive, and start rotor acceleration using the pitch drive. In step S17, the transition is completed and the wind turbine can operate in the energy harvesting mode 74. In step S18, it can be checked whether the energy harvesting mode should be stopped, for example whether the wind speed has dropped below a minimum cut-out wind speed threshold or whether it has risen above a maximum cut-out wind speed threshold. It is clear that the cut-out thresholds can be set differently from the cut-in thresholds, in particular they can be set to lower values ​​(for minimum cut-out) or higher values ​​(for maximum cut-out). In other words, some hysteresis can be provided to avoid frequent changes between sleep mode and energy harvesting mode. Other conditions that may cause the wind turbine to leave the energy harvesting mode that may be checked for in step S18 may include the occurrence of a fault in the wind turbine that inhibits operation, receiving an operator command to cease operation, determining the need for self-preservation action (which occurs periodically) (e.g., untangling tower cables, automatic diagnostics of safety systems, etc.), and / or determining that the energy storage system is fully charged.

[0097] If the condition is not met in step S18, e.g. if the wind speed is still within the operating range, operation in the energy harvesting mode in step S17 can continue. Otherwise, operation can be transitioned back to the sleep mode in step S10. As outlined above, such a transition can similarly be made via the local power mode 71 (e.g. to safely slow down the wind turbine rotor, etc.). Also, as mentioned above, if the wind speed has fallen outside the operating range, but only for a short enough period of time, this can also be checked in step S18, and operation in the energy harvesting mode in step S17 can continue.

[0098] It is clear that some of the steps shown in Fig. 5 and Fig. 6 are optional, such as step S12 (in which case no forecast data may be used) or step S13 (in which case no adaptation of the thresholds may be performed). As another example, only forecast data may be used, without other steps of the method and the respective conditions. Preferably, the method can make the decision on the transition based on forecast data, in particular the forecasted wind speed, if the forecast data is available with sufficient quality (e.g. sufficient confidence), otherwise the decision can be made based on the actual monitored data, for example using combined wind speed conditions or wind speed trend conditions and sufficient wind speed conditions. Thus, a reliable operation can be achieved that minimizes the risk of exhaustion of the energy storage system 50. In particular, failed attempts and rapid succession of restarts of the wind turbine, which may exhaust the energy storage system 50, can be avoided.

[0099] It is clear that the control system 20 may include a wind turbine controller 25, which may perform the above-mentioned methods. Alternatively or additionally, the wind turbine controller 25 may include a wind farm controller, which may perform the above-mentioned methods, for example by sending respective control signals to one or more wind turbines to cause a transition of an operating mode. The control system 20 may also be implemented as a distributed control system, in which case some functions (e.g. wind speed prediction) may be performed by the wind farm controller, whereas other functions (e.g. monitoring and evaluation of wind speed data, transition of an operating mode) may be performed by the wind turbine controller 25. Other implementations are also conceivable.

[0100] While specific embodiments have been disclosed herein, various changes and modifications can be made without departing from the scope of the invention. The present embodiments are to be considered in all respects as illustrative and not restrictive, and all changes that come within the meaning and range of equivalency of the appended claims are intended to be embraced therein.

Claims

1. 1. A method of transitioning operation of a wind turbine (100) to an energy harvesting mode in which the wind turbine operates to generate electrical power from wind energy, comprising: an energy storage system (50) associated with the wind turbine (100) configured to supply power to the auxiliary system (10) of the wind turbine when the wind turbine is not generating or receiving sufficient power to power its auxiliary system (10); The method further comprising: - operating the wind turbine (100) in a first operating mode (72) in which the wind turbine (100) does not generate electrical power from wind energy, and in the first operating mode (72), stopping the supply of electrical power to one or more auxiliary electrical power consumers (12, 13, 14) of a first group (11) of the auxiliary system (10) and supplying electrical power from the energy storage system (50) to one or more auxiliary electrical power consumers (22, 23, 25) of a second group (21) of the auxiliary system (10); - acquiring environmental data including at least one of wind data and weather data; determining whether the acquired environmental data satisfies a predetermined condition, wherein the predetermined condition includes at least one of a wind speed threshold, a wind speed range within which the wind turbine (100) is operable to generate power, a wind speed trend threshold (306), or a predetermined energy threshold for expected energy production; - transitioning operation of the wind turbine (100) to the energy harvesting mode (74) if the predetermined condition is met, the transitioning operation to the energy harvesting mode (74) comprising supplying power from the energy storage system (50) to one or more auxiliary power consumers (12, 13, 14) of the first group (11); Including, The predetermined conditions include the wind speed trend threshold (306). method.

2. The method of claim 1 , wherein the wind speed thresholds among the predetermined conditions include a minimum cut-in wind speed threshold that is greater than or equal to a wind speed value at which the wind turbine (100) is operable to generate power, and / or a maximum cut-in wind speed threshold that is less than or equal to a wind speed value at which the wind turbine (100) is operable to generate power.

3. acquiring the environmental data includes acquiring wind speed data and time filtering the wind speed data; - determining whether the predetermined condition is met preferably comprises comparing the time-filtered wind speed data (301) with the wind speed threshold and / or the wind speed range.

3. The method according to claim 1 or 2.

4. 4. The method of claim 1, wherein determining whether the predetermined condition is met comprises comparing a wind speed trend (305) derived from the acquired wind data to the wind speed trend threshold (306).

5. The method further comprises: deriving the wind speed trend (305) by comparing the time-filtered wind speed data filtered with a first time constant with the time-filtered wind speed data filtered with a second time constant, or by comparing an average wind speed obtained from the wind speed data for a first time point with an average wind speed obtained from the wind speed data for a second time point different from the first time point. The method of claim 4 , comprising:

6. the predetermined conditions include a wind speed condition including the wind speed threshold and / or the wind speed range, and a wind speed trend condition further including the wind speed trend threshold; When the wind speed condition and the wind speed trend condition are satisfied, the predetermined condition is satisfied.

6. The method according to any one of claims 1 to 5.

7. the predetermined conditions include a first wind speed condition including the wind speed threshold and / or the wind speed range and a second wind speed condition further including a second wind speed threshold (303) and / or a second wind speed range; the second wind speed threshold (303) is greater than the wind speed threshold if the wind speed threshold is a minimum threshold and is less than the wind speed threshold if the wind speed threshold is a maximum threshold; and / or The second wind speed ranges are narrower than the first wind speed ranges and are disposed within the first wind speed ranges, When the second wind speed condition is satisfied, the predetermined condition is satisfied.

7. The method according to any one of claims 1 to 6.

8. The method of claim 1 , wherein the wind speed threshold and / or the wind speed range are variable and are determined based on an amount of energy stored in the energy storage system.

9. if the amount of stored energy is less, the wind speed threshold is set to a more stringent value and / or the wind speed range is set to a narrower range; If a larger amount of energy is stored, the wind speed threshold is set to a less stringent value and / or the wind speed range is set to a wider range. The method of claim 8.

10. obtaining the meteorological data includes obtaining a forecast of wind conditions for a future period; determining whether the predetermined condition is met comprises comparing predicted wind conditions to the wind speed threshold and / or the wind speed range; Preferably, the predetermined condition is satisfied when a predicted wind condition at a future time satisfies the wind speed threshold and / or is within the wind speed range.

10. The method according to any one of claims 1 to 9.

11. obtaining the meteorological data includes obtaining a forecast of wind conditions for a future period; determining whether the predetermined condition is satisfied includes determining a continuous period during which the predicted wind conditions are within the wind speed range; Determining whether the predetermined condition is satisfied further comprises: - estimating the amount of energy expected to be generated by the wind turbine (100) within said consecutive time periods; comparing the estimated amount of energy with a predetermined energy threshold greater than an amount of energy required to transition the operation of the wind turbine from the first operation mode (72) to the energy harvesting mode (74), where the condition is met if the estimated amount of energy meets or exceeds the predetermined energy threshold; and / or further comprising determining that the condition is satisfied if the continuous period is greater than a predetermined duration threshold. Including, 11. The method according to any one of claims 1 to 10.

12. the acquired environmental data is local to a location of the wind turbine (100) or a location of a group of wind turbines; the transition is performed individually for each wind turbine (100) or each wind turbine group based on the local environmental data for each wind turbine (100) or each wind turbine group.

12. The method according to any one of claims 1 to 11.

13. If the wind turbine (100) is operating in the energy harvesting mode (74) and a second predetermined condition is satisfied, the method includes transitioning operation of the wind turbine (100) to the first operating mode (72); Preferably, obtaining said meteorological data comprises obtaining a forecast of wind conditions for a future period; Determining whether the second predetermined condition is satisfied includes: - comparing the predicted wind conditions with a cut-out wind speed range; determining a second time period during which the forecasted wind conditions are outside the cutout wind speed range; Including, if the wind turbine (100) is operating in the energy harvesting mode (74) and the second period of time is less than a maintenance period of time, operation of the wind turbine (100) is maintained in the energy harvesting mode (74) during the second period of time.

13. The method according to any one of claims 1 to 12.

14. 1. A wind turbine control system configured to control a transition of operation of a wind turbine into an energy harvesting mode (74) in which the wind turbine (100) operates to generate electrical power from wind energy, the system comprising: an energy storage system (50) associated with the wind turbine (100) configured to supply power to the auxiliary system (10) when the wind turbine (100) is not generating or receiving sufficient power to power the auxiliary system (10); The control system (20) is configured to execute a method according to any one of claims 1 to 13. Wind turbine control systems.

15. 1. A computer program for controlling operation of a wind turbine, comprising: an energy storage system (50) associated with the wind turbine (100) configured to supply power to the auxiliary system (10) when the wind turbine (100) is not generating or receiving sufficient power to power the auxiliary system (10); The computer program comprises control instructions which, when executed by a processing unit (26) of a control system (20) for controlling an operation of the wind turbine (100), cause the processing unit (26) to perform a method according to any one of claims 1 to 13. Computer program.

Citation Information

Patent Citations

  • Operating method of wind power generation equipment

    JP2018510287A

  • Wind turbine operation during grid loss using a storage unit

    JP2020523515A

  • Wind turbine start assist device

    WO2017149657A1

  • Waking a wind turbine from a sleep state

    WO2021069045A1