Method and apparatus for calculating carbon emissions from thermal power generation units
By calculating the actual carbon emissions of thermal power generation units based on actual operating conditions and carbon content, the method addresses the inaccuracy of existing methods, providing more reliable data for carbon emission reduction and neutrality.
Patent Information
- Application Number
- JP2024564684
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Priority Date
- 2023-02-17
- Filing Date
- 2024-01-05
- Publication Date
- 2025-05-02
- Estimated Expiration
- 2044-01-05
AI Technical Summary
Existing methods for calculating carbon emissions from thermal power generation units are inaccurate due to the failure to account for the difference between daily operating values and design values of parameters, as well as the actual carbon content of burnt coal during operation.
The method involves determining the total operating load section of a thermal power generation unit, identifying feature load points based on preset basic load points, calculating the actual carbon emissions of each feature load point using the actual carbon content and energy consumption, and then determining the actual total carbon emissions over a specified period.
This approach provides more accurate calculations of carbon emissions by considering actual operating conditions, leading to improved reliability and support for achieving carbon peak-out and neutrality in coal power generation units.
Smart Images

Figure 2025514460000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to the technical field of carbon emission calculation of a thermal power unit, in particular to a method for calculating carbon emission of a thermal power unit, an apparatus for calculating carbon emission of a thermal power unit, an electronic device, and a readable storage medium. [Background technology]
[0002] At present, the proportion of electrical energy generated by thermal power generation in domestic and industrial electricity consumption remains high, so the investigation of carbon emissions from thermal power generation units is of great significance. Generally, carbon emissions are measured using the accounting method and the continuous emission monitoring system method. The continuous emission monitoring system method has already gained a certain foundation, but the existing technology relies on the principle of "accounting as the main, monitoring as the secondary", and at present, the power generation industry adopts the accounting method to quantify carbon emissions. Among them, calculating the carbon emissions of thermal power generation units based on energy consumption is one of the accounting methods.
[0003] There are many research methods and contents for the energy consumption of traditional coal-fired power generation units, and the calculation method is mature and many achievements have been made, but the calculation method of energy consumption has been basically agreed upon. The direct balance statistical method has a large calculation error, and it is difficult to avoid or reduce the error by better means or methods, so the indirect balance calculation method is usually used to determine and evaluate the energy consumption of the unit. The indirect balance calculation method calculates the steam turbine heat consumption, boiler efficiency, in-house rate, and pipeline efficiency under a certain load condition through performance testing to calculate the test coal consumption under that load, and obtains the corrected energy consumption after correcting the boundary conditions to the design boundary conditions through correction calculation, that is, the standard energy consumption of the unit. Based on the research of energy consumption, the operating energy consumption of the unit at a specific load point is obtained by calculating the influence coefficient of the energy consumption caused by the deviation between the actual boundary conditions and the design value, and the carbon emission result of the thermal power generation unit at this load is obtained, and the carbon emission of the unit in a specific period is obtained by weighting statistics. However, existing calculation methods do not take into account the difference between daily operating values and design parameter values, or the carbon content of the coal actually burned out, resulting in inaccurate calculations of carbon emissions. Summary of the Invention [Problem to be solved by the invention]
[0004] The objective of the embodiments of the present invention is to provide a method and apparatus for calculating carbon emissions of a thermal power unit, which at least solves the problem of inaccurate calculation of carbon emissions due to the difference between daily operating values and design values of parameters and the actual burn-out carbon content of the burning coal not being taken into account. [Means for solving the problem]
[0005] In order to achieve the above object, the first aspect of the present invention comprises: Obtaining a total operating load section of a thermal power generation unit within a predetermined operating period; determining all characteristic load points of the thermal power generation units in the total operating load section according to the total operating load section and a preset basic load point of the thermal power generation units; Determining an actual carbon emission amount of each characteristic load point according to the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption amount of each characteristic load point; determining an actual total carbon emission of the thermal power unit within the predetermined operating period based on the actual carbon emission of all characteristic load points.
[0006] Optionally, the step of determining all characteristic load points of the thermal power generation units in the total operating load section based on the total operating load section and the preset basic load point of the thermal power generation units includes: If the minimum operating load within the total operating load section is equal to or greater than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset base load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a first preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the maximum operating load within the total operating load section is equal to or lower than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset basic load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a second preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the preset basic load point is within the total operating load section, A preset basic load point, a minimum operating load within a total operating load section, and a maximum operating load are all determined as load points; Starting from the preset basic load point, sequentially determine load points other than the basic load point and the load point corresponding to the maximum operating load between the preset basic load point and the load point corresponding to the maximum operating load in the total operating load section according to a first preset interval; Using the preset basic load point as a starting point, determine a load point other than the basic load point and the load point corresponding to the minimum operating load between the preset basic load point and the load point corresponding to the minimum operating load in the total operating load section according to a second preset interval; and determining, as a characteristic load point, an average load of every two adjacent load points among all the load points within the total operating load section.
[0007] Optionally, the step of determining an actual carbon emission amount of each characteristic load point based on an actual burnout carbon content of the combustion coal of the thermal power unit and an actual characteristic energy consumption amount of each characteristic load point includes: Acquiring a domestic ratio, a boiler efficiency, and a steam turbine thermal efficiency for each characteristic load point, and acquiring a carbon content of the combustion coal, a calorific value of the combustion coal, an ash content of the combustion coal, a carbon content of the fly ash after combustion, and a carbon content of the clinker after combustion of the thermal power generation unit; Determining an actual burnout carbon content of the combustion coal based on the carbon content of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power unit; determining an actual characteristic energy consumption for each characteristic load point based on the calorific value of the burning coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency; determining an actual carbon emission amount for each characteristic load point based on the actual characteristic energy consumption of each characteristic load point and the actual burn-off carbon content of the combusted coal.
[0008] Optionally, the step of determining an actual burnout carbon content of the combustion coal based on a carbon content of the combustion coal, an ash content of the combustion coal, a carbon content of the combustion fly ash, and a carbon content of the combustion clinker of the thermal power unit includes: Calculating the actual burnout carbon content of the combustion coal by the following formula:
number
[0009] Optionally, the step of determining an actual characteristic energy consumption for each characteristic load point based on the calorific value of the combusted coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency includes: Calculating the actual characteristic energy consumption of the characteristic load point by the following formula:
number
number
number
[0010] Optionally, the step of determining an actual carbon emission amount for each characteristic load point based on an actual characteristic energy consumption amount for each characteristic load point and an actual burn-off carbon content of the combusted coal comprises: Calculating the actual carbon emission of the characteristic load point according to the following formula:
number
[0011] Optionally, the step of determining an actual total carbon emission of the thermal power generation unit within the predetermined operating period based on the actual carbon emission of all characteristic load points includes the step of calculating an actual total carbon emission of the thermal power generation unit within the predetermined operating period by the following calculation formula:
number
[0012] A second aspect of the present invention is A data acquisition module for acquiring a total operating load section of a thermal power generation unit within a predetermined operating period; A characteristic load point determination module determines all characteristic load points of the thermal power generation units in the total operating load section according to the total operating load section and a preset basic load point of the thermal power generation units; A characteristic load point carbon emission determination module determines an actual carbon emission amount of each characteristic load point according to an actual burnout carbon content of the combustion coal of the thermal power unit and an actual characteristic energy consumption amount of each characteristic load point; and an actual total carbon emission determination module for determining an actual total carbon emission of the thermal power unit within the specified operating period based on the actual carbon emission of all characteristic load points.
[0013] A third aspect of the present invention provides an electronic device including a memory, a processor, and a computer program stored in the memory and operable by the processor, the processor executing the computer program to realize the above-mentioned method for calculating carbon emissions of a thermal power generation unit.
[0014] In another aspect, the present invention provides a machine-readable storage medium having stored thereon instructions for causing a machine to perform the above-mentioned method of calculating carbon emissions of a thermal power generating unit of the present application. Effect of the Invention
[0015] According to the above technical solutions, the beneficial effects of the present invention are as follows:
[0016] In this technical solution, according to the actual operating load of the thermal power unit, the characteristic load points are divided within the total operating load section, and the actual characteristic energy consumption at the characteristic load points and the actual carbon content of the combustion coal of the thermal power unit at the time of burning off are calculated based on the difference between the daily operation and the design value, so as to calculate the actual carbon emission of the thermal power unit, with a smaller error and more accurate calculation results, providing reliable data support for the coal-fired power unit to achieve carbon peak-out and carbon neutrality.
[0017] Other features and advantages of embodiments of the present invention are explained in detail in the following specific embodiment sections. [Brief description of the drawings]
[0018] The drawings are intended to provide a further understanding of the embodiments of the present invention, constitute a part of this specification, and are intended to explain the embodiments of the present invention together with the following specific embodiments, but are not intended to limit the embodiments of the present invention. [Figure 1] 1 is a flow chart of a method for calculating carbon emissions of a thermal power generating unit according to the present invention. [Diagram 2] 4 is a flow chart of actual carbon emissions for characteristic load points according to the present invention. [Diagram 3] 1 is a structural schematic diagram of a carbon emission calculation device for a thermal power generating unit according to the present invention; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0019] Hereinafter, specific embodiments of the present invention will be described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are for the purpose of illustration and description of the present invention, and are not intended to limit the present invention.
[0020] FIG. 1 is a flowchart of the method for calculating carbon emissions of a thermal power unit according to the present invention, FIG. 2 is a flowchart of actual carbon emissions at characteristic load points according to the present invention, and FIG. 3 is a structural schematic diagram of the apparatus for calculating carbon emissions of a thermal power unit according to the present invention. Example 1
[0021] As shown in FIG. 1, an embodiment of the present invention provides a method for calculating carbon emissions of a thermal power generation unit, including the following steps 1 to 4.
[0022] Step 1: Obtain the total operating load section of the thermal power generation unit within a given operating period.
[0023] Step 2: Based on the total operating load section of the thermal power generation unit and the preset basic load point, all the characteristic load points of the thermal power generation unit in the total operating load section are determined.
[0024] Step 3: Determine the actual carbon emission amount of each characteristic load point according to the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption amount of each characteristic load point.
[0025] Step 4: Determine the actual total carbon emission of the thermal power unit within the given operating period based on the actual carbon emission of all characteristic load points.
[0026] Specifically, during the operation of a thermal power generating unit in a certain operation period, its operation load usually changes linearly, i.e., as the operation time passes, its operation load increases or decreases, and the operation load does not jump over time. In step 102, the step of determining all characteristic load points of the thermal power generating unit in the total operation load section based on the total operation load section of the thermal power generating unit and the preset basic load point can be understood as each characteristic load point corresponds to one operator load section of the thermal power generating unit, and all operator load sections are combined to obtain a complete total operation load section.
[0027] Further, the step of determining all the characteristic load points of the thermal power generation units in the total operating load section based on the total operating load section and the preset basic load point of the thermal power generation units includes: If the minimum operating load within the total operating load section is equal to or greater than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset base load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a first preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the maximum operating load within the total operating load section is equal to or lower than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset basic load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a second preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the preset basic load point is within the total operating load section, A preset basic load point, a minimum operating load within a total operating load section, and a maximum operating load are all determined as load points; Starting from the preset basic load point, sequentially determine load points other than the basic load point and the load point corresponding to the maximum operating load between the preset basic load point and the load point corresponding to the maximum operating load in the total operating load section according to a first preset interval; Using the preset basic load point as a starting point, determine a load point other than the basic load point and the load point corresponding to the minimum operating load between the preset basic load point and the load point corresponding to the minimum operating load in the total operating load section according to a second preset interval; and determining, as a characteristic load point, an average load of every two adjacent load points among all the load points within the total operating load section.
[0028] Specifically, in this embodiment, a case where 55% load is the preset basic load point, the first preset amount is set to 10% of the reference test load, and the total operating load range of the thermal power generation unit is 60% to 90% is described as an example. In this case, if the minimum operating load of 60% is equal to or higher than the basic load point of 55%, first, the minimum operating load of 60% and the maximum operating load of 90% are determined as load points, and the maximum load p of the actual operation is calculated based on the preset reference load point. max Determine one load point for each 10% increase until the lowest load p min From maximum load p max All load points p in the above load section m At such a load point p m These include 60% operating load, 65% operating load, 75% operating load, 85% operating load, and 90% operating load. m +p m+1 ) / 2 is set as the characteristic load, and all characteristic load points in the total operating load section are determined. These characteristic load points include the characteristic load point 62.5%, the characteristic load point 70%, the characteristic load point 80%, and the characteristic load point 87.5%. The corresponding steam turbine heat consumption (H Pm +H Pm+1 ) / 2, boiler efficiency (η Pm +η Pm+1 ) / 2, local rate (L Pm +L Pm+1 ) / 2 is p m From p m+1 The characteristic steam turbine heat consumption H corresponding to the load section Pm , characteristic boiler efficiency η Pm , feature internal rate L Pm represents p m From p m+1 The average value of the operating parameter for a load interval represents the operating parameter at the corresponding characteristic load.
[0029] Specifically, in this embodiment, a case where 55% load is the preset basic load point is taken as an example, the first preset amount is set to 5% of the reference test load, and the total operating load range of the thermal power generation unit is 30% to 50%. In this case, if the maximum operating load of 50% is less than the basic load point of 55%, first, the minimum operating load of 30% and the maximum operating load of 50% are determined as load points, and the maximum load p is determined based on the preset standard load point. max From minimum load p min All load points p in the load section m Determine one load point for every 5% increment until obtaining 50%, 45%, 40%, and 35% load. Determine all characteristic load points within the total load interval, and (p n +p n-1 ) / 2 is the characteristic load, and the characteristic load includes the characteristic load point of 47.5%, the characteristic load point of 42.5%, and the characteristic load point of 37.5%. The corresponding steam turbine heat consumption (H Pn +H Pn-1 ) / 2, boiler efficiency (η Pn +η Pn-1 ) / 2, local rate (L Pn +L Pn-1 ) / 2 is p n-1 From p n The characteristic steam turbine heat consumption H corresponding to the load section Pn , characteristic boiler efficiency η Pn , feature internal rate L Pn represents p n-1 From p n The average value of the load section operating parameter represents the operating parameter at the corresponding characteristic load.
[0030] When the preset basic load point is within the total operating load section of the thermal power generation unit, the method of determining the characteristic load point is the same as the above method, and therefore will not be described in detail here.
[0031] Furthermore, as shown in FIG. 2, the step of determining the actual carbon emission amount of each characteristic load point based on the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption amount of each characteristic load point includes the following steps 301 to 304.
[0032] Step 301: Obtain the in-house ratio, boiler efficiency, and steam turbine thermal efficiency for each characteristic load point, and obtain the carbon content of the combustion coal, the calorific value of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power generation unit.
[0033] Step 302: Determine the actual burnout carbon content of the combustion coal according to the carbon content of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power unit.
[0034] Step 303: Determine the actual characteristic energy consumption of each characteristic load point based on the calorific value of the burning coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency.
[0035] Step 304: Determine the actual carbon emission amount of each characteristic load point based on the actual characteristic energy consumption amount of each characteristic load point and the actual burn-off carbon content of the burning coal.
[0036] Further, the step of determining an actual burnout carbon content of the combustion coal based on the carbon content of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power unit includes: Calculating the actual burnout carbon content of the combustion coal by the following formula:
number
[0037] Further, the step of determining an actual characteristic energy consumption of each characteristic load point based on the calorific value of the burning coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency includes: Calculating the actual characteristic energy consumption of the characteristic load point by the following formula:
number
number
number
[0038] Specifically, in this embodiment, the load p max All characteristic load points p in the load section mCalculation of steam turbine heat consumption, boiler efficiency, and in-house ratio at 55% to minimum load p min All characteristic load points p in the total operating load section m The calculation of the characteristic steam turbine heat consumption, characteristic boiler efficiency, and characteristic utility ratio in is performed as described above.
[0039] The impact coefficient of the difference between daily operation and the design value on the steam turbine heat consumption, the impact coefficient of the boiler efficiency, the impact coefficient of the pipeline efficiency, and the impact coefficient of the in-house ratio are determined as follows.
[0040] 1. The influence coefficient factors of steam turbine heat consumption include main steam pressure, main steam temperature, reheat steam temperature, reheat steam pressure loss, unit back pressure and other factors. Specifically, it includes the following: n The coefficient of influence on heat consumption is calculated using the following formula.
number
number
number
[0041] 2. The influence coefficient factors of boiler efficiency include sub-factors such as the inlet flue gas temperature of the air preheater, the outlet flue gas temperature of the air preheater, the inlet air temperature of the air preheater, and the analysis results of the combustion coal elements. Specific subelement β nThe coefficient of influence on boiler efficiency is calculated using the following formula.
number
number
number
[0042] 3. The influence coefficient factors of pipeline efficiency include sub-factors such as system leakage, boiler soot blower, condenser water replenishment, factory heating, pipeline heat dissipation, etc. Specific subelement χ n The coefficient of influence of on the pipeline efficiency is calculated using the formula.
number
number
number
[0043] 4. The influence coefficient factor of the stationary rate includes a sub-element which is the change in the operation method of each auxiliary unit. A specific subelement δ n The coefficient of influence on the in-house rate is calculated using the following formula.
number
number
number
number
[0044] Furthermore, the step of determining the actual total carbon emission of the thermal power generation unit within the predetermined operating period based on the actual carbon emission of all characteristic load points includes the step of calculating the actual total carbon emission of the thermal power generation unit within the predetermined operating period by the following calculation formula:
number
[0045] This embodiment proposes a method for calculating the carbon emission of a thermal power unit based on energy consumption, and calculates the operating energy consumption of the actual characteristic load in the full load section based on the difference between daily operation and the design value according to the correction result of the conventional performance test. Based on this, the carbon emission of the unit at various characteristic loads is calculated taking into account the actual burnout carbon content of the burning coal, and the total carbon emission over the operation period is calculated. By utilizing the research results of the energy consumption of a thermal power unit, the actual energy consumption calculated for the unit is closer to the actual consumption, thereby providing reliable data support for calculating the actual carbon emission of the thermal power unit and achieving carbon peak-out and carbon neutrality of the coal-fired power unit. In addition, in this process, the energy consumption and carbon emission under various operating load conditions are obtained, providing a research direction for reducing carbon emission. Example 2
[0046] As shown in FIG. 3, an embodiment of the present invention includes: A data acquisition module 10 for acquiring a total operating load section of a thermal power generation unit within a predetermined operating period; A characteristic load point determination module 20 for determining all characteristic load points of the thermal power generation units in the total operating load section according to the total operating load section and a preset basic load point of the thermal power generation units; A characteristic load point carbon emission determination module 30, which determines an actual carbon emission of each characteristic load point according to the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption of each characteristic load point; and an actual total carbon emission determination module 40 for determining an actual total carbon emission of the thermal power unit within the specified operating period based on the actual carbon emission of all characteristic load points. Example 3
[0047] An embodiment of the present invention also provides an electronic device including a memory, a processor, and a computer program stored in the memory and operable by the processor, the electronic device being characterized in that, when the processor executes the computer program, it realizes the above-mentioned method for calculating carbon emissions of a thermal power generation unit. Example 4
[0048] An embodiment of the present invention also provides a machine readable storage medium having stored thereon instructions for causing a machine to execute the above method for calculating carbon emissions of a thermal power generation unit. Example 5
[0049] In this embodiment, a 300 MW subcritical unit is used as an example, under a specific pre-set coal type, the operation period is 24 hours, and the operation load is between 45% and 100% of the rated load. The unit is subjected to performance tests to test the steam turbine heat consumption, boiler efficiency, and station efficiency corresponding to the pipeline efficiency of the design value of 0.985 at 45%, 50%, 55%, 65%, 75%, 85%, 95%, and 100% loads, and the results are shown in Table 1 below.
[0050] Unit Test Results [Table 1]
[0051] If the pipeline efficiency is set to a constant of 0.985, all characteristic loads and their corresponding steam turbine heat consumption, boiler efficiency, in-house ratio, and power supply energy consumption B during the operation period are p are shown in Table 2 below.
[0052] Results of each index on feature loadings [Table 2]
[0053] In this total operating load section, each parameter deviates from the design value. The calculation results of the influence coefficient of the steam turbine heat consumption, the influence coefficient of the boiler furnace efficiency, the influence coefficient of the in-house rate, the influence coefficient of the pipeline efficiency, and the actual characteristic energy consumption are shown in Table 3 below.
[0054] Impact coefficients and actual characteristic energy consumption corresponding to various characteristic load points [Table 3]
[0055] The actual burnout carbon content of the burning coal is calculated to obtain the actual carbon emissions at the characteristic load points, which are shown in Table 4 below.
[0056] Carbon emissions corresponding to various characteristic load points [Table 4]
[0057] By expressing the actual power generation of the load section with the characteristic load, the actual carbon emission of this load section is obtained, and the results are shown in Table 5 below.
[0058] Actual carbon emissions for different load sections [Table 5]
[0059] The carbon emission results of each load interval are accumulated to obtain the carbon emission for the entire operation period. The carbon emission of this unit during the 24-hour operation period is 391629.80t.
[0060] Those skilled in the art can understand that all or part of the steps in the method for implementing the above embodiments can be achieved by instructing the relevant hardware by a program stored in a storage medium that includes several instructions for making a microcontroller, chip, or processor execute all or part of the steps of the method described in each embodiment of the present invention. Meanwhile, the storage medium includes various media capable of storing program code, such as USB flash disks, removable hard disks, read-only memories (ROMs), random access memories (RAMs), magnetic disks, and optical disks.
[0061] Although any embodiment of the present invention has been described in detail above with reference to the drawings, the embodiment of the present invention is not limited to the specific details in the above embodiment, and within the scope of the technical concept of the embodiment of the present invention, several simple modifications are possible for the technical solution of the embodiment of the present invention, and all of these simple modifications belong to the protection scope of the embodiment of the present invention. In addition, each specific technical feature described in the above specific embodiment may be combined in any suitable manner as long as there is no contradiction. In order to avoid unnecessary duplication, various combinable aspects in the embodiment of the present invention will not be described separately.
[0062] Furthermore, any combination between various different embodiments of the present invention is possible, and as long as it is not contrary to the concept of the embodiment of the present invention, it should be considered as the disclosure of the embodiment of the present invention. [Explanation of symbols]
[0063] 10 Data Acquisition Module 20. Characteristic Load Point Determination Module 30 Features Load Point Carbon Emission Determination Module 40 Actual Total Carbon Emissions Determination Module
Claims
1. 1. A method for calculating carbon emissions of a thermal power generation unit, comprising: Obtaining a total operating load section of a thermal power generation unit within a predetermined operating period; determining all characteristic load points of the thermal power generation units in the total operating load section according to the total operating load section and a preset basic load point of the thermal power generation units; Determining an actual carbon emission amount of each characteristic load point according to the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption amount of each characteristic load point; and determining an actual total carbon emission of the thermal power unit within the specified operating period based on the actual carbon emission of all characteristic load points.
2. The step of determining all characteristic load points of the thermal power generation units in the total operating load section based on the total operating load section and the preset basic load point of the thermal power generation units includes: If the minimum operating load within the total operating load section is equal to or greater than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset base load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a first preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the maximum operating load within the total operating load section is equal to or lower than the preset basic load point, Determine both the minimum and maximum operating loads within the total operating load section as load points; Starting from the preset basic load point, sequentially determine load points other than the load points corresponding to the minimum and maximum operating loads within the total operating load section according to a second preset interval; determining an average load between two adjacent load points among all load points in the total operating load section as a characteristic load point; If the preset basic load point is within the total operating load section, A preset basic load point, a minimum operating load within a total operating load section, and a maximum operating load are all determined as load points; Using the preset basic load point as a starting point, sequentially determine load points other than the basic load point and the load point corresponding to the maximum operating load between the preset basic load point and the load point corresponding to the maximum operating load in the total operating load section according to a first preset interval; Starting from the preset basic load point, sequentially determine load points other than the basic load point and the load point corresponding to the minimum operating load between the preset basic load point and the load point corresponding to the minimum operating load in the total operating load section according to a second preset interval; The method for calculating carbon emissions of a thermal power generation unit according to claim 1, further comprising: determining an average load of every two adjacent load points among all load points in the total operating load section as a characteristic load point.
3. The step of determining the actual carbon emission amount of each characteristic load point according to the actual burnout carbon content of the combustion coal of the thermal power unit and the actual characteristic energy consumption amount of each characteristic load point includes: Acquiring a domestic ratio, a boiler efficiency, and a steam turbine thermal efficiency for each characteristic load point, and acquiring a carbon content of the combustion coal, a calorific value of the combustion coal, an ash content of the combustion coal, a carbon content of the fly ash after combustion, and a carbon content of the clinker after combustion of the thermal power generation unit; Determining an actual burnout carbon content of the combustion coal based on the carbon content of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power unit; determining an actual characteristic energy consumption for each characteristic load point based on the calorific value of the burning coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency; and determining an actual carbon emission amount of each characteristic load point based on the actual characteristic energy consumption amount of each characteristic load point and the actual burn-off carbon content of the burning coal.
4. Determining an actual burnout carbon content of the combustion coal based on the carbon content of the combustion coal, the ash content of the combustion coal, the carbon content of the fly ash after combustion, and the carbon content of the clinker after combustion of the thermal power unit, Calculating the actual burnout carbon content of the combustion coal by the following formula: [0010] Here, C b is the actual burnout carbon content of the burning coal, C ar is the carbon content of the burning coal, A ar is the ash content of the burning coal, C f is the carbon content of the fly ash after combustion, C s The method for calculating carbon emissions of a thermal power generating unit according to claim 3, characterized in that: is the carbon content of the clinker after combustion.
5. Determining an actual characteristic energy consumption of each characteristic load point based on the calorific value of the burning coal, the in-house rate at the characteristic load point, the boiler efficiency, and the steam turbine thermal efficiency, Calculating the actual characteristic energy consumption of the characteristic load point by the following formula: [0025] Here, B' p is the actual feature energy consumption at the feature load point, and B p is the coal consumption for power supply at the characteristic load point; [0030] And H p is the steam turbine thermal efficiency at the characteristic load, μ is the calorific value of the burned coal, and η p is the boiler efficiency at the characteristic load, and L p is the in-house ratio at the characteristic load, θ is the pipeline efficiency, and Ω p is the influence coefficient of steam turbine heat consumption on energy consumption, and σ p is the influence coefficient of boiler efficiency on energy consumption, [0045] is the influence coefficient of pipeline efficiency on energy consumption, and τ p The method for calculating carbon emissions of a thermal power generating unit according to claim 3, characterized in that: ##EQU1## is an influence coefficient of the in-house rate on the energy consumption.
6. Determining an actual carbon emission amount of each characteristic load point based on an actual characteristic energy consumption amount of each characteristic load point and an actual burn-off carbon content of the burning coal, Calculating the actual carbon emission of the characteristic load point according to the following formula: [0050] Here, C p is the actual carbon emission of the characteristic load point, and B' p is the actual feature energy consumption of the feature load point, and C b 4. The method of claim 3, wherein: t is the actual burnout carbon content of the coal burned.
7. The step of determining an actual total carbon emission of the thermal power generation unit in the predetermined operating period based on the actual carbon emission of all the characteristic load points includes: Calculating the actual total carbon emissions of the thermal power generating unit during the predetermined operating period according to the following formula: [006] where C is the actual total carbon emission of the thermal power unit during the given operating period, n is the number of characteristic load points, and C pi is the actual carbon emission of the i-th characteristic load point, and W i The method for calculating carbon emissions of a thermal power generating unit according to claim 1, characterized in that i i i is the power generation amount of the driver load section corresponding to the i-th characteristic load point.
8. A device for calculating carbon emissions of a thermal power generation unit, comprising: A data acquisition module for acquiring a total operating load section of a thermal power generation unit within a predetermined operating period; A characteristic load point determination module determines all characteristic load points of the thermal power generation units in the total operating load section according to the total operating load section and a preset basic load point of the thermal power generation units; A characteristic load point carbon emission determination module determines an actual carbon emission amount of each characteristic load point according to an actual burnout carbon content of the combustion coal of the thermal power unit and an actual characteristic energy consumption amount of each characteristic load point; and an actual total carbon emission determination module for determining an actual total carbon emission of the thermal power unit within the specified operating period based on the actual carbon emission of all characteristic load points.
9. An electronic device including a memory, a processor, and a computer program stored in the memory and operable on the processor, The electronic device, characterized in that, when the processor executes the computer program, it realizes the method for calculating carbon emissions of a thermal power generation unit according to any one of claims 1 to 7.
10. A machine-readable storage medium having stored thereon instructions for causing a machine to execute the method for calculating carbon emissions of a thermal power generation unit according to any one of claims 1 to 7.
Citation Information
Patent Citations
Electric power system carbon emissions real-time measuring method and carbon meter system
CN106251095A
Coal-fired unit carbon emission calculation method, monitoring system and carbon emission intensity calculation method
CN115343417A
Simulation analysis method and system for influence of carbon transaction mechanism on kilowatt-hour cost
CN115601074A
Power system carbon flow tracking method based on power flow analysis, medium and system