Combined air cushion pressure adjustment chamber
The combined air cushion pressure regulating chamber addresses high construction costs and gas entry risks by connecting the air cushion pressure adjustment chamber to an inclined shaft extension pipe for gas discharge, enhancing safety and reducing costs and environmental impact.
Patent Information
- Application Number
- JP2024003014U
- Authority / Receiving Office
- JP · JP
- Patent Type
- Utility models
- Current Assignee / Owner
- Priority Date
- 2024-04-12
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-09-06
AI Technical Summary
Existing pressure adjustment chambers in hydroelectric power plants face high construction costs and risks of gas entry causing cavitation, especially in air cushion type chambers, and are limited by ground topography and environmental impact.
A combined air cushion pressure regulating chamber with an air cushion pressure adjustment chamber connected to an inclined shaft extension pipe, allowing gas discharge to the atmosphere and reducing construction costs by simultaneous excavation, while ensuring operational reliability and safety.
Reduces construction costs, prevents gas entry, and enhances safety by discharging gases, suitable for challenging ground conditions, and reduces the air cushion pressure adjustment chamber's volume, improving operational reliability and environmental impact.
Smart Images

Figure 0003249018000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to the technical field of water conservancy and hydroelectric power generation, and in particular to a combined air cushion pressure adjustment chamber. [Background technology]
[0002] In the water conservancy system of a hydroelectric power station with a long water supply system, in order to deal with the water hammer that occurs during the transition process such as load shedding due to unit accidents, pump power outages, and load increases and decreases, it is necessary to install a pressure adjustment chamber as a pressure stabilization measure for the hydroelectric power station. In the related technology, depending on whether the pressure adjustment chamber is connected to the atmosphere or not, it can be divided into a normal pressure adjustment chamber (the water surface indoors is a free liquid surface) and an air cushion type pressure adjustment chamber (indoors is pressurized gas), among which, the normal pressure adjustment chamber has high requirements for the ground surface topography and high construction costs. In the air cushion pressure adjustment chamber, there is a risk that gas will enter the water transmission pipe and cause cavitation and other phenomena. Summary of the Invention [Problem to be solved by the invention]
[0003] In order to solve the above technical problems, the present invention provides a combined air cushion pressure adjusting chamber to improve the reliability and safety of operation. [Means for solving the problem]
[0004] An embodiment of the present invention provides a combined air cushion pressure adjustment chamber, which includes a first water supply system and a water hammer adjustment system. The first water supply system includes a first inclined shaft pipe and a second pipe, and one end of the first inclined shaft pipe is connected to one end of the second pipe. The water hammer adjustment system includes an air cushion pressure adjustment chamber and an inclined shaft extension pipe. One end of the inclined shaft extension pipe is connected to the atmosphere and the other end is located at the connection between the first inclined shaft pipe and the second pipe, and the inclined shaft extension pipe is on the same line as the first inclined shaft pipe. The air cushion pressure adjustment chamber is located on one side of the inclined shaft extension pipe and is connected to the inclined shaft extension pipe.
[0005] According to the combined air cushion pressure adjustment chamber of the embodiment of the present invention, the air cushion pressure adjustment chamber is provided on one side of the inclined shaft extension pipe, so that the air cushion pressure adjustment chamber and the inclined shaft extension pipe can be excavated from the underground segment simultaneously with the first inclined shaft pipe and the second pipe, thereby reducing costs. It is also convenient for construction and can save construction costs. In addition, the air cushion pressure adjustment chamber communicates with the inclined shaft extension pipe, so that the gas overflowing from the air cushion pressure adjustment chamber can be discharged to the atmosphere through the inclined shaft extension pipe, which can prevent the gas from entering the unit through the first water supply system, which is advantageous for improving the protection of the unit, and can also discharge the gas mixed into the first water supply system. In addition, since the inclined shaft extension pipe itself has a water storage adjustment function, the volume of the air cushion pressure adjustment chamber can be reduced, which is advantageous for reducing the cost of the combined air cushion pressure adjustment chamber. And the combined air cushion pressure adjustment chamber can be applied to situations where the ground surface has poor traffic conditions, is difficult for construction machines to reach, or the ground surface has a poor rock layer structure.
[0006] In one possible implementation, the water hammer control system further includes a vent pipe, and the inclined shaft extension pipe is connected to the atmosphere via the vent pipe.
[0007] In one possible implementation, the vent piping is cylindrical.
[0008] In one possible implementation, the water hammer adjustment system further includes a connecting pipe, and the air cushion pressure adjustment chamber communicates with the inclined shaft extension piping through the connecting pipe.
[0009] In one possible implementation, the connecting pipe is a steel pipe.
[0010] In one possible implementation, the inclined shaft extension piping includes an extension segment and a connection segment, the extension segment having one end connected to the vent piping and the other end connected to the connection segment, the connection segment having one end connected to the connection pipe and the other end connected to the first inclined shaft piping, and the connection segment being a steel pipe.
[0011] In one possible implementation, the air cushion pressure regulation chamber includes a cylindrical pipe and a hemispherical seal member, the hemispherical seal members being provided at opposite ends of the cylindrical pipe.
[0012] In one possible implementation, the material of the cylindrical piping is steel and the material of the hemispherical seal member is steel.
[0013] In one possible implementation, the combined air cushion pressure regulation chamber further includes a second water supply system in communication with the air cushion pressure regulation chamber.
[0014] In one possible implementation, the air cushion pressure regulation chamber is located on the side of the inclined shaft extension pipe away from the second pipe.
[0015] The drawings herein are incorporated in and constitute a part of the specification, illustrate embodiments consistent with the present invention, and together with the specification, serve to explain the principles of the invention.
[0016] In order to more clearly explain the technical solutions in the embodiments of the present invention or related technologies, the following briefly describes the drawings that need to be used to describe the embodiments or related technologies, and it is obvious that a person skilled in the art can also derive other drawings based on these drawings without creative labor. [Brief description of the drawings]
[0017] [Figure 1] 2 is a schematic diagram of an air cushion pressure adjusting chamber according to some embodiments of the present invention; [Diagram 2] 4 is a schematic diagram of a combined air cushion pressure adjusting chamber according to another embodiment of the present invention; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0018] In order to make the above objectives, features and advantages of the present invention more clearly comprehensible, the technical solution of the present invention is further described below, and it should be noted that, unless contradictory, the embodiments and features of the embodiments of the present invention can be combined with each other.
[0019] In describing the present invention, it should be understood that the orientations or positional relationships indicated by terms such as "upper", "lower", "front", "rear", "bottom", "inner", "outer", etc. are orientations or positional relationships based on the drawings, and are merely for the convenience and simplification of the description of the present invention, and do not indicate or imply that such devices or elements necessarily have a specific orientation or are constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0020] In the description of the embodiments of the present invention, unless otherwise specified and limited, the terms "attached", "coupled" and "connected" should be understood in a broad sense. For example, "connected" may be a detachable connection, a non-detachable connection, a direct connection or an indirect connection through an intermediate medium. In particular, "fixed connection" means that the relative positional relationship between the two is not changed after being connected to each other. In addition, the directional terms such as "inside" and "outside" mentioned in the embodiments of the present invention are merely directions when referring to the drawings, and the directional terms used are used to better and more clearly explain and understand the embodiments of the present invention, and do not indicate or imply that such devices or elements necessarily have a specific orientation or are constructed and operated in a specific orientation, and therefore should not be understood to limit the embodiments of the present invention.
[0021] In describing embodiments of the invention, the terms "comprise," "include," or any other variant thereof are intended to cover a non-exclusive inclusion, whereby a process, method, article, or apparatus that includes a set of elements includes not only those elements, but also other elements not expressly listed or that are inherent to the process, method, article, or apparatus. Absent further limitations, an element qualified with the phrase "comprises a ..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes the element. Absent further limitations, an element qualified with the phrase "comprises a ..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes the element.
[0022] Referring to Fig. 1, Fig. 1 is a schematic diagram of a combined air cushion pressure adjustment chamber according to some embodiments of the present invention. The embodiments of the present invention provide a combined air cushion pressure adjustment chamber 100. The combined air cushion pressure adjustment chamber 100 includes a first water supply system 1 and a water hammer control system 2.
[0023] The first water supply system 1 may include a first inclined pipe 11 and a second pipe 12. One end of the first inclined pipe 11 communicates with one end of the second pipe 12.
[0024] The water hammer control system 2 may include an inclined shaft extension pipe 22. One end of the inclined shaft extension pipe 22 is connected to the atmosphere, and the other end is provided at a connection between the first inclined shaft pipe 11 and the second pipe 12. Specifically, the first inclined shaft pipe 11, the second pipe 12, and the inclined shaft extension pipe 22 are all connected to each other, and the second pipe 12 may be located between the first inclined shaft pipe 11 and the inclined shaft extension pipe 22, and the gas in the inclined shaft extension pipe 22 can be discharged to the atmosphere. The inclined shaft extension pipe 22 and the first inclined shaft pipe 11 adopt an inclined shaft arrangement form.
[0025] The inclined shaft extension pipe 22 is on the same line as the first inclined shaft pipe 11. Specifically, the central axis of the inclined shaft extension pipe 22 is on the same line as the central axis of the first inclined shaft pipe 11. In this way, the hydraulic structure of the combined air cushion pressure adjustment chamber 100 can be ensured, and the water hammer wave can be effectively reflected.
[0026] In addition, the length of the inclined shaft extension pipe 22 may be determined based on the calculation results of the normal water level upstream and the transition process.
[0027] The water hammer control system 2 may include an air cushion pressure control chamber 21. Since the air cushion pressure control chamber 21 can be arranged deep underground, it is possible to omit the mountainside excavation required for a normal pressure control chamber, and it is possible to cancel the construction road above the pressure control chamber, thereby reducing costs and reducing damage to the environment, which is advantageous for water and soil conservation and environmental protection. In addition, the air cushion pressure control chamber 21 can be flexibly arranged and has excellent applicability, which can reduce costs.
[0028] The air cushion pressure adjustment chamber 21 may be provided on one side of the inclined shaft extension pipe 22. In this way, the air cushion pressure adjustment chamber 21 and the inclined shaft extension pipe 22 can be excavated from the underground segment simultaneously with the first inclined shaft pipe 11 and the second pipe 12, thereby reducing costs. In addition, construction is convenient, and construction costs can be saved.
[0029] The air cushion pressure adjustment chamber 21 communicates with the inclined shaft extension pipe 22. This allows gas overflowing from the air cushion pressure adjustment chamber 21 to be discharged via the inclined shaft extension pipe 22, thereby preventing the gas from entering the unit via the first water supply system 1, which is advantageous for improving the protection of the unit. In addition, it is also possible to discharge gas that has entered the first water supply system 1. In addition, since the inclined shaft extension pipe 22 itself has a water storage adjustment function, the volume of the air cushion pressure adjustment chamber 21 can be reduced, which is advantageous for reducing the cost of the combined air cushion pressure adjustment chamber 100.
[0030] According to the combined air cushion pressure adjustment chamber 100 according to the embodiment of the present invention, the air cushion pressure adjustment chamber 21 is provided on one side of the inclined shaft extension pipe 22, so that the air cushion pressure adjustment chamber 21 and the inclined shaft extension pipe 22 can be excavated from the underground segment simultaneously with the first inclined shaft pipe 11 and the second pipe 12, thereby reducing costs. It is also convenient for construction, and construction costs can be saved. In addition, the air cushion pressure adjustment chamber 21 communicates with the inclined shaft extension pipe 22, so that the gas overflowing from the air cushion pressure adjustment chamber 21 can be discharged to the atmosphere through the inclined shaft extension pipe 22, thereby preventing the gas from entering the unit through the first water supply system 1, which is advantageous for improving the protection of the unit, and also for discharging the gas mixed into the first water supply system 1. In addition, since the inclined shaft extension pipe 22 itself has a water storage adjustment function, the volume of the air cushion pressure adjustment chamber 21 can be reduced, which is advantageous for reducing the cost of the combined air cushion pressure adjustment chamber 100. The combined air cushion pressure adjusting chamber 100 can be applied to the situation where the ground surface has poor traffic conditions, is difficult for construction machines to reach, or the rock layer structure of the ground surface is poor.
[0031] Continuing to refer to FIG 1, in some embodiments, the water hammer control system 2 may further include a vent pipe 23. The inclined shaft extension pipe 22 communicates with the atmosphere through the vent pipe 23. The provision of the vent pipe 23 allows the inclined shaft extension pipe 22 to communicate with the atmosphere, which is convenient for installation and reduces the difficulty of installation, thereby reducing the installation cost of the combined air cushion pressure adjustment chamber 100.
[0032] As an example, the ventilation pipe 23 may be extended vertically. In this way, the gas can be easily discharged and the waste of materials can be reduced, which is advantageous for reducing the cost of the combined air cushion pressure adjustment chamber 100.
[0033] 1, in some embodiments, the vent pipe 23 may be formed in a cylindrical shape, thus reducing the difficulty.
[0034] In addition, the ventilation pipe 23 may be formed in other shapes, and the present invention is not limited thereto.
[0035] 1 , in some embodiments, the water hammer control system 2 may further include a connecting pipe 24. The air cushion pressure control chamber 21 communicates with the inclined shaft extension pipe 22 through the connecting pipe 24. This makes it easier to arrange the air cushion pressure control chamber 21, thereby improving the flexibility of the installation of the air cushion pressure control chamber 21.
[0036] As an example, the connecting pipe 24 may have a bent portion, in which case the flow of gas can be buffered and the life of the air cushion pressure adjustment chamber 21 can be extended.
[0037] 1, in some embodiments, the connecting pipe 24 is a steel pipe, that is, the material for making the connecting pipe 24 may be steel, which ensures that the connecting pipe 24 can withstand the internal and external pressure, and thereby ensures the stability and reliability of the combined air cushion pressure adjustment chamber 100.
[0038] In addition, the connecting pipe 24 may be made of other materials capable of withstanding the internal pressure, and the present invention is not limited thereto.
[0039] 1, in some embodiments, the air cushion pressure adjustment chamber 21 may be located on the side of the inclined shaft extension pipe 22 away from the second pipe 12. This makes it easier to layout the air cushion pressure adjustment chamber 21, and makes the structural layout of the combined air cushion pressure adjustment chamber 100 more reasonable. In addition, the inlet resistance of the air cushion pressure adjustment chamber 21 can also be reduced.
[0040] 1 , in some embodiments, the inclined shaft extension pipe 22 includes an extension segment 221 and a connection segment 222, the extension segment 221 has one end connected to the vent pipe 23 and the other end connected to the connection segment 222, the connection segment 222 has one end connected to the connection pipe 24 and the other end connected to the first inclined shaft pipe 11, and the connection segment 222 is a steel pipe. In this way, damage to the connection segment 222 can be avoided, and the reliability and stability of the combined air cushion pressure adjusting chamber 100 can be ensured.
[0041] In addition, the material of the extension segment 221 can be determined according to the pressure calculation results of the transition process, and the hole diameter of the connection segment 222 can be designed according to actual needs.
[0042] Continuing to refer to Fig. 1 and Fig. 2, Fig. 2 is a schematic diagram of a combined air cushion pressure adjustment chamber according to some other embodiments of the present invention. In some embodiments, the air cushion pressure adjustment chamber 21 may include a cylindrical pipe 211 and a hemispherical seal member 212. The hemispherical seal members 212 may be provided on both ends opposite to each other of the cylindrical pipe 211. This facilitates processing and manufacturing, which is advantageous for reducing costs. It can also ensure that the air cushion pressure adjustment chamber 21 has good airtightness.
[0043] In some embodiments, the material of the cylindrical pipe 211 may be steel, and the material of the semi-spherical seal member 212 may be steel, so that the air cushion pressure adjustment chamber 21 can withstand the internal air pressure and liquid pressure at the same time.
[0044] 1 and 2, in some embodiments, the combined air cushion pressure adjustment chamber 100 may further include a second water supply system 3. The second water supply system 3 communicates with the air cushion pressure adjustment chamber 21. In this way, the first water supply system 1 and the second water supply system 3 can share one air cushion pressure adjustment chamber 21, thereby reducing the cost of the combined air cushion pressure adjustment chamber 100.
[0045] In the description herein, the particular features, structures, materials, or characteristics may be combined in any suitable manner in any one or more embodiments or examples.
[0046] The above is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, and all modifications and replacements that a person skilled in the art can easily conceive within the technical scope disclosed in the present invention should be included in the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be in accordance with the scope of protection of the claims.
[0047] 100, combination air cushion pressure adjustment chamber; 1, the first water supply system; 11, the first inclined shaft piping; 12, the second piping; 2, water hammer adjustment system; 21, air cushion pressure adjustment chamber; 211, cylindrical pipe; 212, hemispherical seal member; 22, inclined shaft extension pipe; 221, extension segment; 222, connection segment; 23, ventilation pipe; 24, connection pipe; 3. Second water supply system.
Claims
1. A combination air cushion pressure adjustment chamber, A first water supply system including a first inclined pipe and a second pipe, one end of the first inclined pipe being connected to one end of the second pipe; a water hammer adjustment system connected to the inclined shaft extension pipe, the water hammer adjustment system being connected to the inclined shaft extension pipe and the air cushion pressure adjustment chamber being provided on one side of the inclined shaft extension pipe.
2. 2. The combined air cushion pressure adjusting chamber according to claim 1, wherein the water hammer adjusting system further comprises a vent pipe, and the inclined shaft extension pipe is connected to the atmosphere through the vent pipe.
3. 3. The combined air cushion pressure adjusting chamber according to claim 2, wherein the ventilation pipe is cylindrical.
4. 3. The combined air cushion pressure adjustment chamber according to claim 2, wherein the water hammer adjustment system further comprises a connecting pipe, and the air cushion pressure adjustment chamber is connected to the inclined shaft extension pipe through the connecting pipe.
5. 5. The combined air cushion pressure adjusting chamber according to claim 4, wherein the connecting pipe is a steel pipe.
6. The combined air cushion pressure adjustment chamber according to claim 4, characterized in that the inclined shaft extension piping includes an extension segment and a connection segment, one end of the extension segment is connected to the ventilation piping and the other end is connected to the connection segment, one end of the connection segment is connected to the connection pipe and the other end is connected to the first inclined shaft piping, and the connection segment is a steel pipe.
7. 2. The combined air cushion pressure adjustment chamber according to claim 1, wherein the air cushion pressure adjustment chamber includes a cylindrical pipe and a hemispherical seal member, the hemispherical seal member being provided at both ends opposite to each other of the cylindrical pipe.
8. 8. The combined air cushion pressure adjusting chamber according to claim 7, wherein the material of said cylindrical pipe is steel, and the material of said semi-spherical seal member is steel.
9. 2. The combined air cushion pressure adjustment chamber according to claim 1, further comprising a second water supply system communicating with the air cushion pressure adjustment chamber.
10. 2. The combined air cushion pressure adjustment chamber according to claim 1, wherein the air cushion pressure adjustment chamber is located on the side of the inclined shaft extension pipe away from the second pipe.