Automated Asset Management and Planning
The job planning system optimizes pipe replacement projects by analyzing failure risk values and allowing user interaction, addressing inefficiencies in utility companies' planning methods to reduce waste and improve management accuracy.
Patent Information
- Application Number
- JP2021519545
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2019-06-06
- Filing Date
- 2019-10-09
- Publication Date
- 2024-09-17
- Estimated Expiration
- 2039-10-09
AI Technical Summary
Utility companies face challenges in accurately planning the replacement of aging underground pipes due to limited resources and inefficient manual methods, leading to increased repair costs and service interruptions, with existing models often resulting in wasteful replacements and inconsistent results.
A job planning system and method that utilizes a computer system to analyze failure risk values for interconnected assets, preprocess and post-process data to optimize projects, and display potential improvement projects on a graphical interface for user selection and modification, allowing for efficient and strategic pipe replacement planning.
The system enables utilities to generate optimized pipe replacement projects that align with their specific needs, reducing waste and improving the accuracy of asset management plans, thereby minimizing costs and service disruptions.
Smart Images

Figure 0007551603000008 
Figure 0007551603000015 
Figure 0007551603000004
Abstract
Description
[Technical field]
[0001] This patent application claims priority to each of the following U.S. nonprovisional, international patent applications, and U.S. provisional patent applications:
[0002] U.S. Provisional Application No. 62 / 743,477, filed October 9, 2018; U.S. Provisional Application No. 62 / 743,483, filed October 9, 2018; U.S. Provisional Application No. 62 / 743,485, filed October 9, 2018; U.S. Patent Application No. 16 / 365,466, filed March 26, 2019; U.S. Patent Application No. 16 / 365,522, filed March 26, 2019; International Patent Application No. PCT / US19 / 24139, filed March 26, 2019; International Patent Application No. PCT / US19 / 24141, filed March 26, 2019; U.S. Provisional Application No. 62 / 858,266, filed June 6, 2019.
[0003] This application incorporates by reference each of the eight patent applications listed above, and each of the applications, including U.S. provisional applications, U.S. nonprovisional applications, and international applications, which they directly or indirectly incorporate by reference. This patent application is related to the following U.S. non-provisional, international patent applications, and U.S. provisional patent applications, which are incorporated herein by reference:
[0004] U.S. Provisional Application No. 62 / 649,085, filed March 28, 2018; U.S. Provisional Application No. 62 / 658,189, filed April 16, 2018; U.S. Provisional Application No. 62 / 671,601, filed May 15, 2018; U.S. Patent Application No. 16 / 597,774, filed October 9, 2019 (Attorney Docket No. Fracta-008-US); U.S. Patent Application No. 16 / 597,691, filed October 9, 2019 (Attorney Docket No. Fracta-009-US); International Patent Application No. PCT / US19 / 55465, filed October 9, 2019 (Attorney Docket No. Fracta-009-PCT).
[0005] All of the above provisional and non-provisional patent applications are collectively referred to herein as the "commonly assigned and incorporated applications."
[0006] This patent application relates generally to an automated system and method for asset management and planning, and more particularly to an automated system and method for asset management and planning of repair and replacement work on a network of underground pipes that deliver fluids to consumers. [Background technology]
[0007] Over a million miles of water pipes in the United States alone have reached the end of their useful life and need to be replaced. Over the next 25 years, at least $1 trillion in investments will be required to maintain current levels of service to a growing population. Ignoring the problem will result in higher repair costs and increased service interruptions.
[0008] In the United States, there are about 50,000 water utilities, but due to limited budgets, they do not have the resources to replace all of them. Since it is not possible to replace all of the pipes, it is important to prioritize replacement of the pipes in the worst condition while strategically replacing expired but sound pipes in the future.
[0009] The replacement plans developed by the utilities are highly inaccurate and often not useful. Simple models developed by the utilities have resulted in the wasteful replacement of pipes that would otherwise have had additional years of life. Over the next 25 years, this will result in millions of dollars of wasted energy.
[0010] When arriving at a planned project or job to replace various segments of piping, it is common for utility companies to assign some kind of 1-5 "score" or color code (e.g., 5 different colors) to each piping segment based on some rating of damage risk (e.g., using red for highest risk of leakage). Pipe segments vary in length, and construction projects have a range of minimum and maximum project dimensions depending on various criteria (e.g., budget, cost, and other considerations such as labor and equipment availability, political, social, and environmental factors). Thus, almost every job and project involves replacing a large number of connected piping segments. Typically, a person or a team of people reviews the piping segments with assigned scores or colors to try to determine the best combination of piping segments that will fit the project size goals. This method of "eye balling" and "pattern picking" by reviewing a manual is not only laborious and tedious, but can also produce inconsistent and inaccurate results. Summary of the Invention [Problem to be solved by the invention]
[0011] According to some embodiments, a method is described for planning a project to improve a network of interconnected and managed assets, the method including receiving, by a computer system, a calculated damage risk value for each of a plurality of the managed assets, the damage risk value selected from a range including at least ten different values; and searching through the plurality of assets and generating a plurality of potential improvement projects, each of the potential improvement projects including a plurality of the interconnected and managed assets, generating the potential improvement projects based at least in part on the damage list value of each of the managed assets included in the potential improvement projects. [Means for solving the problem]
[0012] According to some embodiments, the damage risk value may include a value representing the probability of damage, and may be expressed as a percentage of the damage probability. According to some embodiments, the damage risk value may also include a value representing the consequences of damage and / or business risk exposure.
[0013] According to some embodiments, the method may further include pre-processing, which may include combining shorter assets into longer assets, eliminating groups of assets that are not worth searching, eliminating assets that have only a single interconnect and have low damage risk values, and / or combining assets with similar damage risk values.
[0014] According to some embodiments, the method may further include a post-processing step to add additional connected managed assets to the potential improvement project. The adding may be based on either the damage risk value of the managed asset to be added and / or whether the combined damage risk value for the potential improvement project has increased or decreased by adding the managed asset. The post-processing step may also combine two or more potential improvement projects into a single potential improvement project.
[0015] According to some embodiments, the interconnected managed assets are linear segments, such as pipe segments, and the potential improvement projects may be pipe replacement projects, pipe rehabilitation projects, pipe inspection projects, leak detection projects, and / or pipe condition assessment projects. The pipe segments may form a network for delivering water to consumers. According to some embodiments, the pipe segments are configured to deliver fluids, such as fresh water, wastewater, recycled water, brackish water, storm water, sea water, drinking water, steam, compressed air, oil, and / or natural gas.
[0016] According to some embodiments, the method may also include causing the plurality of potential improvement projects to be displayed on a graphical user interface and receiving a selection of, or modification to, one or more of the potential improvement projects from a user.
[0017] According to some embodiments, the method may also include displaying a plurality of potential improvement project plans on a graphical user interface (e.g., a map view and / or a table view), each of the potential improvement project plans including one or more potential improvement projects, and receiving instructions from a user regarding editing the project plans, comparing the project plans, merging the project plans, and / or splitting the project plans.
[0018] According to some embodiments, a system for planning projects to improve a network of interconnected assets is described, the system having a database storing calculated damage risk values for each of a plurality of managed assets, the damage risk values selected from a range including at least ten different values, and a processing system configured to automatically search through the plurality of assets and generate a plurality of potential improvement projects, each involving a plurality of the interconnected managed assets, the generation of the potential improvement projects being based at least in part on the damage risk values of each of the managed assets included in the potential improvement project.
[0019] As used herein, the participatory conjunctions "and," "or," and "and / or" are all intended to refer to one or more of the instances in which the objects or entities they connect may occur or exist. Thus, as used herein, the term "or" in all instances refers to an "inclusive or" and not an "exclusive or."
[0020] To further clarify the above and other advantages and features of the subject matter of the present patent application, specific examples of embodiments thereof are illustrated in the accompanying drawings. It should be understood that elements or parts illustrated in one drawing may be substituted for equivalent or similar elements or parts illustrated in another drawing, and that the drawings merely illustrate exemplary embodiments and therefore should not be considered as limiting the scope of the present patent specification or claims. The subject matter will be described and explained with additional specificity and detail through the use of the accompanying drawings. [Brief description of the drawings]
[0021] [Figure 1]FIG. 1 is a conceptual diagram of a job planner system according to some embodiments. [Diagram 2] 1 is a diagram illustrating some of the functionality and workflow of a job planner platform according to some embodiments. [Diagram 3] 1 is a diagram illustrating aspects of a user interface for a first project generation stage of a job planner according to some embodiments. [Figure 4] 1 is a diagram illustrating an example user interface displaying project outcome generation by a job planner according to some embodiments. [Diagram 5] 1 is a diagram illustrating an example user interface displaying a table view of a project pool according to some embodiments. [Figure 6] 1 is a diagram illustrating an example user interface displaying a more detailed view of a particular project in a project pool according to some embodiments. [Figure 7] 1 is a diagram illustrating an example user interface displaying a map view for a management plan according to some embodiments. [Figure 8] 1 is a diagram illustrating an example user interface displaying an administrative table view according to some embodiments. [Figure 9] 1A and 1B are schematic diagrams illustrating the merging of shorter pipe segments to form longer pipe segments to speed up the job plan search process, according to some embodiments. [Figure 10] 1A-1C are schematic diagrams illustrating three different possible piping replacement jobs under consideration, according to some embodiments. [Figure 11] 1A-1C are schematic diagrams illustrating aspects of one scheme for a search algorithm for job planning according to some embodiments. [Figure 12] 1A-1B are schematic diagrams illustrating aspects of a caching algorithm for a job planning engine according to some embodiments. [Figure 13] Schematic illustrating an example of the resulting project connected to the piping with a high score. [Figure 14] Schematic diagram illustrating one example of the following resulting project of other resulting projects. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0022] A detailed description of some examples of preferred embodiments is given below. Although some embodiments are described, it should be noted that the novel subject matter described in this patent specification should not be limited to any one embodiment or combination of embodiments described herein, but instead encompasses numerous alternatives, modifications, and equivalents. Furthermore, in the following description, various specific details are described in order to provide a thorough understanding, but it is possible to practice some embodiments without some or all of these details. Furthermore, for the sake of convenience, a description of certain technical matters known in the related art will be omitted in order to avoid unnecessarily obscuring the novel subject matter described herein. It is clear that one or some individual features of a specific embodiment described herein can be used in combination with features of other described embodiments or other features. Furthermore, like reference numerals and symbols in various drawings represent like elements.
[0023] According to some embodiments, a system and method for job planning by a water utility company is described. The job planning technique can be used to efficiently develop asset management plans and visualize their impact using information generated from existing pipe risk data. The job planner can act as a central hub that connects risk information to mitigation actions. In this manner, the job planner can leverage prior art risk information such as probability of failure (LOF) and business risk exposure (BRE) analysis. For more information regarding calculating LOF, see co-pending U.S. patent application Ser. No. 16 / 365,466 and International Patent Application No. PCT / US19 / 24139, both of which were filed on Mar. 26, 2019, hereinafter referred to as the "co-pending LOF application" and are incorporated herein by reference. The job planner technology described therein can be used to streamline the workflow of pipe risk management and eliminate inconsistencies from "eye balling" and "pattern picking" through laborious manual review of screens on a graphic information system (GIS). For more information regarding calculating COFs, see co-pending U.S. Patent Application No. 16 / 597,691, filed October 9, 2019 (Attorney Docket No. Fracta-009-US), and International Patent Application No. PCT / US19 / 55365, filed October 9, 2019 (Attorney Docket No. Fracta-009-PCT), hereafter referred to as the "co-pending COF Application" and incorporated herein by reference. The job planner technology described allows risk-based projects to be "packaged" into suitable sizes with minimal effort from water utility staff. These projects can be used either as endpoint guidelines for pipe replacement or as entry points for targeted physical condition assessments that seamlessly integrate with a water utility's existing risk management mitigation tools and strategies.
[0024] Each utility has unique challenges and methods for selecting projects for asset management planning. Thus, employing a goal-directed workflow, the described job planning system and method enables water utility planners to quickly generate high-risk water main coverage projects tailored to their specific needs.
[0025] The described job planning system and method is capable of optimizing main replacement projects by rationally sizing them for a variety of jobs, identifying mains that need to be upsized for new development projects, coordinating upcoming paving plans to synchronize main replacements, and identifying main material to be retired.
[0026] As used herein, the following terms have the following meanings: "LOF": the likelihood or probability of damage to a target asset (most often a percentage or score is used, but alternatively an estimated number of damages or damage ratio can be used). "COF": the outcome of damage to a target asset (can use a score or a monetary value such as a dollar amount). "BRE": the business risk exposure, usually defined as LOF x COF and derived from LOF and COF (the resulting value can be a score, a monetary value, etc.). "Project": a set of multiple assets to manage, hereafter "job" and "project" are used interchangeably. "Job planner": a tool for automatically generating projects based on several values such as LOF, BRE, etc. associated with each asset. "GIS": geographic information system. "Plan": a set of multiple projects. LOF / COF / BRE "rank": the rank of the cohort or group assigned by the sorted LOF / COF / BRE, the size or dimensions of each cohort may not be the same. "asset linkages": the geographic linkages of multiple assets. "search space": the set of assets considered by the job planner (if the search space is larger than the job planner takes, it will take a relatively longer time to generate a project and vice versa). "score": means the value of LOF, COF, BRE, etc.
[0027] FIG. 1 is a conceptual diagram of a job planner system according to some embodiments. In step 110, asset data associated with a number of scores are imported into a job planner engine 100 for evaluation. The example of asset data 102 shown is LOF, BRE, and LOF rank for multiple pipe segments. In step 112, the job planner engine is configured (some example configuration parameters 104 are shown) and the job planner engine is "run." In step 114, the result is a project 106. In step 116, the project 106 is added (if desired) to a project pool 108. In step 118, a plan is created and / or edited by adding and / or moving projects to / from the project pool. Shown is an example plan 120.
[0028] According to some embodiments, a user can manually edit the generated projects. For example, a user can add and / or remove piping segments to / from a project. A user can sort and filter projects by size and / or attributes in the project pool. For example, a user can sort projects by size and / or filter projects that contain piping made of cast iron. A user can download projects and plans in various formats, including equivalent formats such as csv, shapefile, or gpkg.
[0029] 2 is a schematic diagram illustrating some of the functionality and workflow of a job planner platform, according to some embodiments. The job planner workflow can be described in three main stages.
[0030] Stage 1 - Project Generation (210): Create individual projects based on the utility's risk management objectives. The specific steps at this stage are also included within diagram 200. This stage allows the user to create projects that are right-sized for the utility to more efficiently and effectively address potential business risks.
[0031] Stage 2 - View Project Pool (212): This stage allows the user to manage a group of projects before they are selected for a particular asset management program. The specific functionality of this stage is also encompassed within diagram 200. As a project repository, this stage provides a "parking" site for potential projects and allows the user to potentially refine individual projects before moving on to the next stage.
[0032] Stage 3 - Management Plan (214): The highest level of the Job Planner stages, this level allows the user to create individual asset management plans tailored towards specific goals. The specific functions at this stage are also contained within diagram 200. This stage provides the most flexibility in terms of analysis and control, allowing the user to simultaneously manage multiple plans, with different risk management objectives, without losing sight of the overall view of the utility and the detailed information from each project.
[0033] The following sections provide further details of the functionality provided at each stage within the Job Planner, according to several examples.
[0034] Stage 1 - Project Initiation This first stage is the foundation of Job Planner. As a bottom layer, it acts as a landing page for new users of Job Planner to generate projects and populate the empty project pool, i.e., add to the project pool.
[0035] FIG. 3 is a schematic diagram illustrating aspects of a user interface in a first project generation stage of a job planner according to some embodiments. This stage allows a user to define a project with minimal inputs that are relevant to the utility's specific objectives. A map section 310 of the interface shows relevant risk information and pipe information based on user preferences including LOF, COF, BRE and pipe attribute data. According to some embodiments, colors such as red, orange, yellow, light blue and dark blue can be used to indicate five different levels of risk information for various pipe segments in the map section 310. According to some embodiments, the color coding can be assigned according to a percentage of the pipe length. One example is as follows: The pipe length with the highest LOF is colored red; then between 3%-10% of the pipe lengths with the next higher LOF are colored orange; then between 10%-25% of the pipe lengths with the next higher LOF are colored yellow; then between 25%-50% of the pipe lengths with the next higher LOF are colored light blue; and 50% of the pipe lengths with the lowest LOF are colored dark blue.
[0036] According to some embodiments, there are four steps a utility planner can take to generate a new set of projects that can be added to a growing project pool: (1) defining the Planning Boundary, (2) defining the Planning Scope, (3) defining the Planning Criteria, and (4) defining the Project Size.
[0037] Step 1: Defining the planning boundaryIn section 312, the utility planner can define the planning boundary via a drawing tool or upload GIS information stored locally / online. The resulting planning boundary can be stored on the provider's server by its name, allowing the user to reuse it in the future, if desired. According to some embodiments, the user can also upload GIS information and identify areas to be included or excluded for generating projects. For example, the user may wish to upload GIS information for prioritizing future street paving projects for pipe replacement or restoration candidate areas; current street paving projects that have already been completed for a moratorium period that will not allow pipe projects for at least five years; and / or new development areas that require focused pipe replacement / upgrades based on risk mitigation considerations. According to some embodiments, custom risk profiles may be uploaded by the user.
[0038] Step 2: Define the scope of the plan In section 314, the user specifies the target amount of pipe to be included for the analysis. A pipeline planner at a water utility can choose to specify the pipe scope by the total length of pipe to be included in the analysis, or alternatively use a percentage of the total network. The two fields are linked together, so when the user makes a change in either one of these two fields, he / she understands what it means in terms of both the total length and the percentage of the total network.
[0039] Step 3: Define planning criteriaAccording to some embodiments, in section 316, the customer can utilize LOF and BRE information generated via existing machine learning algorithms. For further details on calculating and providing to the customer utility company, see the co-pending LOF application. If the user wants to focus on the probability of breaks to the pipe, the LOF can be used as a project selection criterion. Alternatively, if the user wants to use monetary business risk exposure to account for the criticality of the pipe segment, the BRE information can be selected instead.
[0040] According to some embodiments, users can use their own version of the risk analysis if desired, in which case the user can upload a shapefile or table containing customer risk criteria that can be linked to the cleaned piping network and select the customer risk criteria to generate the project.
[0041] Step 4: Define the project size Public utilities sometimes outsource plumbing work to third-party construction contractors with a specific project size in mind. The project needs to be neither too small nor too large to maximize the incentive to attract more bidders. A "mini" project that is too small is not optimal for contractors to bid on because it cannot cover the cost of manpower and equipment mobilization. Conversely, a project size that is too large may result in concentrated risk by limiting the number of contractors working with the utility. Therefore, it is important for utilities to be able to select optimally sized projects to reduce business risks.
[0042] In section 318, the user can define both the minimum and maximum length of the piping project. Additionally, if adjacent projects are chosen to be merged, a maximum gap can be defined by the utility. This merging functionality can also be accomplished at a later stage in the future.
[0043] Project results occur When the planner completes the above four steps in Stage 1, he / she can finally click on the "Run Job Planner" button 320 and see the result (new project) as shown in Figure 4. The Stage 1 Results page acts as a bridge between Stage 1 and Stage 2.
[0044] 4 is a schematic diagram illustrating a user interface displaying the generation of project results by a job planner according to some embodiments. A new project generated through stage 1 is shown in both a table section 410 and a map section 412. The background of the map section 412 can display different risk criteria defined by the user, such as LOF, COF, BRE, or piping attributes, to provide anchor points for the user analysis / assessment of the resulting project. According to some embodiments, as in the map section 310 of FIG. 3, colors such as red, orange, yellow, light blue, and dark blue can be used to indicate five different levels of risk information.
[0045] The user can select new projects from the results and add them to the project pool either from the table in section 420 or from the map section 412. The table section 420 can be automatically highlighted when the user makes a selection on the map section 412, and vice versa. In the illustrated example, project "PJ101" has been selected by the user (e.g., using a mouse click), and both the entry for PJ101 on the table section 420 and the PJ101 marker on the map section 412 are highlighted, e.g., in yellow.
[0046] If a particular user has used the job planner platform in the past, the project pool may display existing projects in both the table section 422 and the map section 412. According to some embodiments, different colors and / or symbols may be used to distinguish new projects from existing projects. When a newly generated project is added to the project pool, it is marked using a different color and / or symbol so that the user can easily identify the new project as a new member in the project pool. In this way, if the user later decides to remove such projects from the pool, it is easy to select such projects during this process.
[0047] Finally, the user can cancel or save the changes before exiting stage 1 and moving to other stages in the Job Planner. Existing project pools can be downloaded to the user's local computer for further analysis and refinement. According to some embodiments, the user can upload any type of GIS shapefile for boundary delineation.
[0048] Stage 2 - Project Pool ViewThis stage is where the utility planner manages potential project candidates for his asset management plan. The main functionality in this stage includes managing projects, viewing and / or editing project details, comparing projects, and merging / splitting projects. Adding a new project to the project pool is the starting point for a new user to use the Job Planner. This functionality is achieved through Stage 1, which, as described above, has a direct link to Stage 2 upon completion of Stage 1.
[0049] FIG. 5 is a diagram illustrating an example user interface displaying a table view of a project pool according to some embodiments.
[0050] project management Projects can be managed through a table view and a map view. Under the table view shown in FIG. 5, a summary of the project is given in rows, including project ID, pipe material, diameter and length, and risks associated with the project. Under the map view (not shown), the relative location of all projects in the project pool can be reviewed and inspected by the user. As in the map view in stage 1, the user can select background from various risk factors for pipe attributes as anchor points when evaluating the suitability of these project candidates. The user can also click on individual projects in the map to see the detailed information contained in the table view above.
[0051] Although some examples have been described in the context of projects in which piping segments are replaced according to some embodiments, other types of improvement projects can be included within the Job Planner platform. Examples of other types of projects that can be included within the Job Planner include, but are not limited to, pipe rehabilitation, pipe inspection, leak detection, and pipe condition assessment. In general, any invasive or non-invasive fieldwork related to piping asset management can form a project or part of a project. In the input section 510 of FIG. 5, the "Unit Cost" of the project can be set by the user. This unit cost should be entered by the user depending on the estimated cost for the type of project. This unit cost can also be entered or adjusted in the screens in FIGS. 7 and 8.
[0052] FIG. 6 is a diagram illustrating an example user interface displaying a more detailed view of a particular project in a project pool according to some embodiments.
[0053] View / Edit Project Details The user can have the opportunity to go deeper into the project details and inspect more information associated with a single project at the pipe segment level. Figure 6 shows a user interface sample of such a "Project Details" view. In addition to the project level information displayed in the project pool table and map view, the project details functionality allows the user to inspect individual pipe segments within a candidate project. Pipe attribute information and risk parameters from the project level can be evaluated separately for each pipe segment, so the user can have a clear idea of how each segment contributes to the cost and system risk reduction of the project.
[0054] According to some embodiments, the user is able to make certain changes to the project at the user's discretion independent of the pure risk analysis. During a typical planning period, a particular project selection is not tied solely to risk factors. Thus, allowing the user to edit a particular project by adding / removing certain sections of piping provides the necessary flexibility to create better and more realistic projects.
[0055] Comparing Projects Through either the Project Pool view or the Project Detail view, the user can open multiple windows to compare parameters of multiple projects. This functionality can also be provided in a single window.
[0056] Merge / split projects As explained in stage 1, users can combine projects based on their distance or split projects based on practical reasons.
[0057] According to some embodiments, the project pool and project summary information can be downloaded to a user's local computer for further analysis and refinement. According to some embodiments, a user can sort and filter projects in the pool by pipe attributes (material, age, diameter, etc.) and risk characteristics (LOF, COF, BRE), making it more convenient for users to identify projects targeting specific asset management objectives.
[0058] Stage 3 – Plan ManagementThis stage is where utility planners can create, manage, and modify their asset management plans aimed at business risk reduction and mitigation. Functionality at this stage includes managing plans, viewing and editing plans, comparing multiple plans, and merging / splitting plans. New users to Job Planner are required to create their first asset management plan by selecting a project from the project pool. Existing users who already have plans in the system can also create a plan by copying from an existing plan.
[0059] According to some embodiments, a user can easily compare the business risk exposure 610 to the project cost 612 on the interface shown in Figure 6 to ensure that the project is worthwhile. Note that the project cost 612 is closely related to the unit price, which can be entered or modified by the user in section 510 of Figures 5, 7 and 8.
[0060] 7 and 8 are diagrams illustrating a user interface displaying a map view and a table view for managing plans, according to some embodiments.
[0061] Plan Management Similar to managing project pools, users can manage existing plans via either a map view (e.g., FIG. 7) or a table view (e.g., FIG. 8). Users can select one or more plans to be displayed on the map or in the table. On the map view (FIG. 7), users can select a project on the map to view specific information about that plan. Projects belonging to different plans can be displayed with different colors and / or symbols.
[0062] Under the table view (FIG. 8), information such as project piping attribute information and risk information can be provided similar to that provided in the project pool stage. The plan management stage (e.g., in section 810) can provide a summary of the established plan under the table view. This summary gives the user information to the utility such as total risk reduction, risk reduction efficiency, project cost, and return on total capital to the decision maker.
[0063] In addition to the high-level overview, Section 810 can provide a more detailed analysis of the asset management plan, including statistical distributions of water main material, age, and diameter. This can allow utility planners to gain control over the unique objectives of their individual plans and to refine existing plans as new information becomes available.
[0064] Project costs associated with water main projects are flexible due to different types of actions, such as replacement, repair, proactive leak detection, or other types of physical condition assessment. The plan management stage allows users to update investment costs within the platform to accommodate different actions. Comparing these to monetary risk reduction measures helps utility planners make the best decisions to achieve service level objectives with the most efficiency in dollars and manpower.
[0065] View / Edit Plan Plans can be thought of as fundamentally different pools of projects that can be viewed and edited in the same way that a project pool is viewed and edited. For any particular plan, individual projects can be removed from or added to the plan from either the table view or the map view.
[0066] Compare PlansThe plan comparison functionality brings together information from multiple projects so users can identify similarities and differences across multiple plans based on pipe composition, risk factors, as well as project cost. Through the comparison, utilities can determine whether one plan can be used in place of another, or about improvements that can be made.
[0067] Combining / splitting plans Similar to the project merge / split feature described above, the plan merge / split functionality allows for merging between multiple plans to meet utility needs, and for splitting plans to allow for fewer projects within a plan to be possible in future product features.
[0068] Since each plan, like the project pool, carries several projects together, some of the functionalities provided in the project pool stage are shared with the plan management stage. These include viewing / editing projects and merging / splitting projects, thereby providing increased flexibility for users to work their analysis from the highest level to the lowest level. Plan and project summaries can be downloaded to the user's local computer for further analysis and refinement.
[0069] Further details of the search algorithm are described below. In general, the search algorithm includes: (1) pre-processing to narrow the search space, (2) running the search engine, (3) post-processing, and (4) generating the planned project. The following illustrates various aspects of how the job planner generates a project. The search algorithm is described when the target asset is a water pipe, and the pipe connections have already been calculated and are known.
[0070] Pre-processingThe purpose of pre-processing is primarily to narrow the search space for faster processing. According to some embodiments, pre-processing can include: (1) merging short pipes into longer pipes, (2) eliminating groups of pipes that are not worth searching, (3) eliminating end pipe segments with low scores, and (4) merging pipes with similar scores.
[0071] 9A and 9B are schematic diagrams illustrating the merging of shorter pipe segments to form longer pipe segments to speed up the job plan search process, according to some embodiments. In the illustrated example, the pipes with pipe IDs 1, 2, 3, and 4 are relatively short. When they are merged, they are replaced by a single long pipe segment (pipe ID 100001). This simplification simplifies the asset link data (from four lines to one line). Thus, the search space is downsized. Pipe attributes such as material, installation year, diameter, etc. can be considered when merging pipes. For example, the algorithm may select to merge pipes only if all of the attributes are almost or exactly the same. It should be noted that the score for the new pipe segment should be recalculated.
[0072] Further pre-processing can include finding and eliminating groups of pipe segments that are not worth searching. If pipe segments are surrounded by pipe segments with very low scores, these pipe segments can be removed from the search space with or without the surrounding pipe segments. The threshold can be predefined or dynamically calculated. An example of a dynamic threshold is the "average score / 4", "median score / 4", or the score of the pipes that are in the lowest N%.
[0073] Another pre-processing technique can include discarding pipe segments with low scores if they are not connected to multiple pipes. That is, a pipe segment can be eliminated if it is an end of a pipe network and has a relatively low score. According to some embodiments, a predefined threshold of the score or a dynamically calculated threshold of the score can be used. As mentioned above, examples include "average score / 4", "median score / 4", or the score of the pipes that are in the lowest N%.
[0074] Another pre-processing technique can include merging a pipe with other pipes that have similar scores. For example, pipe A has LOF=0.01 and pipe B has LOF=0.0102. If the threshold is 0.001 and pipe A and pipe B are connected, they can actually be merged and treated as a single pipe segment. However, if pipe A has LOF=0.01 and pipe B has LOF=0.02, they will not be merged because the difference in their scores is greater than the pre-defined threshold. The threshold can be a pre-defined fixed value or can be dynamically calculated. One example of dynamically calculating the threshold is (1) sorting all pipes by score, (2) calculating the difference between the nearest neighbor pipes (e.g., 1st vs. 2nd, 2nd vs. 3rd, 3rd vs. 4th, etc.), (3) calculating the average of those differences, and (4) setting the threshold to the average / N. Similar to the pre-processing of merging short pipes described above, pipe attributes can be taken into consideration when merging, and the score of the merged pipes should be recalculated.
[0075] LOF and BRE are often used for asset condition assessment and job planning. However, this information may not be sufficient for effective asset management (e.g., when making decisions about which pipes to replace). For example, pipes can be ranked from 1 to 5, with "5" representing the highest LOF and "1" representing the lowest LOF. A single rank 5 segment, having a high probability of damage, may be found surrounded by rank 1 pipes, having a low probability of damage. Most water utilities do not replace single segments, but rather replace entire areas or blocks of pipes. To assist utilities in asset management, computational search algorithms to find groups of assets with high combined scores of LOF, BRE, etc. have proven extremely useful.
[0076] 10(A)-(C) show three different possible pipe replacement jobs under consideration according to some embodiments. si ) is the probability that one pipe breaks, and Π(1-P si )=(1-P si )(1-P si )...(1-P si ) is the probability that no pipe breaks, and P si =1-(1-P Li ) li is the LOF / i-th pipe segment, and P Li where LOF / length of the i-th pipe segment, and li is the length of the i-th pipe segment. In Figure 10(A), LOF / construction is 0.87, in Figure 10(B), LOF / construction is 0.92, and in Figure 13(C), LOF / construction is 0.95. In this example, the job in Figure 10(C) is the highest priority job of the three.
[0077] 11(A)-(C) are schematic diagrams illustrating aspects of a scheme for a search algorithm for job planning, according to some embodiments. A job planner search engine scans all or a subset of the pipes. In FIG. 11(A), the engine starts with each pipe segment (e.g., "1") and recursively searches all or a subset of each linked pipe segment. The process continues until the project length is greater than a predefined threshold (in FIG. 11(A), after adding the third segment "4-1", the proposed project is "long enough"). FIG. 11(B) shows the case where the result of the current branch is initially not long enough (even after adding segment "3-1", the project is "not long enough"). In this case, the job planner engine searches another branch (adding "2-2") and repeats the process. FIG. 11(C) shows the case where the pipe segment to be added ("4-1") is longer than the threshold ("too long"), the pipe segment is discarded and the job planner moves on to another branch.
[0078] The job planner engine may also stop the search based on other criteria. During the search, the job planner engine recursively calculates a score for the project each time a pipe segment is added to the project being processed. Examples of "scores" include LOF[%], LOF Score, BRE[$], BRE Score, LOF Rank, and BRE Rank, although other quantities may be used. Depending on the score quantity used, the score for the project may be calculated differently.
[0079] For example, when using LOF[%], the job planner can use the following formula:
[0080]
number
[0081] N is the number of pipes included in the project and LOF i is the LOF of the i-th pipe in the project. As another example, when using the BRE score, the job planner can use:
[0082]
number
[0083] N is the number of pipes included in the project and BRE i is the BRE of the i-th pipe in the project. As mentioned above, the scores used and the formula for calculating the scores for a project should be flexible and can be customized by the user.
[0084] Caching Algorithms Due to its relatively large search space, the calculation time of the job planner engine can be very long. As mentioned above, pre-processing can be used to reduce the search space. According to some embodiments, a cache system can be used to reduce the calculation time. In essence, a cache system reuses previously calculated results.
[0085] 12A and 12B are schematic diagrams illustrating aspects of a caching algorithm for a job planning engine according to some embodiments. Each link has a cache container and caches previous results of a search. The container caches data as follows: the longest next subproject of the link if the other next subprojects are shorter or longer than a certain threshold. In FIG. 12A, subproject 1210 is cached in cache container 1200. If there are more subprojects that meet the threshold criteria, the "best subproject" is cached. This "best" could be, for example, the subproject with the highest LOF / subproject. In FIG. 12A, there are two subprojects 1222 and 1224 that meet the threshold criteria. Subproject 1222 is deemed better than subproject 1224 by some criteria (e.g., highest LOF), and therefore subproject 1222 is stored in cache register 1202. In Figure 12(B), a subsequent search is performed for pipe segment "1." As indicated by the "Start" box, two cache containers 1200 and 1202 are accessed and project 1230 is quickly generated from the previously cached subprojects.
[0086] Post-processing The goal of post-processing is roughly to move the suboptimal results closer to the global optimum. It is not practical to search all possible combinations. Therefore, the search space should be narrowed somehow (as described above for pre-processing). Furthermore, the search algorithm can be designed to perform a completely perfect search (e.g., if several pipe segments with consecutive low scores in a certain direction are detected, the search in the given direction is stopped in favor of a new direction). Thus, the search algorithm can be said to be an approximately search for the best project.
[0087] As a result, the usual output from the job planner is a "locally optimal (suboptimal)" result, not a "globally optimal" result. Because of the suboptimal result, the job planner sometimes outputs a counter-intuitive result.
[0088] Below are two examples of such results. In the first example, the resulting project is connected to a pipe with a high score. In the second example, the resulting project is next to another resulting project. The reason why such results are obtained is because the job planner accidentally decided to stop the search or change direction before adding the pipe in a sequential complex calculation.
[0089] FIG. 13 is a schematic diagram illustrating an example of a resulting project connected to a pipe with a high score. The resulting project 1310 is connected to a pipe segment 1320 with a high score (LOF score=5). It can be seen that the job planner found the suboptimal project because the search was terminated due to time constraints. Obviously, the pipe 1320 with the next highest LOF after project 1310 can be merged into the planned project. To avoid missing such pipes, the job planner can be configured to check for such pipes and add them to the project if found. According to some embodiments, the job planner can use two types of criteria when deciding whether to add a pipe, which checks one or both of the following: (1) whether the score of the pipe is greater than a predefined or dynamically calculated threshold, and (2) whether the normalized score of the project (normalized with respect to the project's dimensions such as LOF / project length) is not decreased by adding the pipe.
[0090] 14 is a schematic diagram illustrating an example of a resulting project next to another resulting project, where a resulting project 1410 is connected to another resulting project 1412. According to some embodiments, this can be solved by automatically merging these two projects 1410 and 1412, unless the total length of the merged project is larger than the maximum allowable dimension set by the user.
[0091] According to some embodiments, the three steps (Step 1-Pre-processing, Step 2-Search engine run, and Step 3-Post-processing) can be run twice to improve the final result. The difference between the first run and the second run is that the second run is run without the plumbing included in the project generated in the first run. As mentioned above, the job planner may sometimes generate suboptimal results. It has been found that the second run contributes to the job planner generating a more perfect search result. According to some embodiments, the job planner can equally compare the results of the first run and the second run and generate the final result.
[0092] According to some embodiments, the systems and methods described herein may be applied to assets other than potable water supplies, such as pipes for delivering other fluids, such as wastewater, recycled water, brackish water, storm water, seawater, steam, compressed air, oil, and natural gas, etc. According to some embodiments, the systems and methods described herein may be applied to networks of fiber cables, wires, and utility poles.
[0093] Although the above has been described in some detail for the purpose of clarity, it is clear that certain changes and modifications can be made without departing from the principles thereof. It should be noted that there are many alternative ways of implementing both the process and the apparatus described herein. Thus, the present embodiment should be considered as illustrative rather than restrictive, and the subject matter described herein should not be limited to the details given herein, which details can be modified and equivalent within the scope of the claims.
Claims
1. A method for planning a project for improving a network of interconnected and managed assets, implemented by a computer system, comprising: receiving a calculated damage risk value for each of a plurality of the managed assets, the damage risk value being selected from a range including at least ten different values; and searching through said plurality of assets and generating a plurality of potential improvement projects; each of the potential improvement projects includes a plurality of the interconnected managed assets, and generating the potential improvement projects is based at least in part on the damage risk value of each of the managed assets included within the potential improvement projects; The method further comprising: pre-processing the plurality of assets to generate a reduced set of the plurality of assets; and the search comprising searching through the reduced set.
2. 2. The method of claim 1, wherein said failure risk value comprises a value representing a probability of failure.
3. 3. The method of claim 2, wherein said value representing the probability of failure is a percentage probability of failure.
4. 2. The method of claim 1, wherein the failure risk value comprises a value representative of a failure outcome.
5. 2. The method of claim 1, wherein the corruption risk value comprises a value representing a business risk exposure.
6. 2. The method of claim 1, wherein the pre-processing includes one or more selected from the group consisting of: combining shorter assets into longer assets; eliminating groups of assets not worth searching; eliminating assets that have only a single interconnect and have low damage risk values; and combining assets that have similar damage risk values.
7. A method for planning a project for improving a network of interconnected and managed assets, implemented by a computer system, comprising: receiving a calculated damage risk value for each of a plurality of the managed assets, the damage risk value being selected from a range including at least ten different values; and searching through the plurality of assets and generating a plurality of potential improvement projects, each of the potential improvement projects including a plurality of the interconnected managed assets, generating the potential improvement projects based at least in part on the damage risk value of each of the managed assets included within the potential improvement projects; The method further includes post-processing the plurality of potential improvement projects to add to at least one of the potential projects a managed asset that is connected to the plurality of interconnected managed assets of the potential project.
8. 8. The method of claim 7, wherein the adding is based on the damage risk value of the managed asset to be added and / or based on whether the combined damage risk value of the potential improvement projects is increased or decreased by adding the managed asset.
9. A method for planning a project for improving a network of interconnected and managed assets, implemented by a computer system, comprising: receiving a calculated damage risk value for each of a plurality of the managed assets, the damage risk value being selected from a range including at least ten different values; and searching through the plurality of assets and generating a plurality of potential improvement projects, each of the potential improvement projects including a plurality of the interconnected managed assets, generating the potential improvement projects based at least in part on the damage risk value of each of the managed assets included within the potential improvement projects; The method further includes post-processing the plurality of potential improvement projects to combine two or more potential improvement projects into a single potential improvement project.
10. The method of claim 1 , wherein the interconnected managed assets are linear segments.
11. 11. The method of claim 10, wherein the straight segment is a pipe segment and the potential improvement project is a potential pipe replacement project.
12. 11. The method of claim 10, wherein the linear segment is a pipe segment and the potential improvement projects include one or more types selected from the group consisting of pipe replacement, pipe repair, pipe inspection, leak detection, and pipe condition assessment.
13. 13. The method of claim 12, wherein the piping segments form a network for delivering water to consumers.
14. 13. The method of claim 12, wherein the piping segment is configured to deliver a type of fluid selected from the group consisting of fresh water, wastewater, recycled water, brackish water, storm water, sea water, potable water, steam, compressed air, oil, and natural gas.
15. further displaying the plurality of potential improvement projects on a graphical user interface; and receiving selections or modifications from a user for one or more of the potential improvement projects; 2. The method of claim 1, comprising:
16. further displaying potential improvement project plans on the graphical user interface, each of the potential improvement projects including one or more potential improvement projects; and receiving a selection from a user to one or more selected from the group consisting of: editing the potential improved project plans, comparing the potential improved project plans, merging the potential improved project plans, and splitting the potential improved project plans; 2. The method of claim 1, comprising:
17. 16. The method of claim 15, wherein the display comprises a map view.
18. 17. The method of claim 16, wherein the display comprises a table view.
19. 1. A system for planning a project to improve a network of interconnected managed assets, comprising: a database storing calculated damage risk values for each of a plurality of the managed assets, the damage risk values being selected from a range encompassing at least ten different values; and a processing system configured to automatically search through the plurality of assets and generate a plurality of potential improvement projects; each of the potential improvement projects involving a plurality of the interconnected managed assets, and the occurrence of the potential improvement projects is based at least in part on the damage risk value of each of the managed assets involved within the potential improvement projects; The processing system is further configured to pre-process the plurality of potential improvement projects to coalesce two or more potential improvement projects into a single potential improvement project.
20. 20. The system of claim 19, wherein the failure risk value comprises a value representing a failure probability, a failure consequence, or a business risk exposure.
21. 20. The system of claim 19, wherein the failure risk value comprises a value representing a probability of failure expressed as a percentage value.
22. 20. The system of claim 19, wherein the interconnected and managed assets are linear pipe segments forming a network that supplies water to consumers and the potential improvement projects are potential pipe replacement projects.
23. 20. The system of claim 19, wherein the interconnected and managed assets are piping segments configured to deliver a type of fluid selected from the group consisting of fresh water, wastewater, recycled water, brackish water, storm water, sea water, potable water, steam, compressed air, oil, and natural gas.
Citation Information
Patent Citations
Project management integration support system
JP2004310563A
Management system for public-work project budget management
JP2009271742A
Risk management support system for water supply infrastructure
JP2010108307A
System and method for supporting conduit line renewal planning
JP2016033808A
System to manage maintenance of a pipeline structure, program product, and related methods
US20070083398A1