Construction work management system and construction work management method
The construction work management system uses three-dimensional point cloud data to efficiently and reliably manage work progress at construction sites, reducing complexity and improving traceability through data comparison and display of progress locations.
Patent Information
- Application Number
- JP2020057528
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2020-03-27
- Publication Date
- 2024-09-24
- Estimated Expiration
- 2040-03-27
AI Technical Summary
Managing work progress at large construction sites is complex and burdensome, leading to potential delays and errors, especially as the scale of the project increases.
A construction work management system utilizing three-dimensional point cloud data acquired by a laser scanner to compare with reference data, estimating work progress through a data comparison unit, and displaying progress locations for efficient and reliable management.
Enhances the efficiency and reliability of work progress management at construction sites by reducing worker burden, improving traceability, and enabling precise monitoring of work completion and schedule adherence.
Smart Images

Figure 0007555195000003 
Figure 0007555195000002 
Figure 0007555195000004
Abstract
Description
[Technical field]
[0001] The present invention relates to a construction work management system and a construction work management method for managing the progress of work at a construction site. [Background technology]
[0002] Conventionally, technologies have been developed for acquiring point cloud data of a construction site using a laser scanner or the like and managing the progress of work at the construction site. For example, the following Patent Document 1 is a technology related to a construction management system for construction work, in which an image capture unit acquires the three-dimensional coordinates of the surface of a construction component as three-dimensional point cloud data from a stereo camera, a storage unit stores the design three-dimensional coordinates of the surface of the construction component, and a processing unit sets faces A and B that face each other across a solid area including the three-dimensional coordinates stored in the storage unit.The processing unit then judges whether a construction component has been installed or not based on the amount of three-dimensional point cloud data that exists in the area between faces A and B. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2015-232203 A Summary of the Invention [Problem to be solved by the invention]
[0004] Various tasks are carried out on a daily basis at construction sites, and managing the progress of work is important to prevent delays in construction schedules and work errors. However, the larger the construction object, the more complicated it becomes to manage the progress of work, which places a heavy burden on the work manager. The present invention has been made in consideration of the above circumstances, and an object of the present invention is to more efficiently and reliably manage the progress of work at a construction site. [Means for solving the problem]
[0005] In order to achieve the above-mentioned object, the construction work management system of the present invention is a construction work management system that manages work progress at a construction site, and is characterized by comprising a point cloud data acquisition unit that acquires three-dimensional point cloud data of the construction site acquired by a laser scanner, a data comparison unit that compares the three-dimensional point cloud data with predetermined reference data, and a work progress estimation unit that estimates the work progress status at the construction site based on the comparison result by the data comparison unit. The construction work management method of the present invention is a construction work management method for managing work progress at a construction site, and is characterized by including a point cloud data acquisition process for acquiring 3D point cloud data of the construction site by a laser scanner, a data comparison process for comparing the 3D point cloud data with predetermined reference data, and a work progress estimation process for estimating the progress of work at the construction site based on the comparison result in the data comparison process. Effect of the Invention
[0006] According to the present invention, the progress of work at a construction site can be managed more efficiently and reliably. [Brief description of the drawings]
[0007] [Figure 1] 1 is a diagram showing a schematic configuration of a construction work management system according to an embodiment; [Diagram 2] FIG. 2 is a block diagram showing the functional configuration of a construction work management system. [Diagram 3] FIG. 4 is a diagram showing a flow of work progress management in the first embodiment. [Figure 4] FIG. 11 is a diagram showing a flow of work progress management in the second embodiment. [Diagram 5] FIG. 11 is a diagram showing a flow of work progress management in the third embodiment. [Figure 6] FIG. 13 is a diagram showing a flow of work progress management in the fourth embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0008] DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of a construction work management system and a construction work management method according to the present invention will be described in detail below with reference to the accompanying drawings.
[0009] (Embodiment 1) FIG. 1 is a diagram illustrating a schematic configuration of a construction work management system according to an embodiment. The construction work management system 10 manages the progress of work at a construction site. The construction site may be an architectural construction site such as a building, an apartment building, or a warehouse, or may be a civil engineering construction site such as a dam, a bridge, or a tunnel. The construction work management system 10 includes a computer 12 that functions as a work progress management device, an automatic patrol vehicle 14 (14A, 14B), and a portable information processing terminal 16 (16A, 16B).
[0010] The computer 12 includes a CPU, a ROM for storing and recording control programs and the like, a RAM as an operating area for the control programs, an EEPROM for rewritably storing various data, and an interface section for interfacing with peripheral circuits and the like. The computer 12 may be installed near the construction site, for example in the construction site's management building, or it may be installed at a location away from the construction site, such as the office of the company undertaking the construction work or a data center operated by a cloud service provider. In FIG. 1, the computer 12 is illustrated as a desktop personal computer, but it may be a notebook computer or a tablet terminal, similar to the portable information processing terminal 16 described later.
[0011] The automatic patrol vehicle 14 (14A, 14B) is equipped with a laser scanner 18 and automatically patrols the construction site. The automatic patrol vehicle 14 has a preset patrol route for patrolling the construction site, and while checking its current location using a beacon or GPS installed in the construction site, it scans the surroundings with the laser scanner 18 at a predetermined scanning point and acquires point cloud data within the construction site.
[0012] 1 illustrates a drone 14A and a cart robot 14B as an example of the automatic patrol vehicle 14, but any conventionally known device capable of moving autonomously can be used as the automatic patrol vehicle 14. For example, the drone 14A may be used at a construction site where high-altitude work is frequently performed (or at a portion of the construction site where high-altitude work is performed), and the cart robot 14B may be used at other sites.
[0013] The laser scanner 18 (3D laser scanner) radially irradiates the measurement object with a laser, and obtains the 3D coordinates of the surface shape of the measurement object based on the distance to the measurement object and the irradiation angle calculated from the laser reflection time. Although it depends on the performance of the laser scanner 18, it can perform non-contact measurement at a speed of tens of thousands of points per second, and obtain high-density planar point cloud data. In addition, an image can be taken at the measurement location using a camera built into the laser scanner 18, and the point cloud data can be colored according to the color of the image and the laser reflection intensity (the degree of laser reflection changes depending on the material and color of the object being measured). In addition, even when measuring the back of a target or a wide area that cannot be measured from a single location, it is possible to combine multiple scan data by using targets as common points, or to assign coordinates.
[0014] In this embodiment, the automatic patrol vehicle 14 automatically patrols the construction site and acquires point cloud data of each part of the construction site, but this is not limited to the above. For example, a worker at the construction site may carry a laser scanner 18 and patrol the construction site, perform scanning work at specified points, and acquire point cloud data of each part of the construction site. In addition, instead of having the drone 14A and the cart robot 14B patrol automatically, the patrol and scanning operations may be performed by remote control.
[0015] The portable information processing terminal 16 is a small information processing terminal carried by workers and managers at the construction site, employees of the construction contractor, etc. The portable information processing terminal 16 is provided with a display 160, which can display and output various information described below. The portable information processing terminal 16 also has a speaker and vibration function (not shown), and can sound an alert when instructed by the computer 12.
[0016] In this embodiment, the portable information processing terminal 16 means an information processing terminal different from the computer 12 that functions as a work progress management device, and does not necessarily have to be portable. For example, in Fig. 1, a tablet terminal 16A and a notebook computer 16B are illustrated as examples of the portable information processing terminal 16, but the functions of the portable information processing terminal 16 may be executed by a desktop personal computer installed in a different location from the computer 12.
[0017] FIG. 2 is a block diagram showing the functional configuration of the construction work management system, and in particular shows the functional configuration of the computer 12. The computer 12 functions as a point cloud data acquisition unit 120, a data comparison unit 122, a work progress estimation unit 124, a work progress location display unit 126, and a work management unit 128 as a result of the CPU executing the control program. Furthermore, the reference data D is stored in the EEPROM, which is a storage area (storage) of the computer 12. The storage location of the reference data D is not limited to within the computer 12, and may be an external storage accessible by the computer 12, or the like. Furthermore, the storage area of the computer 12 stores three-dimensional point cloud data, work schedule data, work progress data, and the like, which will be described later.
[0018] The point cloud data acquisition unit 120 acquires three-dimensional point cloud data of the construction site acquired by the laser scanner 18. In this embodiment, the point cloud data acquisition unit 120 acquires the three-dimensional point cloud data of the construction site by reading out the three-dimensional point cloud data acquired by the laser scanner 18 during the automatic patrol of the automatic patrol vehicle 14 from the memory of the laser scanner 18 or by transmitting the data from the laser scanner 18. The acquired three-dimensional point cloud data is stored in the memory area of the computer 12 and is used for various processes described below.
[0019] The data comparison unit 122 compares the three-dimensional point cloud data acquired by the point cloud data acquisition unit 120 with predetermined reference data D. In this embodiment, the reference data D is the three-dimensional point cloud data acquired previously. The "three-dimensional point cloud data acquired previously" will be described. The automatic patrol vehicle 14 automatically patrols at predetermined intervals during the work period at the construction site, and acquires three-dimensional point cloud data with the laser scanner 18 each time. The predetermined intervals may be, for example, once a day or once a week. For example, when acquiring three-dimensional point cloud data once a day, the data comparison unit 122 compares the three-dimensional point cloud data acquired today with the three-dimensional point cloud data acquired yesterday (reference data). Also, when acquiring three-dimensional point cloud data once a week, the data comparison unit 122 compares the three-dimensional point cloud data acquired this week with the three-dimensional point cloud data acquired last week (reference data).
[0020] The work progress estimation unit 124 estimates the work progress at the construction site based on the comparison result by the data comparison unit 122. In this embodiment, since the reference data D is the previously acquired three-dimensional point cloud data, the work progress estimation unit 124 extracts the difference between the previously acquired three-dimensional point cloud data and the currently acquired three-dimensional point cloud data as the work progress location from the previous time to the current time. More specifically, the work progress estimation unit 124 compares 3D point cloud data corresponding to the same area on the construction site and detects point clouds that are differences based on whether there are corresponding points within a certain distance (threshold). These differences correspond to areas that have changed due to work performed since the previous acquisition of 3D point cloud data, i.e., work progress areas. Examples of areas where differences may occur include areas where new components have been added (such as when an interior wall has been added to a floor), areas where components have been removed (such as when work using scaffolding is completed and the scaffolding is removed), and areas where components have been changed.
[0021] The work progress location display unit 126 displays the work progress locations extracted by the work progress estimation unit 124 in an identifiable manner on the 3D point cloud data or the image of the construction site displayed on the display. The display is the display 160 of the portable information processing terminal 16 or the display 12A of the computer 12 (see FIG. 1). For example, when displaying point cloud data on a display, the point cloud corresponding to the difference between the currently acquired point cloud data and the previously acquired point cloud data is displayed in a different color from the other point clouds, making it possible to identify areas where work progress is being made. Furthermore, for example, when image data (image data captured by a camera when acquiring point cloud data) is displayed on a display, the areas where work progress is being made can be identified by marking the areas in the image data (for example, by displaying lines showing the outline of the areas where work progress is being made). The display form of the work progress location display unit 126 is not limited to the above, and any form may be used as long as the worker or the like can specify the work progress location.
[0022] By checking the display, workers and managers at the construction site can understand the progress of work compared to the previous time.In addition, even if they are away from the construction site, they can check the status of the construction site and the progress of work one by one. In addition, the point cloud data and images stored in the memory area can be displayed on a display as appropriate at the instruction of a worker, etc. At this time, for example, the progress of each floor of a building or each management section can be displayed in different colors, and it is also possible to specify any date and check the work progress going back in time.
[0023] The work management unit 128 manages the progress of work at the construction site. The work management unit 128 receives input of the date of the day and the work content performed from, for example, the work manager of the construction site (or a worker or an employee of the business operator undertaking the construction work), and records this as work progress data. The work manager can input the work performed while referring to the work progress location displayed by the work progress location display unit 126, and can confirm that the work has been performed without having to personally patrol. In addition, the work status can be checked retroactively, improving traceability at the construction site.
[0024] FIG. 3 is a diagram showing a flow of work progress management in the first embodiment. First, the automatic patrol vehicle 14 patrols the construction site, scans the surroundings with the laser scanner 18, and acquires point cloud data within the construction site (S300). As described above, this step may be performed by a worker or the like patrolling the construction site with the laser scanner 18, instead of automatic patrol. Next, the point cloud data acquisition unit 120 of the computer 12 (work progress management device) reads the point cloud data acquired by the laser scanner 18, and acquires the point cloud data from the current scan (hereinafter referred to as "current scan data") and image data (step S302: point cloud data acquisition process). Thereafter, noise is removed from the point cloud data as necessary (step S304). The noise may be removed automatically by an application of the computer 12, or manually by an operator.
[0025] Next, the data comparison unit 122 compares the current scan data with the point cloud data from the previous scan (hereinafter referred to as "previous scan data") (step S306: data comparison process), and the work progress estimation unit 124 extracts parts with differences as work progress points (step S307: work progress point extraction process). Then, the work progress area display unit 126 displays the current scan data or the image captured during the current scan on the display, and also displays and marks the work progress area so that it is identifiable (step S308: work progress area display step). The work manager checks the work progress displayed on the display (step S310) and inputs the work details (step S312). The work management unit 128 stores the work content input by the work manager together with the date in the work progress data, and updates the work progress data (step S314).
[0026] As described above, according to the construction work management system 10 of the first embodiment, the work progress state at the construction site is estimated using the 3D point cloud data of the construction site, which is advantageous in reducing the burden on workers and in more reliably grasping the work progress at the construction site compared to workers checking the work progress state visually, etc. Furthermore, since the work progress state is recorded as 3D point cloud data, the work status at the construction site can be left as objective data, which is advantageous in improving the traceability of the construction site. Furthermore, by using the previously acquired 3D point cloud data as reference data as in this embodiment, it is possible to identify areas where work progress has occurred between the previous scan and the current scan, which is advantageous for more detailed management of daily work progress. Furthermore, if the location of work progress is displayed identifiably on the display as in this embodiment, it is advantageous for understanding the progress of work at the construction site in more detail. Furthermore, acquiring 3D point cloud data using the automatic patrol vehicle 14 as in this embodiment is advantageous in reducing the burden on workers and improving the efficiency of construction work compared to workers patrolling the construction site and scanning it.
[0027] (Embodiment 2) In the first embodiment, the work management unit 128 stores the work progress input by the worker as work progress data. In the second embodiment, the function of the work management unit 128 is further enhanced to compare the work progress at the construction site with a predetermined work schedule at the construction site and estimate the construction period required until the work reaches a predetermined stage. The predetermined stage can be arbitrarily determined, for example, "the stage when all work at the construction site is completed" or "the stage when work on a specific floor of a multi-story building is completed."
[0028] In addition, with regard to the configuration of the construction work management system in the second embodiment, the explanation of the points similar to those in the first embodiment will be omitted.
[0029] In the second embodiment, the work management unit 128 can refer to work schedule data. The work schedule data includes a date and the work content scheduled to be performed on that date. The work schedule data is created in advance, for example, by a contractor who undertakes construction work. When creating the work schedule data, for example, the standard labor rate for each task and the number of workers scheduled to be engaged in the task are referenced.
[0030] When the work management unit 128 receives the work progress data (see step S312 in FIG. 3), it compares the work progress data with the work schedule data. If there is no difference between the work schedule data and the work progress data, that is, if the work is progressing as planned, the work management unit 128 estimates the required work period to be the date until the work is completed on the work schedule data. Also, if there is a difference between the work schedule data and the work progress data, i.e., if the work progress is slower or faster than planned, the required construction period is estimated by, for example, adding the number of days required for the remaining work to the current date. At this time, for example, the standard labor rate and the number of days actually required for the work may be compared, and if similar work is scheduled to be performed in the future, the construction period may be estimated based on the number of days actually required for the work.
[0031] FIG. 4 is a diagram showing a flow of work progress management in the second embodiment. Steps S400 to S414 are similar to the flow of the first embodiment described with reference to FIG. 3, and therefore description thereof will be omitted. After step S414, the work management unit 128 compares the updated work progress data (latest work progress data) with the work schedule data, and estimates the required construction period (step 416). When the work management unit 128 notifies the work manager of the required construction period (step S418), the work manager checks the required construction period, and if it is as planned (or the error is within the allowable range), he / she confirms it and ends the flow (step S420). If the error in the required construction period is outside the allowable range, the work manager considers changing the work schedule (step S420), and if the work schedule is changed, the work manager reflects the change in the work schedule data on the work management device (step S422).
[0032] As described above, in the second embodiment, the required construction period until the work is completed is estimated based on the point cloud data of the construction site and the predetermined work schedule. This makes it possible to appropriately review the work schedule even during the work, thereby improving the efficiency at the construction site. Specifically, for example, it can be used to detect construction delays early, and can be used to consider the number of additional personnel needed to make up for delays, or as evidence for price negotiations with the construction work client.
[0033] (Embodiment 3) In the first and second embodiments, the previous scan data (point cloud data) is used as the reference data. In the third embodiment, three-dimensional design data of a construction object is used as the reference data. In this embodiment, a case will be described in which a Building Information Modeling (BIM) model is used as the three-dimensional design data. In BIM, a building database that adds attribute data such as cost, finish, and management information to a 3D digital model of a building created on a computer is utilized in each phase of construction work. A BIM model is a collection of objects, and building material parts can include dimensions such as width, depth, and height, as well as materials and assembly processes (time). In this embodiment, by using a BIM model as reference data, the work procedures at the construction site can be included in the reference data.
[0034] In addition, with regard to the configuration of the construction work management system in the third embodiment, explanation of the points similar to those in the first and second embodiments will be omitted.
[0035] In the third embodiment, the data comparison unit 122 compares the three-dimensional point cloud data acquired by the point cloud data acquisition unit 120 with a BIM model (three-dimensional design data of a construction object). The 3D point cloud data may contain objects that are not included in the BIM model, such as construction equipment used in the work, temporary handrails and scaffolding, temporary materials, etc. The point clouds corresponding to these objects are removed, for example, by noise removal processing (such as step S504 in FIG. 5). In addition, the coordinate systems (origin, scale, direction) of the point cloud data and the BIM model are matched in advance.
[0036] The work progress estimation unit 124 extracts the difference between the BIM model and the 3D point cloud data. Since the BIM model includes all the components that constitute the construction object, even when compared with the 3D point cloud data during construction, there are components corresponding to each point. For example, when the point cloud data obtained by scanning a wall with exposed core material is compared with the BIM model, the position of the core material scanned as the point cloud and the position of the core material on the BIM model are approximately the same. Therefore, the work progress estimation unit 124 compares the 3D point cloud data corresponding to the same area on the construction site with the BIM model, and determines whether there is a component whose surface is located within a certain distance (threshold value) from the position corresponding to each point of the 3D point cloud data.
[0037] If there are no differences between the 3D point cloud data and the BIM model, it can be assumed that work is proceeding as designed. On the other hand, if there is a difference between the BIM model and the 3D point cloud data, it is possible that the work is not proceeding as designed. Possible causes in this case include, for example, work errors (such as incorrect component installation positions or component model numbers), BIM model errors (such as errors in the design structure or component specification), and system errors (such as misalignment of coordinates between the 3D point cloud data and the BIM model). The cause of the error is identified, for example, by the work manager or the creator of the BIM model.
[0038] The work progress area display unit 126 functions as a difference area display unit that displays the areas where differences have been extracted by the work progress estimation unit 124 in an identifiable manner on the 3D point cloud data or BIM model displayed on the display, or on the image captured during the current scan. Specifically, models (line segments) based on 3D point cloud data are displayed on the BIM model, and point clouds where there are differences in the 3D point cloud data are displayed in a different color from the other point clouds. By clearly displaying the areas where there are differences in this way, it is possible to assist work managers, BIM model creators, and others in identifying the causes of errors.
[0039] FIG. 5 is a diagram showing a flow of work progress management in the third embodiment. Steps S500 to S504 are similar to the flow of the first embodiment described with reference to FIG. 3, and therefore description thereof will be omitted. After step S504, the data comparison unit 122 compares the current scan data with the BIM model (step S506: data comparison process), and the work progress estimation unit 124 extracts the difference between the current scan data and the BIM model (work progress estimation process). If there is no difference (step S508: No), this flow ends. On the other hand, if there are differences (for example, if a component that exists in the point cloud data is not on the BIM model) (step S508: Yes), the work manager or the like is notified of this (step S510). At this time, the difference location display unit displays the current scan data BIM model or the image captured during the current scan on the display, and also displays the locations where differences were detected in an identifiable manner. The work manager or the like checks the difference displayed on the display and identifies the cause of the difference (step S512). After that, the person in charge responds according to the identified cause. For example, if there is a change in the BIM model, the change is also reflected in the BIM model stored in the work management device (step S514).
[0040] As described above, in the third embodiment, a BIM model (three-dimensional design data of a construction object) is used as reference data, and the difference between the BIM model and the three-dimensional point cloud data is extracted. This is advantageous in checking whether work at a construction site is progressing as designed. In addition, by making the differences between the BIM model and the 3D point cloud data clearly visible on the screen, it becomes possible to gain a more detailed understanding of the progress of work at the construction site.
[0041] (Embodiment 4) In the fourth embodiment, a case will be described in which construction schedule management at a construction site is performed using three-dimensional point cloud data and a BIM model. In addition, with regard to the configuration of the construction work management system in the fourth embodiment, explanation of the points similar to those in the first to third embodiments will be omitted.
[0042] In the fourth embodiment, the work management unit 128 compares the work progress schedule at the construction site included in the BIM model with the three-dimensional point cloud data, and estimates the deviation between the work progress schedule and the actual work progress. As described above, the BIM model can also include the process (time) of assembling each building material part. Therefore, by setting the date (work schedule information) when installation work will be performed for each part of the BIM model, it is possible to grasp the work progress schedule as of each work date, and by comparing this work progress schedule with the actual work progress shown in the three-dimensional point cloud data, it is possible to detect delays in work, mistakes in the work order, and the like.
[0043] Specifically, for example, the work progress estimation unit 124 classifies each component model (each component constituting the construction object) constituting the BIM model into the following three states. 1. Not started: There is no point cloud data in the area where the part of interest exists. 2. Completed: The error between the shape of the part of interest and the shape of the point cloud data for that part is within a specified range. 3. In progress: The error between the shape of the part of interest and the shape of the point cloud data of that part is not within a specified range, but the point cloud data exists within the range in which the part of interest exists.
[0044] The work management unit 128 judges whether the components scheduled for installation completion (or components for which installation work is scheduled to begin) are in a completed (or in-progress) state by the time point cloud data is acquired (the time of the current scan). If all components scheduled for installation completion are in a completed or in-progress state by the time of the current scan, it is presumed that the work is progressing as scheduled. On the other hand, if there are components that are scheduled for installation completion but have not yet been started by the time of the current scan, it is presumed that the work is delayed.
[0045] FIG. 6 is a diagram showing a flow of work progress management in the fourth embodiment. Steps S600 to S604 are similar to the flow of the first embodiment described with reference to FIG. 3, and therefore description thereof will be omitted. After step S604, the data comparison unit 122 compares the current scan data with the BIM model, and the work progress estimation unit 124 classifies the status of each component model that makes up the BIM model into either “not started,” “completed,” or “in progress” (step S606). The work management unit 128 compares the work schedule information of each component model with the classification result of step S606, and estimates the deviation between the actual work progress and the work schedule (step S608). That is, if a component that is scheduled to be installed is in a completed or in-progress state by the time of the current scan, it is estimated that the work related to that component is progressing as scheduled. Also, if there is a component that is not started among the components that are scheduled to be installed by the time of the current scan, it is estimated that the work related to that component is delayed.
[0046] The work management unit 128 notifies the work manager or the like of the estimated result of the deviation between the actual work progress and the work schedule (step S610). At this time, the difference part display unit may display the current scan data BIM model or the image captured during the current scan on the display, and may also display the part where the deviation was detected in an identifiable manner. The work manager etc. checks the discrepancy between the notified actual work progress and the work schedule, and if it is as planned (or the discrepancy is within the tolerance range), confirms it as is and ends the flow. If the discrepancy is outside the tolerance range, the work manager etc. considers changing the work schedule (step S612), and if the work schedule is changed, reflects the change in the work progress schedule included in the BIM model (step S614).
[0047] As described above, in the fourth embodiment, the construction period deviation is estimated based on the point cloud data of the construction site and the work progress schedule included in the BIM model. This makes it possible to appropriately review the work schedule even during work, and to discover errors in the work order early on, thereby improving work efficiency at the construction site. [Explanation of symbols]
[0048] 10 Construction Work Management System 12 Computer (work progress management device) 120 Point cloud data acquisition section 122 Data Comparison Section 124 Work Progress Estimation Unit 126 Work progress display section 128 Work Management Department 14 Automatic patrol vehicle 16 Portable information processing terminal 18 Laser Scanner
Claims
1. A construction work management system that manages work progress at a construction site using three-dimensional design data of a construction object, the three-dimensional design data includes work schedule information including a date on which installation work will be performed on a component model constituting the three-dimensional design data; A point cloud data acquisition unit that acquires three-dimensional point cloud data of the construction site acquired by a laser scanner; a data comparison unit that compares the three-dimensional point cloud data with the three-dimensional design data; a work progress estimation unit which classifies the state of the component model based on a comparison result by the data comparison unit into one of an unstarted state where no point cloud data exists within the range of the component of interest, a completed state where the error between the shape of the component of interest and the shape of the point cloud data of that part is within a specified range, and an in-progress state where the error between the shape of the component of interest and the shape of the point cloud data of that part is not within a specified range but point cloud data exists within the range of the component of interest; a work management unit which compares the work plan information of the component model with a classification result by the work progress estimation unit, and if a component to be installed is in the completed state or the in-progress state by the time the three-dimensional point cloud data is obtained, estimates that the work related to the component is progressing as planned, and if any component to be installed is in the unstarted state by the time the three-dimensional point cloud data is obtained, estimates that the work related to the component is delayed, thereby estimating a discrepancy between the actual work progress and the work plan for the component model; A construction work management system characterized by comprising:
2. a difference portion display unit that displays the three-dimensional point cloud data on a display and identifiably displays the portion where the deviation is estimated, 2. The construction work management system according to claim 1.
3. 3. The construction work management system according to claim 1, further comprising an automatic patrol vehicle that is equipped with the laser scanner and automatically patrols the construction site.
4. A construction work management method executed by a work progress management device for managing work progress at a construction site using three-dimensional design data of a construction object, comprising: the three-dimensional design data includes work schedule information including a date on which installation work will be performed on a component model constituting the three-dimensional design data; A point cloud data acquisition process for acquiring three-dimensional point cloud data of the construction site acquired by a laser scanner; a data comparison step of comparing the three-dimensional point cloud data with the three-dimensional design data; a work progress estimation step for classifying the state of the component model based on a comparison result in the data comparison step into one of an unstarted state in which no point cloud data exists within the range of the component of interest, a completed state in which the error between the shape of the component of interest and the shape of the point cloud data of that part is within a specified range, and an in-progress state in which the error between the shape of the component of interest and the shape of the point cloud data of that part is not within a specified range but point cloud data exists within the range of the component of interest; a work management process unit which compares the work plan information of the component model with the classification result in the work progress estimation process, and if a component to be installed is in the completed state or the in-progress state by the time the three-dimensional point cloud data is obtained, estimates that the work related to the component is progressing as planned, and if any component to be installed is in the unstarted state by the time the three-dimensional point cloud data is obtained, estimates that the work related to the component is delayed, thereby estimating a discrepancy between the actual work progress and the work plan related to the component model; A construction work management method comprising:
Citation Information
Patent Citations
Construction management system, construction management program, and construction management method
JP2015232203A
Construction planing system
JP2016212469A
Construction process management system and construction process management method
JP2019148946A