Vertical recycled aluminum manufacturing equipment

A two-stage recycling process using waste tires for heat and a water cooling structure efficiently produces high-purity recycled aluminum by minimizing loss and impurities, addressing inefficiencies and costs in existing methods.

JP7555554B1Active Publication Date: 2024-09-25KYUTEX CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2024102670
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2024-06-26
Publication Date
2024-09-25
Estimated Expiration
2044-06-26

AI Technical Summary

Technical Problem

Existing methods for recycling aluminum scrap materials are inefficient, result in significant aluminum loss, and are costly due to the need for multiple melting steps and high impurity removal efforts, making domestic recycling economically unviable.

Method used

A two-stage recycling process using dry distillation gasification furnaces and metal melting furnaces, where waste tires generate high-temperature gas to melt iron-coated and pure aluminum scrap materials separately, with a water cooling structure to manage heat and reduce impurities, and utilize the generated heat for multiple applications.

Benefits of technology

The process reduces aluminum loss and impurities, lowers fuel costs, simplifies operations, and enables efficient production of high-purity recycled aluminum with integrated energy utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007555554000001_ABST
    Figure 0007555554000001_ABST
Patent Text Reader

Abstract

To provide a recycled aluminum material production device that uses waste tires and scrap materials containing aluminum as main resources and can efficiently and low-costly produce recycled aluminum material with few impurities. [Solution] In the first boiler 01 and second boiler 02, which are dry distillation gasification furnaces, dry distillation gas is generated using waste tires 08, and in the first calcination furnace (metal melting furnace) 04, the dry distillation gas is ignited and the high-temperature gas generated is used to heat the aluminum scrap material 11 containing iron that has been introduced, and the aluminum is separated from the iron. Only the molten aluminum is allowed to flow into the second calcination furnace (metal melting furnace) 05 through the outlet hole 12. In the second calcination furnace 05, the dry distillation gas that has flowed in from the second boiler 02 is ignited and the high-temperature gas generated is used to heat the pure aluminum scrap material 15 that has been introduced and the molten aluminum that has flowed in from the first calcination furnace 04, and the molten or reheated aluminum is allowed to flow out of the second calcination furnace 05, producing recycled aluminum material.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a light metal melting facility that uses waste tires and aluminum-containing scrap materials as main resources, and can efficiently and low-costly produce recycled aluminum material with few impurities while minimizing the loss of aluminum during the recycling stage. [Background technology]

[0002] SDGs is an abbreviation of "Sustainable Development Goals" and is a common goal adopted by the UN member states unanimously in September 2015 at the UN Summit. Target 5 of SDGs 12 states, "By 2030, substantially reduce waste generation through prevention, reduction, recycling and reuse." Examples of recycling and reuse include melting metal products such as iron and aluminum to make new products from recycled metals, pelletizing plastic products to use them for toys, and generating energy from waste materials, as described in the invention of Patent Document 1, "extracting carbonized gas from waste tires in a carbonization gasification furnace and combusting the carbonized gas in a light metal melting furnace." There are many ways to achieve this.

[0003] The invention in the aforementioned Patent Document 1 is a device that uses energy generated from waste materials (waste tires) and can melt metals using that energy to produce recycled metals. However, when melting scrap aluminum with iron and extracting the aluminum that reaches its melting point first due to the difference in melting points between iron and aluminum to produce recycled aluminum, impurities contained in the recycled aluminum cannot be sufficiently removed by melting it once, and in order to increase the aluminum content to a level that can be distributed as recycled material, it is necessary to heat the aluminum material that has already been recycled in the same process and remove the impurities, which doubles the effort and cost.

[0004] Next, in order to bring the aluminum content of the iron-containing aluminum scrap material to a level that allows it to be distributed as recycled material, it is also possible to provide a first and second melting process in one metal recycling device. The invention in Patent Document 2 relates to a method for melting iron-containing materials in which "the first melting process, the second melting process, and the tapping process constitute one melting process cycle, and this melting process is repeatedly carried out." However, when recycled aluminum material is produced using this method, since this invention is merely a process for tapping molten iron, if the iron-containing material is charged into a melting furnace in the second melting process, the impurities contained in the recycled aluminum material cannot be removed, and the purpose of this invention is to shorten the cycle time, which is different from the purpose of removing impurities.

[0005] In addition, the applicant considered a method of disposing two firing furnaces one above the other as shown in Fig. 1, melting scrap aluminum with iron in the upper firing furnace, guiding the molten aluminum flowing out of the scrap aluminum with iron to the lower firing furnace through a hole connecting the two firing furnaces, and reheating the molten aluminum in the lower firing furnace. However, the molten aluminum heated in the lower firing furnace flows in little by little from the upper furnace, so that it is easy to vaporize by continuing to heat it, resulting in a problem of losing recyclable aluminum. This method is not limited to this method. Aluminum has a lower melting point than other metals and is easy to recycle, but when, for example, scrap aluminum cans or aluminum engines are melted to generate recyclable materials, the method of disposing these scrap materials in a furnace and heating them generally has the disadvantage of losing about 20% to 30%, which makes the business inefficient. Currently, there are more businesses that export scrap materials containing aluminum than businesses that recycle aluminum domestically, which is a factor that makes it difficult to expand the domestic recycling business. [Prior art documents] [Patent documents]

[0006] [Patent Document 1] JP2006-343002A [Patent Document 2] Patent No. 7311771 Summary of the Invention [Problem to be solved by the invention]

[0007] Therefore, the objective of the present invention is to provide a recycled aluminum material production device that uses waste tires and scrap materials containing aluminum as the main resources, and can efficiently and low-costly produce recycled aluminum material with few impurities while minimizing the loss of aluminum during the recycling stage. [Means for solving the problem]

[0008] In order to solve the above problems, the recycled aluminum material generating device according to the present invention includes a first boiler (dry distillation gasification furnace) for generating dry distillation gas using waste tires, a first sintering furnace (metal melting furnace) connected to the first boiler through a flue, a second boiler for generating dry distillation gas using waste tires, a second sintering furnace (metal melting furnace) connected to the second boiler through a flue and stacked under the first sintering furnace, an exhaust flue for gas generated in the first sintering furnace, and an exhaust pipe to which the exhaust flue for gas generated in the second sintering furnace is connected and leads to a chimney, and the first sintering furnace has an inlet for aluminum scrap material with iron and an aluminum plate on its bottom. the second sintering furnace has an inlet for pure aluminum scrap and an aluminum inlet on its top surface, the aluminum outlet hole of the first sintering furnace and the aluminum inlet hole of the second sintering furnace are connected, in the first sintering furnace, the dry distillation gas generated from the first boiler is ignited and the aluminum of the iron-containing aluminum scrap is melted by the heat, and the molten aluminum flows into the second sintering furnace through the aluminum outlet hole, and in the second sintering furnace, the dry distillation gas generated from the second boiler is ignited and the pure aluminum scrap and the molten aluminum flowing in from the first sintering furnace are simultaneously heated by the heat, to produce recycled aluminum. In addition to the above features, the present invention is characterized in that a water-cooled structure is provided on the outer periphery of the first boiler or the second boiler, the water-cooled structure has a flow path in contact with the outer surface of the first boiler or the second boiler, the flow path passes cooling water to cool the first boiler or the second boiler, the cooling water after cooling is discharged as hot water, and the discharged hot water can be used as hot water for heating in greenhouses or underfloor heating in homes, or as hot water for drying wood, etc. Furthermore, in order to solve the above-mentioned problems, the method for producing recycled aluminum material according to the present invention generates dry distillation gas using waste tires in a first boiler, and feeds scrap aluminum containing iron into a first sintering furnace connected to the first boiler through a flue. In the first sintering furnace, the dry distillation gas flowing in from the first boiler is ignited, and the scrap aluminum containing iron is heated with the generated high-temperature gas of 1000°C to 1100°C, and the iron is separated, and only the molten aluminum is flowed into a second sintering furnace. In the second boiler, dry distillation gas is generated using waste tires. The dry distillation gas is then sent to a second calcination furnace connected through a flue, and in the second calcination furnace, the molten aluminum that has flowed in from the first calcination furnace and is stored in the second calcination furnace is ignited by the dry distillation gas that has flowed in from the second boiler, and is heated by the generated high-temperature gas of 650°C to 800°C. Furthermore, pure aluminum scrap is introduced into the stored molten aluminum and heated at the same time, and the aluminum melted from the pure aluminum scrap and the molten aluminum that has flowed in from the first calcination furnace and been reheated are discharged outside the second calcination furnace, producing recycled aluminum. Effect of the Invention

[0009] The structure uses combustible gas generated from waste tires as a heat source for heating scrap materials in the first and second baking furnaces, and introduces the combustible gas into the baking furnace, ignites it, and generates high-temperature gas, which melts aluminum materials with iron or aluminum materials with a high aluminum content. This structure has the advantages of reducing fuel costs and not requiring complicated temperature control. In addition, by keeping the temperature in the first baking furnace at 1000℃ to 1100℃, it is possible to prevent the emission of harmful and toxic substances such as dioxins, gases, and odors. Scrap aluminum containing iron is heated in the first baking furnace, and the molten aluminum extracted is then poured into the second baking furnace where it is heated again, making it possible to significantly reduce the impurities contained in the recycled aluminum produced from the molten aluminum in the second baking furnace. By adding pure aluminum scrap to the molten aluminum flowing from the first baking furnace to the second baking furnace and heating it simultaneously in the second baking furnace, it is possible to prevent the loss of pure aluminum scrap during melting and the vaporization of the molten aluminum that flows in, and to produce large amounts of recycled aluminum with fewer impurities. The structure of the present invention, which completes the entire process from feeding in waste tires to producing recycled aluminum material in an integrated device, can simplify labor-intensive work and management, and also achieve efficiency in terms of business operations. The hot water discharged after cooling each boiler can be used as hot water for heating greenhouses or underfloor heating in homes, or for drying wood, etc., making it possible to efficiently utilize the energy generated in the entire process, from the input of waste tires to the production of recycled aluminum. [Brief description of the drawings]

[0010] [Figure 1] FIG. 2 is a side cross-sectional view of the recycled aluminum material generating apparatus of the present invention. [Diagram 2] This is a diagram showing the flow of molten aluminum based on Figure 1. [Diagram 3] FIG. 2 is a flow chart showing the operation of the recycled aluminum material generating device of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0011] An embodiment of the recycled aluminum material generating apparatus of the present invention will be described below with reference to the accompanying drawings. As shown in the side cross-sectional view of FIG. 1, the recycled aluminum production apparatus of the present invention is composed of a first boiler (pyrolysis gasification furnace) 01 for generating dry distillation gas using waste tires, a second boiler (pyrolysis gasification furnace) 02 for generating dry distillation gas using waste tires, which is stacked below the first boiler, a first calcination furnace (metal melting furnace) 04 for heating scrap aluminum with iron, which is connected to the first boiler 01 through a flue 03a, a second calcination furnace (metal melting furnace) 05 for heating scrap pure aluminum, which is stacked below the first calcination furnace 01 and connected to the second boiler 02 through a flue 03b, and an exhaust pipe 07 that connects the exhaust flue 06a through which gas and steam generated in the first calcination furnace 04 flows out and the exhaust flue 06b through which gas and steam generated in the second calcination furnace 05 flows out, and leads to a chimney exposed to the outside of a building.

[0012] The first boiler 01 and the second boiler 02 are provided with a dry distillation gasification furnace having a waste tire input hole 09 for storing waste tires 08 inside the first boiler 01 and the second boiler 02, and dry distill the input waste tires 08 to generate dry distillation gas. The input waste tires 08 can be sufficiently gasified without the need for work such as crushing and compression. Although not shown, the functions that can be provided with the dry distillation gasification furnace are not limited to those described above, and may include providing an ash discharge door for removing the ash of the waste tires 08 after dry distillation, and providing a water-cooling structure on the outer periphery for cooling the furnaces of the first boiler 01 and the second boiler 02 after incineration.

[0013] The first firing furnace 04 is a metal melting furnace connected to the first boiler 01 through a flue 03a. The first firing furnace 04 inputs the aluminum scrap material 11 containing iron from an inlet 10 for the aluminum scrap material containing iron, ignites the dry distillation gas that is dry distilled in the first boiler and is guided through the flue 03a, and keeps the temperature of the generated high-temperature gas at 1000°C to 1100°C to heat the aluminum scrap material containing iron 11. Since the melting point of the iron in the aluminum scrap material containing iron 11 is 1536°C and the melting point of the aluminum is about 660°C, the aluminum melts first and flows out to the bottom. Then, the bottom of the first firing furnace 04 is provided with an outlet hole 12 for the molten aluminum, and only the molten aluminum flows out of the first firing furnace through the outlet hole 12, so that the iron and aluminum can be separated. The bottom surface of the first firing furnace 04 is inclined and the outflow hole 12 is provided at the lowest part, so that the molten aluminum flowing out from the iron-containing aluminum scrap material 11 can be efficiently collected at the outflow hole 12.

[0014] The second firing furnace 05 is a metal melting furnace connected to the second boiler 02 through a flue 03b. An inlet (not shown) connected to the outlet 12 at the bottom of the first firing furnace 04 is provided on the top of the second firing furnace 05. The second firing furnace 05 ignites the dry distillation gas introduced through the flue 03b and dry distilled in the second boiler 02, keeps the temperature of the generated high-temperature gas at 650°C to 800°C, and heats the molten aluminum 13 flowing in from the outlet 12 connecting the first firing furnace 04 and the second firing furnace 05 to produce pure aluminum slag. The pure aluminum scrap material 15 is charged from the charge port 14 of the scrap material, the molten aluminum 13 and the pure aluminum scrap material 15 are heated at the same time, and a molten aluminum outlet hole 16 is provided at the bottom of the second firing furnace 05, and the molten aluminum consisting of the aluminum melted from the iron-containing aluminum scrap material 11 from which impurities have been removed by heating twice and the aluminum melted from the pure aluminum scrap material 15 charged into the second firing furnace 05 can be discharged out of the second firing furnace 05 through the outlet hole 16. At this time, the timing of charging the pure aluminum scrap material 15 is preferably when the molten aluminum flowing in from the outlet hole 12 has accumulated in the second firing furnace to a certain extent. This is because the pure aluminum scrap material 15 is heated so as to melt into the molten aluminum, and therefore loss due to vaporization can be greatly reduced. This method makes it possible to generate more recycled aluminum material than by directly heating in the furnace. As with the first firing furnace 04, the bottom surface of the second firing furnace 05 is inclined and an outflow hole 16 is provided at the lowest part of the inclination, so that the molten aluminum can be efficiently discharged from the outflow hole 16.

[0015] The pure aluminum scrap material 15 fed into the second baking furnace 05 can be various, such as aluminum window frame / sash scrap material, frying pans, pots, etc., but since soft aluminum materials such as aluminum drink can scraps have a large loss rate even if compressed and fed, it is preferable to use scrap materials such as frying pans and pots that are formed by stretching aluminum, but this is not limited to this.

[0016] The exhaust pipe 07 is a cylindrical pipe connecting an exhaust flue 06a through which gas and steam generated in the first firing furnace flows out and an exhaust flue 06b through which gas and steam generated in the second firing furnace flows out, and the exhaust pipe 07 is connected to a chimney 17 exposed to the outside of the building, and exhausts the post-combustion gas and steam outside the building. The vertical recycled aluminum production device according to the present invention can prevent the emission of harmful / toxic gases and odors by increasing the temperature of the gas in the firing furnace, but an additional function such as providing an exhaust gas analyzer between the exhaust flue 06a and 06b and the exhaust pipe 07 to further consider the environment may be provided.

[0017] In this way, the combustible gas generated from waste tires is used as a heat source for heating scrap materials in the first and second baking furnaces, and the combustible gas is introduced into the baking furnace, ignited, and high-temperature gas is generated, which melts aluminum materials with iron and pure aluminum materials with a high aluminum content. This structure has the advantages of reducing fuel costs and not requiring complicated temperature control. In addition, by keeping the temperature in the first baking furnace at 1000℃ to 1100℃, it is possible to prevent the emission of harmful and toxic substances such as dioxins, gases, and odors. Next, by adding a process within the equipment whereby scrap aluminum containing iron is heated in the first firing furnace, and the molten aluminum extracted is then flowed into the second firing furnace and heated again, it is possible to significantly reduce the impurities contained in the recycled aluminum produced from the molten aluminum in the second firing furnace. Then, by adding pure aluminum scrap to the molten aluminum that flows from the first firing furnace to the second firing furnace and heating them simultaneously in the second firing furnace, it is possible to prevent the loss of pure aluminum scrap during melting and the vaporization of the molten aluminum that flows in, and to produce large amounts of recycled aluminum with fewer impurities. Furthermore, the structure of the present invention, which completes the entire process from inputting waste tires to producing recycled aluminum in an integrated device, can simplify manual work and management, and improve business efficiency. In addition, the hot water discharged after cooling from each boiler can be used as hot water for heating greenhouses and floor heating in homes, or as hot water for drying wood, etc., making it possible to efficiently utilize the energy generated in the entire process from inputting waste tires to producing recycled aluminum.

[0018] Next, the operation of the vertical recycled aluminum material producing apparatus of the present invention will be described below with reference to the flow chart of FIG. In the dry distillation gas generation process, waste tires 08 are fed into the first boiler (dry distillation gasification furnace) 01 and the second boiler (dry distillation gasification furnace) 02 from waste tire feed ports 09a and 09b on the sides of each boiler shown in Figures 1 and 2. Then, the first boiler and the second boiler are ignited and operated to dry distill the waste tires 08 in the furnaces and generate dry distillation gas. In the high-temperature gas melting process, the iron-containing aluminum scrap material 11 is fed into the first firing furnace 04 from the feed port 10, the dry distillation gas generated in the first boiler is flowed into the first firing furnace, the dry distillation gas is ignited, and the temperature of the generated high-temperature gas is maintained at 1000°C to 1100°C to heat the iron-containing aluminum scrap material 11 in the first firing furnace. The aluminum melts first from the iron-containing aluminum scrap material 11, and then flows down the bottom of the first firing furnace 04 to the molten aluminum outlet hole 12 provided on the bottom. In the medium-to-high temperature gas melting process, the dry distillation gas generated in the second boiler is flowed into the second firing furnace 05, the dry distillation gas is ignited, the temperature of the generated high-temperature gas is maintained between 650°C and 800°C, and the molten aluminum 13 that flows in from the outlet hole 12 of the first firing furnace is stored in the second firing furnace 05. In the molten aluminum mixing process, the temperature of the generated high-temperature gas is maintained between 650°C and 800°C, and pure aluminum scrap material 15 (scrap aluminum frying pans and pots) is fed from a feed port 14 into the molten aluminum 13 stored in the second baking furnace. Then, the pure aluminum scrap material 15 and the molten aluminum that has flowed in from the first baking furnace 04 through the outflow hole 12 are heated at the same time. In the recycled aluminum production process, the molten aluminum heated in the second firing furnace 05 flows down the bottom of the second firing furnace 05 and into the molten aluminum outlet hole 15 located at the bottom of the second firing furnace. A recycled aluminum mold 18 is provided at the outlet of outlet hole 15, and the molten aluminum is poured into mold 18 to produce recycled aluminum material. The scrap aluminum material 11 with iron heated in the first baking furnace 04 becomes iron material remaining in the furnace after the aluminum flows out, and the waste tires become ash after dry distillation in the first boiler and the second boiler, so they are removed from each device. In addition, a water-cooling structure such as water pipes is provided on the outer periphery of the first boiler and the second boiler, which are dry distillation gasification furnaces, to cool the furnaces, and the water used to cool the furnaces is discharged as hot water, so that it can be used for various purposes. For example, it can be used to provide hot water to swimming pool facilities, for greenhouse cultivation such as vinyl houses and floor heating in houses, for drying wood and wild plants (vegetables), for use in hot spring facilities, and as an energy source for power generation. [Explanation of symbols]

[0019] 01 No. 1 boiler (dry distillation gasification furnace) 02 No. 2 boiler (dry distillation gasification furnace) 03 Flue 03a Flue connecting the first boiler and the first kiln 03b Flue connecting the second boiler and the second kiln 04 First firing furnace (metal melting furnace) 05 Second baking furnace (metal melting furnace) 06 Exhaust flue 06a Exhaust flue for gas and steam after combustion in the first kiln 06b Exhaust flue for gas and steam after combustion in the second kiln 07 Exhaust pipe 08 Waste tires 09 Waste tire slot 09a Waste tire inlet for the first boiler 09b Waste tire inlet for the second boiler 10. Aluminum scrap feed slot with steel 11 Aluminum scrap with iron 12 Molten aluminum outlet hole of the first firing furnace 13 Molten aluminum flowing from the first baking furnace 14. Pure aluminum scrap material inlet 15 Pure aluminum scrap 16 Molten aluminum outlet hole of second baking furnace 17 Chimney 18 Recycled aluminum mold 19 Direction of movement of molten aluminum

Claims

1. a first boiler for generating dry distillation gas using waste tires; a first calciner connected to the first boiler through a flue; A second boiler for generating dry distillation gas using waste tires; a second calciner connected to the second boiler through a flue and stacked under the first calciner; an exhaust flue for the gas generated in the first calcination furnace and an exhaust pipe connecting the exhaust flue for the gas generated in the second calcination furnace and leading to a chimney; The first firing furnace has an inlet for feeding aluminum scrap containing iron and an aluminum outlet hole on the bottom surface, The second firing furnace has an inlet for inserting pure aluminum scrap material and an aluminum inlet hole on the top surface, The aluminum outlet hole of the first firing furnace and the aluminum inlet hole of the second firing furnace are connected to each other, In the first calcination furnace, the dry distillation gas generated from the first boiler is ignited, and the aluminum of the aluminum scrap material containing iron is melted by the heat generated in the first calcination furnace. The molten aluminum flows out through the aluminum outflow hole into a second firing furnace, In the second calcination furnace, the dry distillation gas generated from the second boiler is ignited, and the heat is used to simultaneously heat the pure aluminum scrap material and the molten aluminum flowing in from the first calcination furnace; The feature is that recycled aluminum materials are produced Recycled aluminum production equipment

2. A water-cooling structure is provided on the outer periphery of the first boiler or the second boiler; The water-cooling structure has a flow path in contact with an outer surface of the first boiler or the second boiler, The flow path passes cooling water to cool the first boiler or the second boiler, The cooling water after cooling is discharged as hot water, The discharged hot water can be used as hot water for greenhouse cultivation or floor heating in a house, or as hot water for drying wood, wild plants, or vegetables. The apparatus for producing recycled aluminum according to claim 1.

3. The first boiler uses waste tires to generate dry distillation gas. Feed scrap aluminum containing iron into a first baking furnace connected to the first boiler through a flue; In the first firing furnace, the dry distillation gas flowing from the first boiler is ignited, and the aluminum scrap material with iron is heated with the generated high-temperature gas of 1000°C to 1100°C, and the aluminum is separated from the iron, and only the molten aluminum is flowed into the second firing furnace; In the second boiler, waste tires are used to generate dry distillation gas, and the dry distillation gas is sent to the second calcination furnace connected through a flue. In the second firing furnace, the molten aluminum that flows in from the first firing furnace and is stored in the second firing furnace is heated by the high-temperature gas of 650°C to 800°C generated by igniting the dry distillation gas that flows in from the second boiler, and further, pure aluminum scrap material is introduced into the stored molten aluminum and heated at the same time. The pure aluminum scrap material is melted and the reheated molten aluminum that flows from the first sintering furnace is discharged out of the second sintering furnace; The feature is that recycled aluminum materials are produced How to make recycled aluminum

Citation Information

Patent Citations

  • A method and apparatus for melting low melting point metals using wast e tires as fuel

    JP1976119604A

  • Melting furnace for metal

    JP1987112737A

  • Dry distillation gasification furnace, light metal melting furnace and light metal melting equipment

    JP2006343002A

  • Heat treatment device / method

    JP2010012409A

  • Melting method for iron-containing materials

    JP7311771B2