Existing bridge surface surveying systems require additional equipment like inclinometers, complicating the setup and do not efficiently guide formwork positioning during construction, and they fail to consider the changing height of construction blocks due to load and environmental conditions.
A bridge surface surveying system using a total station placed on a mobile work vehicle or tripod, with a first known point on the bridge column head and a second known point on a completed block, allowing for easy identification of the total station's three-dimensional position, enabling direct surveying of construction block surfaces and guiding formwork placement.
The system simplifies the surveying process by eliminating the need for inclinometers and allows precise, obstacle-free measurement of construction block heights, facilitating efficient formwork positioning and accurate height adjustments during construction.
Smart Images

Figure 0007561011000001 
Figure 0007561011000002 
Figure 0007561011000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a bridge surface surveying system and a bridge surface surveying method using a total station. [Background technology]
[0002] For example, in the construction of PC bridges using cantilever construction, the height of the girders changes successively during construction due to changes in the load condition and structure, as well as changes in the environmental temperature. For this reason, the bridge surface height must be surveyed periodically and the construction height must be corrected as construction progresses. Recently, systems that use total stations to automatically measure the height of the completed bridge have been used. One specific example is the installation height management system described in Patent Document 1. This installation height management system installs a total station on the bridge's column capitals and places a target on the top surface of a completed block after construction is complete. In addition, an inclinometer is placed on the top surface of the block under construction. The total station, target, and inclinometer in each position are used to measure the bridge surface height of the block under construction. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2020-33762 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the installation height management system described in the above Patent Document 1, the top surface of the block being constructed cannot be sighted from the total station installed on the bridge column head. Therefore, an inclinometer is placed on the top surface of the construction block being constructed to compensate for this. That is, the system of Patent Document 1 requires an inclinometer in addition to a target, which increases the number of types of equipment required and complicates the overall configuration of the system. Furthermore, there is no mention of considering using a total station to guide the position of the formwork for the blocks when installing them during the construction of the blocks, thereby improving workability.
[0005] The object of the present invention is to provide a bridge surface surveying system and method that allows the location of a total station to be moved as construction progresses and the total station's three-dimensional position to be easily determined with each movement, thereby making it easy to survey the top surface of a construction block. [Means for solving the problem]
[0006] In order to achieve the above-mentioned object, a bridge surface surveying system according to a first aspect of the present invention comprises a total station placed in an area where a mobile work vehicle is present on a bridge, a first known point placed at the capital of the bridge column, a second known point placed at a position where the total station can be sighted, and a control unit that controls surveying by the total station, wherein the control unit determines the three-dimensional self-position (X, Y, Z) of the total station based on the detection results of the positional information of the first known point and the second known point by the total station, and performs a survey of the top surface of a construction block in the area where the mobile work vehicle is present using the total station in a state where the self-position has been determined.
[0007] Here, "being positioned in the area where a mobile work vehicle on a bridge is located" is used in this specification to mean not only that the total station is directly attached to a component part of the mobile work vehicle, but also that it can be positioned in the area where the mobile work vehicle is located independently from the mobile work vehicle by using a tripod or the like. In addition, the phrase "performing a survey of the top surface of a construction block" is used to mean not only measuring the finished height of the top surface of the construction block after it is completed, but also guiding the position of the formwork when installing the formwork for the block in the early stages of construction.
[0008] According to this aspect, the total station is placed in the area where the mobile work vehicle is present on the bridge. Therefore, the total station can be positioned in a place where it can overlook the area where the mobile work vehicle is present, i.e., the top surface of the construction block. This makes it possible to directly survey the top surface of the construction block, since it is less susceptible to the influence of obstacles. In other words, equipment such as a conventional inclinometer is no longer necessary. On the other hand, since the total station changes its own position every time it moves as construction progresses, it is necessary to grasp the self-position of the total station each time. According to this aspect, the first known point is placed at the head of a bridge column, and the second known point is placed at a position that can be sighted by the total station. Therefore, the control unit can determine the three-dimensional self-position (X, Y, Z) of the total station based on the detection results of the position information of the first known point and the second known point by the total station. In other words, according to this aspect, it is easy to determine the self-position of the total station. Then, the total station, which has determined its own position, can easily carry out surveying of the upper surface of the construction block in the area where the mobile work vehicle is present. That is, in the early stages of block construction, it becomes possible to guide the formwork position when setting up the formwork for the block, and also, after the construction block is completed, it is possible to easily measure the finished height of the upper surface.
[0009] A second aspect of the present invention is characterized in that, in the bridge surface surveying system of the first aspect, the second known point is located on a completed block located in the overhanging direction from the column capital of the bridge, and the control unit determines the two-dimensional horizontal position (X, Y) of the total station based on the detection results of positional information of the first known point and the second known point by the total station, and further determines the vertical position (Z) of the total station based on the detection results of the positional information of the first known point, thereby identifying the three-dimensional self-position (X, Y, Z) of the total station.
[0010] According to this aspect, the second known point is located on a completed block located in the overhanging direction from the column capital of the bridge. The three-dimensional position of the completed block is not specified before completion, but is specified after completion. Therefore, it can be said that the completed block can be used as a known point for the total station. As a result, since both the first known point and the second known point are located on the bridge, the total station is less susceptible to the influence of obstacles, and therefore it is easy to perform the process of specifying its own position. However, since the completed block is positioned in the direction of overhang from the bridge's column capital, it exists in a cantilever structure. In this cantilever structure, its height (Z direction) may fluctuate due to changes in the load condition, structural system, and even changes in environmental temperature. On the other hand, it is possible to consider that its two-dimensional position (X, Y) in the horizontal direction does not fluctuate. According to this aspect, the control unit determines the two-dimensional horizontal position (X, Y) of the total station based on the detection result of the position information of the first known point and the second known point by the total station. Furthermore, the control unit determines the vertical position (Z) of the total station based on the detection result of the position information of the first known point, thereby identifying the three-dimensional self-position (X, Y, Z) of the total station. Since it can be said that there is no risk of the first known point fluctuating, the position (Z) in the height direction can be determined. Therefore, the three-dimensional self-position (X, Y, Z) of the total station can be identified without being substantially affected by the state of the cantilever structure of the completed block.
[0011] A third aspect of the present invention is characterized in that, in the bridge surface surveying system of the second aspect, the second known point is a survey point for the finished height of the completed block.
[0012] According to this aspect, the second known point is a survey point for the finished height of the completed block, so that the survey point, which is the survey position for the finished height, can also be used as a known point, which is a reference point required for the total station to determine its own position, which is efficient.
[0013] A fourth aspect of the present invention is characterized in that, in the bridge surface surveying system of the first aspect, the second known point is located at a position away from the bridge surface of the bridge.
[0014] According to this aspect, the second known point is located at a position away from the bridge deck of the bridge, so that it is easy to select a position at which the total station can be aimed, and it is easy to place the total station at the position.
[0015] A bridge surface surveying method according to a fifth aspect of the present invention is characterized in that a total station is placed in an area where a mobile work vehicle is present on a bridge, a first known point is placed at the capital of the bridge column, a second known point is placed at a position where the total station can be sighted, the three-dimensional self-position (X, Y, Z) of the total station is determined based on the detection results of position information of the first known point and the second known point by the total station, and a survey of the top surface of a construction block in the area where the mobile work vehicle is present is performed by the total station in a state where the self-position has been determined.
[0016] According to this aspect, the total station is placed in an area on the bridge where the mobile work vehicle is present, so that it is possible to obtain the same effects as in the first aspect.
[0017] A sixth aspect of the present invention is characterized in that, in the bridge surface surveying method of the fifth aspect, the second known point is located on a completed block located at the tip of the bridge in the direction of projection from the column capital, and the two-dimensional horizontal position (X, Y) of the total station is determined based on the detection results of positional information of the first known point and the second known point by the total station, and further the three-dimensional self-position (X, Y, Z) of the total station is specified by determining the vertical position (Z) of the total station based on the detection results of the positional information of the first known point.
[0018] According to this aspect, the second known point is arranged on a completed block located in the overhanging direction from the column capital of the bridge, so that the same effect as in the second aspect can be obtained.
[0019] A seventh aspect of the present invention is characterized in that, in the bridge surface surveying method of the fifth aspect, the second known point is located at a position away from the bridge surface of the bridge.
[0020] According to this aspect, the second known point is located at a position away from the bridge face of the bridge, so that it is possible to obtain the same effect as the fourth aspect. [Brief description of the drawings]
[0021] [Figure 1] FIG. 1 is a schematic side view illustrating a first embodiment of a bridge surface surveying system according to the present invention. [Diagram 2] FIG. 2 is a perspective view of a main part for explaining the first embodiment. [Diagram 3] 1 is a flowchart for explaining the execution of a survey by the system of the first embodiment. [Figure 4] FIG. 11 is a schematic side view for explaining a second embodiment of a bridge surface surveying system according to the present invention. [Diagram 5] 11 is a flowchart for explaining the execution of a survey by the system of the second embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0022] [Embodiment 1] Hereinafter, a bridge surface surveying system according to a first embodiment of the present invention will be described in detail with reference to Figs. 1 to 3. In the following explanation, the three mutually orthogonal axes are referred to as the X-axis, Y-axis, and Z-axis, as shown in each figure. The Z-axis direction corresponds to the vertical direction (the direction in which gravity acts). The X-axis and Y-axis directions correspond to the horizontal direction. Here, the X-axis direction corresponds to the overhang direction of the bridge, and the Y-axis direction corresponds to the width direction of the bridge.
[0023] 1 and 2, the bridge surface surveying system 1 of this embodiment comprises a total station 7 placed in an area where a mobile work vehicle 5 is present on a bridge 3 during cantilever construction of a PC bridge, a first known point 11 placed at a column capital 9 of the bridge 3, a second known point 13 placed at a position where the total station 7 can be sighted, and a control unit 15 that controls the surveying by the total station 7. Here, the "known points" of the first known point 11 and the second known point 13 are literally places whose positions have been specified, that is, places whose positions are understood. In Fig. 1, reference numeral 2 denotes a pier, and a column head 9 is located on top of a leg head 4 of the pier 2. A bridge 3 is constructed by constructing blocks BL one block at a time (1BL → 2BL → 3BL) from the column head 9 via a mobile work vehicle 5 in two directions that are the projection directions, that is, in two directions, the +X direction and the -X direction in the X-axis direction. In Fig. 1, each block 1BL, 2BL, and 3BL indicates a completed block. The next block nBL is constructed on the completed block 3BL located at the tip of the projection direction to extend it. Fig. 1 corresponds to the initial stage of construction of the next block nBL, and shows a state in which a block formwork 6 for constructing the next block nBL has been installed.
[0024] The control unit 15 is configured to determine the three-dimensional self-position (X, Y, Z) of the total station 7 based on the detection results of position information of a first known point (X1, Y1, Z1) 11 and a second known point (X2, Y2, Z2) 13 (Figure 2) by the total station 7. Furthermore, the control unit 15 is configured to perform surveying by having the total station 7, having identified its own position (X, Y, Z), shine light on the top surface 19 of the construction block 17 (Figure 2), which is the next block nBL in the presence area of the mobile work vehicle 5.
[0025] Hereinafter, each of the components constituting the bridge surface survey system 1 according to this embodiment will be described in detail. <Total Station> The total station 7 is a widely used surveying instrument that can measure the distance and angle to a target point by shining light onto the target point and electronically analyzing the light that is reflected back to the instrument. If the position and orientation of the total station 7 have been determined in advance by surveying or the like, the three-dimensional position (X, Y, Z) of the target point can be measured by converting the distance and angle obtained by the measurement into three-dimensional coordinates.
[0026] <Total station placement> The total station 7 is placed in an area on the bridge 3 where the mobile work vehicle 5 is located. In this embodiment, the total station 7 is directly attached to a component of the mobile work vehicle 5. That is, it is attached so as to be located above the upper surface so as to face the upper surface 19 of the construction block 17. The mounting structure for mounting the total station 7 to the component of the mobile work vehicle 5 is a general one, so illustration and explanation are omitted. In Figure 2, the mobile work vehicle 5 is not illustrated and only the total station 7 is shown. Furthermore, the total station 7 is not limited to being attached directly to a component part of the mobile work vehicle 5, but may also be placed independently of the mobile work vehicle 5 using a tripod or the like, in a location that overlooks the area in which the mobile work vehicle 5 is located, i.e., the top surface of the construction block 17.
[0027] <First known point> In this embodiment, the first known point (X1, Y1, Z1) 11 used to grasp the self-position of the total station 7 is placed at the column capital 9 of the bridge 3 as described above. Specifically, the first known point 11 is located on the top surface of the column capital 9 at the center in the X-axis direction and the Y-axis direction. However, it is not limited to this central location. The three-dimensional position of the top surface of the column capital 9 of the bridge 3 can be considered to be specified. A prism target, which is widely used in the surveying field, is used as the first known point 11. However, the first known point 11 is not limited to the prism target as long as it can return reflected light to the total station 7.
[0028] <Second Known Point> The second known point (X2, Y2, Z2) 13 is placed at a collimable position of the total station 7 as described above. In this embodiment, the second known point 13 is located on the completed block BL located in the overhanging direction (X-axis direction) from the column capital 9 of the bridge 3. More specifically, the second known point 13 is a measurement point 21 of the finished height of the completed block 3BL, which is at the tip of the completed block 3BL in the overhanging direction, as shown in Figures 1 and 2. This measurement point 21 of the finished height is located at the center of the completed block 3BL in the Y-axis direction in this embodiment. Here, it goes without saying that the second known point 13 is not limited to being located at the center. Incidentally, in Figure 2, the three completed blocks 1BL, 2BL, and 3BL are collectively described as a single completed block BL. The second known point 13 is a prism target that is widely used in the surveying field, like the first known point 11. The second known point 13 is not limited to the prism target as long as it can return reflected light to the total station 7.
[0029] <Control unit, determining the self-position of the total station> As described above, the control unit 15 determines the three-dimensional self-position (X, Y, Z) of the total station 7 based on the detection results of the position information of the first known point (X1, Y1, Z1) 11 and the second known point 13 by the total station 7. In this embodiment, the second known point (X2, Y2, Z2) 13 is located at the center in the Y-axis direction of the tip of the completed block 3BL in the overhanging direction. Here, the completed block 3BL is located at the tip of the overhanging direction from the column capital 9 of the bridge 3, so it exists in a cantilever structure. In this cantilever structure, the height direction (Z direction) may fluctuate due to changes in the load state, structural system, and further changes in environmental temperature. On the other hand, it is possible to consider that the two-dimensional position (X2, Y2) in the horizontal direction does not fluctuate. Therefore, in this embodiment, the second known point (X2, Y2, Z2) 13 is used as a reference point for determining the two-dimensional position (X, Y) of the total station 7 in the horizontal direction.
[0030] Specifically, light is irradiated from the total station 7 to the first known point (X1, Y1, Z1) 11 and the second known point (X2, Y2, Z2) 13, which are the target points, and the reflected light is received and electronically analyzed to measure the distance and angle to the target points. The self-position of the total station 7 is not specified, but the positions of the first known point (X1, Y1) 11 and the second known point (X2, Y2) 13, which are the target points, are both specified. Therefore, first, the distance obtained by the measurement is converted by the two-point method of the backward intersection method to obtain the two-dimensional self-position (X0, Y0) of the total station 7 in the horizontal direction.
[0031] Next, the control unit 15 further obtains the vertical position (Z) of the total station 7 based on the detection result of the position information of the first known point (X1, Y1, Z1) 11. That is, the three-dimensional self-position (Z0) of the total station is obtained. Since it can be said that there is no risk of the position of the first known point 11 fluctuating, the self-position (Z0) in the height direction can be obtained by irradiating the first known point 11 with light. The three-dimensional self-position (X0, Y0, Z0) of the total station 7 can be determined from the two-dimensional self-position (X0, Y0) and the height direction self-position (Z0) obtained as described above. That is, the three-dimensional self-position (X0, Y0, Z0) of the total station 7 can be determined without being substantially affected by the state of the cantilever structure of the completed block 3BL.
[0032] <Survey of the top surface of the construction block> As described above, the control unit 15 performs surveying by having the total station 7 determine its own position (X0, Y0, Z0) by shining light onto the top surface 19 of the construction block 17, which is the next block nBL in the location area of the mobile work vehicle 5. Specifically, in the early stages of construction of the construction block 17, when setting up the formwork 6 for the block, the formwork position is guided by light irradiation 8 (Fig. 1) from a total station 7. That is, the formwork 6 for the block is set up along the irradiation point of the light irradiation 8. Then, the construction block 17 is made by assembling reinforcing bars and pouring concrete inside the formwork 6. Next, with the concrete of the construction block 17 in a hardened state, light 10 is irradiated onto the upper surface 19 thereof, and the height of the upper surface 19 is measured. The height of the upper surface 19 of the construction block 17 can be measured either with or without placing a prism target.
[0033] <Determining the self-position of the total station 7 ~ Surveying of construction blocks> Next, the entire process of surveying a bridge surface using the bridge surface surveying system 1 of this embodiment will be described with reference to the flowchart of FIG. (1) First, in step S1, the following steps (101) to (103) are carried out. (101) A total station 7 is attached to a mobile work vehicle 5 on a bridge 3. (102) A first known point (X1, Y1, Z1) 11 is placed on the column capital 9 of the bridge 3. (103) A second known point (X2, Y2, Z2) 13 is placed on the completed block 3BL, which is a collimating position of the total station 7. Here, since there is no need to decide the order in which steps (101) to (103) are performed, they may be performed simultaneously. The relative arrangement of the total station 7, the first known point 11, and the second known point 13 is such that the total station 7 can sight the first known point 11 and the second known point 13.
[0034] (2) Next, in step S2, the following steps (201) and (202) are carried out. (201) The two-dimensional self-position (X0, Y0) of the total station 7 is calculated as described above. (202) The self-position (Z0) of the total station 7 in the height direction is obtained as described above.
[0035] (3) Next, in step S3, the three-dimensional self-position (X0, Y0, Z0) of the total station 7 is calculated based on the self-positions (X0, Y0) and (Z0) calculated in steps (201) and (202) above. This allows the self-position (X0, Y0, Z0) of the total station 7 to be specified in the bridge surface surveying system 1. (4) Next, in step S4, the total station 7, with its own position (X0, Y0, Z0) identified, measures the top surface 19 of the construction block 17 in the area in which the mobile work vehicle 5 is located. That is, in the early stages of construction of the block BL, the formwork position is guided when setting up the formwork 6 for the block. In addition, after the construction block 17 is completed, the finished height of the top surface 19 is measured. After the measurement, the mobile work vehicle 5 is moved and the construction of the next block is carried out in the same manner as above.
[0036] <Explanation of Effects of First Embodiment> (1) According to this embodiment, the total station 7 is placed in the area where the mobile work vehicle 5 exists on the bridge 3. Therefore, the total station 7 can be positioned in the area where the mobile work vehicle 5 exists, i.e., in a place where it can overlook the top surface of the construction block. As a result, the survey of the top surface 19 of the construction block 17 is less affected by obstacles, so it is possible to survey directly. In other words, equipment such as a conventional inclinometer is not required. On the other hand, since the total station 7 changes its own position every time it moves as construction progresses, it is necessary to perform a process of grasping the own position of the total station 7 each time. According to this embodiment, the first known point (X1, Y1, Z1) 11 is disposed at the column head 9 of the bridge 3, and the second known point (X2, Y2, Z2) 13 is disposed at a position where the total station 7 can collimate. Therefore, the control unit 15 can specify the three-dimensional own position (X0, Y0, Z0) of the total station 7 based on the detection result of the position information of the first known point 11 and the second known point 13 by the total station 7. That is, according to this embodiment, the own position (X0, Y0, Z0) of the total station 7 can be easily specified. Then, the total station 7, with its own position (X0, Y0, Z0) identified, can easily carry out surveying of the top surface 19 of the construction block 17 in the area in which the mobile work vehicle 5 is present. That is, in the early stages of block construction, it becomes possible to guide the formwork position when setting up the formwork 6 for the block, and also, after the construction block 17 is completed, the finished height of its top surface 19 can be easily measured.
[0037] (2) Furthermore, according to this embodiment, the second known point (X2, Y2, Z2) 13 is located on the completed block 3BL located in the overhanging direction from the column capital 9 of the bridge 3. The three-dimensional position of the completed block 3BL is not specified before completion, but is specified after completion. Therefore, it can be said that the completed block 3BL can be used as a known point for the total station 7. As a result, since both the first known point (X1, Y1, Z1) 11 and the second known point (X2, Y2, Z2) 13 are located on the bridge 3, the total station 7 is less susceptible to the influence of obstacles, and therefore it is possible to easily perform the process of specifying its own three-dimensional position (X0, Y0, Z0). According to this embodiment, the control unit 15 determines the two-dimensional position (X0, Y0) of the total station 7 in the horizontal direction based on the detection result of the position information of the first known point (X1, Y1, Z1) 11 and the second known point (X2, Y2, Z2) 13 by the total station 7. Furthermore, the control unit 15 determines the vertical position (Z0) of the total station 7 based on the detection result of the position information of the first known point (X1, Y1, Z1) 11, thereby identifying the three-dimensional self-position (X0, Y0, Z0) of the total station 7. Since it can be said that there is no risk of the first known point 11 fluctuating, the position (Z0) in the height direction can be obtained. Therefore, the three-dimensional self-position (X0, Y0, Z0) of the total station 7 can be identified without being substantially affected by the state of the cantilever structure of the completed block 3BL.
[0038] (3) Furthermore, according to this embodiment, the second known point (X2, Y2, Z2) 13 is the survey point 21 of the finished height of the completed block 3BL. Therefore, the survey point 21, which is the survey position of the finished height, can also be used as a known point, which is a reference point required for the total station to determine its own position, which is efficient.
[0039] [Embodiment 2] Next, the bridge surface surveying system 1 according to the second embodiment of the present invention will be described in detail with reference to FIGS. In the bridge surface surveying system 1 of this embodiment, the second known point 13 is placed at a position away from the bridge surface 19 of the bridge 3. Specifically, as shown in Fig. 4, the second known point 13 is not placed on the bridge 3 but at a position away to the side of the bridge 3. The position may be any position that can be sighted from the total station 7 attached to the mobile work vehicle 5, and is not limited to a specific location. Other configurations are the same as those of the first embodiment, so the same parts are denoted by the same reference numerals and the description thereof will be omitted. Also, the description of the same operations and effects as those of the first embodiment will be omitted.
[0040] <Determining the self-position of the total station 7 ~ Surveying of construction blocks> Next, the entire process of surveying a bridge surface using the bridge surface surveying system 1 of this embodiment will be described with reference to the flowchart of FIG. (1) First, in step S11, the following steps (301) to (303) are carried out. (301) A total station 7 is attached to a mobile work vehicle 5 on a bridge 3. (302) A first known point (X1, Y1, Z1) 11 is placed on the column capital 9 of the bridge 3. (303) A second known point 13 is placed to the side of the bridge 3, which is a position where the total station 7 can be sighted. Here, since there is no need to decide the order of performing (301) to (303), they may be performed simultaneously. The relative arrangement of the total station 7, the first known point 11, and the second known point 13 is such that the total station 7 can sight the first known point 11 and the second known point 13.
[0041] (2) Next, in step S12, the three-dimensional self-position (X0, Y0, Z0) of the total station 7 is determined based on the detection results of the position information of the first known point (X1, Y1, Z1) 11 and the second known point (X2, Y2, Z2) 13 by the total station 7. (3) Next, in step S13, the total station 7, which has determined its own position (X0, Y0, Z0), performs a survey of the upper surface 19 of the construction block 17 in the area in which the mobile work vehicle 5 is located. The execution of this survey is the same as step S4 in the first embodiment, and a description thereof will be omitted.
[0042] According to this embodiment, the second known point 13 is placed at a position away from the bridge surface of the bridge 3, so that it is easy to select a collimating position for the total station 7 and to place it at the collimating position.
[0043] [Other embodiments] The present invention has been described above using embodiment 1 and embodiment 2. However, the present invention is not limited to the above-mentioned embodiment examples, and various modifications are possible within the scope of the invention described in the claims, and it goes without saying that these modifications are also included in the scope of the present invention. For example, in the above embodiment, the second known point 13 is a survey point 21 of the finished height of the completed block 3BL at the tip in the protruding direction of the completed block 3BL, but is not limited to this and a survey point of the finished height of other completed blocks 2BL, etc. may be used.
[0044] Furthermore, in the above embodiment, the total station 7 is attached directly to the mobile work vehicle 5, so when construction of the construction block 17 is completed and the mobile work vehicle 5 moves to the next construction position, it moves together with the mobile work vehicle 5. If the total station 7 is not directly attached to a component of the mobile work vehicle 5, but is placed in the area where the mobile work vehicle 5 is present while being independent of the mobile work vehicle 5 using a tripod or the like, movement to the next construction position can be easily performed by moving the total station 7 together with the tripod. [Explanation of symbols]
[0045] 1...bridge surface survey system, 2...pier, 3...bridge, 4...leg head, 5...mobile work vehicle, 6...formwork for blocks, 7...total station, 8...light irradiation, 9...column capital, 10...light irradiation, 11...first known point, 13...second known point, 15...control unit, 17...construction block, 19...top surface, 21...measurement point of finished height, BL...block, nBL...next block
Claims
1. A total station is placed in an area where a mobile work vehicle is present on the bridge and where the top surface of the construction block can be viewed; A first known point located at a column capital of a bridge; A second known point disposed at a collimable position of the total station; A control unit for controlling the surveying by the total station, The control unit is Identifying a three-dimensional self-position (X, Y, Z) of the total station based on a detection result of position information of the first known point and the second known point by the total station; A survey is carried out on the top surface of the construction block in the area where the mobile work vehicle is present by the total station in the state where the self-location has been identified. A bridge surface surveying system.
2. 2. The bridge surface survey system according to claim 1, The second known point is disposed on a completed block located in a projecting direction from the column capital of the bridge, The control unit is determining a two-dimensional horizontal position (X, Y) of the total station based on the detection result of position information of the first known point and the second known point by the total station, and further determining a vertical position (Z) of the total station based on the detection result of the position information of the first known point, thereby identifying a three-dimensional self-position (X, Y, Z) of the total station; A bridge surface surveying system.
3. 3. The bridge surface survey system according to claim 2, The second known point is a measurement point of the finished height of the completed block. A bridge surface surveying system.
4. 2. The bridge surface survey system according to claim 1, The second known point is located at a position away from the bridge deck of the bridge. A bridge surface surveying system.
5. A total station is placed in an area where the mobile work vehicle is present on the bridge and where the top surface of the construction block can be viewed. Placing a first known point at a bridge column capital; Placing a second known point at a collimable position of the total station; Based on the detection results of the position information of the first known point and the second known point by the total station, the three-dimensional self-position (X, Y, Z) of the total station is identified, and the total station in the state where the self-position is identified performs a survey of the upper surface of the construction block in the presence area of the mobile work vehicle. A bridge surface survey method comprising the steps of:
6. The bridge surface surveying method according to claim 5, The second known point is disposed on a completed block located in a projecting direction from the column capital of the bridge, determining a two-dimensional horizontal position (X, Y) of the total station based on the detection result of position information of the first known point and the second known point by the total station, and further determining a vertical position (Z) of the total station based on the detection result of the position information of the first known point, thereby identifying a three-dimensional self-position (X, Y, Z) of the total station; A bridge surface survey method comprising the steps of:
7. The bridge surface surveying method according to claim 5, The second known point is located at a position away from the bridge deck of the bridge. A bridge surface survey method comprising the steps of:
Citation Information
Patent Citations
Three-dimensional surveying method for tunnel
JP1993079841A
Survey method and program for displaying result thereof
JP2004170164A
Installation height management system and installation height management method
JP2020033762A