Simulation device, program, and simulation method

The simulation device allocates product orders to both completed and in-progress intermediate inventories, enhancing production planning by simulating manufacturing processes and adjusting delivery dates, thus optimizing inventory management.

JP7562236B2Active Publication Date: 2024-10-07KOBE STEEL LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
JP2021118533
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-07-19
Publication Date
2024-10-07
Estimated Expiration
2041-07-19

AI Technical Summary

Technical Problem

Existing production planning methods only allocate product orders to intermediate inventories that have been manufactured, failing to account for those in the middle of manufacturing.

Method used

A simulation device and method that allocates product orders to both completed and in-progress intermediate inventories, simulating the manufacturing process to connect the remaining steps and adjust delivery dates accordingly.

Benefits of technology

Enables the formulation of a more accurate production plan by considering in-progress intermediate inventories, optimizing inventory allocation and reducing delivery delays.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007562236000001
    Figure 0007562236000001
  • Figure 0007562236000002
    Figure 0007562236000002
  • Figure 0007562236000003
    Figure 0007562236000003
Patent Text Reader

Abstract

To obtain a simulation device capable of simulating an order for a product by allocating not only an intermediate stock that has already been manufactured but also an intermediate stock that is in the process of manufacturing.SOLUTION: A simulation device includes a data input unit 22 for inputting forecast data of product orders and production plan data of intermediate stocks, an inventory allocation unit 26 capable of allocating the product order input by the data input unit 22 to an intermediate stock, and a result output unit 23 for outputting simulation results including excess / deficiency of intermediate inventory. Intermediate inventory to be allocated by the inventory allocation unit 26 includes intermediate inventory that has already been manufactured and intermediate inventory that is in the process of manufacturing.SELECTED DRAWING: Figure 2
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a simulation device, a program, and a simulation method. [Background technology]

[0002] The following Patent Document 1 discloses a production planning method for a production management system that holds intermediate stocks in multiple manufacturing processes during production. This method makes it possible to allocate product orders to intermediate stocks. [Prior art documents] [Patent documents]

[0003] [Patent Document 1] Patent No. 5442526 Summary of the Invention [Problem to be solved by the invention]

[0004] However, the production planning method described in the above Patent Document 1 is based on the premise that intermediate inventory is completed at the time of allocation, so orders for products can only be allocated to intermediate inventory that has already been manufactured.

[0005] The present invention has been made in consideration of the above circumstances, and has an object to provide a simulation device, a program, and a simulation method that are capable of simulating product orders by allocating not only already manufactured intermediate inventory but also intermediate inventory in the middle of production. [Means for solving the problem]

[0006] A simulation device according to one embodiment of the present invention is a simulation device for formulating a production plan for intermediate inventory for a production line that manufactures products from raw materials through a plurality of manufacturing processes, and includes a data input unit that inputs forecast data for product orders and production plan data for intermediate inventory, an inventory allocation unit that is capable of allocating the product orders input by the data input unit to intermediate inventory, and a result output unit that outputs simulation results including intermediate inventory surpluses and shortages, where the intermediate inventory to be allocated by the inventory allocation unit includes intermediate inventory that has been manufactured and intermediate inventory that is in the process of being manufactured.

[0007] According to this embodiment, the inventory allocation unit can simulate the product orders entered by the data input unit by allocating them not only to intermediate inventory that has already been manufactured but also to intermediate inventory in the process of being manufactured, making it possible to appropriately formulate a production plan for intermediate inventory based on the product order forecast (order plan).

[0008] In the above aspect, the system further includes an order job generation unit which generates an order job related to the product order input by the data input unit, and when the inventory allocation unit allocates the product order to intermediate inventory in the middle of production, the order job generation unit generates, as an order job, a production process which connects the remaining production process until the intermediate inventory is completed and the production process from the intermediate inventory to the product.

[0009] According to this embodiment, when the inventory allocation unit allocates an order for a product to intermediate inventory in the middle of production, it becomes possible to simulate the manufacturing process that connects the remaining manufacturing process until the intermediate inventory is completed and the manufacturing process from the intermediate inventory to the product as an order job.

[0010] In the above aspect, the system further includes an intermediate inventory job management unit that manages intermediate inventory jobs related to the production of intermediate inventory, and when the inventory allocation unit allocates an order for a product to intermediate inventory in the middle of production, the intermediate inventory job management unit changes the intermediate inventory job related to the allocated intermediate inventory to the order job generated by the order job generation unit.

[0011] According to this aspect, when the inventory allocation unit allocates an order for a product to intermediate inventory during production, it becomes possible to change the intermediate inventory job to an order job and perform a simulation thereafter.

[0012] In the above aspect, the system further includes a delivery date setting unit, and when the inventory allocation unit allocates a product order to intermediate inventory, the delivery date setting unit sets the delivery date of the product order for the intermediate inventory allocated by the inventory allocation unit.

[0013] According to this aspect, when the inventory allocation unit allocates an order for a product to intermediate inventory, it becomes possible to perform simulations thereafter based on the order delivery date of the product rather than the completion delivery date of the intermediate inventory.

[0014] In the above aspect, the delivery date setting unit sets a completion delivery date for surplus intermediate stock that has not been allocated by the inventory allocation unit because the order quantity of the product is less than the intermediate stock quantity.

[0015] According to this aspect, for intermediate stock that has not been allocated by the stock allocation unit, it is possible to perform a simulation based on the completion delivery date of the intermediate stock, rather than the order delivery date of the product.

[0016] In the above aspect, the system further includes an order job generation unit which generates an order job related to the product order input by the data input unit, and when the inventory allocation unit allocates the product order to an intermediate inventory that has already been manufactured, the order job generation unit generates an order job for the manufacturing process from the intermediate inventory to the product.

[0017] According to this aspect, when the inventory allocation unit allocates an order for a product to manufactured intermediate inventory, it becomes possible to thereafter simulate the manufacturing process from the intermediate inventory to the product as an order job.

[0018] A program according to one embodiment of the present invention is a program for causing a computer mounted on a simulation device for formulating a production plan for intermediate inventory, for a production line which manufactures products from raw materials through multiple manufacturing processes, to function as: a data input means for inputting forecast data for product orders and production plan data for intermediate inventory; an inventory allocation means capable of allocating the product orders input by the data input means to intermediate inventory; and a result output means for outputting a simulation result including intermediate inventory surplus or shortage, wherein the intermediate inventory to be allocated by the inventory allocation section includes intermediate inventory which has already been manufactured and intermediate inventory which is in the process of being manufactured.

[0019] According to this embodiment, the product order inputted by the data input means can be simulated by the inventory allocation means by allocating it not only to already manufactured intermediate inventory but also to intermediate inventory in the middle of production, and as a result, it becomes possible to appropriately formulate a production plan for intermediate inventory based on the product order forecast (order plan).

[0020] A simulation method according to one embodiment of the present invention is a simulation method for formulating a production plan for intermediate inventory for a production line that manufactures products from raw materials through a number of manufacturing processes, in which forecast data for product orders and production plan data for intermediate inventory are input, the input product orders are allocated to intermediate inventory, the intermediate inventory to be allocated includes intermediate inventory that has already been manufactured and intermediate inventory that is in the process of being manufactured, and a simulation result including surplus or shortage of intermediate inventory is output.

[0021] According to this embodiment, the input product order can be simulated by allocating not only already manufactured intermediate inventory but also intermediate inventory in the process of being manufactured, and as a result, it becomes possible to appropriately formulate a production plan for intermediate inventory based on the product order forecast (order plan). Effect of the Invention

[0022] According to the present invention, it is possible to perform a simulation of an order for a product by allocating not only the intermediate inventory of a product that has already been manufactured but also the intermediate inventory in the middle of the manufacturing process. [Brief description of the drawings]

[0023] [Figure 1] 1 is a diagram showing a simplified configuration of a simulation device according to an embodiment of the present invention; [Diagram 2] FIG. 2 is a simplified diagram showing functions of a data processing unit. [Diagram 3] FIG. 13 is a simplified diagram illustrating an example of an intermediate inventory master. [Figure 4] FIG. 13 is a diagram illustrating a simplified example of a product type master. [Diagram 5] FIG. 13 is a diagram showing a simplified example of order forecast data. [Figure 6] FIG. 13 is a diagram showing a simplified example of intermediate inventory production plan data. [Figure 7] 10 is a flowchart showing the flow of processing executed by a data processing unit. [Figure 8] FIG. 13 is a diagram illustrating an example of a simulation. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0024] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. In the drawings, the same components are designated by the same reference numerals, and detailed descriptions thereof will be omitted as appropriate.

[0025] FIG. 1 is a diagram showing a simplified configuration of a simulation device 1 according to an embodiment of the present invention. The simulation device 1 is a simulation device for formulating a production plan for intermediate inventory, which is a semi-finished product in the middle of production, for a production line that manufactures products from raw materials through multiple manufacturing processes. The simulation device 1 is configured by a computer system or the like, and includes a data processing unit 11, an input unit 12, memory units 13 and 14, and a display unit 15. The data processing unit 11 is a CPU or the like, the input unit 12 is a mouse or a keyboard or the like, the memory unit 13 is a HDD or an SSD or the like, the memory unit 14 is a ROM or a RAM or the like, and the display unit 15 is an LCD or an organic EL display or the like. A program 100 is stored in the memory unit 14.

[0026] 2 is a diagram showing in simplified form the functions of the data processing unit 11. When the data processing unit 11 executes the program 100, the data processing unit 11 functions as a simulation engine 21, a data input unit 22 (input interface), a result output unit 23 (output interface), an inventory management unit 24, an order management unit 25, an inventory allocation unit 26, an order job generation unit 27, an intermediate inventory job management unit 28, a remaining process information creation unit 29, and a delivery date setting unit 30. In other words, the program 100 is a program for causing a computer mounted on the simulation device 1 to function as these processing units. The processing contents of each processing unit will be described later.

[0027] In addition, an intermediate stock master 51, a product type master 52, order forecast data 53, and intermediate stock production plan data 54 are created in advance and stored in the storage unit 13. A simulation result 55 is stored in the storage unit 13 and is displayed on the display unit 15.

[0028] 3 is a simplified diagram showing an example of the intermediate inventory master 51. In the intermediate inventory master 51, manufacturing process information (equipment used, work load, and inter-process lead time) from raw materials to completion as intermediate inventory is set for each intermediate inventory type. The intermediate inventory type is the type of intermediate inventory, and in this example, two types of intermediate inventory types Ca and Cb are set. Since intermediate inventory is versatile, there may be multiple product types that can be allocated to a certain intermediate inventory.

[0029] 4 is a simplified diagram showing an example of the product type master 52. In the product type master 52, manufacturing process information (equipment used, work load, and inter-process lead time) from intermediate stock to product completion is set for each product type. In this example, two types of products, A and B, are set. Product A can be manufactured from intermediate stock of intermediate stock type Ca through processes 1 to 5. Product B can be manufactured from intermediate stock of intermediate stock type Ca through processes 1 to 5, and can also be manufactured from intermediate stock of intermediate stock type Cb through processes 1 to 3.

[0030] 5 is a simplified diagram showing an example of order forecast data 53. In the order forecast data 53, forecasts of product types, production volume (weight), order timing (order entry date), and delivery dates are set for each order. In this example, two orders S1 and S2 are set.

[0031] 6 is a simplified diagram showing an example of intermediate inventory production plan data 54. In the intermediate inventory production plan data 54, the production volume (weight) of the intermediate inventory, the production start timing (production start date), and the target completion timing (target completion date) corresponding to the delivery date of the intermediate inventory are set for each intermediate inventory type. In this example, two types of intermediate inventory types Ca and Cb are set.

[0032] Note that the contents and numerical values ​​shown in Figures 3 to 6 are merely examples and are not limited to these. In addition, in the examples shown in Figures 3 to 6, a "day" is assumed as the timing mesh, but the timing mesh may be defined by any unit period other than a "day".

[0033] 7 is a flowchart showing the flow of processing executed by the data processing unit 11. For example, the operator inputs a command to start execution of a simulation, whereby the following processing is started.

[0034] First, in step SP101, the data input unit 22 reads the intermediate inventory master 51, the product type master 52, the order forecast data 53, and the intermediate inventory production plan data 54 from the storage unit 13.

[0035] Next, in step SP102, the simulation engine 21 sets the simulation date through initialization.

[0036] Next, in step SP103, the simulation engine 21 refers to the intermediate inventory production plan data 54 to determine whether or not there will be an input of intermediate inventory on the simulation date.

[0037] If intermediate stock is to be added on the simulation day (step SP103: YES), then in step SP104, the simulation engine 21 generates an intermediate stock job, and then executes the process of step SP105. The simulation engine 21 sets the earliest start timing at the equipment for the first process as the production start timing of the intermediate stock, and simulates it as a job with the target completion timing as the delivery date. Also, unless it is allocated to an order, it simulates up to the final process as intermediate stock, and after the final process is completed, it is held in inventory. The quantity of intermediate stock is updated when it becomes inventory.

[0038] If there is no intermediate inventory input on that simulation date (step SP103: NO), then in step SP105, the simulation engine 21 refers to the order forecast data 53 to determine whether or not there will be an order for the product input on that simulation date.

[0039] If an order is placed on the simulation day (step SP105: YES), then in step SP106, the simulation engine 21 adds the order to the placed orders, and then executes the process of step SP107.

[0040] If no orders are entered on that simulation day (step SP105: NO), then in step SP107, the simulation engine 21 determines whether or not there are any orders to be searched for. If there are any unallocated orders remaining on that simulation day, the result of the determination is "YES", and if there are no unallocated orders remaining, the result of the determination is "NO".

[0041] If there are any unallocated orders remaining (step SP107: YES), then in step SP108, the inventory allocation unit 26 searches for intermediate inventory to which the orders are to be allocated.

[0042] Next, in step SP109, the simulation engine 21 judges whether or not an intermediate inventory to which the allocation is to be made has been found.

[0043] If no intermediate stock to which the item is to be allocated is found (step SP109: NO), the simulation engine 21 executes the processes from step SP107 onwards for the next order.

[0044] If intermediate stock to which the order is to be allocated is found (step SP109: YES), then in step SP110, the inventory allocation unit 26 allocates the order to the intermediate stock. The order is allocated to the intermediate stock at the allocation timing corresponding to the order timing. The intermediate stock to be allocated includes not only completed intermediate stock but also intermediate stock in the middle of production or raw materials. If there are multiple intermediate stocks available for allocation, intermediate stock with a small number of production steps after allocation, intermediate stock with a small total lead time after allocation, intermediate stock with a small total lead time and processing time after allocation, intermediate stock with a long retention time as inventory, intermediate stock with a small number of product varieties to which the order is to be allocated, or intermediate stock with a small total order weight of the products to which the order is to be allocated will be allocated with priority.

[0045] Next, in step SP111, the order job generating section 27 generates an order job, the remaining process information creating section 29 sets the remaining process, and the delivery date setting section 30 sets the delivery date of the order. Also, the order management section 25 decreases the quantity of the submitted order.

[0046] When the inventory allocation unit 26 allocates an order for a product to intermediate inventory in the middle of production, the order job generation unit 27 generates, as an order job, a manufacturing process that connects the remaining manufacturing process until the intermediate inventory is completed and the manufacturing process from the intermediate inventory to the product. Also, when the inventory allocation unit 26 allocates an order for a product to intermediate inventory in the middle of production, the intermediate inventory job management unit 28 changes the intermediate inventory job related to the allocated intermediate inventory to an order job generated by the order job generation unit 27.

[0047] On the other hand, when the inventory allocation unit 26 allocates the product order to the manufactured intermediate inventory, the order job generation unit 27 generates the manufacturing process from the intermediate inventory to the product as an order job.

[0048] For jobs for orders allocated to intermediate inventory, the allocation timing is set as the starting point on the time axis, and the remaining manufacturing process is simulated. The simulation method is not limited, but for example, a method of piling up or collapsing the load with equipment capacity as a constraint can be used. In the method of piling up or collapsing the load, a rule can be applied that prioritizes jobs with less margin for the delivery date.

[0049] When the inventory allocation unit 26 allocates an order for a product to intermediate inventory, the delivery date setting unit 30 sets a delivery date for the product order for the intermediate inventory allocated by the inventory allocation unit 26, and the simulation engine 21 performs a simulation with a priority based on the delivery date of the product. Also, for surplus intermediate inventory that was not allocated by the inventory allocation unit 26 because the number of product orders is less than the intermediate inventory quantity, the delivery date setting unit 30 sets a completion delivery date for the intermediate inventory, and the simulation engine 21 performs a simulation with a priority based on the completion delivery date for the intermediate inventory.

[0050] Next, in step SP112, the simulation engine 21 judges whether the intermediate inventory to which the allocation is made is in the middle of production or has been completed.

[0051] If the intermediate stock of the allocation destination is in the middle of production (step SP112: YES), then in step SP113, the intermediate stock job management unit 28 decreases the quantity of the intermediate stock job of the allocation destination.

[0052] If the intermediate inventory to be allocated has been completed (step SP112: NO), then in step SP114, the inventory management unit 24 decreases the quantity of the completed intermediate inventory.

[0053] If there are no unallocated orders (step SP107: NO), then in step SP115, the simulation engine 21 determines processing tasks based on priority by adjusting the load for each facility. Note that a task means the work of each process included in the multiple processes that make up a job.

[0054] Next, in step SP116, the inventory management unit 24 adds the quantity of completed intermediate inventory, and the order management unit 25 adds the quantity of shipped orders.

[0055] Next, in step SP117, the simulation engine 21 updates the next process task information based on the next process and the earliest start date for each job.

[0056] Next, in step SP118, the simulation engine 21 updates the simulation date to the next day.

[0057] Next, in step SP119, the simulation engine 21 judges whether or not to end the simulation. For example, if a preset simulation end date has passed, it is judged that the simulation is to be ended.

[0058] If the simulation is not to be ended (step SP119: NO), the processing from step SP103 onwards is repeatedly executed.

[0059] When the simulation is to be ended (step SP120), the result output unit 23 outputs the simulation result. The simulation result includes information indicating an excess or shortage of intermediate inventory, such as the amount of intermediate inventory held by day. The simulation result also includes the order and manufacturing schedule for each job (when and which equipment will process each process). The simulation result also includes the allocation result for each order (when and which process of which job will it be allocated to). The simulation result also includes information indicating the manufacturing lead time for each order (from the first process to the final process) and the customer lead time (from order entry to the final process), which can be calculated based on this information.

[0060] Fig. 8 is a diagram showing an example of a simulation in the case where the master and data shown in Fig. 3 to 6 are inputted. The contents of the simulation will be explained below for each day.

[0061] April 1st The simulation date is initialized to April 1st.

[0062] April 2 From the intermediate stock production plan data 54, a job for manufacturing 20 tons of intermediate stock type Ca is created, and a load (10 min / ton*20 tons=200 min) is piled up in the first process, hot rolling.

[0063] Due to load adjustment in hot rolling, the intermediate stock type Ca is processed in hot rolling and piled up as a next processing task in cold rolling 2, which is the second process, on April 4th, two days later (the lead time of the intermediate stock master 51).

[0064] April 4 In cold rolling 2, intermediate stock type Ca is processed.

[0065] 20 tons of intermediate inventory type Ca will be completed. This completion date is in time for the target completion date Ta of April 4th.

[0066] April 6 From the intermediate inventory production plan data 54, a job for manufacturing 60 tons of intermediate inventory type Cb is created, and a load (8 min / ton*60 tons=480 min) is piled up in the first process, hot rolling.

[0067] Due to the load adjustment in hot rolling, intermediate stock type Cb is processed by hot rolling, and two days later (the lead time of the intermediate stock master 51), on April 8, the load (12 minutes / ton * 60 tons = 720 minutes) is piled up in the second process, cold rolling 1, as the next processing task.

[0068] April 7 Based on the order forecast data 53, order S1 (product type A, 30 tons) is added to the existing orders.

[0069] It is determined that product A can be allocated to intermediate stock type Ca from product master 52. Since there is 20 tons of intermediate stock type Ca at this point, 20 tons of the 30 tons of order S1 are allocated to intermediate stock type Ca. The remaining 10 tons of order S1 will remain as remaining allocation.

[0070] A job for order S1 (20 tons) is created. The remaining process is set based on the process information in the product type master 52. April 13th is set as the delivery date based on the order forecast data 53.

[0071] The load (40min / ton*20ton=800min) is piled up on Annealing 1, the first of the remaining processes.

[0072] In annealing 1, order S1 is processed.

[0073] One day later (the lead time of the product type master 52), on April 8, a load (15 minutes / ton*20 tons=300 minutes) is piled up as the next processing task in the second process, which is cleaning.

[0074] The submitted order weight (i.e. remaining allocated weight) of order S1 on April 8 (the next day) is updated to 10 tons.

[0075] April 8 Order S1 (20 tons) is processed in the washing process.

[0076] Due to the load adjustment in cleaning, order S1 is processed in cleaning, and two days later (the lead time of product type master 52), on April 10th, the load (15 minutes / ton * 20 tons = 300 minutes) is piled up in the third process, plating, as the next processing task.

[0077] In cold rolling 1, intermediate stock type Cb (60 tons) is processed.

[0078] One day later (the lead time of the intermediate inventory master 51), on April 9th, a load (12 minutes / ton*60 tons=720 minutes) is piled up in the cold rolling 2, which is the third process, as a next processing task.

[0079] April 9 Based on the order forecast data 53, order S2 (product type B, 40 tons) is added to the existing orders.

[0080] From the product type master 52, it is determined that product type B can be allocated to intermediate inventory types Ca and Cb. At this point, there is neither finished product inventory nor in-process inventory in intermediate inventory type Ca. As there is no finished product inventory in intermediate inventory type Cb, but there is 60 tons in-process inventory (in-process inventory of cold rolling 2 in the third process), all of order S2 (40 tons) is allocated to in-process intermediate inventory type Cb. In other words, of the in-process intermediate inventory type Cb (60 tons), 40 tons are simulated with the order, process information, and delivery date changed to order S2. The remaining 20 tons are simulated as intermediate inventory type Cb.

[0081] A job for order S2 (40 tons) is generated. The remaining processes are set based on the process information in the product type master 52. At this time, the third and subsequent processes of intermediate stock type Cb are connected to the process information of product type B (allocated intermediate stock type Cb) in the product type master 52, and process information consisting of cold rolling 2, annealing 2, cleaning, plating, slittering, and shipping inspection is set.

[0082] Based on the order forecast data 53, April 15th is set as the delivery date.

[0083] The weight of intermediate inventory type Cb, which is the allocation destination, is reduced by the amount allocated to order S2. Specifically, the weight is updated to 20 tons (60 tons - 40 tons) and the load is updated to 400 minutes (20 minutes / ton * 20 tons).

[0084] A load (20 min / ton * 40 ton = 800 min) is piled up in cold rolling 2, which is the first remaining process of order S2.

[0085] In cold rolling 2, order S2, which has little margin for the delivery date, is processed. In this example, since there are other items with higher priority, intermediate stock type Cb, which has margin for the delivery date, is not processed. In other words, by performing a simulation based on the delivery date, jobs after allocation to order S2 will flow through the process faster than jobs as intermediate stock. This makes it possible to avoid delivery delays caused by waiting for intermediate stock to be completed.

[0086] As for intermediate stock type Cb, the processing was carried over, so a load of 400 minutes was piled up in the same cold rolling mill 2 on the following day, April 10th.

[0087] For order S2, a load (30 minutes / ton*40 tons=1200 minutes) is piled up as a next processing task in annealing 2, which is the second process, on April 10, one day later (the lead time of the product type master 52).

[0088] The submitted order weight (remaining allocated weight) of order S2 on the following day, April 10, is updated to 0 tons.

[0089] April 10 In cold rolling 2, intermediate stock type Cb (20 tons) is processed.

[0090] Due to the load adjustment in cold rolling 2, the load (30 minutes / ton * 20 tons = 600 minutes) of intermediate inventory type Cb will be piled up as the next processing task in annealing 2, which is the fourth process, on April 11th, one day later (the lead time of the intermediate inventory master 51).

[0091] In annealing 2, order S2 is processed.

[0092] Due to the load adjustment in Annealing 2, the load (10 minutes / ton * 40 tons = 400 minutes) of order S2 will be piled up as the next processing task in the third process, cleaning, on April 11th, one day later (the lead time of product type master 52).

[0093] Order S1 (20 tons) is processed for plating.

[0094] Due to the load adjustment in plating, the load (20 minutes / ton * 20 tons = 400 minutes) of order S1 will pile up as the next processing task in the slitter, which is the fourth process, on April 11th, one day later (the lead time of product type master 52).

[0095] April 12 The final process (shipping inspection) of order S1 is completed one day earlier than the delivery date T1, making it possible to ship.

[0096] April 14 Intermediate inventory type Cb (20 tons) will be completed one day earlier than the target completion date Tb.

[0097] April 15 The final process (shipping inspection) of order S2 is completed on the same day as delivery date T2, making it available for shipment.

[0098] <Summary> According to the simulation device 1 of this embodiment, the product order input by the data input unit 22 can be simulated by allocating not only the manufactured intermediate stock but also the intermediate stock in the middle of production by the inventory allocation unit 26. As a result, it becomes possible to appropriately formulate a production plan for the intermediate stock based on the product order forecast (order plan).

[0099] Furthermore, according to the simulation device 1 of this embodiment, when the inventory allocation unit 26 allocates an order for a product to intermediate inventory in the middle of production, it becomes possible to thereafter simulate, as an order job, the production process that connects the remaining production process until the intermediate inventory is completed and the production process from the intermediate inventory to the product.

[0100] Furthermore, according to the simulation device 1 of this embodiment, when the inventory allocation unit 26 allocates an order for a product to intermediate inventory during production, it becomes possible to change the intermediate inventory job to an order job and perform a simulation thereafter.

[0101] Furthermore, according to the simulation device 1 of this embodiment, when the inventory allocation unit 26 allocates a product order to intermediate inventory, it becomes possible to perform simulations based on the order delivery date of the product rather than the completion delivery date of the intermediate inventory.

[0102] Furthermore, according to the simulation device 1 of this embodiment, for intermediate stock not allocated by the stock allocation unit 26, it is possible to perform a simulation based on the completion delivery date of the intermediate stock, rather than the order delivery date of the product.

[0103] Furthermore, according to the simulation device 1 of this embodiment, when the inventory allocation unit 26 allocates an order for a product to an intermediate inventory that has already been manufactured, it becomes possible to thereafter simulate the manufacturing process from the intermediate inventory to the product as an order job. [Explanation of symbols]

[0104] 1 Simulation device 11 Data Processing Section 21 Simulation Engine 22 Data Entry Section 23 Result output section 26 Inventory Allocation Department 27 Order job generation unit 28 Intermediate Stock Job Management Department 30 Delivery Date Setting Department 100 Programs

Claims

1. A simulation device for formulating a production plan for intermediate inventory for a production line that manufactures products from raw materials through multiple manufacturing processes, comprising: a data input unit for inputting forecast data of product orders and production plan data of intermediate inventory; an inventory allocation unit capable of allocating the product order inputted by the data input unit to intermediate inventory; The intermediate inventory to be allocated by the inventory allocation unit includes completed intermediate inventory and intermediate inventory in the middle of production, a result output unit that outputs a simulation result including an intermediate inventory surplus or shortage; An inventory management department that manages completed intermediate inventory; an intermediate inventory job management unit that manages intermediate inventory jobs related to the manufacture of intermediate inventory; an order job generating unit that generates an order job related to an order for the product input by the data input unit; a delivery date setting unit that sets a delivery date for a product order for the allocated intermediate inventory; a simulation engine for executing the simulation; Equipped with When the inventory allocation unit allocates an order for a product to intermediate inventory, the simulation engine performs a simulation with a priority based on the delivery date of the product set by the delivery date setting unit, and determines whether the intermediate inventory to be allocated is in the middle of production or has been completed, When the intermediate inventory of the allocation destination is in the middle of production, the intermediate inventory job management unit decreases the quantity of the intermediate inventory job of the allocation destination, while When the intermediate inventory of the allocation destination is completed, the inventory management unit decreases the quantity of the completed intermediate inventory of the allocation destination. Simulation device.

2. 2. The simulation device according to claim 1, wherein the delivery date setting unit sets a completion delivery date for surplus intermediate inventory that has not been allocated by the inventory allocation unit because the number of orders for the product is less than the intermediate inventory quantity.

3. A computer installed in a simulation device that formulates a production plan for intermediate inventory for a production line that manufactures products from raw materials through multiple manufacturing processes is a data input unit for inputting forecast data of product orders and production plan data of intermediate inventory; an inventory allocation unit capable of allocating the product order inputted by the data input unit to intermediate inventory; The intermediate inventory to be allocated by the inventory allocation unit includes completed intermediate inventory and intermediate inventory in the middle of production, a result output unit that outputs a simulation result including an intermediate inventory surplus or shortage; An inventory management department that manages completed intermediate inventory; an intermediate inventory job management unit that manages intermediate inventory jobs related to the manufacture of intermediate inventory; an order job generating unit that generates an order job related to an order for the product input by the data input unit; a delivery date setting unit that sets a delivery date for a product order for the allocated intermediate inventory; a simulation engine for executing the simulation; A program for causing the device to function as a When the inventory allocation unit allocates an order for a product to intermediate inventory, the simulation engine performs a simulation with a priority based on the delivery date of the product set by the delivery date setting unit, and determines whether the intermediate inventory to be allocated is in the middle of production or has been completed, When the intermediate inventory of the allocation destination is in the middle of production, the intermediate inventory job management unit decreases the quantity of the intermediate inventory job of the allocation destination, while When the intermediate inventory of the allocation destination is completed, the inventory management unit decreases the quantity of the completed intermediate inventory of the allocation destination. program.

4. A simulation method for formulating a production plan for intermediate inventory for a production line that manufactures products from raw materials through multiple manufacturing processes, comprising the steps of: Enter the forecast data for product orders and production plan data for intermediate inventory, The entered product order is allocated to intermediate inventory, The intermediate inventory to be allocated includes completed intermediate inventory and intermediate inventory in the middle of production. Manage completed intermediate inventory, Manage intermediate inventory jobs related to intermediate inventory production; Generate order jobs for the entered product orders; Set delivery dates for product orders for the intermediate inventory allocated, Run the simulation, Output simulation results including intermediate inventory surpluses and shortages, When a product order is allocated to intermediate inventory, a simulation is performed based on the priority of the product's delivery date, and it is determined whether the intermediate inventory to which the product is allocated is in the process of being manufactured or has been completed. When the intermediate inventory of the allocation destination is in the middle of production, the quantity of the intermediate inventory job of the allocation destination is decreased, while If the intermediate inventory of the allocation destination is completed, the quantity of the completed intermediate inventory of the allocation destination is decreased. Simulation method.

Citation Information

Patent Citations

  • Engine exhaust controller

    JP1979042526A

  • Production tracing device

    JP1995296063A

  • Method and device for forming working process production plan

    JP1997153090A

  • Schedule preparation method, schedule preparation program, and schedule preparation device

    JP2011227605A