Model management system, model management method and model management program

The model management system addresses the complexity and cost issues of managing numerous inference models in substrate manufacturing by dividing them into hierarchical layers, facilitating efficient parameter sharing and optimization across different equipment types.

JP7563858B2Active Publication Date: 2024-10-08TOKYO ELECTRON LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
JP2022561826
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Priority Date
2020-11-10
Filing Date
2021-10-29
Publication Date
2024-10-08
Estimated Expiration
2041-10-29

AI Technical Summary

Technical Problem

The management of numerous inference models in substrate manufacturing processes becomes complex and costly due to the use of multiple types of equipment and processes in various chambers, leading to an increase in the number of models that need to be optimized.

Method used

A model management system that divides models into multiple layers, with a first management unit managing models in a predetermined hierarchy, calculating new model parameters, controlling their settings, and transmitting these parameters to higher-level management units, allowing for efficient model parameter sharing and reduction of management costs.

Benefits of technology

This approach efficiently manages models by consolidating the number of models and reducing management costs, enabling effective optimization and updating of model parameters across different layers and equipment types in substrate manufacturing processes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007563858000001
    Figure 0007563858000001
  • Figure 0007563858000002
    Figure 0007563858000002
  • Figure 0007563858000003
    Figure 0007563858000003
Patent Text Reader

Abstract

Provided are a model management system, a model management method, and a model management program for efficiently managing a model applied to a substrate manufacturing process. A model management system for managing a model applied to a substrate manufacturing process, separately at three or more hierarchical levels. The model management system has a first management unit for managing a model at a prescribed hierarchical level and one or more second management units for managing models at hierarchical levels one hierarchical level below the prescribed hierarchical level, the first management unit having a calculation unit for calculating, when the model parameters of the models managed by the second management units are updated, a new model parameter on the basis of each of the updated model parameters, and a control unit for exercising control such that the new parameter is set to the model managed by each of a plurality of management units at the lowest hierarchical level belonging to the first management unit.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present disclosure relates to a model management system, a model management method, and a model management program. [Background technology]

[0002] In the field of substrate manufacturing processes, various inference models have been constructed and are used, for example, to detect abnormalities in equipment, infer the results of process processing, diagnose deterioration of components, infer internal states, and control processes.

[0003] On the other hand, in a substrate manufacturing process, multiple types of equipment are used, and various processes are performed in various types of chambers of each equipment model. Therefore, if each inference model is optimized, the number of inference models to be managed becomes enormous, which increases management costs. [Prior art documents] [Patent documents]

[0004] [Patent Document 1] International Publication No. 2018 / 173121 [Patent Document 2] International Publication No. 2019 / 163823 Summary of the Invention [Problem to be solved by the invention]

[0005] The present disclosure provides a model management system, a model management method, and a model management program that efficiently manage models applied to a substrate manufacturing process. [Means for solving the problem]

[0006] A model management system according to an aspect of the present disclosure has, for example, the following configuration. A model management system that manages models applied to a substrate manufacturing process by dividing the models into three or more hierarchical levels, A first management unit that manages models at a predetermined hierarchy; Manage models at a level one level lower than the specified level multiple and a second management unit, The first management unit is a calculation unit that calculates new model parameters based on each updated model parameter when the model parameters of the model managed by the second management unit are updated; a control unit that controls so that the new model parameters are set in models managed by each of a plurality of lowest-level management units belonging to the first management unit; 、 a transmission unit that transmits the new model parameters to a management unit that manages a model that is one level higher than the model managed by the first management unit; has. Effect of the Invention

[0007] According to the present disclosure, it is possible to provide a model management system, a model management method, and a model management program that efficiently manage models applied to a substrate manufacturing process. [Brief description of the drawings]

[0008] [Figure 1] FIG. 1 is a diagram illustrating an example of a system configuration of a model management system in the first phase. [Diagram 2] FIG. 2 is a diagram illustrating an example of a system configuration of the model management system in the second phase. [Diagram 3] FIG. 3 is a diagram illustrating an example of a system configuration of the model management system in the third phase. [Figure 4] FIG. 4 is a diagram illustrating an example of the system configuration of the model management system in the fourth phase. [Diagram 5] FIG. 5 is a diagram illustrating an example of a system configuration of the model management system in the fifth phase. [Figure 6] FIG. 6 is a diagram illustrating an example of the system configuration of the model management system in the sixth phase. [Figure 7]FIG. 7 is a diagram illustrating an example of the system configuration of the model management system in the seventh phase. [Figure 8] FIG. 8 is a sequence diagram showing the flow of a model management process by the model management system. [Figure 9] FIG. 9 is a diagram illustrating an example of the hardware configuration of the xth hierarchical management device. [Figure 10] FIG. 10 is a diagram illustrating an example of the functional configuration of the xth hierarchical management device. [Figure 11] FIG. 11 is a flowchart showing the flow of management processing by the xth hierarchical management device. [Figure 12] FIG. 12 is a diagram illustrating an example of a hardware configuration of the execution device. [Figure 13] FIG. 13 illustrates an example of a functional configuration of the execution device. [Figure 14A] FIG. 14A is a flowchart showing the flow of the sequential learning process performed by the execution device. [Figure 14B] FIG. 14B is a flowchart showing the flow of the batch learning process performed by the execution device. [Figure 15] FIG. 15 is a diagram illustrating an example of a system configuration of a model management system. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0009] Hereinafter, each embodiment will be described with reference to the accompanying drawings. In this specification and the drawings, components having substantially the same functional configurations are denoted by the same reference numerals, and redundant description will be omitted.

[0010] [First embodiment] <System configuration of model management system> First, the system configuration of the model management system according to the first embodiment will be described. The model management system according to the first embodiment has a plurality of management devices, and each management device manages models (model structures and model parameters) in each hierarchical level. The models managed by each management device may have one or more types of model structures (in the first embodiment, a case will be described in which each management device manages models with two types of model structures). Furthermore, in the model management system according to the first embodiment, when model parameters are optimized by performing a learning process on a model, new model parameters are generated, making it possible to share the model parameters between management devices in the same hierarchical level.

[0011] This consolidates the types of model parameters (i.e., the number of models) that each management device must manage, reducing management costs. Also, management costs (costs required for learning) are reduced compared to when a large amount of data is received from a management device at a lower level and re-learned.

[0012] As a result, the model management system according to the first embodiment makes it possible to efficiently manage models.

[0013] Therefore, in the following, the process by which model parameters are shared in the model management system will be explained in multiple phases.

[0014] (1) System configuration of the model management system in the first phase Fig. 1 is a diagram showing an example of a system configuration of a model management system in the first phase. As shown in Fig. 1, a model management system 100 includes a model management device 110, a learning data storage unit 111, and learning units 112_1 and 112_2.

[0015] The model management system 100 also includes a first hierarchical management device 120, second hierarchical management devices 131 to 133, . . . a (n-1)th hierarchical management device 141, and nth hierarchical management devices 151 and 152, which are an example of a management section.

[0016] Furthermore, the model management system 100 includes a substrate processing apparatus 160 , an execution apparatus 170 , a substrate processing apparatus 180 , and an execution apparatus 190 .

[0017] The learning data storage unit 111 stores learning data used when performing learning processing for a model (model structure="model A") having a model structure according to a first purpose. The first purpose here refers to, for example, detection of anomalies in a substrate processing apparatus, inference of the result of a process processing, diagnosis of deterioration of parts, inference of an internal state, etc. Inference of the result of a process processing includes inference of a film formation rate, inference of an etching rate, inference of the shape of the result, etc.

[0018] Furthermore, the learning data storage unit 111 stores learning data used when performing learning processing for a model (model structure="model B") having a model structure according to a second purpose. The second purpose here refers to, for example, a purpose such as process control.

[0019] The learning unit 112_1 has a model (model structure="model A") having a model structure according to the first purpose, and performs a learning process using learning data for the model structure="model A" read from the learning data storage unit 111. In addition, the learning unit 112_1 performs the learning process to obtain model parameters="parameters P A 0” to the model management device 110.

[0020] The learning unit 112_2 has a model (model structure="model B") having a model structure according to the second purpose, and performs a learning process using learning data for the model structure="model B" read out from the learning data storage unit 111. In addition, the learning unit 112_2 performs the learning process to obtain model parameters="parameters P B 0” to the model management device 110.

[0021] The model management device 110 stores two types of models (model structures=“model A” and “model B”; model parameters=“parameter P A 0”, “Parameter P B 0”). In the first phase, the model management device 110 manages two types of models (model structures=“model A” and “model B”, model parameters=“parameter P A 0”, “Parameter P B 0”) to the first hierarchical management device 120.

[0022] It is assumed that the model management device 110 and the first hierarchical management device 120 are connected to different networks via a firewall (not shown). It is also assumed that the first hierarchical management device 120 to the n-th hierarchical management devices 151, 152 are connected to the same local network in the same substrate processing factory.

[0023] The second hierarchical management devices 131, 132, 133 through the n-th hierarchical management devices 151, 152 manage models of substrate processing apparatuses in the same substrate processing factory according to their respective purposes by dividing them into a plurality of hierarchical groups.

[0024] For example, the second hierarchical management devices 131, 132, and 133 manage the models of the substrate processing apparatuses in the same substrate processing factory according to their respective purposes by dividing them into groups of substrate processing apparatuses having the same "equipment model." Specifically, when the substrate processing apparatuses are heat treatment apparatuses, for example, The second hierarchical management device 131 manages the models corresponding to the group of "heat treatment devices having an oxidation furnace" The second hierarchical management device 132 manages models corresponding to the group of "heat treatment devices having a nitriding furnace", The second hierarchical management device 133 manages the models of equipment corresponding to the group of "heat treatment equipment having a metal furnace."

[0025] Furthermore, when the substrate processing apparatus is an etching apparatus, for example, The second hierarchical management device 131 manages the models corresponding to the group of equipment types of “etching equipment for etching oxide films”; The second hierarchical management device 132 manages the models of equipment corresponding to the group of "etching equipment for etching poly-Si film."

[0026] Furthermore, the third hierarchical management device manages the models corresponding to the groups grouped by the second hierarchical management devices 131-133 among the models according to the respective purposes of the substrate processing apparatuses in the same substrate processing factory, by dividing them into groups of substrate processing apparatuses having the same "chamber type." Specifically, when the substrate processing apparatuses are heat treatment apparatuses, for example, The third hierarchical management device manages models that correspond to the group of heat treatment devices whose chamber type is "a chamber for processing an interlayer insulating film" among models whose equipment type corresponds to the group of "heat treatment devices having a nitriding furnace", Another third-level management device manages models corresponding to the group of heat treatment devices whose chamber type is "chamber for processing gate insulating film" among models corresponding to the group of heat treatment devices whose equipment type is "heat treatment devices having a nitridation furnace", Another third-level management device manages models corresponding to a group of heat treatment devices whose chamber type is a "chamber for processing a gate electrode layer" among models corresponding to a group of "heat treatment devices having a metal furnace"; Another third-level management device manages models that correspond to the group of heat treatment devices whose chamber type is a "chamber for processing metal films" among models whose equipment type corresponds to the group of "heat treatment devices having metal furnaces."

[0027] Furthermore, when the substrate processing apparatus is an etching apparatus, for example, The third hierarchical management device manages models that correspond to the group of etching equipment whose chamber type is "chamber for opening contact holes" among models that correspond to the group of "etching equipment for etching poly-Si films", The other third-level management devices manage models that correspond to the group of etching equipment whose chamber type is "chambers that process trenches for wiring" among models that correspond to the group of "etching equipment that etches poly-silicon films" in terms of equipment type.

[0028] In addition, the fourth-level management device is a model of each substrate processing equipment in the same substrate processing factory according to the purpose. Grouped by the second hierarchical management device, and Grouped by the third hierarchical management device, The models corresponding to each group are further divided into groups of substrate processing apparatuses having the same "process group" and managed. Specifically, when the substrate processing apparatus is a thermal processing apparatus, for example, The fourth hierarchical management device manages models corresponding to a group of heat treatment equipment in charge of the process group = "first process group" among models corresponding to a group of heat treatment equipment whose chamber type is "chamber for processing interlayer insulating film", Another fourth-level management device manages models corresponding to a group of thermal processing equipment responsible for the process group = "second process group" among models corresponding to a group of thermal processing equipment whose chamber type is "chamber for processing interlayer insulating film".

[0029] Furthermore, when the substrate processing apparatus is an etching apparatus, for example, The fourth hierarchical management device manages models corresponding to a group of etching equipment in charge of the process group = "first process group" among models corresponding to a group of etching equipment whose chamber type is "chamber for opening contact holes", Another fourth hierarchical level management device manages models corresponding to a group of etching equipment in charge of the process group = "second process group" among models corresponding to a group of etching equipment whose chamber type is "chamber for opening contact holes".

[0030] Returning to the explanation of the system configuration in Fig. 1, the first hierarchical management device 120 manages the model transmitted from the model management device 110. In addition, in the first phase, the first hierarchical management device 120 transmits the model transmitted from the model management device 110 to the second hierarchical management devices 131-133.

[0031] In the example of Figure 1, a case is shown in which three second hierarchical management devices are connected to the first hierarchical management device 120, but the number of second hierarchical management devices connected to the first hierarchical management device 120 is not limited to three.

[0032] The second hierarchical management devices 131-133 manage models transmitted from the connected first hierarchical management device 120. Note that, although the example in Fig. 1 shows a case where the same model is transmitted from the connected first hierarchical management device 120 to each of the second hierarchical management devices 131-133, the models transmitted to each of the second hierarchical management devices 131-133 may be different.

[0033] Furthermore, in the first phase, the second hierarchical management devices 131 to 133 each transmit the model transmitted from the first hierarchical management device 120 to a third hierarchical management device (not shown).

[0034] 1, the (n-1)th hierarchical management device 141 manages a model transmitted from the (n-2)th hierarchical management device to which it is connected. In addition, in the first phase, the (n-1)th hierarchical management device 141 transmits the model transmitted from the (n-2)th hierarchical management device to the nth hierarchical management devices 151 and 152.

[0035] In the example of Figure 1, a case is shown in which there are two nth hierarchical management devices connected to the (n-1)th hierarchical management device 141, but the number of nth hierarchical management devices connected to the (n-1)th hierarchical management device 141 is not limited to two.

[0036] 1, the nth hierarchical management devices 151 and 152 manage the model transmitted from the (n-1)th hierarchical management device to which they are connected. In addition, in the first phase, the nth hierarchical management devices 151 and 152 transmit the model transmitted from the (n-1)th hierarchical management device 141 to the execution devices 170 and 190.

[0037] The substrate processing apparatus 160 is a processing apparatus that performs a substrate manufacturing process in a physical space, such as a heat treatment apparatus or an etching apparatus.

[0038] The execution device 170 is The model (model structure = “Model A”, model parameters = “Parameter P A 0") is arranged in an inference unit 171_1, The model (model structure = “Model B”, model parameters = “Parameter P B 0") is arranged in an inference unit 171_2, has.

[0039] The inference unit 171_1 generates a model (model structure="model A", model parameters="parameter P A 0" is executed. Further, the inference unit 171_1 outputs an inference result (for example, an inference result of anomaly detection, an inference result of a process processing result, an inference result of part deterioration diagnosis, an inference result of an internal state, etc.). The inference result output from the inference unit 171_1 is stored in the actual measurement data storage unit 172 as actual measurement data, for example, in association with the correct answer data.

[0040] Further, the inference unit 171_2 generates a model (model structure="model B", model parameters="parameter P B0" is executed. The inference unit 171_2 outputs an inference result (for example, an inference result (control value) in process control, etc.). The inference result output from the inference unit 171_2 is stored in the actual measurement data storage unit 172 as actual measurement data, for example, in association with the correct answer data.

[0041] Similarly, the substrate processing apparatus 180 is a processing apparatus that performs a substrate manufacturing process in a physical space, such as a heat treatment apparatus or an etching apparatus.

[0042] The execution device 190 is The model (model structure = “Model A”, model parameters = “Parameter P A 0") is arranged in an inference unit 191_1, The model (model structure = "Model B", model parameters = "Parameter P B 0") is arranged in an inference unit 191_2, has.

[0043] The inference unit 191_1 generates a model (model structure="model A", model parameters="parameter P A 0" is executed. Further, the inference unit 191_1 outputs an inference result (for example, an inference result of anomaly detection, an inference result of a process processing result, an inference result of part deterioration diagnosis, an inference result of an internal state, etc.). The inference result output from the inference unit 191_1 is stored in the actual measurement data storage unit 192 as actual measurement data, for example, in association with the correct answer data.

[0044] Further, the inference unit 191_2 generates a model (model structure="model B", model parameters="parameter P B 0" is executed. Furthermore, the inference unit 191_2 outputs an inference result (for example, an inference result (control value) in process control, etc.). The inference result output from the inference unit 191_2 is stored in the actual measurement data storage unit 192 as actual measurement data, for example, in association with the correct answer data.

[0045] (2) System configuration of the model management system in the second phase Fig. 2 is a diagram showing an example of the system configuration of the model management system in the second phase. As shown in Fig. 2, in the second phase, in addition to the system configuration in the first phase, the execution device 170 of the model management system 100 further includes learning units 210_1 and 210_2. Also, the execution device 190 includes learning units 220_1 and 220_2.

[0046] The learning unit 210_1 receives the model (model structure="model A", model parameters="parameter P A 0”) is arranged. The learning unit 210_1 performs additional learning processing by using the actual measurement data read from the actual measurement data storage unit 172. As a result, the learning unit 210_1 performs an optimized model parameter=“parameter P A 1” to the n-th hierarchical management device 151.

[0047] In addition, the learning unit 210_2 receives the model (model structure="model B", model parameters="parameter P B 0”) is arranged. The learning unit 210_2 performs additional learning processing by using the actual measurement data read from the actual measurement data storage unit 172. As a result, the learning unit 210_2 performs an optimized model parameter=“parameter P A 1” to the n-th hierarchical management device 151.

[0048] Similarly, the learning unit 220_1 receives the model (model structure="model A", model parameters="parameter P A 0”) is arranged. The learning unit 220_1 performs additional learning processing by using the actual measurement data read out from the actual measurement data storage unit 192. As a result, the learning unit 220_1 performs an optimized model parameter=“parameter P A 2” to the n-th hierarchy management device 152.

[0049] In addition, the learning unit 220_2 receives the model (model structure="model B", model parameters="parameter P B 0”) is arranged. The learning unit 220_2 performs additional learning processing by using the actual measurement data read out from the actual measurement data storage unit 192. As a result, the learning unit 220_2 performs an optimized model parameter=“parameter P B 2” to the n-th hierarchy management device 152.

[0050] (3) System configuration of the model management system in the third phase 3 is a diagram showing an example of a system configuration of the model management system in the third phase. As shown in FIG. 3, in the third phase, the n-th hierarchical management device 151: Model structure = "Model A", "Model B" In the second phase, the model parameters transmitted from the learning units 210_1 and 210_2 are “parameters P A 1”, “Parameter P B 1” and Manage.

[0051] In the third phase, the n-th hierarchical management device 151 sets the model parameter=“parameter P A 1”, the model parameter set in the inference unit 171_1 is set to “parameter P A 0”. In the third phase, the n-th hierarchical management device 151 updates the model parameter=“parameter P B 1”, the model parameters set in the inference unit 171_2 are set to “parameter P B Update the byte to 0.

[0052] Similarly, the n-th hierarchical management device 152 Model structure = "Model A", "Model B" In the second phase, the model parameters transmitted from the learning units 220_1 and 220_2 are “parameters P A 2”, “Parameter PB 2” and Manage.

[0053] In the third phase, the n-th hierarchical management device 152 sets the model parameter=“parameter P A 2”, the model parameters set in the inference unit 191_1 are set to “parameter P A 0”. In the third phase, the n-th hierarchical management device 152 updates the model parameter=“parameter P B 2”, the model parameters set in the inference unit 191_2 are set to “parameter P B Update the byte to 0.

[0054] (4) System configuration of the model management system in the fourth phase 4 is a diagram showing an example of the system configuration of the model management system in the fourth phase. As shown in FIG. 4, in the fourth phase, the n-th hierarchical management device 151 performs a model parameter="parameter P A 1”, “Parameter P B 1” to the (n−1)th hierarchical management device 141.

[0055] Similarly, in the fourth phase, the n-th hierarchical management device 152 sets the model parameter="parameter P A 2”, “Parameter P B 2” to the (n−1)th hierarchical management device 141.

[0056] (5) System configuration of the model management system in the fifth phase 5 is a diagram illustrating an example of a system configuration of the model management system in the fifth phase. As shown in FIG. 5, in the fifth phase, the (n-1)th hierarchical management device 141: In the fourth phase, the model parameter=“parameter P A 1”, “Parameter P B 1” and In the fourth phase, the model parameter=“parameter P A 2”, “Parameter P B 2” and Based on the new model parameters = “Parameter P A 3”, “Parameter P B 3”. The (n-1)th hierarchical management device 141 may calculate the new model parameters in any manner. For example, A 1” and “Parameter P A 2” is weighted and added to obtain “parameter P A Similarly, the parameter P B 1” and “Parameter P B 2” is weighted and added to obtain “parameter P B 3" may be calculated.

[0057] In addition, the weights used in weighted addition are arbitrary. For example, among the parameters to be added, parameters that do not satisfy a predetermined evaluation criterion may be weighted to zero (or may be excluded from being added).

[0058] Also, as shown in FIG. 5, in the fifth phase, the (n-1)th hierarchical management device 141 creates a model structure="model A", "model B" and a new model parameter="parameter P A 3”, “Parameter P B In the fifth phase, the (n-1)th hierarchical management device 141 manages the new model parameters=“parameter P A 3”, “Parameter P B 3” to the n-th hierarchical management devices 151 and 152 connected to the (n−1)-th hierarchical management device 141.

[0059] Furthermore, as shown in FIG. 5, in the fifth phase, the n-th hierarchical management devices 151 and 152 Model structure = "Model A", "Model B" New model parameters=“Parameter PA 3”, “Parameter P B 3” and Manage.

[0060] In the fifth phase, the n-th hierarchical management device 151 sets a new model parameter=“parameter P A 3”, the model parameters set in the model arranged in the inference unit 171_1 are set to “parameter P A In the fifth phase, the n-th hierarchical management device 151 updates the new model parameter=“parameter P B 3”, the model parameters set in the model arranged in the inference unit 171_2 are set to “parameter P B 1” will be updated.

[0061] Furthermore, in the fifth phase, the n-th hierarchical management device 152 sets a new model parameter=“parameter P A 3”, the model parameters set in the model arranged in the inference unit 191_1 are set to “parameter P A In the fifth phase, the n-th hierarchical management device 152 updates the new model parameter=“parameter P B 3”, the model parameters set in the model arranged in the inference unit 191_2 are set to “parameter P B 2”.

[0062] As a result, new model parameters ("parameters P A 3”, “Parameter P B 3”) is set. That is, the models managed by the n-th hierarchical management devices 151, 152 at the lowest level belonging to the (n−1)-th hierarchical management device 141 are shared (the model is shared between the n-th hierarchical management devices).

[0063] (6) System configuration of the model management system in the sixth phase 6 is a diagram showing an example of the system configuration of the model management system in the sixth phase. As shown in FIG. 6, in the sixth phase, the (n-1)th hierarchical management device 141 receives a new model parameter="parameter P A 3”, “Parameter P B 3” to the (n−2)th hierarchical management device. Note that, in this example, the (n−2)th hierarchical management device is described as the second hierarchical management device 132.

[0064] Similarly, in the sixth phase, the other (n-1)th hierarchical management devices connected to the second hierarchical management device 132 transmit new model parameters to the second hierarchical management device 132 at a predetermined timing.

[0065] Also, as shown in FIG. 6, in the sixth phase, the other (n-1)th hierarchical management devices connected to the second hierarchical management devices 131 and 133 transmit new model parameters to the second hierarchical management devices 131 and 132, respectively, at predetermined timing.

[0066] (7) System configuration of the model management system in the seventh phase 7 is a diagram showing an example of the system configuration of the model management system in the seventh phase. As shown in FIG. 7, in the seventh phase, the second hierarchical management device 132: In the sixth phase, the model parameter=“parameter P A 3”, “Parameter P B 3” and In the sixth phase, model parameters transmitted from a plurality of other (n-1)th hierarchical management devices connected to the second hierarchical management device 132; and Based on the new model parameters = “Parameter P A 6”, “Parameter P B 6” is calculated.

[0067] As shown in FIG. 7, in the seventh phase, the second hierarchical management device 132 creates a model structure="model A", "model B" and a new model parameter="parameter P A 6”, “Parameter P B In the seventh phase, the second hierarchical management device 132 manages the new model parameters=“parameter P A 6”, “Parameter P B 6” to the (n−1)th hierarchical management device 141, etc.

[0068] Furthermore, as shown in FIG. 7, in the seventh phase, the (n-1)th hierarchical management device 141: Model structure = "Model A", "Model B" New model parameters=“Parameter P A 6”, “Parameter P B 6” and Manage.

[0069] Furthermore, as shown in FIG. 7, in the seventh phase, the (n-1)th hierarchical management device 141 sets a new model parameter=“parameter P A 6”, “Parameter P B 6” to the n-th hierarchical management devices 151 and 152 connected to the (n−1)-th hierarchical management device 141.

[0070] Furthermore, as shown in FIG. 7, in the seventh phase, the n-th hierarchical management devices 151 and 152 Model structure = "Model A", "Model B" New model parameters=“Parameter P A 6”, “Parameter P B 6” and Manage.

[0071] Furthermore, in the seventh phase, the n-th hierarchical management device 151 sets a new model parameter=“parameter P A6”, the model parameters set in the model arranged in the inference unit 171_1 are set to “parameter P A In the seventh phase, the n-th hierarchical management device 151 updates the new model parameter=“parameter P B 6”, the model parameters set in the model arranged in the inference unit 171_2 are set to “parameter P B 3”.

[0072] In the seventh phase, the n-th hierarchical management device 152 sets a new model parameter=“parameter P A 6”, the model parameters set in the model arranged in the inference unit 191_1 are set to “parameter P A In the seventh phase, the n-th hierarchical management device 152 updates the new model parameter=“parameter P B 6”, the model parameters set in the model arranged in the inference unit 191_2 are set to “parameter P B 3”.

[0073] As a result, new model parameters ("parameters P A 6”, “Parameter P B 6”) is set. That is, the models managed by the n-th hierarchical management devices 151, 152 in the lowest hierarchical level belonging to the second hierarchical management device 132 are shared (the model is shared between the management devices in the third hierarchical level).

[0074] In the above explanation, the seventh phase has been described, but the eighth phase may be executed. In this case, the models managed by the n-th hierarchical management devices 151 and 152, which are the lowest hierarchical management devices belonging to the first hierarchical management device 120, are shared. In the above explanation, the first to eighth phases are executed once. However, the first to eighth phases may be executed repeatedly multiple times.

[0075] Furthermore, the order of execution of each phase is not limited to the order of execution described above. For example, the first to fifth phases may be repeatedly executed multiple times before the sixth and seventh phases are executed. Furthermore, the sixth to seventh phases may be repeatedly executed multiple times before the eighth phase is executed.

[0076] In the above description, the model parameters of the model structure="Model A" and the model parameters of the model structure="Model B" are updated at the same timing in each phase. However, the model parameters of the model structure="Model A" and the model parameters of the model structure="Model B" may be updated at different timings in each phase.

[0077] <Model management process flow> Next, the flow of the model management process by the model management system 100 will be described with reference to a sequence diagram. Fig. 8 is a sequence diagram showing the flow of the model management process by the model management system. Note that, when executing the model management process shown in Fig. 8, it is assumed that the learning processes by the learning units 112_1 and 112_2 have been completed, and the model structure and model parameters are managed by the model management device 110.

[0078] 8, in step S801, the model management device 110 transmits the model structure and model parameters being managed by it to the first hierarchical management device 120. The model structure and model parameters transmitted to the first hierarchical management device 120 are sequentially transmitted to management devices in lower hierarchical levels belonging to the first hierarchical management device 120, for example, up to the (n-1)th hierarchical management device 141.

[0079] In step S811, the (n−1)th hierarchical management device 141 transmits the transmitted model structure and model parameters to the nth hierarchical management device 151.

[0080] In step S812, the n-th hierarchical management device 151 transmits the transmitted model structure and model parameters to the execution device 170.

[0081] In step S813, the execution device 170 sets the transmitted model parameters to the transmitted model structure and executes the model. The execution device 170 also stores the inference result output from the model and the correct answer data in association with each other as actual measurement data, and performs a learning process using the stored actual measurement data.

[0082] In step S814, the execution device 170 transmits to the n-th hierarchical management device 151 the model parameters optimized by performing a learning process using the actual measurement data.

[0083] Furthermore, in step S821, the (n-1)th hierarchical management device 141 transmits the transmitted model structure and model parameters to the nth hierarchical management device 152.

[0084] In step S822, the n-th hierarchical management device 152 transmits the transmitted model structure and model parameters to the execution device 190.

[0085] In step S823, the execution device 190 sets the transmitted model parameters to the transmitted model structure and executes the model. The execution device 190 also stores the inference result output from the model and the correct answer data in association with each other as actual measurement data, and performs a learning process using the stored actual measurement data.

[0086] In step S824, the execution device 190 transmits to the n-th hierarchical management device 152 the model parameters optimized by performing a learning process using the actual measurement data.

[0087] In step S831, the n-th hierarchical management device 151 transmits the optimized model parameters to the (n−1)-th hierarchical management device 141.

[0088] In step S832, the n-th hierarchical management device 152 transmits the optimized model parameters to the (n−1)-th hierarchical management device 141.

[0089] In step S833, the (n−1)th hierarchical management device 141 generates new model parameters based on the model parameters transmitted from the nth hierarchical management device 151 and the model parameters transmitted from the nth hierarchical management device 152.

[0090] In step S834, the (n-1)th hierarchical management device 141 transmits the new model parameters to the nth hierarchical management device 151. After that, the same processes as those in steps S812 to S814 and S831 are performed.

[0091] In step S835, the (n-1)th hierarchical management device 141 transmits the new model parameters to the nth hierarchical management device 152. After that, the same processes as those in steps S822 to S824 and S832 are performed.

[0092] Moreover, in the hierarchical levels above the (n-1)th hierarchical management device 141, the same processes as those in steps S831 to S835 are repeated.

[0093] As a result, in step S841, each of the multiple second tier management devices transmits the optimized model parameters to the first tier management device 120 to which it is connected.

[0094] In step S842, the first hierarchical management device 120 generates new model parameters using model parameters transmitted from multiple second hierarchical management devices one hierarchical level lower that are connected to the first hierarchical management device 120. The new model parameters generated by the first hierarchical management device 120 are transmitted to multiple second hierarchical management devices one hierarchical level lower that are connected to the first hierarchical management device 120. Thereafter, the same processes as those in steps S811 to S814, S831, steps S821 to S824, and S832 are performed.

[0095] <Hardware configuration of the xth hierarchical management device> Next, the hardware configuration of each of the management devices from the first hierarchical management device 120 to the nth hierarchical management devices 151, 152 will be described. Note that since each of the management devices from the first hierarchical management device 120 to the nth hierarchical management devices 151, 152 has the same hardware configuration, here, the hardware configuration of the xth hierarchical management device, which is the management device for the xth hierarchical layer (x is any integer from 1 to n), will be described. Fig. 9 is a diagram showing an example of the hardware configuration of the xth hierarchical management device.

[0096] 9, the xth hierarchical management device 900 has a CPU (Central Processing Unit) 901, a ROM (Read Only Memory) 902, and a RAM (Random Access Memory) 903. The xth hierarchical management device 900 also has a GPU (Graphics Processing Unit) 904. The processors (processing circuits, processing circuitry) such as the CPU 901 and GPU 904 and the memories such as the ROM 902 and RAM 903 form a so-called computer.

[0097] Furthermore, the xth hierarchical management device 900 has an auxiliary storage device 905, a display device 906, an operation device 907, an I / F (Interface) device 908, and a drive device 909. The various hardware components of the xth hierarchical management device 900 are connected to each other via a bus 910.

[0098] The CPU 901 is a computing device that executes various programs installed in the auxiliary storage device 905 (for example, a model management program, which will be described later).

[0099] The ROM 902 is a non-volatile memory and functions as a main storage device. The ROM 902 stores various programs, data, etc. required for the CPU 901 to execute various programs installed in the auxiliary storage device 905. Specifically, the ROM 902 stores boot programs such as a Basic Input / Output System (BIOS) and an Extensible Firmware Interface (EFI).

[0100] The RAM 903 is a volatile memory such as a dynamic random access memory (DRAM) or a static random access memory (SRAM), and functions as a main storage device. The RAM 903 provides a working area in which various programs installed in the auxiliary storage device 905 are expanded when the CPU 901 executes them.

[0101] The GPU 904 is a computing device for image processing, and in this embodiment, performs high-speed calculations by parallel processing on two-dimensional data when the model management program is executed by the CPU 901. The GPU 904 is equipped with an internal memory (GPU memory) and temporarily stores information required when performing parallel processing on two-dimensional data.

[0102] The auxiliary storage device 905 stores various programs and various data used when the various programs are executed by the CPU 901. For example, a distribution information storage unit 1011, an update information storage unit 1012, and a lower layer information storage unit 1013, which will be described later, are realized in the auxiliary storage device 905.

[0103] The display device 906 is, for example, a display device that displays the internal state of the xth hierarchical management device 900. The operation device 907 is an input device used when a user of the xth hierarchical management device 900 inputs various instructions to the xth hierarchical management device 900. The I / F device 908 is a connection device for transmitting and receiving data to and from other management devices.

[0104] The drive device 909 is a device for setting the recording medium 920. The recording medium 920 here includes media that record information optically, electrically, or magnetically, such as a CD-ROM, a flexible disk, a magneto-optical disk, etc. The recording medium 920 may also include semiconductor memories that record information electrically, such as ROM, flash memory, etc.

[0105] The various programs to be installed in the auxiliary storage device 905 are installed, for example, by setting the distributed recording medium 920 in the drive device 909 and reading out the various programs recorded in the recording medium 920 by the drive device 909. Alternatively, the various programs to be installed in the auxiliary storage device 905 may be installed by being downloaded via a network (not shown).

[0106] <Functional configuration of the xth hierarchical management device> Next, a description will be given of the functional configuration of each of the management devices from the first hierarchical management device 120 to the nth hierarchical management devices 151, 152. Note that since each of the management devices from the first hierarchical management device 120 to the nth hierarchical management devices 151, 152 has the same functional configuration, a description will be given here of the functional configuration of the xth hierarchical management device, which is a management device for the xth hierarchical layer (x is any integer from 1 to n).

[0107] However, in the following description, when x=1, the management device one hierarchical level higher than the x-th hierarchical management device refers to the model management device 110. When x=n, the management device one hierarchical level lower than the x-th hierarchical management device refers to the execution devices 170, 190, etc.

[0108] 10 is a diagram showing an example of the functional configuration of an xth hierarchical management device. As described above, a model management program is installed in the xth hierarchical management device 900, and by executing this program, the xth hierarchical management device 900 functions as an upper layer information acquisition unit 1001 and a sharing unit 1002. In addition, the xth hierarchical management device 900 functions as a lower layer information acquisition unit 1003, an optimization unit 1004, and an upper layer information transmission unit 1005.

[0109] The upper layer information acquisition unit 1001 is a management device in the hierarchical layer one layer higher, and acquires both the model structure and the model parameters, or the model parameters, when transmitted from a management device to which the xth hierarchical management device 900 is connected. In addition, the upper layer information acquisition unit 1001 stores the acquired model structure and model parameters in the distribution information storage unit 1011. Alternatively, the upper layer information acquisition unit 1001 uses the acquired model parameters to update the model parameters already stored in the distribution information storage unit 1011.

[0110] The sharing unit 1002 is an example of a control unit, and when a new model and model parameters are stored in the distribution information storage unit 1011, the sharing unit 1002 reads them out and transmits them to a management device one hierarchical level lower, which is a management device connected to the xth hierarchical management device 900. Also, when a model parameter stored in the distribution information storage unit 1011 is updated, the sharing unit 1002 reads them out and transmits them to a management device one hierarchical level lower, which is a management device connected to the xth hierarchical management device 900.

[0111] The lower layer information acquisition unit 1003 is a management device one layer lower, and acquires model parameters when they are transmitted from a management device connected to the xth hierarchical management device 900. In addition, the lower layer information acquisition unit 1003 stores the acquired model parameters in the lower layer information storage unit 1013.

[0112] The optimization unit 1004 is an example of a calculation unit, and is notified by the lower layer information acquisition unit 1003 and reads out the model parameters stored in the lower layer information storage unit 1013 to generate new model parameters. As described above, the calculation method of the new model parameters is arbitrary, and for example, the new model parameters may be generated by performing weighted addition on the multiple model parameters read out from the lower layer information storage unit 1013. In addition, the condition for the optimization unit 1004 to generate the new model parameters is arbitrary, and the new model parameters may be generated when any arbitrary condition is satisfied. For example, the new model parameters may be generated on the condition that a predetermined period has elapsed, or on the condition that a predetermined number or more of multiple model parameters have been stored. Note that the multiple model parameters refer to model parameters transmitted from multiple management devices connected to the xth hierarchical management device 900, which are multiple management devices at a layer one layer lower.

[0113] Furthermore, the optimization unit 1004 uses the generated new model parameters to update the model parameters already stored in the distribution information storage unit 1011. Furthermore, the optimization unit 1004 stores the generated new model parameters in the update information storage unit 1012.

[0114] The upper layer information transmitting unit 1005 is an example of a transmitting unit, and when new model parameters are stored in the update information storage unit 1012, it reads them out and transmits them at a predetermined timing to a management device one hierarchical level higher, which is a management device to which the xth hierarchical management device 900 is connected.

[0115] <Flow of management process by the xth hierarchical management device> Next, it will be explained about the flow of management processing by the xth hierarchical management device 900. Fig. 11 is a flowchart showing the flow of management processing by the xth hierarchical management device.

[0116] In step S1101, the upper layer information acquisition unit 1001 of the xth hierarchical management device 900 acquires a model structure and model parameters from a management device one layer higher than the xth hierarchical management device 900 connected to, and stores them in the distribution information storage unit 1011.

[0117] In step S1102, the sharing unit 1002 of the xth hierarchical management device 900 reads the model structure and model parameters from the distribution information storage unit 1011, and transmits them to a management device one hierarchical level lower, which is connected to the xth hierarchical management device.

[0118] In step S1103, the lower layer information acquisition unit 1003 of the xth hierarchical management device 900 determines whether or not model parameters have been transmitted from any of the management devices connected to the xth hierarchical management device 900, which are one layer lower.

[0119] In step S1103, if it is determined that the model parameters have been transmitted (YES in step S1103), the process proceeds to step S1104.

[0120] In step S1104, the lower layer information acquisition unit 1003 of the xth hierarchical management device 900 stores the transmitted model parameters in the lower layer information storage unit 1013. The optimization unit 1004 reads out the model parameters from the lower layer information storage unit 1013, generates new model parameters, and updates the model parameters already stored in the distribution information storage unit 1011 and the update information storage unit 1012. The sharing unit 1002 transmits the new updated model parameters to a management device one layer lower that is connected to the xth hierarchical management device 900. The upper layer information transmission unit 1005 transmits the new updated model parameters to a management device one layer higher that is connected to the xth hierarchical management device 900. Then, the process proceeds to step S1105.

[0121] On the other hand, if it is determined in step S1103 that the model parameters have not been transmitted (NO in step S1103), the process proceeds directly to step S1105.

[0122] In step S1105, the upper layer information acquisition unit 1001 of the xth hierarchical management device 900 determines whether or not model parameters have been transmitted from a management device one layer higher, to which the xth hierarchical management device 900 is connected.

[0123] In step S1105, if it is determined that the model parameters have been transmitted (YES in step S1105), the process proceeds to step S1106.

[0124] In step S1106, the upper layer information acquisition unit 1001 of the xth hierarchical management device 900 acquires the model parameters transmitted from a management device at a hierarchical level one hierarchical level higher than the xth hierarchical management device 900, which is connected to the xth hierarchical management device 900. The upper layer information acquisition unit 1001 of the xth hierarchical management device 900 also uses the acquired model parameters to update the model parameters already stored in the distribution information storage unit 1011. Furthermore, the sharing unit 1002 transmits the new updated model parameters to a management device at a hierarchical level one hierarchical level lower than the xth hierarchical management device 900, which is connected to the xth hierarchical management device 900, and the process proceeds to step S1107.

[0125] On the other hand, if it is determined in step S1105 that the model parameters have not been transmitted (NO in step S1105), the process proceeds directly to step S1107.

[0126] In step S1107, the xth hierarchical management device 900 judges whether or not to end the management process. If it is judged in step S1107 that the management process should not be ended (NO in step S1107), the process returns to step S1103.

[0127] On the other hand, if it is determined in step S1107 that the management process is to be ended (YES in step S1107), the management process is ended.

[0128] <Hardware configuration of the execution device> Next, a description will be given of the hardware configuration of the execution devices 170, 190. Fig. 12 is a diagram showing an example of the hardware configuration of an execution device. Note that the hardware configuration of the execution devices 170, 190 is generally the same as the hardware configuration of the xth hierarchical management device 900, so only the differences will be described here.

[0129] The CPU 1201 is a computing device that executes various programs (such as an execution program described below) installed in the auxiliary storage device 1205 .

[0130] The auxiliary storage device 1205 stores various programs and various data used when the various programs are executed by the CPU 1201. For example, model information storage units 1321 and 1323 and actual measurement data storage units 172-1 and 172-2, which will be described later, are realized in the auxiliary storage device 1205.

[0131] 12 is an example, and the execution devices 170 and 190 may be configured, for example, by a field-programmable gate array (FPGA). Alternatively, the execution devices 170 and 190 may be configured, for example, by an AI chip (a semiconductor specialized for AI (Artificial Intelligence) processing).

[0132] <Functional configuration of the execution device> Next, the functional configuration of the execution device 170 will be described. Fig. 13 is a diagram showing an example of the functional configuration of the execution device. As shown in Fig. 13, the execution device 170 has a virtual space (for real-time control, for simulation) that processes data collected from a physical space and executes or updates a model. The execution device 170 also has a storage group that stores the data collected from the physical space and model parameters updated in the virtual space.

[0133] The physical space in which the execution device 170 collects data includes: A substrate processing apparatus 160; A measuring device 1301 that measures data used by an inference unit 171_1 to execute a model or by a sequential learning unit 1311 to perform sequential learning of a model during substrate processing by the substrate processing device 160; A measuring device 1302 that measures data used by the inference unit 171_2 to execute a model or by the sequential learning unit 1313 to perform sequential learning of a model during substrate processing by the substrate processing apparatus 160; Includes:

[0134] The virtual space (for real-time control) of the execution device 170 includes sequential learning units 1311 and 1313, an instruction unit 1312, a notification unit 1314, and inference units 171_1 and 171_2.

[0135] The sequential learning unit 1311 performs sequential learning (online learning) based on data collected by the measuring device 1301, and adjusts model parameters of the model arranged in the inference unit 171_1. The model parameters adjusted by the sequential learning unit 1311 may be stored in the model information storage unit 1321.

[0136] 1, the inference unit 171_1 executes a model based on data collected from the measuring device 1301, and outputs inference results (for example, inference results of anomaly detection, inference results of process processing results, inference results of component deterioration diagnosis, inference results of internal states, etc.). The inference results output from the inference unit 171_1 are notified to the instruction unit 1312, and are stored in the actual measurement data storage unit 172_1 in association with, for example, correct answer data.

[0137] The instruction unit 1312 generates an instruction (e.g., a target value of a process) according to the inference result notified by the inference unit 171_1 (e.g., an inference result of an abnormality detection, an inference result of a process processing result, an inference result of a component deterioration diagnosis, an inference result of an internal state, etc.). The instruction unit 1312 also transmits the generated instruction to the substrate processing apparatus 160. In this case, the substrate processing apparatus 160 calculates a control value based on the transmitted instruction (e.g., a target value of a process) and performs control. The instruction unit 1312 may be realized by a model having a learning function.

[0138] The sequential learning unit 1313 performs sequential learning (online learning) based on the data collected by the measuring device 1302, and adjusts the model parameters of the model arranged in the inference unit 171_2. The model parameters adjusted by the sequential learning unit 1313 may be stored in the model information storage unit 1323.

[0139] 1, the inference unit 171_2 executes a model based on data collected from the measuring device 1302 and outputs an inference result (for example, an inference result (control value) in process control, etc.). The inference result output from the inference unit 171_2 is notified to the notification unit 1314 and is stored in the actual measurement data storage unit 172_2 in association with, for example, the correct answer data.

[0140] The notification unit 1314 transmits the inference result (e.g., the inference result (control value) in the process control) notified by the inference unit 171_2 to the substrate processing apparatus 160. In this case, the substrate processing apparatus 160 performs control according to the transmitted inference result (e.g., the inference result (control value) in the process control).

[0141] In the example of FIG. 13, the instruction unit 1312 is configured to be arranged in a virtual space (for real-time control), but the instruction unit 1312 may be configured to be realized in the substrate processing apparatus 160.

[0142] The virtual space (for simulation) of the execution device 170 includes learning sections 210_1 and 210_2.

[0143] As described with reference to FIG. 2, the learning unit 210_1 receives the model (model structure="model A", model parameters="parameter P A 0”) is arranged. When a certain amount of actual measurement data is accumulated, the learning unit 210_1 reads out the actual measurement data from the actual measurement data storage unit 172_1 and performs additional learning processing (batch learning processing). As a result, the learning unit 210_1 obtains the optimized model parameters (“parameter P A 1”) is stored in the model information storage unit 1321. The model parameters (“parameter P A 1”) is transmitted to the n-th hierarchical management device 151 at a predetermined timing.

[0144] When new model parameters are transmitted from the n-th hierarchical management device 151, the learning unit 210_1 sets the new model parameters to model structure="model A" and performs a simulation using the actual measurement data stored in the actual measurement data storage unit 172_1. This allows the learning unit 210_1 to verify in advance whether or not there is a problem with the new model parameters before the new model parameters are set in the inference unit 171_1.

[0145] As described with reference to FIG. 2, the learning unit 210_2 receives the model (model structure="model B", model parameters="parameter P B 0”) is arranged. When a certain amount of actual measurement data is accumulated, the learning unit 210_2 reads out the actual measurement data from the actual measurement data storage unit 172_2 and performs additional learning processing (batch learning processing). As a result, the learning unit 210_2 obtains optimized model parameters (“parameter P B 1”) is stored in the model information storage unit 1323. The model parameters (“parameter P B 1”) is transmitted to the n-th hierarchical management device 151 at a predetermined timing.

[0146] When new model parameters are transmitted from the n-th hierarchical management device 151, the learning unit 210_2 sets the new model parameters to model structure="model B" and performs a simulation using the actual measurement data stored in the actual measurement data storage unit 172_2. This allows the learning unit 210_2 to verify in advance whether or not there is a problem with the new model parameters before the new model parameters are set in the inference unit 171_2.

[0147] <Flow of sequential learning process and batch learning process by execution unit> Next, the flow of the sequential learning process and the batch learning process performed by the execution unit 170 will be described.

[0148] (1) Flow of sequential learning process FIG. 14A is a flowchart showing the flow of the sequential learning process performed by the execution device.

[0149] In step S1401, the execution device 170 receives a model (model structure="model A", "model B", model parameters="parameter P A 0”, “Parameter P B 0" is obtained.

[0150] In step S1401, the execution device 170 executes the following: A 0” is set in the inference unit 171_1 and the learning unit 210_1. The execution device 170 also assigns the model parameter “parameter P B The model in which 0" is set is provided to the inference unit 171_2 and the learning unit 210_2.

[0151] In step S1403, the inference units 171_1 and 171_2 of the execution device 170 execute the model based on the data collected from the substrate processing apparatus 160, and output the inference results.

[0152] In step S1404, the sequential learning units 1311 and 1313 of the execution device 170 perform sequential learning based on the data collected from the substrate processing device 160, and adjust the model parameters, respectively.

[0153] In step S1405, the execution device 170 stores the inference results output from the inference units 171_1 and 171_2 in the actual measurement data storage unit 172_1 or 172_2 in association with the supervised answer data.

[0154] In step S1406, the execution device 170 determines whether or not to end the sequential learning process. If it is determined in step S1406 that the sequential learning process is not to end (NO in step S1406), the execution device 170 proceeds to step S1407.

[0155] In step S1407, the execution device 170 determines whether or not new model parameters have been transmitted from the n-th hierarchical management device 151. If it is determined in step S1407 that new model parameters have not been transmitted (NO in step S1407), the process returns to step S1403.

[0156] On the other hand, if it is determined in step S1407 that new model parameters have been transmitted (YES in step S1407), the process proceeds to step S1408.

[0157] In step S1408, the execution device 170 performs a simulation using the model parameters transmitted from the n-th hierarchical management device 151 to verify the suitability of the model parameters.

[0158] In step S1408, if it is not verified that the model parameters are appropriate (NO in step S1408), the process returns to step S1403.

[0159] On the other hand, if it is verified in step S1408 that the model parameters are appropriate (YES in step S1408), the process returns to step S1402. As a result, the model in which the new model parameters are set is allocated to the corresponding inference unit.

[0160] On the other hand, if it is determined in step S1406 that the sequential learning process is to be ended (YES in step S1406), the sequential learning process is ended.

[0161] (2) Batch learning process flow FIG. 14B is a flowchart showing the flow of the batch learning process performed by the execution device.

[0162] In step S1411, the executing device 170 determines whether a certain amount of actual measurement data has been accumulated in the actual measurement data storage units 172_1 and 172_2. If it is determined in step S1411 that a certain amount of actual measurement data has not been accumulated (NO in step S1411), the process proceeds to step S1416.

[0163] On the other hand, if it is determined in step S1411 that a certain amount of actual measurement data has been accumulated (YES in step S1411), the process proceeds to step S1412.

[0164] In step S1412, the learning units 210_1 and 210_2 of the execution unit 170 read out the actual measurement data from the actual measurement data storage units 172_1 and 172_2.

[0165] In step S1413, the learning units 210_1 and 210_2 of the execution device 170 perform additional learning processing (batch learning processing) using the read-out actual measurement data.

[0166] In step S1414, the execution device 170 performs the additional learning process on the model parameters optimized by the learning units 210_1 and 210_2, ie, the parameter P A 1”, “Parameter P B 1” is acquired and stored in the model information storage units 1321 and 1323.

[0167] In step S 1415 , the execution device 170 transmits the optimized model parameters to the n-th hierarchical management device 151 .

[0168] In step S1416, the execution device 170 determines whether or not to end the batch learning process. If it is determined in step S1409 that the batch learning process should not be ended (NO in step S1416), the process returns to step S1411.

[0169] On the other hand, if it is determined in step S1416 that the batch learning process is to be ended (YES in step S1416), the batch learning process is ended.

[0170] <Summary> As is clear from the above description, the model management system 100 according to the first embodiment: ·Manage models applied to the PCB manufacturing process in three or more layers. The system has a management device (first management unit) that manages models at the xth hierarchical level, and one or more (x+1)th hierarchical level management devices (second management units) that are connected to the management device that manages models at the xth hierarchical level and manage models at a level one hierarchical level lower. A management device that manages models at the xth hierarchical level calculates new model parameters based on each updated model parameter when model parameters of one or more models managed at the (x+1)th hierarchical level are updated. A management device that manages models in the xth hierarchical level controls so that new model parameters are set in models managed by each of a plurality of management devices in the lowest hierarchical level that belong to the management device that manages models in the xth hierarchical level.

[0171] In this way, in the first embodiment, models are divided into three or more hierarchical levels, and model parameters are shared between management devices at the same level, thereby consolidating the number of models and reducing management costs.

[0172] As a result, according to the first embodiment, the model applied to the substrate processing can be efficiently managed.

[0173] [Second embodiment] In the above first embodiment, the case where models are managed in a single substrate processing factory by dividing them into three or more hierarchical layers has been described. However, the method of dividing models into three or more hierarchical layers is not limited to this.

[0174] For example, models may be divided into two hierarchical levels within the same substrate processing factory, and a common management device that manages models for multiple substrate processing factories may be located outside the factory, allowing for overall management into three or more hierarchical levels.

[0175] Fig. 15 is a second diagram showing an example of the system configuration of the model management system. As shown in Fig. 15, in the case of a model management system 1500, a model management device 1510 manages a model in a substrate processing factory α and a model in a substrate processing factory β.

[0176] Specifically, the model management device 1510 manages the models (model structure=“model A”, “model B”, model parameters=“parameter P A 0”, “Parameter P B 0" in the first phase. Furthermore, the model management device 1510 transmits the model to the first hierarchical management device 120 of the substrate processing factory α and to the first hierarchical management device (not shown) of the substrate processing factory β.

[0177] As shown in FIG. 15, in the case of a model management system 1500, a substrate processing factory α has a first hierarchical management device 120 and second hierarchical management devices 131 and 132, but does not have a management device at a third hierarchical level or higher.

[0178] In other words, the second hierarchical management devices 131 and 132 are the lowest hierarchical management devices, and are connected to the execution devices 170 and 190, respectively.

[0179] In addition, the model management device 1510, for example, in the seventh phase, In the sixth phase, the model parameters transmitted from the first hierarchical management device 120 of the substrate processing factory α; In the sixth phase, the model parameters transmitted from the first hierarchical management device 120 of the substrate processing factory β; In the seventh phase, the model management device 1510 manages the new model parameters and transmits the new model parameters to the first tier management device 120 in the substrate processing factory α and the first tier management device in the substrate processing factory β.

[0180] As a result, the model parameters of the models managed by each of the multiple management apparatuses (the multiple management apparatuses of the substrate processing factories α and β) in the lowest layer belonging to the model management apparatus 1510 are updated using the new model parameters.

[0181] In this way, in the second embodiment, the models are divided into two hierarchical levels within the same substrate processing factory, and a common management device that manages the models of multiple substrate processing factories is located outside the factory, so that the models are managed in three or more hierarchical levels as a whole. As a result, according to the second embodiment, it is possible to enjoy the same effects as the first embodiment.

[0182] [Other embodiments] In the above first and second embodiments, the first hierarchical management device to the nth hierarchical management device are each separate management devices, but the first hierarchical management device to the nth hierarchical management device may also be formed as an integrated device.

[0183] In the above first and second embodiments, it has been described that when the xth hierarchical management device transmits newly generated model parameters, the model parameters are transmitted to all management devices that are one hierarchical level lower than the xth hierarchical management device and connected to the xth hierarchical management device. However, the destination of the model parameters may be a management device that is one hierarchical level lower than the xth hierarchical management device and may be configured to transmit the model parameters to some management devices that are connected to the xth hierarchical management device.

[0184] In the above first and second embodiments, the management process has been described in which the model management system manages models according to the respective purposes of the existing substrate processing apparatus. However, the same applies to the case where a new substrate processing apparatus is added. Specifically, the management device that manages models according to the respective purposes of the new substrate processing apparatus is as follows: -Connected to a management device that manages models corresponding to the new group of substrate processing equipment; Acquires a model structure and model parameters (the latest model parameters at the time of addition) from a management device at a higher level than the management device connected to the management device; Manage the acquired models and model parameters and send them to the corresponding execution device.

[0185] In this way, even when a new substrate processing apparatus is added, the latest model can be arranged in the inference unit of the corresponding execution apparatus as a model suited to the purpose of the newly added substrate processing apparatus. In other words, the management apparatus that manages the model suited to the purpose of the new substrate processing apparatus controls so that the latest model parameters are set in the model suited to the purpose of the new substrate processing apparatus.

[0186] When transmitting the latest model parameters to the management device that manages the model according to each purpose of the new substrate processing apparatus, the latest model parameters are also transmitted to other management devices at the same level. However, the latest model parameters may not be transmitted to other management devices at the same level, and the management devices may continue to manage the set model parameters. Furthermore, when transmitting the latest model parameters, a simulation may be performed in advance, and the transmission may be performed after verification is completed.

[0187] In addition, in the first and second embodiments, details of the model were not mentioned, but the model used in the first and second embodiments may be, for example, a machine learning model including deep learning, for example, ·RNN (Recurrent Neural Network), ·LSTM (Long Short-Term Memory), ·CNN(Convolutional Neural Network), ·R-CNN (Region based Convolutional Neural Network), ·YOLO (You Only Look Once), ·SSD (Single Shot MultiBox Detector), ·GAN (Generative Adversarial Network), ·SVM (Support Vector Machine), Decision trees, Random Forest It may be any of the above.

[0188] Alternatively, the model may be a model using a genetic algorithm such as GA (Genetic Algorism) or GP (Genetic Programming), or a model trained by reinforcement learning.

[0189] Alternatively, the model used in the first and second embodiments may be a model obtained by general statistical analysis other than deep learning, such as Principal Component Regression (PCR), Partial Least Square (PLS), LASSO, ridge regression, linear polynomial, autoregressive model, moving average model, autoregressive moving average model, or ARX model.

[0190] In the above first and second embodiments, the model management program is executed by each management device in each layer independently. However, when the management devices in each layer are configured by multiple computers, for example, and the model management program is installed in the multiple computers, the model management program may be executed in a distributed computing mode.

[0191] In the above first and second embodiments, the management device is described as being configured as a separate device for each hierarchical level, but as long as management is separate for each hierarchical level, the management devices for different hierarchical levels may be configured as an integrated device. Alternatively, some functions may be shared and executed between the management devices for different hierarchical levels.

[0192] Furthermore, in the above first and second embodiments, a method of downloading and installing the model management program via a network (not shown) has been mentioned as an example of a method of installing the model management program into the auxiliary storage device 905. At this time, no particular reference was made to the download source, but when installing using such a method, the download source may be, for example, a server device that stores the model management program in an accessible manner. Furthermore, the server device may be, for example, a device that accepts access from a management device via a network (not shown) and downloads the model management program on the condition that a fee is paid. In other words, the server device may be a device that provides a service of providing the model management program.

[0193] The present invention is not limited to the configurations shown in the above embodiments, combinations with other elements, etc. These points can be changed without departing from the spirit of the present invention, and can be appropriately determined according to the application form.

[0194] This application claims priority based on Japanese Patent Application No. 2020-187177, filed on November 10, 2020, the entire contents of which are incorporated herein by reference. [Explanation of symbols]

[0195] 100: Model Management System 110: Model management device 120: 1st layer management device 131~133: 2nd layer management device 141:(n-1) layer management device 151, 152: nth layer management device 160, 180: substrate processing apparatus 170, 190: Execution device 171_1, 171_2: Reasoning section 191_1, 191_2: Reasoning section 210_1, 210_2: Learning department 220_1, 220_2: Learning Department 1001: Upper Layer Information Acquisition Unit 1002: Sharing Unit 1003: Lower Layer Information Acquisition Unit 1004: Optimization Unit 1005: Upper Layer Information Transmission Unit

Claims

1. A model management system that manages models applied to a substrate manufacturing process by dividing the models into three or more hierarchical levels, a first management unit that manages models at a predetermined hierarchy; a plurality of second management units that manage models at a hierarchy level one hierarchy level lower than the predetermined hierarchy level, The first management unit is a calculation unit that calculates new model parameters based on each updated model parameter when the model parameters of the model managed by the second management unit are updated; a control unit that controls so that the new model parameters are set in models managed by each of a plurality of lowest-level management units belonging to the first management unit; a transmission unit that transmits the new model parameters to a management unit that manages a model that is one level higher than the model managed by the first management unit; A model management system having

2. 2 . The model management system according to claim 1 , wherein the hierarchical levels are divided according to an equipment model of an equipment that performs the substrate manufacturing process, a chamber type of an equipment that performs the substrate manufacturing process, and a process group of an equipment that performs the substrate manufacturing process.

3. 2. The model management system according to claim 1, wherein the model is either a model that outputs an inference result for an anomaly detection in an apparatus that executes the substrate manufacturing process, an inference result for the result of process processing, an inference result for component deterioration diagnosis, or an inference result for an internal state, or a model that outputs an inference result in controlling the substrate manufacturing process.

4. 2. The model management system according to claim 1, wherein the calculation unit calculates the new model parameters when a predetermined condition is satisfied, and the control unit controls the new model parameters to be set in the plurality of models in the lowest layer at a predetermined timing.

5. The model management system according to claim 1 , wherein the control unit controls so that the new model parameters are set in parts of models managed by each of the plurality of management units in the lowest layer.

6. The control unit is 2. The model management system according to claim 1, wherein when a new device for performing the substrate manufacturing process is added, the system controls so that the new model parameters are set in a model corresponding to the added device.

7. A model management method for a model management system that manages models applied to a substrate manufacturing process by dividing the models into three or more hierarchical levels, comprising the steps of: a first management step in which a first management unit manages a model at a predetermined level; a second management step in which each of a plurality of second management units manages a model at a level one level lower than the predetermined level, The first management step includes: a calculation step of calculating new model parameters based on each updated model parameter when the model parameters of the model managed in the second management step are updated; a control step of controlling so that the new model parameters are set in models managed by each of a plurality of lowest-level management units belonging to the first management unit; a transmission step of transmitting the new model parameters to a management unit that manages a model at a level one level higher than the model managed by the first management unit; The model management method includes:

8. A model management system computer manages models applied to the PCB manufacturing process in three or more hierarchical levels. a first management step in which a first management unit manages a model at a predetermined level; a second management step in which each of a plurality of second management units manages a model at a level one level lower than the predetermined level, The first management step includes: a calculation step of calculating new model parameters based on each updated model parameter when the model parameters of the model managed in the second management step are updated; a control step of controlling so that the new model parameters are set in models managed by each of a plurality of lowest-level management units belonging to the first management unit; a transmission step of transmitting the new model parameters to a management unit that manages a model at a level one level higher than the model managed by the first management unit; A model management program with

Citation Information

Patent Citations

  • Vehicle air-conditioning control device, and control method and program for air conditioner of vehicle

    JP2019093969A

  • Hybrid aggregation for deep learning neural networks

    US20180253646A1

  • Server device, trained model providing program, trained model providing method, and trained model providing system

    WO2018173121A1

  • Information processing system

    WO2019163823A1

  • Determining a correction to a process

    WO2020094325A1