Production planning device and production planning program
The production planning device and program address the challenge of integrating unconfirmed orders into batch processing by determining processing policies and yield considerations, improving delivery date accuracy for both confirmed and unconfirmed orders.
Patent Information
- Application Number
- JP2024129014
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2024-08-05
- Publication Date
- 2024-10-30
- Estimated Expiration
- 2044-08-05
AI Technical Summary
Existing production planning systems struggle to accurately incorporate unconfirmed orders into production plans, especially in processes involving batch processing, where it is difficult to manage the timing of production steps without waste or unreasonableness, and fail to provide highly accurate delivery date predictions for both confirmed and unconfirmed orders.
A production planning device and program that distinguishes between confirmed and unconfirmed orders, determines processing policies based on deadlines, and creates production plans that consider yield and efficiency, allowing for accurate delivery date predictions by integrating unconfirmed orders into batch processing processes.
Enhances the accuracy of delivery date predictions for both confirmed and unconfirmed orders by creating production plans that account for yield and efficiency, even in batch processing environments.
Smart Images

Figure 0007575831000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a production planning device and a production planning program, and more particularly to a production planning device and a production planning program for a production process including a batch processing process. [Background technology]
[0002] For companies and business operators who produce or manufacture a wide variety of products (hereinafter collectively referred to as "production" in this application), creating production plans that are as free from unnecessary and wasteful work as possible from the customer's perspective is essential in order to increase the likelihood of gaining trust from customers and overcome the challenges of reducing production costs and management burdens. In order to appropriately harmonize orders for each product obtained through sales activities with the production plans from a management perspective, companies and business operators (hereinafter collectively referred to as "companies, etc." in this application) have traditionally devised various methods.
[0003] A technology has been disclosed in the prior art that adjusts production plans by outputting ordering information (material cost occurrence status) of parts required for production and processing cost occurrence status from inquiry information (unconfirmed configuration portion) as warning information to sales, thereby assisting in the determination of inquiry information (unconfirmed configuration portion) (Patent Document 1). [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2003-345969 A Summary of the Invention [Problem to be solved by the invention]
[0005] In normal economic activities, it is common for customers or potential customers (hereinafter collectively referred to as "customers, etc." in this application) to make requests regarding a certain product or merchandise (hereinafter collectively referred to as "products" in this application) to know the delivery date if they were to order the product, even though it is not yet certain whether they will place an order for the product.
[0006] However, it is not necessarily easy to incorporate not only confirmed orders but also unconfirmed orders (hereinafter also referred to as "unconfirmed orders") into a production plan and then make a highly accurate delivery date forecast for the unconfirmed orders. In particular, when a process known as a "batch processing process" is included in the production process or manufacturing process for producing the product (hereinafter collectively referred to as the "production process" in this application), it becomes even more difficult to solve the above-mentioned problem.
[0007] To be more specific, a batch processing process differs from a continuous processing process in that it is a process in which a number of processing objects are usually subjected to various processing steps based on a single processing condition, for a certain period of time or for each unit processing. Due to the nature of the processing as described above, once a batch processing process is started, it is usually not possible to stop or restart the processing step until the processing step is completely completed. For this reason, among all the production processes for producing a final product, a batch processing process is the process in which the management or adjustment of the start timing of the processing step can be the biggest challenge in realizing an efficient production plan.
[0008] In addition, as mentioned above, in economic activities, there is a demand to provide customers with highly accurate delivery date forecasts for unconfirmed orders, and therefore it is very significant that the management and / or adjustment of production processes, including batch processing processes, can be realized with a high degree of accuracy while taking into account unconfirmed orders. In production planning that includes not only confirmed orders but also unconfirmed orders, how to predict the delivery dates of both with a high degree of accuracy is an important issue, particularly for manufacturers who handle a wide variety of products.
[0009] However, Patent Document 1 does not disclose or suggest a production planning device or a production planning program that can solve the above-mentioned problems and realize a highly accurate delivery date prediction while taking into account unconfirmed order items, even in a production process that includes a batch processing process. Moreover, as far as the inventors of the present application know, there is no production planning device or production planning program that includes a batch processing process and can realize a highly accurate delivery date prediction while taking into account unconfirmed order items in the prior art. [Means for solving the problem]
[0010] The present invention can solve at least some of the above-mentioned problems and greatly contribute to the realization of a production planning device or production planning program including a batch processing process that can realize delivery date predictions with a high degree of accuracy by taking into account not only products whose orders have been confirmed (hereinafter also referred to as "confirmed order items") but also products whose orders have not been confirmed.
[0011] The inventor of the present application noticed that in the creation of a production plan including a batch processing process, in order to provide a highly accurate delivery date forecast to a customer, etc., a production plan is usually created only for confirmed order items. However, as described above, in actual business activities, there are more and more requests for delivery date forecasts for unconfirmed order items. In light of this, the inventor of the present application repeatedly studied and analyzed the realization of the creation of a production plan including a batch processing process that includes not only confirmed order items but also unconfirmed order items.
[0012] As a result, the inventors of the present application have found that by distinguishing whether or not to take into consideration the final product yield rate, which is thought to be the factor that has the greatest impact due to the presence of unconfirmed order items, and then implementing the solutions appropriate to each case shown below, it is possible to improve the accuracy of delivery date predictions for unconfirmed order items in a production process that includes a batch processing process, even if the unconfirmed order items are included. (1) When the yield rate is not taken into consideration (in other words, when it is not affected by the yield rate in the batch processing process) To the extent that the unconfirmed orders can be processed in the same batch process as the firm orders, an overall production schedule is created based on the completion dates of the batch processes of the firm orders. (2) When the yield rate is taken into consideration (in other words, when you want to increase the yield rate in the batch processing process as much as possible) It is determined whether a predetermined yield is satisfied by processing only the confirmed order items in the batch processing step, and if the predetermined yield is not satisfied and the predetermined yield is satisfied when the unconfirmed order items are processed by the batch processing step, an overall production plan is created based on the end time of the batch processing step for the confirmed order items.
[0013] The present invention has been created based on the above-mentioned findings and ingenuity.
[0014] One production plan creation device of the present invention is a production plan creation device that creates a production plan for a production process including a batch processing process. Specifically, this production plan creation device includes a first storage means for storing first deadline information including a first deadline that is a deadline required to end the batch processing process of a first object whose order has been confirmed, a second storage means for storing second deadline information including a second deadline that is a deadline required to end the batch processing process of a second object whose order has not been confirmed, a processing policy decision unit that decides a policy for processing one unit processing object that processes the first object and the second object in accordance with the first deadline regardless of whether there is a difference between the first deadline and the second deadline, and a production plan creation unit that creates the production plan based on the first deadline decided by the processing policy decision unit.
[0015] This production planning device can realize the presentation of a highly accurate production plan (more specifically, a delivery date forecast) for the second object, which is an unconfirmed order item, to a customer, etc. Specifically, the production planning device creates a production plan that virtually includes the second object, which is an unconfirmed order item, in a production plan based on the first deadline of the first object, which has already been ordered and is scheduled to be actually produced, without considering the delivery date for the second object (for example, the delivery date required by a customer, etc.). As a result, it becomes possible to greatly increase the accuracy of delivery date forecasts not only for the first object, which is a confirmed order item, but also for the second object, which is an unconfirmed order item.
[0016] In the above-mentioned production plan creation device, the above-mentioned first storage means further stores first specification information which is the specification of the above-mentioned first object, and the above-mentioned second storage means further stores second specification information which is the specification of the above-mentioned second object. In addition, the production plan creation device further includes a first judgment unit which judges whether or not a predetermined yield is satisfied by processing only the first object in the above-mentioned unit processing object, and a process which determines a processing method for the first object and the second object in the above-mentioned unit processing object based on the first specification information and the second specification information when the above-mentioned predetermined yield is not satisfied by processing only the first object. The system further includes a method determination unit and a second judgment unit which judges whether the processing method determined by the processing method determination unit satisfies the aforementioned specified yield, and when the second judgment unit judges that the aforementioned specified yield is satisfied, the above-mentioned production plan creation unit creates the production plan based on the first deadline determined by the processing policy determination unit. Since this is a production plan which takes into consideration the yield perspective (which may include the perspectives of manufacturing cost and production efficiency), it is a preferred embodiment because it makes it possible to present a more accurate production plan (more specifically, a delivery date prediction) for the second target to a customer, etc.
[0017] A production plan creation program of the present invention is a production plan creation program executed by a computer of a production plan creation device that creates a production plan for a production process including a batch processing process. Specifically, this production plan creation program includes a processing policy decision step of deciding a policy for processing one unit processing object that processes the first object and the second object according to the first deadline, regardless of the presence or absence of a difference between the first deadline and the second deadline, based on first deadline information including a first deadline that is a requested deadline for the end of the batch processing process of a first object whose order has been confirmed and stored in a first storage means, and second deadline information including a second deadline that is a requested deadline for the end of the batch processing process of a second object whose order has not been confirmed and stored in a second storage means, and a production plan creation step of creating the production plan based on the first deadline determined by the processing policy decision unit.
[0018] According to this production plan creation program, it is possible to present a highly accurate production plan (more specifically, a delivery date forecast) for the second object, which is an unconfirmed order item, to a customer, etc. Specifically, according to this production plan creation program, a production plan is created in which the second object, which is an unconfirmed order item, is virtually included in a production plan based on the first deadline of the first object, which has already been ordered and is scheduled to be actually produced, without considering the delivery date for the second object (for example, the delivery date required by the customer, etc.). As a result, it is possible to greatly increase the accuracy of delivery date forecasts not only for the first object, which is a confirmed order item, but also for the second object, which is an unconfirmed order item.
[0019] In addition, in the above-mentioned production plan creation program, first specification information, which is the specification of the above-mentioned first object, is further stored in the above-mentioned first storage means, and second specification information, which is the specification of the above-mentioned second object, is further stored in the above-mentioned second storage means. In addition, the production plan creation program includes a first judgment step of judging whether or not a predetermined yield is satisfied by processing only the first object in the above-mentioned unit processing object, and, if the above-mentioned predetermined yield is not satisfied by processing only the first object, a processing method for the first object and the second object in the unit processing object is determined based on the first specification information and the second specification information. The method further includes a processing method decision step for determining whether the processing method decided by the processing method decision step satisfies the aforementioned specified yield, and a second judgment step for determining whether the processing method decided by the processing method decision step satisfies the aforementioned specified yield.If it is determined in the second judgment step that the aforementioned specified yield is satisfied, the above-mentioned production plan creation step creates the production plan based on the first deadline decided by the processing policy decision step, which is a production plan that takes into consideration the yield perspective (which may include the perspectives of manufacturing cost and production efficiency), so it is possible to present a more accurate production plan (more specifically, delivery date prediction) for the second target to a customer, etc.
[0020] In this application, the term "batch processing process" generally refers to a process in which a process (including heat treatment, chemical treatment, photochemical treatment, film formation / coating treatment, immersion treatment, and mechanical processing) is carried out on a plurality of objects to be processed (including materials and processed products) for a certain period of time or for each unit process under a certain set of processing conditions. Effect of the Invention
[0021] According to one production planning device or one production planning program of the present invention, in a production process including a batch processing process, a production plan that takes into account not only confirmed order items but also unconfirmed order items makes it possible to increase the accuracy of delivery date prediction for the unconfirmed order items. [Brief description of the drawings]
[0022] [Figure 1] 1 is a diagram showing a schematic configuration of a production plan creation device according to a first embodiment. [Diagram 2] 4 is a flowchart illustrating an example of each process when using the production plan creation device in the first embodiment. [Diagram 3] This is an explanatory diagram showing an example of calculating the requested completion deadline for the "batch processing process" among all production processes for a confirmed order item (first target) or an unconfirmed order item (second target) in the first embodiment, based on the deadline requested by a customer, etc. for completing all production processes (hereinafter also referred to as the "customer requested deadline"). [Figure 4] FIG. 11 is an explanatory diagram showing an example of a method for adjusting the end request deadline of a batch processing process by the processing policy decision unit 32 when one type of first target and one type of second target both exist as production targets in a production plan of the first embodiment, and the first deadline of the first target is different from the second deadline of the second target, and both the first target and the second target are processed by the batch processing process. [Diagram 5] An explanatory diagram corresponding to Figure 4 when two types of first objects and one type of second object exist as production objects in a production plan of the first embodiment, and the first deadlines of the first objects and the second deadlines of the second objects are all different. [Figure 6] 6 is an explanatory diagram corresponding to FIG. 4 of an example different from the example shown in FIG. 5. [Figure 7] FIG. 11 is a diagram showing a schematic configuration of a production plan creation device according to a second embodiment. [Figure 8] 10 is a flowchart illustrating an example of each process when using a production plan creation device in a second embodiment. [Figure 9]When processing by a batch processing step (cutting processing step) in the second embodiment, (a) is an example of a layout diagram (plan view) of a unit processing object (metal plate) S and a first object X when a predetermined yield is satisfied by processing only the first object X. (b) is an example of a layout diagram (plan view) of a unit processing object (metal plate) S and the first object X and the second object Y when a predetermined yield is not satisfied by processing only the first object X, and when a predetermined yield is not satisfied by processing the first object X and the second object Y. (c) is an example of a layout diagram (plan view) of a unit processing object (metal plate) S and the first object X and the second object Y when a predetermined yield is not satisfied by processing only the first object X, and when a predetermined yield is satisfied by processing the first object X and the second object Y. [Figure 10] FIG. 13 is an example of a layout diagram (plan view) of a unit processing object (metal plate) S and a first object X and a second object Y in a case where a predetermined yield is not satisfied by processing only multiple types of first objects X and Z, and a predetermined yield is satisfied by processing the multiple types of first objects X and Z and a second object Y in a batch processing process (cutting processing process) in the second embodiment. [Figure 11] FIG. 13 is a diagram showing a schematic configuration of a production plan creation device according to another embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0023] Next, an embodiment of the present invention will be described in detail with reference to the accompanying drawings. In this description, common parts are given common reference symbols throughout the drawings unless otherwise specified. In addition, the elements of the present embodiment are not necessarily shown to scale in the drawings. In addition, some symbols may be omitted in order to make each drawing easier to see.
[0024] <First embodiment> Fig. 1 is a diagram showing a schematic configuration of a production schedule creation device 100 for a production process including a batch processing process in this embodiment. Fig. 2 is a flowchart explaining an example of each process when the production schedule creation device 100 in this embodiment is used.
[0025] FIG. 3 is an explanatory diagram showing an example of calculating a requested completion deadline (first deadline) for a "batch processing process" among all the production processes for a confirmed order item (first target) or an unconfirmed order item (second target) in this embodiment, based on a deadline (hereinafter referred to as the "customer requested deadline") required by a customer or the like for completing all the production processes.
[0026] Moreover, Figure 4 is an explanatory diagram showing an example of a method for adjusting the completion request deadline of a batch processing process by the processing policy determination unit 32 when one type of first target and one type of second target both exist and the first deadline of the first target is different from the second deadline of the second target in this embodiment, and both the first target and the second target are processed by the batch processing process. Fig. 5 is an explanatory diagram corresponding to Fig. 4 in the present embodiment, in which two types of first objects and one type of second object exist together, and the first deadlines of the first objects and the second deadlines of the second objects are all different. In addition, Fig. 6 is an explanatory diagram corresponding to Fig. 4 in an example different from the example shown in Fig. 5.
[0027] The configuration of the production plan creation device 100 of this embodiment will be described below.
[0028] As shown in FIG. 1, the production plan creation device 100 of this embodiment has at least the following components (a1) to (d1). (a1) A first storage means 10 for storing first deadline information including a first deadline which is a deadline for requesting completion of a batch processing step for a confirmed order item (first target). (b1) A second storage means 20 for storing second deadline information including a second deadline which is a deadline for requesting completion of a batch processing step of an unconfirmed order item (second target). (c1) a processing policy decision unit 32 that decides a policy for processing one unit processing object that processes the first object and the second object in accordance with the first deadline, regardless of whether there is a difference between the first deadline and the second deadline; (d1) a production plan creation unit 60 that creates a production plan based on the first deadline determined by the processing policy determination unit 32;
[0029] The production plan creation device 100 of this embodiment creates a production plan for a production process in which at least a part of all the production processes for producing targets (first targets and second targets) that will become finished products (including intermediate products that may be transferred or leased) is a batch processing process. Each of the above-mentioned configurations (a1) to (d1) will be described in detail below.
[0030] The first storage means 10 of this embodiment stores first deadline information including a first deadline, which is a deadline requested for completion (e.g., a deadline requested for completion by a customer) of a batch processing process that is a part of a process for producing a confirmed order product, i.e., a first object. Therefore, the first deadline information stored in the first storage means 10 may be only the above-mentioned first deadline, but may also include, in addition to the first deadline, for example, product information of the first object, processing conditions, processing quantity, customer name, contact information, and / or information of the sales representative who received the order for the first object. As shown in FIG. 1, the first deadline information can be stored by the first storage means 10 of the production plan creation device 100 using the input unit 70, which is a known input means (e.g., a touch panel, a mouse, a keyboard, a microphone, etc.) for receiving various input operations.
[0031] The second storage means 20 of this embodiment stores second deadline information including a second deadline, which is a deadline requested for completion (for example, a deadline requested for completion from a potential customer) of a batch processing process that is a part of a process for producing an unconfirmed order product, i.e., a second object, whose order is not yet confirmed. Thus, similar to the first storage means 10, the second deadline information stored in the second storage means 20 may be only the second deadline described above, but may also include, in addition to the second deadline, for example, product information of the potential second object, processing conditions, processing quantity, customer name, contact information, and / or information of a sales representative who has gained the possibility of receiving an order for the second object through sales activities. Note that, similar to the first deadline information, the second deadline information can be stored by the second storage means 20 of the production plan creation device 100 using the input unit 70.
[0032] The processing policy decision unit 32 of this embodiment is, for example, a part of the first control unit 30 that is responsible for controlling the batch processing process. The processing policy decision unit 32 of this embodiment decides a policy for processing one unit processing target, which processes a first target that is a confirmed order item and a second target that is an unconfirmed order item, in accordance with the first deadline, regardless of whether there is a difference between the first deadline stored in the first storage means 10 and the second deadline stored in the second storage means 20. Note that, in this embodiment, the first control unit 30 includes the processing policy decision unit 32, but this embodiment is not limited to this aspect. For example, another aspect that can be adopted is that the processing policy decision unit 32 also serves as the first control unit 30.
[0033] In this embodiment, "one unit processing object" may refer to, for example, a metal material in a batch processing process in a production process of metal processed products, in which a single metal material (e.g., a metal plate) is cut to obtain multiple metal pieces (a first object or raw material for the first object, and a second object or raw material for the second object).
[0034] In the above example, the "one unit processing object" is one metal material (e.g., a metal plate), but examples of the "one unit processing object" are not limited to the metal material. For example, in a production process of a plated product in which the batch processing process is a plating process in which plating is performed on the surface of the plated product, the "one unit processing object" may be the number of plated processing objects (first object and second object) that can be immersed in a plating bath at one time. In a production process of a semiconductor product in which the batch processing process is a cleaning process of silicon wafers that are the source of semiconductor products, the "one unit processing object" may be the number of silicon wafers (first object and second object) that can be immersed in a cleaning solution at one time. In a production process of a steel product in which the batch processing process is a heat treatment process of steel material that is the source of steel products, the "one unit processing object" may be the number of processing objects (first object and second object) that can be heat treated in a heating furnace at one time.
[0035] Here, the first deadline (more precisely, the planned first deadline) and the second deadline (more precisely, the planned second deadline) of the batch processing process in this embodiment are calculated by the processing policy determination unit 32 in the first control unit 30 as follows:
[0036] FIG. 3 is an explanatory diagram showing an example of calculating a requested completion deadline (first deadline) of a "batch processing process" among all the production processes based on a customer requested deadline ("Z" in FIG. 3) from a customer, etc., for a firm order item (first target) in this embodiment. The example in FIG. 3 shows an example of a production schedule (production plan) for producing product A. Also, "dates" are a list of some dates in a certain month, provided for the convenience of explaining FIG. 3.
[0037] To explain a typical example, when the batch processing process is the above-mentioned cutting processing process, the first deadline for the batch processing process ("Pa1" in FIG. 3) is calculated based on the customer request deadline ("Z" in FIG. 3) and by working backwards (in other words, counting backwards) from the customer request deadline, taking into consideration the waiting period for shipment after all production processes are completed (the period from "Pa3" to "Z" in FIG. 3), the end time (or end date) of the "welding process" ("Pa3" in FIG. 3), and the end time (or end date) of the "pressing process" ("Pa2" in FIG. 3). In other words, the requested deadline for completion of the "batch processing process" (first deadline) can be calculated based on the customer-requested deadline ("Z" in Figure 3), the waiting period (the period from "Pa3" to "Z" in Figure 3), the time (or number of days) required for the welding process (the period from "Pa2" to "Pa3" in Figure 3), and the time (or number of days) required for the pressing process (the period from "Pa1" to "Pa2" in Figure 3).
[0038] Therefore, as also applied to Figures 4 to 6 described below, in the production plan creation device 100 of this embodiment, before the first deadline is stored in the first storage means 10, the customer requested deadline ("Z" in Figure 3) is stored in the first storage means 10, and the requested completion deadline (first deadline) of the "batch processing process" is calculated by going back (in other words, calculating backwards) from the customer requested deadline based on the period required for one or more processes after the "batch processing process". This is another aspect that can be adopted.
[0039] In the above example, the "standby period" may be calculated as a "spare time (or spare days)" in case the "batch processing step", the "welding step" and / or the "pressing step" take longer than expected due to some circumstances. In another example, the "standby period" may be calculated as a "slow cooling step / room temperature leaving step" following the "welding step", and the first deadline may be calculated.
[0040] The above-mentioned example of the first deadline of the first object, which is a confirmed order item, can also be applied to the second deadline of the second object, which is an unconfirmed order item. Therefore, another possible embodiment is that before the second deadline is stored in the second storage means 20, the customer-requested deadline of the second object ("Z" in FIG. 3) is stored in the second storage means 20, and the requested deadline for completion of the "batch processing process" (second deadline) is calculated by going back (in other words, calculating backwards) from the customer-requested deadline based on the period required for one or more processes after the "batch processing process".
[0041] The production plan creation unit 60 of this embodiment creates a production plan based on the first deadline determined by the processing policy determination unit 32.
[0042] Specifically, the production plan creation unit 60 includes a first control unit 30 including a processing policy determination unit 32, and a second control unit 90. The second control unit 90 is responsible for controlling all (one or more) processing steps other than the batch processing step in the production process of this embodiment (including, for example, providing information on the processing step and adjusting the processing plan for the processing step). The second control unit 90 of this embodiment may employ a known control system (for example, "TPiCS (registered trademark)-X-5.1" manufactured by TPix Laboratory Co., Ltd., "FLEXSCHE (registered trademark) GP" manufactured by FLEXSCHE Co., Ltd., or "Seiryu (registered trademark)" manufactured by Technoa Co., Ltd.).
[0043] Based on the adjusted processing plan (which may also be called a "processing schedule") for all processing steps other than the batch processing step provided by the second control unit 90 and the first deadline determined by the processing policy determination unit 32, the production plan creation unit 60 creates a production plan for the first target, which is a confirmed order item in this embodiment, and the second target, which is an unconfirmed order item. The production plan creation unit 60 in this embodiment may employ a known production planning system, for example, "TPiCS (registered trademark)-X-5.1" manufactured by TPix Laboratory Co., Ltd., "FLEXSCHE (registered trademark) GP" manufactured by FLEXSCHE Co., Ltd., or "Seiryu (registered trademark)" manufactured by Technoa Co., Ltd.
[0044] In this embodiment, the production plan created by the above-mentioned production plan creation unit 60 can be output by the output unit 80 (for example, a display device, an audio output device, a USB terminal, a printer, a communication device) as necessary. For example, the output unit 80 can output a delivery schedule for a production process including a batch processing process.
[0045] Next, mainly based on Figures 1, 2, 4 and 5, two examples will be explained in which a first object which is a confirmed order item and a second object which is an unconfirmed order item are processed in one unit processing object.
[0046] The production plan creation process of this embodiment includes the steps shown in FIG.
[0047] First, various information on the first target of the confirmed order item (first deadline information including at least the first deadline) and various information on the second target of the unconfirmed order item (second deadline information including at least the second deadline) are input using the input unit 70 (step Sa1). As a result, in one example of this embodiment, the first storage means 10 can store at least the first deadline information, and the second storage means 20 can store at least the second deadline information.
[0048] Thereafter, regardless of whether there is a difference between the first deadline stored in the first storage means 10 and the second deadline stored in the second storage means 20, a policy is determined to process one unit processing object (e.g., one metal plate) that processes the first object, which is a confirmed order item, and the second object, which is an unconfirmed order item, in accordance with the first deadline (step Sa2). In one example of this embodiment, this policy determination can be performed by the processing policy determination unit 32.
[0049] Thereafter, a production plan based on the first deadline determined in step Sa2 is created (step Sa3). In one example of this embodiment, the production plan is created by the production plan creation unit 60. For example, a production plan for the first target and the second target in this embodiment can be created based on information on a processing plan provided by a second control unit 90 that controls all (one or more) processing steps other than the batch processing step in the production process of this embodiment, and the first deadline determined by the processing policy determination unit 32.
[0050] FIG. 4 is an explanatory diagram showing an example of a method for adjusting the requested completion deadline of a batch processing process by the processing policy decision unit 32 when one type of first target and one type of second target both exist as production targets in a production plan of this embodiment, and the first deadline of the first target is different from the second deadline of the second target, and both the first target and the second target are processed by a batch processing process.
[0051] In the example of FIG. 4, product A is the first target of the confirmed order item, and product B is the second target of the unconfirmed order item. Pa1, Pa2, and Pa3 are all the same as those described in FIG. 3. FIG. 4(a) is an example of the stage of the above-mentioned step Sa1, and FIG. 4(b) is the stage of the above-mentioned step Sa2 or step Sa3. To explain in more detail, in FIG. 4(b), the first and second deadlines of Pa1 are aligned so as to fall within the dotted frame (9 days in FIG. 4), in other words, the stage of step Sa2 is determined to process the second deadline in accordance with the first deadline. In addition, the stage of step Sa3 is determined by the production plan creation unit 60 creating a production plan (delivery date forecast) that determines the delivery dates (Z in FIG. 4(b)) of products A and B based on the first deadline.
[0052] As shown in FIG. 4(a), at the stage of step Sa1, in other words, before the processing policy decision unit 32 decides on the policy for the deadline for requested completion of the batch processing process, it can be seen that the second deadline (7 days in FIG. 4) calculated by calculating backwards from the delivery date (more precisely, the predicted delivery date) (Z) of product B (second target) is earlier than the first deadline (9 days in FIG. 4) calculated by calculating backwards from the delivery date (more precisely, the predicted delivery date) (Z) of product A (first target).
[0053] 4(b), in this embodiment, the processing policy decision unit 32 decides to process a batch processing step (e.g., a laser cutting step) using one unit processing object (e.g., a metal plate) in accordance with the first deadline. Therefore, in this example, the processing policy decision unit 32 decides a processing policy in accordance with the first deadline stored in the first storage means 10, and the production plan creation unit 60 creates a production plan based on the first deadline.
[0054] 4 also applies to a case where the first deadline of product A (first target) is earlier than the second deadline of product B (second target). In other words, when the first deadline of the first target is earlier than the second deadline of the second target, the processing policy decision unit 32 decides a processing policy to match the first deadline.
[0055] Therefore, in the example of Figure 4, even if a first object and a second object are included as production objects, a production plan is created that virtually includes the second object, so to speak, by using the first deadline for the batch processing process, which is the most difficult production process to determine the end time for, determined by the processing policy determination unit 32, without taking into account the delivery date for the second object.
[0056] FIG. 5 also shows an example of a case in which two types of first objects and one type of second object exist as production objects in the production plan of this embodiment, and the first deadlines of the first objects and the second deadlines of the second objects are all different.
[0057] In the example of FIG. 5, products A and C are the first targets of the confirmed order items, and product B is the second target of the unconfirmed order items. Pa1, Pa2, and Pa3 are all the same as those explained in FIG. 3. Pa4 may be, for example, an "assembly process." In addition, FIG. 5(a) is an example of the stage of step Sa1 described above, and FIG. 5(b) is the stage of step Sa2 or step Sa3 described above, similar to the explanation of FIG. 4(b).
[0058] As shown in Figure 5(a), at the stage of step Sa1, in other words, before the policy for the required completion deadline for the batch processing process is decided by the processing policy decision unit 32, the required completion deadline for the "batch processing process" among all production processes for each of two types of first targets (products A and C) and one type of second target (product B) is calculated for the first targets and the second targets, respectively, and it is found that the earliest required completion deadline for the batch processing process is one of the first deadlines (7 days in Figure 5).
[0059] 5(b), in this embodiment, the processing policy determination unit 32 determines that a batch processing step (e.g., a laser cutting step) using one unit processing object (e.g., a metal plate) is to be processed according to the earliest first deadline. Therefore, in this example, when the first storage means 10 contains first deadline information including a plurality of different first deadlines, the processing policy determination unit 32 determines a policy of processing according to the earliest first deadline, and the production plan creation unit 60 creates a production plan based on the earliest first deadline.
[0060] On the other hand, Figure 6 shows another example where two types of first objects and one type of second object exist, and the first deadlines of the first objects and the second deadlines of the second objects are all different.
[0061] In the example of Figure 6, similarly to the example shown in Figure 5, products A and C are the first targets of confirmed order items, and product B is the second target of unconfirmed order items. Also, Pa1, Pa2, Pa3, and Pa4 are all the same as those explained in Figure 5. Also, Figure 6(a) is an example of the stage of step Sa1 described above, and Figure 6(b) is the stage of step Sa2 or step Sa3 described above, similarly to the explanation of Figure 4(b).
[0062] As shown in Figure 6(a), for two types of first targets (products A and C) and one type of second target (product B), the required completion deadline for the "batch processing process" among all production processes was calculated for each of the first targets and the second targets. As a result, it was found that the earliest required completion deadline for the batch processing process is the second deadline (7 days in Figure 6).
[0063] However, in the example shown in FIG. 6, the processing policy determination unit 32 determines that a batch processing process (e.g., a laser cutting process) using one unit processing object (e.g., a metal plate) will be processed according to the earliest first deadline, rather than the second deadline.
[0064] 5, in this example, when the first storage means 10 includes a plurality of different first deadlines, the processing policy decision unit 32 decides a processing policy according to the earliest first deadline, and the production plan creation unit 60 creates a production plan based on the earliest first deadline. From a different perspective, even when the second storage means 20 stores second deadline information including a second deadline that is earlier than the first deadline, the processing policy decision unit 32 decides a processing policy according to the earliest first deadline, and the production plan creation unit 60 creates a production plan based on the earliest first deadline.
[0065] Furthermore, a person skilled in the art, upon reading each of the above examples, would be able to apply the above examples to batch processing steps other than the cutting processing step without individual explanation.
[0066] As described above, in this embodiment, regardless of whether there is a difference between the first deadline and the second deadline, the processing policy decision unit 32 decides a policy for processing one unit processing object that processes the first object and the second object in accordance with the first deadline. As a result, even in a production process that includes a batch processing process that processes the first object and the second object, it is possible to greatly increase the accuracy of delivery date prediction.
[0067] The production plan creation program of this embodiment will be described below.
[0068] 2 in the above-mentioned production plan creation device 100 can be read as each step in the production plan creation program of this embodiment executed by a computer. Therefore, the above-mentioned processing policy decision step by the processing policy decision unit 32 can be read as a processing policy decision step, and the above-mentioned production plan creation step by the production plan creation unit 60 can be read as a production plan creation step. Therefore, the production plan creation program can include instructions for causing a computer to execute each step.
[0069] The production plan creation program of this embodiment can be used together with the production plan creation device 100 or apart from the production plan creation device 100. For example, a server equipped with a CPU (Central Processing Unit) monitors or integrally controls each process shown in FIG. 2 by a program for executing each process shown in FIG. 2. In this embodiment, the program can be stored in a storage means of the server (for example, a known hard disk drive) or a known recording medium such as an optical disk inserted into an optical disk drive or the like provided in the server, but the storage destination of the program is not limited thereto. For example, a part or all of the program can monitor or control each process shown in FIG. 2 via a known technology such as a local area network or an Internet line.
[0070] In addition, the above-mentioned production plan creation device 100 or production plan creation program can be applied even when the production process of one product includes two or more batch processing processes. That is, in the batch processing process, regardless of whether or not there is a difference between the first deadline of the first object and the second deadline of the second object, a production plan creation device or a production plan creation program can be implemented by a person skilled in the art who has come into contact with this specification, in which a unit processing object that processes the first object and the second object is processed according to the first deadline and an overall production plan is created based on the first deadline.
[0071] Furthermore, in the case where the first storage means 10 contains a plurality of different first deadlines, the production plan creation program of this embodiment determines a processing policy in accordance with the earliest first deadline in the processing policy decision step, and creates a production plan based on that earliest first deadline in the production plan creation step.
[0072] <Second embodiment> Next, this embodiment will be described in detail with reference to Figures 7 to 10. Note that descriptions that overlap with the first embodiment may be omitted.
[0073] Fig. 7 is a diagram showing a schematic configuration of a production schedule creation device 200 for a production process including a batch processing process in this embodiment. Fig. 8 is a flowchart explaining an example of each process when the production schedule creation device 200 in this embodiment is used.
[0074] 9 shows an example of a layout diagram (plan view) of a unit processing object (metal plate) S and a first object X when a predetermined yield is satisfied by processing only the first object X, (b) an example of a layout diagram (plan view) of a unit processing object (metal plate) S and the first object X and the second object Y when a predetermined yield is not satisfied by processing only the first object X, and when a predetermined yield is not satisfied by processing the first object X and the second object Y, and (c) an example of a layout diagram (plan view) of a unit processing object (metal plate) S and the first object X and the second object Y when a predetermined yield is not satisfied by processing only the first object X, and when a predetermined yield is satisfied by processing the first object X and the second object Y.
[0075] The configuration of the production plan creation device 200 of this embodiment will be described below.
[0076] As shown in FIG. 7, the production plan creation device 200 of this embodiment has at least the following components (a2) to (g2). (a2) A first storage means 10 for storing first deadline information including a first deadline, which is a deadline for requesting completion of a batch processing step, of a confirmed order item (first object), and first specification information, which is a specification of the first object. (b2) A second storage means 20 for storing second deadline information including a second deadline, which is a deadline for requesting completion of a batch processing step, of an unconfirmed order item (second object), and second specification information, which is a specification of the second object. (c2) a first judgment unit 34 that judges whether a predetermined yield is satisfied by processing only the first object in one unit processing object that processes the first object and the second object; (d2) a processing method determination unit 36 that determines a processing method for the first object and the second object in the unit processing object based on the first specification information and the second specification information when the predetermined yield is not satisfied by processing only the first object. (e2) a second judgment unit 38 that judges whether the processing method determined by the processing method determination unit 36 satisfies the predetermined yield. (f2) a processing policy decision unit 32 that decides a policy for processing one unit processing object that processes the first object and the second object in accordance with the first deadline, when the second judgment unit 38 judges that the predetermined yield is satisfied, regardless of whether there is a difference between the first deadline and the second deadline. (g2) a production plan creation unit 60 that creates a production plan based on the first deadline determined by the processing policy determination unit 32 when the second judgment unit 38 determines that the predetermined yield is satisfied.
[0077] The production schedule creation device 200 of this embodiment, like the production schedule creation device 100 of the first embodiment, creates a production plan for a production process in which at least a part of all the production processes for producing objects (first objects and second objects) that will become finished products (including intermediate products that may be transferred or leased) is a batch processing process. Each of the above-mentioned configurations (a2) to (g2) will be described in detail below.
[0078] The first storage means 10 of this embodiment stores at least the first deadline information including the first deadline, which is the requested end deadline (e.g., the requested end deadline from the customer) of the batch processing process, which is a part of the process of producing the confirmed order product, i.e., the first object, and the first specification information, which is the specification of the first object. Note that, in this embodiment, the "specification" means, for example, when the batch processing process is a laser cutting process and one unit processing object to be cut in the laser cutting process is a metal plate, the requirements for the first object or the raw material of the first object, such as the "type of metal (composition of the alloy if the metal is an alloy)", "thickness of the metal", and / or "shape of the metal piece obtained after cutting" of the metal plate. In addition, the first storage means 10 can store information other than the above-mentioned first deadline information and first specification information, as in the first embodiment.
[0079] The second storage means 20 of this embodiment stores at least second deadline information including a second deadline, which is a requested end deadline (e.g., a requested end deadline from a customer) of a batch processing process that is a part of a process for producing an unconfirmed order product, i.e., a second object, and second specification information, which is a specification of the second object. Similarly to the first embodiment, the second storage means 20 can also store information other than the above-mentioned second deadline information and second specification information.
[0080] Explaining with reference to the flowchart of Fig. 8, in this embodiment, various information of the first object (at least the first deadline information and first specification information) and various information of the second object of the unconfirmed order item (at least the second deadline information and second specification information) are input using the input unit 70 (step Sb1). As a result, as described above, in one example of this embodiment, the first storage means 10 can store at least the first deadline information and the first specification information, and the second storage means 20 can store at least the second deadline information and the second specification information.
[0081] The first determination unit 34, the processing method determination unit 36, the second determination unit 38, and the processing policy determination unit 32 of this embodiment can function as part of a first control unit 230 that is responsible for controlling the batch processing process, for example.
[0082] The first judgment unit 34 of this embodiment judges, based on the above-mentioned information on the first object and the information on the second object input from the input unit 70, whether or not a specified yield can be met by processing only the first object when the first object and the second object are processed in one unit processing object (first judgment process, step Sb2).
[0083] In the production plan creation device 200, for example, when a "single unit processing object" is a metal plate, and it is preset that the "predetermined yield" is "satisfied" when 40% or more of the mass, weight, or area of the metal plate in a planar view can be considered as the area of the metal pieces obtained after cutting, the first judgment unit 34 judges whether or not the area of the metal pieces is 40% or more in the metal plate that processes a first object and a second object by processing only the first object.
[0084] In the case of Fig. 9(a) using the above example, the ratio of the area occupied by the first object X, which is a metal piece (a hexagonal metal piece in a plan view) obtained after cutting, to the total area of the metal plate S in a plan view is 40% or more. Explaining with reference to the flowchart of Fig. 8, as shown in step Sb2, in the case of Fig. 9(a), the first judgment unit 34 creates a production plan based on processing only the first object in the "one unit processing object" since the area of the metal piece is 40% or more by processing only the first object, in other words, presents a delivery date forecast (in this example, a delivery date forecast for only the first object) to a customer, etc.
[0085] On the other hand, if the first judgment unit 34 determines that a predetermined yield (e.g., 40% or more) will not be met by processing only the first object X, the processing method determination unit 36 determines the processing method for the first object and the second object in the one unit processing object based on the first specification information of the first object and the second specification information of the second object (processing method determination process, step Sb3).
[0086] 9(b) or (c) using the above example, the area of the hexagonal metal pieces obtained after cutting by processing only the first object X satisfies a predetermined yield (e.g., 40% or more). Therefore, in these cases, as shown in steps Sb2 and Sb3 in FIG. 8, the processing method determination unit 36 determines a processing method for processing both the first object X and the second object Y in the one unit processing object.
[0087] An example of the above-mentioned "processing method" is, in the case of FIG. 9(b) or (c) above, arranging the first object X and the second object Y of the metal pieces obtained after cutting for one unit processing object (metal plate S) so that they are ideally closest packed in a plan view.
[0088] Thereafter, when the above-mentioned processing method is determined in step Sb3, the second judging section 38 of this embodiment judges whether or not the above-mentioned "predetermined yield" is satisfied by the processing method (second judgment step, step Sb4).
[0089] 9(b) using the above example, even if both the first object X (a metal piece having a hexagonal shape in a plan view) and the second object Y (a metal piece having a pentagonal shape in a plan view) of the metal pieces obtained after cutting are arranged on the metal plate S, the proportion of the mass or weight or the total area of the first object X and the second object Y, which are metal pieces obtained after cutting, is less than 40%. Therefore, in the example of FIG. 9(b), as a result of the judgment by the second judgment unit 38, the process returns to the stage of exploring the possibility of receiving new orders for the first object and / or the second object (i.e., step Sb1).
[0090] In addition, in FIG. 9(c) using the above example, both the first object X and the second object Y of the metal piece obtained after cutting are arranged on the metal plate S, so that the total area occupied by the first object X and the second object Y, which are metal pieces obtained after cutting, is 40% or more. Therefore, in the example of FIG. 9(c), as a result of the judgment by the second judgment unit 38, regardless of whether there is a difference between the first deadline stored in the first storage means 10 and the second deadline stored in the second storage means 20, a policy is decided to process one unit processing object (one metal plate in this example) that processes the first object, which is a confirmed order item, and the second object, which is an unconfirmed order item, in accordance with the first deadline (processing policy decision process, step Sb5). In one example of this embodiment, this policy can be decided by the processing policy decision unit 32.
[0091] In this embodiment, when a processing policy is determined by the processing policy determination unit 32, a production plan based on the first deadline is created using the first control unit 230 including the processing policy determination unit 32 and the second control unit 90, as in the first embodiment (production plan creation process, step Sb6). In one example of this embodiment, the production plan can be created by the production plan creation unit 260.
[0092] As described above, in this embodiment, regardless of whether there is a difference between the first deadline and the second deadline, the processing policy decision unit 32 decides a policy for processing one unit processing target that processes the first target and the second target in accordance with the first deadline. In addition, the production plan creation device 200, which includes the first judgment unit 34 and the second judgment unit 38, creates a production plan taking into consideration the viewpoint of yield (which may include the viewpoint of manufacturing cost and production efficiency). As a result, even in a production process that includes a batch processing process in which the first target and the second target are processed, it is possible to present a more accurate production plan (more specifically, a delivery date forecast) for the second target in particular, to a customer, etc., taking into consideration the yield.
[0093] The production plan creation program of this embodiment will be described below.
[0094] The description of each step in the flowchart shown in Fig. 8 in the above-mentioned production plan creation device 200 can be read as a description of each step in the production plan creation program of this embodiment executed by a computer. Therefore, the first judgment step by the above-mentioned first judgment unit 34 can be read as a first judgment step, and the above-mentioned processing method determination step by the processing method determination unit 36 can be read as a processing method determination step. Furthermore, the above-mentioned second judgment step by the second judgment unit 38 can be read as a second judgment step, and the above-mentioned processing policy determination step by the processing policy determination unit 32 can be read as a processing method determination step. Therefore, the production plan creation program may include an instruction to cause a computer to execute each step.
[0095] The production plan creation program can be used together with the production plan creation device 200 or independently of the production plan creation device 200. For example, a server equipped with a CPU (Central Processing Unit) monitors or integrally controls each process shown in FIG. 8 by a program for executing each step shown in FIG. 8. In this embodiment, the program can be stored in a storage means of the server (for example, a known hard disk drive) or a known recording medium such as an optical disk inserted into an optical disk drive or the like provided in the server, but the storage destination of the program is not limited thereto. For example, a part or all of the program can monitor or control the process shown in FIG. 2 via a known technology such as a local area network or an Internet line.
[0096] In addition, the above-mentioned production plan creation device 200 or production plan creation program can be applied even when the production process of one product includes two or more batch processing steps. That is, if the batch processing step does not satisfy a predetermined yield rate by processing only the first object, and if the predetermined yield rate is satisfied when the first object and the second object are processed by the processing method determined by the processing method determination unit or the processing method determination step, a person skilled in the art who has come into contact with this specification can implement a production plan creation device or a production plan creation program in which an entire production plan is created based on the first deadline.
[0097] <Modification of the second embodiment> This modified example is similar to the second embodiment, except that two types of first objects and one type of second object exist as production objects in the production plan, and the first deadlines of the first objects and the second deadlines of the second objects are all different. Therefore, explanations that overlap with the first embodiment or the second embodiment may be omitted.
[0098] For ease of explanation of this modified example, we will use as an example a case in which a batch processing process, which is part of the process for producing the first object and the second object, is a laser cutting process, and one unit processing object to be cut in the laser cutting process is a metal plate.
[0099] FIG. 10 shows an example of a layout diagram (in a plan view) of a unit processing object (metal plate) S and first objects X and second objects Y in a case where, when processing using a batch processing process (cutting processing process) in this modified example, a predetermined yield is not met by processing only multiple types of first objects X (metal pieces having a hexagonal shape in a plan view) and Z (metal pieces having a diamond shape in a plan view), and the predetermined yield is met by processing the multiple types of first objects X, Z and a second object Y (metal pieces having a pentagonal shape in a plan view).
[0100] 10, which employs the above-mentioned example, the processing method for processing both the first object X and the second object Y in the single unit processing object is determined by the processing method determination unit 36 (step Sb3). Therefore, thereafter, the second judgment unit 38 judges that the total area of each metal piece obtained after cutting by processing the multiple types of first objects X, Z and second object Y satisfies a predetermined yield (e.g., 40% or more) (step Sb4).
[0101] As a result of the judgment made by the second judgment unit 38, regardless of whether there is a difference between the first deadline stored in the first storage means 10 and the second deadline stored in the second storage means 20, if the first storage means 10 contains multiple different first deadlines, the production plan creation device 200 of this modified example determines a processing policy to be in accordance with the earliest first deadline in the processing policy decision step.
[0102] Therefore, in this modified example, when the first storage means 10 includes a plurality of different first deadlines, the processing policy decision unit 32 decides a processing policy to match the earliest first deadline, and the production plan creation unit 60 creates a production plan based on the earliest first deadline. From a different perspective, even when the second storage means 20 stores second deadline information including a second deadline that is earlier than the first deadline, the processing policy decision unit 32 decides a processing policy to match the earliest first deadline, and the production plan creation unit 60 creates a production plan based on the earliest first deadline.
[0103] Regarding the production plan creation program of this modified example, when the first storage means 10 contains a plurality of different first deadlines, the production plan creation program of this modified example determines a processing policy in accordance with the earliest first deadline in the processing policy decision step, and creates a production plan based on that earliest first deadline in the production plan creation step.
[0104] <Other embodiments> In the above-mentioned embodiments and modifications, the first storage means 10 and the second storage means 20 are provided as separate recording media, but the above-mentioned embodiments and modifications are not limited to such an embodiment. FIG. 11 is a diagram showing a schematic configuration of a production plan creation device 300 as another embodiment. As shown in FIG. 11, a first storage means 312 that plays the role of the first storage means 10 and a second storage means 314 that plays the role of the second storage means 20 may be configured as a single recording medium 310. In other words, a single recording medium 310 may play the roles of both the first storage means 10 and the second storage means 20 of the first embodiment, for example.
[0105] In the above-mentioned first embodiment, a single unit processing object that processes two types of first objects and one type of second object is described as an example in Fig. 5 and Fig. 6, but the above-mentioned first embodiment and other embodiments and modifications are not limited to such an aspect. For example, the above-mentioned embodiments and modifications can be applied to a single unit processing object that processes multiple types of first objects and multiple types of second objects.
[0106] Furthermore, in each of the above-mentioned embodiments and variants, even if there is a difference between the first deadline and the second deadline in the processing policy determination unit 32, the processing policy determination process, or the processing policy determination step, a policy is determined to process one unit processing object that processes the first object and the second object in accordance with the first deadline. However, if the difference between the first deadline and the second deadline is too large, this may be desirable from the viewpoint of presenting a highly accurate production plan (more specifically, a delivery date forecast) for the second object, which is an unconfirmed order item, to a customer, but may not be desirable from the viewpoint of presenting the earliest possible delivery date forecast.
[0107] Therefore, in each of the above-mentioned embodiments and variant examples, creating a production plan based on the first deadline only when the difference between the first deadline and the second deadline is 168 hours or less (7 days or less) (more preferably 120 hours or less (5 days or less), and even more preferably 72 hours or less (3 days or less)), is a more preferable aspect from the viewpoint of being able to present a highly accurate production plan (more specifically, a delivery date forecast) for the second target, which is an unconfirmed order item, to a customer, etc., and also presenting a delivery date forecast as early as possible.
[0108] The disclosure of the above-mentioned embodiments is provided for the purpose of explaining the embodiments, and is not provided for the purpose of limiting the present invention. In addition, modifications within the scope of the present invention, including other combinations of the above-mentioned embodiments, are also included in the scope of the claims. [Industrial Applicability]
[0109] The production planning device and production planning program of the present invention can be widely used as a production planning device or production planning program for production processes including batch processing processes, taking into account not only confirmed order items but also unconfirmed order items. [Explanation of symbols]
[0110] 10,312 1st storage means 20,314 Second storage means 30,230 First Control Section 32 Processing Policy Decision Department 34 1st Judgment Department 36 Processing Method Decision Section 38 Second Judgment Department 60,260 Production Planning Department 70 Input section 80 Output section 90 Second Control Section 100,200,300 Production planning device 310 Recording media
Claims
1. A production plan creation device that creates a production plan for a production process including a batch processing process, a first storage means for storing first deadline information including a first deadline that is a deadline for requesting completion of the batch processing step for a first object for which an order has been confirmed; A second storage means for storing second deadline information including a second deadline that is a deadline for requesting completion of the batch processing process of a second target whose order has not been confirmed; a processing policy decision unit that decides a policy for processing one unit processing target, which processes the first target and the second target, in accordance with the first deadline, regardless of whether there is a difference between the first deadline and the second deadline; a production plan creation unit that creates the production plan based on the first deadline determined by the processing policy determination unit, Production planning device.
2. The first storage means further stores first specification information which is a specification of the first object, The second storage means further stores second specification information which is a specification of the second object, a first determination unit that determines whether or not a predetermined yield is satisfied by processing only the first object in the unit processing object; a processing method determination unit that determines a processing method for the first object and the second object in the unit processing object based on the first specification information and the second specification information when the predetermined yield is not satisfied by processing only the first object; a second determination unit that determines whether the predetermined yield is satisfied by the processing method determined by the processing method determination unit, When the second judgment unit judges that the predetermined yield is satisfied, the production plan creation unit creates the production plan based on the first deadline determined by the processing policy decision unit. The production plan creating device according to claim 1.
3. When one or more types of the first objects include a plurality of different first deadlines in the first storage means, the processing policy decision unit decides a processing policy according to the earliest first deadline, and the production plan creation unit creates the production plan based on the earliest first deadline. The production plan creation device according to claim 1 or 2.
4. the production plan creation unit creates the production plan based on the first deadline only when a difference between the first deadline and the second deadline is 168 hours or less. The production plan creation device according to claim 1 or 2.
5. Further, an output unit is provided which outputs a delivery schedule of the production process including the batch processing process based on the production plan. The production plan creation device according to claim 1 or 2.
6. The first storage means and the second storage means are a single recording medium. The production plan creation device according to claim 1 or 2.
7. A production planning program for creating a production plan for a production process including a batch processing process, a processing policy decision step for deciding a policy for processing one unit processing object for processing the first object and the second object in accordance with the first deadline, regardless of whether there is a difference between the first deadline and the second deadline, based on first deadline information including a first deadline that is a requested deadline for completing the batch processing process of a first object whose order has been confirmed and stored in a first storage means, and second deadline information including a second deadline that is a requested deadline for completing the batch processing process of a second object whose order has not been confirmed and stored in a second storage means; and a production plan creating step of creating the production plan based on the first deadline determined by the processing policy determining step. Production planning program.
8. First specification information, which is a specification of the first object, is further stored in the first storage means; Second specification information, which is a specification of the second object, is further stored in the second storage means; a first determination step of determining whether a predetermined yield is satisfied by processing only the first object in the unit processing object; a processing method determination step of determining a processing method for the first object and the second object in the unit processing object based on the first specification information and the second specification information when the predetermined yield is not satisfied by processing only the first object; a second determination step of determining whether the predetermined yield is satisfied by the processing method determined by the processing method determination step, When it is determined in the second determination step that the predetermined yield is satisfied, the production plan creation step creates the production plan based on the first deadline determined in the processing policy determination step. The production plan creation program according to claim 7.
Citation Information
Patent Citations
Production schedule generating device
JP1994075970A
Production planning method and integrated operation system for dyeing factory
JP2002073149A
System, method, device and program for supporting production management
JP2003186523A
Supporting system and method for business operation
JP2003345969A
Adjustment request support device, delivery date reply / shipment adjustment system, and delivery date reply / shipment adjustment method
JP2008021182A