Repair method for thin layer floating parts of exterior wall tiles
The repair method for exterior wall tiles addresses tile peeling and floating issues by forming grooves, inserting anchor members, and injecting adhesives to stabilize the bond between the concrete frame and crimp mortar, providing a durable solution for wet construction methods.
Patent Information
- Application Number
- JP2021064109
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2020-04-28
- Filing Date
- 2021-04-05
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2041-04-05
AI Technical Summary
The frequent occurrence of tile peeling and floating issues in exterior walls constructed using wet construction methods with 45 Nicho tiles and 45 mosaic tiles, leading to a decline in construction quality and the need for effective repair methods.
A repair method involving groove formation, anchor member insertion, adhesive injection, and joint filling to stabilize the bond between the concrete frame and crimp mortar, using a thin plate-shaped anchor member and adhesives to secure the tiles.
Effectively repairs thin floating portions by enhancing the adhesion between the concrete frame and crimp mortar, preventing further separation and ensuring a durable bond.
Smart Images

Figure 0007588409000001 
Figure 0007588409000002 
Figure 0007588409000003
Abstract
Description
[Technical field]
[0001] This invention relates to a repair method for thin layer floating parts of exterior wall tiles, and in particular to a repair method for floating parts in wet mosaic sheet construction using 45 two-piece tiles, 45 mosaic tiles, etc. [Background technology]
[0002] Mosaic sheet construction using wet construction methods such as 45 Nito tiles and 45 Mosaic tiles gives a luxurious feel to exterior walls and is thought to be easy to maintain, so it has become explosively popular and widely used. This has accelerated competition in the construction industry, and cheap construction has become more common. This is thought to have caused problems such as a decline in construction quality in some areas.
[0003] Due to these various problems, the symptoms of tile peeling and floating have become evident and are occurring frequently today.
[0004] It is believed that replacement should be carried out for tile fragments that have peeled off or other problems with construction. In addition, various proposals have been made for preventing tiles from peeling off and repairing floating tiles on directly attached exterior walls (for example, Patent Documents 1, 2, and 3).
[0005] When using 45mm 2-piece tiles, 45mm mosaic tiles, etc. for wet mosaic sheet installation, the general procedure for installing the mosaic is to high-pressure wash and roughen the concrete structure, apply base adjustment mortar (which is only done partially these days to repair gaps in the tiles), apply pressed mortar, install the mosaic sheet, and then fill in the tile joints.
[0006] In tile exterior walls constructed in this manner, peeling can occur between the concrete structure and the compressed mortar, which can result in floating between the concrete structure and the compressed mortar.
[0007] The techniques of Patent Documents 1, 2, 3, etc. mainly relate to a construction method for repairing peeling between compressed mortar and tile material (loose ceramic pieces of tile).
[0008] There has been a proposal for an exterior wall repair method that aims to form a strong repair mortar layer on the outside of an exterior wall where floating has occurred between the surface layer and the structure by integrating it with the structure (Patent Document 4).This involves forming a mortar layer on the outside of an exterior wall where floating has occurred between the surface layer formed of mortar or tiles and the structure, with a net buried in it that is fixed to the structure with anchors. [Prior art documents] [Patent documents]
[0009] [Patent Document 1] JP 2007-51538 A [Patent Document 2] JP 2016-199950 A [Patent Document 3] JP 2018-197477 A [Patent Document 4] Japanese Patent Application Publication No. 11-36610 Summary of the Invention [Problem to be solved by the invention]
[0010] The purpose of this invention is to propose a repair method for floating areas in wet mosaic sheet construction using 452 tiles, 45 mosaic tiles, etc., in particular a repair method for floating areas that occur between the concrete structure and pressed mortar, i.e. a repair method for thin layer floating areas of exterior wall tiles. [Means for solving the problem]
[0011] [1] A repair method for a floating land occurring between a concrete structure and the pressure-bonded mortar of a building having a structure in which tiles are attached to the concrete structure via pressure-bonded mortar, comprising the steps of: a groove forming step of forming a groove in the joint of the tile in the region where the floating occurs, the groove having a predetermined upper end opening length extending in the longitudinal direction of the joint, a predetermined engraved depth extending to a depth reaching the inside of the surface of the concrete structure, and a predetermined narrow width in a lateral direction perpendicular to the longitudinal direction; an anchor insertion process for inserting a thin-plate-shaped anchor member into the groove, the thin-plate-shaped anchor member having an upper end edge having an upper end edge length corresponding to the upper end opening length of the groove, a vertical length from the upper end edge to a lower end edge opposite to the upper end edge side having a size corresponding to the engraved depth of the groove, and a thickness corresponding to the lateral width of the groove; a first adhesive injection step of injecting a first adhesive between the inner wall surface of the groove and both side wall surfaces of the anchor member and into the floating land between the concrete body and the pressure-bonded mortar; a joint filling step of filling the joints after the adhesive has hardened; A repair method for thin floating parts of exterior wall tiles.
[0012] [2] After the groove forming step and before the anchor inserting step, A repair method for a thin layer of floating land of an exterior wall tile [1], which includes a floating land depth confirmation process for confirming the depth from the surface of the tile to the floating land.
[0013] [3] A repair method for a thin floating portion of an exterior wall tile according to [1] or [2], further comprising a second adhesive injection step of injecting a second adhesive into the bottom of the groove before the anchor insertion step.
[0014] [4] In the first adhesive injection step in which the first adhesive is injected between the inner wall surface of the groove and both side wall surfaces of the anchor member, the first adhesive is injected between the inner wall surface of the groove formed in the pressure mortar and both side wall surfaces of the anchor member, and between the inner wall surface of the groove formed inside the surface of the concrete skeleton and both side wall surfaces of the anchor member. A repair method for thin floating areas of exterior wall tiles of any of [1] to [3].
[0015] [5] A repair method for a thin layer floating portion of an exterior wall tile according to any one of [1] to [4], wherein the anchor member has an upper edge recess in the center of the upper edge that is recessed toward the lower edge.
[0016] [6] A repair method for a thin layer floating portion of an exterior wall tile according to any one of [1] to [5], which includes a process of attaching a co-floor holding jig to the building, the co-floor holding jig pressing down the tile in the area where the floating has occurred from the outside of the building toward the concrete body, before carrying out at least the first adhesive injection process. Effect of the Invention
[0017] According to this invention, it is possible to provide a repair method for floating areas in wet mosaic sheet construction using 452 tiles, 45 mosaic tiles, etc., in particular a repair method for floating areas that occur between the concrete structure and pressed mortar, i.e., a repair method for thin floating areas of exterior wall tiles. [Brief description of the drawings]
[0018] [Figure 1] This is a cross-sectional view with some parts omitted to explain an example of floating between the concrete structure and the compressed mortar of a building in which tiles are attached to the concrete structure via compressed mortar. [Diagram 2]FIG. 11 is a cross-sectional view with some parts omitted, illustrating an example of a process for forming grooves in tile joints in an area where floating or land has occurred using an electric sander in one embodiment of the present invention. [Diagram 3] FIG. 11 is a cross-sectional view with some parts omitted, illustrating the step of checking the depth from the surface of the tile to the raised land portion, which is performed after the groove forming step in one embodiment of the present invention. [Figure 4] 4A and 4B are diagrams illustrating an example of an anchor insertion step for inserting a thin-plate anchor member into a groove formed in a groove forming step in one embodiment of the present invention, in which (a) is a front view of one embodiment of a thin-plate anchor member, and (b) is a cross-sectional view, with a portion omitted, illustrating an example of the state in which the anchor member shown in FIG. 4A has been inserted into the groove. [Diagram 5] 5 is a partially omitted cross-sectional view taken in a direction perpendicular to FIG. 4(b) for explaining a state in which a thin-plate-shaped anchor member is inserted into a groove formed in a groove forming step. FIG. [Figure 6] 4(a) is a diagram for explaining an example of an anchor insertion process in which a thin-plate-shaped anchor member having a different shape from the thin-plate-shaped anchor member shown in FIG. 4(a) is used to insert the thin-plate-shaped anchor member into a groove formed in a forming process, where (a) is a front view of one embodiment of the thin-plate-shaped anchor member, and (b) is a cross-sectional view with a portion omitted for explaining an example of the state in which the anchor member shown in FIG. 6(a) is inserted into the groove. [Figure 7] 5A and 5B are cross-sectional views, with some parts omitted, illustrating a first adhesive injection step performed in one embodiment of the present invention. [Figure 8] FIG. 4 is a cross-sectional view, with some parts omitted, illustrating a joint filling process performed in one embodiment of the present invention. [Figure 9] 1A and 1B show an embodiment of a common holding jig used in a common holding jig installation step performed in one embodiment of the present invention, where FIG. [Figure 10] This is a front view, with some parts omitted, of a building on which the repair method of the present invention is being carried out for the thin floating portions of exterior wall tiles, showing the state in which a co-floor holding jig has been installed during the co-floor holding jig installation process. [Figure 11]FIG. 4 is a cross-sectional view with some parts omitted, illustrating a second adhesive injection process performed in one embodiment of the present invention. [Figure 12] 4(a) to 4(f) are cross-sectional views with some parts omitted, illustrating an example of a repair method for a thin layer floating portion of an exterior wall tile of the present invention when a second adhesive injection process is performed. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0019] The repair method for the thin layer floating portion of the exterior wall tile in this embodiment is a repair method for the floating portion that occurs between the concrete structure and the compressed mortar of a building in which tiles are attached to the concrete structure via compressed mortar.
[0020] 1 is a cross-sectional view with some parts omitted to explain an example of a building structure in which tiles 3a, 3b, 3c, and 3d are attached to a concrete skeleton 1 via compressed mortar 2, in which floating 4 occurs between the concrete skeleton 1 and compressed mortar 2. Hereinafter, in this specification and drawings, tiles 3a, 3b, 3c, 3d, ... may be collectively referred to as "tile 3."
[0021] In wet mosaic sheet installation using 45 two-piece tiles, 45 mosaic tiles, etc., generally, the concrete structure is subjected to high-pressure cleaning and roughening, then pressure-bonded mortar 2 is applied, tiles 3 are attached on top of that, and the tile joints are filled to form joints 5a, 5b, 5c. Hereinafter, in this specification and drawings, the joints 5a, 5b, 5c may be collectively referred to as "joint 5".
[0022] In a building having such a structure in which tiles 3 are attached to a concrete structure 1 via pressure-bonded mortar 2, a floating part 4 may occur between the concrete structure 1 and the pressure-bonded mortar 2.
[0023] The repair method for the thin layer floating part of the exterior wall tile of this embodiment is a repair method for such floating land. Hereinafter, one embodiment of the present invention will be described with reference to the attached drawings.
[0024] (Process for checking areas where floating land occurs) The above-mentioned tiled exterior wall of the building is subjected to a tapping survey using a test hammer or the like to find out whether there is any floating, and the area and extent of the thin floating part of the exterior wall tile where the repair method of this embodiment is to be applied are confirmed.
[0025] A tapping survey using a test hammer or the like was conducted on the tiled exterior walls of a building to find that floating land had occurred, and the area and extent of the thin floating land in the exterior wall tiles of this embodiment was confirmed by carrying out the repair method thereon.
[0026] For example, the area indicated as "uneven land" in FIG. 10 is the area where uneven land has occurred and where the repair method for the thin-layer uneven land of the exterior wall tile of this embodiment will be carried out.
[0027] (Co-floor holding jig installation process) Taking into consideration circumstances such as the area where floating occurs, during the first adhesive injection process described below, it is possible that the increase in internal pressure caused by the first adhesive being injected and filled into the floating area may cause the pressed mortar 2 that has not peeled off from the surface of the outer wall of the concrete structure around the floating area to peel off, even if the adhesive strength is weak, and new gaps may be formed in that area.
[0028] In such cases, in order to prevent such an incident from occurring, a process is carried out in which a joint float holding jig is attached to the building to hold down tiles 3 in the area where the float has occurred, or in the area surrounding the area where the float has occurred, or in the area where the float has occurred and its surrounding areas, from the outside of the building toward the concrete structure 1.
[0029] FIG. 10 is a front view, with some parts omitted, seen from outside the building, showing the state in which the common float holding jig 30 has been installed in the common float holding jig installation process.
[0030] Taking into consideration the circumstances of the floating area and the like, it was predicted that in the area indicated as the "expected area of co-floating" in Figure 10, as described above, during the first adhesive injection process described below, the first adhesive is injected and filled into the floating area, causing an increase in internal pressure to occur, which may cause the bonded mortar 2 that has not peeled off from the surface of the outer wall of the concrete structure around the floating area to peel off, even if the adhesive strength is weak, and new gaps may form in its place.
[0031] Therefore, a common floating pressing jig (pressing metal fitting 30) shown in FIG. 9 with reference numeral 30 was used and attached to the common floating predicted range.
[0032] In Figures 9 and 10, a joint-floating holding jig (pressing metal 30) consisting of cross-shaped thin metal pieces 30a, 30b is fastened to joint portion 5 with metal screws 31, so that the joint-floating holding jig (pressing metal 30) holds down tiles 3 in the area where floating-land has occurred, or the surrounding area of the area where floating-land has occurred, or the area where floating-land has occurred and its surrounding areas, from the outside of the building toward the concrete structure 1.
[0033] (Groove formation process) Slits are formed in the joints 5 of the tiles 3 in the area where the floating land 4 occurs. In Fig. 10, a total of eight slits, or grooves 6, are formed in the floating land portion.
[0034] The upper end opening 6a of the groove 6 has a predetermined upper end opening length L1 (FIG. 4(b)) extending in the longitudinal direction in which the joint portion 5 extends.
[0035] The groove 6 is formed toward the concrete body 1 with a depth D1 (FIG. 4(b)) such that the depth of the groove 6 reaches into the surface of the concrete body 1.
[0036] Such a groove 6 can be formed, for example, by using an electric sander 20 as shown in Fig. 2. In this way, groove 6 with width W1 (Fig. 3) corresponding to the thickness of blade 21 of electric sander 20 can be formed to a predetermined depth reaching into the surface of concrete structure 1, and in a state of being curved convexly toward concrete structure 1 as shown in Figs. 2, 3, and 4(b). In other words, groove 6 having a predetermined narrow width (W1) can be carved in the horizontal direction perpendicular to the longitudinal direction in which joint portion 5 extends.
[0037] By using an electric sander 20 whose cutting edge 21 is curved in an arc as shown in Figure 2 to carve a groove 6 that will become a slit, it is possible to form a groove 6 that curves convexly from the surface side of the exterior wall of the building toward the concrete structure 1, as shown in Figures 2 and 4(b).
[0038] In addition, in Figure 10, the eight grooves 6 are formed in the longitudinal direction in which the joint portions 5 extend, which is the up-and-down direction in Figure 10, but the grooves 6 may also be formed in the longitudinal direction in which the joint portions 5 extend, which is the left-right direction in Figure 10.
[0039] As long as it is formed in the longitudinal direction of the joint portion 5 of the tile 3 in the area where the floating land 4 occurs, it may be a groove extending in the vertical direction in Figure 10, or a groove extending in the vertical direction in Figure 10.
[0040] (Floating land depth confirmation process) After the groove forming step, a floating land depth confirmation step is carried out to confirm the depth from the outer surface of the tile 3 to the floating land portion 4.
[0041] In the embodiment shown in Fig. 3, the measurement is performed using a graduated floating land depth measuring instrument 40. The floating land depth measuring instrument 40 is inserted tip-first into the groove 6 as shown in Fig. 3, and the floating land portion is confirmed with the tip of the floating land depth measuring instrument 40. If the groove 6 formed in the groove forming step has an incision depth D1 that is sufficient for the depth from the outer surface of the tile 3 to the floating land portion 4, the electric sander 20 or the like is used again to form the groove 6 having an incision depth D1 sufficient for the depth from the outer surface of the tile 3 to the floating land portion 4.
[0042] By carrying out the floating land depth confirmation process, a groove 6 having a sufficient engraving depth D1 is formed relative to the depth from the outer surface of the tile 3 to the floating land portion 4, which is advantageous in achieving strong fixation between the concrete structure 1 and the floating mortar 2 by adhering them via an adhesive 8 and an anchor member 7, as described below.
[0043] (Anchor insertion process) As shown in FIGS. 4(a), (b) and 5, a thin plate-shaped anchor member 7 is inserted into the groove 6 formed in the groove forming step.
[0044] The upper end edge 7a of the anchor member 7 has an upper end edge length L2 in the longitudinal direction of the anchor member 7. The upper end edge length L2 of the upper end edge 7a corresponds to the upper end opening length L1 of the groove 6 in the longitudinal direction of the joint portion 5.
[0045] The vertical length D2 of the anchor member 7 from the upper end side 7a to the lower end side 7b opposite to the upper end side 7a corresponds to the engraved depth D1 of the groove 6.
[0046] The thickness W2 of the anchor member 7 corresponds to the width W1 of the groove 6.
[0047] The upper end side length L2 corresponding to the upper end opening length L1 of the groove 6 is approximately equal to the upper end opening length L1, and since the anchor member 7 is inserted into the groove 6, it is slightly smaller than the upper end opening length L1.
[0048] The vertical length D2 from the upper end edge 7a to the lower end edge 7b, which corresponds to the engraving depth D1 of the groove 6, is approximately equal to the engraving depth D1, and since the anchor member 7 is inserted into the groove 6, it is slightly smaller than the engraving depth D1.
[0049] The wall thickness W2 of the anchor member 7 corresponding to the width W1 of the groove 6 is approximately equal to the width W1 of the groove 6, and since the anchor member 7 is inserted into the groove 6, it is slightly smaller than the width W1.
[0050] In the above-described embodiment, the shape of the anchor member 7 viewed from the front side is such that the groove 6 is convex from the exterior wall surface side of the building toward the concrete body 1. Accordingly, as shown in FIG. 4(a), the upper end edge 7a has the longest (largest) upper end edge length L2, and the longitudinal length gradually decreases from the upper end edge 7a to the lower end edge 7b.
[0051] In the embodiment shown in Fig. 4(a), the anchor member 7 has a truncated cone shape as viewed from the front side, with the bottom edge 7b being parallel to the top edge 7a. In correspondence with the shape of the groove 6 that is curved convexly from the exterior wall surface side of the building toward the concrete skeleton 1, the bottom edge 7b of the anchor member 7 as viewed from the front side can also be curved convexly in an arc downward in Fig. 4(a).
[0052] Figures 6(a) and (b) explain the case of using an anchor member 17 having a different shape from the anchor member 7 shown in Figures 4(a) and (b). Similar to anchor member 7, anchor member 17 has a truncated cone shape when viewed from the front side, with lower end edge 17b being parallel to upper end edge 17a, but has a more gentle convex bay shape than anchor member 7.
[0053] As described above, a thin-plate-like anchor member 7 having an upper edge 7a with an upper edge length L2 corresponding to the upper opening length L1 of the groove 6, a vertical length D2 from the upper edge 7a to the lower edge 7b opposite the upper edge 7a with a size corresponding to the groove 6 carving depth D1, and a wall thickness W2 corresponding to the width W1 of the groove 6 is inserted into the groove 6 which has a narrow width W1 and is curved from the exterior wall surface side of the building toward the concrete skeleton 1. The floating land 4 occurring between the concrete skeleton 1 and the pressed mortar 2 faces the side wall surfaces 7d, 7e of the anchor member 7 in a wide area (long area) in the longitudinal direction of the joint portion 5.
[0054] After the thin-plate-shaped anchor member 7 is loaded into the groove 6, in the first adhesive injection process described below, the first adhesive is injected between the inner wall surfaces 6d, 6e of the groove 6 and both side wall surfaces 7d, 7e of the anchor member 7, and into the floating land 4 between the concrete body 1 and the compressed mortar 2. As described above, the floating land 4 generated between the concrete body 1 and the compressed mortar 2 faces the side wall surfaces 7d, 7e of the anchor member 7 over a wide area (long area) in the longitudinal direction of the joint portion 5. This makes it easy to inject and fill the first adhesive, and the injected first adhesive can spread over a wide area within the floating land 4.
[0055] This allows the first adhesive to bond the concrete body 1 and the floating mortar 2 together, thereby firmly fixing the mortar 2.
[0056] In addition, the first adhesive (epoxy resin, etc.) filled in the float 4 can increase the strength of the thin plate-shaped anchor 7 against a load applied in the horizontal direction (left and right direction in FIG. 5).
[0057] Furthermore, the first adhesive (epoxy resin, etc.) injected while the thin-plate anchor member 7 is inserted in the groove 6 spreads over the surface of the concrete structure 1 on the exterior wall surface side, thereby suppressing the deepening of concrete neutralization that progresses from the outer surface side of the exterior wall of the concrete structure 1 where floating 4 has occurred toward the inside of the concrete structure 1, which is expected to lead to the preservation of the concrete structure 1.
[0058] As described above, the anchor member 7 can be formed in various shapes as long as the upper edge 7a has an upper edge length L2 corresponding to the upper opening length L1 of the groove 6, the vertical length D2 from the upper edge 7a to the lower edge 7b opposite the upper edge 7a has a size corresponding to the engraved depth D1 of the groove 6, and the anchor member 7 is a thin plate having a thickness W2 corresponding to the horizontal width W1 of the groove 6.
[0059] For example, a thin metal plate such as stainless steel can be used. From the viewpoint of improving adhesion to the adhesive, a thin metal plate such as stainless steel that is bent in a wavy or uneven shape, a thin metal plate such as stainless steel that has a plurality of minute through holes drilled therein or has a plurality of minute unevenness formed on the surfaces of both side walls 7d, 7e, or a thin plate body formed from a mesh material such as stainless steel mesh can be used.
[0060] (First adhesive injection process) After inserting a thin plate-shaped anchor member 7 into the groove 6, an adhesive 8 such as an epoxy resin is injected as shown in FIGS. 7(a) and 7(b).
[0061] 7(a) and (b) are cross-sectional views with some parts omitted, illustrating the first adhesive injection step.
[0062] The tip of injection nozzle 51 of injector 50 is inserted into groove 6 from upper end opening 6a of groove 6, and adhesive 8 is injected into groove 6 (FIGS. 7(a) and 7(b)).
[0063] As a result, adhesive 8 is injected between the inner wall surfaces 6d, 6e of the groove 6 and both side walls 7d, 7e of the anchor member 7, and into the floating land 4 between the concrete body 1 and the pressure-bonded mortar 2.
[0064] As described above, a thin-plate-shaped anchor member 7 having an upper edge 7a with an upper edge length L2 corresponding to the upper edge opening length L1 of the groove 6, a vertical length D2 from the upper edge 7a to the lower edge 7b opposite the upper edge 7a with a size corresponding to the engraved depth D1 of the groove 6, and a thickness W2 corresponding to the horizontal width W1 of the groove 6, is inserted into the groove 6, which has a narrow horizontal width W1, an upper opening 6a extending a predetermined upper opening length L1 in the longitudinal direction in which the joint portion 5 extends, and a predetermined engraved depth D1 reaching into the surface of the concrete structure 1, and an upper edge 7a having an upper edge length L2 corresponding to the upper opening length L1 of the groove 6, and a vertical length D2 from the upper edge 7a to the lower edge 7b opposite the upper edge 7a with a size corresponding to the engraved depth D1 of the groove 6, and an adhesive 8 is injected into the thin-plate-shaped anchor member 7.
[0065] Therefore, adhesive 8 is injected between the inner wall surfaces 2d, 2e of the groove 6 formed in the pressed mortar 2 and both side wall surfaces 7d, 7e at the upper end of the anchor member 7, and between the inner wall surfaces 6d, 6e of the groove 6 formed inside the surface of the concrete body 1 and both side wall surfaces 7d, 7e of the anchor member 7.
[0066] Then, adhesion and hardening occurs between the two. As a result, the concrete structure 1 and the floating mortar 2 are adhered to each other via the adhesive 8 and the anchor member 7, and the concrete structure 1 and the floating mortar 2 are firmly fixed to each other.
[0067] As shown in Figures 4(a), (b) and 6, if the anchor member 7 has an upper edge recess 7c, 17c in the center of the upper edge 7a which is recessed toward the lower edge 7b, this is advantageous because the tip of the injection nozzle 51 of the injector 50 can be inserted into the upper edge recess 7c to inject adhesive, as shown in Figure 7(b).
[0068] (Joint filling process) After the adhesive 8 injected in the first adhesive injection step has hardened, the joints 5 are filled with a joint material as shown in FIG.
[0069] An anchor member 7 is inserted into a groove 6 formed in a joint portion 5, and an adhesive such as epoxy resin is injected therein and hardened, after which the joint is filled, making it easy to finish the tile joint.
[0070] Although an embodiment of the present invention has been described above with reference to the attached drawings, the present invention is not limited to the above-described embodiment and can be modified in various ways within the technical scope understood from the description of the claims.
[0071] For example, in cases where floating has occurred as confirmed in the floating area confirmation process, but the area in which the repair method for the thin floating portion of the exterior wall tile of this embodiment is to be performed is not very large, the common floating holding jig attachment process can be omitted.
[0072] Furthermore, before carrying out the above-mentioned anchor inserting step shown in Figures 4 to 6, as shown in Figures 11 and 12(b), a second adhesive injection step can be carried out in which a second adhesive is injected into the bottom of groove 6 (i.e., the inner side of concrete body 1 of groove 6 which is a slit, and the lower side in Figure 11). This is a step in which a second adhesive made of epoxy resin or the like is filled into the bottom of groove 6 cut and formed in the groove forming step (Figure 2).
[0073] Figures 12(a)-(f) are cross-sectional views with some parts omitted to explain the repair method of the present invention in which a second adhesive injection step (Figures 11, 12(b)) is carried out before the anchor insertion step (Figure 12(c)). Parts that are common to the embodiment explained using Figures 1-10 are given the same reference numerals and explanations are omitted.
[0074] Figure 12(a) corresponds to the groove formation process described in Figure 2, Figure 12(c) corresponds to the anchor insertion process described in Figures 4 and 6, Figures 12(d) and 12(e) correspond to the first adhesive injection process described in Figures 7(a) and (b), respectively, and Figure 12(f) corresponds to the joint filling process described in Figure 8.
[0075] As the second adhesive, an epoxy resin such as a high viscosity epoxy resin can be used, as in the case of the first adhesive described above.
[0076] Before carrying out the anchor loading step (FIG. 12(c)), the above-mentioned second adhesive injection step is carried out to fill the tip side (the lower side in FIGS. 4(b) and 6(b)) of the anchor member 7 to be loaded into the groove 6 in the anchor loading step (FIG. 12(c)) with the second adhesive (e.g., high-viscosity epoxy resin) as shown in FIGS. 11 and 12(b). As a result, when the next step of the anchor loading step is carried out as shown in FIG. 12(c), the tip side of the anchor member 7 is fixed by the second adhesive (e.g., high-viscosity epoxy resin).
[0077] In the above-mentioned first adhesive injection process (FIGS. 7(a) and (b)), the first adhesive (such as an epoxy resin) is filled into the narrow gap caused by peeling, but there is a possibility that the gap will widen due to the pressure applied during filling.
[0078] Therefore, if the above-mentioned second adhesive injection step (FIGS. 11 and 12(b)) is carried out in advance, the tip side of the anchor member 7 is fixed with the second adhesive (e.g., high-viscosity epoxy resin), which is advantageous in preventing the gap from widening.
[0079] Since the second adhesive injection process is performed for the purpose described above, it is sufficient to perform it before the anchor insertion process is carried out. Although not shown in Figures 12(a) to (f), if the floating land depth confirmation process (Figure 3) is performed after the groove formation process (Figure 2), the second adhesive injection process (Figures 11, 12(b)) should be performed after the floating land depth confirmation process (Figure 3) and before the anchor insertion process (Figure 12(c)) is carried out.
Claims
1. A repair method for a floating land occurring between a concrete structure and a compressed mortar of a building having a structure in which tiles are attached to the concrete structure via compressed mortar, comprising: a groove forming step of forming a groove in the joint of the tile in the region where the floating occurs, the groove having a predetermined upper end opening length extending in the longitudinal direction of the joint, a predetermined engraved depth extending to a depth reaching the inside of the surface of the concrete structure, and a predetermined narrow width in a lateral direction perpendicular to the longitudinal direction; an anchor insertion process for inserting a thin-plate-shaped anchor member into the groove, the thin-plate-shaped anchor member having an upper end edge having an upper end edge length corresponding to the upper end opening length of the groove, a vertical length from the upper end edge to a lower end edge opposite to the upper end edge side having a size corresponding to the engraved depth of the groove, and a thickness corresponding to the lateral width of the groove but smaller than the lateral width; a first adhesive injection step for injecting a first adhesive between the inner wall surface of the groove and both side wall surfaces of the anchor member and into the floating land between the concrete body and the pressure-bonded mortar, the first adhesive being injected between the inner wall surface of the groove formed in the pressure-bonded mortar and both side wall surfaces of the anchor member and between the inner wall surface of the groove formed inside the surface of the concrete body and both side wall surfaces of the anchor member; a joint filling step of filling the joints after the adhesive has hardened; A repair method for thin floating parts of exterior wall tiles.
2. After the groove forming step and before the anchor inserting step, 2. The repair method for thin layer raised land portions of exterior wall tiles according to claim 1, further comprising a raised land depth confirmation step for confirming the depth from the surface of the tile to the raised land portion.
3. 3. A repair method for a thin layer floating portion of an exterior wall tile according to claim 1, further comprising a second adhesive injection step of injecting a second adhesive into the bottom of the groove before the anchor insertion step.
4. 4. A repair method for a thin layer floating portion of an exterior wall tile as described in any one of claims 1 to 3, wherein the anchor member has an upper edge recess in the center of the upper edge which is recessed toward the lower edge.
5. A repair method for a thin layer floating portion of an exterior wall tile described in any one of claims 1 to 4, comprising a co-floating holding jig attachment process of attaching to the building a co-floating holding jig that holds down the tile in the area where the floating has occurred from the outside of the building toward the concrete body side, before performing at least the first adhesive injection process.
Citation Information
Patent Citations
Exterior wall repairing method and anchor pin
JP1999036610A
Tile repair method and anchor plate therefor
JP1999036613A
Connecting material for preventing tile exfoliation
JP2007051538A
Fall prevention structure and fall prevention method of existing finished wall
JP2012117227A
Adhesive injection device and pinning method
JP2014070451A