Wind turbine assembly method and assembly system
The method and system for assembling wind power generators using a support structure, lifting device, and gate-shaped frame address the challenge of large cranes and ground area requirements, enhancing workability and efficiency by directly positioning components on the tower, thus reducing the need for extensive construction space and crane size.
Patent Information
- Application Number
- JP2022208058
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2022-12-26
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2042-12-26
AI Technical Summary
Conventional wind power generator assembly methods require larger cranes and increased ground area as generators become larger, leading to deteriorated workability during strong winds.
A method and system using a support structure, lifting device, and a gate-shaped frame to individually lift and horizontally move components of the wind power generator, such as the nacelle, hub, and blades, directly to their connection points on the tower, reducing the need for large cranes and minimizing ground area requirements.
This approach reduces the required ground area for construction and improves workability by allowing assembly with smaller cranes, even under adverse conditions, while maintaining efficient component positioning and connection accuracy.
Smart Images

Figure 0007593555000001 
Figure 0007593555000002 
Figure 0007593555000003
Abstract
Description
[Technical field]
[0001] The present disclosure relates to a method and system for assembling a wind turbine generator. [Background technology]
[0002] 2. Description of the Related Art In recent years, wind power generation has been attracting attention as one of the power generation businesses that utilize renewable energy, and there is a need to enlarge wind power generators in order to improve power generation efficiency.
[0003] Traditionally, cranes have been used to construct wind turbines, and when assembling the wind turbine tower and installing the nacelle, hub, etc. at the top of the tower, each part is suspended by the crane and lifted to the installation site (for example, Patent Document 1). [Prior art documents] [Patent documents]
[0004] [Patent Document 1] JP 2017-145714 A Summary of the Invention [Problem to be solved by the invention]
[0005] In the conventional assembly method of wind power generators, as the wind power generator becomes larger, the crane used for construction must also become larger. As the crane becomes larger, the area of the installation site for the crane also increases, which causes a problem of an increase in the ground area required for construction. In addition, as the wind power generator and the crane become larger, there is also a problem of deterioration of construction in strong winds.
[0006] An object of the present disclosure is to provide a method and system for assembling a wind turbine generator that can reduce the ground area required for constructing the wind turbine generator and improve ease of construction. [Means for solving the problem]
[0007] According to one aspect of an embodiment of the present invention, there is provided a method for assembling a wind power generator using an assembly system including: a support pillar installed around a tower of the wind power generator; a lifting device installed on the support pillar and lifting and lowering along the support pillar; and a portal frame installed on the lifting device and moving horizontally toward and away from the tower, the method including the steps of: a nacelle installation step of suspending a nacelle of the wind power generator from the portal frame and lifting it to the tip of the tower by the lifting device, horizontally moving the portal frame to move the nacelle to just above the tip, and connecting the nacelle to the tower; and a hub installation step of suspending a hub of the wind power generator from the portal frame and lifting it to the tip of the tower by the lifting device, horizontally moving the portal frame to move the hub to a position facing the nacelle, and connecting the hub to the nacelle. a nacelle rotating step of rotating the nacelle around a central axis of the tower so that a connection portion of the hub with the plurality of blades of the wind turbine generator faces a base end portion of the blades; and a blade installation step of suspending one of the multiple blades of the wind power generator on the portal frame and lifting it to the tip of the tower using the lifting device, moving the portal frame horizontally to move the one blade to a position opposite the hub, connecting the one blade to the hub, and similarly connecting the remaining multiple blades one by one to the hub using the lifting device and the portal frame.
[0008] Similarly, an assembly system for a wind power generator according to an aspect of an embodiment of the present invention includes: a support pillar installed around a tower of a wind power generator; a lifting device installed on the support pillar and moving up and down along the support pillar to lift a nacelle, a hub, and each of a plurality of blades of the wind power generator individually to a tip of the tower; and a portal frame installed on the lifting device and movable in a horizontal direction toward and away from the tower, capable of suspending the nacelle, the hub, and each of the plurality of blades individually, and horizontally moving the nacelle, the hub, and each of the plurality of blades lifted by the lifting device individually to a connection portion with another component of the wind power generator. After the nacelle is connected to the tower, the hub is connected to the nacelle, and the nacelle is rotated around the central axis of the tower so that a connection portion of the hub with the plurality of blades is positioned opposite the base end portion of the blade, one of the plurality of blades is horizontally moved to a position opposite the hub to connect the one blade to the hub, and the remaining plurality of blades are similarly connected one by one to the hub using the lifting device and the portal frame. . Effect of the Invention
[0009] According to the present disclosure, it is possible to provide a method and system for assembling a wind turbine generator that can reduce the ground area required for constructing the wind turbine generator and improve ease of construction. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a diagram showing a schematic configuration of a wind power generator according to an embodiment; [Diagram 2] FIG. 1 is a diagram showing a schematic configuration of an assembly system for a wind power generator according to an embodiment; [Diagram 3] Side view of the lift-up device [Figure 4] Plan view of the lift-up device [Diagram 5] Front view of the portal frame [Figure 6] Side view of the portal frame [Figure 7] Plan view of the portal frame [Figure 8] A front view showing the state in which the blade suspension beam is installed on the portal frame [Figure 9] A side view showing the state in which the blade suspension beam is installed on the portal frame [Figure 10] Plan view showing the state where the blade suspension beam is installed on the portal frame [Figure 11] Side view showing the first stage of assembly of the wind turbine [Figure 12] Side view showing the second stage of the wind turbine assembly procedure [Figure 13] Side view showing the third stage of the wind turbine assembly process [Figure 14] Side view showing the fourth stage of the wind turbine assembly procedure [Figure 15] Side view showing the fifth stage of the wind turbine assembly procedure [Figure 16] Side view showing the sixth step in the wind turbine assembly process [Figure 17] Side view showing the seventh stage of the wind turbine assembly procedure [Figure 18] Plan view of the seventh stage shown in Fig. 17 [Figure 19] Side view showing the eighth stage of the wind turbine assembly procedure [Figure 20] Plan view of the eighth stage shown in FIG. [Figure 21] Side view showing the ninth stage of the wind turbine assembly procedure [Figure 22] Plan view of the ninth stage shown in FIG. [Diagram 23] Side view showing the 10th step in the wind turbine assembly process [Figure 24] Side view showing step 11 of the wind turbine assembly procedure [Diagram 25] Plan view of the 11th stage shown in FIG. [Figure 26] Side view showing step 12 of the wind turbine assembly procedure [Figure 27] Side view showing step 13 of the wind turbine assembly procedure DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] Hereinafter, an embodiment will be described with reference to the accompanying drawings. In order to facilitate understanding of the description, the same components in each drawing are denoted by the same reference numerals as much as possible, and duplicated description will be omitted.
[0012] In the following description, the X, Y, and Z directions are perpendicular to each other. The X and Y directions are horizontal, and the Z direction is vertical. The X direction is the movement direction of the portal frame 30, with the X positive side being the approach direction to the support 10 and the X negative side being the separation direction. The Y direction is the opposing direction of the pair of climbing beams 23, 24 of the lift-up device 20, with the Y positive side being the side of one climbing beam 23 and the Y negative side being the side of the other climbing beam 24. For convenience of description, the Z positive side may be referred to as the upper side and the Z negative side may be referred to as the lower side in the following description.
[0013] <Outline of wind turbine generator configuration> Fig. 1 is a diagram showing a schematic configuration of a wind power generator 100 according to an embodiment. As shown in Fig. 1, the wind power generator 100 includes a tower 101, a nacelle 102, a hub 103, and a plurality of blades 104A to 104C.
[0014] The tower 101 is installed on a foundation and stands upright. The tower 101 is, for example, cylindrical. The tower 101 is divided into a plurality of members along the Z direction in consideration of workability, and is assembled from the bottom up at the construction site. In the example of FIG. 1, the tower 101 is composed of five members, namely, a bottom tower 101A, a second tower 101B, a third tower 101C, a fourth tower 101D, and a top tower 101E, from the bottom up, but the number of members is not limited to this. In FIG. 1, a dashed line is drawn horizontally above the lower end of the bottom tower 101A, and this dashed line represents the ground surface at the construction site. The same applies to the drawings from FIG. 11 onwards.
[0015] The nacelle 102 is attached to the upper end of the tower 101. The nacelle 102 is installed to be rotatable around the central axis C1 of the tower, for example.
[0016] The hub 103 is attached to one end (the end on the X negative side in FIG. 1) of the nacelle 102. The hub 103 is installed to be rotatable with respect to the nacelle 102 about a rotation axis C2 along the longitudinal direction of the nacelle 102.
[0017] The blades 104A to 104C are elongated members extending radially outward from the rotation axis C2 of the hub 103, and their respective base ends are connected to the three connection parts 103A to 103C of the hub 103. The blades 104A to 104C are preferably arranged at approximately equal intervals in the circumferential direction around the rotation axis C2. In the example of FIG. 1, the blade 104A has three blades, a first blade 104A, a second blade 104B, and a third blade 104C, and the blades 104A to 104C are arranged at intervals of approximately 120 degrees around the rotation axis C2. Similarly, the connection parts 103A, 103B, and 103C of the hub 103 to which the blades 104A, 104B, and 104C are connected are also arranged at intervals of approximately 120 degrees around the rotation axis C2.
[0018] In the wind power generator 100, the hub 103 and the blades 104A to 104C rotate together as a rotor, and the nacelle 102 receives the rotation of the rotor to generate power.
[0019] <Outline of wind power generator assembly system 1> The configuration of a wind power generator assembly system 1 according to this embodiment will be described with reference to Figures 2 to 10. Figure 2 is a diagram showing a schematic configuration of the wind power generator assembly system 1 according to this embodiment. The wind power generator assembly system 1 shown in Figure 2 (hereinafter may also be simply referred to as "assembly system 1") is a system for assembling the wind power generator 100 shown in Figure 1.
[0020] As shown in FIG. 2, the assembly system 1 includes a support 10, a lift-up device 20 (lifting device), and a gate-shaped frame 30.
[0021] The support 10 is installed around the tower 101 of the wind power generator 100. The support 10 has four pillars 11, 12, 13, and 14 erected around the tower 101, and a plurality of beams 15 connecting adjacent pillars. The support 10 is installed around the central axis C1 of the tower 101 in a quadrilateral shape with the pillars 11, 12, 13, and 14 forming the corners and the beams 15 forming the sides. As shown in Fig. 2, for example, the beams 15 each extend horizontally, and a plurality of beams 15 are arranged at approximately equal intervals along the Z direction.
[0022] The lift-up device 20 is installed on the support 10 and moves up and down along the support 10 in the up and down direction indicated by the arrow A in Fig. 2. The lift-up device 20 lifts the nacelle 102, the hub 103, and each of the blades (the first blade 104A, the second blade 104B, and the third blade 104C) of the wind power generator 100 individually to the tip of the tower 101.
[0023] The lift-up device 20 has a pair of climbing beams 23, 24 and a pair of measuring devices 21, 22. The pair of climbing beams 23, 24 are arranged extending horizontally along a pair of opposite sides of the rectangular shape of the support 10, and the portal frame 30 is movably installed thereon. The pair of measuring devices 21, 22 are connected to two of the four pillars of the support 10 (the two pillars 11, 12 arranged on the X-negative side in the example of FIG. 2), and are devices that can rise and fall along the two pillars 11, 12. The measuring devices 21, 22 are, for example, hydraulic cylinders, and jack up the climbing beams 23, 24 connected to the upper parts thereof.
[0024] The portal frame 30 is mounted on the lift-up device 20 and moves horizontally toward and away from the tower 101 as indicated by the arrow B in Fig. 2. The portal frame 30 can individually suspend the nacelle 102, hub 103, first blade 104A, second blade 104B, and third blade 104C of the wind power generator 100, and horizontally moves the nacelle 102, hub 103, first blade 104A, second blade 104B, and third blade 104C lifted by the lift-up device 20 horizontally to the connection parts with other components of the wind power generator 100, respectively.
[0025] The portal frame 30 has a pair of pillars 33, 34 extending upward from the pair of climbing beams 23, 24 of the lift-up device 20, respectively, and a beam 35 connecting the upper ends of the pair of pillars 33, 34. In addition, a suspension device 38 is provided in the center of the beam 35 for suspending each component of the wind power generator 100 from the portal frame 30. The suspension device 38 can suspend the component via a wire 39 (see Figures 5, 8, etc.) and hold it at a predetermined height relative to the portal frame 30.
[0026] Fig. 3 is a side view of the lift-up device 20. Fig. 4 is a plan view of the lift-up device 20. As shown in Figs. 3 and 4, the climbing beams 23 and 24 of the lift-up device 20 are composed of two members, first beams 23A and 24A and second beams 23B and 24B, respectively.
[0027] The base ends (X-positive direction sides) of the first beams 23A and 24A are connected to the measuring devices 21 and 22, respectively, and the tip ends (X-negative direction sides) extend away from the support 10. The base ends of the first beams 23A and 24A are fixed to the upper ends of the measuring devices 21 and 22. As shown in FIG. 3, bundles 26 are provided at the lower ends of the tip ends of the first beams 23A and 24A, respectively, to connect with the lower parts of the measuring devices 21 and 22.
[0028] The second beams 23B, 24B are selectively connected to the base end side or the tip end side of the first beams 23A, 24A, and are connected so as to extend in the same direction as the first beams 23A, 24A. When the nacelle 102 and the hub 103 are attached, the second beams 23B, 24B are connected to the base end side of the first beams 23A, 24A. This state is shown by solid lines in Figures 3 and 4. When the second beams 23B, 24B are connected to the base end side of the first beams 23A, 24A, as shown in Figure 3, bundles 26 are provided at the lower parts of the tip sides (X positive direction sides) of the second beams 23B, 24B, which are connected to the lower parts of the measuring devices 21, 22, respectively.
[0029] In particular, in this embodiment, when attaching the blades 104A to 104C, the second beams 23B and 24B are detached from the base ends of the first beams 23A and 24A and reconnected to the tip ends of the first beams 23A and 24A, as shown by dotted lines in Fig. 4. This causes the climbing beams 23 and 24 to extend in a direction away from the support 10 (X negative direction).
[0030] The pair of climbing beams 23, 24 are connected by a tie beam 25 extending in the Y direction. For example, as shown in Fig. 4, one tie beam 25 can be installed at each of the base end and tip end of the first beams 23A, 24A, and one tie beam 25 can be installed at each of the tip end of the second beams 23B, 24B. Note that the arrangement and number of the tie beams 25 are not limited to the example shown in Fig. 4.
[0031] As shown in FIG. 4, a plurality of support mechanisms 16 are provided between each of the pillars 11-14 of the support 10 of the assembly system 1 and the tower 101 of the wind power generator 100. The tower 101 is supported on the support 10 via each of the support mechanisms 16. The support mechanisms 16 are configured as a set of four, for example, installed at the same height position of each of the pillars 11-14, and each set can support the tower 101 from four directions at the same height of the support 10. Each set of the support mechanisms 16 is provided on the support 10, spaced apart in the vertical direction. The support mechanisms 16 are, for example, hydraulic actuators that can expand and contract in one direction connecting each of the pillars 11-14 and the center C1 of the tower 101, and each set can support the tower 101 by pressing the outer circumferential surface of the tower 101 from each of the pillars 11-14.
[0032] Fig. 5 is a front view of the portal frame 30. Fig. 6 is a side view of the portal frame 30. Fig. 7 is a plan view of the portal frame 30.
[0033] 5 to 7, the portal frame 30 has a pair of movable bases 31, 32. The movable bases 31, 32 each have a plurality of wheels 31A, 32A, and are installed so as to be movable on the climbing beams 23, 24, respectively, by the wheels 31A, 32A. The wheels 31A, 32A can be rotated by being provided with a driving force by a driving source such as a motor installed in the movable bases 31, 32.
[0034] In order to stabilize the moving direction of the wheels 31A, 32A of the portal frame 30 in the X direction, a guide member such as a rail for guiding the wheels 31A, 32A may be installed on the upper surfaces of the climbing beams 23, 24. Furthermore, the moving bases 31, 32 need only be able to move at least the portal frame 30 in the X direction, and elements other than the wheels 31A, 32A, such as bearings, may be used.
[0035] A pair of pillars 33, 34 of the portal frame 30 are installed so as to extend upward from the movable bases 31, 32, respectively.
[0036] A suspension device 38 is installed at approximately the center of the beam 35. The suspension device 38 can suspend components such as the blocks 101A to 101E of the tower 101, the nacelle 102, and the hub 103 via wires 39 or the like. The suspension device 38 may be configured to have a function of adjusting the length of the wires 39 interposed between the beam 35 and each component, for example, by using a winch device or the like. This allows the Z-direction position of each component of the wind power generator 100 suspended from the portal frame 30 to be adjusted as desired, thereby improving positioning accuracy when connecting with other components and improving work efficiency.
[0037] The beam 35 connecting the pair of pillars 33, 34 may have a slide mechanism that can move the position at which each component of the wind power generator 100 is suspended along the extension direction (Y direction) of the beam 35. By providing such a slide mechanism, the position in the Y direction of each component of the wind power generator 100 suspended from the portal frame 30 can be adjusted as desired, improving the positioning accuracy when connecting with other components and improving work efficiency. Furthermore, by using this slide mechanism in combination with the Z-direction wire adjustment mechanism of the suspension device 38, the position in two directions, the Z direction and the Y direction, of each component of the wind power generator 100 suspended from the portal frame 30 can be adjusted as desired, further improving the positioning accuracy when connecting with other components and further improving work efficiency.
[0038] As shown in Figs. 5 and 7, the beam 35 of the portal frame 30 has a first beam 36 and a second beam 37 that can be connected and separated at the middle part in the extending direction of the beam 35. The first beam 36 is rotatably connected to one of the pair of columns, 33, and the second beam 37 is rotatably connected to the other column 34. In the example of Figs. 5 to 7, the first beam 36 is formed longer than the second beam 37, and is configured so that the central part of the beam 35 becomes the tip of the first beam 36 when both are connected in a straight line. Therefore, the suspension device 38 installed in the center of the beam 35 is installed at the tip of the first beam 36.
[0039] Also, as shown by arrow C in Fig. 7, first beam 36 is installed so as to rotate in the X positive direction. Also, as shown by arrow D in Fig. 7, second beam 37 is installed so as to rotate in the X negative direction. The reason for setting the rotation direction of first beam 36 and second beam 37 in this manner is that in this embodiment, the base ends of blades 104A-104C are inclined in the Y negative direction when installing blades 104A-104C (see Fig. 22, etc.), and this is a direction suitable for avoiding interference with blades 104A-104C after installation.
[0040] As shown in Figs. 2, 5 and 8, the portal frame 30 has a fall prevention device 53 that connects the pair of moving bases 31 and 32. The fall prevention device 53 is, for example, a beam-shaped member extending in a substantially horizontal direction. By providing the fall prevention device 53 on the portal frame 30 in this manner, when the first beam 36 and the second beam 37 of the beam 35 are opened and the pair of columns 33 and 34 are separated, the pair of columns 33 and 34 can be prevented from falling. The fall prevention device 53 may be disposed below the lower ends of the elements of the wind power generator 100 suspended by the portal frame 30, and may be configured to connect the pair of columns 33 and 34. The fall prevention device 53 may be permanently installed, or may be configured to be installed sequentially before the operation of opening the first beam 36 and the second beam 37 of the beam 35 is performed.
[0041] Fig. 8 is a front view showing the state in which the blade hoist beam 40 is installed on the portal frame 30. Fig. 9 is a side view showing the state in which the blade hoist beam 40 is installed on the portal frame 30. Fig. 10 is a plan view showing the state in which the blade hoist beam 40 is installed on the portal frame 30.
[0042] As shown in Figures 8 to 10, the assembly system 1 further includes a blade hoisting beam 40. The blade hoisting beam 40 is an element that is suspended from the portal frame 30 and that suspends and supports the blades 104A to 104C. In Figures 8 to 10, the schematic outlines of the blades 104A to 104C suspended by the blade hoisting beam 40 are shown by dotted lines.
[0043] The blade suspension beam 40 supports the blades 104A-104C so that its longitudinal direction coincides with the extension direction of the blades 104A-104C, and supports the blades 104A-104C at two locations 41A and 41B at both ends in the longitudinal direction. Of the two support locations, the support portion on one end 41A side has a rotation angle adjustment device 51 for adjusting the rotation angle θ of the blades 104A-104C about the axis C3, and the support portion on the other end 41B side has an inclination angle adjustment device 52 for adjusting the inclination angle α of the blades 104A-104C with respect to the horizontal direction.
[0044] The blade suspension beam 40 has a main frame 41 and a tip frame 42. The main frame 41 extends in the longitudinal direction of the blades 104A to 104C. The tip frame 42 is a relatively short frame that is perpendicular to the main frame 41, and is provided at one end 41A of the main frame 41.
[0045] Two hoisting hooks 43 are provided at a predetermined interval along the extension direction on the upper surface of the main frame 41. A wire 39 connected to the hoisting device 38 of the portal frame 30 is hooked onto these two hoisting hooks 43, whereby the blade hoisting beam 40 is suspended from the portal frame 30.
[0046] A pair of capstans 44 are built into both ends of the tip frame 42. The capstans 44 are installed so that their rotation axes are in the same direction as the extension direction of the main frame 41. As shown in FIG. 8, a circular wire 47 is wound around the pair of capstans 44. This wire 47 is also wound around the lower part of the blades 104A to 104C to be suspended. Furthermore, a driving source such as a motor 45 is connected to at least one of the pair of capstans 44, and the capstan 44 is driven to rotate as shown by the arrow E in FIG. 8 by the driving force transmitted from the motor 45, whereby the position of the wire 47 also moves in the circular direction relative to the capstan 44 and the blades 104A to 104C. As a result, the suspended blades 104A to 104C can be rotated around the axis C3 to adjust the rotation angle θ.
[0047] That is, in this embodiment, the pair of capstans 44, the motor 45, and the wire 47 constitute the rotation angle adjustment device 51, and realize the function of the rotation angle adjustment device 51.
[0048] As shown in Figures 9 and 10, a winch 46 is installed on the other end 41B of the main frame 41. The winch 46 has a drum 46A and a motor 46B. The upper end of a pulley wire 48 is wound around the drum 46A. A looped wire 49 is connected to the lower pulley of the pulley wire 48, and this wire 49 is hung below the blades 104A to 104C.
[0049] When the motor 46B is driven, the driving force is transmitted to the drum 46A, and the drum 46A is rotated. Since the end of the pulley wire 48 is wound around the drum 46A, the pulley wire 48 can move up and down as shown by the arrow F in Fig. 9 according to the rotation direction of the drum 46A. As a result, the blades 104A to 104C suspended via the pulley wire 48 and the wire 49 also move up and down at the wound portions of the wire 49. As a result, the inclination angle α of the blades 104A to 104C with respect to the horizontal direction can be adjusted around the axis C4 along the Y direction at the center of gravity of the blades 104A to 104C.
[0050] That is, in this embodiment, the winch 46, the pulley wire 48, and the wire 49 configure the inclination angle adjustment device 52 and realize the function of the inclination angle adjustment device 52.
[0051] In addition, as shown in Fig. 9, for example, when the blade hoisting beam 40 supports the blades 104A-104C at both ends 41A and 41B, it is preferable that the center of gravity of the blades 104A-104C can be located at the X-direction position of the pillars 33 and 34 of the portal frame 30, and thus the attitude of the blades 104A-104C can be easily maintained horizontally. This configuration can be realized, for example, by adjusting the length of each wire 39, 47, 48, and 49 supporting the blades 104A-104C and the position of the two hoisting hooks 43. In addition, in the case of this configuration, the inclination angle adjustment device 52 can adjust the inclination angle α of the blades 104A-104C around the rotation axis C4 that passes through the center of gravity and is perpendicular to the axis C3 of the blades 104A-104C as shown in Fig. 9.
[0052] 9, the blade hoisting beam 40 may be configured to include a generator 50. The generator 50 supplies power to the motor 45 of the rotation angle adjustment device 51 and the motor 46B of the inclination angle adjustment device 52. Considering the effect on the center of gravity, the generator 50 is preferably installed, for example, at a midpoint between the two hoisting hooks 43 of the main frame 41.
[0053] In addition, each component of the assembly system 1, that is, the support 10, the lift-up device 20, the portal frame 30, and the blade suspension beam 40, is preferably made of metal in consideration of strength and durability.
[0054] Next, the effect of the assembly system 1 for the wind power generator according to this embodiment will be described. The assembly system 1 of this embodiment includes a support 10 installed around the tower 101 of the wind power generator 100, a lift-up device 20 installed on the support 10 and ascending and descending along the support 10 to individually raise the nacelle 102, the hub 103, and each of the plurality of blades 104A to 104C of the wind power generator 100 to the tip of the tower 101, and a portal frame 30 installed on the lift-up device 20, movable in the horizontal direction approaching and separating from the tower 101, capable of individually suspending the nacelle 102, the hub 103, and each of the plurality of blades 104A to 104C, and horizontally moving the nacelle 102, the hub 103, and each of the plurality of blades 104A to 104C raised by the lift-up device 20 to a connection portion with other components of the wind power generator 100.
[0055] With this configuration, each part of the wind power generator 100 can be transported to a connection position with other parts at the top of the tower 101 using the lift-up device 20 and the portal frame 30, so that the lift-up device 20 can be lowered to a predetermined position at the bottom of the support 10 to suspend each part of the wind power generator 100 from the portal frame 30. In other words, there is no need to use a crane to lift each part of the wind power generator 100 to a connection position with other parts at the top of the tower 101, and the height at which each part is lifted can be kept lower than in the conventional method, so that the crane used to transport each part of the wind power generator 100 can be made smaller than in the conventional method. If the crane can be made smaller, the area of the installation site for the crane can also be reduced. In addition, the weight of the crane is also lighter, so the strength requirements for the ground at the installation site can be relaxed. Furthermore, even if the wind power generator 100 becomes larger, the height at which each component is suspended from the gantry frame 30 by the crane does not change, and only the height of the pillars 10 of the assembly system 1 and the lifting distance of the lift-up device 20 increase. This means that the workability is not adversely affected even under adverse conditions such as strong winds, and workability can be improved.
[0056] In the conventional method, when the wind power generator becomes large and the assembly workability deteriorates by only lifting each component by a crane, a method has been proposed in which the rotor is assembled in advance by connecting the blades 104A to 104C to the hub 103 on the ground or at a lower position of the tower, and then the assembled rotor is lifted to the installation position at the top of the tower. In the case of such a conventional method, it is considered that the ground area required for construction is about 1.5 times the diameter of the rotor, that is, the length of the blade (length in the Y direction in the present embodiment). In contrast, in the assembly system 1 of the present embodiment, the nacelle 102, the hub 103, and each of the multiple blades 104A to 104C of the wind power generator 100 can be transported individually to the connection position with other components at the top of the tower 101 using the lift-up device 20 and the gate-shaped frame 30. As a result, the dimension in the Y direction can be accommodated within the width of the gate-shaped frame 30 when transporting each component, so that the ground area required for construction of the wind power generator 100 can be further reduced compared to the conventional method. As a result, the wind power generator assembly system 1 according to this embodiment can reduce the ground area required for constructing the wind power generator, and can improve workability.
[0057] In the assembly system 1 of this embodiment, the support 10 has four pillars 11-14 erected around the tower 101 and a beam 15 connecting adjacent pillars 11-14, and is installed in a quadrangle around the central axis C1 of the tower 101 with the pillars 11-14 as corners and the beam 15 as sides. The lift-up device 20 is arranged extending horizontally along a pair of opposite sides of the quadrangle of the support 10, and has a pair of climbing beams 23, 24 on which the portal frame 30 is movably installed, and a pair of measuring devices 21, 22 connected to two of the four pillars 11-14 of the support 10 (two pillars 11, 12 in this embodiment) and capable of ascending and descending along the two pillars 11, 12. The climbing beams 23, 24 have first beams 23A, 24A whose base ends are connected to the measuring devices 21, 22 and whose tip ends extend away from the support 10, and second beams 23B, 24B connected to the base or tip ends of the first beams 23A, 24A so as to extend in the same direction as the first beams 23A, 24A. When the nacelle 102 and the hub 103 are attached, the second beams 23B, 24B are connected to the base ends of the first beams 23A, 24A, and when the blades 104A to 104C are attached, the second beams 23B, 24B are removed from the base ends of the first beams 23A, 24A and reconnected to the tip ends of the first beams 23A, 24A, and the climbing beams 23, 24 are extended in the direction away from the support 10.
[0058] With this configuration, in order to suspend the long blades 104A-104C from the portal frame 30 relative to the nacelle 102 and the hub 103, it is possible to move the position of the portal frame 30 away from the support pillar 10. As a result, it is possible to suspend the blades 104A-104C from the portal frame 30 while avoiding the base ends of the blades 104A-104C coming into contact with the support pillar 10 or the tower 101, without changing the installation position of the lift-up device 20 relative to the support pillar 10 from the two pillar members 11 and 12. This further improves the work efficiency.
[0059] The assembly system 1 of this embodiment further includes a blade hoisting beam 40 that is suspended from the portal frame 30 and suspends and supports the blades 104A-104C. The blade hoisting beam 40 supports the blades 104A-104C so that its longitudinal direction coincides with the extension direction of the blades 104A-104C, and supports the blades 104A-104C at two locations, 41A and 41B, in the longitudinal direction. One of the two support portions, 41A, has a rotation angle adjustment device 51 for adjusting the rotation angle θ of the blades 104A-104C about the axis C3, and the other, 41B, has an inclination angle adjustment device 52 for adjusting the inclination angle α of the blades 104A-104C with respect to the horizontal direction.
[0060] With this configuration, when the long blades 104A to 104C are suspended from the portal frame 30 with respect to the nacelle 102 and the hub 103, the long blade suspension beam 40 can be used to support the blades 104A to 104C so that the longitudinal direction coincides with the extension direction of the blades 104A to 104C. This allows the blades 104A to 104C to be supported more stably. In addition, while suspended from the blade suspension beam 40, the rotation angle θ and the tilt angle α of the blades 104A to 104C with respect to the connecting parts 103A to 103C can be adjusted by the rotation angle adjustment device 51 and the tilt angle adjustment device 52. This allows the efficiency and accuracy of the work in the process of connecting the blades 104A to 104C to the hub 103 to be improved.
[0061] Furthermore, in the assembly system 1 of this embodiment, the portal frame 30 has a pair of pillars 33, 34 extending upward from the pair of climbing beams 23, 24, respectively, and a beam 35 connecting the upper ends of the pair of pillars 33, 34. The beam 35 of the portal frame 30 has a first beam 36 and a second beam 37 that can be connected and separated at a middle portion of the beam 35, and the first beam 36 is rotatably connected to one of the pair of pillars 33, and the second beam 37 is rotatably connected to the other of the pair of pillars 34.
[0062] With this configuration, even if the multiple blades 104A to 104C of the wind power generator 100 are individually connected to the hub 103 using the lift-up device 20 and the portal frame 30, the first beam 36 and the second beam 37 of the beam 35 arranged above the blades after being connected to the hub 103 can be separated and rotated toward the columns 33 and 34 to avoid being above the blades. This makes it possible to lower the lift-up device 20 without being hindered by the blades after being connected to the hub 103. As a result, the assembly system 1 including the lift-up device 20 and the portal frame 30 can be used, and a construction method can be implemented in which each part of the wind power generator 100 is individually transported to the top end of the tower and connected and assembled in sequence, so that the ground area required for the construction of the wind power generator can be more reliably reduced and construction efficiency can be improved.
[0063] <How to assemble a wind turbine> A method for assembling a wind power generator using the assembly system 1 according to this embodiment will be described with reference to Figs.
[0064] FIG. 11 is a side view showing the first stage of the assembly procedure of the wind power generator 100. As a step before the first stage of FIG. 11, the bottom tower 101A, the second tower 101B, the third tower 101C, the fourth tower 101D, and the top tower 101E are connected to each other to assemble the tower 101 of the wind power generator 100, and the support columns 10 are installed around the tower 101. The support columns 10 are raised upward, for example, according to the installation of each stage of the tower 101, and additional support columns are pulled in and connected between the raised lower end and the installation surface. This process is repeated, and the support columns 10 are extended upward in stages, and finally reach the state shown in FIG. 11.
[0065] 11, the lift-up device 20 is placed at a predetermined position below the support 10, and the nacelle 102 is suspended from the portal frame 30 via wires 39 using a crane or the like. When the suspension of the nacelle 102 is completed, the lift-up device 20 moves upward as shown by arrow A1 (nacelle installation step).
[0066] 12 is a side view showing the second stage of the assembly procedure for the wind power generator 100. The lift-up device 20 rises to a predetermined position on the upper end of the support column 10. After that, as shown by arrow B1, the portal frame 30 moves toward the support column 10, and as a result, the nacelle 102 suspended from the portal frame 30 moves to the connection position at the upper end of the tower 101 (nacelle installation step).
[0067] 13 is a side view showing a third stage of the assembly procedure of the wind power generator 100. When the portal frame 30 moves to a position above the support 10 and the nacelle 102 suspended from the portal frame 30 moves to a connection position at the upper end of the tower 101, the nacelle 102 is connected to the upper end of the tower 101 (nacelle installation step). At this time, the nacelle 102 is brought close to the upper end of the tower 101 while the position of the rotation axis of the nacelle 102 is adjusted so as to align with the position of the axis C1 of the tower 101. As a result, the nacelle 102 is connected to the tower 101 so as to be rotatable around the rotation axis C1.
[0068] 8 and other figures, the lower part of the portal frame 30 is open, and furthermore, the support columns 10 are disposed on the outer periphery of the tower 101, so that in the third stage state shown in Fig. 13, no other members are interposed between the nacelle 102 and the tower 101. For this reason, for example, by extending the wires 39 downward using the suspension device 38 of the portal frame 30 to lower the height position of the nacelle 102, the connection portions of the nacelle 102 and the tower 101 can be easily brought close to opposing positions to connect the two.
[0069] 14 is a side view showing a fourth stage of the assembly procedure of the wind power generator 100. The nacelle 102 attached to the tower 101 is rotated 180 degrees around the central axis C1 of the tower 101 as shown by arrow G, so that the connection part between the nacelle 102 and the hub 103 faces the negative X direction. The lift-up device 20 is lowered to a predetermined position at the lower end of the support 10, and the hub 103 is suspended from the portal frame 30 via the wire 39 using a crane or the like. When the suspension of the hub 103 is completed, the lift-up device 20 moves upward as shown by arrow A2 (hub installation step).
[0070] 15 is a side view showing a fifth stage of the assembly procedure of the wind power generator 100. The lift-up device 20 rises to a predetermined position at the upper end of the support 10. Thereafter, the portal frame 30 moves toward the support 10 as shown by arrow B2, and as a result, the hub 103 suspended from the portal frame 30 moves to the connection position of the nacelle 102, and the hub 103 is connected to the nacelle 102 (hub installation step). At this time, the hub 103 is brought close to the nacelle 102 while the position of the rotation axis of the hub 103 is adjusted so as to align with the position of the axis C2 of the nacelle 102. As a result, the hub 103 is connected to the nacelle 102 so as to be rotatable around the rotation axis C2.
[0071] 16 is a side view showing a sixth stage of the assembly procedure of the wind power generator 100. The lift-up device 20 is lowered to a predetermined position at the lower end of the support 10. Here, the second beams 23B, 24B of the climbing beams 23, 24 are moved from the base end side to the tip end side of the first beams 23A, 24A, and the climbing beams 23, 24 are extended in a direction away from the support 10 (extension step). As shown by arrow B3, the portal frame 30 moves in a direction away from the support 10 to the position of the relocated second beams 23B, 24B (movement step). Furthermore, the blade suspension beam 40 is installed on the portal frame 30 (suspension beam installation step).
[0072] FIG. 17 is a side view showing a seventh stage of the assembly procedure of the wind power generator 100. FIG. 18 is a plan view of the seventh stage shown in FIG. 17. As shown by the arrow H in FIG. 17 and FIG. 18, the nacelle 102 is rotated around the central axis C1 of the tower 101 so that the connection parts 103A to 103C of the hub 103 with the blades 104A to 104C face the base ends of the blades 104A to 104C (nacelle rotation step). Specifically, the nacelle 102 is rotated about 75 degrees around the central axis C1 so that the tip end of the hub 103 faces the Y negative direction side with respect to the nacelle 102. As a result, as shown in FIG. 18, the direction of the rotation axis C2 of the hub 103 is inclined about 15 degrees with respect to the Y direction. Additionally, the position of hub 103 around rotation axis C2 is adjusted so that one connection portion 103A of connection portions 103A to 103C with the three blades of hub 103 faces first blade 104A. For example, connection portion 103A is adjusted so as to face the horizontal direction (X negative direction side).
[0073] In the seventh stage, as shown in Fig. 17, the first blade 104A is suspended from the blade hoisting beam 40 via wires 47-49 using a crane or the like. As shown in Fig. 18, the first blade 104A is installed at an angle with respect to the X direction so that the longitudinal direction of the base end (for example, the direction of the axis C3 shown in Fig. 8) is perpendicular to the rotation axis C2 of the hub 103. At this time, the blade hoisting beam 40 is disposed so as to be accommodated between a pair of pillars 33, 34 of the portal frame 30. When the suspension of the first blade 104A is completed, the lift-up device 20 moves upward as shown by the arrow A3 (blade installation step).
[0074] FIG. 19 is a side view showing an eighth stage of the assembly procedure of the wind power generator 100. FIG. 20 is a plan view of the eighth stage shown in FIG. 19. The lift-up device 20 rises to a predetermined position at the upper end of the support 10. Thereafter, the portal frame 30 moves toward the support 10 as shown by the arrow B4, and the first blade 104A suspended from the portal frame 30 approaches a position facing the connection part 103A of the hub 103 (approaching step), and the base end of the first blade 104A is connected to the connection part 103A of the hub 103 (blade installation step). At this time, the first blade 104A approaches the hub 103 while the rotation angle θ of the axis C3 of the first blade 104A and the tilt angle α about the rotation axis C4 are adjusted so that the base end of the first blade 104A faces the connection part 103A of the hub 103. The rotation angle θ with respect to the connection portion 103A is adjusted by the rotation angle adjustment device 51 (rotation angle adjustment step), and the inclination angle α with respect to the connection portion 103A is adjusted by the inclination angle adjustment device 52 (inclination angle adjustment step). At this time, the blade suspension beam 40 is disposed so as to be accommodated between the pair of pillars 33, 34 of the portal frame 30.
[0075] FIG. 21 is a side view showing a ninth stage of the assembly procedure of the wind power generator 100. FIG. 22 is a plan view of the ninth stage shown in FIG. 21. As shown in FIG. 22, the connection between the first beam 36 and the second beam 37 constituting the beam 35 of the portal frame 30 is released. The first beam 36, with the blade suspension beam 40 suspended, rotates in the X positive direction as shown by arrow C, and moves together with the blade suspension beam 40 out of the way of above the first blade 104A already installed on the hub 103. The second beam 37 rotates in the X negative direction as shown by arrow D, and moves out of the way of above the first blade 104A already installed on the hub 103.
[0076] After the first blade 104A is attached to the hub 103, if the first blade 104A attached between the beam 35 of the portal frame 30 and the lift-up device 20 is interposed and the lift-up device 20 is attempted to be lowered, the downward movement of the beam 35 of the portal frame 30 is hindered by the first blade 104A. To avoid this situation, after the first blade 104A is connected to the hub 103, the first beam 36 and the second beam 37 of the portal frame 30 are rotated to move the beam 35 away from above the first blade 104A (avoidance step). This allows the lift-up device 20 to be lowered.
[0077] Since the first blade 104A already installed on the hub 103 is in a position in which its base end is inclined toward the negative Y direction relative to the X direction, the first beam 36, the second beam 37, and the blade suspension beam 40 are all rotated in the directions of arrows C and D, respectively, to more reliably avoid the first blade 104A from above.
[0078] After the first beam 36 and the second beam 37 are rotated in this manner and the beam 35 has cleared the area above the first blade 104A, the lift-up device 20 descends to a predetermined position at the lower end of the pillar 10 as shown by arrow A4 in Fig. 21 (descent step). At the timing after the upper end of the portal frame 30 has descended below the first blade 104A, the first beam 36 and the second beam 37 of the portal frame 30 are rotated in the directions opposite to the arrows C and D, respectively, so that the first beam 36 and the second beam 37 are returned to a connected state between the pair of pillars 33 and 34 again (connection step).
[0079] 23 is a side view showing a tenth stage of the assembly procedure of the wind power generator 100. As shown by arrow I, the hub 103 rotates 120 degrees around the rotation axis C2, and the first blade 104A rotates toward the X positive direction. As a result, the position of the hub 103 around the rotation axis C2 is adjusted so that one connection portion 103B of the connection portions 103A to 103C with the three blades of the hub 103 faces the second blade 104B. For example, the connection portion 103B is adjusted to face the horizontal direction (the X negative direction).
[0080] In the tenth stage, the second blade 104B is suspended from the blade hanging beam 40 via wires 47-49 using a crane or the like. The second blade 104B is also installed at an angle with respect to the X direction so that the longitudinal direction of the base end is perpendicular to the rotation axis C2 of the hub 103, similar to the first blade 104A shown in Fig. 18 (see Fig. 25). After that, the lift-up device 20 rises as shown by the arrow A5 (blade installation step).
[0081] FIG. 24 is a side view showing an eleventh stage of the assembly procedure of the wind power generator 100. FIG. 25 is a plan view of the eleventh stage shown in FIG. 24. The lift-up device 20 rises to a predetermined position at the upper end of the support 10. Thereafter, the portal frame 30 moves toward the support 10 as shown by the arrow B5, and the second blade 104B suspended from the portal frame 30 approaches a position facing the connection part 103B of the hub 103 (approaching step), and the base end of the second blade 104B is connected to the connection part 103B of the hub 103 (blade installation step). At this time, the second blade 104B approaches the hub 103 while the rotation angle θ of the axis C3 of the second blade 104B and the inclination angle α about the rotation axis C4 are adjusted so that the base end of the second blade 104B faces the connection part 103B of the hub 103. The rotation angle θ with respect to the connection portion 103B is adjusted by the rotation angle adjustment device 51 (rotation angle adjustment step), and the inclination angle α with respect to the connection portion 103B is adjusted by the inclination angle adjustment device 52 (inclination angle adjustment step).
[0082] After the 11th stage, similarly to the 9th stage shown in Figures 21 and 22, the first beam 36 and the second beam 37 constituting the beam 35 of the portal frame 30 are released from their connection and rotated to avoid the beam 35 from above the second blade 104B already installed on the hub 103 (avoidance step). After that, the lift-up device 20 descends to a predetermined position at the lower end of the pillar 10 (descent step). The first beam 36 and the second beam 37 are returned to the connected state again at a timing after the portal frame 30 descends below the second blade 104B (connection step).
[0083] 26 is a side view showing a twelfth stage of the assembly procedure of the wind power generator 100. As shown by arrow J, the hub 103 rotates 120 degrees around the rotation axis C2, and the second blade 104B rotates toward the X positive direction. As a result, the position of the hub 103 around the rotation axis C2 is adjusted so that one connection portion 103C of the connection portions 103A to 103C with the three blades of the hub 103 faces the third blade 104C. For example, the connection portion 103C is adjusted to face the horizontal direction (the X negative direction).
[0084] In the twelfth stage, first, third blade 104C is suspended from blade hanging beam 40 via wires 47-49 using a crane or the like. Similar to first blade 104A shown in FIG. 18, third blade 104C is also installed at an angle with respect to the X direction so that the longitudinal direction of its base end is perpendicular to rotation axis C2 of hub 103.
[0085] After that, as shown in FIG. 26, the lift-up device 20 rises to a predetermined position at the upper end. Next, as shown by the arrow B6, the gate-shaped frame 30 moves toward the support 10, and the third blade 104C suspended from the gate-shaped frame 30 approaches a position facing the connection part 103C of the hub 103 (approaching step), and the base end of the third blade 104C is connected to the connection part 103C of the hub 103 (blade installation step). At this time, the third blade 104C approaches the hub 103 while adjusting the rotation angle θ of the axis C3 of the third blade 104C and the inclination angle α about the rotation axis C4 so that the base end of the third blade 104C faces the connection part 103C of the hub 103. The rotation angle θ with respect to the connection part 103C is adjusted by the rotation angle adjustment device 51 (rotation angle adjustment step), and the inclination angle α with respect to the connection part 103C is adjusted by the inclination angle adjustment device 52 (inclination angle adjustment step).
[0086] 27 is a side view showing a thirteenth stage of the assembly procedure of the wind power generator 100. The first beam 36 and the second beam 37 constituting the beam 35 of the portal frame 30 are released from the connection and rotated to avoid the beam 35 from above the third blade 104C already installed on the hub 103 (avoidance step). After that, the lift-up device 20 descends to a predetermined position at the lower end of the support 10 as shown by arrow A6 (descent step). After the lift-up device 20 descends, the nacelle 102 rotates 90 degrees around the central axis C1 of the tower 101 as shown by arrow K, and the hub 103 transitions to a posture facing the negative X direction. As a result, the assembly of the wind power generator 100 is completed.
[0087] After the thirteenth stage, each device of the assembly system 1 is removed from around the wind power generator 100, and the wind power generator 100 is finally in a completed state as shown in FIG.
[0088] Next, the effect of the wind power generator assembly method according to this embodiment will be described. The wind power generator assembly method according to this embodiment includes a nacelle installation step (the process from the first stage in FIG. 11 to the third stage in FIG. 13), a hub installation step (the process from the fourth stage in FIG. 14 to the fifth stage in FIG. 15), and a blade installation step (the process from the sixth stage in FIG. 16 to the thirteenth stage in FIG. 27). In the nacelle installation step, the nacelle 102 of the wind power generator 100 is hung from the portal frame 30 and raised to the tip of the tower 101 by the lift-up device 20, and the portal frame 30 is moved horizontally to move the nacelle 102 to just above the tip of the tower 101, and the nacelle 102 is connected to the tower 101. In the hub installation step, the hub 103 of the wind power generator 100 is hung from the portal frame 30 and raised to the tip of the tower 101 by the lift-up device 20, the portal frame 30 is moved horizontally to move the hub 103 to a position facing the nacelle 102, and the hub 103 is connected to the nacelle 102. In the blade installation step, one of the multiple blades 104A to 104C of the wind power generator 100 is hung from the portal frame 30 and raised to the tip of the tower 101 by the lift-up device 20, the portal frame 30 is moved horizontally to move the lifted one blade to a position facing the hub 103, and this one blade is connected to the hub 103, and the remaining multiple blades are similarly connected one by one to the hub 103 using the lift-up device 20 and the portal frame 30.
[0089] With this configuration, each part of the wind power generator 100 can be transported to a connection position with other parts at the top of the tower 101 using the lift-up device 20 and the portal frame 30, so that the lift-up device 20 can be lowered to a predetermined position at the bottom of the support 10 to suspend each part of the wind power generator 100 from the portal frame 30. In other words, there is no need to use a crane to lift each part of the wind power generator 100 to a connection position with other parts at the top of the tower 101, and the height at which each part is lifted can be kept lower than in the conventional method, so that the crane used to transport each part of the wind power generator 100 can be made smaller than in the conventional method. If the crane can be made smaller, the area of the installation site for the crane can also be reduced. In addition, the weight of the crane is also lighter, so the strength requirements for the ground at the installation site can be relaxed. Furthermore, even if the wind power generator 100 becomes larger, the height at which each component is suspended from the gantry frame 30 by the crane does not change, and only the height of the pillars 10 of the assembly system 1 and the lifting distance of the lift-up device 20 increase. This means that the workability is not adversely affected even under adverse conditions such as strong winds, and workability can be improved.
[0090] In the conventional method, when the wind power generator becomes large and the assembly workability deteriorates by only lifting each component by a crane, a method has been proposed in which the rotor is assembled in advance by connecting the blades 104A to 104C to the hub 103 on the ground or at a lower position of the tower, and then the assembled rotor is lifted to the installation position at the top of the tower. In the case of such a conventional method, it is considered that the ground area required for construction is about 1.5 times the diameter of the rotor, that is, the width of the blade (length in the Y direction in the present embodiment) as long as the major axis of the rotor. In contrast, in the present embodiment, the nacelle installation step, hub installation step, and blade installation step described above allow the nacelle 102, hub 103, and each of the multiple blades 104A to 104C of the wind power generator 100 to be transported individually to the connection position with other components at the top of the tower 101 using the lift-up device 20 and the portal frame 30. As a result, the dimension in the Y direction can be accommodated within the width of the portal frame 30 when transporting each component, so that the ground area required for construction of the wind power generator 100 can be further reduced compared to the conventional method. As a result, the wind power generator assembly method according to this embodiment can reduce the ground area required for constructing the wind power generator and improve workability.
[0091] In addition, the wind turbine assembly method of this embodiment includes, after the hub installation step, a nacelle rotation step (seventh step in Figures 17 and 18) in which the nacelle 102 is rotated around the central axis C1 of the tower 101 so that the connection portions 103A-103C of the hub 103 with the blades 104A-104C are positioned opposite the base ends of the blades 104A-104C.
[0092] With this configuration, the direction in which the blades 104A to 104C are horizontally moved by the portal frame 30 to install them on the hub 103 can be the same as the direction when installing the nacelle 102 on the tower 101 and when installing the hub 103 on the nacelle 102. As a result, after the nacelle installing step and the hub installing step, the blade installing step can be performed without changing the installation position of the lift-up device 20 of the assembly system 1 relative to the support 10, thereby improving work efficiency.
[0093] In addition, the wind turbine assembly method of this embodiment includes an extension step (the sixth step in Figure 16) between the hub installation step and the blade installation step, in which the second beams 23B, 24B of the climbing beams 23, 24 of the lift-up device 20 are detached from the base end sides of the first beams 23A, 24A and reconnected to the tip sides of the first beams 23A, 24A, and the climbing beams 23, 24 are extended in a direction away from the support 10.
[0094] With this configuration, the position of the portal frame 30 can be separated from the support pillar 10 in order to suspend the long blades 104A-104C from the portal frame 30 relative to the nacelle 102 and the hub 103. This makes it possible to suspend the blades 104A-104C from the portal frame 30 while preventing the base ends of the blades 104A-104C from contacting the support pillar 10 or the tower 101, without changing the installation position of the lift-up device 20 relative to the support pillar 10. This further improves the work efficiency.
[0095] Furthermore, in the wind turbine assembly method according to this embodiment, the blade installation step includes a moving step of moving the portal frame 30 onto the second beams 23B, 24B that were reattached in the extension step, and a suspension beam installation step of installing the blade suspension beam 40 on the portal frame 30 (the above is the sixth step in Figure 16), an approach step of moving the portal frame 30 to bring the blades 104A-104C closer to the connection parts 103A-103C of the hub 103, a rotation angle adjustment step of adjusting the rotation angle θ of the blades 104A-104C relative to the connection parts 103A-103C using the rotation angle adjustment device 51, and an inclination angle adjustment step of adjusting the inclination angle α of the blades 104A-104C relative to the connection parts 103A-103C using the inclination angle adjustment device 52 (the above is the eighth step in Figures 19 and 20, the eleventh step in Figures 24 and 25, and the twelfth step in Figure 26).
[0096] With this configuration, when the long blades 104A to 104C are suspended from the portal frame 30 with respect to the nacelle 102 and the hub 103, the long blade suspension beam 40 can be used to support the blades 104A to 104C so that the longitudinal direction coincides with the extension direction of the blades 104A to 104C. This allows the blades 104A to 104C to be supported more stably. In addition, while suspended from the blade suspension beam 40, the rotation angle θ and the tilt angle α of the blades 104A to 104C with respect to the connecting parts 103A to 103C can be adjusted by the rotation angle adjustment device 51 and the tilt angle adjustment device 52. This allows the efficiency and accuracy of the work in the process of connecting the blades 104A to 104C to the hub 103 to be improved.
[0097] Furthermore, in the wind turbine assembly method according to this embodiment, the blade installation step includes an avoidance step in which, after connecting one of the multiple blades 104A-104C to the hub 103, the first beam 36 and the second beam 37 of the portal frame 30 are rotated to avoid the blade 104A-104C from above, a descent step in which the lift-up device 20 is lowered after the avoidance step, and a connection step in which, after the upper end of the portal frame 30 is lowered below the installed blade by the descent step, the first beam 36 and the second beam 37 of the portal frame 30 are rotated to connect between a pair of pillars 33, 34 (after the ninth step in Figures 21 and 22, the eleventh step in Figures 24 and 25, and the thirteenth step in Figure 27).
[0098] With this configuration, even if the multiple blades 104A-104C of the wind power generator 100 are individually connected to the hub 103 using the lift-up device 20 and the portal frame 30, the lift-up device 20 can be lowered without being obstructed by the blades after they have been connected to the hub 103. This makes it possible to use the assembly system 1 equipped with the lift-up device 20 and the portal frame 30, and to implement a construction method in which each part of the wind power generator 100 is individually transported to the top end of the tower and connected and assembled in sequence, so that the ground area required for construction of the wind power generator can be more reliably reduced and construction ease can be improved.
[0099] The present embodiment has been described above with reference to specific examples. However, the present disclosure is not limited to these specific examples. Any design modifications made by a person skilled in the art to these specific examples are also included within the scope of the present disclosure as long as they have the features of the present disclosure. The elements of each of the above-mentioned specific examples and their arrangements, conditions, shapes, etc. are not limited to those exemplified and can be changed as appropriate. The combination of each of the elements of each of the above-mentioned specific examples can be changed as appropriate as long as no technical contradiction occurs.
[0100] In the above embodiment, the assembly system 1 for the wind power generator 100 according to this embodiment is applied to the construction of a land-based wind power generation facility, but it can also be applied to the construction of an offshore wind power generation facility. [Explanation of symbols]
[0101] 1 Wind turbine assembly system 10 pillars 11, 12, 13, 14 Pillar material 15 Beam material 20 Lift-up device (lifting device) 21, 22 Measurement device 23, 24 Climbing beam 23A, 24A 1st beam 23B, 24B 2nd beam 30 Gate Frame 33, 34 Pillar material 35 Beam material 36 First Beam 37 Second Beam 38 Suspension equipment 53 Preventing gate frames from collapsing 40 Blade Lifting Beam 51 Rotation angle adjustment device 52 Tilt angle adjustment device 100 Wind Turbine 101 Tower 102 Nacelle 103 Hub 103A, 103B, 103C Connections 104A No. 1 Blade 104B 2nd Blade 104C 3rd Blade C1 Tower central axis, nacelle rotation axis
Claims
1. A support pole is installed around the tower of the wind turbine. A lifting device that is installed on the support and moves up and down along the support; A portal frame is installed on the lifting device and moves in a horizontal direction toward and away from the tower; A method for assembling a wind turbine generator using an assembly system comprising: a nacelle installation step of suspending a nacelle of the wind power generator from the portal frame, lifting it to the tip of the tower by the lifting device, horizontally moving the portal frame to move the nacelle to directly above the tip, and connecting the nacelle to the tower; a hub installation step of suspending a hub of the wind power generator from the portal frame, raising it to the tip of the tower by the lifting device, horizontally moving the portal frame to move the hub to a position facing the nacelle, and connecting the hub to the nacelle; a nacelle rotating step of rotating the nacelle around a central axis of the tower so that a connection portion of the hub with the plurality of blades of the wind turbine generator faces a base end portion of the blades; a blade installation step of suspending one of the plurality of blades of the wind power generator on the portal frame and raising it to the tip of the tower by the lifting device, horizontally moving the portal frame to move the one blade to a position facing the hub, connecting the one blade to the hub, and similarly connecting the remaining blades to the hub one by one using the lifting device and the portal frame; A method for assembling a wind turbine generator comprising:
2. The support pillars include four pillars erected around the tower and beams connecting adjacent pillars, and are installed in a quadrilateral shape around the central axis, with the pillars forming corners and the beams forming sides; The lifting device is arranged to extend horizontally along a pair of opposite sides of the rectangular shape of the support, and includes a pair of climbing beams on which the portal frame is movably installed, and a pair of measuring devices connected to two of the four pillars of the support and capable of lifting and lowering along the two pillars; The climbing beam has a first beam whose base end side is connected to the measuring device and whose tip end side extends away from the support, and a second beam connected to the base end side or tip side of the first beam so as to extend in the same direction as the first beam, and until the hub installation step, the second beam is connected to the base end side of the first beam, Between the hub installation step and the blade installation step, a stretching step of removing the second beam of the climbing beam from the base end side of the first beam and reconnecting it to the tip side of the first beam, and stretching the climbing beam in a direction away from the support; 2. A method for assembling a wind turbine generator according to claim 1, comprising:
3. The assembly system further includes a blade suspension beam suspended from the portal frame for suspending and supporting the blade, The blade suspension beam supports the blade so that its longitudinal direction coincides with the extension direction of the blade, and supports the blade at two points on both ends in the longitudinal direction. One of the two support portions has a rotation angle adjustment device for adjusting the rotation angle of the blade about its axis, and the other has an inclination angle adjustment device for adjusting the inclination angle of the blade with respect to the horizontal direction. The blade installation step includes: a moving step of moving the portal frame onto the second beam reattached in the extending step; a hoisting beam installation step of installing the blade hoisting beam on the portal frame; an approaching step of moving the portal frame to bring the blade closer to the connection portion of the hub; a rotation angle adjusting step of adjusting the rotation angle of the blade with respect to the connection portion by the rotation angle adjusting device; an inclination angle adjusting step of adjusting the inclination angle of the blade with respect to the connection portion by the inclination angle adjusting device; 3. A method for assembling a wind turbine generator according to claim 2, comprising:
4. The portal frame includes a pair of pillars extending upward from the pair of climbing beams, and a beam connecting the upper ends of the pair of pillars, The beams of the portal frame include a first beam and a second beam that can be connected and separated at a middle portion of the beams, the first beam is rotatably connected to one of the pair of columns, and the second beam is rotatably connected to the other of the pair of columns, The blade installation step includes: an avoidance step of connecting one of the plurality of blades to the hub, and then rotating the first beam member and the second beam member of the portal frame to avoid the blade from above; a lowering step of lowering the lifting device after the avoidance step; a connecting step of rotating the first beam member and the second beam member of the portal frame to connect them between the pair of pillar members after the upper end portion of the portal frame is lowered below the installed blade by the lowering step; 4. A method for assembling a wind turbine generator according to claim 3, comprising:
5. A support pole is installed around the tower of the wind turbine. A lifting device is installed on the support and moves up and down along the support to lift the nacelle, the hub, and each of the plurality of blades of the wind turbine generator individually to the tip of the tower; a portal frame that is installed on the lifting device and can move horizontally toward and away from the tower, can suspend the nacelle, the hub, and each of the blades individually, and horizontally moves the nacelle, the hub, and each of the blades lifted by the lifting device individually to a connection portion with another component of the wind power generator; Equipped with the portal frame is configured to connect the nacelle to the tower, connect the hub to the nacelle, and rotate the nacelle around a central axis of the tower so that a connection portion of the hub with the plurality of blades faces a base end of the blade, and then horizontally move one of the plurality of blades to a position facing the hub to connect the one blade to the hub; Similarly, the remaining blades are connected one by one to the hub using the lifting device and the gate-shaped frame. Wind turbine assembly system.
6. The support pillars include four pillars erected around the tower and beams connecting adjacent pillars, and are installed in a quadrilateral shape around the central axis of the tower, with the pillars forming corners and the beams forming sides; The lifting device is arranged to extend horizontally along a pair of opposite sides of the rectangular shape of the support, and includes a pair of climbing beams on which the portal frame is movably installed, and a pair of measuring devices connected to two of the four pillars of the support and capable of lifting and lowering along the two pillars; The climbing beam has a first beam whose base end side is connected to the measuring device and whose tip end side extends away from the support, and a second beam connected to the base end side or tip side of the first beam so as to extend in the same direction as the first beam; The second beam is When the nacelle and the hub are attached, the nacelle and the hub are connected to the base end side of the first beam, When the blade is attached, it is removed from the base end side of the first beam and reconnected to the tip side of the first beam, and the climbing beam is extended in a direction away from the support.
6. A system for assembling a wind turbine generator according to claim 5.
7. The blade lifting mechanism further includes a blade lifting beam that is suspended from the portal frame and supports the blade by suspending the blade. The blade suspension beam supports the blade so that its longitudinal direction coincides with the extension direction of the blade, and supports the blade at two points on both ends in the longitudinal direction. One of the two support portions has a rotation angle adjustment device for adjusting the rotation angle of the blade about its axis, and the other has an inclination angle adjustment device for adjusting the inclination angle of the blade with respect to the horizontal direction.
7. A system for assembling a wind turbine generator according to claim 6.
8. The portal frame includes a pair of pillars extending upward from the pair of climbing beams, and a beam connecting the upper ends of the pair of pillars, The beams of the portal frame include a first beam and a second beam that can be connected and separated at a middle portion of the beams, the first beam is rotatably connected to one of the pair of columns, and the second beam is rotatably connected to the other of the pair of columns, The portal frame has a fall prevention device for preventing the pair of pillars from falling when the first beam member and the second beam member of the beam member are opened and the pair of pillar members are separated, 8. A system for assembling a wind turbine generator according to claim 7.
9. The beam member has a slide mechanism that can move a position at which the nacelle, the hub, and each of the plurality of blades is suspended along an extension direction of the beam member.
9. The assembly system for a wind turbine generator according to claim 8.
Citation Information
Patent Citations
Wind power generator
JP2017145714A
Rotating body installation method and rotating body installation apparatus
JP2018178633A
Assembling method of rotary body
JP2020041269A