How to install an electric fence and how to set up the posts
The method automates electric fence installation by assessing soil hardness and adjusting for terrain and animal-specific wire configurations, improving efficiency and reliability in electric fence construction.
Patent Information
- Application Number
- JP2021022118
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-02-15
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2041-02-15
AI Technical Summary
Existing electric fence installation methods require significant manual labor and lack automation, particularly in determining suitable soil hardness for post installation, making them labor-intensive and inefficient.
An automated method for electric fence installation that assesses soil hardness to determine suitable installation positions, adjusts for unsuitable soil conditions, and incorporates intermediate supports based on animal height and terrain features to prevent entry or escape.
Facilitates labor-saving, automated electric fence installation by ensuring suitable soil conditions and appropriate positioning, reducing the risk of pillar instability and enhancing animal containment efficacy.
Smart Images

Figure 0007595345000001 
Figure 0007595345000002 
Figure 0007595345000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for installing an electric fence that prevents animals from entering or escaping, and a method for installing posts for use in an electric fence or the like. [Background technology]
[0002] Electric fences generally involve setting up posts at intervals of 5 to 6 meters and stringing wires in multiple layers, all of which is done manually. Installing an electric fence requires multiple trips to the same location, which requires a large number of people to do the work, and is therefore very labor-intensive. For example, it takes five people two hours each to set up a 500m electric fence in an abandoned rice paddy, and five people seven days each to set up a 1,500m electric fence in a wild grassland. There are concerns that the agricultural workforce will continue to decline in the future, so efforts toward automation are needed to make it possible to install electric fences with less labor by just one or two people. For example, Patent Documents 1 to 3 propose electric fences that are designed to improve the ease of installation and transportability of the electric fence itself, or to prevent theft. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2011-223963 A [Patent Document 2] JP 2009-22246 A [Patent Document 3] JP 2008-79521 A Summary of the Invention [Problem to be solved by the invention]
[0004] However, neither Patent Document 1 proposes a method for installing an electric fence that would make it easier to automate the work of installing an electric fence, such as determining the suitability of soil hardness for erecting posts.
[0005] Therefore, an object of the present invention is to provide a method for installing an electric fence and a method for installing posts for use with an electric fence, which makes it easy to automate the work of installing the posts by determining the suitability of the installation position based on the soil hardness and determining an appropriate installation position in advance. [Means for solving the problem]
[0006] The electric fence installation method of the present invention described in claim 1 is a method for installing an electric fence that includes a plurality of posts 1 and overhead wires 2 provided between the posts 1, and prevents the intrusion or escape of a target animal 3, and includes a protection area setting step for setting a protection area 4 for the target animal 3, a boundary line determination step for determining a boundary line generated by the protection area 4, and a method for setting an electric fence based on the boundary line. , by the line curvature of the boundary line A support position tentative determination step for determining a tentative erection position of the support 1; ,before The soil hardness at the temporary installation position is Measure the soil hardness The method includes a soil hardness measuring step using a soil measuring device, a setting position determining step of comparing the soil hardness measured in the soil hardness measuring step with a preset soil hardness and determining whether the position is suitable for setting up the posts 1, a post position determining step of determining the temporary setting positions as the setting positions when the positions are determined to be suitable for all the posts 1 in the setting position determining step, and a post setting step of setting up the posts 1 at the setting positions determined in the post position determining step, In the tentative support position determination step, an inflection point of the boundary line is set as the tentative installation position, and if the line curvature between two adjacent inflection points on the boundary line is equal to or smaller than a predetermined value, the boundary line is determined as the tentative installation position; If it is determined that the erection position is inappropriate in the erection position determination step, the tentative erection position already determined is determined in the tentative post position determination step. A position shifted toward the guardian area 4 side. New temporary location As the soil hardness at the new temporary installation position is measured using the soil measuring device, the suitability of the new measured soil hardness is judged in the installation position judgment step, and the soil hardness measuring step and the installation position judgment step are repeated until the installation position judgment step judges that the soil hardness is suitable. The present invention as described in claim 2 is characterized in that, in the method of installing an electric fence as described in claim 1, the set soil hardness includes a first set soil hardness and a second set soil hardness that sets a hardness higher than the first set soil hardness, and in the installation position determination step, when the soil hardness of the temporary installation position is equal to or higher than the first set soil hardness and equal to or lower than the second set soil hardness, it is determined that the installation position is suitable. The present invention as described in claim 3 is characterized in that, in the method of installing an electric fence as described in claim 1 or claim 2, the new temporary installation position is located on the side of the protected area 4 than the temporary installation position that has been determined to be unsuitable. The present invention as described in claim 4 is characterized in that, in the method for installing an electric fence as described in any one of claims 1 to 3, it comprises the steps of: a target animal determination step of determining the target animal 3; a minimum overhead line height determination step of determining a minimum ground height H from the ground surface 5 to the overhead line 2 to be installed at the lowest level based on the target animal 3 determined in the target animal determination step; a height difference determination step of determining whether a recess 5y exceeding the minimum ground height H or a protrusion 5z equal to or greater than the virtual overhead lines 6x, 6y, 6z is present between the posts 1 for a virtual overhead line 6x, 6y, 6 connecting the minimum ground height H from the ground surface 5 of each of the adjacent posts 1 at the erection position determined in the post position determination step; and an intermediate post placement determination step of determining to place intermediate posts 8a, 8b between the posts 1 if the recess 5y or the protrusion 5z is present between the posts 1 in the height difference determination step. The present invention as described in claim 5 is characterized in that, in the electric fence installation method as described in claim 4, it includes a wiring condition determination step for determining the distance between the wiring wires and the number of wiring stages based on the target animal 3 determined in the target animal determination step. Claim 6The present invention described is characterized in that, in the method for installing an electric fence as described in claim 4, the soil measuring device is equipped with a ground surface height measuring means for measuring ground surface height, and has a ground surface height measuring step for measuring the ground surface height at the erection position and the ground surface height of the ground surface 5 between the posts 1 using the ground surface height measuring means, and in the elevation difference determination step, the concave portion 5y or the convex portion 5z is determined using the ground surface height measured in the ground surface height measuring step. Claim 7 The installation method of the support 1 of the present invention described is a method for installing the support 1, A protection area setting step for setting a protection area 4 for a target animal 3, a boundary line determination step for determining a boundary line generated by the protection area 4, and a line curvature of the boundary line based on the boundary line. A step of determining a temporary position of the support 1, and determining the soil hardness at the temporary position, Measure the soil hardness The method includes a soil hardness measuring step using a soil measuring device, a setting position determining step of comparing the soil hardness measured in the soil hardness measuring step with a preset soil hardness and determining whether the position is suitable for setting up the pole 1, a pole position determining step of determining the temporary setting position as the setting position if the pole 1 is determined to be suitable in the setting position determining step, and a pole setting step of setting up the pole 1 at the setting position determined in the setting position determining step, In the tentative support position determination step, an inflection point of the boundary line is set as the tentative installation position, and if the line curvature between two adjacent inflection points on the boundary line is equal to or smaller than a predetermined value, the boundary line is determined as the tentative installation position; If it is determined that the erection position is inappropriate in the erection position determination step, the tentative erection position already determined is determined in the tentative post position determination step. The position is shifted toward the guardian area 4 side. New temporary location As the soil hardness at the new temporary installation position is measured using the soil measuring device, the suitability of the new measured soil hardness is judged in the installation position judgment step, and the soil hardness measuring step and the installation position judgment step are repeated until the installation position judgment step judges that the soil hardness is suitable. Effect of the Invention
[0007] According to the present invention, the soil hardness at the temporary installation position is measured and the suitability of the installation position is determined based on the measured soil hardness, so that the support pole will not tilt or fall over after installation due to the soil being too soft, and there is no inconvenience of the soil being too hard to install the support pole. Since an appropriate installation position can be determined in advance, it is easy to automate the work in the support pole installation step. [Brief description of the drawings]
[0008] [Figure 1] A flowchart showing a method for installing an electric fence according to an embodiment of the present invention. [Diagram 2] Conceptual diagram of electric fence installation according to this embodiment [Diagram 3] A flowchart showing the post position determination process in the electric fence installation method according to the present embodiment. [Figure 4] FIG. 1 is an explanatory diagram showing a process for determining the placement of intermediate posts in an electric fence installation method according to an embodiment; DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0009] The method for installing an electric fence according to the first embodiment of the present invention includes a protection area setting step for setting a protection area for a target animal, a boundary line determination step for determining a boundary line generated by the protection area, and a step for setting an electric fence based on the boundary line. , by the line curvature of the boundary line A support position tentative determination step for determining a tentative erection position of the support; ,tentative The soil hardness at the installation location is Measuring soil hardness The method includes a soil hardness measuring step using a soil measuring device, a setting position determining step of comparing the soil hardness measured in the soil hardness measuring step with a preset soil hardness and determining whether the positions are suitable for setting up posts, a post position determining step of determining a temporary setting position as a setting position when it is determined that all the posts are suitable in the setting position determining step, and a post setting step of setting up the posts at the setting positions determined in the post position determining step, In the tentative support position determination step, an inflection point of the boundary line is determined as a tentative installation position, and if a line curvature between two adjacent inflection points on the boundary line is equal to or less than a predetermined value, the boundary line is determined as the tentative installation position; If the erection position is determined to be inappropriate in the erection position determination step, the tentative erection position already determined is used in the tentative pillar position determination step. The position was shifted toward the defensive area.New temporary location As The soil hardness of the new provisional installation position is measured using a soil measuring device, the suitability of the new measured soil hardness is judged in an installation position judgment step, and the tentative pillar position determination step and the installation position judgment step are repeated until the soil hardness is judged to be suitable in the installation position judgment step. According to this embodiment, the soil hardness at the temporary installation position is measured and the suitability of the installation position is determined based on the measured soil hardness, so that the support pole will not tilt or fall over after installation due to the soil being too soft, and there will be no inconvenience of the support pole being unable to be installed due to the soil being too hard. Since an appropriate installation position can be determined in advance, it is easy to automate the work in the support pole installation step.
[0010] A second embodiment of the present invention relates to a method for installing an electric fence according to the first embodiment, in which the set soil hardnesses are a first set soil hardness and a second set soil hardness which is set to a hardness higher than the first set soil hardness, and in the installation position determination step, when the soil hardness of the temporary installation position is equal to or higher than the first set soil hardness and equal to or lower than the second set soil hardness, it is determined that the installation position is suitable. According to this embodiment, soil hardness less than the first set soil hardness can be determined to be too soft, and soil hardness higher than the second set soil hardness can be determined to be too hard.
[0011] A third embodiment of the present invention is a method for installing an electric fence according to the first or second embodiment, in which a new temporary installation position is located on the protected area side of the temporary installation position that has been determined to be unsuitable. According to this embodiment, the area to be protected is set as the protection area, and the direction in which the post position is shifted is set as the protection area, so that objects to be protected, such as crops and people, can be reliably protected by the electric fence.
[0012] A fourth embodiment of the present invention, in a method for installing an electric fence according to any of the first to third embodiments, comprises a target animal determination step for determining a target animal, a minimum overhead line height determination step for determining a minimum ground level height from the ground surface to the overhead line to be installed at the lowest level based on the target animal determined in the target animal determination step, a height difference determination step for determining whether a concave portion that exceeds the minimum ground level or a convex portion that is equal to or greater than the virtual overhead line connecting the minimum ground levels from the ground surface of each of adjacent posts exists between the posts at the erection position determined in the post position determination step, and an intermediate post placement determination step for determining to place an intermediate post between the posts if a concave portion or convex portion exists between the posts in the height difference determination step. According to this embodiment, when a recess that exceeds the minimum height above ground level or a protrusion that is higher than the virtual overhead line exists between the posts, an intermediate post can be placed to reliably prevent the intrusion or escape of target animals.
[0013] A fifth embodiment of the present invention is a method for installing an electric fence according to the fourth embodiment, which includes a wiring condition determination step for determining the distance between the wires and the number of wire tiers based on the target animal determined in the target animal determination step. According to this embodiment, by setting the distance between the overhead lines and the number of levels of the overhead lines appropriate for the target animal, it is possible to reliably prevent the target animal from entering or escaping.
[0014] The present invention Sixth In this embodiment, in the method of installing an electric fence according to the fourth embodiment, the soil measuring device is provided with a ground surface height measuring means for measuring the ground surface height, and includes a ground surface height measuring step in which the ground surface height at the installation position and the ground surface height between the posts are measured by the ground surface height measuring means, and in the height difference determination step, a concave or convex portion is determined using the ground surface height measured in the ground surface height measuring step. According to this embodiment, the soil measuring device is equipped with a ground surface height measuring means for measuring the ground surface height, making it possible to measure the ground surface height at the same time as measuring the soil hardness. By using the measured ground surface height to determine whether there are concave or convex parts, intermediate supports can be appropriately positioned to reliably prevent the intrusion or escape of target animals.
[0015] The present invention Seventh The method for installing a support pole according to the embodiment of the present invention includes the steps of: A protection area setting step for setting a protection area for a target animal, a boundary line determination step for determining a boundary line generated by the protection area, and a line curvature of the boundary line based on the boundary line. A step of determining a tentative position of the support pole, and determining the soil hardness at the tentative position, Measuring soil hardness The method includes a soil hardness measuring step using a soil measuring device, a setting position determining step of comparing the soil hardness measured in the soil hardness measuring step with a preset soil hardness and determining whether the position is suitable for setting up a post, a post position determining step of determining a temporary setting position as a setting position when the post is determined to be suitable in the setting position determining step, and a post setting step of setting up the post at the setting position determined in the post position determining step, In the tentative support position determination step, an inflection point of the boundary line is determined as a tentative installation position, and if a line curvature between two adjacent inflection points on the boundary line is equal to or less than a predetermined value, the boundary line is determined as the tentative installation position; If the erection position is determined to be inappropriate in the erection position determination step, the tentative erection position already determined is used in the tentative pillar position determination step. The position was shifted toward the defensive area. New temporary location As The soil hardness of the new temporary installation position is determined, the soil hardness of the new temporary installation position is measured using a soil measuring device, the suitability of the new measured soil hardness is determined in an installation position determination step, and the soil hardness measurement step and the installation position determination step are repeated until it is determined to be suitable in the installation position determination step. According to this embodiment, the soil hardness at the temporary installation position is measured and the suitability of the installation position is determined based on the measured soil hardness, so that the support pole will not tilt or fall over after installation due to the soil being too soft, and there will be no inconvenience of the support pole being unable to be installed due to the soil being too hard. Since an appropriate installation position can be determined in advance, it is easy to automate the work in the support pole installation step. EXAMPLES
[0016] An electric fence installation method according to an embodiment of the present invention will now be described. Note that all or part of the steps described below using a flowchart can be processed by a computer.
[0017] Figure 1 is a flowchart showing the method of installing an electric fence according to this embodiment, Figure 2 is a conceptual diagram of electric fence installation according to this embodiment, Figure 3 is a flowchart showing the process of determining the post position in the electric fence installation method according to this embodiment, and Figure 4 is an explanatory diagram showing the process of determining the intermediate post placement in the electric fence installation method according to this embodiment. The method for installing an electric fence according to this embodiment is carried out in the following steps shown in FIG.
[0018] As shown in FIG. 2, this embodiment is a method for installing an electric fence that is made up of a plurality of posts 1 and wires 2 provided between each of the posts 1 and prevents a target animal 3 from entering or escaping. In the method for installing an electric fence according to this embodiment, first, the topography and the presence or absence of wildlife at the site where the electric fence is to be installed are surveyed (S10). The electric fence installation location survey step S10 may be carried out at an actual site, but when a computer is used, it may also be carried out using map data.
[0019] Based on the survey of the planned location for installing the electric fence in the electric fence installation location survey step S10, a protection area 4 (see FIG. 2) for the target animal 3 is set (S11). The concept of the guardianship area 4 is shown in Figure 2. The objects to be protected are crops, people, and private homes, and in the pastureland shown in Figure 2(a), the guardianship area 4 is outside the pastureland based on the concept that "target animals 3 will not escape from the pastureland and damage crops in the fields." Figure 2(b) shows that the guardianship area 4 is the fields, and Figure 2(c) shows that the guardianship area 4 is the fields and private homes. When the guardian area setting step in S11 is carried out by a computer, map data is displayed and the guardian area 4 is set by inputting it into the displayed map data. By setting the guardian area 4 in the guardian area setting step in S11, the boundary line created by the guardian area 4 can be determined (S12). In the boundary line determination step in S12, the outer edge of the guardian area 4 can be determined as the boundary line, and when performed by a computer, the boundary line can be determined by determining the outer edge of the guardian area 4. When the boundary line is determined in the boundary line determining step in S12, a temporary erection position of the pillar 1 is determined based on the boundary line (S13). In the tentative pillar position determination step in S13, a tentative erection position of the pillar 1 is determined based on the pillar interval and the line curvature. For example, the pillar 1 is placed at the inflection point of the boundary line, and if the line curvature between the inflection points is equal to or less than a predetermined value, the number of pillars required for a preset maximum pillar interval is calculated, and the calculated number of pillars are placed between the inflection points so as to be evenly spaced. If the map data contains altitude data in advance, the pillars can be placed taking into account the ground level height of the boundary line. When the ground level height is taken into account, the determination in the elevation difference determination step described below can be used. Once the temporary installation position of the pillar 1 has been determined in the temporary pillar position determination step S13, the soil measuring device is guided using the installation data for the protection area 3, the boundary line, and the temporary installation position, and the soil hardness at the temporary installation position is measured using the soil measuring device (S14). The soil measuring device preferably includes a memory calculation unit and a position detection unit. For example, a GNSS receiving device or a gyro device can be used as the position detection unit. By including the memory calculation unit and the position detection unit, the soil measuring device can calculate the travel route of the soil measuring device based on the acquired data of the guarded area 3 and the boundary line, identify the measurement point from the acquired data of the temporary installation position, and guide the soil measuring device based on the position data detected by the position detection unit. The soil hardness measured in the soil hardness measuring step in S14 is compared with a preset soil hardness to determine whether the location is suitable for erecting the support 1 (S15). If the soil measuring device is equipped with a memory and calculation unit, a set soil hardness can be stored in advance in the memory and calculation unit, so that the determined result can be output. If it is determined in the erection position determination step in S15 that all the pillars 1 are suitable, the temporary erection positions are determined as the erection positions (S16).
[0020] Here, the process from the soil hardness measurement step in S14 to the post position determination step in S16 will be described in more detail with reference to FIG. FIG. 3 shows a case where the set soil hardness includes a first set soil hardness and a second set soil hardness that is higher than the first set soil hardness. For example, the soil hardness to be determined is from the surface to 15 cm. If the soil hardness from the surface to 15 cm is less than 500 kPa, it is determined to be too soft, and if the soil hardness from the surface to 15 cm exceeds 4000 kPa, it is determined to be too hard. In this case, the first set soil hardness is set to 500 kPa, and the second set soil hardness is set to 4000 kPa. If the soil hardness measured in the soil hardness measurement step in S14 falls below the first set soil hardness (Yes in S15a), the temporary installation position is changed to the guarded area 4 side (S13a), and the soil hardness of the changed guarded area 4 is measured again (S14). If the soil hardness measured in the changed guarded area 4 is equal to or greater than the first set soil hardness (No in S15a), the measured soil hardness is compared with the second set soil hardness (S15b). In S15b, if the measured soil hardness exceeds the second set soil hardness (Yes in S15b), the temporary installation position is changed to the guarded area 4 side (S13b), and the soil hardness of the changed guarded area 4 is measured again (S14).
[0021] In this way, if the erection position is judged to be unsuitable in the erection position judgment step (S15), a new temporary erection position different from the already determined temporary erection position is decided in the tentative post position determination step (S13), the soil hardness of the new temporary erection position is measured using a soil measuring device, and the suitability of the new measured soil hardness is judged in the erection position judgment step (S15), and the tentative post position determination step (S13) and the erection position judgment step (S15) are repeated until the erection position judgment step (S15) judges that the position is suitable. Furthermore, in the erection position determination step (S15), when the soil hardness of the temporary erection position is equal to or greater than the first set soil hardness and equal to or less than the second set soil hardness, it is determined that the position is suitable for erection. This prevents the support 1 from tilting or falling over after installation due to the soil being too soft, and also prevents the support from being unable to be erected due to the soil being too hard. Since an appropriate erection position can be determined in advance, it is easy to automate the work in the pillar installation step. In addition, by setting the area to be protected as the protection area 4 and shifting the new temporary installation position toward the protection area 4 side from the temporary installation position that was determined to be unsuitable, objects to be protected, such as crops and people, can be reliably protected with an electric fence.
[0022] As shown in FIG. 1, in addition to the guard area setting step in S11, a target animal 3 is determined (S17). The minimum ground level from the ground surface to the overhead wire 2 installed at the lowest level is determined based on the target animal determined in the target animal determination step in S17 (S18). A data table of minimum ground heights for each target animal 3 is stored in the storage unit, and the minimum ground height can be determined by inputting or selecting the target animal 3. In the ground surface height measuring step S19, the ground surface height at the erection position and the ground surface height between the pillars 1 are measured, and the ground surface heights measured in the ground surface height measuring step S19 are used to determine whether there are any concave or convex portions (S20). The ground surface height measuring means used for measurement in the ground surface height measuring step in S19 is preferably provided in the soil measurement device, and it is preferable that the soil measurement device measures the ground surface height while traveling along the boundary line at the timing when the soil hardness is measured. If a predetermined concave or convex portion is present between the pillars 1 in the height difference determination step in S20, it is determined that an intermediate pillar is to be disposed between the pillars 1 (S21).
[0023] FIG. 4 shows a flow of determining the placement of intermediate supports from the target animal determining step (S17) to the intermediate support placement determining step (S21). In the target animal determination step S17, it is determined whether the target animal 3 is, for example, a "cow," "sheep," "horse," "deer," "wild boar," "bear," "civet / raccoon," "fox / raccoon dog," or "monkey." As shown in FIG. 4(b), the minimum height from the ground surface to the overhead wire 2 installed at the lowest level is determined as follows, for example, for "cattle", 30 cm, for "sheep", 15 cm, for "horse", 60 cm, for "deer", 45 cm, for "wild boar", 20 cm, for "bear", 15 cm, for "civet / raccoon", 10 cm, for "fox / raccoon dog", and 15 cm for "monkey".
[0024] FIG. 4(c) shows a method of determination in the elevation difference determination step in S20. FIG. 4(c) shows four pillars 1a, 1b, 1c, and 1d. Between adjacent pillars 1a and 1b, a virtual overhead line 6x is set connecting the minimum ground height H of pillar 1a from the ground surface 5a to the minimum ground height H of pillar 1b from the ground surface 5b, between adjacent pillars 1b and 1c, a virtual overhead line 6y is set connecting the minimum ground height H of pillar 1b from the ground surface 5b to the minimum ground height H of pillar 1c from the ground surface 5c, and between adjacent pillars 1c and 1d, a virtual overhead line 6z is set connecting the minimum ground height H of pillar 1c from the ground surface 5c to the minimum ground height H of pillar 1d from the ground surface 5d. As shown in FIG. 4(c), the minimum ground height H for the virtual overhead line 6x is line 7x, the minimum ground height H for the virtual overhead line 6y is line 7y, and the minimum ground height H for the virtual overhead line 6z is line 7z. Since the ground surface 5 between the pillars 1a and 1b does not have a convex portion 5z greater than the virtual overhead line 6x or a concave portion 5y greater than the line 7x (Yes in S20), it is determined that the intermediate pillars 8a and 8b are not necessary (S21a). The ground surface 5 between the pillars 1b and 1c does not have a convex portion 5z greater than the virtual overhead line 6y, but does have a concave portion 5y greater than the line 7y (No in S20), so an intermediate pillar 8a is placed (S21b). The ground surface 5 between the pillars 1c and 1d does not have a recess 5y exceeding the line 7z, but does have a protrusion 5z greater than or equal to the virtual overhead line 6y (No in S20), so an intermediate pillar 8b is placed (S21b). As shown in FIG. 4(c), the lowest level overhead lines 9 are provided as follows: overhead line 9a between pillar 1a and pillar 1b, overhead line 9b between pillar 1b and intermediate pillar 8a, overhead line 9c between intermediate pillar 8a and pillar 1c, overhead line 9d between pillar 1c and intermediate pillar 8b, and overhead line 9e between intermediate pillar 8b and pillar 1d. The intermediate supports 8a, 8b are arranged so that the overhead line 9 at the lowest level does not come into contact with the ground surface 5 and the distance between the overhead line 9 and the ground surface 5 is equal to or less than the minimum height H above the ground surface.
[0025] In this way, in the elevation difference determination step S20, it is determined whether a concave portion 5y that exceeds the minimum ground height H, or a convex portion 5z that is equal to or greater than the virtual overhead lines 6x, 6y, 6z connecting the minimum ground height H from the ground surface 5 of each of adjacent pillars 1 exists between the pillars 1 at the temporary erection position determined in the provisional pillar position determination step 13 or the erection position determined in the pillar position determination step 16. Furthermore, when a recess 5y exceeding the minimum ground height H or a protrusion 5z exceeding the virtual overhead lines 6x, 6y, 6z is present between the posts 1, intermediate posts 8a, 8b can be placed to reliably prevent the target animal 3 from entering or escaping.
[0026] As shown in FIG. 1, the distance between the overhead lines and the number of overhead line tiers are determined based on the target animal determined in the target animal determination step in S17 (S22). In the overhead line condition determination step in S22, for example, for "cow", the overhead line distance is 30 cm and the number of overhead line tiers is 3; for "sheep", the overhead line distance from the lowest tier to the third tier is 15 cm, the overhead line distance between the third and fourth tiers is 20 cm, the overhead line distance between the fourth and fifth tiers is 25 cm, and the number of overhead line tiers is 5; for "horse", the overhead line distance from the lowest tier to the third tier is 30 cm and the number of overhead line tiers is 3; for "deer", the overhead line distance from the lowest tier to the third tier is 30 cm, the overhead line distance between the third and fourth tiers is 25 cm, and the number of overhead line tiers is 5; The distance is 45cm and the number of overhead line tiers is 4; for a "wild boar", the distance between the lines is 20cm and the number of lines is 3; for a "bear", the distance between the lines is 15cm and the number of lines is 4; for a "civet / raccoon", the distance between the lines is 10cm and the number of lines is 4; for a "fox / raccoon dog", the distance between the lines is 15cm and the number of lines is 3; and for a "monkey", the distance between the lines from the bottom to the 4th tier is 15cm, the distance between the lines from the 5th to the 8th tier is 20cm, and the number of lines is 8. In this way, by setting the inter-wire distance and the number of wire tiers appropriate for the target animal 3, it is possible to reliably prevent the target animal 3 from entering or escaping. A data table of the distance between the overhead lines, the number of overhead line tiers, and the height of the topmost tier for each target animal 3 is stored in a memory unit, and the distance between the overhead lines, the number of overhead line tiers, and the height of the topmost tier can be determined by inputting or selecting a target animal 3.
[0027] 1, the support 1 is installed at the erection position determined in the support position determination step in S16. Also, the intermediate supports 8a and 8b determined in the intermediate support placement determination step in S21 are installed. Furthermore, it is preferable to arrange the overhead lines at the same time as the support 1 and the intermediate supports 8a, 8b are installed. Since the distance between the overhead lines and the number of overhead lines are determined in the overhead line condition determination step S22, the erection work and the overhead line routing work can be carried out simultaneously. In addition, position data for all of the temporary installation positions determined in the tentative post position determination step S13, or position data for all of the installation positions determined in the post position determination step S16, and further position data for all of the intermediate posts 8a, 8b determined in the intermediate post placement determination step S21 are stored, and in the post installation step S23, the electric fence installation device is guided based on this position data, thereby reducing the workload and achieving automation without human labor. Furthermore, since the soil measuring device is equipped with a ground surface height measuring means for measuring the ground surface height, it becomes possible to measure the ground surface height at the same time as measuring the soil hardness, and by using the measured ground surface height to determine the concave portion 5y or the convex portion 5z, the intermediate supports 8a, 8b can be appropriately positioned to reliably prevent the target animal 3 from entering or escaping. In this embodiment, a method for installing an electric fence has been described, but the present invention can also be applied to a method for installing posts used for electric fences, etc., by using the step of tentatively determining the post position (S13), the step of measuring soil hardness (S14), the step of determining the erection position (S15), the step of determining the post position (S16), and the step of installing the post (S23). [Industrial Applicability]
[0028] The electric fence installation method of the present invention is suitable for electric fences in pastures and electric fences used to protect against pests. [Explanation of symbols]
[0029] 1, 1a, 1b, 1c, 1d posts 2. Overhead Lines 3. Target animals 4. Guardian Area 5, 5a, 5b, 5c, 5d Ground surface 5y recess 5z Convex 6x, 6y, 6z Virtual overhead lines 7x, 7y, 7z lines 8a, 8b intermediate support 9, 9a, 9b, 9c, 9d, 9e overhead lines H Minimum height above ground
Claims
1. A method for installing an electric fence that includes a plurality of posts and a wire between each of the posts to prevent the intrusion or escape of a target animal, comprising: a protection area setting step for setting a protection area for the target animal; a boundary line determination step for determining a boundary line generated by the guardianship area; a tentative support position determination step for determining a tentative support position based on the boundary line and a line curvature of the boundary line; a soil hardness measuring step of measuring soil hardness at the temporary installation position using a soil measuring device that measures the soil hardness; a step of comparing the soil hardness measured in the step of measuring soil hardness with a preset soil hardness and determining whether the soil hardness is suitable as a position for erecting the pole; a pillar position determination step of determining the temporary erection positions as the erection positions when it is determined that all of the pillars are suitable in the erection position determination step; a post installation step of installing the post at the erection position determined in the post position determination step; having In the tentative support position determination step, an inflection point of the boundary line is set as the tentative installation position, and if the line curvature between two adjacent inflection points on the boundary line is equal to or smaller than a predetermined value, the boundary line is determined as the tentative installation position; If the erection position determination step determines that the erection position is unsuitable, the post position tentative decision step determines a new temporary erection position that is shifted toward the guard area side from the already determined temporary erection position, measures the soil hardness at the new temporary erection position using the soil measuring device, and determines the suitability of the new measured soil hardness in the erection position determination step. The soil hardness measurement step and the erection position determination step are repeated until the erection position determination step determines that the new soil hardness is suitable. A method for installing an electric fence.
2. The set soil hardness includes a first set soil hardness and a second set soil hardness that is higher than the first set soil hardness, In the erection position determination step, when the soil hardness of the temporary erection position is equal to or higher than the first set soil hardness and equal to or lower than the second set soil hardness, the temporary erection position is determined to be suitable as the erection position.
2. The method for installing an electric fence according to claim 1 .
3. The new temporary installation position is set closer to the guard area than the temporary installation position that was determined to be inappropriate.
3. A method for installing an electric fence as claimed in claim 1 or 2.
4. A target animal determination step of determining the target animal; a minimum overhead line height determination step for determining a minimum ground surface height from the ground surface to the overhead line provided at the lowest level based on the target animal determined in the target animal determination step; a height difference determination step for determining whether a concave portion exceeding the minimum height on the ground surface or a convex portion equal to or larger than the virtual overhead line connecting the minimum height on the ground surface of each of the adjacent pillars exists between the pillars at the erection positions determined in the pillar position determination step; an intermediate support arrangement determination step for determining, if the concave portion or the convex portion is present between the supports in the height difference determination step, to arrange an intermediate support between the supports; have A method for installing an electric fence according to any one of claims 1 to 3.
5. and a line condition determination step of determining a line distance and a line number of layers according to the target animal determined in the target animal determination step.
5. The method for installing an electric fence according to claim 4.
6. The soil measuring device includes a ground surface height measuring means for measuring a ground surface height, a ground surface height measuring step of measuring the ground surface height of the erected position and the ground surface height of the ground surface between the supports by the ground surface height measuring means; In the elevation difference determination step, the concave portion or the convex portion is determined using the ground surface height measured in the ground surface height measurement step.
5. The method for installing an electric fence according to claim 4.
7. A method for installing a support, comprising the steps of: A protection area setting step for setting a protection area for a target animal; a boundary line determination step for determining a boundary line generated by the guardianship area; a tentative support position determination step for determining a tentative support position based on the boundary line and a line curvature of the boundary line; a soil hardness measuring step of measuring soil hardness at the temporary installation position using a soil measuring device that measures the soil hardness; a step of comparing the soil hardness measured in the step of measuring soil hardness with a preset soil hardness and determining whether the soil hardness is suitable as a position for erecting the pole; a pillar position determination step of determining the temporary erection position as the erection position when the erection position determination step determines that the pillar is suitable; a post installation step of installing the post at the erection position determined in the post position determination step; having In the tentative support position determination step, an inflection point of the boundary line is set as the tentative installation position, and if the line curvature between two adjacent inflection points on the boundary line is equal to or smaller than a predetermined value, the boundary line is determined as the tentative installation position; If the erection position determination step determines that the erection position is unsuitable, the post position tentative decision step determines a new temporary erection position that is shifted toward the guard area side from the already determined temporary erection position, measures the soil hardness at the new temporary erection position using the soil measuring device, and determines the suitability of the new measured soil hardness in the erection position determination step. The soil hardness measurement step and the erection position determination step are repeated until the erection position determination step determines that the new soil hardness is suitable. A method for installing a support, comprising the steps of:
Citation Information
Patent Citations
Electric type pasture fence
JP1986031031A
Earth auger
JP1989290891A
Wire-entangled fence laying device
JP1999287057A
Electric fence for preventing damages due to beasts
JP2008079521A
Post containing electric pasture instrument for electric fence, and electric pasture unit for the electric fence
JP2009022246A