Tunnel construction management method

The 3D surveying system with a laser scanner and total station addresses the challenge of managing tunnel deformation in real-time, facilitating the selection of optimal construction methods for mountain tunnels, enhancing safety and efficiency.

JP7623232B2Active Publication Date: 2025-01-28SHIMIZU CORP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
JP2021103770
Authority / Receiving Office
JP · JP
Patent Type
Patents
Current Assignee / Owner
Filing Date
2021-06-23
Publication Date
2025-01-28
Estimated Expiration
2041-06-23

AI Technical Summary

Technical Problem

Existing tunnel construction methods struggle to accurately and efficiently manage tunnel deformation behavior in real-time, particularly in mountainous terrain with low-intensity and unpredictable ground conditions, leading to challenges in selecting optimal excavation and support structures.

Method used

A tunnel construction management method utilizing a 3D surveying system with a laser scanner and total station to perform multiple measurements, calculate deformation behavior, and display construction methods in real-time based on set thresholds, enabling immediate selection of appropriate construction strategies.

Benefits of technology

Enables real-time grasping of tunnel deformation and allows for the selection of optimal construction methods, reducing the time, effort, and cost associated with traditional measurement methods while ensuring safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 0007623232000006
    Figure 0007623232000006
  • Figure 0007623232000007
    Figure 0007623232000007
  • Figure 0007623232000008
    Figure 0007623232000008
Patent Text Reader

Abstract

To provide a tunnel construction management method capable of selecting, in real time, a construction method corresponding to the properties of excavated ground and tunnel deformation behavior in the ground.SOLUTION: A tunnel construction management method comprises the steps of: performing a measurement of the three-dimensional coordinates of a plurality of measuring points on a construction surface after tunnel excavation at least twice at different times; calculating the deformation behavior of the tunnel based on a difference in data obtained in the measurement; superimposing a display image corresponding to a threshold value set for the deformation behavior on the three-dimensional image of the tunnel and displaying the image; and displaying a construction method according to the threshold value of the deformation behavior.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to a tunnel construction management method for selecting an appropriate construction method in tunnel excavation. [Background technology]

[0002] When constructing a tunnel, surveying is carried out at each designated excavation stage to ensure that the excavation is being carried out as planned. At tunnel construction sites, where construction is being carried out on constantly changing ground, it is important to collect on-site information as quickly as possible through accurate surveying and ground observation, and to manage the construction so that appropriate measures can be taken.

[0003] For example, in the New Austrian Tunneling Method (NATM) used to excavate mountain tunnels, the natural ground is managed by a method called measurement technique A in order to ensure the stability of the natural ground around the tunnel and to perform appropriate construction according to the natural ground properties. In measurement technique A, for example, the natural ground is measured over time and the deformation behavior of the tunnel is managed. Measurement technique A is used to confirm and evaluate the characteristics of the deformation behavior of the tunnel and to determine the next construction method to be used. The cross sections to be measured for measurement technique A are provided at intervals of 10 to 30 m in the direction of tunnel excavation according to the natural ground properties.

[0004] As the tunnel is excavated and the face is formed, the initial values ​​of the measurement points are measured using a 3D surveying device capable of automatic 3D measurement, and then the measurement points are automatically measured every 12 to 24 hours, and the incremental displacement at the measurement points is automatically recorded. Basically, measurements are taken at five measurement points per cross section. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2008-298432 A [Patent Document 2] JP 2014-2027 A [Patent Document 3] JP 2020-133118 A [Patent Document 4] JP 2020-172784 A Summary of the Invention [Problem to be solved by the invention]

[0006] As mentioned above, the cross sections to be measured by the measurement work A are provided at predetermined intervals in accordance with the natural ground properties. Measurements are taken over time at the measurement points at the predetermined locations, and the coordinate displacements at these measurement points are quantified and managed as the tunnel deformation behavior due to the tunnel excavation.

[0007] Low-strength, discontinuous plastic flow ground can cause large deformation during tunnel construction. In tunnel construction in such ground, even if surveying is performed to grasp the deformation of the ground based on standard measurement method A, it is difficult to accurately grasp and evaluate the displacement behavior of the tunnel. Therefore, with standard measurement method A, it is not possible to determine in real time which excavation method or tunnel support structure is optimal for the ground, and there is a risk that re-construction will be required.

[0008] Furthermore, increasing the number of measurement points and the number of measurement cross sections for measurement work A requires a great deal of time, labor, and cost for the measurement work, so there are limitations to predicting and evaluating the displacement behavior on the excavation surface. According to the inventions described in Patent Documents 1 to 4, it is described that the tunnel excavation surface is measured and the measurement results are displayed in real time, but there has been no proposal yet to select a construction method that corresponds to the tunnel deformation behavior.

[0009] An object of the present invention is to provide a tunnel construction management method capable of selecting, in real time, a construction method that corresponds to the excavated ground properties and the tunnel deformation behavior in the ground. [Means for solving the problem]

[0010] The present invention is a tunnel construction management method comprising the steps of: conducting at least two surveys at different times of the three-dimensional coordinates of a plurality of measurement points on the construction surface after excavation of a tunnel; calculating the deformation behavior of the tunnel based on the difference in data obtained in the surveys; superimposing a display image corresponding to a threshold value set for the deformation behavior on a three-dimensional image of the tunnel; and displaying a construction method corresponding to the threshold value for the deformation behavior.

[0011] According to the present invention, by performing three-dimensional surveying of the construction surface after tunnel excavation over time, it is possible to grasp the deformation behavior of the tunnel in real time and to select a construction method according to the deformation behavior.

[0012] In addition, the construction surface of the present invention may include an excavation surface of the natural ground and a surface of concrete constructed on the excavation surface, and the process of calculating the deformation behavior of the tunnel may include a process of measuring a plurality of three-dimensional coordinates on the construction surface corresponding to a virtual unit plane set based on a predetermined circumferential length and a predetermined extension length of the tunnel, a process of calculating an average value of the plurality of three-dimensional coordinates, and a process of calculating the difference in the average value over time.

[0013] According to the present invention, by using surveying equipment such as a laser scanner to calculate deformation of the excavated surface of a tunnel and the surface of concrete applied to the excavated surface in real time, changes in the tunnel can be grasped at an early stage.

[0014] Furthermore, the threshold value of the present invention may be set in stages according to the magnitude of the difference.

[0015] According to the present invention, by setting a construction method according to a threshold value, it is possible to display an appropriate construction method according to real-time deformation of the tunnel.

[0016] In addition, the present invention may select the construction method displayed according to the state of the deformation behavior, and apply the construction method to the tunnel.

[0017] According to the present invention, the manager can select the displayed construction method and carry out construction on the tunnel, thereby enabling construction management that can quickly respond to changes in the tunnel. Effect of the Invention

[0018] According to the present invention, a construction method that corresponds to the excavated ground properties and the tunnel deformation behavior in the ground can be selected in real time. [Brief description of the drawings]

[0019] [Figure 1] FIG. 2 is a diagram showing the configuration of a completed form survey management system used in a tunnel construction management method. [Diagram 2] FIG. 1 is a diagram showing an overview of a surveying method inside a tunnel. [Diagram 3] FIG. 2 is a block diagram showing a configuration of a management device. [Figure 4] 4 is a cross-sectional view taken along the tunnel axis direction, showing the configuration of the tunnel. FIG. [Diagram 5] FIG. 2 is a radial cross-sectional view showing the configuration of the tunnel. [Figure 6] FIG. 1 is a diagram showing a method for surveying a tunnel. [Figure 7] FIG. 1 is a diagram showing a method for time-series surveying of a tunnel. [Figure 8] FIG. 1 illustrates a method for calculating the thickness of concrete. [Figure 9] This is a diagram explaining the early closure of a tunnel and subsequent surveying. [Figure 10] 1 is a flowchart showing a process flow of a tunnel construction management method. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0020] Hereinafter, an embodiment of a tunnel construction management method according to the present invention will be described with reference to the drawings. The tunnel construction management method uses a management system capable of three-dimensionally measuring the shape inside a tunnel. First, the management system will be described.

[0021] As shown in Figure 1, the completed form construction management system 1 used in the tunnel construction management method comprises a laser scanner 10 (three-dimensional scanner) that surveys the three-dimensional shape inside the tunnel, a total station 30 that surveys the three-dimensional coordinates inside the tunnel, and a management device 20 that manages the construction of the tunnel based on the survey data from the laser scanner 10 and the total station 30.

[0022] The laser scanner 10 includes, for example, a laser sensor 11 that irradiates laser light and receives a portion of the reflected light, and a main body 12 that rotatably supports and rotates the laser sensor 11. The laser sensor 11 includes a laser light emitter (not shown) and a light receiver (not shown). The laser sensor 11 irradiates a target object with laser light in a planar manner while rotating, for example, in the vertical and horizontal directions, measures the time it takes to receive a portion of the reflected light from the target object, and generates point cloud data.

[0023] The laser sensor 11 is supported by the main body 12 so as to be rotatable about the y-axis (tilt direction) and is driven to rotate. This allows the laser sensor 11 to scan the target in the up and down directions. The main body 12 is placed on a tripod S. The main body 12 is driven to rotate about the z-axis relative to the tripod S. This allows the laser sensor 11 to be supported so as to be rotatable about the z-axis (horizontal direction) and is driven to rotate.

[0024] In this way, the laser scanner 10 can three-dimensionally scan a predetermined area of ​​the object, and can obtain data on the surface shape of the object in the predetermined area. The total station 30 measures the three-dimensional survey coordinates of multiple side points in the tunnel T. The total station 30 outputs the multiple survey coordinate data to the laser scanner 10. The laser scanner 10 measures the three-dimensional shape of the excavation surface based on the measurement points based on the survey coordinates, based on the multiple survey coordinate data.

[0025] As shown in Fig. 2, the laser scanner 10 surveys the excavation surface of a tunnel and the surface of the face mirror when excavation is completed, for example, and obtains data on the surface shape. The laser scanner 10 outputs the measured point cloud data to the management device 20. The laser scanner 10 surveys the concrete sprayed surface after concrete is sprayed onto the excavation surface for the first time, for example, and obtains data on the surface shape. The laser scanner 10 also surveys the surface shape of the concrete sprayed surface after shoring is erected and concrete is sprayed for the second time to cover the surface of the shoring, for example, and obtains data on the surface shape.

[0026] The management device 20 is realized by a terminal device such as a personal computer (PC), a tablet terminal device, a smartphone, etc. The management device 20 is communicably connected to the laser sensor 11 by wire or wirelessly.

[0027] As shown in Figure 3, the management device 20 includes a calculation unit 21 that calculates the three-dimensional shape of the object based on data acquired from the laser sensor 11, a display unit 22 that displays various information generated based on the calculation results of the calculation unit 21, and a memory unit 23 that stores various data.

[0028] The calculation unit 21 is realized by, for example, a hardware processor such as a CPU (Central Processing Unit) executing a program (software). Some or all of these components may be realized by hardware (including circuitry) such as an LSI (Large Scale Integration), an ASIC (Application Specific Integrated Circuit), an FPGA (Field-Programmable Gate Array), or a GPU (Graphics Processing Unit), or may be realized by a combination of software and hardware. The program may be stored in a storage device such as an HDD (Hard Disk Drive) or a flash memory in advance, or may be stored in a removable storage medium such as a DVD or a CD-ROM, and installed by mounting the storage medium in a drive device. In addition, the computer program may be distributed to a computer via a communication line, and the computer that receives the distribution may execute the program.

[0029] The calculation unit 21 acquires measurement data obtained by three-dimensionally scanning the target object by the laser sensor 11. The calculation unit 21 generates image data of the three-dimensional shape of the target object based on the acquired data. A detailed explanation of the measurement principle by the calculation unit 21 is described in Patent Document 1. For example, the calculation unit 21 generates image data and numerical data of the three-dimensional shape of the target object, and also generates management information by comparing design data and measurement data stored in the storage unit 23. The calculation unit 21 controls the display unit 22 to display the display contents of the generated image data, etc.

[0030] The display unit 22 displays management information and an image of the three-dimensional shape inside the tunnel generated by the calculation unit 21. The display unit 22 is realized by a display device such as a liquid crystal display, an organic EL display, or an LED display.

[0031] The storage unit 23 records the survey data measured by the laser sensor 11, the image data generated by the calculation unit, the design data including the design items of the tunnel, etc. The storage unit 23 is a storage device such as a HDD, a flash memory, a RAM (Random Access Memory), or a ROM (Read Only Memory).

[0032] Next, a tunnel construction management method for managing the excavation of a tunnel will be described. The tunnel construction management method is applied, for example, to the construction of a mountain tunnel. In the construction of a mountain tunnel, the natural ground is blasted and excavated using machinery or human power, and then a support structure is constructed to support the natural ground, and the natural ground is excavated while maintaining an internal space, to construct the tunnel.

[0033] According to this construction method, construction is carried out on the assumption that the ground near the face will be self-sustaining from the time of excavation to the completion of the construction of the support. Therefore, construction management of mountain tunnels requires careful consideration in advance and establishment of construction procedures after excavation to prevent the collapse of the ground.

[0034] As shown in Fig. 4, the tunnel T to be constructed has an excavated face T1 at the forefront. Behind the excavation direction of the face T1, concrete is sprayed onto the excavated face to form a layer of sprayed concrete T2.

[0035] As shown in FIG. 5, in the tunnel T, a layer of shotcrete T2 is formed on the surface of the excavation surface K. The layer of shotcrete T2 includes, for example, a first shotcrete sprayed on the natural ground, a support structure assembled on the surface of the first shotcrete, and a second shotcrete sprayed on the surface of the support structure. Next, a layer of lining concrete T3 is formed to cover the surface of the layer of shotcrete T2. In the tunnel excavation of a low-strength natural ground, a layer of invert shotcrete T4 is formed on the surface of the excavation surface K at the bottom of the tunnel T, and then a layer of invert concrete T5 is formed to cover the surface of the layer of invert shotcrete T4. In addition, in the tunnel T, a plurality of rock bolts B are driven radially into the natural ground.

[0036] At the top of tunnel T, multiple steel pipe forepillings P are installed at a specified angle upward from the surface of the ground toward the tunnel axis direction using an auxiliary construction method. The steel pipe forepillings P are arranged along the outer periphery of the tunnel. Silica resin or the like is pressure-injected into the steel pipe forepillings P to ensure the independence of the excavated surface up to the support structure.

[0037] As shown in Fig. 6 and Fig. 7, in the tunnel T, the surface shape of the sprayed concrete T2 is three-dimensionally constructed by the construction management system 1 at the face of the excavation surface that appears in the construction cycle. Based on the difference between the survey data of the surface shape of the current sprayed concrete T2 and the survey data of the surface shape of the past sprayed concrete T2, the management device 20 calculates (1) the initial deformation speed, (2) the tunnel deformation at the sprayed surface finished form survey position, and (3) the current excavation incremental deformation, and (4) displays the tunnel excavation influence of the early closing incremental deformation and the tunnel deformation behavior characteristics in a color tone display that is colored based on a threshold value on the display unit to visualize them, and selects the next construction corresponding to the tunnel deformation behavior. Below, a specific tunnel construction management method based on the construction management system 1 will be described.

[0038] The construction management system 1 performs three-dimensional as-built surveying at the face T1 for each construction cycle of the tunnel T. The laser scanner 10 is located at the center of the tunnel and one excavation length rearward from the face T1. The total station 30 is located rearward of the laser scanner 10. The total station 30 measures three-dimensional surveying coordinates of multiple measurement points based on targets set at those measurement points. The targets G measured by the total station 30 are set at three points within a maximum range of 7 m from the laser scanner 10 and are automatically recognized during three-dimensional surveying by the laser scanner 10. The total station 30 transmits the three-dimensional surveying coordinates of the measurement points to the laser scanner 10.

[0039] When tunnel T is a two-lane road, the laser scanner 10 performs 3D surveying of the tunnel face T1 and a range of 20 m behind itself (2D: D is the excavation width). The laser scanner 10 performs surveying at a distance of 10 m with measurement points spaced 12.5 mm apart, and performs 3D as-built surveying of the tunnel face T1 with measurement points spaced approximately 7 mm apart on the side of the tunnel around the laser scanner 10.

[0040] The management device 20 calculates the following values ​​as deformation behavior of the tunnel T based on the completed form survey using the laser scanner 10: (1) initial deformation speed, (2) tunnel deformation at the sprayed surface completed form survey position, (3) current excavation incremental deformation, and (4) early closure incremental displacement. For example, the management device 20 calculates the difference between the point cloud data of the measurement point surveyed this time and the point cloud data of the measurement point surveyed previously based on a concrete thickness calculation method described below. The management device 20 generates a display image based on the calculation results, and displays the display image in a color-coded manner based on a threshold on the display unit 22. The concrete thickness is calculated based on the following method.

[0041] As shown in Figure 8, a rectangular virtual unit plane of a specified length (10 cm) in the circumferential direction by a specified length (10 cm) in the extension direction is defined in the tunnel construction area. The virtual unit plane is set on the sprayed surface in the design. 3D surveying is performed using a laser scanner with the virtual unit plane as the reference. The surveying is performed at least twice, once on the excavated surface and once on the surface after the sprayed concrete has been applied. In addition, 3D surveying is performed more than twice at different times over the same position on the construction surface after excavation and on the concrete surface, as described below.

[0042] The surface of the sprayed concrete has unevenness of about 5 to 10 mm. In contrast, the ground on the excavated surface has unevenness of a similar degree, although it differs depending on the geology. A laser scanner is used to survey the excavated surface before the sprayed concrete is applied and the surface of the concrete after application in a virtual unit plane, at grid points spaced 5 to 12.5 mm apart. The survey results in point cloud data that is a collection of 3D coordinates of the surface of the concrete before and after the sprayed concrete is applied in the virtual unit plane. The thickness of the concrete is calculated based on the point cloud data of the excavated surface and the concrete surface obtained by the survey.

[0043] The thickness of the sprayed concrete is small compared to the distance from the laser scanner 10 to the survey surface, so it is calculated by averaging the point cloud data in the virtual unit plane. An approximation of the thickness of the concrete at the center point of the virtual unit plane is obtained by calculating the difference between the average value of the point cloud data in the virtual unit plane and the average value of the point cloud data on the surface of the sprayed concrete. The management device 20 generates an image of the point cloud data of the concrete surface obtained by the surveying in three-dimensional coordinates and displays it on the display unit 22. At this time, the management device 20 displays the point cloud data of the concrete surface by changing the color tone according to the thickness threshold value.

[0044] The above method describes the thickness of sprayed concrete, but the thickness of the covering concrete and the thickness of the invert concrete can also be calculated using a similar method and displayed on the display unit 22 by changing the color tone.

[0045] Next, a method for calculating the initial deformation speed of the tunnel T will be described. The management device 20 uses point cloud data P(i-1) of the concrete sprayed surface at measurement point (i-1) measured last time in the excavation cycle and point cloud data P(i) at measurement point (i) measured this time at the same position as last time to calculate the average value of the distance from the center of the virtual unit plane, and calculates the surface position in the previous survey and the surface position in the current survey.

[0046] The management device 20 calculates the initial deformation speed based on the difference between the surface position in the previous survey and the surface position in the current survey. The management device 20 generates an image in which the calculated initial deformation speed is plotted on the point cloud data of the concrete surface, and displays it on the display unit 22. For example, the management device 20 displays the initial deformation speed by changing the color tone according to a preset threshold value. The management device 20 displays on the display unit 22 the response to the next construction set in correspondence with the threshold value as shown in Table 1. [Table 1]

[0047] Next, a method for calculating the tunnel deformation at the sprayed surface completed survey position will be described. The management device 20 calculates the average value of the distances from the center of the virtual unit plane using point cloud data P(i-1, i-2, i-3, . . .) acquired at the sprayed surface of the concrete at the measurement points (i-1, i-2, i-3, . . .) surveyed up to the previous time in the excavation cycle and point cloud data P(i) acquired at the same position (i-1, i-2, i-3, . . .) surveyed up to the previous time. The management device 20 calculates the tunnel deformation at the sprayed surface completed survey position based on the difference between the respective average values. For example, the management device 20 changes the color tone of the tunnel deformation at the sprayed surface completed survey position according to a preset threshold value and displays it. The management device 20 displays the response of the next construction set corresponding to the threshold value on the display unit 22 as shown in Table 2. [Table 2]

[0048] Next, a method for calculating the current tunnel excavation incremental deformation will be described. The management device 20 calculates the average value of the distance away from the center of the virtual unit plane using point cloud data P(i-1) acquired at the previously surveyed measurement point (i-1) and point cloud data P(i) rearward from the same position as the previous time of the currently surveyed measurement point (i). The management device 20 calculates the current excavation incremental deformation based on the difference between the average values ​​of the distances. The management device 20 displays the current excavation incremental deformation by changing the color tone according to a preset threshold value. The management device 20 displays the construction method set corresponding to the threshold value on the display unit 22 as shown in Table 3. [Table 3]

[0049] Next, a method for calculating the early closure incremental deformation will be described. The management device 20 calculates the average value of the distance from the center of the virtual unit plane using point cloud data P(2) of the measurement point (aa) in the entire cross section of the early closed concrete sprayed surface and point cloud data P(1) of the measurement point in the entire cross section before early closure. The management device 20 calculates the early closure incremental deformation based on the difference between the average values ​​of the respective distances. The management device 20 displays the early closure incremental deformation by changing the color tone according to a preset threshold value as shown in Table 4. [Table 4] The management device 20 displays on the display unit 22 the construction method set in accordance with the threshold value.

[0050] As shown in Fig. 9, in the subsequent tunnel excavation construction, the incremental deformation due to tunnel excavation will be confirmed and evaluated as the current excavation incremental deformation mentioned above, regardless of whether early closure occurs or not (Table 4). [Table 5]

[0051] Next, the process flow of the tunnel construction management method will be explained. The construction surface that is the target of 3D surveying by the laser scanner 10 includes the excavation surface of the natural ground and the surface of the concrete applied to the excavation surface. The concrete surface includes the surface of the concrete applied to the excavation surface, such as the surface of the shotcrete, the surface of the lining concrete, and the surface of the invert concrete.

[0052] FIG. 10 shows the flow of each process of the tunnel construction management method. Using a laser scanner 10, the three-dimensional coordinates of a plurality of measurement points on the construction surface after excavation of the tunnel are measured at least twice at different times (step S10). In this measurement, the management device 20 calculates the average value of a plurality of three-dimensional coordinates measured on the construction surface corresponding to a virtual unit plane set based on a predetermined length in the circumferential direction and a predetermined length in the extension direction of the tunnel T, and further calculates the difference in the average value over time to calculate the concrete thickness and the amount of movement of the concrete surface over time. That is, the management device 20 calculates the deformation behavior of the tunnel T based on the difference in the data acquired in the measurement (step S12).

[0053] Next, the management device 20 generates a three-dimensional image of the tunnel, and overlays and displays a display image using colors corresponding to thresholds that are set in stages according to the magnitude of the difference in data on the three-dimensional image (step S14). The administrator can grasp the deformation behavior of the tunnel T in real time based on the image displayed on the display unit 22. Next, the management device 20 displays a construction method corresponding to the threshold value of the deformation behavior (step S16). The administrator selects the construction method displayed on the display unit 22 according to the state of the deformation behavior, and carries out construction on the tunnel T using the selected construction method (step S18).

[0054] By selecting a construction method displayed on the display unit 22, the manager can quickly carry out construction using an appropriate construction method that corresponds to the real-time deformation behavior of the tunnel. The above steps are performed for each predetermined tunnel excavation cycle.

[0055] As described above, according to the tunnel construction management method, the management device 20 can visualize and display in real time evaluation items related to the deformation of the ground based on three-dimensional surveying using a laser scanner. Also, according to the tunnel construction management method, the management device 20 can display in real time construction methods as measures corresponding to the state of deformation of the ground.

[0056] According to the tunnel construction management method, the management device 20 can display the tunnel excavation impact and tunnel deformation behavior characteristics (1) initial deformation speed, (2) tunnel deformation at the sprayed surface finished form survey position, (3) current excavation incremental deformation, and (4) early closure incremental deformation threshold in an image visualized using color tones, as well as display a construction method as a countermeasure. According to the tunnel construction management method, the next construction method to be performed in response to the natural ground properties and tunnel deformation behavior can be selected in real time based on the display content by the management device 20. According to the tunnel construction management method, the construction corresponding to the tunnel deformation behavior based on the survey results can be appropriately selected based on the display content by the management device 20.

[0057] Although one embodiment of the present invention has been described above, the present invention is not limited to the above embodiment, and can be modified as appropriate without departing from the spirit of the present invention. For example, the tunnel construction management method has been exemplified by the construction of a mountain tunnel, but it may be applied to the construction of tunnels other than mountain tunnels. Furthermore, the surveying method exemplified in the above embodiment is only an example, and other surveying instruments and methods may be used as long as similar results can be obtained. [Explanation of symbols]

[0058] 1 Construction management system 10. Laser Scanner 11 Laser Sensor 12 Main body 20 Management device 21 Arithmetic section 22 Display section 23 Memory section 30 Total Station B Rock bolt G Target K Excavation surface P Steel pipe forepiling T-Tunnel T1 Face T2 Shotcrete T3 Lining concrete T4 Invert Shotcrete T5 Invert Concrete

Claims

1. A step of measuring three-dimensional coordinates of a plurality of measurement points on a construction surface after excavation of a tunnel at least twice at different times; calculating a deformation behavior of the tunnel based on a difference between the data acquired in the survey; A step of superimposing a display image corresponding to a threshold value set for the deformation behavior on the three-dimensional image of the tunnel and displaying the display image; and displaying a construction method according to the state of the deformation behavior, As the characteristics of the deformation behavior, threshold values ​​are set for the initial deformation speed, the tunnel deformation at the position of the sprayed surface completed form survey, the current tunnel excavation incremental deformation, and the early closing incremental deformation, and the color tone is changed according to the threshold value. Tunnel construction management methods.

2. The construction surface includes an excavation surface of the natural ground and a surface of concrete constructed on the excavation surface, The step of calculating the deformation behavior of the tunnel includes: A step of measuring a plurality of three-dimensional coordinates on the construction surface corresponding to a virtual unit plane set based on a predetermined length in a circumferential direction and a predetermined length in an extension direction of the tunnel; calculating an average value of the plurality of three-dimensional coordinates; and calculating a difference in the average value over time. A tunnel construction management method according to claim 1.

3. The threshold value is set in stages according to the magnitude of the difference. A tunnel construction management method according to claim 2.

4. The construction method displayed according to the state of the deformation behavior is selected, and the construction method is applied to the tunnel. A tunnel construction management method according to any one of claims 1 to 3.

Citation Information

Patent Citations

  • System for integrated control of computerized construction of tunnel

    JP2003056277A

  • Method for displaying cross section measurement result and its program

    JP2005083893A

  • Display method of tunnel wall surface displacement, and program thereof

    JP2008298432A

  • Method of measuring displacement of space within tunnel

    JP2014002027A

  • Tunnel construction management method

    JP2020133118A