Block for constructing a port structure and method for constructing a port structure using the same
The block design with protrusions and perforated walls addresses structural instability and wave energy dissipation issues in port construction, ensuring stable harbor structures by vertical wave energy dissipation and filler material compression.
Patent Information
- Application Number
- KR1020230067746
- Authority / Receiving Office
- KR · KR
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2023-05-25
- Publication Date
- 2026-11-06
- Estimated Expiration
- 2043-05-25
AI Technical Summary
Conventional port structure construction methods face challenges in maintaining structural stability under wave and earth pressures, and ineffective wave energy dissipation, particularly in interlocking block systems, leading to reduced stability and potential damage.
A block design with protrusions, perforated walls, and locking mechanisms that allow for vertical wave energy dissipation and stabilization through filler material compression, ensuring stable construction by suppressing movement between blocks.
Enhances structural stability and efficiently dissipates wave energy, reducing reflected waves and improving the calmness within the harbor by allowing seawater to flow vertically through the inlet, thus maintaining a stable construction state.
Smart Images

Figure 112023058246116-PAT00001_ABST
Abstract
Description
Technology Field
[0001] The present invention relates to a block for constructing a port structure and a method for constructing a port structure using the same. More specifically, the invention relates to a block for constructing a port structure and a method for constructing a port structure using the same, wherein the structural stability of the port structure can be enhanced by ensuring that the construction state is maintained stably even under continuous wave pressure or earth pressure, as movement between individual entities is suppressed by the filling of a filler material, and furthermore, waves approaching from the sea side in the constructed state flow into the water section through an inlet provided in each entity and flow vertically, thereby enabling efficient dissipation of wave energy. Background Technology
[0002] Ports are one of the marine facilities.
[0003] A port basically includes waterway facilities such as shipping lanes, outer facilities such as breakwaters, port transportation facilities such as roads, and mooring facilities such as quays, allowing for the entry and exit of vessels, boarding and disembarking of persons, loading, unloading, storage and handling of cargo, and marine recreational activities.
[0004] At this time, a quay, which is a mooring facility, is a wall structure that faces the sea direction of a dock installed to allow ships to safely dock and handle cargo and passengers, and is built for the boarding and disembarking of passenger ships and the loading and unloading of cargo. When the water depth in front is within 4.5m, it is called a wharf.
[0005] Here, harbor structures can be classified into gravity type, pier type, shelf type, steel sheet pile type, and floating pier, etc., depending on the structural type.
[0006] In addition, gravity structures can be classified into interlocking block type (Concrete Block Type), caisson type, and cellular block type depending on the structure used in the walls.
[0007] In this case, the caisson type is manufactured on land or at a floating dock and installed at a planned location by means of a marine crane or tugboat, and has the advantage of being highly economical when installed in deep water because the filling material inside the compartment can be replaced with cheaper materials than concrete, such as sand, crushed rubble, rubble, and steel slag.
[0008] However, since the caisson is a large concrete hull of typically 1,000 tons or more with a minimum size of B 20m × L 8m × H 15m, there was a problem that large marine equipment was required during the installation process, and if the caisson was not filled immediately after installation, it would deviate from the construction baseline even under wave conditions smaller than the wave.
[0009] Furthermore, the cell block method involves pre-fabricating box-shaped hollow blocks made of reinforced concrete known as "cellulars" on land, placing them on foundation rubble, filling the inside of the cells with rubble, and then pouring cap concrete to complete the structure; this method has the advantage of low construction costs.
[0010] However, since box-shaped hollow blocks have open top and bottom surfaces, the construction process of filling the cells with materials such as rubble after installation involves a multi-stage construction process that is very complex and requires long offshore working hours, leading to vulnerabilities in construction management and a high risk of safety accidents.
[0011] For this reason, the interlocking block system is recently gaining attention for the construction of gravity-type structures.
[0012] However, conventional interlocking blocks, such as those disclosed in Korean Registered Patent No. 10-1487131, had a problem in that the structural stability of port structures was reduced because the connection between individual blocks could be weak during the construction process. In particular, there was a problem in that the energy dissipation of seawater, such as waves, flowing from the sea side to the land side in the constructed state did not meet expectations, leading to reduced structural stability or damage.
[0013] For the reasons mentioned above, attempts are being made in the relevant field to develop a block for constructing port structures and a method for constructing port structures using the same, which not only enhances the structural stability of port structures by maintaining a stable construction state but also facilitates the dissipation of wave energy from the sea side during construction; however, satisfactory results have not been obtained to date. Prior art literature
[0014] Republic of Korea Registered Patent No. 10-1487131 The problem to be solved
[0015] The present invention is proposed to resolve the problems of the conventional technology described above, and aims to provide a block for constructing a port structure and a method for constructing a port structure using the same, which not only enhances the structural stability of a port structure by suppressing movement between individual entities through the filling of filler material so that the constructed state is stably maintained even under continuous wave pressure or earth pressure, but also enables efficient dissipation of wave energy by allowing waves approaching from the sea side to flow vertically through the inlet provided in each individual entity into the water section. means of solving the problem
[0016] To achieve the above objective, the present invention,
[0017] A block for constructing a harbor structure is proposed, comprising: a main body having a preset length, width, and height; a first protrusion formed to protrude from one side and the other side of one end of the main body in the longitudinal direction; and a second protrusion formed to protrude from one side and the other side of the other end of the main body in the longitudinal direction; wherein the main body comprises: an inlet portion facing from the front of the end of the main body in the longitudinal direction toward the rear; and a water flow portion extending to the rear in the longitudinal direction in communication with the inlet portion, wherein a perforated wall is formed with a completely open bottom and a partially open top, and wherein seawater flowing from the sea side flows into the water flow portion through the inlet portion, and the seawater flowing into the water flow portion flows up and down through the open portion of the perforated wall.
[0018] The above main body includes: a locking projection formed protruding from the upper surface of one end in the longitudinal direction; and a locking groove formed recessed from the lower surface of one end in the longitudinal direction.
[0019] The above main body may further include at least one passage that is formed to be connected in the longitudinal direction to either one end in the longitudinal direction or the other end, and communicates with the above-mentioned fluid portion.
[0020] Piping leading to the outside may be connected to the above passage.
[0021] The first and second protrusions include a projection extending from the top to the bottom of one side; and a groove extending from the top to the bottom of the other side.
[0022] The projection and groove of the first projection are located in the opposite direction to the projection and groove of the second projection.
[0023] The above perforated wall may have a perforation rate of 5 to 30%.
[0025] In addition, to achieve the above objectives, the present invention,
[0026] A method for constructing a port structure using blocks for constructing a port structure is proposed, comprising: a mound installation step of reinforcing the seabed ground serving as a seating point for blocks for constructing a port structure and then installing a rubble mound; a base member arrangement step of arranging base members, each having a retaining ledge formed at a certain height on an upper surface at one end in the longitudinal direction along the flattened upper surface of the rubble mound, such that one side of one base member is butted against another side of the base member; a block stacking step of forming multiple layers by repeating the arrangement such that one side of one block for constructing a port structure is butted against another side of the base member on the base member; a filler filling step of filling a filler material into each of the spaces between one block for constructing a port structure and another adjacent block stacked in the multiple layers; and a capping concrete arrangement step of placing capping concrete on top of the uppermost block for constructing a port structure.
[0027] In the above block stacking step, the bottommost block for constructing the port structure is connected to the base member by the locking groove of the main body engaging with the locking projection of the base member.
[0028] In the above block stacking step, each of the blocks for constructing the port structure is positioned so that its entrance faces the sea side.
[0029] In the block stacking step described above, the blocks for constructing the port structure in the even-numbered layers among the plurality of layers can form a left-right symmetrical shape with the blocks for constructing the port structure in the odd-numbered layers.
[0030] In the above-mentioned upper concrete placement step, the upper concrete is connected to the upper block for constructing the structure by the catch groove formed on the bottom surface of one end in the longitudinal direction of the upper concrete engaging with the catch projection formed on the upper surface of one end in the longitudinal direction of the main body of the upper block for constructing the port structure.
[0031] The present invention may further include a rear filling step of filling backfill gravel behind the blocks for constructing the port structure stacked in multiple layers; a mat laying step of laying a filter mat on the surface of the backfill gravel; and a pavement forming step of laying a pavement so as to form a horizontal plane with the upper concrete after filling the upper surface with landfill soil. Effects of the invention
[0032] The block for constructing a harbor structure according to the present invention has an inlet and a water flow section formed in the main body, so that seawater from the outside can flow into the water flow section through the inlet, and the seawater flowing into the water flow section can flow up and down through the open parts of the perforated wall, thereby facilitating the dissipation of wave energy, which reduces reflected waves, thereby improving the calmness within the harbor and enhancing the stability of the structure.
[0033] The block for constructing a port structure according to the present invention includes a first protrusion and a second protrusion provided at each of the longitudinal ends of the main body. By filling the space formed by the butting of one side of one and the other side of another with a filler material, restraint is achieved by the compressive resistance of the filler material, thereby suppressing the movement of one and the other. Consequently, the construction state can be stably maintained even under continuous wave pressure or earth pressure, thereby improving the structural stability of the port structure.
[0034] The block for constructing a port structure according to the present invention has a locking projection and a locking groove formed at one end of the longitudinal direction of the main body in the direction opposite to the direction in which wave pressure or earth pressure is applied. When wave pressure or earth pressure acts on the first protrusion of each main body forming a plurality of layers and the filler material filled between the main bodies is compressed in one direction, the resistance to the pressure applied to the filler material is exerted by the locking projection formed on the main body. Consequently, the main body is restrained by the compressive resistance of the filler material, and the filler material and the main body are roughly integrated, preventing slippage between the upper and lower layers. Therefore, the construction state can be maintained stably even under continuous wave pressure or earth pressure, thereby improving the structural stability of the port structure. Brief explanation of the drawing
[0035] FIG. 1 is a perspective view showing the external appearance of a block for constructing a harbor structure according to the present invention. FIG. 2 is a cross-sectional view of a block for constructing a harbor structure according to the present invention. FIG. 3 is a cross-sectional view in another direction of a block for constructing a harbor structure according to the present invention. FIG. 4 is a cross-sectional view of a block for constructing a harbor structure according to the present invention when a catch projection and a catch groove are formed with different lengths. FIG. 5 is an exemplary diagram showing a form in which a passage is formed in either the first protrusion or the second protrusion in a block for constructing a port structure according to the present invention. FIG. 6 is an example diagram showing a shape in which one side and the other side of a first protrusion and a second protrusion protrude with the same length in a block for constructing a structure according to the present invention. FIG. 7 is a schematic flowchart of a method for constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 8 is an example diagram showing the mound installation step in a method for constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 9 is an exemplary diagram showing the base member placement step in a method for constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 10 is an example diagram showing a block stacking step in a method for constructing a port structure using blocks for constructing a port structure according to the present invention. FIG. 11 is an exemplary diagram showing the filling step of a filler material in a method for constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 12 is an example diagram showing the upper concrete placement step in a method for constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 13 is a cross-sectional view of a port structure (breakwater) of one type completed by the method of constructing a port structure using a block for constructing a port structure according to the present invention. FIG. 14 is a cross-sectional view of another type of harbor structure (quay wall) completed by the method of constructing a harbor structure using a block for constructing a harbor structure according to the present invention. Specific details for implementing the invention
[0036] The present invention will be described in detail below with reference to the attached drawings.
[0038] As illustrated in FIG. 1, a block (A) for constructing a harbor structure according to the present invention comprises a main body (10); a first protrusion (20); and a second protrusion (30).
[0039] The main body (10) of the present invention is composed of a preset length, width, and height.
[0040] At this time, the main body (10) includes an inlet section (11) extending from the front of one end in the longitudinal direction toward the rear as shown in FIG. 2; and a water section (12) that is connected to the inlet section (11) and extends to the rear in the longitudinal direction, with a perforated wall (13) formed at the bottom that is completely open and at the top that is partially open, so that seawater coming from the sea side can flow into the water section (12) through the inlet section (11), and the seawater flowing into the water section (12) can flow up and down through the open part of the perforated wall (13) at the top of the water section (12).
[0041] Here, the perforated wall (13) may have a perforation ratio (=cross-sectional area of the open part / cross-sectional area of the perforated wall) of 5 to 30%.
[0042] And the perforated wall (13) can be formed in a slit shape as shown in FIG. 3.
[0043] Therefore, when the upper concrete (400) described below is installed on the upper outer side of the water flow section (12) and the circulation of seawater through the open area is restricted, a layer of compressed air can be formed on the upper inner side of the water flow section (12) by passing through the inlet section (11) when seawater rises inside the main body (10).
[0044] And the main body (10) includes a catch (14) protruding from the upper surface of one end of the longitudinal direction opposite to the compressive or earth pressure; and a catch groove (15) recessed from the lower surface of one end of the longitudinal direction below the catch (14). As the catch (14) formed in one is received in the catch groove (15) formed in the other, stacking can be performed without interference by the catch (14), and resistance to the pressure exerted on the filler (300) described below by the catch (14) in the stacked state can be exerted.
[0045] At this time, the length of the section forming the catch (14) and the length of the section forming the catch groove (15) may be formed to be the same, but are not limited thereto.
[0046] That is, the length of the section forming the catch (14) and the length of the section forming the catch groove (15) can be formed differently from each other as shown in FIG. 4, so that one of the main body (10) and the other can be stacked in a step shape, and thus can be easily constructed on an inclined surface, etc.
[0047] Additionally, the main body (10) is formed to be connected in the longitudinal direction to either one end or the other end as shown in FIG. 5, and further includes at least one passage (16) communicating with the water section (12), so that seawater flowing into the water section (12) can be discharged to the outside through the passage (16).
[0048] At this time, a pipe (not shown in the drawing) leading to the outside is connected to the passage (16), so that seawater discharged through the passage (16) flows along the pipe, thereby preventing unintended leakage to the surroundings.
[0049] The first protrusion (20) of the present invention is formed to protrude to one side and the other side of one end in the longitudinal direction of the main body (10).
[0050] At this time, the first protrusion (20) may have one side or the other side protrude more widely, but is not limited thereto.
[0051] That is, the first protrusion (20) can have one side and the other side protruding with the same width as shown in FIG. 6.
[0052] And the first protrusion (20) includes a projection (21) extending from the top to the bottom of one side; and a groove (22) extending from the top to the bottom of another side; so that when one side is arranged to be in contact with another side, the forward and backward movement of one side and the other can be suppressed as one projection (21) engages with the other groove (22).
[0053] The second protrusion (30) of the present invention is formed to protrude to one side and the other side of the other end in the longitudinal direction of the main body (10).
[0054] At this time, the second protrusion (30) may have one side or the other side protrude more widely, but is not limited thereto.
[0055] That is, the second protrusion (30) can protrude with the same width on one side and the other side.
[0056] And the second protrusion (30) includes a projection (31) extending from the top to the bottom of one side; and a groove (32) extending from the top to the bottom of another side; so that when one side is arranged to be in contact with another side, the forward and backward movement of one side and the other can be suppressed as one projection (31) engages with the other groove (32).
[0058] Meanwhile, as illustrated in FIG. 7, a method for constructing a port structure using a block for constructing a port structure according to the present invention comprises: a mound installation step (S1); a base member placement step (S2); a block stacking step (S3); a filler filling step (S4); and a top concrete placement step (S5).
[0059] The mound installation step (S1) of the present invention involves reinforcing the seabed ground that serves as the landing point for the block (A) for constructing a port structure, as shown in FIG. 8, and then installing a rubble mound (100).
[0060] Therefore, the base member (200) described below can be supported by the rubble mound (100).
[0061] At this time, perforations (110) extending from the upper surface to the lower surface may be formed in the rubble mound (100) at intervals along the length direction.
[0062] Therefore, by inserting a supporting member (120), such as a pile, into the space between the blocks (A) for constructing the port structure—that is, the space where the filling material (300) described below is filled—and fitting it into the drilled section (110), the sliding of the base member (200) on the upper surface of the rubble mound (100) can be prevented.
[0063] The base member placement step (S2) of the present invention is to arrange base members (200) having a catch (210) formed at a certain height on one end of the upper surface in the longitudinal direction along the upper surface of the flattened rubble mound (100) as shown in FIG. 9, such that one side of one base member (200) and one side of another base member are placed against each other.
[0064] Therefore, the block (A) for constructing a port structure can be supported by the base member (200).
[0065] At this time, the base member (200) includes an irregularity (220) formed on the bottom surface, so that as the irregularity (220) comes into contact with the upper surface of the rubble mound (100), slipping on the upper surface of the rubble mound (100) can be suppressed.
[0066] The block stacking step (S3) of the present invention forms a plurality of layers by repeating the arrangement so that one side of one block (A) for constructing a port structure and another side of another block are butted together, as shown in FIG. 10.
[0067] Therefore, a port structure can be formed by multiple blocks (A) for constructing a port structure.
[0068] In this block stacking step (S3), each block (A) for constructing a port structure is positioned so that the inlet (11) faces the sea side, thereby allowing seawater to flow into the water section (12) from the outside through the inlet (11).
[0069] At this time, the block (A) for constructing a port structure forming the lower section can be stacked by partially engaging the block (A) for constructing a port structure forming the upper section with the block (A) for constructing a port structure forming the lower section without interference from the block (14) by receiving the catch (14) formed on the upper surface of one end in the longitudinal direction of the main body (10) into the catch groove (15) formed on the lower surface of one end in the longitudinal direction of the main body (10) of the block (A) for constructing a port structure forming the upper section.
[0070] And the bottommost block (A) for constructing a port structure can be stacked by partially engaging the bottommost block (A) with the base member (200) without interference from the bottommost block (A) by receiving a catch (210) formed on the upper surface of the base member (200) in the longitudinal direction inside a catch groove (15) formed on the lower surface of the main body (10) in the longitudinal direction.
[0071] And in the block stacking step (S3), the even-numbered blocks (A) for constructing a port structure among the multiple layers form a left-right symmetrical shape with the odd-numbered blocks (A) for constructing a port structure among the multiple layers, so that the even-numbered layers and the odd-numbered layers among the multiple layers can be arranged in a zigzag shape.
[0072] The filler filling step (S4) of the present invention fills the space between one of the blocks (A) for constructing a port structure stacked in multiple layers as shown in FIG. 11 and another adjacent to it with a filler (300).
[0073] Therefore, each block (A) for constructing a port structure can be restrained by the compressive resistance of the filler (300).
[0074] Here, the filler (300) may include various materials such as crushed stone, recycled aggregate, and concrete blocks.
[0075] The upper concrete placement step (S5) of the present invention places the upper concrete (400) on top of the uppermost block (A) for constructing the harbor structure as shown in FIG. 12.
[0076] Therefore, the movement of the block (A) for constructing a port structure, which forms multiple stages, can be suppressed by the load action of the upper concrete (400).
[0077] At this time, the upper concrete (400) may be of any ordinary shape and structure as long as it is capable of pressing the blocks (A) for constructing a harbor structure that form multiple layers, so a detailed description of the upper concrete (400) is omitted.
[0078] However, the upper concrete (400) includes a catch groove (410) formed on the bottom surface of one end in the longitudinal direction, for example, the rear end.
[0079] Accordingly, when the upper concrete (400) is placed, the upper projection (14) formed on the upper surface of the main body (10) in the longitudinal direction of the uppermost port structure construction block (A) is received into the lower surface of the upper concrete (400) in the longitudinal direction of the lower surface of the upper concrete (400), thereby allowing the upper concrete (400) to be seated without interference from the upper projection (14) of the uppermost port structure construction block (A).
[0080] Additionally, the method for constructing a port structure using a block (A) for constructing a port structure according to the present invention may further include a rear filling step (S6) performed after the upper concrete placement step (S5); a mat laying step (S7); and a paved road (800) formation step (S8).
[0081] The rear filling step (S6) of the present invention fills the rear of the port structure construction blocks (A), which are stacked in multiple layers, with backfill rubble (500).
[0082] Therefore, rear support can be provided for each of the blocks (A) for constructing a port structure stacked in multiple layers by backfill rubble (500).
[0083] The mat laying step (S7) of the present invention lays a filter mat (600) on the surface of the backfill gravel (500).
[0084] Therefore, the surface flow of the backfill rubble (500) can be suppressed by the filter mat (600), and the flow of the landfill soil (700) described below can also be suppressed.
[0085] The step (S8) of forming the pavement (800) of the present invention involves burying the landfill soil (700) behind the filter mat (600) and then paving the pavement (800) so as to form a horizontal plane with the upper concrete (400).
[0086] Therefore, access to the port structure can be stably achieved via the paved road (800).
[0088] The construction of a port structure using a block (A) for constructing a port structure according to the present invention is described in detail as follows.
[0089] The block (A) for constructing a port structure according to the present invention is stacked in multiple layers so as to extend above the water surface from a base member (200) placed on a rubble mound (100) on the seabed.
[0090] At this time, each section is formed by arranging one side of a block (A) for constructing a port structure and the other side of a block so that they meet.
[0091] That is, each section is formed by butting one side of the first protrusion (20) and the second protrusion (30) formed on one end and the other end in the longitudinal direction of one main body (10) of a port structure construction block (A) with one side of the first protrusion (20) and the second protrusion (30) formed on one end and the other end in the longitudinal direction of another main body (10) of a port structure construction block (A).
[0092] Here, the first protrusion (20) and the second protrusion (30) include a projection (21, 31) extending from the top to the bottom of one side; and a groove (22, 32) extending from the top to the bottom of another side. When one side is brought into contact with another side, one of the projections (21, 31) engages with the other groove (22, 32), thereby engaging one of the blocks (A) for constructing the port structure with the other, thereby suppressing forward and backward movement and improving the structural stability of the port structure.
[0093] And the main body (10) of the block (A) for constructing a port structure includes a catch (14) protruding from the upper surface of one end in the longitudinal direction opposite to the wave pressure or earth pressure; and a catch groove (15) recessed from the lower surface of one end in the longitudinal direction opposite to the wave pressure or earth pressure. When stacking in multiple layers, the catch (14) formed on the main body (10) of the block (A) for constructing a port structure, more specifically the lower layer, is received in the catch groove (15) formed on the main body (10) of the block (A) for constructing a port structure, more specifically the upper layer. As a result, the lower layer block (A) for constructing a port structure and the upper layer block (A) for constructing a port structure can be partially engaged and stacked, thereby suppressing movement in the forward and backward directions, and thus improving the structural stability of the port structure.
[0094] That is, as shown in FIG. 13, the longitudinal end of the main body (10), on which the catch (14) and catch groove (15) are formed, is positioned to face the land side, thereby suppressing rearward displacement even when wave pressure acts during construction, so that the construction state can be maintained stably. Also, as shown in FIG. 14, the longitudinal end of the main body (10), on which the catch (14) and catch groove (15) are formed, is positioned to face the sea side, thereby suppressing forward displacement even when earth pressure acts during construction, so that the construction state can be maintained stably, and thus the structural stability of the harbor structure can be improved.
[0095] Here, when one end of the main body (10) in the longitudinal direction, having a catch (14) and a catch groove (15) formed thereon, is positioned to face the sea side, backfill rubble (500) can be filled behind the structure construction blocks stacked in multiple layers, and since the rear support of the structure construction blocks is provided by the backfill rubble (500), the structural stability of the harbor structure can be improved.
[0096] Additionally, a filter mat (600) can be laid on the surface of the backfill gravel (500), and after the backfill soil (700) is filled behind the filter mat (600), a paved road (800) can be paved, so that access to the port structure can be made stably by the paved road (800).
[0097] In addition, the bottom block (A) for constructing the lowest port structure is accommodated by a catch (15) formed on the bottom surface of one end in the longitudinal direction of the main body (10) and a catch (210) formed on the upper surface of one end in the longitudinal direction of the base member (200). Since a portion of the bottom block (A) for constructing the lowest structure can be partially engaged with the base member (200) and stacked without interference from the catch (210), the movement of the bottom block (A) in the forward and backward directions can be suppressed, thereby allowing the construction state to be maintained stably even when wave pressure and earth pressure are applied during construction, in other words, the structural stability of the port structure can be improved.
[0098] In addition, in the present invention, a top concrete (400) is placed on the upper part of the uppermost block (A) for constructing a port structure, and since the load of the top concrete (400) is applied to each of the blocks (A) for constructing a port structure in a stacked state, the movement of the blocks (A) for constructing a port structure can be suppressed by the pressure caused by this, thereby improving the structural stability of the port structure.
[0099] At this time, the upper concrete (400) has a catch groove (410) formed on the bottom surface at one end in the longitudinal direction that catches on a catch projection (14) formed on the top surface at one end in the longitudinal direction of the main body (10) of the upper structure construction block. Since the upper concrete (400) and the upper structure construction block can be interlocked and connected, movement in the front and rear directions can be suppressed, and thus the seating state can be maintained stably even when blast pressure and earth pressure are applied while the upper structure construction block is seated.
[0100] In addition, when stacking blocks (A) for constructing a port structure, the even-numbered blocks (A) for constructing a port structure among the multiple layers form a left-right symmetrical shape with the odd-numbered blocks (A) for constructing a port structure, and since the even-numbered and odd-numbered layers among the multiple layers can be arranged in a zigzag shape, interlocking between the blocks (A) for constructing a port structure is achieved, and in particular, lateral movement can be suppressed, thereby further improving the structural stability of the port structure.
[0101] However, if the block (A) for constructing a port structure stacked in multiple layers moves laterally due to a greater external force, the structural stability may be reduced.
[0102] However, in the present invention, a filler material (300) is filled into the space between each of the blocks (A) for constructing a port structure that form each layer and the other one adjacent thereto. Since each of the blocks (A) for constructing a port structure is constrained by the compressive resistance of the filler material (300), the lateral movement of each of the stacked blocks (A) for constructing a port structure can be suppressed, thereby preventing a decrease in the structural stability of the port structure due to the lateral movement of the stacked blocks (A).
[0103] At this time, the filler material (300) filled in the space between one of the structural construction blocks (A) forming each stage and another adjacent one comes into contact with the first protrusion (20) and is compressed in one direction as one of the structural construction blocks (A) moves in one direction due to wave pressure or earth pressure action. When the filler material (300) is compressed, the stopper (14) of the lower structural construction block (A) exerts resistance against the pressure applied to the filler material (300), thereby compacting the filler material (300). Consequently, the compressive resistance of the filler material (300) and the restraint by the stopper (14) of the structural construction block (A) allow the structural construction block (A) and the filler material (300) to be roughly integrated, thus preventing a decrease in the structural stability of the harbor structure even under wave pressure or earth pressure action.
[0104] Meanwhile, the block (A) for constructing a port structure according to the present invention can not only increase the structural stability of the port structure but also facilitate the dissipation of wave energy.
[0105] That is, the main body (10) forming the block (A) for constructing a harbor structure according to the present invention comprises: an inlet section (11) extending from the front of one end in the longitudinal direction toward the rear; and a water section (12) connected to the inlet section (11) and extending toward the rear in the longitudinal direction, wherein a perforated wall (13) is formed with a completely open bottom and a partially open top. Seawater can flow into the water section (12) from the outside through the inlet section (11), and the seawater flowing into the water section (12) can flow up and down through the open portion formed in the perforated wall (13) at the top of the water section (12). As a result, the dissipation of wave energy can be facilitated, thereby reducing reflected waves, which can improve the calm temperature inside the harbor and enhance the stability of the structure.
[0106] At this time, the perforated wall (13) has a perforation rate (= cross-sectional area of the open part / cross-sectional area of the perforated wall) of 5~30%, so a high wave-dissipating effect can be expected. When the upper concrete (400), etc. is installed on the upper outer side of the water flow section (12) and the flow of seawater through the open part is restricted, when seawater rises within the main body (10), a layer of compressed air can be formed on the upper inner side of the water flow section (12) after passing through the inlet part (11), thereby mitigating the impact pressure applied to the upper concrete (400), etc. due to the rise of seawater, so that structural movement and damage to the upper concrete (400) can be prevented.
[0107] When constructing a breakwater using block-type structures, seawater within the harbor may become stagnant due to the blockage of flow.
[0108] However, the main body (10) forming the block (A) for constructing a port structure according to the present invention may further include at least one passage (16) that is formed to be connected in the longitudinal direction to either one end or the other end and communicates with the water flow section (12), so that seawater flowing into the water flow section (12) can be discharged to the outside through the passage (16), thereby allowing fresh offshore seawater to be introduced into the port.
[0109] Here, a pipe leading to the outside can be connected to the passage (16), so that seawater discharged through the passage (16) can be introduced into a stagnant water deep inside the harbor.
[0111] The present invention as described above is not limited to the embodiments described above and may be modified within the scope that does not deviate from the essence of the invention claimed in the claims, and such modifications fall within the scope of protection of the present invention as defined by the claims below. Explanation of the symbols
[0112] 10: Main body 11: Inlet 12 : Water retention section 13 : Perforated wall 14 : Catching tab 15 : Catching groove 16 : Passage 20 : First protrusion 21: Protrusion 22: Groove 30: Second protrusion 31: Projection 32 : Home 100 : Mound 110 : Perforation section 120 : Support member 200 : Base member 210 : Stopper 220 : Unevenness 300 : Filler 400 : Upper concrete 410 : Catching groove 500 : Backfill gravel 600 : Filter mat 700 : Landfill soil 800 : Paved road A: Block for constructing port structures S1: Mound installation stage S2: Base member placement step S3: Block stacking step S4: Filler filling stage S5: Upper concrete placement stage S6: Rear filling stage S7: Mat laying stage S8: Pavement formation stage
Claims
Claim 1 A main body having a preset length, width, and height; a first protrusion formed protruding from one side and the other side of one end of the main body in the longitudinal direction; and a second protrusion formed protruding from one side and the other side of the other end of the main body in the longitudinal direction; wherein the main body comprises an inlet portion facing from the front of the end of the main body in the longitudinal direction toward the rear; and a water flow portion extending to the rear in the longitudinal direction in communication with the inlet portion, wherein the lower part is completely open and a perforated wall formed at the upper part is partially open, so that seawater flowing from the sea side flows into the water flow portion through the inlet portion, and the seawater flowing into the water flow portion flows up and down through the open part of the perforated wall, and the first protrusion and the second protrusion comprise a projection portion extending from the upper part of one side to the lower part; and a groove portion extending from the upper part of the other side to the lower part.The first protrusion is formed to protrude toward one side and the other side of one end of the main body in the longitudinal direction, wherein the length of the protruding section protruding toward the one side is formed to be longer than the length of the protruding section protruding toward the other side, thereby forming a left-right asymmetrical shape; the second protrusion is formed to protrude toward one side and the other side of one end of the main body in the longitudinal direction, wherein the length of the protruding section protruding toward the other side is formed to be longer than the length of the protruding section protruding toward the one side, thereby forming a left-right asymmetrical shape; wherein the length of the protruding section protruding toward the one side of the first protrusion is the same as the length of the protruding section protruding toward the other side of the second protrusion, and the length of the protruding section protruding toward the other side of the first protrusion is the same as the length of the protruding section protruding toward the one side of the second protrusion, so that the first protrusion and the second protrusion form a front-rear asymmetrical shape; and wherein the projection located on one side of the first protrusion and the second protrusion of the main body is located on the other side of the first protrusion and the second protrusion of the main body. A block for constructing a harbor structure, characterized in that a space is formed between the main body and another main body by being abutted against the above-mentioned groove, and a filler material is filled through the space. Claim 2 A block for constructing a harbor structure according to claim 1, wherein the main body comprises: a catch projection formed protruding from an upper surface at one end in the longitudinal direction; and a catch groove formed recessed from a lower surface at one end in the longitudinal direction. Claim 3 A block for constructing a harbor structure according to paragraph 2, characterized in that the main body is formed to be longitudinally connected to either one end in the longitudinal direction or the other end, and further comprises at least one passage communicating with the water section. Claim 4 A block for constructing a port structure, characterized in that, in paragraph 3, a pipe leading to the outside is connected to the passage. Claim 5 delete Claim 6 A block for constructing a harbor structure according to claim 1, characterized in that the projection and groove of the first projection are located in the opposite direction to the projection and groove of the second projection. Claim 7 A block for constructing a port structure according to claim 1, characterized in that the perforated wall has a perforation rate of 5 to 30%. Claim 8 A method for constructing a port structure using a block for constructing a port structure according to claim 1, comprising: a mound installation step of reinforcing the ground of the seabed serving as the anchoring point for the block for constructing the port structure and then installing a rubble mound; a base member arrangement step of arranging base members, each having a retaining projection formed at a certain height on an upper surface at one end in the longitudinal direction along the upper surface of the flattened rubble mound, such that one side of one base member and another side of another base member are in contact with each other; a block stacking step of forming multiple layers by repeating the arrangement such that one side of one block for constructing the port structure and another side of another block are in contact with each other on the base member; and a filler filling step of filling a filler into each of the spaces between one block for constructing the port structure and another adjacent block stacked in the multiple layers. A method for constructing a port structure using a block for constructing a port structure, characterized by including: a step of placing a top concrete on the uppermost block for constructing a port structure. Claim 9 A method for constructing a port structure using a block for constructing a port structure, wherein, in the block stacking step, the bottommost block for constructing a port structure is connected to the base member by the catch groove of the main body engaging with the catch projection of the base member. Claim 10 A method for constructing a port structure using blocks for constructing a port structure, characterized in that, in the block stacking step of claim 8, each of the blocks for constructing the port structure is arranged such that its entrance faces the sea side. Claim 11 A method for constructing a port structure using blocks for constructing a port structure, characterized in that, in the block stacking step of claim 8, the blocks for constructing a port structure in an even number of layers among the plurality of layers form a left-right symmetrical shape with the blocks for constructing a port structure in an odd number of layers. Claim 12 A method for constructing a port structure using a block for constructing a port structure, characterized in that, in the step of placing the upper concrete, the upper concrete is connected to the upper block for constructing a port structure by the catch groove formed on the bottom surface of one end in the longitudinal direction of the upper concrete catch on the upper surface of one end in the longitudinal direction of the main body of the upper block for constructing a port structure. Claim 13 A method for constructing a port structure using blocks for constructing a port structure, characterized by further including, in claim 8, a backfilling step of filling backfilling rubble behind the blocks for constructing a port structure stacked in multiple layers; a mat laying step of laying a filter mat on the surface of the backfilling rubble; and a pavement forming step of laying a pavement so as to form a horizontal plane with the upper concrete after filling the upper surface with landfill soil.
Citation Information
Patent Citations
Combined artificial reef and coastalc erosion protection submerged breakwater block and construction method using the same
KR101156791B1
Interlocking block And Port structure using interlocking blocks And Construction method of port structure using interlocking block
KR102315282B1
Floating concrete unit block and floating concrete structure containing this
KR102361308B1
wave dissipating revetment block of double structure
KR200416688Y1
Wave dissipation block
KR1020100108476A